Appendix 11-Updated Schedule

Embed Size (px)

Citation preview

  • 7/29/2019 Appendix 11-Updated Schedule

    1/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    1 44% AL JALAMID COMMUNICATIONS SCHEDULE 246 days Jul 5 '09 Apr 29 '10 114.96 days Jul 5 '09 NA

    2 100% General 82 days Jul 5 '09 Oct 14 '09 82 days Jul 5 '09 Oct 14 '09

    3 100% NOA Signed 1 day Jul 5 '09 Jul 5 '09 0 days Jul 5 '09 Jul 5 '09

    4 100% Kick Off Meeting 0 days Jul 21 '09 Jul 21 '09 0 days Jul 21 '09 Jul 21 '09 3

    5 100% Pre-Mobilization Deliverables 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09

    6 100% HSE Management Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 47 100% 90 Day Look ahead Schedule 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 6SS

    8 100% Temporary Facilities Layout Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 7SS

    9 100% Construction Licenses And Permits 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 8SS

    10 100% Site Mobilization Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 9SS

    11 100% Safety Induction And Issuance Of Project Badges 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 10SS

    12 100% Equipment Inspection Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 11SS

    13 100% Insurance Policies 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 12SS

    14 100% Detailed Sub-Contract Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 13SS

    15 100% Quality Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 14SS

    16 100% Completion Of Pre-Mobilization And Commenced Mobilization 0 days Jul 29 '09 Jul 29 '09 0 days Jul 27 '09 Jul 27 '09 5

    17 100% ID Preparation 82 days Jul 5 '09 Oct 14 '09 82 days Jul 5 '09 Oct 14 '09

    18

    19 97% Engineering Design For Al Jalamid 102 days Aug 1 '09 Dec 9 '09 167 days Aug 2 '09 NA

    20 100% Initial Site Visit 2 days Aug 10 '09 Aug 11 '09 2 days Aug 10 '09 Aug 11 '09

    21 100% 30% Design 55 days Aug 1 '09 Oct 10 '09 72 days Aug 2 '09 Oct 31 '09

    22 100% Design Sessions 6 days Aug 1 '09 Aug 6 '09 6 days Aug 2 '09 Aug 8 '0923 100% Voice & Data Communication Network , OSP, ISP, Trenching 2 days Aug 1 '09 Aug 2 '09 1 day Aug 2 '09 Aug 2 '09 4FS+9 days

    24 100% TETRA Wireless 2 days Aug 1 '09 Aug 2 '09 1 day Aug 3 '09 Aug 3 '09 23SS

    25 100% GSM Enhancement 2 days Aug 3 '09 Aug 4 '09 1 day Aug 5 '09 Aug 5 '09 24SS+2 days

    26 100% Video Conferencing System 2 days Aug 3 '09 Aug 4 '09 1 day Aug 5 '09 Aug 5 '09 25SS

    27 100% VSAT System 2 days Aug 5 '09 Aug 6 '09 1 day Aug 8 '09 Aug 8 '09 26SS+2 days

    28 100% Drawings Submittals 30 days Aug 12 '09 Sep 15 '09 1 day Aug 4 '09 Aug 4 '09 23,24,25,26,27,20

    29 100% Materials Submittals 30 days Aug 12 '09 Sep 15 '09 22 days Aug 26 '09 Sep 27 '09 28SS

    30 100% 30% Design Submission 1 day Sep 16 '09 Sep 16 '09 22 days Aug 26 '09 Sep 27 '09 28,29

    31 100% 30% Design Review 5 days Sep 17 '09 Sep 29 '09 1 day Sep 27 '09 Sep 27 '09 30

    32 100% 30% Design Meeting 1 day Sep 30 '09 Sep 30 '09 9 days Sep 28 '09 Oct 7 '09 31

    33 100% Incorporate 30% Design Changes 7 days Oct 1 '09 Oct 8 '09 1 day Oct 3 '09 Oct 3 '09 32

    34 100% 30% Design Approval 1 day Oct 10 '09 Oct 10 '09 6 days Oct 4 '09 Oct 10 '09 33

    35 100% 30% Design Complete 0 days Oct 10 '09 Oct 10 '09 1 day Oct 31 '09 Oct 31 '09 34

    36 100% 60% Design 17 days Oct 10 '09 Oct 28 '09 37 days Oct 11 '09 Nov 22 '09

    37 100% Incorporation Of 30 % Design Comments 12 days Oct 10 '09 Oct 22 '09 22 days Oct 11 '09 Nov 4 '09 33

    38 100% 60% Design Submittal 1 day Oct 24 '09 Oct 24 '09 1 day Nov 4 '09 Nov 4 '09 37

    39 100% 60% Design Review 3 days Oct 25 '09 Oct 27 '09 1 day Nov 9 '09 Nov 9 '09 38

    40 100% 60% Design Approval 1 day Oct 28 '09 Oct 28 '09 1 day Nov 22 '09 Nov 22 '09 39

    41 100% 60% Design Complete 0 days Oct 28 '09 Oct 28 '09 0 days Nov 22 '09 Nov 22 '09 40

    42 100% 90% Design 14 days Oct 28 '09 Nov 12 '09 37 days Nov 22 '09 Jan 9 '10

    43 100% Incorporation Of 60% Design Comments 7 days Oct 28 '09 Nov 4 '09 24 days Nov 22 '09 Dec 24 '09 39

    44 100% 90% Design Submittal 1 day Nov 5 '09 Nov 5 '09 1 day Dec 24 '09 Dec 24 '09 43

    45 100% 90% Design Review 5 days Nov 7 '09 Nov 11 '09 5 days Jan 3 '10 Jan 7 '10 44

    46 100% 90% Design Approval 1 day Nov 12 '09 Nov 12 '09 1 day Jan 9 '10 Jan 9 '10 45

    47 100% 90% Design Complete 0 days Nov 12 '09 Nov 12 '09 0 days Jan 9 '10 Jan 9 '10 46

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 1

  • 7/29/2019 Appendix 11-Updated Schedule

    2/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    48 89% 100% Design 19 days Nov 12 '09 Dec 9 '09 41 days Jan 9 '10 NA

    49 100% Incorporation Of 90% Design Comments 10 days Nov 12 '09 Nov 23 '09 37 days Jan 9 '10 Feb 20 '10 45

    50 100% 100% Design Submittals 1 day Nov 24 '09 Nov 24 '09 1 day Feb 20 '10 Feb 21 '10 49

    51 43% 100% Design Review 7 days Nov 25 '09 Dec 8 '09 3 days Feb 22 '10 NA 50

    52 0% 100% Design Approval 1 day Dec 9 '09 Dec 9 '09 0 days NA NA 51

    53 0% 100% Design Complete 0 days Dec 9 '09 Dec 9 '09 0 days NA NA 5254

    55 73% Procurement 78 days Oct 24 '09 Jan 28 '10 89.24 days Oct 31 '09 NA

    56 100% Commence Placement Of Purchase Order 0 days Oct 24 '09 Oct 24 '09 0 days Oct 31 '09 Oct 31 '09 3 5FS+12 days

    57 58% Data and Voice Communication Equipment 76 days Oct 25 '09 Jan 26 '10 43.76 days Dec 29 '09 NA 56

    58 100% Placing of P.O. 1 day Oct 25 '09 Oct 25 '09 1 day Jan 26 '10 Jan 26 '10

    59 90% Delivery to SBM Warehouse 54 days Oct 26 '09 Jan 2 '10 48.6 days Dec 29 '09 NA 58

    60 0% Staging & Configuration 21 days Jan 3 '10 Jan 26 '10 0 days NA NA 59

    61 0% Switches, Routers and Firewalls IOS Upgrade 5 days Jan 3 '10 Jan 7 '10 0 days NA NA

    62 0% Backbone Switches Configuration 3 days Jan 9 '10 Jan 11 '10 0 days NA NA 61

    63 0% Edge Switches Configuration 4 days Jan 9 '10 Jan 12 '10 0 days NA NA 62SS

    64 0% Call Manager Version Upgrade 1 day Jan 13 '10 Jan 13 '10 0 days NA NA 63

    65 0% Call Managers Configuration 6 days Jan 14 '10 Jan 20 '10 0 days NA NA 64

    66 0% IP Phones Addition 4 days Jan 14 '10 Jan 18 '10 0 days NA NA 65SS

    67 0% Unity Version Upgrade 1 day Jan 19 '10 Jan 19 '10 0 days NA NA 66

    68 0% Unity Configuration 6 days Jan 20 '10 Jan 26 '10 0 days NA NA 67

    69 0% Equipment Ready for Delivery to Site 0 days Jan 26 '10 Jan 26 '10 0 days NA NA 6070 0% Industrial Buildings 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    71 0% Laboratory Building 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    72 0% Guardhouse 2 Explosive Storage 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    73 0% Water Plant Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    74 0% Administration Building 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    75 0% Training Center 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    76 0% Security Building 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    77 0% Area 20 Secondary Crushing Substation & Operations Bl . 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    78 0% Area 30 Communition Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    79 0% First Aid Clinic/ Firehouse 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    80 0% Area 70 Load Out Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    81 0% Central Control Building 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    82 0% Substation (Utilities) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    83 0% Fuel Truck Comfort Station 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    84 0% Area 10 Primary Crushing Substation & Operations Bldg. 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    85 0% Mosque 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    86 0% Dining / Change House 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    87 0% Guardhouse 1A (Main Gate) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    88 0% Guardhouse 1B (High Security) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    89 0% Guardhouse Truck Area ( Guardhouse 3) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    90 0% Area 60 Dryer Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    91 0% Maintenance / Warehouse 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    92 0% Area 40 Flotation Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    93 0% Power Plant Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    94 0% Al Jalamid Village 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 2

  • 7/29/2019 Appendix 11-Updated Schedule

    3/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    95 0% Labor Residence 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    96 0% Management Residence Type 1 (2ea) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    97 0% Supervisor Residence (4ea) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    98 0% Management Residence Type 2 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    99 0% Laundry/Warehouse 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    100 0% Workshop 0 days Jan 26 '10 Jan 26 '10 0 days NA NA101 0% Central Common Area 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    102 0% Dining Hall and Kitchen 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    103 0% Club House 0 days Jan 26 '10 Jan 26 '10 0 days NA NA

    104 0% Mosque 0 days J an 26 '10 Jan 26 '10 0 days NA NA

    105 100% OSP Cabling 30 days Oct 27 '09 Dec 6 '09 24 days Dec 16 '09 Jan 12 '10 56,57SS+2 days

    106 100% Placing of P.O. 1 day Oct 27 '09 Oct 27 '09 1.8 days Dec 16 '09 Dec 17 '09

    107 100% Delivery to Site 30 days Oct 27 '09 Dec 6 '09 11 days Dec 31 '09 Jan 12 '10

    108 61% Wireless Communication 73 days Oct 29 '09 Jan 27 '10 43.59 days Nov 24 '09 NA 56,105SS+2 days

    109 100% Placing of P.O. 1 day Oct 29 '09 Oct 29 '09 1 day Nov 24 '09 Nov 24 '09

    110 60% Delivery to Site 72 days Oct 31 '09 Jan 27 '10 43.2 days Nov 24 '09 NA 109

    111 90% VSAT 11 days Nov 1 '09 Nov 12 '09 76.62 days Nov 11 '09 NA 56,108SS+2 days

    112 100% Placing of P.O. 1 day Nov 1 '09 Nov 1 '09 1 day Nov 11 '09 Nov 11 '09

    113 90% Delivery to Site 10 days Nov 2 '09 Nov 12 '09 63 days Dec 5 '09 NA 112

    114 59% GSM Enhancement 64 days Nov 3 '09 Jan 21 '10 58.2 days Nov 7 '09 NA 56,111SS+2 days

    115 100% Final BOM 1 day Nov 3 '09 Nov 3 '09 1 day Nov 7 '09 Nov 7 '09

    116 100% Material Order (PO) 1 day Nov 4 '09 Nov 4 '09 1 day Dec 24 '09 Dec 24 '09 115117 60% Material Delivery Passive 30 days Nov 5 '09 Dec 15 '09 18 days Dec 26 '09 NA 116

    118 60% Material Delivery Active 60 days Nov 5 '09 Jan 19 '10 36 days Dec 26 '09 NA 116

    119 100% Site Storage Available 1 day Nov 3 '09 Nov 3 '09 1 day Dec 25 '09 Dec 26 '09

    120 40% Material Delivery Passive (SBM Warehouse) 3 days Dec 16 '09 Dec 19 '09 1.2 days Jan 30 '10 NA 117,119

    121 0% Material Delivery Active (SBM Warehouse) 1 day Jan 20 '10 Jan 20 '10 0 days NA NA 118,119

    122 0% Material Delivery Passive (to site) 1 day Dec 20 '09 Dec 20 '09 0 days NA NA 119,120

    123 0% Material Delivery Active (to site) 1 day Jan 21 '10 Jan 21 '10 0 days NA NA 119,121

    124 100% Structured Cabling & Telecomm Spaces 30 days Nov 5 '09 Dec 15 '09 25 days Dec 15 '09 Jan 12 '10 56,114SS+2 days

    125 100% Placing of P.O. 1 day Nov 5 '09 Nov 5 '09 1 day Dec 15 '09 Dec 15 '09

    126 100% Delivery to Site 30 days Nov 5 '09 Dec 15 '09 24 days Dec 16 '09 Jan 12 '10

    127 100% Video Conferencing Equipment 30 days Nov 8 '09 Dec 17 '09 39 days Nov 17 '09 Jan 6 '10 56,124SS+2 days

    128 100% Placing of P.O. 1 day Nov 8 '09 Nov 8 '09 1 day Nov 17 '09 Nov 17 '09

    129 100% Delivery to Site 30 days Nov 8 '09 Dec 17 '09 38 days Nov 18 '09 Jan 6 '10

    130 100% Civil Materials 10 days Nov 10 '09 Nov 21 '09 15 days Dec 15 '09 Dec 31 '09 56,127SS+2 days

    131 100% Placing of P.O. 1 day Nov 10 '09 Nov 10 '09 1 day Dec 15 '09 Dec 15 '09

    132 100% Delivery to Site 10 days Nov 10 '09 Nov 21 '09 14 days Dec 16 '09 Dec 31 '09

    133 0% Procurement Completion 1 day Jan 28 '10 Jan 28 '10 0 days NA NA 57,111,108,114,124,1

    134

    135 18% Installation/Construction 181 days Aug 18 '09 Mar 29 '10 25.92 days Oct 24 '09 NA

    136 100% Detailed Site Survey 5 days Oct 27 '09 Nov 1 '09 5 days Oct 25 '09 Oct 29 '09 1 7FS+10 days,35

    137 100% Construction Kick-Off Meeting 1 day Oct 27 '09 Oct 27 '09 1 day Jan 2 '10 Jan 2 '10

    138 100% Site Mobilization 38 days Oct 25 '09 Dec 13 '09 38 days Nov 7 '09 Dec 26 '09

    139 100% Site Office 35 days Oct 25 '09 Dec 9 '09 30 days Nov 16 '09 Dec 26 '09 35FS+12 days

    140 100% Site Offices Fabrication 25 days Oct 25 '09 Nov 22 '09 12 days Dec 5 '09 Dec 17 '09

    141 100% Land Preparation 10 days Oct 25 '09 Nov 4 '09 11 days Nov 16 '09 Dec 3 '09 140SS

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 3

  • 7/29/2019 Appendix 11-Updated Schedule

    4/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    142 100% Site Offices Delivery to Project Site 2 days Nov 23 '09 Nov 24 '09 3 days Dec 1 '09 Dec 6 '09 140,141

    143 100% Site Offices Assembly 6 days Nov 25 '09 Dec 7 '09 16 days Dec 2 '09 Dec 21 '09 142

    144 100% Site Office Furniture Delivery to Project Site 2 days Dec 8 '09 Dec 9 '09 1 day Dec 26 '09 Dec 26 '09 143

    145 100% Complete Site Offices & Temporary Facilities 0 days Dec 9 '09 Dec 9 '09 1 day Dec 26 '09 Dec 26 '09 140,141,142,143,144

    146 100% Manpower Mobilization 3 days Dec 10 '09 Dec 13 '09 31 days Nov 7 '09 Dec 17 '09 1 39,17

    147 47% OSP 58 days Dec 14 '09 Feb 18 '10 18.92 days Jan 13 '10 NA 35,146148 70% Al Jalamid Industrial Area 58 days Dec 14 '09 Feb 18 '10 25.9 days Jan 17 '10 NA

    149 70% FOC Pulling 58 days Dec 14 '09 Feb 18 '10 25.9 days Jan 17 '10 NA 105

    150 100% Admin Building to Central Control Building 4 days Dec 14 '09 Dec 17 '09 1 day Feb 10 '10 Feb 10 '10

    151 100% Admin Building to Mosque 1 day Dec 14 '09 Dec 14 '09 1 day Jan 26 '10 Jan 26 '10 150SS

    152 100% Admin Building to Training Center 1 day Dec 15 '09 Dec 15 '09 1 day Jan 28 '10 Jan 28 '10 151

    153 100% Admin Building to Security Building 2 days Dec 16 '09 Dec 17 '09 1 day Feb 14 '10 Feb 14 '10 152

    154 100% Admin Building to Guard House 1A 1 day Dec 19 '09 Dec 19 '09 1 day Feb 14 '10 Feb 15 '10 153

    155 100% Admin Building to Guard House Explosive Storage 15 days Dec 19 '09 Jan 4 '10 5 days Jan 23 '10 Jan 27 '10 154SS

    156 0% Admin Building to Admin Village X 2 15 days Dec 31 '09 Jan 17 '10 0 days NA NA 155FS-4 days

    157 100% Training Center to Change House & Dining Hall 1 day Jan 5 '10 Jan 5 '10 1 day Jan 27 '10 Jan 27 '10 155

    158 100% Security Building to First Aid Clinic 1 day Jan 6 '10 Jan 6 '10 1 day Feb 15 '10 Feb 15 '10 157

    159 100% First Aid Clinic to Guard House 1A 1 day Jan 16 '10 Jan 16 '10 1 day Feb 24 '10 Feb 24 '10 156FS-2 days

    160 100% Security Building to Guardhouse 1B 1 day Jan 16 '10 Jan 16 '10 1 day Feb 16 '10 Feb 16 '10 159SS

    161 100% Central Control Building to Laboratory X 2 6 days Jan 17 '10 Jan 23 '10 1 day Feb 16 '10 Feb 16 '10 160

    162 100% Security Building to Central Control Bldg 3 days Jan 19 '10 Jan 21 '10 1 day Feb 16 '10 Feb 16 '10 161SS+2 days

    163 100% Laboratory to Substation Utilities X 2 3 days Jan 23 '10 Jan 25 '10 1 day Feb 28 '10 Feb 28 '10 162164 100% Substation Utilities to Maintenance Warehouse X 2 3 days Jan 23 '10 Jan 25 '10 1 day Feb 13 '10 Feb 13 '10 163SS

    165 100% Central Control Building to Maintenance Warehouse X 2 5 days Jan 26 '10 Jan 31 '10 1 day Feb 11 '10 Feb 11 '10 164

    166 100% Central Control Building to Dryer Substation 3 days Feb 1 '10 Feb 3 '10 1 day Jan 20 '10 Jan 20 '10 165

    167 100% Central Control Building to Water Plant Substation 2 days Feb 1 '10 Feb 2 '10 1 day Jan 28 '10 Jan 28 '10 166SS

    168 100% Central Control Building to Guardhouse 3 2 days Feb 3 '10 Feb 4 '10 1 day Jan 20 '10 Jan 20 '10 167

    169 100% Water Plant Substation to Comfort Station 1 day Feb 3 '10 Feb 3 '10 1 day Jan 21 '10 Jan 21 '10 168SS

    170 100% Central Control Building to Power Plant Main Substation 3 days Feb 4 '10 Feb 7 '10 1 day Feb 18 '10 Feb 18 '10 169

    171 100% Central Control Building to Loadout Substation 1 day Feb 4 '10 Feb 4 '10 1 day Feb 18 '10 Feb 18 '10 170SS

    172 100% Central Control Building to Flotation Substation 1 day Feb 6 '10 Feb 6 '10 1 day Jan 26 '10 Jan 26 '10 171

    173 100% Central Control Building to Communition Substation 2 days Feb 7 '10 Feb 8 '10 2 days Jan 27 '10 Jan 28 '10 172

    174 100% Central Control Building to Primary Crushing 7 days Feb 9 '10 Feb 16 '10 4 days Jan 17 '10 Jan 20 '10 173

    175 100% Central Control Building to Secondary Crushing Substati 6 days Feb 13 '10 Feb 18 '10 3 days Feb 13 '10 Feb 15 '10 174SS+3 days

    176 0% Al Jalamid Village 6 days Dec 14 '09 Dec 20 '09 0 days NA NA

    177 0% FOC Pulling 6 days Dec 14 '09 Dec 20 '09 0 days NA NA 105

    178 0% Village Central Common Area To Mosque 6 days Dec 14 '09 Dec 20 '09 0 days NA NA

    179 0% Village Central Common Area To Dining Hall 3 days Dec 14 '09 Dec 16 '09 0 days NA NA

    180 0% Village Central Common Area To Gatehouse 3 days Dec 14 '09 Dec 16 '09 0 days NA NA

    181 0% Village Central Common Area To Club House 3 days Dec 14 '09 Dec 16 '09 0 days NA NA

    182 0% Village Central Common Area To Laborer's Residence 3 days Dec 14 '09 Dec 16 '09 0 days NA NA

    183 0% Laborer's Residence To Supervisor's Residence 3 days Dec 14 '09 Dec 16 '09 0 days NA NA

    184 0% Supervisor's Residence To Manager's Residence 3 days Dec 14 '09 Dec 16 '09 0 days NA NA

    185 0% Building Site Access 81 days Aug 18 '09 Dec 1 '09 0 days Nov 24 '09 NA

    186 100% Industrial Buildings 81 days Aug 18 '09 Dec 1 '09 57 days Nov 24 '09 Feb 4 '10

    187 100% Laboratory Building 0 days Aug 18 '09 Aug 18 '09 0 days Nov 24 '09 Nov 24 '09

    188 100% Guardhouse 2 Explosive Storage 0 days Aug 25 '09 Aug 25 '09 0 days Dec 5 '09 Dec 5 '09

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 4

  • 7/29/2019 Appendix 11-Updated Schedule

    5/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    189 100% Water Plant Substation 0 days Sep 10 '09 Sep 10 '09 0 days Dec 7 '09 Dec 7 '09

    190 100% Administration Building 0 days Sep 20 '09 Sep 20 '09 0 days Dec 9 '09 Dec 9 '09

    191 100% Training Center 0 days Sep 30 '09 Sep 30 '09 0 days Dec 12 '09 Dec 12 '09

    192 100% Security Building 0 days Oct 10 '09 Oct 10 '09 0 days Dec 14 '09 Dec 14 '09

    193 100% Area 20 Secondary Crushing Substation & Operations Bldg. 0 days Oct 15 '09 Oct 15 '09 0 days Dec 16 '09 Dec 16 '09

    194 100% Area 30 Communition Substation 0 days Oct 15 '09 Oct 15 '09 0 days Dec 16 '09 Dec 16 '09

    195 100% First Aid Clinic/ Firehouse 0 days Oct 20 '09 Oct 20 '09 0 days Dec 21 '09 Dec 21 '09

    196 100% Area 70 Load Out Substation 0 days Oct 20 '09 Oct 20 '09 0 days Dec 23 '09 Dec 23 '09

    197 100% Central Control Building 0 days Oct 20 '09 Oct 20 '09 0 days Dec 28 '09 Dec 28 '09

    198 100% Substation Utilities 0 days Oct 31 '09 Oct 31 '09 0 days Jan 3 '10 Jan 3 '10

    199 100% Feul Truck Comfort Station 0 days Oct 31 '09 Oct 31 '09 0 days Jan 5 '10 Jan 5 '10

    200 100% Area 10 Primary Crushing Substation & Operations Building 0 days Oct 31 '09 Oct 31 '09 0 days Jan 10 '10 Jan 10 '10

    201 100% Mosque 0 days Oct 31 '09 Oct 31 '09 0 days Jan 12 '10 Jan 12 '10

    202 100% Change House & Dining Hall Building 0 days Oct 31 '09 Oct 31 '09 0 days Jan 16 '10 Jan 16 '10

    203 100% Guardhouse 1A (Main Gate) 0 days Nov 15 '09 Nov 15 '09 0 days Jan 18 '10 Jan 18 '10

    204 100% Guardhouse 1B (High Security) 0 days Nov 15 '09 Nov 15 '09 0 days Jan 21 '10 Jan 21 '10

    205 100% Guardhouse Truck Area( Guardhouse 3) 0 days Nov 15 '09 Nov 15 '09 0 days Jan 24 '10 Jan 24 '10

    206 100% Area 60 Dryer Substation 0 days Nov 10 '09 Nov 10 '09 0 days Jan 28 '10 Jan 28 '10

    207 100% Maintenance / Warehouse 0 days Nov 21 '09 Nov 21 '09 0 days Jan 31 '10 Jan 31 '10

    208 100% Area 60 Flotation Substation 0 days Nov 30 '09 Nov 30 '09 0 days Feb 2 '10 Feb 2 '10

    209 100% Power Plant & Main Substation 0 days Dec 1 '09 Dec 1 '09 0 days Feb 4 '10 Feb 4 '10

    210 0% Al Jalamid Village 40 days Oct 5 '09 Nov 21 '09 0 days NA NA211 0% Labor Residence 0 days Oct 5 '09 Oct 5 '09 0 days NA NA

    212 0% Management Residence Type 1 (2ea) 0 days Oct 15 '09 Oct 15 '09 0 days NA NA

    213 0% Supervisor Residence (4ea) 0 days Oct 18 '09 Oct 18 '09 0 days NA NA

    214 0% Management Residence Type 2 0 days Oct 20 '09 Oct 20 '09 0 days NA NA

    215 0% Laundry/Warehouse 0 days Nov 10 '09 Nov 10 '09 0 days NA NA

    216 0% Workshop 0 days Nov 10 '09 Nov 10 '09 0 days NA NA

    217 0% Central Common Area 0 days Nov 10 '09 Nov 10 '09 0 days NA NA

    218 0% Dining Hall and Kitchen 0 days Nov 15 '09 Nov 15 '09 0 days NA NA

    219 0% Club House 0 days Nov 15 '09 Nov 15 '09 0 days NA NA

    220 0% Mosque 0 days Nov 21 '09 Nov 21 '09 0 days NA NA

    221 6% ISP 91 days D ec 13 '09 Mar 29 '10 6.67 days Dec 17 '09 NA

    222 8% Industrial Buildings 91 days Dec 13 '09 Mar 29 '10 8.78 days Dec 17 '09 NA 146

    223 20% Laboratory Building 44 days Dec 13 '09 Feb 2 '10 18 days Dec 17 '09 NA 187

    224 100% Communication Room Ready 0 days Dec 13 '09 Dec 13 '09 0 days Dec 17 '09 Dec 17 '09

    225 0% Installation of Cable Ladders & Trays 1 day Dec 16 '09 Dec 16 '09 0 days NA NA 124

    226 100% Installation of Communication Racks 1 day Dec 16 '09 Dec 16 '09 1 day Feb 20 '10 Feb 20 '10 225SS,124

    227 0% Installation Of Power Cabling & Grounding 1 day Dec 16 '09 Dec 16 '09 0 days NA NA 226SS,124

    228 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Dec 16 '09 Dec 16 '09 1 day Feb 21 '10 Feb 21 '10 227SS,124

    229 100% Testing of UTP Cables 1 day Dec 17 '09 Dec 17 '09 1 day Feb 22 '10 Feb 22 '10 228

    230 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 224,71

    231 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 229SS,230

    232 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 226,230

    233 0% Installation of UTP & Fiber Patch cords 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 124,228

    234 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 233,230

    235 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 161,163,231

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 5

  • 7/29/2019 Appendix 11-Updated Schedule

    6/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    236 0% Testing of Fiber Cables 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 235

    237 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 232,226,228,231

    238 0% Interfacing With Overall Network 1 day Feb 2 '10 Feb 2 '10 0 days NA NA 236

    239 0% Guard House 2 Explosive Storage 40 days Dec 16 '09 Feb 1 '10 0 days NA NA 188,223SS+3 days

    240 0% Communication Room Ready 0 days Dec 16 '09 Dec 16 '09 0 days NA NA

    241 0% Installation of Cable Ladders & Trays 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 124

    242 0% Installation of Communication Racks 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 241SS,124

    243 0% Installation Of Power Cabling & Grounding 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 242SS,124

    244 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 243SS,124

    245 0% Testing of UTP Cables 1 day Dec 19 '09 Dec 19 '09 0 days NA NA 244

    246 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 240,72

    247 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 245SS,246

    248 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 242,246

    249 0% Installation of UTP & Fiber Patch cords 1 day Dec 19 '09 Dec 19 '09 0 days NA NA 124,244

    250 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 249,246

    251 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 155,247

    252 0% Testing of Fiber Cables 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 251

    253 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 248,242,244,247

    254 0% Interfacing With Overall Network 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 253

    255 13% Water Plant Substation 41 days Dec 21 '09 Feb 7 '10 11.07 days Dec 26 '09 NA 189,239SS+4 days

    256 0% Communication Room Ready 0 days Dec 21 '09 Dec 21 '09 0 days NA NA

    257 0% Installation of Cable Ladders & Trays 1 day Dec 22 '09 Dec 22 '09 0 days NA NA 124258 100% Installation of Communication Racks 1 day Dec 22 '09 Dec 22 '09 1 day Feb 25 '10 Feb 25 '10 257SS,124

    259 0% Installation Of Power Cabling & Grounding 1 day Dec 22 '09 Dec 22 '09 0 days NA NA 258SS,124

    260 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Dec 22 '09 Dec 22 '09 1 day Feb 25 '10 Feb 25 '10 259SS,124

    261 0% Testing of UTP Cables 1 day Dec 23 '09 Dec 23 '09 0 days NA NA 260

    262 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 256,73

    263 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 261SS,262

    264 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 258,262

    265 0% Installation of UTP & Fiber Patch cords 1 day Dec 23 '09 Dec 23 '09 0 days NA NA 124,260

    266 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 265,262

    267 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 4 '10 Feb 4 '10 0 days NA NA 167,169,263

    268 0% Testing of Fiber Cables 1 day Feb 6 '10 Feb 6 '10 0 days NA NA 267

    269 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 264,258,260,263

    270 0% Interfacing With Overall Network 1 day Feb 7 '10 Feb 7 '10 0 days NA NA 268

    271 19% Administration Building 48 days Dec 24 '09 Feb 18 '10 17.46 days Dec 29 '09 NA 190,255SS+3 days

    272 0% Communication Room Ready 0 days Dec 24 '09 Dec 24 '09 0 days NA NA

    273 100% Installation of Cable Ladders & Trays 6 days Dec 26 '09 Dec 31 '09 2 days Feb 13 '10 Feb 14 '10 124

    274 100% Installation of Communication Racks 2 days Dec 26 '09 Dec 27 '09 1 day Feb 17 '10 Feb 17 '10 273SS,124

    275 0% Installation Of Power Cabling & Grounding 5 days Dec 28 '09 Jan 2 '10 0 days NA NA 274,124

    276 100% Installation & Termination of UTP Patch Panel & Face Pl 4 days Dec 28 '09 Dec 31 '09 7 days Feb 18 '10 Feb 25 '10 275SS,124

    277 100% Testing of UTP Cables 2 days Jan 2 '10 Jan 3 '10 1 day Feb 24 '10 Feb 24 '10 276

    278 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 272,74

    279 0% Installation & Configuration of Switches 10 days Jan 30 '10 Feb 9 '10 0 days NA NA 274,278

    280 0% Installation of Fiber Patch Panel 7 days Jan 30 '10 Feb 6 '10 0 days NA NA 277,278

    281 0% Installation of UTP & Fiber Patch cords 10 days Jan 2 '10 Jan 12 '10 0 days NA NA 276,124

    282 0% Installation of IP Telephones 10 days Jan 30 '10 Feb 9 '10 0 days NA NA 281,278

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 6

  • 7/29/2019 Appendix 11-Updated Schedule

    7/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    283 100% Installation of Video Conferencing Equipment 6 days Jan 13 '10 Jan 19 '10 2 days Jan 4 '10 Jan 5 '10 127,281

    284 0% Splicing Of Indoor/Outdoor Fiber Cables 7 days Feb 7 '10 Feb 14 '10 0 days NA NA 150,151,152,153,154, , ,

    285 0% Testing of Fiber Cables 3 days Feb 15 '10 Feb 17 '10 0 days NA NA 284

    286 0% Labeling Rack, Patch panels and Switches 2 days Feb 10 '10 Feb 11 '10 0 days NA NA 279,274,276,280

    287 0% Interfacing With Overall Network 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 285

    288 7% Training Center 37 days Jan 3 '10 Feb 15 '10 5.93 days Jan 7 '10 NA 191,271SS+8 days

    289 0% Communication Room Ready 0 days Jan 3 '10 Jan 3 '10 0 days NA NA

    290 0% Installation of Cable Ladders & Trays 5 days Jan 4 '10 Jan 9 '10 0 days NA NA 124

    291 100% Installation of Communication Racks 1 day Jan 4 '10 Jan 4 '10 1 day Feb 21 '10 Feb 21 '10 290SS,124

    292 0% Installation Of Power Cabling & Grounding 3 days Jan 5 '10 Jan 7 '10 0 days NA NA 291,124

    293 100% Installation & Termination of UTP Patch Panel & Face Pl 5 days Jan 5 '10 Jan 10 '10 1 day Feb 22 '10 Feb 22 '10 292SS,124

    294 100% Testing of UTP Cables 2 days Jan 11 '10 Jan 12 '10 1 day Feb 25 '10 Feb 25 '10 293

    295 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 289,75

    296 0% Installation of Fiber Patch Panel 5 days Jan 30 '10 Feb 3 '10 0 days NA NA 295,294

    297 0% Installation & Configuration of Switches 6 days Jan 30 '10 Feb 4 '10 0 days NA NA 291,295

    298 0% Installation of UTP & Fiber Patch cords 2 days Jan 11 '10 Jan 12 '10 0 days NA NA 293,124

    299 0% Installation of IP Telephones 3 days Feb 6 '10 Feb 8 '10 0 days NA NA 297,295

    300 0% Installation of Video Conferencing Equipment 5 days Jan 13 '10 Jan 18 '10 0 days NA NA 298,127

    301 0% Splicing Of Indoor/Outdoor Fiber Cables 7 days Feb 4 '10 Feb 11 '10 0 days NA NA 152,157,296

    302 0% Testing of Fiber Cables 2 days Feb 13 '10 Feb 14 '10 0 days NA NA 301

    303 0% Labeling Rack, Patch panels and Switches 2 days Feb 6 '10 Feb 7 '10 0 days NA NA 297,291,293,296

    304 0% Interfacing With Overall Network 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 302305 14% Security Building 22 days Jan 10 '10 Feb 4 '10 9.71 days Jan 14 '10 NA 192,288SS+6 days

    306 0% Communication Room Ready 0 days Jan 10 '10 Jan 10 '10 0 days NA NA

    307 0% Installation of Cable Ladders & Trays 3 days Jan 11 '10 Jan 13 '10 0 days NA NA 124

    308 100% Installation of Communication Racks 1 day Jan 11 '10 Jan 11 '10 1 day Feb 21 '10 Feb 21 '10 307SS,124

    309 0% Installation Of Power Cabling & Grounding 2 days Jan 12 '10 Jan 13 '10 0 days NA NA 308,124

    310 100% Installation & Termination of UTP Patch Panel & Face Pl 2 days Jan 12 '10 Jan 13 '10 1 day Feb 24 '10 Feb 24 '10 309SS,124

    311 100% Testing of UTP Cables 1 day Jan 14 '10 Jan 14 '10 1 day Feb 25 '10 Feb 25 '10 310

    312 0% Delivery from Warehouse to Building Communication Ro 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 306,76

    313 0% Installation of Fiber Patch Panel 2 days Jan 30 '10 Jan 31 '10 0 days NA NA 312,311

    314 0% Installation & Configuration of Switches 2 days Jan 30 '10 Jan 31 '10 0 days NA NA 308,312

    315 0% Installation of UTP & Fiber Patch cords 2 days Jan 14 '10 Jan 16 '10 0 days NA NA 124,310

    316 0% Installation of IP Telephones 2 days Jan 30 '10 Jan 31 '10 0 days NA NA 315,312

    317 0% Splicing Of Indoor/Outdoor Fiber Cables 2 days Feb 1 '10 Feb 2 '10 0 days NA NA 153,158,160,162,313

    318 0% Testing of Fiber Cables 1 day Feb 3 '10 Feb 3 '10 0 days NA NA 317

    319 0% Labeling Rack, Patch panels and Switches 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 314,308,310,313

    320 0% Interfacing With Overall Network 1 day Feb 4 '10 Feb 4 '10 0 days NA NA 318

    321 0% Area 20 Secondary Crushing Substation & Operations Bl 30 days Jan 18 '10 Feb 22 '10 0 days NA NA 193,305SS+7 days

    322 0% Communication Room Ready 0 days Jan 18 '10 Jan 18 '10 0 days NA NA

    323 0% Installation of Cable Ladders & Trays 1 day Jan 19 '10 Jan 19 '10 0 days NA NA 124

    324 0% Installation of Communication Racks 1 day Jan 19 '10 Jan 19 '10 0 days NA NA 323SS,124

    325 0% Installation Of Power Cabling & Grounding 1 day Jan 20 '10 Jan 20 '10 0 days NA NA 324,124

    326 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Jan 20 '10 Jan 20 '10 0 days NA NA 325SS,124

    327 0% Testing of UTP Cables 1 day Jan 21 '10 Jan 21 '10 0 days NA NA 326

    328 0% Delivery from Warehouse to Building Communication Ro 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 322,77

    329 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 328,327

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 7

  • 7/29/2019 Appendix 11-Updated Schedule

    8/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    330 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 324,328

    331 0% Installation of UTP & Fiber Patch cords 1 day Jan 21 '10 Jan 21 '10 0 days NA NA 326,124

    332 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 331,328

    333 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 175,329

    334 0% Testing of Fiber Cables 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 333

    335 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 330,324,326,329

    336 0% Interfacing With Overall Network 1 day Feb 22 '10 Feb 22 '10 0 days NA NA 334

    337 13% Area 30 Communition Substation 19 days Jan 20 '10 Feb 11 '10 7.6 days Jan 25 '10 NA 194,321SS+2 days

    338 0% Communication Room Ready 0 days Jan 20 '10 Jan 20 '10 0 days NA NA

    339 0% Installation of Cable Ladders & Trays 1 day Jan 21 '10 Jan 21 '10 0 days NA NA 124

    340 100% Installation of Communication Racks 1 day Jan 21 '10 Jan 21 '10 1 day Feb 27 '10 Feb 27 '10 339SS,124

    341 0% Installation Of Power Cabling & Grounding 1 day Jan 23 '10 Jan 23 '10 0 days NA NA 340,124

    342 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Jan 23 '10 Jan 23 '10 1 day Feb 27 '10 Feb 27 '10 341SS,124

    343 0% Testing of UTP Cables 1 day Jan 24 '10 Jan 24 '10 0 days NA NA 342

    344 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 338,78

    345 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 344,343

    346 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 340,344

    347 0% Installation of UTP & Fiber Patch cords 1 day Jan 24 '10 Jan 24 '10 0 days NA NA 342,124

    348 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 347,344

    349 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 9 '10 Feb 9 '10 0 days NA NA 173,345

    350 0% Testing of Fiber Cables 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 349

    351 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 346,340,342,345352 0% Interfacing With Overall Network 1 day Feb 11 '10 Feb 11 '10 0 days NA NA 350

    353 20% First Aid Clinic / Firehouse 6 days Jan 25 '10 Feb 1 '10 10.4 days Jan 30 '10 NA 195,337SS+4 days

    354 0% Communication Room Ready 0 days Jan 25 '10 Jan 25 '10 0 days NA NA

    355 0% Installation of Cable Ladders & Trays 1 day Jan 26 '10 Jan 26 '10 0 days NA NA 124

    356 100% Installation of Communication Racks 1 day Jan 26 '10 Jan 26 '10 1 day Feb 17 '10 Feb 17 '10 355SS,124

    357 0% Installation Of Power Cabling & Grounding 1 day Jan 27 '10 Jan 27 '10 0 days NA NA 356,124

    358 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Jan 27 '10 Jan 27 '10 1 day Feb 22 '10 Feb 22 '10 357SS,124

    359 100% Testing of UTP Cables 1 day Jan 28 '10 Jan 28 '10 1 day Feb 23 '10 Feb 23 '10 358

    360 0% Delivery from Warehouse to Building Communication Ro 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 354,79

    361 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 360,359

    362 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 356,360

    363 0% Installation of UTP & Fiber Patch cords 1 day Jan 28 '10 Jan 28 '10 0 days NA NA 358,124

    364 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 363,360

    365 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 158,159,361

    366 0% Testing of Fiber Cables 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 365

    367 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 362,356,358,361

    368 0% Interfacing With Overall Network 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 367

    369 7% Area 70 Load Out Substation 10 days Jan 27 '10 Feb 8 '10 3.4 days Feb 1 '10 NA 196,353SS+2 days

    370 0% Communication Room Ready 0 days Jan 27 '10 Jan 27 '10 0 days NA NA

    371 0% Installation of Cable Ladders & Trays 1 day Jan 28 '10 Jan 28 '10 0 days NA NA 124

    372 100% Installation of Communication Racks 1 day Jan 28 '10 Jan 28 '10 1 day Feb 28 '10 Feb 28 '10 371SS,124

    373 0% Installation Of Power Cabling & Grounding 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 372,124

    374 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 373SS,124

    375 0% Testing of UTP Cables 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 374

    376 0% Delivery from Warehouse to Building Communication Ro 2 days Jan 28 '10 Jan 30 '10 0 days NA NA 370,80

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 8

  • 7/29/2019 Appendix 11-Updated Schedule

    9/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    377 0% Installation of Fiber Patch Panel 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 376,375

    378 0% Installation & Configuration of Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 372,376

    379 0% Installation of UTP & Fiber Patch cords 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 374,124

    380 0% Installation of IP Telephones 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 379,376

    381 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 6 '10 Feb 6 '10 0 days NA NA 171,377

    382 0% Testing of Fiber Cables 1 day Feb 7 '10 Feb 7 '10 0 days NA NA 381

    383 0% Labeling Rack, Patch panels and Switches 1 day Feb 2 '10 Feb 2 '10 0 days NA NA 378,372,374,377

    384 0% Interfacing With Overall Network 1 day Feb 8 '10 Feb 8 '10 0 days NA NA 382

    385 0% Central Control Building 26 days Feb 1 '10 Mar 3 '10 0 days NA NA 197,369SS+4 days

    386 0% Communication Room Ready 0 days Feb 1 '10 Feb 1 '10 0 days NA NA

    387 0% Installation of Cable Ladders & Trays 3 days Feb 2 '10 Feb 4 '10 0 days NA NA 124

    388 0% Installation of Communication Racks 1 day Feb 2 '10 Feb 2 '10 0 days NA NA 387SS,124

    389 0% Installation Of Power Cabling & Grounding 2 days Feb 3 '10 Feb 4 '10 0 days NA NA 388,124

    390 0% Installation & Termination of UTP Patch Panel & Face Pl 3 days Feb 6 '10 Feb 8 '10 0 days NA NA 389,124

    391 0% Testing of UTP Cables 1 day Feb 9 '10 Feb 9 '10 0 days NA NA 390

    392 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 2 '10 Feb 3 '10 0 days NA NA 386,81

    393 0% Installation of Fiber Patch Panel 2 days Feb 10 '10 Feb 11 '10 0 days NA NA 392,391

    394 0% Installation & Configuration of Switches 3 days Feb 4 '10 Feb 7 '10 0 days NA NA 388,392

    395 0% Installation of UTP & Fiber Patch cords 2 days Feb 9 '10 Feb 10 '10 0 days NA NA 390,124

    396 0% Installation of IP Telephones 3 days Feb 11 '10 Feb 14 '10 0 days NA NA 395,392

    397 0% Splicing Of Indoor/Outdoor Fiber Cables 8 days Feb 20 '10 Feb 28 '10 0 days NA NA 150,161,162,166,167, , , , , , , ,

    398 0% Testing of Fiber Cables 2 days Mar 1 '10 Mar 2 '10 0 days NA NA 397399 0% Labeling Rack, Patch panels and Switches 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 394,388,390,393

    400 0% Interfacing With Overall Network 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 398

    401 20% Substation Utilities 6 days Feb 7 '10 Feb 14 '10 8.4 days Feb 11 '10 NA 198,385SS+5 days

    402 100% Communication Room Ready 0 days Feb 7 '10 Feb 7 '10 0 days Feb 11 '10 Feb 11 '10

    403 0% Installation of Cable Ladders & Trays 1 day Feb 8 '10 Feb 8 '10 0 days NA NA 124

    404 100% Installation of Communication Racks 1 day Feb 8 '10 Feb 8 '10 1 day Feb 18 '10 Feb 18 '10 403SS,124

    405 0% Installation Of Power Cabling & Grounding 1 day Feb 8 '10 Feb 8 '10 0 days NA NA 404SS,124

    406 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 9 '10 Feb 9 '10 1 day Feb 11 '10 Feb 11 '10 405,124

    407 100% Testing of UTP Cables 1 day Feb 10 '10 Feb 10 '10 1 day Feb 20 '10 Feb 20 '10 406

    408 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 8 '10 Feb 9 '10 0 days NA NA 402,82

    409 0% Installation of Fiber Patch Panel 1 day Feb 11 '10 Feb 11 '10 0 days NA NA 408,407

    410 0% Installation & Configuration of Switches 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 404,408

    411 0% Installation of UTP & Fiber Patch cords 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 406,124

    412 0% Installation of IP Telephones 1 day Feb 11 '10 Feb 11 '10 0 days NA NA 411,408

    413 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 163,164,409

    414 0% Testing of Fiber Cables 1 day Feb 14 '10 Feb 14 '10 0 days NA NA 413

    415 0% Labeling Rack, Patch panels and Switches 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 410,404,406,409

    416 0% Interfacing With Overall Network 1 day Feb 14 '10 Feb 14 '10 0 days NA NA 415

    417 20% Feul Truck Comfort Station 6 days Feb 9 '10 Feb 16 '10 8.2 days Feb 13 '10 NA 199,401SS+2 days

    418 100% Communication Room Ready 0 days Feb 9 '10 Feb 9 '10 0 days Feb 13 '10 Feb 13 '10

    419 0% Installation of Cable Ladders & Trays 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 124

    420 100% Installation of Communication Racks 1 day Feb 10 '10 Feb 10 '10 1 day Feb 28 '10 Feb 28 '10 419SS,124

    421 0% Installation Of Power Cabling & Grounding 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 420SS,124

    422 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 10 '10 Feb 10 '10 1 day Feb 28 '10 Feb 28 '10 421SS,124

    423 100% Testing of UTP Cables 1 day Feb 11 '10 Feb 11 '10 1 day Feb 28 '10 Feb 28 '10 422

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 9

  • 7/29/2019 Appendix 11-Updated Schedule

    10/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    424 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 10 '10 Feb 11 '10 0 days NA NA 418,83

    425 0% Installation of Fiber Patch Panel 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 424,423

    426 0% Installation & Configuration of Switches 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 420,424

    427 0% Installation of UTP & Fiber Patch cords 1 day Feb 11 '10 Feb 11 '10 0 days NA NA 422,124

    428 0% Installation of IP Telephones 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 427,424

    429 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 14 '10 Feb 14 '10 0 days NA NA 169,425

    430 0% Testing of Fiber Cables 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 429

    431 0% Labeling Rack, Patch panels and Switches 1 day Feb 14 '10 Feb 14 '10 0 days NA NA 426,420,422,425

    432 0% Interfacing With Overall Network 1 day Feb 16 '10 Feb 16 '10 0 days NA NA 430

    433 0% Area 10 Primary Crushing Substation & Operations Bldg. 7 days Feb 14 '10 Feb 22 '10 0 days NA NA 200,417SS+4 days

    434 0% Communication Room Ready 0 days Feb 14 '10 Feb 14 '10 0 days NA NA

    435 0% Installation of Cable Ladders & Trays 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 124

    436 0% Installation of Communication Racks 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 435SS,124

    437 0% Installation Of Power Cabling & Grounding 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 436SS,124

    438 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 16 '10 Feb 16 '10 0 days NA NA 437,124

    439 0% Testing of UTP Cables 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 438

    440 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 15 '10 Feb 16 '10 0 days NA NA 434,84

    441 0% Installation of Fiber Patch Panel 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 440,439

    442 0% Installation & Configuration of Switches 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 436,440

    443 0% Installation of UTP & Fiber Patch cords 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 438,124

    444 0% Installation of IP Telephones 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 443,440

    445 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 174,441446 0% Testing of Fiber Cables 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 445

    447 0% Labeling Rack, Patch panels and Switches 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 442,443,444

    448 0% Interfacing With Overall Network 1 day Feb 22 '10 Feb 22 '10 0 days NA NA 446

    449 0% Mosque 5 days Feb 16 '10 Feb 22 '10 0 days NA NA 201,433SS+2 days

    450 0% Communication Room Ready 0 days Feb 16 '10 Feb 16 '10 0 days NA NA

    451 0% Installation of Cable Ladders & Trays 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 124

    452 0% Installation of Communication Racks 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 451SS,124

    453 0% Installation Of Power Cabling & Grounding 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 452SS,124

    454 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 453,124

    455 0% Testing of UTP Cables 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 454SS

    456 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 17 '10 Feb 18 '10 0 days NA NA 450,85

    457 0% Installation of Fiber Patch Panel 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 456,455

    458 0% Installation & Configuration of Switches 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 452,456

    459 0% Installation of UTP & Fiber Patch cords 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 454,124

    460 0% Installation of IP Telephones 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 459,456

    461 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 151,457462 0% Testing of Fiber Cables 1 day Feb 22 '10 Feb 22 '10 0 days NA NA 461

    463 0% Labeling Rack, Patch panels and Switches 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 458,452,454,457

    464 0% Interfacing With Overall Network 1 day Feb 22 '10 Feb 22 '10 0 days NA NA 463

    465 20% Change House & Dining Hall Bldg. 6 days Feb 20 '10 Feb 27 '10 6.6 days Feb 23 '10 NA 202,449SS+3 days

    466 100% Communication Room Ready 0 days Feb 20 '10 Feb 20 '10 0 days Feb 23 '10 Feb 23 '10

    467 0% Installation of Cable Ladders & Trays 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 124

    468 100% Installation of Communication Racks 1 day Feb 21 '10 Feb 21 '10 1 day Feb 24 '10 Feb 24 '10 467SS,124

    469 0% Installation Of Power Cabling & Grounding 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 468SS,124

    470 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 22 '10 Feb 22 '10 1 day Feb 24 '10 Feb 24 '10 469,124

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 10

  • 7/29/2019 Appendix 11-Updated Schedule

    11/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    471 100% Testing of UTP Cables 1 day Feb 23 '10 Feb 23 '10 1 day Feb 25 '10 Feb 25 '10 470

    472 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 21 '10 Feb 22 '10 0 days NA NA 466,86

    473 0% Installation of Fiber Patch Panel 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 472,471

    474 0% Installation & Configuration of Switches 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 468,472

    475 0% Installation of UTP & Fiber Patch cords 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 470,124

    476 0% Installation of IP Telephones 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 475,472

    477 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 157,473

    478 0% Testing of Fiber Cables 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 477

    479 0% Labeling Rack, Patch panels and Switches 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 474,468,239,244

    480 0% Interfacing With Overall Network 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 479

    481 0% Guardhouse 1A ( Main Gate) 5 days Feb 22 '10 Feb 28 '10 0 days NA NA 203,465SS+2 days

    482 0% Communication Room Ready 0 days Feb 22 '10 Feb 22 '10 0 days NA NA

    483 0% Installation of Cable Ladders & Trays 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 124

    484 0% Installation of Communication Racks 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 483SS,124

    485 0% Installation Of Power Cabling & Grounding 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 484SS,124

    486 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 485SS,124

    487 0% Testing of UTP Cables 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 486

    488 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 23 '10 Feb 24 '10 0 days NA NA 482,87

    489 0% Installation of Fiber Patch Panel 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 488,487

    490 0% Installation & Configuration of Switches 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 484,488

    491 0% Installation of UTP & Fiber Patch cords 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 486,124

    492 0% Installation of IP Telephones 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 491,488493 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 159,489

    494 0% Testing of Fiber Cables 1 day Feb 28 '10 Feb 28 '10 0 days NA NA 493

    495 0% Labeling Rack, Patch panels and Switches 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 490,484,486,489

    496 0% Interfacing With Overall Network 1 day Feb 28 '10 Feb 28 '10 0 days NA NA 495

    497 0% Guardhouse 1B (High Security) 5 days Feb 25 '10 Mar 3 '10 0 days NA NA 204,481SS+3 days

    498 0% Communication Room Ready 0 days Feb 25 '10 Feb 25 '10 0 days NA NA

    499 0% Installation of Cable Ladders & Trays 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 124

    500 0% Installation of Communication Racks 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 499SS,124

    501 0% Installation Of Power Cabling & Grounding 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 500SS,124

    502 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 501SS,124

    503 0% Testing of UTP Cables 1 day Feb 28 '10 Feb 28 '10 0 days NA NA 502

    504 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 27 '10 Feb 28 '10 0 days NA NA 498,88

    505 0% Installation of Fiber Patch Panel 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 504,503

    506 0% Installation & Configuration of Switches 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 500,504

    507 0% Installation of UTP & Fiber Patch cords 1 day Feb 28 '10 Feb 28 '10 0 days NA NA 502,124

    508 0% Installation of IP Telephones 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 507,504509 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 2 '10 Mar 2 '10 0 days NA NA 160,505

    510 0% Testing of Fiber Cables 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 509

    511 0% Labeling Rack, Patch panels and Switches 1 day Mar 2 '10 Mar 2 '10 0 days NA NA 506,500,502,505

    512 0% Interfacing With Overall Network 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 511

    513 0% Guardhouse Truck Area ( Guardhouse 3) 6 days Feb 28 '10 Mar 7 '10 0 days NA NA 205,497SS+2 days

    514 0% Communication Room Ready 0 days Feb 28 '10 Feb 28 '10 0 days NA NA

    515 0% Installation of Cable Ladders & Trays 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 124

    516 0% Installation of Communication Racks 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 515SS,124

    517 0% Installation Of Power Cabling & Grounding 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 516SS,124

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 11

  • 7/29/2019 Appendix 11-Updated Schedule

    12/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    518 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 517SS,124

    519 0% Testing of UTP Cables 1 day Mar 2 '10 Mar 2 '10 0 days NA NA 518

    520 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 1 '10 Mar 2 '10 0 days NA NA 514,89

    521 0% Installation of Fiber Patch Panel 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 520,519

    522 0% Installation & Configuration of Switches 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 516,520

    523 0% Installation of UTP & Fiber Patch cords 1 day Mar 2 '10 Mar 2 '10 0 days NA NA 518,124

    524 0% Installation of IP Telephones 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 523,520

    525 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 4 '10 Mar 4 '10 0 days NA NA 168,521

    526 0% Testing of Fiber Cables 1 day Mar 6 '10 Mar 6 '10 0 days NA NA 525

    527 0% Labeling Rack, Patch panels and Switches 1 day Mar 4 '10 Mar 4 '10 0 days NA NA 522,516,518,521

    528 0% Interfacing With Overall Network 1 day Mar 7 '10 Mar 7 '10 0 days NA NA 526

    529 7% Area 60 Dryer Substation 6 days Mar 4 '10 Mar 11 '10 1.87 days Feb 28 '10 NA 206,513SS+4 days

    530 0% Communication Room Ready 0 days Mar 4 '10 Mar 4 '10 0 days NA NA

    531 0% Installation of Cable Ladders & Trays 1 day Mar 6 '10 Mar 6 '10 0 days NA NA 124

    532 100% Installation of Communication Racks 1 day Mar 6 '10 Mar 6 '10 1 day Feb 28 '10 Feb 28 '10 531SS,124

    533 0% Installation Of Power Cabling & Grounding 1 day Mar 6 '10 Mar 6 '10 0 days NA NA 532SS,124

    534 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 7 '10 Mar 7 '10 0 days NA NA 533,124

    535 0% Testing of UTP Cables 1 day Mar 8 '10 Mar 8 '10 0 days NA NA 534

    536 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 6 '10 Mar 7 '10 0 days NA NA 530,90

    537 0% Installation of Fiber Patch Panel 1 day Mar 9 '10 Mar 9 '10 0 days NA NA 536,535

    538 0% Installation & Configuration of Switches 1 day Mar 8 '10 Mar 8 '10 0 days NA NA 532,536

    539 0% Installation of UTP & Fiber Patch cords 1 day Mar 8 '10 Mar 8 '10 0 days NA NA 534,124540 0% Installation of IP Telephones 1 day Mar 9 '10 Mar 9 '10 0 days NA NA 539,536

    541 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 166,537

    542 0% Testing of Fiber Cables 1 day Mar 11 '10 Mar 11 '10 0 days NA NA 541

    543 0% Labeling Rack, Patch panels and Switches 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 538,532,534,537

    544 0% Interfacing With Overall Network 1 day Mar 11 '10 Mar 11 '10 0 days NA NA 543

    545 0% Maintenance / Warehouse 19 days Mar 7 '10 Mar 29 '10 0 days NA NA 207,529SS+2 days

    546 0% Communication Room Ready 0 days Mar 7 '10 Mar 7 '10 0 days NA NA

    547 0% Installation of Cable Ladders & Trays 3 days Mar 8 '10 Mar 10 '10 0 days NA NA 124

    548 0% Installation of Communication Racks 1 day Mar 8 '10 Mar 8 '10 0 days NA NA 547SS,124

    549 0% Installation Of Power Cabling & Grounding 3 days Mar 9 '10 Mar 11 '10 0 days NA NA 548,124

    550 0% Installation & Termination of UTP Patch Panel & Face Pl 3 days Mar 13 '10 Mar 15 '10 0 days NA NA 549,124

    551 0% Testing of UTP Cables 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 550

    552 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 8 '10 Mar 9 '10 0 days NA NA 546,91

    553 0% Installation of Fiber Patch Panel 4 days Mar 17 '10 Mar 21 '10 0 days NA NA 552,551

    554 0% Installation & Configuration of Switches 6 days Mar 10 '10 Mar 16 '10 0 days NA NA 548,552

    555 0% Installation of UTP & Fiber Patch cords 3 days Mar 16 '10 Mar 18 '10 0 days NA NA 550,124556 0% Installation of IP Telephones 6 days Mar 20 '10 Mar 25 '10 0 days NA NA 555,552

    557 0% Splicing Of Indoor/Outdoor Fiber Cables 4 days Mar 22 '10 Mar 25 '10 0 days NA NA 164,553

    558 0% Testing of Fiber Cables 2 days Mar 27 '10 Mar 28 '10 0 days NA NA 557

    559 0% Labeling Rack, Patch panels and Switches 2 days Mar 22 '10 Mar 23 '10 0 days NA NA 554,548,550,553

    560 0% Interfacing With Overall Network 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 558

    561 0% Area 40 Flotation Substation 7 days Mar 9 '10 Mar 17 '10 0 days NA NA 208,545SS+2 days

    562 0% Communication Room Ready 0 days Mar 9 '10 Mar 9 '10 0 days NA NA

    563 0% Installation of Cable Ladders & Trays 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 124

    564 0% Installation of Communication Racks 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 563SS,124

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 12

  • 7/29/2019 Appendix 11-Updated Schedule

    13/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    565 0% Installation Of Power Cabling & Grounding 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 564SS,124

    566 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 11 '10 Mar 11 '10 0 days NA NA 565,124

    567 0% Testing of UTP Cables 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 566

    568 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 10 '10 Mar 11 '10 0 days NA NA 562,92

    569 0% Installation of Fiber Patch Panel 1 day Mar 14 '10 Mar 14 '10 0 days NA NA 568,567

    570 0% Installation & Configuration of Switches 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 564,568

    571 0% Installation of UTP & Fiber Patch cords 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 566,124

    572 0% Installation of IP Telephones 1 day Mar 14 '10 Mar 14 '10 0 days NA NA 571,568

    573 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 172,569

    574 0% Testing of Fiber Cables 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 573

    575 0% Labeling Rack, Patch panels and Switches 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 570,564,566,569

    576 0% Interfacing With Overall Network 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 574

    577 0% Power Plant & Main Substation 6 days Mar 11 '10 Mar 18 '10 0 days NA NA 209,561SS+2 days

    578 0% Communication Room Ready 0 days Mar 11 '10 Mar 11 '10 0 days NA NA

    579 0% Installation of Cable Ladders & Trays 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 124

    580 0% Installation of Communication Racks 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 579SS,124

    581 0% Installation Of Power Cabling & Grounding 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 580SS,124

    582 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 14 '10 Mar 14 '10 0 days NA NA 581,124

    583 0% Testing of UTP Cables 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 582

    584 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 13 '10 Mar 14 '10 0 days NA NA 578,93

    585 0% Installation of Fiber Patch Panel 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 584,583

    586 0% Installation & Configuration of Switches 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 580,583587 0% Installation of UTP & Fiber Patch cords 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 582,124

    588 0% Installation of IP Telephones 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 587,583

    589 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 170,585

    590 0% Testing of Fiber Cables 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 589

    591 0% Labeling Rack, Patch panels and Switches 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 586,580,582,585

    592 0% Interfacing With Overall Network 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 591

    593 0% Al Jalamid Village 13 days Mar 14 '10 Mar 29 '10 0 days NA NA 146

    594 0% Labor Residence 6 days Mar 14 '10 Mar 21 '10 0 days NA NA 211,577SS+2 days

    595 0% Communication Room Ready 0 days Mar 14 '10 Mar 14 '10 0 days NA NA

    596 0% Installation of Cable Ladders & Trays 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 124

    597 0% Installation of Communication Racks 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 596SS,124

    598 0% Installation Of Power Cabling & Grounding 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 597SS,124

    599 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 598,124

    600 0% Testing of UTP Cables 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 599

    601 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 15 '10 Mar 16 '10 0 days NA NA 595,95

    602 0% Installation of Fiber Patch Panel 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 601,600603 0% Installation & Configuration of Switches 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 597,601

    604 0% Installation of UTP & Fiber Patch cords 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 599,124

    605 0% Installation of IP Telephones 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 604,601

    606 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 602

    607 0% Testing of Fiber Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 606

    608 0% Labeling Rack, Patch panels and Switches 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 603,597,599,602

    609 0% Interfacing With Overall Network 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 608

    610 0% Management Residence Type 1 (2ea) 5 days Mar 14 '10 Mar 20 '10 0 days NA NA 212,594SS

    611 0% Communication Room Ready 0 days Mar 14 '10 Mar 14 '10 0 days NA NA

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 13

  • 7/29/2019 Appendix 11-Updated Schedule

    14/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    612 0% Installation of Cable Ladders & Trays 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 124

    613 0% Installation of Communication Racks 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 612SS,124

    614 0% Installation Of Power Cabling & Grounding 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 613SS,124

    615 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 614SS,124

    616 0% Testing of UTP Cables 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 615

    617 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 15 '10 Mar 16 '10 0 days NA NA 611,96

    618 0% Installation of Fiber Patch Panel 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 617,616

    619 0% Installation & Configuration of Switches 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 613,617

    620 0% Installation of UTP & Fiber Patch cords 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 615,124

    621 0% Installation of IP Telephones 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 620,617

    622 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 618

    623 0% Testing of Fiber Cables 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 622

    624 0% Labeling Rack, Patch panels and Switches 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 619,613,615,618

    625 0% Interfacing With Overall Network 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 624

    626 0% Supervisor's Residence (4ea) 5 days Mar 16 '10 Mar 22 '10 0 days NA NA 213,610SS+2 days

    627 0% Communication Room Ready 0 days Mar 16 '10 Mar 16 '10 0 days NA NA

    628 0% Installation of Cable Ladders & Trays 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 124

    629 0% Installation of Communication Racks 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 628SS,124

    630 0% Installation Of Power Cabling & Grounding 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 629SS,124

    631 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 630SS,124

    632 0% Testing of UTP Cables 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 631

    633 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 17 '10 Mar 18 '10 0 days NA NA 627,97634 0% Installation of Fiber Patch Panel 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 633,632

    635 0% Installation & Configuration of Switches 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 629,633

    636 0% Installation of UTP & Fiber Patch cords 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 631,124

    637 0% Installation of IP Telephones 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 636,633

    638 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 634

    639 0% Testing of Fiber Cables 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 638

    640 0% Labeling Rack, Patch panels and Switches 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 635,629,631,634

    641 0% Interfacing With Overall Network 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 640

    642 0% Management Residence Type 2 5 days Mar 16 '10 Mar 22 '10 0 days NA NA 214,626SS

    643 0% Communication Room Ready 0 days Mar 16 '10 Mar 16 '10 0 days NA NA

    644 0% Installation of Cable Ladders & Trays 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 124

    645 0% Installation of Communication Racks 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 644SS,124

    646 0% Installation Of Power Cabling & Grounding 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 645SS,124

    647 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 646SS,124

    648 0% Testing of UTP Cables 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 647

    649 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 17 '10 Mar 18 '10 0 days NA NA 643,98650 0% Installation of Fiber Patch Panel 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 649,648

    651 0% Installation & Configuration of Switches 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 645,649

    652 0% Installation of UTP & Fiber Patch cords 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 647,124

    653 0% Installation of IP Telephones 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 652,649

    654 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 650

    655 0% Testing of Fiber Cables 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 654

    656 0% Labeling Rack, Patch panels and Switches 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 651,645,647,650

    657 0% Interfacing With Overall Network 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 656

    658 0% Laundry / Warehouse 5 days Mar 18 '10 Mar 24 '10 0 days NA NA 215,642SS+2 days

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 14

  • 7/29/2019 Appendix 11-Updated Schedule

    15/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    659 0% Communication Room Ready 0 days Mar 18 '10 Mar 18 '10 0 days NA NA

    660 0% Installation of Cable Ladders & Trays 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 124

    661 0% Installation of Communication Racks 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 660SS,124

    662 0% Installation Of Power Cabling & Grounding 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 661SS,124

    663 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 662SS,124

    664 0% Testing of UTP Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 663

    665 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 20 '10 Mar 21 '10 0 days NA NA 659,99

    666 0% Installation of Fiber Patch Panel 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 665,664

    667 0% Installation & Configuration of Switches 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 661,665

    668 0% Installation of UTP & Fiber Patch cords 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 663,124

    669 0% Installation of IP Telephones 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 668,665

    670 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 666

    671 0% Testing of Fiber Cables 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 670

    672 0% Labeling Rack, Patch panels and Switches 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 667,661,663,666

    673 0% Interfacing With Overall Network 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 672

    674 0% Workshop 5 days Mar 18 '10 Mar 24 '10 0 days NA NA 216,658SS

    675 0% Communication Room Ready 0 days Mar 18 '10 Mar 18 '10 0 days NA NA

    676 0% Installation of Cable Ladders & Trays 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 124

    677 0% Installation of Communication Racks 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 676SS,124

    678 0% Installation Of Power Cabling & Grounding 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 677SS,124

    679 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 678SS,124

    680 0% Testing of UTP Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 679681 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 20 '10 Mar 21 '10 0 days NA NA 675,100

    682 0% Installation of Fiber Patch Panel 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 681,680

    683 0% Installation & Configuration of Switches 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 677,681

    684 0% Installation of UTP & Fiber Patch cords 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 679,124

    685 0% Installation of IP Telephones 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 684,681

    686 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 682

    687 0% Testing of Fiber Cables 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 686

    688 0% Labeling Rack, Patch panels and Switches 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 683,677,679,682

    689 0% Interfacing With Overall Network 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 688

    690 0% Central Common Area 5 days Mar 21 '10 Mar 27 '10 0 days NA NA 217,674SS+2 days

    691 0% Communication Room Ready 0 days Mar 21 '10 Mar 21 '10 0 days NA NA

    692 0% Installation of Cable Ladders & Trays 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 124

    693 0% Installation of Communication Racks 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 692SS,124

    694 0% Installation Of Power Cabling & Grounding 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 693SS,124

    695 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 694SS,124

    696 0% Testing of UTP Cables 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 695697 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 22 '10 Mar 23 '10 0 days NA NA 691,101

    698 0% Installation of Fiber Patch Panel 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 697,696

    699 0% Installation & Configuration of Switches 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 693,697

    700 0% Installation of UTP & Fiber Patch cords 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 695,124

    701 0% Installation of IP Telephones 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 700,697

    702 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 698

    703 0% Testing of Fiber Cables 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 702

    704 0% Labeling Rack, Patch panels and Switches 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 699,693,695,698

    705 0% Interfacing With Overall Network 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 704

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 15

  • 7/29/2019 Appendix 11-Updated Schedule

    16/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    706 0% Dining Hall and Kitchen 5 days Mar 23 '10 Mar 29 '10 0 days NA NA 218,690SS+2 days

    707 0% Communication Room Ready 0 days Mar 23 '10 Mar 23 '10 0 days NA NA

    708 0% Installation of Cable Ladders & Trays 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 124

    709 0% Installation of Communication Racks 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 708SS,124

    710 0% Installation Of Power Cabling & Grounding 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 709SS,124

    711 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 710SS,124

    712 0% Testing of UTP Cables 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 711

    713 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 24 '10 Mar 25 '10 0 days NA NA 707,102

    714 0% Installation of Fiber Patch Panel 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 713,712

    715 0% Installation & Configuration of Switches 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 709,713

    716 0% Installation of UTP & Fiber Patch cords 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 711,124

    717 0% Installation of IP Telephones 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 716,713

    718 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 714

    719 0% Testing of Fiber Cables 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 718

    720 0% Labeling Rack, Patch panels and Switches 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 715,709,711,714

    721 0% Interfacing With Overall Network 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 720

    722 0% Club House 5 days Mar 23 '10 Mar 29 '10 0 days NA NA 219,706SS

    723 0% Communication Room Ready 0 days Mar 23 '10 Mar 23 '10 0 days NA NA

    724 0% Installation of Cable Ladders & Trays 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 124

    725 0% Installation of Communication Racks 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 724SS,124

    726 0% Installation Of Power Cabling & Grounding 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 725SS,124

    727 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 726SS,124728 0% Testing of UTP Cables 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 727

    729 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 24 '10 Mar 25 '10 0 days NA NA 723,103

    730 0% Installation of Fiber Patch Panel 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 729,728

    731 0% Installation & Configuration of Switches 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 725,729

    732 0% Installation of UTP & Fiber Patch cords 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 727,124

    733 0% Installation of IP Telephones 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 732,729

    734 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 730

    735 0% Testing of Fiber Cables 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 734

    736 0% Labeling Rack, Patch panels and Switches 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 731,732,733

    737 0% Interfacing With Overall Network 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 736

    738 0% Mosque 5 days Mar 23 '10 Mar 29 '10 0 days NA NA 220,722SS

    739 0% Communication Room Ready 0 days Mar 23 '10 Mar 23 '10 0 days NA NA

    740 0% Installation of Cable Ladders & Trays 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 124

    741 0% Installation of Communication Racks 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 740SS,124

    742 0% Installation Of Power Cabling & Grounding 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 741SS,124

    743 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 742SS,124744 0% Testing of UTP Cables 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 743

    745 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 24 '10 Mar 25 '10 0 days NA NA 739,104

    746 0% Installation of Fiber Patch Panel 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 745,744

    747 0% Installation & Configuration of Switches 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 741,745

    748 0% Installation of UTP & Fiber Patch cords 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 743,124

    749 0% Installation of IP Telephones 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 748,745

    750 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 746

    751 0% Testing of Fiber Cables 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 750

    752 0% Labeling Rack, Patch panels and Switches 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 747,741,743,746

    MA'ADEN PERMANENT COMMUNICATIONS PROJECT

    AL-JALAMID

    SBM Page 16

  • 7/29/2019 Appendix 11-Updated Schedule

    17/21

    ID %Com lete

    Task Name BaselineDuration

    BaselineStart

    BaselineFinish

    ActualDuration

    Actual Start Actual Finish Predecessors

    753 0% Interfacing With Overall Network 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 752

    754 6% Wireless Communication 30 days Jan 28 '10 Mar 3 '10 2.4 days Jan 30 '10 NA 146

    755 0% Installation of Equipment, Basestation 7 days Jan 28 '10 Feb 4 '10 0 days NA NA 110

    756 0% Fixed and Vehicle Radio 8 days Feb 6 '10 Feb 14 '10 0 days NA NA 755

    757 13% System Programming 15 days Feb 6 '10 Feb 22 '10 4.25 days Jan 30 '10 NA

    758 0% System Programming 7 days Feb 6 '10 Feb 13 '10 0 days NA NA 756SS

    759 100% Radio Programming 8 days Feb 14 '10 Feb 22 '10 1 day Jan 30 '10 Jan 30 '10 758

    760 7% Communication Tower 30 days Jan 28 '10 Mar 3 '10 2.07 days Feb 13 '10 NA 110

    761 100% Soil Testing, Foundation Work 10 days Jan 28 '10 Feb 8 '10 2 days Feb 13 '10 Feb 14 '10

    762 0% Concrete Foundation Curing 12 days Feb 9 '10 Feb 22 '10 0 days NA NA 761

    763 0% Installation of Tower 8 days Feb 23 '10 Mar 3 '10 0 days NA NA 762

    764 0% Communication Cable Installation 5 days Feb 23 '10 Feb 28 '10 0 days NA NA 763SS

    765 11% GSM Enhancement 66 days Nov 3 '09 Jan 24 '10 12.68 days Oct 24 '09 NA 114SS

    766 100% Overall Site Survey 3 days Nov 3 '09 Nov 5 '09 44 days Oct 24 '09 Dec 19 '09

    767 100% Initial Overall Site Survey 2 days Nov 3 '09 Nov 4 '09 2 days Oct 24 '09 Oct 25 '09 35FS+14 days

    768 100% Signal Measurement 2 days Nov 3 '09 Nov 4 '09 2 days Oct 24 '09 Oct 25 '09 767SS

    769 100% Survey Report 1 day Nov 5 '09 Nov 5 '09 1 day Dec 19 '09 Dec 19 '09 768

    770 6% Industrial Buildings 36 days Dec 14 '09 Jan 24 '10 2.19 days Jan 30 '10 NA 146

    771 10% Administration Building 36 days Dec 14 '09 Jan 24 '10 3.4 days Jan 30 '10 NA 190,114SS

    772 100% Final Site Survey 1 day Dec 14 '09 Dec 14 '09 1 day Jan 30 '10 Jan 30 '10

    773 0% Site Ready (Scaffoldings, Ladders, Structure) 2 days Dec 20 '09 Dec 21 '09 0 days NA NA 120

    774 0% Passive DAS Installation 3 days Dec 22 '09 Dec 24 '09 0 days NA NA775 0% Cables 2 days Dec 22 '09 Dec 23 '09 0 days NA NA 122,773

    776 0% Components (antennas, splitters, couplers) 2 days Dec 22 '09 Dec 23 '09 0 days NA NA 122,773

    777 0% Cable Testing 1 day Dec 24 '09 Dec 24 '09 0 days NA NA 775

    778 0% Active Installa