Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 1 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
APPENDIX 4.5 Subproject List Initial list of candidate subproject (rural road, Kishoreganj) (1/2)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 2 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Kishoreganj) (2/2)
Final Report Subproject Lists Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 3 Preparatory Survey on Upper Meghna River Basin Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Netrokona)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 4 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Sunamganj) (1/5)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 5 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Sunamganj) (2/5)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 6 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Sunamganj) (3/5)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 7 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Sunamganj) (4/5)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 8 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Sunamganj) (5/5)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 9 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Habiganj) (1/4)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 10 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Habiganj) (2/4)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 11 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Habiganj) (3/4)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 12 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (rural road, Habiganj) (4/4)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 13 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (rural road,Brahmonbaria) (1/3)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 14 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (rural road,Brahmonbaria) (2/3)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 15 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (rural road,Brahmonbaria) (3/3)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 16 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (hat, Kishoreganj)
Initial list of candidate subproject (hat, Netrokona)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 17 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (hat, Sunamganj)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 18 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (hat, Habiganj)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 19 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (hat, Brahmanbaria) (1/2)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 20 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (hat, Brahmanbaria) (2/2)
Initial list of candidate subproject (ghat, Kishoreganj)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 21 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (ghat,Netrokona)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 22 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (ghat, Sunamganj)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 23 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Initial list of candidate subproject (ghat, Habiganj)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 24 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Initial list of candidate subproject (ghat,Brahmanbaria)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 25 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Final list of candidate subproject (rural road) (1/3)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 26 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Final list of candidate subproject (rural road) (2/3)
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 27 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Final list of candidate subproject (rural road) (3/3)
Subproject Lists Final Report
Appendix 4.5
Preparatory Survey on Upper Meghna River Basin A4.5 - 28 Nippon Koei Co., Ltd.
Watershed Management Improvement Project
Final list of candidate subproject (hat)
HAT SELECTION 29
1 1-1 Kishoreganj Pakundia Agarosindur Bahahadia RM R5
2 1-4 Kishoreganj Itna Joysiddhi Mudirgaon RM N9
3 1-9 Kishoreganj Sadar Danapatuli Kaliar Kanda Bazar RM N1
4 1-20 Kishoreganj Sadar Pumdi Pumdi bazar RM R4
5 1-21 Kishoreganj Sadar " Adu master bazar RM R4
6 1-22 Kishoreganj Sadar " Nimeukhali bazar RM R4
7 1-27 Kishoreganj Sadar Saharam Dhuldia Dhuldia Hat GC N1
8 1-32 Kishoreganj Sadar Gopdighi Bogadia RM N2
9 1-41 Kishoreganj Sadar Joyka Shadakhali RM N1
10 2-5 Netrokona Purbadhala Hogla Patra Bazar RM R1
11 2-6 Netrokona Purbadhala Ghagra Ghagra Bazar RM R1
12 2-13 Netrokona Khaliajuri MENDIPUR Satgoan Bazar RM R15
13 3-16 Sunamganj Dharmapasha Selborash Badshagonj RM N4
14 3-45 Sunamganj Sunamganji Sadar Mohanpur Joynagar GC N12
15 4-3 Habiganj HABIGANJ-S Poil Poil Natun Bazar RM R13
16 4-5 Habiganj Bahubal Putijuri up Digoambar RM R13
17 4-7 Habiganj Bahubal Satkapon up Shoaia Bazer RM R13
18 4-10 Habiganj AZMIRIGANJ Badolpur Paharpur GC R8
19 4-11 Habiganj AZMIRIGANJ Kakailsew Nischintopur RM R9
20 4-17 Habiganj Baniachong Pukra Aowar Mohal Bazar RM R13
21 4-19 Habiganj Baniachong Sujatpur Sujatpur Bazar GC R10
22 4-20 Habiganj Baniachong Muradpur Muradpur Bazar RM R9
Brahmanbaria : Not applicable
Total GC Total 4 (nos)
(Growth center market) Kishoregnj 1 (nos)
Netorkona 0 (nos)
Sunamganj 1 (nos)
Habiganj 2 (nos)
Brahmanbaria 0 (nos)
RM Total 18 (nos)
(Rural market) Kishoregnj 8 (nos)
Netorkona 3 (nos)
Sunamganj 1 (nos)
Habiganj 6 (nos)
Brahmanbaria 0 (nos)
TypeHaor project
No.No. List No. District Upazila Union name Hat name
Final Report Subproject Lists
Appendix 4.5
Nippon Koei Co., Ltd. A4.5 - 29 Preparatory Survey on Upper Meghna River Basin
Watershed Management Improvement Project
Final list of candidate subproject (ghat)
GHAT SELECTIONGHAT SELECTION 29
1 1-3 Kishoreganj Itna Bashikura bazar Type-B N7
2 1-4 Kishoreganj Itna Joysiddhi bazar Type-B R9
3 1-9 Kishoreganj Sadar Kaliarkanda Bazar Ghat Type-B N1
4 1-18 Kishoreganj Sadar Char Pumdi bazar Ghat Type-B R4
5 1-19 Kishoreganj Sadar Rampur bazar Ghat Type-B R4
6 1-24 Kishoreganj Sadar Char Katkhal Type-A R9
7 1-27 Kishoreganj Sadar Olua Type-A N2
8 1-30 Kishoreganj Sadar Kacharighat Type-A R7
9 1-32 Kishoreganj Sadar Panahar bazar Ghat Type-B N1
10 1-33 Kishoreganj Sadar shudi bazar Ghat Type-B N1
11 2-4 Netrokona Purbadhala Patra Ghat Type-A R1
12 2-5 Netrokona Purbadhala Ghagra Ghat Type-A R1
13 2-6 Netrokona Purbadhala Moheshpotti Ghat Type-A R1
14 3-9 Sunamganj Sulla Rahutola Bazar Ghat Type-B R14
15 3-37 Sunamganj Derai Boalia Type-A R8
16 3-46 Sunamganj SUNAMGANJ-SADAR Joynagar Ghat Type-A N12
17 3-55 Sunamganj Dakhin Sunamganj Pathariabazar GC Type-B N12
18 3-56 Sunamganj Dakhin Sunamganj Birgaonbazar Type-B N12
19 4-2 Habiganj HABIGANJ-S Purbo Poil Bazar Ghat Type-B R13
20 4-3 Habiganj HABIGANJ-S Poil Natun Bazar Ghat Type-B R13
21 4-11 Habiganj Baniachonj Sujath pur Bazar Type-B R10
Brahmanbaria : Not applicable
Type-A : Not with market, Type-B : with market
Type-A Type-B
Total 21 8 13 (nos)
Kishoregnj 10 3 7 (nos)
Netorkona 3 3 0 (nos)
Sunamganj 5 2 3 (nos)
Habiganj 3 0 3 (nos)
Brahmanbaria 0 0 0 (nos)
No. List No. District Upazila Ghat nameHaor project
No.Type