28
Rooley Moor Wind Farm Environmental Statement Appendix 7.2: Outline Peat Management Plan

Appendix 7.2: Outline Peat Management Plan · 2014. 9. 5. · Outline Peat Management Plan V1 2 Investigating the impacts of wind farm development on peatlands in England: Part 1

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • Rooley Moor Wind Farm Environmental Statement

    Appendix 7.2: Outline Peat Management Plan

  • Rooley Moor Wind Farm

    CORONATION POWER

    Outline Peat Management Plan

    V1 | REV C

    18th August 2014

  • Outline Peat Management Plan

    V1 i

    Rooley Moor Wind Farm

    Project no: JE30481

    Document title: Outline Peat Management Plan

    Document no: V1

    Revision: REV B

    Date: 25 Jun 2014

    Client name: Coronation Power

    Project manager: Jo Moran

    Author: Hannah Russell and Peter Skinner

    File name: C:\Users\jmoran\AppData\Local\Microsoft\Windows\Temporary Internet

    Files\Content.Outlook\NUF78R7K\Rooley_Moor_OPMP_revised_120814 FINAL (2).docx

    Sinclair Knight Merz (Europe) Ltd (Jacobs)

    4th Floor, Metro

    33 Trafford Road

    Salford

    T +44 161 873 8500

    F +44 161 873 7115

    www.jacobs.com

    COPYRIGHT: The concepts and information contained in this document are the property of Sinclair Knight Merz (Europe) Limited (Jacobs). Use

    or copying of this document in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.

    Document history and status

    Revision Date Description By Review Approved

    REV A 20/06/2014 First draft for practice review P Skinner M Brown -

    REV B 25/06/2014 Revised draft for practice review H Russell M Brown M Brown

    REV B 30/06/2014 Draft for client Comment H Russell E Romaine E

    Romaine

    Rev C 13/08/2014 Updates for revised layout H Russell C Stewart C Stewart

  • Outline Peat Management Plan

    V1 ii

    Contents

    1. Introduction ................................................................................................................................................ 1

    1.1 Objectives ....................................................................................................................................................................................... 1

    1.2 Policy and Guidance for Peat Management ................................................................................................................................... 1

    1.2.1 Legislation and Guidance ............................................................................................................................................................... 1

    2. Peat Conditions on Site ............................................................................................................................ 3

    2.1 Definition of Peat ............................................................................................................................................................................ 3

    2.2 Sources of Information .................................................................................................................................................................... 3

    2.3 Description of Peat at Rooley Moor ................................................................................................................................................ 3

    3. Avoidance, Minimisation, Handling and Reinstatement ....................................................................... 8

    3.1 Introduction ..................................................................................................................................................................................... 8

    3.2 Further minimisation before and during the construction phase ..................................................................................................... 8

    4. Peat Balance .............................................................................................................................................. 9

    4.1 Excavation and Reinstatement Volumes ........................................................................................................................................ 9

    4.1.1 Turbine Foundations ..................................................................................................................................................................... 10

    4.1.2 Crane Hardstandings .................................................................................................................................................................... 10

    4.1.3 Construction Compound, Control Building and Substation ........................................................................................................... 11

    4.1.4 New Access Tracks ...................................................................................................................................................................... 11

    4.1.4.1 Floating Tracks ............................................................................................................................................................................. 11

    4.1.4.2 Cut and Fill Tracks ........................................................................................................................................................................ 11

    4.1.5 Borrow Pits.................................................................................................................................................................................... 11

    4.1.6 Cable Trenches............................................................................................................................................................................. 12

    4.2 Net Balance .................................................................................................................................................................................. 13

    5. Excavation, Storage, Re-use and Restoration ..................................................................................... 14

    5.1 Excavation .................................................................................................................................................................................... 14

    5.2 Temporary Storage ....................................................................................................................................................................... 14

    5.3 Bare Peat ...................................................................................................................................................................................... 15

    5.4 Infrastructure Reuse ..................................................................................................................................................................... 15

    5.4.1 Cut and Fill Access Tracks ........................................................................................................................................................... 16

    5.4.2 Floating Access Tracks ................................................................................................................................................................. 16

    5.4.3 Turbine Foundations and Hardstanding........................................................................................................................................ 16

    5.4.4 Borrow Pits.................................................................................................................................................................................... 17

    5.5 Reuse of Peat for Other Restoration Purposes ............................................................................................................................ 17

  • Outline Peat Management Plan

    V1 1

    1. Introduction

    1 This draft Peat Management Plan (PMP) has been prepared as part of the Environmental Impact

    Assessment (EIA) accompanying the planning application for Rooley Moor Wind Farm (the

    ‘Development’).

    2 The draft PMP will be further developed and implemented subsequent to the Development receiving

    planning consent. Further details and specific plans will be determined during the detailed design

    process and once further site investigations have been undertaken. These details will then be included

    in a PMP as a part of the appointed Principal Contractor’s detailed Construction Environmental

    Management Plan (CEMP) for the Development. A draft CEMP is provided in Appendix 4.1 of this

    Environmental Statement. The PMP addresses the management of peat during construction and

    immediate restoration.

    1.1 Objectives

    3 Peat has been afforded significant consideration throughout the Rooley Moor Wind Farm design

    process. This is in response to concerns raised by statutory and non-statutory stakeholders during the

    scoping phase which identified impacts to peatlands as a concern. It is understood this is largely in

    response to ‘lessons learned’ following the development of the Scout Moor Wind Farm, adjacent to the

    proposed Rooley Moor Wind Farm.

    4 The role of the PMP is to demonstrate that the management of peat excavated during construction of

    the Development has been considered and will be treated appropriately during the construction

    process. Together with the proposed Habitat Management measures (refer to Chapter 8: Non-Avian

    Ecology) it presents mitigation measures that will minimise any impacts on peat, and assist the long

    term habitat restoration and management plans for key peatland areas of the site, that are designed to

    enhance the site through improvement of the ecological habitat.

    5 The PMP outlines the overall design approach that has been applied to the Development to minimise

    peatland disruption and aims to ensure that all further opportunities to minimise peat disturbance and

    extraction during construction will be taken.

    6 The PMP identifies appropriate and industry proven methods for the reuse of excess peat to restore

    the effects of construction activities, without significant environmental or health and safety implications

    and to reduce the release of carbon and minimise risk in terms of human health.

    1.2 Policy and Guidance for Peat Management

    1.2.1 Legislation and Guidance

    7 Peat as a carbon landscape has the capacity to act as a carbon sink. The management of peat

    therefore has implications for carbon emissions and climate change. The legislation and guidance

    regarding climate change and carbon which is relevant to the management of peat includes:

    The Kyoto Protocol (Ref. 1) and the Kyoto Protocol and National Accounting for Peatlands (Ref. 2);

    The UK Climate Change Act (Ref. 3);

    The Carbon and Water Guidelines, Carbon Landscapes and Drainage (Ref. 4);

    Forests and climate change: UK Forestry Standard Guidelines, Forestry Commission (Ref. 5);

    Scottish Environment Protection Agency (SEPA), Regulatory Position Statement – Developments on

    Peat (Ref. 6);

    Scottish Government, Guidance on Developments on Peatland – Site Surveys (Ref. 7);

    Floating Roads on Peat, Scottish Natural Heritage (Ref. 8);

    Guidance on the Assessment of Peat Volumes, Reuse of Excavated Peat and the Minimisation of

    Waste, Scottish Renewables and SEPA (Ref. 9).

    8 The following guidance specifically relates to wind farm construction and peatland restoration:

  • Outline Peat Management Plan

    V1 2

    Investigating the impacts of wind farm development on peatlands in England: Part 1 Final Report,

    (Ref.10)

    Best Practice Guidance to Planning Policy Statement 18 ‘Renewable Energy’, (Ref. 11);

    Wind Farm Developments on Peat Land fact sheet. Scottish Government (Ref. 12); and

    Good practice during wind farm construction, A joint publication by Scottish Renewables, Scottish

    Natural Heritage, Scottish Environment Protection Agency, Forestry Commission Scotland (Ref. 13).

    9 It is acknowledged that many of the publications listed above have been developed by the Scottish

    Government; this is due to the recent increase in wind farm developments in upland areas with peat

    and the need for legislation and guidance to mitigate negative impacts. The Scottish documents are

    considered to be best practice within the UK and are therefore appropriate for use within this OPMP.

  • Outline Peat Management Plan

    V1 3

    2. Peat Conditions on Site

    2.1 Definition of Peat

    10 Peat is defined as the partially decomposed remains of plants and soil organisms which have

    accumulated at the surface of the soil profile (Ref.14). Active peatlands are traditionally described

    using a simple 2-layer model; the acrotelm including active peat vegetation and catotelm (Ref.15).

    This simple two-layer conceptual understanding has been developed to aid a hydrological and

    ecological understanding of peat ecosystems.

    11 The acrotelm is the upper aerobic layer of peat and consists of living and partially decayed plant

    material. It typically has a higher hydraulic conductivity than underlying peat and is defined with

    relation to distance to the water table. Acrotelm thickness varies with topography - such as hummocks,

    peat hags, hollows and with time, especially in drought periods or when it is drained. The catotelm

    layer sits under the acrotlem and consists of highly decayed material and is significantly denser. It has

    a very low hydraulic conductivity. Conditions are permanently anaerobic and anoxic because the

    catotelm is permanently below the water table. The catotelm is less cohesive than the acrotelm layer

    and is considered to be less suitable for storage and re-use.

    2.2 Sources of Information

    12 Assessment has been made of the areal extent, depths and structure of peat likely to be disturbed at

    the Development site synthesising multiple data sources. Initially, peatland habitats on site were

    identified through desk based studies reviewing published geological, hydrological and ordnance

    survey mapping. Following the desk based studies, site walkover surveys were conducted by

    ecologists and hydrologists in May 2012. Following on from these surveys, detailed peat probing was

    conducted across the wind farm site on a 50m grid in June 2012. Peat cores were also obtained and

    logged.

    13 The data collected during the desk and field studies are presented within the Rooley Moor Wind Farm

    main ES. A summary of the relevant chapters, documents and field studies used in the

    characterisation of the peat for this OPMP are presented below;

    Chapter 7 Hydrology, Geology and Hydrogeology – Rooley Moor Wind Farm ES

    Chapter 8 Non-Avian Ecology – Rooley Moor Wind Farm ES.

    Rooley Moor Wind Farm Peatslide Hazard and Risk Assessment Interpretive Report Vol 1 and 2 (June

    2014), prepared by Jacobs.

    Rooley Moor Wind Farm Peatslide Hazard and Risk Assessment Factual Report (June 2014),

    prepared by Jacobs.

    Peat depth probing and Peatslide risk assessment surveys carried out in October 2012 (250 survey

    points) (see Appendix 7.3 of the ES); and

    Water level measurements in peat (20 locations), peat depth probing (98 survey points) and peat core

    analysis (64 peat core locations) April 2014.

    14 Figures (1-10) of the PSRA Factual Report (ES Appendix 7.3) showing the distribution and depth of

    peat across the site as well as all probe, core and dip-well locations sampled during the field work

    phases of investigation are located in ES Appendix 7.3.

    2.3 Description of Peat at Rooley Moor

    15 The Development Area encompasses the eastern extent of an upland plateau which forms Rooley

    Moor, Knowl Moor and Scout Moor. Much of the study area is elevated above 350 metres above

    ordnance datum (m aOD) and encompasses three main peaks which form a north-south trending

    ridge along the length of the Development Area. These peaks are Top of Leach located in the north of

    the study area (474m aOD), Hammer Hill located in the centre of the study area (440m aOD) and Top

    of Pike located in the south of the site (398m aOD)..

  • Outline Peat Management Plan

    V1 4

    16 These hills form the crest of a watershed which creates five surface water catchments. These

    catchments ultimately drain to the River Irwell (north and west), the River Spodden (east) or Nadden

    Brook (south) (see ES Figure 7.1). Several of the catchments contain United Utilities (UU) public

    water supply reservoirs which receive surface water inputs from many of the watercourses located

    within the upper parts of the catchments. A full and detailed description of the surface water

    catchments within the Application Site is presented in Chapter 7 of the main ES. Consultation with UU

    indicates that water quality in their public water supply reservoirs around Rooley Moor are suffering

    from deteriorating water quality. The key issues relate to increasing dissolved organic content (DOC)

    in water bodies; this is thought to be due to increasing rates of peat erosion on Rooley Moor and

    adjacent Scout Moor.

    17 The average annual catchment rainfall for the area is approximately 1,510mm based on data obtained

    from the FEH (Ref 16) indicating a moderately wet climate having the potential to exhibit a moderately

    high runoff regime.

    18 Peat depth probing carried out by Jacobs personnel in October 2012 and April 2014 has been used to

    produce a detailed peat depth plan for the Application Site (see Figure 10 of the PSRA Factual

    Report). The plan shows the presence of peat deposits in the northern, eastern and western areas of

    the Application Site. The southern half of the Application Site is mapped as being peat free (

  • Outline Peat Management Plan

    V1 5

    Table 1 Summary of Peat Characteristics Data

    1) Infrastructure 2) Core Location

    Average Von Post Humification (H) and

    Moisture (B) Scores Average Depth to Water

    (m) Acrotelm Catotelm

    Met Mast C21, C24 H6 B2 H10 B3 -

    New Track C7, C14, C25 H5 B2 H9 B4 -

    Track Upgrade C0, C1, C2, C3, C4, C5,

    C6 H6 B3 H9 B3 0.05

    Turbine 1 C9, C12, C30, C31, C32 H6 B2 H9 B3 0.30

    Turbine 2 C8, C33, C34, C35 H6 B3 H9 B3 0.50

    Turbine 3 C10, C42, C43, C44 H5 B2 H9 B4 -

    Turbine 4 C11, C13, C29 H6 B3 H9 B2 0.55

    Turbine 5 C18, C19, C36, C37,

    C38 H6 B2 H9 B2

    0.33

    Turbine 6 C15, C20, C39, C40,

    C41 H5 B2 H8 B4

    -

    Turbine 7 C16, C17, C45, C46,

    C47 H6 B3 H9 B4

    0.42

    Turbine 8 C22, C51, C52, C53 H7 B2 H10 B4 0.17

    Turbine 9 C48, C49, C50 H7 B2 H10 B3 0.50

    Turbine 10 C23, C54, C55, C56 H5 B3 H10 B4 0.05

    Turbine 11 C26, C57, C58, C59 H6 B3 H9 B4 0.00

    Turbine 12 C27, C28, C60, C61,

    C62, C63 H6 B3 H9 B3

    0.00

    NOTES (-) indicates no water level data recorded for this location

    Detailed description of Von Post scores is presented in Appendix 1

    20 In summary, acrotelm thickness measures in core samples ranged from 0m to 0.25m with an average

    thickness of 0.1m, across much of the site the peat profile appeared quite degraded. Average water

    table depth based on two rounds of water level monitoring indicated average water table depth is

    0.25m across the site although there were spatial variations. Water levels were highest around turbine

    T11 and T12 in the north of the Application Site. Readings were taken in late spring and seasonal

    variations should be expected.

    21 Chapter 8 Non-Avian Ecology reports the findings of National Vegetation Classification (NVC)

    mapping of the Development Area (see ES Figure 8.3. The survey identified that the majority of the

    peat land in the Development Area was vegetated by degraded/modified mire communities such as

    M20 Eriophorum vaginatum blanket mire and M25 Molinia caerulea-potentilla erecta mire. Chapter 8:

    Non-Avian Ecology suggests that the peat land across Rooley Moor would have formerly been

    dominated by blanket mire vegetation. Blanket mire develops in areas of high rainfall, and has an

    ombrogenous (that is, rainfall fed) hydrological regime; however, the influence of continuous heavy

    grazing (perhaps coupled with burning and atmospheric pollution) the original bog vegetation has

    become modified to such to lower ecological value habitat. Much of the peat land across the

    Development Area, south of Ding Quarry, around Ding Clegg and further east around Hamer Hill is

    therefore considered to be degraded.

    22 The findings of the ecology study (see Chapter 8: Non-Avian Ecology) are supported by peat

    characteristic analysis; Von-Post humidification scores for the acrotelm were generally H6-H7,

  • Outline Peat Management Plan

    V1 6

    indicating moderately to highly decomposed peat with a very indistinct plant structure. These scores

    are higher than would be expected for a healthy, actively peat-forming acrotelm (which should be less

    decomposed) suggesting that the acrotelm layer in the study area is degraded. The interpretation that

    the peaty acrotelm is degraded across much of the site is reflected in the moisture von post scores

    which were typically B2-B3, indicating a low to moderate moisture content in the peat. Dip-well levels

    from piezometers installed in the peat around proposed turbine locations indicated that average water

    table depth across the site was 0.25m below the acrotelm layer, across the duration of the study. The

    acrotelm needs to be saturated in order to support the bog plants which in turn form peat and help

    stabilise it.

    23 Two larger areas of M3 Eriophorum angustifolium bog pool communities were mapped to the north of

    Ding Quarry (12.36ha) and on Brandwood Moor (13.3ha) (See ES Figure 8.3). According to the JNCC

    (2010) (Ref 17), M3 is typically found in areas of shallow peat in acidic environments and is commonly

    associated with eroded blanket mire in north-west of Britain. It is reported to represent a seral stage in

    the redevelopment of active mire vegetation. Water levels in the peat in these areas were at ground

    level, indicating total saturation through the peat profile and an intact hydrological system. In addition,

    some small bog pools were observed.

    24 No active subsurface drainage pipes were identified in the peat profile during the peat probing

    surveys, however, erosional features were observed around the periphery of the active M3 covered

    peat to the north of Ding Quarry. Despite this area being the most eroded area of peat, NVC surveys

    by ecologists also identified this as the best example of blanket bog in the study area.

    25 Erosion in this area of peatland appears to have been caused by significant overland flow across the

    peat which is located on the plateau up slope. It may have been exacerbated through drawdown

    caused by the loss of peat below the main peat lense as a result of the excavation of Ding Quarry.

    Hagging has also occurred where the water flowing across the bog has caused erosion and

    subsequent slumping of the overlying peat (see Plate 1 and Plate 2).

    Plate 1 Erosion Channel at NGR 385230 419248

    Plate 2 View looking to area down gradient of erosion

    channel at NGR385088 419192

    26 In summary, peat lands are located in the north, east and west of the Development Area; the south is

    largely peat free. Much of the peat was found to relatively dry, the active acrotelm layer was typically

    thin and water levels were found to be below the main acrotelm layer. Land use such as burning,

    grazing and hill walking is thought to have contributed to the degradation of the peat resource here.

    Two areas of active peat containing M3 habitat were identified, both areas are located in the north of

    the site north of Ding Quarry and around Top of Leach Hill. These areas of active bog were not

    considered to be pristine and significant erosion features were noted down gradient of the lense of

    peat near Ding Quarry.

  • Outline Peat Management Plan

    V1 7

  • Outline Peat Management Plan

    V1 8

    3. Avoidance, Minimisation, Handling and Reinstatement

    3.1 Introduction

    27 The OPMP has been developed as part of an iterative process with the findings of an initial peat

    balance analysis being utilised to further optimize the wind farm design. This has been done in order

    to prevent the unnecessary excavation or disturbance of peat.

    28 As outlined in the main ES, the wind farm layout avoids development in areas with peat soils greater

    than 1.0m depth as far as possible. However, there are a number of constraints at the site, including

    utilities and watercourses, which has meant some infrastructure has had to be located on areas with

    peat.

    29 In these instances, the volume of peat excavated has been further minimised through design

    measures such as the inclusion of a floating track design in areas with deeper peat.

    3.2 Further minimisation before and during the construction phase

    30 In addition to the optimizing work already carried out, the disturbance of peat resulting from the

    construction of the tracks, crane harstandings and foundations will be minimised as much as

    practicably possible.

    31 Utilising all the data collected to date and throughout the construction process, the Principal

    Contractor (and / or Designer) will implement methods to minimise the volumes of excavated peat.

    Appropriate handling and storage of excavated materials will be undertaken such that their integrity

    and subsequent reuse is not jeopardised.

    32 An ecological clerk of works (ECOW) will be employed and prior to each phase of construction will

    walk the site with engineers, pointing out areas of sensitive habitat and identifying where impact can

    be reduced by minor movement of infrastructure within the micro-siting available. These areas will be

    clearly marked with post and tape. The ecological clerk of works will also ensure that any micro-siting

    does not lead to movements into more sensitive habitats.

    33 All contractors will be made aware of the sensitivity of peat habitats. Contractors will be required to

    work within the narrowest practical construction corridor when working in or near areas of peat, again

    identified by the ECoW and incorporated into method statements.

    34 All plans and method statements will be accompanied by justification of the final design and/or

    construction methods identified by the Principal Contractor, including reasons for discounting

    alternative methods. This is required in order to demonstrate that all avenues for avoiding hydrological

    disruption and reducing the disturbance and excavation of peat have been considered.

    35 The Principal Contractor will be required to ensure that excavated peat is reused on site in

    landscaping and re-profiling works, to minimise visual impacts and facilitate habitat and ecological

    restoration, improvement and enhancement.

  • Outline Peat Management Plan

    V1 9

    4. Peat Balance

    4.1 Excavation and Reinstatement Volumes

    36 Donaldson Associates have provided the peat excavation volumes and reinstatement volumes

    associated with construction of the Development. These have been calculated based on the following

    data and assumptions:

    a contour map of assumed peat depth based on interpolation of values from probing and coring across

    the site;

    dimensions of the proposed areas for excavation for site infrastructure;

    an estimated acrotelm depth of 0.10m across the site,

    an assumption that the probe depth is representative of the actual depth of the peat,

    Construction of ten new access tracks leading to turbines, track Nos 9 and 7 are floating tracks and

    therefore will not result in any excavation;

    The average peat depth at each turbine is 0.4m and the overall excavation for turbine foundations is

    26m x 26m in plan;

    The average peat depth at each crane hardstanding is 0.63m and the typical size is 45m x 28m;

    5 no. laybys will be constructed along access tracks with an average peat depth of 0.3m; and

    37 At this stage and based on the location of Development infrastructure in relation to peat depth and

    topography it is calculated that all excavated peat can be re-used on site in landscaping/restoration

    activities. Table 2 summarises the peat excavation and reinstatement volumes estimated by

    Donaldsons, the full calculation sheet is presented in Appendix 2.

    Table 2 Indicative Peat Balance

    Donaldson ID Infrastructure

    Average Peat Depth (m)

    Excavated (m3)

    Re-instated (m3)

    A2 Access Track Upgrade 0.3 1,088 115

    A4 Borrow Pit Road 2 0.1 718 1,958

    A4 Road 2 0.0 - 1,069

    A4 road 2 1.1 6,540 2,998

    A4 Road 2 0.0 885

    A4 Road 4 0.5 2,657 1,218

    A4 Road 6 0.3 2,171 232

    A4 Road 7 0.7 1,722 296

    A4 Road 9 - Floating 0.7 - 575

    A4 Road 3, 5, 8 & 10 T-Heads 0.9 7,140 3,570

    A4 Road 7 - floating 0.6 - 486

  • Outline Peat Management Plan

    V1 10

    Donaldson ID Infrastructure

    Average Peat Depth (m)

    Excavated (m3)

    Re-instated (m3)

    A4 Temporary Road 0.3 710 203

    A4 Met Mast Road 0.7 1,148 375

    A5 New Access road Widening 0.5 2,830

    A6 Met Mast 0.0 - 15

    A7 Crane Hardstanding (x12) 0.5 7,515 234

    A8 Laybys 0.5 420 420

    B1 Construction Compound 0.0 -

    E5 Control Building 0.3 807 2,301

    C4 Turbine Foundations (x12) 0.5 4,032 1,550

    F1 Borrow Pits 0.0 - 23,143*

    Grand Total 44,094 44,094

    NOTES * indicates figure estimated by Jacobs based on volume peat required to reinstate borrow pits with up to 1m peat. (-)Indicates no peat will be excavated at infrastructure

    4.1.1 Turbine Foundations

    38 During turbine construction, peat will be excavated to the substrate to make room for the concrete

    turbine foundation, and for a small working area surrounding the foundation footprint. This initial

    excavation will have a 20m diameter. Surrounding the excavation areas is a 1:2 gradient batter, the

    plan area of which is determined by the mean peat depth at each turbine. Once excavated, the turbine

    foundation is installed, occupying a foundation footprint, up to 20m in width.

    39 Peat will be used to cap turbine foundations, full details regarding turbine foundation design are

    presented in Chapter 4: Project Description of the main ES. In summary, the cap will comprise

    approximately 150mm of topsoil or peat, which will either be flush with the existing ground surface, or

    will form a raised mound between 300 and 500mm above the existing ground level, depending on the

    depth of the foundation at each specific turbine location. Due to the sloping nature of the site, finished

    ground level may have to be built up on the ‘downhill’ side of the foundation. This could be by up to 1-

    1.5m depending on the severity of the slope.

    40 A total of 4,032m3 of peat will be excavated from turbine foundations; it is estimated a total of 1,550m

    3

    will be reused in reinstatement and landscaping around the installed turbines. Therefore, there will be

    a net excess of peat at turbine locations.

    4.1.2 Crane Hardstandings

    41 A crane hardstanding is required adjacent to each turbine for the purpose of turbine installation and

    maintenance. Each crane pad has an area of 25m x 40m and will required the full excavation of peat

    (where present) to substrate and replacement with rock is required to provide a suitably stable surface

    for turbine placement.

  • Outline Peat Management Plan

    V1 11

    42 Once excavated, a small proportion of the peat will be re-used to batter the edges of platforms grading

    the bases into the local landscape.

    43 A total of 7,515m3 peat will be excavated from crane hardstanding foundations. It is estimated a total

    of 234m3 will be re-used in reinstatement and landscaping. The surplus of 7,281m

    3 will need to be re-

    used elsewhere on site.

    4.1.3 Construction Compound, Control Building and Substation

    44 The construction compound and substation are all located in areas with no peat (i.e. average peat soil

    depth is

  • Outline Peat Management Plan

    V1 12

    and borrow pit 2 has a surface area of 14,385m2, it is proposed that part of the restoration of the

    borrow pits will use 23,143m3 peat material in addition to other soils excavated during wind farm

    construction. Peat will be reinstated to a depth of

  • Outline Peat Management Plan

    V1 13

    4.2 Net Balance

    53 The peat balance identifies that approximately 44,094m3 peat will be excavated on the Application Site

    and sufficient capacity has been identified to re-use all of this peat on site in landscaping. As a result,

    no surplus peat will be generated from excavation resulting in no net loss of peat on Rooley Moor as a

    result of the construction of the wind farm.

    54 The following section outlines illustrative methods for the handling and re-use of peat, which will be

    subject to more detailed design ahead of construction.

  • Outline Peat Management Plan

    V1 14

    5. Excavation, Storage, Re-use and Restoration

    5.1 Excavation

    55 Prior to any excavations, the Principal Contractor will produce a detailed Method Statement identifying

    where and how excavated peat will be used in reinstatement or landscaping works. Specific

    requirements for the excavation, handling, storage and reinstatement of peat will be outlined in this

    Method Statement. The Principal Contractor will consider potential impacts on downstream

    hydrological receptors and also the potential for instability issues with the excavated material. Some of

    the requirements to be contained within this are outlined below.

    56 Areas of peat within the footprint of excavation will have the top layer of vegetation stripped off as turf

    prior to construction by an experienced specialist contractor. When excavating areas of peat,

    excavated turves should be as intact as possible. Often it is easiest to achieve this by removing large

    turves, the peat turf will be removed in 300mm layers in order to keep the peat intact.

    57 Underlying catotelmic peat will then be removed and stored separately and kept damp following

    procedures outlined in the Carbon and Water Guidelines (Ref 4).

    58 Excavated peat turf and catotelmic peat will be handled so as to avoid cross contamination between

    distinct horizons and ensure reuse potential is maximised.

    59 Care will be taken when stripping and removing topsoil and peat turves and appropriate storage

    methods used on site, i.e. excavated material will be stored in separate horizons and vegetation rich

    top layers will be stored vegetation side up.

    60 Classification of excavated materials will depend on their identified re-use in reinstatement works. At

    this site it is anticipated that the material to be excavated will comprise peat (which may be sub-

    divided into amorphous peat, fibrous peat, and turf), clay and mineral soils (subsoil and topsoil).

    5.2 Temporary Storage

    61 Excavated peat may need to be stored on site. A temporary shallow peat stockpile will be constructed,

    within which the peat can be stored. For deeper peat deposits, the excavation will ensure that the top

    vegetation and fibrous layers are kept separate from the deeper humic peat. When storing peat, the

    peat profile will be maintained. These peat stores will be bunded using impermeable material (most

    likely soils sourced from non-peat soil turbine excavations). The bunds will extend to a level above the

    toe of the stockpiled material to provide restraint to surface runoff.

    62 Excavated turves will be stored adjacent to the construction area in a way to ensure that they remain

    moist and viable. Temporary peat storage areas should be in locations where the water table can be

    kept artificially high such as ground hollows, slope toes, ditches and drains.

    63 Temporary storage areas required for peat will be identified in the Principal Contractor’s Construction

    Method Statement (CMS). This will describe any intended drainage, pollution prevention and material

    stability mitigation measures that may be required.

    64 The design and location of stockpiles, including incorporated drainage elements, will be agreed with

    the ECoW and Geotechnical Consultant / Geotechnical Clerk of Works prior to excavation works

    commencing.

    65 Temporary peat storage areas will be located so that erosion and runoff is limited, leachate from the

    material is controlled, and stability of the existing peatland in the vicinity is not affected. Excavated

    material is to be stockpiled at least 50m away from watercourses. This will ensure that any wetting

    required on stored peat does not runoff and discharge into adjacent watercourses. Suitable storage

    areas are more appropriately sited in areas with lower ecological value and low gradient slopes.

    Cleared areas of forestry are preferred to areas of higher ecological value or areas close to

    watercourses.

    66 In the event of drought conditions, a bowser of similar will be bought to site and stockpiled peat will be

    sprayed to maintain high moisture contents and ensure the viability of the peat. Care will be taken to

    ensure this does not result on erosion/washing out of stockpiled peat. An up-gradient cut off ditch will

  • Outline Peat Management Plan

    V1 15

    be installed around the edge of the storage bund in order to collect up-gradient surface water runoff

    and divert water runoff from eroding the bund foot.

    67 Any edges of cut peat that may remain exposed, or areas of peat excavation on steep slopes, will be

    covered with geotextile or similar approved techniques. This will allow re-turfing and re-vegetation and

    reduce erosion risks.

    68 Haul distances of excavated peat will be kept as short as possible and as close to intended re-use

    destinations to minimise plant movements in relation to any earthworks activity, including peat

    management, in order to minimise the potential impact on the peat structure. It is important that

    temporary storage is safe and keeps the material suitable for its planned reuse.

    69 The handling and storage of peat will seek to ensure that excavated peat does not lose either its

    structure or moisture content. Peat turves require particularly careful storage and wetting and to be

    maintained to prevent drying out and subsequent oxidisation to ensure that they remain fit for re-use.

    70 Stockpiling of peat will be in large volumes, taking due regard to potential loading effects. Piles will be

    bladed off at the side to minimise the available drying surface area. Higher stockpiles are more likely

    to become dewatered, while smaller piles expose a greater area to evaporation. Reducing mound size

    may also increase likelihood of erosional losses as Particulate Organic Carbon (POC). Overall

    volumes of stockpiling will be minimised and height and surface areas kept to a minimum.

    71 When planning the temporary storage areas any additional disturbance areas will be minimised.

    72 Transport of peat to temporary storage areas, restoration areas or designated spoil areas will be by

    low ground pressure vehicles to avoid excessive compaction of the peat.

    5.3 Bare Peat

    73 A core aim will be to minimise the time any bare peat is exposed. The phasing of work will be carried

    out so as to minimise the amount of total exposed ground at any one time. By stripping turf and

    replacing as soon as possible after peat has been re-distributed there will be minimal areas of bare

    peat.

    74 Any peat areas that remain partially bare will be covered using geotextile or a similar method to stop

    erosion. Any areas of bare peat, where vegetation is not re-growing, will be seeded with a seed

    mixture obtained from the existing habitat. Areas where full recovery is complete will have fences

    removed.

    75 This approach has been shown to work on other peat sites and the turves re-grow quickly both

    establishing vegetation and consolidating the peat. The re-vegetated areas will be monitored. Any

    areas of bare peat, where vegetation is not re-growing, will be seeded with a seed mixture obtained

    from the existing habitats on site.

    5.4 Infrastructure Reuse

    76 The Principal Contractor will be required to provide appropriate plant for undertaking all reinstatement

    works such that no unnecessary disturbance of the ground surface occurs. In order to minimise

    disturbance and damage to the ground surface, any mobile plant required for reinstatement and

    landscaping works will be positioned on constructed access tracks, hardstanding areas or existing

    disturbed areas wherever possible. The use of a long reach excavator for excavations and

    reinstatement works is preferable as it enables sufficient room to allow initial side casting and

    subsequent pulling back of turves over reinstated peat or soil.

    77 Excavated catotelmic peat will only be used in restoration works where the topography allows straight

    forward deposition with no pre-treatment or containment measures and without risk to the

    environment. Suitable scenarios may be present in those disturbed areas where the natural or the

    receiving topography profile allows such use (for example in turbine foundation excavations).

    78 Reinstatement of vegetation will be focused on natural regeneration utilising peat vegetated turves. To

    encourage stabilisation and early establishment of vegetation cover, where available, peat turves or

    other topsoil and vegetation turves in keeping with the surrounding vegetation type will be used to

    provide a dressing for the final surface.

  • Outline Peat Management Plan

    V1 16

    79 Consideration will also be given to the impacts of poor drainage control in any areas where peat is

    used in reinstatement, for instance, track verges and reinstatement of construction compounds.

    80 Any reinstatement and re-profiling proposals will consider, and mitigate against, identified significant

    risks to environmental receptors. In particular, in areas of replaced peat, water management will be

    considered in the Principal Contractor’s Construction Method Statements to ensure that as far as

    possible an appropriate hydrological regime is re-established within areas of disturbance. Particular

    attention will be paid to maintaining hydrological continuity and preventing the creation of preferential

    subsurface flow paths (for instance within backfilled cable trenches).

    81 Any surplus peat will spread in areas identified by the geotechnical clerk of works in conjunction with

    the ecological clerk of works as suitable.

    5.4.1 Cut and Fill Access Tracks

    82 When constructing tracks rapid restoration of track verges will be undertaken as track construction

    progresses. Immediately following construction some turves will be replaced along the road edges to

    allow quicker re-vegetation and soften visual landscaping of the road edges

    83 The majority of the site’s access tracks will be constructed using a cut and fill methodology. Excavated

    peat from cut and fill sections of access tracks will be used for dressing the side slopes of track

    sections. Only peat turf and fibrous peat is likely to be suitable for battering road verges.

    84 Track edges and passing places would be reinstated post construction through the removal of capping

    material and the reuse of peat turves. Where peat turves are used to reinstate track edges this will be

    done in a manner to ensure works tie in with the surrounding topography, landscape and ground

    conditions. Where gradients permit, peat edges may be built up slightly above the road level to reduce

    visual effects from the surrounding area if it is necessary to limit track visibility.

    85 The design and construction of tracks on peat will be done in such a way so as to reduce impacts on

    and maintain the existing peat hydrology at the site. The built track will allow for the transmittance of

    water, so natural drainage can be maintained as much as possible. This will be achieved by using

    suitably graded stone in track base construction so as to permit flow through the track. The design of

    the semi-permeable tracks will try and mimic the natural permeability of the peat so that the tracks

    themselves do not become rapid flow paths from one side of the track to the other.

    5.4.2 Floating Access Tracks

    86 Floating tracks avoid the need to excavate the peat and re-fill with imported rock. However, the weight

    of the track structure can cause compression of the underlying acrotelm resulting in reduced

    transmittance of water resulting in the ponding of water up gradient of tracks and derogation of water

    supply down gradient of tracks. Drainage through the floating track will be maintained using balance

    pipes/cross-drains constructed at regular points through the track. As for the cut and fill track drainage,

    the design of the track drainage will mimic natural peat permeability so as not to create rapid flow

    paths and exacerbate peat erosion.

    5.4.3 Turbine Foundations and Hardstanding

    87 Peat will be replaced around the turbine base excavations, and re-turfed. Peat will be spread over the

    areas disturbed by construction activities, around the crane hardstandings, rotor assembly

    hardstandings and other areas used in the construction phase.

    88 The re-vegetation of temporary hardstanding areas will depend on the identified reinstatement use

    and associated vegetation character bounding the areas of restoration, with the aim being to match

    turves and topsoil to similar ground conditions. Where appropriate, excess peat turves could be used

    for screening bunds, landscaping or as part of the Outline Habitat Management Plan (see Chapter 8)

    in conjunction with reseeding. The seed mix used on site would be agreed with the ECoW, Natural

    England and local authorities and would use local native species akin to the local ecological baseline.

    89 It is envisaged that the majority of the excavated peat materials will be reused for the purpose of

    borrow pit restoration, which will be restored to create bog habitats. The final size of the borrow pits

  • Outline Peat Management Plan

    V1 17

    have yet to be confirmed and are provisional estimates based on the aggregate requirement for the

    scheme.

    5.4.4 Borrow Pits

    90 Borrow pit reinstatement using excavated peat will depend on the final restoration profiles of the

    borrow pit areas and will be subject to the ground conditions close to borrow pits (to be confirmed in

    the final PMP).

    91 The borrow pit design will allow for unconsolidated peat to be used at depths of up to 1m for

    restoration purposes.

    92 The Contractors Method Statement will provide information on intended final restoration profiles and

    method statement for how this is to be achieved, the likely volumes of material required in addition to

    peat, where the material is to be sourced and hydrology design to create and maintain peat wetland

    status.

    93 Borrow pit design will take account of medium and long term restoration objectives relating to habitat

    and environment. In particular they will be designed such that water levels within the restored habitat

    can be maintained at ground level, to allow water-logged conditions to be maintained. This can be

    achieved by excavating the borrow pits downslope where possible, allowing the downslope worked

    face to retain high water levels within the restored area thus preventing peat drying out.

    94 Catotelmic peat will be reused within the borrow pits to create the desired profile and this will be

    surfaced with acrotelmic material (turves) where available or reseeded to the local environment and

    habitats. This approach encourages rapid vegetation regeneration, preventing desiccation and carbon

    losses from the peat used in the restoration.

    95 The final design will also take into consideration the stability of the emplaced peat materials and

    include any additional measures i.e. stabilistation, required to ensure there are no residual risks to the

    environment or human health resulting from peat slides.

    5.5 Reuse of Peat for Other Restoration Purposes

    96 Rooley Moor forms part of a Drinking Water Protected Area (DWPA) under Article 7 of the Water

    Framework Directive. The most relevant objective (to this project) for DWPA is to ensure necessary

    protection in the DWPA with the aim of avoiding deterioration in water quality in order to reduce the

    level of purification treatment required in producing drinking water. As a result of this UU are seeking

    match funding through a LIFE fund bid, in order to seek money to undertake remedial and

    enhancement works on Rooley Moor and the adjacent moors, Scout Moor and Knowl Moor.

    97 Due to this proposal being put forward, working with United Utilities and providing funding to form part

    of the match funding for the LIFE bid will be the preferred option as a holistic approach, uniformly

    undertaken across all of the contiguous moorlands (which are predominantly common lands); is

    undoubtedly the most sound approach to take. However, in the event that LIFE funding is not realised,

    the basis of an Outline Habitat Management Plan (OHMP) is presented in Chapter 8: Non-Avian

    Ecology which will be implemented within the Development Area. A summary of the parts of the plan

    which involve the re-use of peat in restoration works on Rooley Moor is presented below.

    98 The formation of peatland is reliant on a high water table, whether temporary or permanent. The

    existing erosion features identified to the north of Ding Quarry will promote dewatering of upgradient

    peat. In order to allow peat bog restoration, the lowering of the water table by the erosion gullies must

    be significantly reduced. It is assumed that the water table can be restored in the gully areas via

    blocking using peat, supported by dam structures.

    99 A detailed gully blocking and reinstatement method statement will be agreed with Natural England and

    UU prior to the commencement of construction. The details will be contained within the CEMP. The

    most appropriate methods would be used, chosen on a site by site basis as described in the OHMP.

    As described in the OHMP, the gullies will be blocked, often with blocks of intact peat, at regular

    intervals along their length. This allows water tables to rise and the surface to be more water-logged

    slowing down decomposition of organic matter and creating the wet conditions for Sphagnum

    regeneration.

  • Outline Peat Management Plan

    V1 18

    100 There are however a number of considerations that must be taken into account when selecting the

    dam material which include slope, drain size and exposure of mineral substrate. It is proposed to use

    peat turves and fibrous material for ditch blocking. Peat turves will be placed over the top of dams to

    promote regrowth of vegetation. No amorphous catotelm will be used for ditch blocking. Some

    catotelm could be used in deeper furrows close to dam areas where will not be unsupported.

    101 Estimates for peat volume re-use in gully blocking have not be included within the peat balance, the

    anticipated volume of peat re-use in these features is likely to be circa 500m3, based on experience of

    similar schemes.

  • Outline Peat Management Plan

    V1 19

    References

    1. The Kyoto Protocol (1997)

    2. Kyoto Protocol and National Accounting for Peatlands (2012);

    3. The UK Climate Change Act (2008);

    4. Carbon Landscapes and Drainage, 2012 ‘The Carbon and Water Guidelines’, www.clad.ac.uk;

    5. Forestry Commission, 2011, ‘Forests and climate change: UK Forestry Standard Guidelines;

    6. Scottish Environment Protection Agency (SEPA), Regulatory Position Statement – Developments on

    Peat (2010);

    7. Scottish Government, Guidance on Developments on Peatland – Site Surveys (2011);

    8. Floating Roads on Peat, Scottish Natural Heritage (2010);

    9. Guidance on the Assessment of Peat Volumes, Reuse of Excavated Peat and the Minimisation of

    Waste, Scottish Renewables and SEPA

    10. Investigating the impacts of windfarm development on peatlands in England: Part 1 Final Report.

    Natural England Commissioned Report NECRO32.

    11. Best Practice Guidance to Planning Policy Statement 18 ‘Renewable Energy’, August 2009;

    12. Wind Farm Developments on Peat Land fact sheet. Scottish Government (June 2011)

    13. Good practice during windfarm construction, A joint publication by Scottish Renewables, Scottish

    Natural Heritage, Scottish Environment Protection Agency, Forestry Commission Scotland, Version 1,

    October 2010.

    14. JNCC Report 445 (2011) Towards an Assessment of the state of UK Peatlands. Available online at

    http://jncc.defra.gov.uk/pdf/jncc445_web.pdf Last accessed 25th June 2014.

    15. Clymo RS (1992). Models of Peat Growth. Suo, 43 (4-5) 127-136.

    16. FEH (Flood Estimation Handbook) CD-ROM 3 produced by the CEH (Centre for Ecology and

    Hydrology, 2009)

    17. National Vegetation Classification: field guide to mires and heaths. Joint Nature Conservation

    Committee (2010). Available online at http://jncc.defra.gov.uk/pdf/mires_heaths.pdf Last accessed

    18/06/14.

    http://jncc.defra.gov.uk/pdf/jncc445_web.pdfhttp://jncc.defra.gov.uk/pdf/mires_heaths.pdf

  • Outline Peat Management Plan

    V1

    Appendix 1. Peat Characteristics Data

  • Outline Peat Management Plan Peat Investigation Data

    Core numberCore Depth (m)

    Depth of peat with auger (m)

    Peat depthAcrotelm

    depthCatatelm

    depthDry soil bulk

    density

    Organic Carbon Content

    Acrotelm Catotelm Acrotelm CatotelmWell depth

    (m)Water level after

    1hr (m bgl)Water level

    02/05/14 (m bgl)

    m m m g/cm3 % H score H score B score B score m m mC0 0.10 0 0 0 0 - - - -C1 0.40 0 0 0 0 - - - -C2 0.10 0 0 0 0 - - - -C3 0.15 0 0 0 0 - - - -C4 0.20 0.2 0.2 0.05 0.15 6 10 2 2C5 0.40 0.4 0.4 0.05 0.35 6 9 2 3C6 0.70 0.7 0.7 0.15 0.55 0.28 52 5 9 3 3 0.5 0.1 0.05C7 0.35 0.35 0.35 0 0.35 - - - -C8 0.50 0.4 0.4 0 0.4 - - - - 0.52 Dry 0.76C9 0.45 0.3 0.3 0 0.3 - 9 - -C10 0.50 0.5 0.5 0.15 0.35 7 10 2 2 0.64 0.23 0.23C11 0.90 0.9 0.9 0.1 0.8 6 9 2 4 0.91 Dry 0.3C12 0.40 0.2 0.2 0.05 0.15 7 10 2 2C13 2.00 2 2 0.2 1.8 7 7 2 3C14 0.40 0.4 0.4 0.1 0.3 5 9 4 2C15 0.40 0.25 0.25 0.1 0.15 5 9 3 2C16 0.50 0.4 0.4 0.1 0.3 7 10 3 4 0.46 Dry 0.08C17 0.40 0.4 0.4 0.05 0.35 5 8 3 3C18 1.80 1.8 1.8 0.2 1.6 0.32 64 6 7 2 3 1.07 0.8 0.05C19 0.55 0.15 0.15 0.05 0.1 7 10 2 2 0.9 0.53 0.5C20 0.30 0.2 0.2 0.07 0.13 4 6 2 3C21 0.30 0.3 0.3 0.02 0.28 6 10 3 2C22 0.90 0.9 0.9 0 0.9 - 9 - 2 0.77 Dry 0.28C23 0.20 0.15 0.15 0.03 0.12 4 10 3 2C24 0.10 0.08 0.08 0.03 0.05 6 10 2 2C25 0.25 0.25 0.25 0.05 0.2 6 10 4 2C26 1.10 1.1 1.1 0.05 1.05 5 8 4 3 0.46 Dry 0C27 0.60 0.6 0.6 0.1 0.5 5 8 3 2 0.76 Dry 0C28 1.00 0.8 0.8 0.1 0.7 0.2 57 6 8 2 3 1.04 Dry 0.35C29 0.70 0.5 0.5 0.05 0.45 6 10 2 2 0.86 Dry 0.8C30 0.45 0.45 0.45 0.1 0.35 6 9 3 2C31 0.60 0.6 0.6 0.15 0.45 6 10 2 2 0.44 Dry 0.3C32 0.20 0.2 0.2 0.1 0.1 6 9 2 2C33 0.45 0.45 0.45 0.1 0.35 5 10 2 3C34 0.25 0.15 0.15 0.05 0.1 5 8 3 4C35 0.45 0.35 0.35 0.2 0.15 6 8 2 4C36 0.25 0.2 0.2 0.05 0.15 7 10 2 2

    Von Post H scores Von Post B scores Dipwell measurementsPeat depths and characteristics

    Page 1 of 2

  • Outline Peat Management Plan Peat Investigation Data

    Core numberCore Depth (m)

    Depth of peat with auger (m)

    Peat depthAcrotelm

    depthCatatelm

    depthDry soil bulk

    density

    Organic Carbon Content

    Acrotelm Catotelm Acrotelm CatotelmWell depth

    (m)Water level after

    1hr (m bgl)Water level

    02/05/14 (m bgl)

    m m m g/cm3 % H score H score B score B score m m m

    Von Post H scores Von Post B scores Dipwell measurementsPeat depths and characteristics

    C37 0.50 0.3 0.3 0.05 0.25 7 9 2 2C38 0.85 0.85 0.85 0.25 0.6 0.38 50 5 9 2 3 0.62 Dry 0.45C39 0.35 0.2 0.2 0.1 0.1 4 9 4 2C40 0.45 0.4 0.4 0.1 0.3 5 9 3 2C41 0.40 0.4 0.4 0.1 0.3 6 9 3 2C42 0.30 0.3 0.3 0.05 0.25 5 8 3 2C43 0.13 0.1 0.1 0.03 0.07 4 10 4 2C44 0.45 0.4 0.4 0.02 0.38 6 8 2 2C45 0.90 0.9 0.9 0.15 0.75 0.24 66 7 10 2 3 0.69 Dry 0.7625C46 0.20 0.2 0.2 0.05 0.15 5 9 4 3C47 0.35 0.35 0.35 0.05 0.3 5 10 4 2C48 0.15 0.1 0.1 0 0.1 - 10 - 2C49 0.25 0.25 0.25 0.05 0.2 0.38 46 7 10 3 2C50 0.15 0.1 0.1 0 0.1 - 10 - 2C51 1.00 1 1 0.15 0.85 0.15 63 6 9 4 3 0.9 0.82 0.05C52 0.35 0.35 0.35 0.05 0.3 7 10 2 2C53 0.35 0.35 0.35 0.05 0.3 7 10 3 2C54 0.25 0.1 0.1 0.02 0.08 4 9 4 4C55 0.30 0.3 0.3 0.05 0.25 7 10 2 2C56 0.65 0.65 0.65 0.02 0.63 0.33 56 8 10 3 3 1.57 1.15 0.05C57 0.85 0.85 0.85 0.1 0.75 7 9 4 3 0.66 Dry 0C58 0.95 0.95 0.95 0.02 0.93 0.18 56 5 8 3 2 0.75 0.72 0C59 0.65 0.65 0.65 0.05 0.6 7 9 3 3C60 0.35 0.35 0.35 0.1 0.25 8 9 3 2C61 1.05 1.05 1.05 0.1 0.95 0.44 54 7 9 2 2C62 1.00 1 1 0.15 0.85 6 9 3 3 0.73 Dry 0C63 1.00 1 1 0.1 0.9 7 10 2 2

    Average 0.52 0.47 0.47 0.07 0.40 0.29 56.40 5.93 9.14 2.72 2.47 0.76 0.62 0.25 STDEV 0.37 0.40 0.40 0.06 0.36 0.10 6.40 1.04 0.93 0.76 0.66 0.27 0.36 0.28 COUNT 64 64 64 64 64 10 10 54 58 54 57 20 7 20

    Page 2 of 2

  • Outline Peat Management Plan

    V1

    Appendix 2. Peat Calculations

  • Von Post Humification and Moisture Scale for Peat Classification

    H1Completely undecomposed peat which, when squeezed, releases almost clear water. Plant remains easily identifiable. No amorphous material present.

    H2Almost entirely undecomposed peat which, when squeezed, releases clear or yellowish water. Plant remains still easily identifiable. No amorphous material present.

    H3Very slightly decomposed peat which, when squeezed, releases muddy brown water, but from which no peat passes between the fingers. Plant remains still identifiable, and no amorphous material present.

    H4Slightly decomposed peat which, when squeezed, releases very muddy dark water. No peat is passed between the fingers but the plant remains are slightly pasty and have lost some of their identifiable features.

    H5Moderately decomposed peat which, when squeezed, releases very “muddy” water with a very small amount of amorphous granular peat escaping between the fingers. The structure of the plant remains is quite indistinct although it is still possible to recognize certain features. The residue is very pasty.

    H6 Moderately highly decomposed peat with a very indistict plant structure. When squeezed, about one-third of the peat escapes between the fingers. The residue is very pasty but shows the plant structure more distinctly than before squeezing.

    H7 Highly decomposed peat. Contains a lot of amorphous material with very faintly recognizable plant structure. When squeezed, about one-half of the peat escapes between the fingers. The water, if any is released, is very dark and almost pasty.

    H8Very highly decomposed peat with a large quantity of amorphous material and very indistinct plant structure. When squeezed, about two-thirds of the peat escapes between the fingers. A small quantity of pasty water may be released. The plant material remaining in the hand consists of residues such as roots and fibres that resist decomposition.

    H9Practically fully decomposed peat in which there is hardly any recognizable plant structure. When squeezed it is a fairly uniform paste.

    H10 Completely decomposed peat with no discernible plant structure. When squeezed, all the wet peat escapes between the fingers.

    B1 Dry peatB2 Low moistureB3 Moderate moisture contentB4 High moisture contentB5 Very high moisture content

    Von Post Humidification scale

    Von Post moisture scale