7/29/2019 Appendix 11-Updated Schedule
1/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
1 44% AL JALAMID COMMUNICATIONS SCHEDULE 246 days Jul 5 '09 Apr 29 '10 114.96 days Jul 5 '09 NA
2 100% General 82 days Jul 5 '09 Oct 14 '09 82 days Jul 5 '09 Oct 14 '09
3 100% NOA Signed 1 day Jul 5 '09 Jul 5 '09 0 days Jul 5 '09 Jul 5 '09
4 100% Kick Off Meeting 0 days Jul 21 '09 Jul 21 '09 0 days Jul 21 '09 Jul 21 '09 3
5 100% Pre-Mobilization Deliverables 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09
6 100% HSE Management Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 47 100% 90 Day Look ahead Schedule 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 6SS
8 100% Temporary Facilities Layout Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 7SS
9 100% Construction Licenses And Permits 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 8SS
10 100% Site Mobilization Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 9SS
11 100% Safety Induction And Issuance Of Project Badges 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 10SS
12 100% Equipment Inspection Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 11SS
13 100% Insurance Policies 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 12SS
14 100% Detailed Sub-Contract Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 13SS
15 100% Quality Plan 8 days Jul 21 '09 Jul 29 '09 6 days Jul 21 '09 Jul 27 '09 14SS
16 100% Completion Of Pre-Mobilization And Commenced Mobilization 0 days Jul 29 '09 Jul 29 '09 0 days Jul 27 '09 Jul 27 '09 5
17 100% ID Preparation 82 days Jul 5 '09 Oct 14 '09 82 days Jul 5 '09 Oct 14 '09
18
19 97% Engineering Design For Al Jalamid 102 days Aug 1 '09 Dec 9 '09 167 days Aug 2 '09 NA
20 100% Initial Site Visit 2 days Aug 10 '09 Aug 11 '09 2 days Aug 10 '09 Aug 11 '09
21 100% 30% Design 55 days Aug 1 '09 Oct 10 '09 72 days Aug 2 '09 Oct 31 '09
22 100% Design Sessions 6 days Aug 1 '09 Aug 6 '09 6 days Aug 2 '09 Aug 8 '0923 100% Voice & Data Communication Network , OSP, ISP, Trenching 2 days Aug 1 '09 Aug 2 '09 1 day Aug 2 '09 Aug 2 '09 4FS+9 days
24 100% TETRA Wireless 2 days Aug 1 '09 Aug 2 '09 1 day Aug 3 '09 Aug 3 '09 23SS
25 100% GSM Enhancement 2 days Aug 3 '09 Aug 4 '09 1 day Aug 5 '09 Aug 5 '09 24SS+2 days
26 100% Video Conferencing System 2 days Aug 3 '09 Aug 4 '09 1 day Aug 5 '09 Aug 5 '09 25SS
27 100% VSAT System 2 days Aug 5 '09 Aug 6 '09 1 day Aug 8 '09 Aug 8 '09 26SS+2 days
28 100% Drawings Submittals 30 days Aug 12 '09 Sep 15 '09 1 day Aug 4 '09 Aug 4 '09 23,24,25,26,27,20
29 100% Materials Submittals 30 days Aug 12 '09 Sep 15 '09 22 days Aug 26 '09 Sep 27 '09 28SS
30 100% 30% Design Submission 1 day Sep 16 '09 Sep 16 '09 22 days Aug 26 '09 Sep 27 '09 28,29
31 100% 30% Design Review 5 days Sep 17 '09 Sep 29 '09 1 day Sep 27 '09 Sep 27 '09 30
32 100% 30% Design Meeting 1 day Sep 30 '09 Sep 30 '09 9 days Sep 28 '09 Oct 7 '09 31
33 100% Incorporate 30% Design Changes 7 days Oct 1 '09 Oct 8 '09 1 day Oct 3 '09 Oct 3 '09 32
34 100% 30% Design Approval 1 day Oct 10 '09 Oct 10 '09 6 days Oct 4 '09 Oct 10 '09 33
35 100% 30% Design Complete 0 days Oct 10 '09 Oct 10 '09 1 day Oct 31 '09 Oct 31 '09 34
36 100% 60% Design 17 days Oct 10 '09 Oct 28 '09 37 days Oct 11 '09 Nov 22 '09
37 100% Incorporation Of 30 % Design Comments 12 days Oct 10 '09 Oct 22 '09 22 days Oct 11 '09 Nov 4 '09 33
38 100% 60% Design Submittal 1 day Oct 24 '09 Oct 24 '09 1 day Nov 4 '09 Nov 4 '09 37
39 100% 60% Design Review 3 days Oct 25 '09 Oct 27 '09 1 day Nov 9 '09 Nov 9 '09 38
40 100% 60% Design Approval 1 day Oct 28 '09 Oct 28 '09 1 day Nov 22 '09 Nov 22 '09 39
41 100% 60% Design Complete 0 days Oct 28 '09 Oct 28 '09 0 days Nov 22 '09 Nov 22 '09 40
42 100% 90% Design 14 days Oct 28 '09 Nov 12 '09 37 days Nov 22 '09 Jan 9 '10
43 100% Incorporation Of 60% Design Comments 7 days Oct 28 '09 Nov 4 '09 24 days Nov 22 '09 Dec 24 '09 39
44 100% 90% Design Submittal 1 day Nov 5 '09 Nov 5 '09 1 day Dec 24 '09 Dec 24 '09 43
45 100% 90% Design Review 5 days Nov 7 '09 Nov 11 '09 5 days Jan 3 '10 Jan 7 '10 44
46 100% 90% Design Approval 1 day Nov 12 '09 Nov 12 '09 1 day Jan 9 '10 Jan 9 '10 45
47 100% 90% Design Complete 0 days Nov 12 '09 Nov 12 '09 0 days Jan 9 '10 Jan 9 '10 46
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 1
7/29/2019 Appendix 11-Updated Schedule
2/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
48 89% 100% Design 19 days Nov 12 '09 Dec 9 '09 41 days Jan 9 '10 NA
49 100% Incorporation Of 90% Design Comments 10 days Nov 12 '09 Nov 23 '09 37 days Jan 9 '10 Feb 20 '10 45
50 100% 100% Design Submittals 1 day Nov 24 '09 Nov 24 '09 1 day Feb 20 '10 Feb 21 '10 49
51 43% 100% Design Review 7 days Nov 25 '09 Dec 8 '09 3 days Feb 22 '10 NA 50
52 0% 100% Design Approval 1 day Dec 9 '09 Dec 9 '09 0 days NA NA 51
53 0% 100% Design Complete 0 days Dec 9 '09 Dec 9 '09 0 days NA NA 5254
55 73% Procurement 78 days Oct 24 '09 Jan 28 '10 89.24 days Oct 31 '09 NA
56 100% Commence Placement Of Purchase Order 0 days Oct 24 '09 Oct 24 '09 0 days Oct 31 '09 Oct 31 '09 3 5FS+12 days
57 58% Data and Voice Communication Equipment 76 days Oct 25 '09 Jan 26 '10 43.76 days Dec 29 '09 NA 56
58 100% Placing of P.O. 1 day Oct 25 '09 Oct 25 '09 1 day Jan 26 '10 Jan 26 '10
59 90% Delivery to SBM Warehouse 54 days Oct 26 '09 Jan 2 '10 48.6 days Dec 29 '09 NA 58
60 0% Staging & Configuration 21 days Jan 3 '10 Jan 26 '10 0 days NA NA 59
61 0% Switches, Routers and Firewalls IOS Upgrade 5 days Jan 3 '10 Jan 7 '10 0 days NA NA
62 0% Backbone Switches Configuration 3 days Jan 9 '10 Jan 11 '10 0 days NA NA 61
63 0% Edge Switches Configuration 4 days Jan 9 '10 Jan 12 '10 0 days NA NA 62SS
64 0% Call Manager Version Upgrade 1 day Jan 13 '10 Jan 13 '10 0 days NA NA 63
65 0% Call Managers Configuration 6 days Jan 14 '10 Jan 20 '10 0 days NA NA 64
66 0% IP Phones Addition 4 days Jan 14 '10 Jan 18 '10 0 days NA NA 65SS
67 0% Unity Version Upgrade 1 day Jan 19 '10 Jan 19 '10 0 days NA NA 66
68 0% Unity Configuration 6 days Jan 20 '10 Jan 26 '10 0 days NA NA 67
69 0% Equipment Ready for Delivery to Site 0 days Jan 26 '10 Jan 26 '10 0 days NA NA 6070 0% Industrial Buildings 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
71 0% Laboratory Building 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
72 0% Guardhouse 2 Explosive Storage 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
73 0% Water Plant Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
74 0% Administration Building 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
75 0% Training Center 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
76 0% Security Building 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
77 0% Area 20 Secondary Crushing Substation & Operations Bl . 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
78 0% Area 30 Communition Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
79 0% First Aid Clinic/ Firehouse 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
80 0% Area 70 Load Out Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
81 0% Central Control Building 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
82 0% Substation (Utilities) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
83 0% Fuel Truck Comfort Station 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
84 0% Area 10 Primary Crushing Substation & Operations Bldg. 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
85 0% Mosque 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
86 0% Dining / Change House 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
87 0% Guardhouse 1A (Main Gate) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
88 0% Guardhouse 1B (High Security) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
89 0% Guardhouse Truck Area ( Guardhouse 3) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
90 0% Area 60 Dryer Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
91 0% Maintenance / Warehouse 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
92 0% Area 40 Flotation Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
93 0% Power Plant Substation 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
94 0% Al Jalamid Village 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 2
7/29/2019 Appendix 11-Updated Schedule
3/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
95 0% Labor Residence 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
96 0% Management Residence Type 1 (2ea) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
97 0% Supervisor Residence (4ea) 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
98 0% Management Residence Type 2 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
99 0% Laundry/Warehouse 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
100 0% Workshop 0 days Jan 26 '10 Jan 26 '10 0 days NA NA101 0% Central Common Area 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
102 0% Dining Hall and Kitchen 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
103 0% Club House 0 days Jan 26 '10 Jan 26 '10 0 days NA NA
104 0% Mosque 0 days J an 26 '10 Jan 26 '10 0 days NA NA
105 100% OSP Cabling 30 days Oct 27 '09 Dec 6 '09 24 days Dec 16 '09 Jan 12 '10 56,57SS+2 days
106 100% Placing of P.O. 1 day Oct 27 '09 Oct 27 '09 1.8 days Dec 16 '09 Dec 17 '09
107 100% Delivery to Site 30 days Oct 27 '09 Dec 6 '09 11 days Dec 31 '09 Jan 12 '10
108 61% Wireless Communication 73 days Oct 29 '09 Jan 27 '10 43.59 days Nov 24 '09 NA 56,105SS+2 days
109 100% Placing of P.O. 1 day Oct 29 '09 Oct 29 '09 1 day Nov 24 '09 Nov 24 '09
110 60% Delivery to Site 72 days Oct 31 '09 Jan 27 '10 43.2 days Nov 24 '09 NA 109
111 90% VSAT 11 days Nov 1 '09 Nov 12 '09 76.62 days Nov 11 '09 NA 56,108SS+2 days
112 100% Placing of P.O. 1 day Nov 1 '09 Nov 1 '09 1 day Nov 11 '09 Nov 11 '09
113 90% Delivery to Site 10 days Nov 2 '09 Nov 12 '09 63 days Dec 5 '09 NA 112
114 59% GSM Enhancement 64 days Nov 3 '09 Jan 21 '10 58.2 days Nov 7 '09 NA 56,111SS+2 days
115 100% Final BOM 1 day Nov 3 '09 Nov 3 '09 1 day Nov 7 '09 Nov 7 '09
116 100% Material Order (PO) 1 day Nov 4 '09 Nov 4 '09 1 day Dec 24 '09 Dec 24 '09 115117 60% Material Delivery Passive 30 days Nov 5 '09 Dec 15 '09 18 days Dec 26 '09 NA 116
118 60% Material Delivery Active 60 days Nov 5 '09 Jan 19 '10 36 days Dec 26 '09 NA 116
119 100% Site Storage Available 1 day Nov 3 '09 Nov 3 '09 1 day Dec 25 '09 Dec 26 '09
120 40% Material Delivery Passive (SBM Warehouse) 3 days Dec 16 '09 Dec 19 '09 1.2 days Jan 30 '10 NA 117,119
121 0% Material Delivery Active (SBM Warehouse) 1 day Jan 20 '10 Jan 20 '10 0 days NA NA 118,119
122 0% Material Delivery Passive (to site) 1 day Dec 20 '09 Dec 20 '09 0 days NA NA 119,120
123 0% Material Delivery Active (to site) 1 day Jan 21 '10 Jan 21 '10 0 days NA NA 119,121
124 100% Structured Cabling & Telecomm Spaces 30 days Nov 5 '09 Dec 15 '09 25 days Dec 15 '09 Jan 12 '10 56,114SS+2 days
125 100% Placing of P.O. 1 day Nov 5 '09 Nov 5 '09 1 day Dec 15 '09 Dec 15 '09
126 100% Delivery to Site 30 days Nov 5 '09 Dec 15 '09 24 days Dec 16 '09 Jan 12 '10
127 100% Video Conferencing Equipment 30 days Nov 8 '09 Dec 17 '09 39 days Nov 17 '09 Jan 6 '10 56,124SS+2 days
128 100% Placing of P.O. 1 day Nov 8 '09 Nov 8 '09 1 day Nov 17 '09 Nov 17 '09
129 100% Delivery to Site 30 days Nov 8 '09 Dec 17 '09 38 days Nov 18 '09 Jan 6 '10
130 100% Civil Materials 10 days Nov 10 '09 Nov 21 '09 15 days Dec 15 '09 Dec 31 '09 56,127SS+2 days
131 100% Placing of P.O. 1 day Nov 10 '09 Nov 10 '09 1 day Dec 15 '09 Dec 15 '09
132 100% Delivery to Site 10 days Nov 10 '09 Nov 21 '09 14 days Dec 16 '09 Dec 31 '09
133 0% Procurement Completion 1 day Jan 28 '10 Jan 28 '10 0 days NA NA 57,111,108,114,124,1
134
135 18% Installation/Construction 181 days Aug 18 '09 Mar 29 '10 25.92 days Oct 24 '09 NA
136 100% Detailed Site Survey 5 days Oct 27 '09 Nov 1 '09 5 days Oct 25 '09 Oct 29 '09 1 7FS+10 days,35
137 100% Construction Kick-Off Meeting 1 day Oct 27 '09 Oct 27 '09 1 day Jan 2 '10 Jan 2 '10
138 100% Site Mobilization 38 days Oct 25 '09 Dec 13 '09 38 days Nov 7 '09 Dec 26 '09
139 100% Site Office 35 days Oct 25 '09 Dec 9 '09 30 days Nov 16 '09 Dec 26 '09 35FS+12 days
140 100% Site Offices Fabrication 25 days Oct 25 '09 Nov 22 '09 12 days Dec 5 '09 Dec 17 '09
141 100% Land Preparation 10 days Oct 25 '09 Nov 4 '09 11 days Nov 16 '09 Dec 3 '09 140SS
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 3
7/29/2019 Appendix 11-Updated Schedule
4/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
142 100% Site Offices Delivery to Project Site 2 days Nov 23 '09 Nov 24 '09 3 days Dec 1 '09 Dec 6 '09 140,141
143 100% Site Offices Assembly 6 days Nov 25 '09 Dec 7 '09 16 days Dec 2 '09 Dec 21 '09 142
144 100% Site Office Furniture Delivery to Project Site 2 days Dec 8 '09 Dec 9 '09 1 day Dec 26 '09 Dec 26 '09 143
145 100% Complete Site Offices & Temporary Facilities 0 days Dec 9 '09 Dec 9 '09 1 day Dec 26 '09 Dec 26 '09 140,141,142,143,144
146 100% Manpower Mobilization 3 days Dec 10 '09 Dec 13 '09 31 days Nov 7 '09 Dec 17 '09 1 39,17
147 47% OSP 58 days Dec 14 '09 Feb 18 '10 18.92 days Jan 13 '10 NA 35,146148 70% Al Jalamid Industrial Area 58 days Dec 14 '09 Feb 18 '10 25.9 days Jan 17 '10 NA
149 70% FOC Pulling 58 days Dec 14 '09 Feb 18 '10 25.9 days Jan 17 '10 NA 105
150 100% Admin Building to Central Control Building 4 days Dec 14 '09 Dec 17 '09 1 day Feb 10 '10 Feb 10 '10
151 100% Admin Building to Mosque 1 day Dec 14 '09 Dec 14 '09 1 day Jan 26 '10 Jan 26 '10 150SS
152 100% Admin Building to Training Center 1 day Dec 15 '09 Dec 15 '09 1 day Jan 28 '10 Jan 28 '10 151
153 100% Admin Building to Security Building 2 days Dec 16 '09 Dec 17 '09 1 day Feb 14 '10 Feb 14 '10 152
154 100% Admin Building to Guard House 1A 1 day Dec 19 '09 Dec 19 '09 1 day Feb 14 '10 Feb 15 '10 153
155 100% Admin Building to Guard House Explosive Storage 15 days Dec 19 '09 Jan 4 '10 5 days Jan 23 '10 Jan 27 '10 154SS
156 0% Admin Building to Admin Village X 2 15 days Dec 31 '09 Jan 17 '10 0 days NA NA 155FS-4 days
157 100% Training Center to Change House & Dining Hall 1 day Jan 5 '10 Jan 5 '10 1 day Jan 27 '10 Jan 27 '10 155
158 100% Security Building to First Aid Clinic 1 day Jan 6 '10 Jan 6 '10 1 day Feb 15 '10 Feb 15 '10 157
159 100% First Aid Clinic to Guard House 1A 1 day Jan 16 '10 Jan 16 '10 1 day Feb 24 '10 Feb 24 '10 156FS-2 days
160 100% Security Building to Guardhouse 1B 1 day Jan 16 '10 Jan 16 '10 1 day Feb 16 '10 Feb 16 '10 159SS
161 100% Central Control Building to Laboratory X 2 6 days Jan 17 '10 Jan 23 '10 1 day Feb 16 '10 Feb 16 '10 160
162 100% Security Building to Central Control Bldg 3 days Jan 19 '10 Jan 21 '10 1 day Feb 16 '10 Feb 16 '10 161SS+2 days
163 100% Laboratory to Substation Utilities X 2 3 days Jan 23 '10 Jan 25 '10 1 day Feb 28 '10 Feb 28 '10 162164 100% Substation Utilities to Maintenance Warehouse X 2 3 days Jan 23 '10 Jan 25 '10 1 day Feb 13 '10 Feb 13 '10 163SS
165 100% Central Control Building to Maintenance Warehouse X 2 5 days Jan 26 '10 Jan 31 '10 1 day Feb 11 '10 Feb 11 '10 164
166 100% Central Control Building to Dryer Substation 3 days Feb 1 '10 Feb 3 '10 1 day Jan 20 '10 Jan 20 '10 165
167 100% Central Control Building to Water Plant Substation 2 days Feb 1 '10 Feb 2 '10 1 day Jan 28 '10 Jan 28 '10 166SS
168 100% Central Control Building to Guardhouse 3 2 days Feb 3 '10 Feb 4 '10 1 day Jan 20 '10 Jan 20 '10 167
169 100% Water Plant Substation to Comfort Station 1 day Feb 3 '10 Feb 3 '10 1 day Jan 21 '10 Jan 21 '10 168SS
170 100% Central Control Building to Power Plant Main Substation 3 days Feb 4 '10 Feb 7 '10 1 day Feb 18 '10 Feb 18 '10 169
171 100% Central Control Building to Loadout Substation 1 day Feb 4 '10 Feb 4 '10 1 day Feb 18 '10 Feb 18 '10 170SS
172 100% Central Control Building to Flotation Substation 1 day Feb 6 '10 Feb 6 '10 1 day Jan 26 '10 Jan 26 '10 171
173 100% Central Control Building to Communition Substation 2 days Feb 7 '10 Feb 8 '10 2 days Jan 27 '10 Jan 28 '10 172
174 100% Central Control Building to Primary Crushing 7 days Feb 9 '10 Feb 16 '10 4 days Jan 17 '10 Jan 20 '10 173
175 100% Central Control Building to Secondary Crushing Substati 6 days Feb 13 '10 Feb 18 '10 3 days Feb 13 '10 Feb 15 '10 174SS+3 days
176 0% Al Jalamid Village 6 days Dec 14 '09 Dec 20 '09 0 days NA NA
177 0% FOC Pulling 6 days Dec 14 '09 Dec 20 '09 0 days NA NA 105
178 0% Village Central Common Area To Mosque 6 days Dec 14 '09 Dec 20 '09 0 days NA NA
179 0% Village Central Common Area To Dining Hall 3 days Dec 14 '09 Dec 16 '09 0 days NA NA
180 0% Village Central Common Area To Gatehouse 3 days Dec 14 '09 Dec 16 '09 0 days NA NA
181 0% Village Central Common Area To Club House 3 days Dec 14 '09 Dec 16 '09 0 days NA NA
182 0% Village Central Common Area To Laborer's Residence 3 days Dec 14 '09 Dec 16 '09 0 days NA NA
183 0% Laborer's Residence To Supervisor's Residence 3 days Dec 14 '09 Dec 16 '09 0 days NA NA
184 0% Supervisor's Residence To Manager's Residence 3 days Dec 14 '09 Dec 16 '09 0 days NA NA
185 0% Building Site Access 81 days Aug 18 '09 Dec 1 '09 0 days Nov 24 '09 NA
186 100% Industrial Buildings 81 days Aug 18 '09 Dec 1 '09 57 days Nov 24 '09 Feb 4 '10
187 100% Laboratory Building 0 days Aug 18 '09 Aug 18 '09 0 days Nov 24 '09 Nov 24 '09
188 100% Guardhouse 2 Explosive Storage 0 days Aug 25 '09 Aug 25 '09 0 days Dec 5 '09 Dec 5 '09
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 4
7/29/2019 Appendix 11-Updated Schedule
5/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
189 100% Water Plant Substation 0 days Sep 10 '09 Sep 10 '09 0 days Dec 7 '09 Dec 7 '09
190 100% Administration Building 0 days Sep 20 '09 Sep 20 '09 0 days Dec 9 '09 Dec 9 '09
191 100% Training Center 0 days Sep 30 '09 Sep 30 '09 0 days Dec 12 '09 Dec 12 '09
192 100% Security Building 0 days Oct 10 '09 Oct 10 '09 0 days Dec 14 '09 Dec 14 '09
193 100% Area 20 Secondary Crushing Substation & Operations Bldg. 0 days Oct 15 '09 Oct 15 '09 0 days Dec 16 '09 Dec 16 '09
194 100% Area 30 Communition Substation 0 days Oct 15 '09 Oct 15 '09 0 days Dec 16 '09 Dec 16 '09
195 100% First Aid Clinic/ Firehouse 0 days Oct 20 '09 Oct 20 '09 0 days Dec 21 '09 Dec 21 '09
196 100% Area 70 Load Out Substation 0 days Oct 20 '09 Oct 20 '09 0 days Dec 23 '09 Dec 23 '09
197 100% Central Control Building 0 days Oct 20 '09 Oct 20 '09 0 days Dec 28 '09 Dec 28 '09
198 100% Substation Utilities 0 days Oct 31 '09 Oct 31 '09 0 days Jan 3 '10 Jan 3 '10
199 100% Feul Truck Comfort Station 0 days Oct 31 '09 Oct 31 '09 0 days Jan 5 '10 Jan 5 '10
200 100% Area 10 Primary Crushing Substation & Operations Building 0 days Oct 31 '09 Oct 31 '09 0 days Jan 10 '10 Jan 10 '10
201 100% Mosque 0 days Oct 31 '09 Oct 31 '09 0 days Jan 12 '10 Jan 12 '10
202 100% Change House & Dining Hall Building 0 days Oct 31 '09 Oct 31 '09 0 days Jan 16 '10 Jan 16 '10
203 100% Guardhouse 1A (Main Gate) 0 days Nov 15 '09 Nov 15 '09 0 days Jan 18 '10 Jan 18 '10
204 100% Guardhouse 1B (High Security) 0 days Nov 15 '09 Nov 15 '09 0 days Jan 21 '10 Jan 21 '10
205 100% Guardhouse Truck Area( Guardhouse 3) 0 days Nov 15 '09 Nov 15 '09 0 days Jan 24 '10 Jan 24 '10
206 100% Area 60 Dryer Substation 0 days Nov 10 '09 Nov 10 '09 0 days Jan 28 '10 Jan 28 '10
207 100% Maintenance / Warehouse 0 days Nov 21 '09 Nov 21 '09 0 days Jan 31 '10 Jan 31 '10
208 100% Area 60 Flotation Substation 0 days Nov 30 '09 Nov 30 '09 0 days Feb 2 '10 Feb 2 '10
209 100% Power Plant & Main Substation 0 days Dec 1 '09 Dec 1 '09 0 days Feb 4 '10 Feb 4 '10
210 0% Al Jalamid Village 40 days Oct 5 '09 Nov 21 '09 0 days NA NA211 0% Labor Residence 0 days Oct 5 '09 Oct 5 '09 0 days NA NA
212 0% Management Residence Type 1 (2ea) 0 days Oct 15 '09 Oct 15 '09 0 days NA NA
213 0% Supervisor Residence (4ea) 0 days Oct 18 '09 Oct 18 '09 0 days NA NA
214 0% Management Residence Type 2 0 days Oct 20 '09 Oct 20 '09 0 days NA NA
215 0% Laundry/Warehouse 0 days Nov 10 '09 Nov 10 '09 0 days NA NA
216 0% Workshop 0 days Nov 10 '09 Nov 10 '09 0 days NA NA
217 0% Central Common Area 0 days Nov 10 '09 Nov 10 '09 0 days NA NA
218 0% Dining Hall and Kitchen 0 days Nov 15 '09 Nov 15 '09 0 days NA NA
219 0% Club House 0 days Nov 15 '09 Nov 15 '09 0 days NA NA
220 0% Mosque 0 days Nov 21 '09 Nov 21 '09 0 days NA NA
221 6% ISP 91 days D ec 13 '09 Mar 29 '10 6.67 days Dec 17 '09 NA
222 8% Industrial Buildings 91 days Dec 13 '09 Mar 29 '10 8.78 days Dec 17 '09 NA 146
223 20% Laboratory Building 44 days Dec 13 '09 Feb 2 '10 18 days Dec 17 '09 NA 187
224 100% Communication Room Ready 0 days Dec 13 '09 Dec 13 '09 0 days Dec 17 '09 Dec 17 '09
225 0% Installation of Cable Ladders & Trays 1 day Dec 16 '09 Dec 16 '09 0 days NA NA 124
226 100% Installation of Communication Racks 1 day Dec 16 '09 Dec 16 '09 1 day Feb 20 '10 Feb 20 '10 225SS,124
227 0% Installation Of Power Cabling & Grounding 1 day Dec 16 '09 Dec 16 '09 0 days NA NA 226SS,124
228 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Dec 16 '09 Dec 16 '09 1 day Feb 21 '10 Feb 21 '10 227SS,124
229 100% Testing of UTP Cables 1 day Dec 17 '09 Dec 17 '09 1 day Feb 22 '10 Feb 22 '10 228
230 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 224,71
231 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 229SS,230
232 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 226,230
233 0% Installation of UTP & Fiber Patch cords 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 124,228
234 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 233,230
235 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 161,163,231
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 5
7/29/2019 Appendix 11-Updated Schedule
6/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
236 0% Testing of Fiber Cables 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 235
237 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 232,226,228,231
238 0% Interfacing With Overall Network 1 day Feb 2 '10 Feb 2 '10 0 days NA NA 236
239 0% Guard House 2 Explosive Storage 40 days Dec 16 '09 Feb 1 '10 0 days NA NA 188,223SS+3 days
240 0% Communication Room Ready 0 days Dec 16 '09 Dec 16 '09 0 days NA NA
241 0% Installation of Cable Ladders & Trays 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 124
242 0% Installation of Communication Racks 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 241SS,124
243 0% Installation Of Power Cabling & Grounding 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 242SS,124
244 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Dec 17 '09 Dec 17 '09 0 days NA NA 243SS,124
245 0% Testing of UTP Cables 1 day Dec 19 '09 Dec 19 '09 0 days NA NA 244
246 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 240,72
247 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 245SS,246
248 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 242,246
249 0% Installation of UTP & Fiber Patch cords 1 day Dec 19 '09 Dec 19 '09 0 days NA NA 124,244
250 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 249,246
251 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 155,247
252 0% Testing of Fiber Cables 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 251
253 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 248,242,244,247
254 0% Interfacing With Overall Network 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 253
255 13% Water Plant Substation 41 days Dec 21 '09 Feb 7 '10 11.07 days Dec 26 '09 NA 189,239SS+4 days
256 0% Communication Room Ready 0 days Dec 21 '09 Dec 21 '09 0 days NA NA
257 0% Installation of Cable Ladders & Trays 1 day Dec 22 '09 Dec 22 '09 0 days NA NA 124258 100% Installation of Communication Racks 1 day Dec 22 '09 Dec 22 '09 1 day Feb 25 '10 Feb 25 '10 257SS,124
259 0% Installation Of Power Cabling & Grounding 1 day Dec 22 '09 Dec 22 '09 0 days NA NA 258SS,124
260 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Dec 22 '09 Dec 22 '09 1 day Feb 25 '10 Feb 25 '10 259SS,124
261 0% Testing of UTP Cables 1 day Dec 23 '09 Dec 23 '09 0 days NA NA 260
262 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 256,73
263 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 261SS,262
264 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 258,262
265 0% Installation of UTP & Fiber Patch cords 1 day Dec 23 '09 Dec 23 '09 0 days NA NA 124,260
266 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 265,262
267 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 4 '10 Feb 4 '10 0 days NA NA 167,169,263
268 0% Testing of Fiber Cables 1 day Feb 6 '10 Feb 6 '10 0 days NA NA 267
269 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 264,258,260,263
270 0% Interfacing With Overall Network 1 day Feb 7 '10 Feb 7 '10 0 days NA NA 268
271 19% Administration Building 48 days Dec 24 '09 Feb 18 '10 17.46 days Dec 29 '09 NA 190,255SS+3 days
272 0% Communication Room Ready 0 days Dec 24 '09 Dec 24 '09 0 days NA NA
273 100% Installation of Cable Ladders & Trays 6 days Dec 26 '09 Dec 31 '09 2 days Feb 13 '10 Feb 14 '10 124
274 100% Installation of Communication Racks 2 days Dec 26 '09 Dec 27 '09 1 day Feb 17 '10 Feb 17 '10 273SS,124
275 0% Installation Of Power Cabling & Grounding 5 days Dec 28 '09 Jan 2 '10 0 days NA NA 274,124
276 100% Installation & Termination of UTP Patch Panel & Face Pl 4 days Dec 28 '09 Dec 31 '09 7 days Feb 18 '10 Feb 25 '10 275SS,124
277 100% Testing of UTP Cables 2 days Jan 2 '10 Jan 3 '10 1 day Feb 24 '10 Feb 24 '10 276
278 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 272,74
279 0% Installation & Configuration of Switches 10 days Jan 30 '10 Feb 9 '10 0 days NA NA 274,278
280 0% Installation of Fiber Patch Panel 7 days Jan 30 '10 Feb 6 '10 0 days NA NA 277,278
281 0% Installation of UTP & Fiber Patch cords 10 days Jan 2 '10 Jan 12 '10 0 days NA NA 276,124
282 0% Installation of IP Telephones 10 days Jan 30 '10 Feb 9 '10 0 days NA NA 281,278
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 6
7/29/2019 Appendix 11-Updated Schedule
7/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
283 100% Installation of Video Conferencing Equipment 6 days Jan 13 '10 Jan 19 '10 2 days Jan 4 '10 Jan 5 '10 127,281
284 0% Splicing Of Indoor/Outdoor Fiber Cables 7 days Feb 7 '10 Feb 14 '10 0 days NA NA 150,151,152,153,154, , ,
285 0% Testing of Fiber Cables 3 days Feb 15 '10 Feb 17 '10 0 days NA NA 284
286 0% Labeling Rack, Patch panels and Switches 2 days Feb 10 '10 Feb 11 '10 0 days NA NA 279,274,276,280
287 0% Interfacing With Overall Network 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 285
288 7% Training Center 37 days Jan 3 '10 Feb 15 '10 5.93 days Jan 7 '10 NA 191,271SS+8 days
289 0% Communication Room Ready 0 days Jan 3 '10 Jan 3 '10 0 days NA NA
290 0% Installation of Cable Ladders & Trays 5 days Jan 4 '10 Jan 9 '10 0 days NA NA 124
291 100% Installation of Communication Racks 1 day Jan 4 '10 Jan 4 '10 1 day Feb 21 '10 Feb 21 '10 290SS,124
292 0% Installation Of Power Cabling & Grounding 3 days Jan 5 '10 Jan 7 '10 0 days NA NA 291,124
293 100% Installation & Termination of UTP Patch Panel & Face Pl 5 days Jan 5 '10 Jan 10 '10 1 day Feb 22 '10 Feb 22 '10 292SS,124
294 100% Testing of UTP Cables 2 days Jan 11 '10 Jan 12 '10 1 day Feb 25 '10 Feb 25 '10 293
295 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 289,75
296 0% Installation of Fiber Patch Panel 5 days Jan 30 '10 Feb 3 '10 0 days NA NA 295,294
297 0% Installation & Configuration of Switches 6 days Jan 30 '10 Feb 4 '10 0 days NA NA 291,295
298 0% Installation of UTP & Fiber Patch cords 2 days Jan 11 '10 Jan 12 '10 0 days NA NA 293,124
299 0% Installation of IP Telephones 3 days Feb 6 '10 Feb 8 '10 0 days NA NA 297,295
300 0% Installation of Video Conferencing Equipment 5 days Jan 13 '10 Jan 18 '10 0 days NA NA 298,127
301 0% Splicing Of Indoor/Outdoor Fiber Cables 7 days Feb 4 '10 Feb 11 '10 0 days NA NA 152,157,296
302 0% Testing of Fiber Cables 2 days Feb 13 '10 Feb 14 '10 0 days NA NA 301
303 0% Labeling Rack, Patch panels and Switches 2 days Feb 6 '10 Feb 7 '10 0 days NA NA 297,291,293,296
304 0% Interfacing With Overall Network 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 302305 14% Security Building 22 days Jan 10 '10 Feb 4 '10 9.71 days Jan 14 '10 NA 192,288SS+6 days
306 0% Communication Room Ready 0 days Jan 10 '10 Jan 10 '10 0 days NA NA
307 0% Installation of Cable Ladders & Trays 3 days Jan 11 '10 Jan 13 '10 0 days NA NA 124
308 100% Installation of Communication Racks 1 day Jan 11 '10 Jan 11 '10 1 day Feb 21 '10 Feb 21 '10 307SS,124
309 0% Installation Of Power Cabling & Grounding 2 days Jan 12 '10 Jan 13 '10 0 days NA NA 308,124
310 100% Installation & Termination of UTP Patch Panel & Face Pl 2 days Jan 12 '10 Jan 13 '10 1 day Feb 24 '10 Feb 24 '10 309SS,124
311 100% Testing of UTP Cables 1 day Jan 14 '10 Jan 14 '10 1 day Feb 25 '10 Feb 25 '10 310
312 0% Delivery from Warehouse to Building Communication Ro 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 306,76
313 0% Installation of Fiber Patch Panel 2 days Jan 30 '10 Jan 31 '10 0 days NA NA 312,311
314 0% Installation & Configuration of Switches 2 days Jan 30 '10 Jan 31 '10 0 days NA NA 308,312
315 0% Installation of UTP & Fiber Patch cords 2 days Jan 14 '10 Jan 16 '10 0 days NA NA 124,310
316 0% Installation of IP Telephones 2 days Jan 30 '10 Jan 31 '10 0 days NA NA 315,312
317 0% Splicing Of Indoor/Outdoor Fiber Cables 2 days Feb 1 '10 Feb 2 '10 0 days NA NA 153,158,160,162,313
318 0% Testing of Fiber Cables 1 day Feb 3 '10 Feb 3 '10 0 days NA NA 317
319 0% Labeling Rack, Patch panels and Switches 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 314,308,310,313
320 0% Interfacing With Overall Network 1 day Feb 4 '10 Feb 4 '10 0 days NA NA 318
321 0% Area 20 Secondary Crushing Substation & Operations Bl 30 days Jan 18 '10 Feb 22 '10 0 days NA NA 193,305SS+7 days
322 0% Communication Room Ready 0 days Jan 18 '10 Jan 18 '10 0 days NA NA
323 0% Installation of Cable Ladders & Trays 1 day Jan 19 '10 Jan 19 '10 0 days NA NA 124
324 0% Installation of Communication Racks 1 day Jan 19 '10 Jan 19 '10 0 days NA NA 323SS,124
325 0% Installation Of Power Cabling & Grounding 1 day Jan 20 '10 Jan 20 '10 0 days NA NA 324,124
326 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Jan 20 '10 Jan 20 '10 0 days NA NA 325SS,124
327 0% Testing of UTP Cables 1 day Jan 21 '10 Jan 21 '10 0 days NA NA 326
328 0% Delivery from Warehouse to Building Communication Ro 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 322,77
329 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 328,327
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 7
7/29/2019 Appendix 11-Updated Schedule
8/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
330 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 324,328
331 0% Installation of UTP & Fiber Patch cords 1 day Jan 21 '10 Jan 21 '10 0 days NA NA 326,124
332 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 331,328
333 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 175,329
334 0% Testing of Fiber Cables 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 333
335 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 330,324,326,329
336 0% Interfacing With Overall Network 1 day Feb 22 '10 Feb 22 '10 0 days NA NA 334
337 13% Area 30 Communition Substation 19 days Jan 20 '10 Feb 11 '10 7.6 days Jan 25 '10 NA 194,321SS+2 days
338 0% Communication Room Ready 0 days Jan 20 '10 Jan 20 '10 0 days NA NA
339 0% Installation of Cable Ladders & Trays 1 day Jan 21 '10 Jan 21 '10 0 days NA NA 124
340 100% Installation of Communication Racks 1 day Jan 21 '10 Jan 21 '10 1 day Feb 27 '10 Feb 27 '10 339SS,124
341 0% Installation Of Power Cabling & Grounding 1 day Jan 23 '10 Jan 23 '10 0 days NA NA 340,124
342 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Jan 23 '10 Jan 23 '10 1 day Feb 27 '10 Feb 27 '10 341SS,124
343 0% Testing of UTP Cables 1 day Jan 24 '10 Jan 24 '10 0 days NA NA 342
344 0% Delivery from SBM Warehouse to Building Communicati 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 338,78
345 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 344,343
346 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 340,344
347 0% Installation of UTP & Fiber Patch cords 1 day Jan 24 '10 Jan 24 '10 0 days NA NA 342,124
348 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 347,344
349 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 9 '10 Feb 9 '10 0 days NA NA 173,345
350 0% Testing of Fiber Cables 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 349
351 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 346,340,342,345352 0% Interfacing With Overall Network 1 day Feb 11 '10 Feb 11 '10 0 days NA NA 350
353 20% First Aid Clinic / Firehouse 6 days Jan 25 '10 Feb 1 '10 10.4 days Jan 30 '10 NA 195,337SS+4 days
354 0% Communication Room Ready 0 days Jan 25 '10 Jan 25 '10 0 days NA NA
355 0% Installation of Cable Ladders & Trays 1 day Jan 26 '10 Jan 26 '10 0 days NA NA 124
356 100% Installation of Communication Racks 1 day Jan 26 '10 Jan 26 '10 1 day Feb 17 '10 Feb 17 '10 355SS,124
357 0% Installation Of Power Cabling & Grounding 1 day Jan 27 '10 Jan 27 '10 0 days NA NA 356,124
358 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Jan 27 '10 Jan 27 '10 1 day Feb 22 '10 Feb 22 '10 357SS,124
359 100% Testing of UTP Cables 1 day Jan 28 '10 Jan 28 '10 1 day Feb 23 '10 Feb 23 '10 358
360 0% Delivery from Warehouse to Building Communication Ro 2 days Jan 27 '10 Jan 28 '10 0 days NA NA 354,79
361 0% Installation of Fiber Patch Panel 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 360,359
362 0% Installation & Configuration of Switches 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 356,360
363 0% Installation of UTP & Fiber Patch cords 1 day Jan 28 '10 Jan 28 '10 0 days NA NA 358,124
364 0% Installation of IP Telephones 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 363,360
365 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 158,159,361
366 0% Testing of Fiber Cables 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 365
367 0% Labeling Rack, Patch panels and Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 362,356,358,361
368 0% Interfacing With Overall Network 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 367
369 7% Area 70 Load Out Substation 10 days Jan 27 '10 Feb 8 '10 3.4 days Feb 1 '10 NA 196,353SS+2 days
370 0% Communication Room Ready 0 days Jan 27 '10 Jan 27 '10 0 days NA NA
371 0% Installation of Cable Ladders & Trays 1 day Jan 28 '10 Jan 28 '10 0 days NA NA 124
372 100% Installation of Communication Racks 1 day Jan 28 '10 Jan 28 '10 1 day Feb 28 '10 Feb 28 '10 371SS,124
373 0% Installation Of Power Cabling & Grounding 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 372,124
374 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Jan 30 '10 Jan 30 '10 0 days NA NA 373SS,124
375 0% Testing of UTP Cables 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 374
376 0% Delivery from Warehouse to Building Communication Ro 2 days Jan 28 '10 Jan 30 '10 0 days NA NA 370,80
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 8
7/29/2019 Appendix 11-Updated Schedule
9/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
377 0% Installation of Fiber Patch Panel 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 376,375
378 0% Installation & Configuration of Switches 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 372,376
379 0% Installation of UTP & Fiber Patch cords 1 day Jan 31 '10 Jan 31 '10 0 days NA NA 374,124
380 0% Installation of IP Telephones 1 day Feb 1 '10 Feb 1 '10 0 days NA NA 379,376
381 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 6 '10 Feb 6 '10 0 days NA NA 171,377
382 0% Testing of Fiber Cables 1 day Feb 7 '10 Feb 7 '10 0 days NA NA 381
383 0% Labeling Rack, Patch panels and Switches 1 day Feb 2 '10 Feb 2 '10 0 days NA NA 378,372,374,377
384 0% Interfacing With Overall Network 1 day Feb 8 '10 Feb 8 '10 0 days NA NA 382
385 0% Central Control Building 26 days Feb 1 '10 Mar 3 '10 0 days NA NA 197,369SS+4 days
386 0% Communication Room Ready 0 days Feb 1 '10 Feb 1 '10 0 days NA NA
387 0% Installation of Cable Ladders & Trays 3 days Feb 2 '10 Feb 4 '10 0 days NA NA 124
388 0% Installation of Communication Racks 1 day Feb 2 '10 Feb 2 '10 0 days NA NA 387SS,124
389 0% Installation Of Power Cabling & Grounding 2 days Feb 3 '10 Feb 4 '10 0 days NA NA 388,124
390 0% Installation & Termination of UTP Patch Panel & Face Pl 3 days Feb 6 '10 Feb 8 '10 0 days NA NA 389,124
391 0% Testing of UTP Cables 1 day Feb 9 '10 Feb 9 '10 0 days NA NA 390
392 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 2 '10 Feb 3 '10 0 days NA NA 386,81
393 0% Installation of Fiber Patch Panel 2 days Feb 10 '10 Feb 11 '10 0 days NA NA 392,391
394 0% Installation & Configuration of Switches 3 days Feb 4 '10 Feb 7 '10 0 days NA NA 388,392
395 0% Installation of UTP & Fiber Patch cords 2 days Feb 9 '10 Feb 10 '10 0 days NA NA 390,124
396 0% Installation of IP Telephones 3 days Feb 11 '10 Feb 14 '10 0 days NA NA 395,392
397 0% Splicing Of Indoor/Outdoor Fiber Cables 8 days Feb 20 '10 Feb 28 '10 0 days NA NA 150,161,162,166,167, , , , , , , ,
398 0% Testing of Fiber Cables 2 days Mar 1 '10 Mar 2 '10 0 days NA NA 397399 0% Labeling Rack, Patch panels and Switches 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 394,388,390,393
400 0% Interfacing With Overall Network 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 398
401 20% Substation Utilities 6 days Feb 7 '10 Feb 14 '10 8.4 days Feb 11 '10 NA 198,385SS+5 days
402 100% Communication Room Ready 0 days Feb 7 '10 Feb 7 '10 0 days Feb 11 '10 Feb 11 '10
403 0% Installation of Cable Ladders & Trays 1 day Feb 8 '10 Feb 8 '10 0 days NA NA 124
404 100% Installation of Communication Racks 1 day Feb 8 '10 Feb 8 '10 1 day Feb 18 '10 Feb 18 '10 403SS,124
405 0% Installation Of Power Cabling & Grounding 1 day Feb 8 '10 Feb 8 '10 0 days NA NA 404SS,124
406 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 9 '10 Feb 9 '10 1 day Feb 11 '10 Feb 11 '10 405,124
407 100% Testing of UTP Cables 1 day Feb 10 '10 Feb 10 '10 1 day Feb 20 '10 Feb 20 '10 406
408 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 8 '10 Feb 9 '10 0 days NA NA 402,82
409 0% Installation of Fiber Patch Panel 1 day Feb 11 '10 Feb 11 '10 0 days NA NA 408,407
410 0% Installation & Configuration of Switches 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 404,408
411 0% Installation of UTP & Fiber Patch cords 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 406,124
412 0% Installation of IP Telephones 1 day Feb 11 '10 Feb 11 '10 0 days NA NA 411,408
413 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 163,164,409
414 0% Testing of Fiber Cables 1 day Feb 14 '10 Feb 14 '10 0 days NA NA 413
415 0% Labeling Rack, Patch panels and Switches 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 410,404,406,409
416 0% Interfacing With Overall Network 1 day Feb 14 '10 Feb 14 '10 0 days NA NA 415
417 20% Feul Truck Comfort Station 6 days Feb 9 '10 Feb 16 '10 8.2 days Feb 13 '10 NA 199,401SS+2 days
418 100% Communication Room Ready 0 days Feb 9 '10 Feb 9 '10 0 days Feb 13 '10 Feb 13 '10
419 0% Installation of Cable Ladders & Trays 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 124
420 100% Installation of Communication Racks 1 day Feb 10 '10 Feb 10 '10 1 day Feb 28 '10 Feb 28 '10 419SS,124
421 0% Installation Of Power Cabling & Grounding 1 day Feb 10 '10 Feb 10 '10 0 days NA NA 420SS,124
422 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 10 '10 Feb 10 '10 1 day Feb 28 '10 Feb 28 '10 421SS,124
423 100% Testing of UTP Cables 1 day Feb 11 '10 Feb 11 '10 1 day Feb 28 '10 Feb 28 '10 422
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 9
7/29/2019 Appendix 11-Updated Schedule
10/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
424 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 10 '10 Feb 11 '10 0 days NA NA 418,83
425 0% Installation of Fiber Patch Panel 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 424,423
426 0% Installation & Configuration of Switches 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 420,424
427 0% Installation of UTP & Fiber Patch cords 1 day Feb 11 '10 Feb 11 '10 0 days NA NA 422,124
428 0% Installation of IP Telephones 1 day Feb 13 '10 Feb 13 '10 0 days NA NA 427,424
429 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 14 '10 Feb 14 '10 0 days NA NA 169,425
430 0% Testing of Fiber Cables 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 429
431 0% Labeling Rack, Patch panels and Switches 1 day Feb 14 '10 Feb 14 '10 0 days NA NA 426,420,422,425
432 0% Interfacing With Overall Network 1 day Feb 16 '10 Feb 16 '10 0 days NA NA 430
433 0% Area 10 Primary Crushing Substation & Operations Bldg. 7 days Feb 14 '10 Feb 22 '10 0 days NA NA 200,417SS+4 days
434 0% Communication Room Ready 0 days Feb 14 '10 Feb 14 '10 0 days NA NA
435 0% Installation of Cable Ladders & Trays 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 124
436 0% Installation of Communication Racks 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 435SS,124
437 0% Installation Of Power Cabling & Grounding 1 day Feb 15 '10 Feb 15 '10 0 days NA NA 436SS,124
438 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 16 '10 Feb 16 '10 0 days NA NA 437,124
439 0% Testing of UTP Cables 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 438
440 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 15 '10 Feb 16 '10 0 days NA NA 434,84
441 0% Installation of Fiber Patch Panel 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 440,439
442 0% Installation & Configuration of Switches 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 436,440
443 0% Installation of UTP & Fiber Patch cords 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 438,124
444 0% Installation of IP Telephones 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 443,440
445 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 174,441446 0% Testing of Fiber Cables 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 445
447 0% Labeling Rack, Patch panels and Switches 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 442,443,444
448 0% Interfacing With Overall Network 1 day Feb 22 '10 Feb 22 '10 0 days NA NA 446
449 0% Mosque 5 days Feb 16 '10 Feb 22 '10 0 days NA NA 201,433SS+2 days
450 0% Communication Room Ready 0 days Feb 16 '10 Feb 16 '10 0 days NA NA
451 0% Installation of Cable Ladders & Trays 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 124
452 0% Installation of Communication Racks 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 451SS,124
453 0% Installation Of Power Cabling & Grounding 1 day Feb 17 '10 Feb 17 '10 0 days NA NA 452SS,124
454 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 453,124
455 0% Testing of UTP Cables 1 day Feb 18 '10 Feb 18 '10 0 days NA NA 454SS
456 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 17 '10 Feb 18 '10 0 days NA NA 450,85
457 0% Installation of Fiber Patch Panel 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 456,455
458 0% Installation & Configuration of Switches 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 452,456
459 0% Installation of UTP & Fiber Patch cords 1 day Feb 20 '10 Feb 20 '10 0 days NA NA 454,124
460 0% Installation of IP Telephones 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 459,456
461 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 151,457462 0% Testing of Fiber Cables 1 day Feb 22 '10 Feb 22 '10 0 days NA NA 461
463 0% Labeling Rack, Patch panels and Switches 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 458,452,454,457
464 0% Interfacing With Overall Network 1 day Feb 22 '10 Feb 22 '10 0 days NA NA 463
465 20% Change House & Dining Hall Bldg. 6 days Feb 20 '10 Feb 27 '10 6.6 days Feb 23 '10 NA 202,449SS+3 days
466 100% Communication Room Ready 0 days Feb 20 '10 Feb 20 '10 0 days Feb 23 '10 Feb 23 '10
467 0% Installation of Cable Ladders & Trays 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 124
468 100% Installation of Communication Racks 1 day Feb 21 '10 Feb 21 '10 1 day Feb 24 '10 Feb 24 '10 467SS,124
469 0% Installation Of Power Cabling & Grounding 1 day Feb 21 '10 Feb 21 '10 0 days NA NA 468SS,124
470 100% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 22 '10 Feb 22 '10 1 day Feb 24 '10 Feb 24 '10 469,124
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 10
7/29/2019 Appendix 11-Updated Schedule
11/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
471 100% Testing of UTP Cables 1 day Feb 23 '10 Feb 23 '10 1 day Feb 25 '10 Feb 25 '10 470
472 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 21 '10 Feb 22 '10 0 days NA NA 466,86
473 0% Installation of Fiber Patch Panel 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 472,471
474 0% Installation & Configuration of Switches 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 468,472
475 0% Installation of UTP & Fiber Patch cords 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 470,124
476 0% Installation of IP Telephones 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 475,472
477 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 157,473
478 0% Testing of Fiber Cables 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 477
479 0% Labeling Rack, Patch panels and Switches 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 474,468,239,244
480 0% Interfacing With Overall Network 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 479
481 0% Guardhouse 1A ( Main Gate) 5 days Feb 22 '10 Feb 28 '10 0 days NA NA 203,465SS+2 days
482 0% Communication Room Ready 0 days Feb 22 '10 Feb 22 '10 0 days NA NA
483 0% Installation of Cable Ladders & Trays 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 124
484 0% Installation of Communication Racks 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 483SS,124
485 0% Installation Of Power Cabling & Grounding 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 484SS,124
486 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 23 '10 Feb 23 '10 0 days NA NA 485SS,124
487 0% Testing of UTP Cables 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 486
488 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 23 '10 Feb 24 '10 0 days NA NA 482,87
489 0% Installation of Fiber Patch Panel 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 488,487
490 0% Installation & Configuration of Switches 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 484,488
491 0% Installation of UTP & Fiber Patch cords 1 day Feb 24 '10 Feb 24 '10 0 days NA NA 486,124
492 0% Installation of IP Telephones 1 day Feb 25 '10 Feb 25 '10 0 days NA NA 491,488493 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 159,489
494 0% Testing of Fiber Cables 1 day Feb 28 '10 Feb 28 '10 0 days NA NA 493
495 0% Labeling Rack, Patch panels and Switches 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 490,484,486,489
496 0% Interfacing With Overall Network 1 day Feb 28 '10 Feb 28 '10 0 days NA NA 495
497 0% Guardhouse 1B (High Security) 5 days Feb 25 '10 Mar 3 '10 0 days NA NA 204,481SS+3 days
498 0% Communication Room Ready 0 days Feb 25 '10 Feb 25 '10 0 days NA NA
499 0% Installation of Cable Ladders & Trays 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 124
500 0% Installation of Communication Racks 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 499SS,124
501 0% Installation Of Power Cabling & Grounding 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 500SS,124
502 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Feb 27 '10 Feb 27 '10 0 days NA NA 501SS,124
503 0% Testing of UTP Cables 1 day Feb 28 '10 Feb 28 '10 0 days NA NA 502
504 0% Delivery from Warehouse to Building Communication Ro 2 days Feb 27 '10 Feb 28 '10 0 days NA NA 498,88
505 0% Installation of Fiber Patch Panel 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 504,503
506 0% Installation & Configuration of Switches 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 500,504
507 0% Installation of UTP & Fiber Patch cords 1 day Feb 28 '10 Feb 28 '10 0 days NA NA 502,124
508 0% Installation of IP Telephones 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 507,504509 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 2 '10 Mar 2 '10 0 days NA NA 160,505
510 0% Testing of Fiber Cables 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 509
511 0% Labeling Rack, Patch panels and Switches 1 day Mar 2 '10 Mar 2 '10 0 days NA NA 506,500,502,505
512 0% Interfacing With Overall Network 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 511
513 0% Guardhouse Truck Area ( Guardhouse 3) 6 days Feb 28 '10 Mar 7 '10 0 days NA NA 205,497SS+2 days
514 0% Communication Room Ready 0 days Feb 28 '10 Feb 28 '10 0 days NA NA
515 0% Installation of Cable Ladders & Trays 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 124
516 0% Installation of Communication Racks 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 515SS,124
517 0% Installation Of Power Cabling & Grounding 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 516SS,124
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 11
7/29/2019 Appendix 11-Updated Schedule
12/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
518 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 1 '10 Mar 1 '10 0 days NA NA 517SS,124
519 0% Testing of UTP Cables 1 day Mar 2 '10 Mar 2 '10 0 days NA NA 518
520 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 1 '10 Mar 2 '10 0 days NA NA 514,89
521 0% Installation of Fiber Patch Panel 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 520,519
522 0% Installation & Configuration of Switches 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 516,520
523 0% Installation of UTP & Fiber Patch cords 1 day Mar 2 '10 Mar 2 '10 0 days NA NA 518,124
524 0% Installation of IP Telephones 1 day Mar 3 '10 Mar 3 '10 0 days NA NA 523,520
525 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 4 '10 Mar 4 '10 0 days NA NA 168,521
526 0% Testing of Fiber Cables 1 day Mar 6 '10 Mar 6 '10 0 days NA NA 525
527 0% Labeling Rack, Patch panels and Switches 1 day Mar 4 '10 Mar 4 '10 0 days NA NA 522,516,518,521
528 0% Interfacing With Overall Network 1 day Mar 7 '10 Mar 7 '10 0 days NA NA 526
529 7% Area 60 Dryer Substation 6 days Mar 4 '10 Mar 11 '10 1.87 days Feb 28 '10 NA 206,513SS+4 days
530 0% Communication Room Ready 0 days Mar 4 '10 Mar 4 '10 0 days NA NA
531 0% Installation of Cable Ladders & Trays 1 day Mar 6 '10 Mar 6 '10 0 days NA NA 124
532 100% Installation of Communication Racks 1 day Mar 6 '10 Mar 6 '10 1 day Feb 28 '10 Feb 28 '10 531SS,124
533 0% Installation Of Power Cabling & Grounding 1 day Mar 6 '10 Mar 6 '10 0 days NA NA 532SS,124
534 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 7 '10 Mar 7 '10 0 days NA NA 533,124
535 0% Testing of UTP Cables 1 day Mar 8 '10 Mar 8 '10 0 days NA NA 534
536 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 6 '10 Mar 7 '10 0 days NA NA 530,90
537 0% Installation of Fiber Patch Panel 1 day Mar 9 '10 Mar 9 '10 0 days NA NA 536,535
538 0% Installation & Configuration of Switches 1 day Mar 8 '10 Mar 8 '10 0 days NA NA 532,536
539 0% Installation of UTP & Fiber Patch cords 1 day Mar 8 '10 Mar 8 '10 0 days NA NA 534,124540 0% Installation of IP Telephones 1 day Mar 9 '10 Mar 9 '10 0 days NA NA 539,536
541 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 166,537
542 0% Testing of Fiber Cables 1 day Mar 11 '10 Mar 11 '10 0 days NA NA 541
543 0% Labeling Rack, Patch panels and Switches 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 538,532,534,537
544 0% Interfacing With Overall Network 1 day Mar 11 '10 Mar 11 '10 0 days NA NA 543
545 0% Maintenance / Warehouse 19 days Mar 7 '10 Mar 29 '10 0 days NA NA 207,529SS+2 days
546 0% Communication Room Ready 0 days Mar 7 '10 Mar 7 '10 0 days NA NA
547 0% Installation of Cable Ladders & Trays 3 days Mar 8 '10 Mar 10 '10 0 days NA NA 124
548 0% Installation of Communication Racks 1 day Mar 8 '10 Mar 8 '10 0 days NA NA 547SS,124
549 0% Installation Of Power Cabling & Grounding 3 days Mar 9 '10 Mar 11 '10 0 days NA NA 548,124
550 0% Installation & Termination of UTP Patch Panel & Face Pl 3 days Mar 13 '10 Mar 15 '10 0 days NA NA 549,124
551 0% Testing of UTP Cables 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 550
552 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 8 '10 Mar 9 '10 0 days NA NA 546,91
553 0% Installation of Fiber Patch Panel 4 days Mar 17 '10 Mar 21 '10 0 days NA NA 552,551
554 0% Installation & Configuration of Switches 6 days Mar 10 '10 Mar 16 '10 0 days NA NA 548,552
555 0% Installation of UTP & Fiber Patch cords 3 days Mar 16 '10 Mar 18 '10 0 days NA NA 550,124556 0% Installation of IP Telephones 6 days Mar 20 '10 Mar 25 '10 0 days NA NA 555,552
557 0% Splicing Of Indoor/Outdoor Fiber Cables 4 days Mar 22 '10 Mar 25 '10 0 days NA NA 164,553
558 0% Testing of Fiber Cables 2 days Mar 27 '10 Mar 28 '10 0 days NA NA 557
559 0% Labeling Rack, Patch panels and Switches 2 days Mar 22 '10 Mar 23 '10 0 days NA NA 554,548,550,553
560 0% Interfacing With Overall Network 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 558
561 0% Area 40 Flotation Substation 7 days Mar 9 '10 Mar 17 '10 0 days NA NA 208,545SS+2 days
562 0% Communication Room Ready 0 days Mar 9 '10 Mar 9 '10 0 days NA NA
563 0% Installation of Cable Ladders & Trays 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 124
564 0% Installation of Communication Racks 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 563SS,124
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 12
7/29/2019 Appendix 11-Updated Schedule
13/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
565 0% Installation Of Power Cabling & Grounding 1 day Mar 10 '10 Mar 10 '10 0 days NA NA 564SS,124
566 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 11 '10 Mar 11 '10 0 days NA NA 565,124
567 0% Testing of UTP Cables 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 566
568 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 10 '10 Mar 11 '10 0 days NA NA 562,92
569 0% Installation of Fiber Patch Panel 1 day Mar 14 '10 Mar 14 '10 0 days NA NA 568,567
570 0% Installation & Configuration of Switches 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 564,568
571 0% Installation of UTP & Fiber Patch cords 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 566,124
572 0% Installation of IP Telephones 1 day Mar 14 '10 Mar 14 '10 0 days NA NA 571,568
573 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 172,569
574 0% Testing of Fiber Cables 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 573
575 0% Labeling Rack, Patch panels and Switches 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 570,564,566,569
576 0% Interfacing With Overall Network 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 574
577 0% Power Plant & Main Substation 6 days Mar 11 '10 Mar 18 '10 0 days NA NA 209,561SS+2 days
578 0% Communication Room Ready 0 days Mar 11 '10 Mar 11 '10 0 days NA NA
579 0% Installation of Cable Ladders & Trays 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 124
580 0% Installation of Communication Racks 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 579SS,124
581 0% Installation Of Power Cabling & Grounding 1 day Mar 13 '10 Mar 13 '10 0 days NA NA 580SS,124
582 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 14 '10 Mar 14 '10 0 days NA NA 581,124
583 0% Testing of UTP Cables 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 582
584 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 13 '10 Mar 14 '10 0 days NA NA 578,93
585 0% Installation of Fiber Patch Panel 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 584,583
586 0% Installation & Configuration of Switches 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 580,583587 0% Installation of UTP & Fiber Patch cords 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 582,124
588 0% Installation of IP Telephones 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 587,583
589 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 170,585
590 0% Testing of Fiber Cables 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 589
591 0% Labeling Rack, Patch panels and Switches 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 586,580,582,585
592 0% Interfacing With Overall Network 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 591
593 0% Al Jalamid Village 13 days Mar 14 '10 Mar 29 '10 0 days NA NA 146
594 0% Labor Residence 6 days Mar 14 '10 Mar 21 '10 0 days NA NA 211,577SS+2 days
595 0% Communication Room Ready 0 days Mar 14 '10 Mar 14 '10 0 days NA NA
596 0% Installation of Cable Ladders & Trays 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 124
597 0% Installation of Communication Racks 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 596SS,124
598 0% Installation Of Power Cabling & Grounding 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 597SS,124
599 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 598,124
600 0% Testing of UTP Cables 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 599
601 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 15 '10 Mar 16 '10 0 days NA NA 595,95
602 0% Installation of Fiber Patch Panel 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 601,600603 0% Installation & Configuration of Switches 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 597,601
604 0% Installation of UTP & Fiber Patch cords 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 599,124
605 0% Installation of IP Telephones 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 604,601
606 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 602
607 0% Testing of Fiber Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 606
608 0% Labeling Rack, Patch panels and Switches 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 603,597,599,602
609 0% Interfacing With Overall Network 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 608
610 0% Management Residence Type 1 (2ea) 5 days Mar 14 '10 Mar 20 '10 0 days NA NA 212,594SS
611 0% Communication Room Ready 0 days Mar 14 '10 Mar 14 '10 0 days NA NA
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 13
7/29/2019 Appendix 11-Updated Schedule
14/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
612 0% Installation of Cable Ladders & Trays 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 124
613 0% Installation of Communication Racks 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 612SS,124
614 0% Installation Of Power Cabling & Grounding 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 613SS,124
615 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 15 '10 Mar 15 '10 0 days NA NA 614SS,124
616 0% Testing of UTP Cables 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 615
617 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 15 '10 Mar 16 '10 0 days NA NA 611,96
618 0% Installation of Fiber Patch Panel 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 617,616
619 0% Installation & Configuration of Switches 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 613,617
620 0% Installation of UTP & Fiber Patch cords 1 day Mar 16 '10 Mar 16 '10 0 days NA NA 615,124
621 0% Installation of IP Telephones 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 620,617
622 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 618
623 0% Testing of Fiber Cables 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 622
624 0% Labeling Rack, Patch panels and Switches 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 619,613,615,618
625 0% Interfacing With Overall Network 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 624
626 0% Supervisor's Residence (4ea) 5 days Mar 16 '10 Mar 22 '10 0 days NA NA 213,610SS+2 days
627 0% Communication Room Ready 0 days Mar 16 '10 Mar 16 '10 0 days NA NA
628 0% Installation of Cable Ladders & Trays 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 124
629 0% Installation of Communication Racks 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 628SS,124
630 0% Installation Of Power Cabling & Grounding 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 629SS,124
631 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 630SS,124
632 0% Testing of UTP Cables 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 631
633 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 17 '10 Mar 18 '10 0 days NA NA 627,97634 0% Installation of Fiber Patch Panel 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 633,632
635 0% Installation & Configuration of Switches 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 629,633
636 0% Installation of UTP & Fiber Patch cords 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 631,124
637 0% Installation of IP Telephones 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 636,633
638 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 634
639 0% Testing of Fiber Cables 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 638
640 0% Labeling Rack, Patch panels and Switches 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 635,629,631,634
641 0% Interfacing With Overall Network 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 640
642 0% Management Residence Type 2 5 days Mar 16 '10 Mar 22 '10 0 days NA NA 214,626SS
643 0% Communication Room Ready 0 days Mar 16 '10 Mar 16 '10 0 days NA NA
644 0% Installation of Cable Ladders & Trays 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 124
645 0% Installation of Communication Racks 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 644SS,124
646 0% Installation Of Power Cabling & Grounding 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 645SS,124
647 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 17 '10 Mar 17 '10 0 days NA NA 646SS,124
648 0% Testing of UTP Cables 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 647
649 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 17 '10 Mar 18 '10 0 days NA NA 643,98650 0% Installation of Fiber Patch Panel 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 649,648
651 0% Installation & Configuration of Switches 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 645,649
652 0% Installation of UTP & Fiber Patch cords 1 day Mar 18 '10 Mar 18 '10 0 days NA NA 647,124
653 0% Installation of IP Telephones 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 652,649
654 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 650
655 0% Testing of Fiber Cables 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 654
656 0% Labeling Rack, Patch panels and Switches 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 651,645,647,650
657 0% Interfacing With Overall Network 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 656
658 0% Laundry / Warehouse 5 days Mar 18 '10 Mar 24 '10 0 days NA NA 215,642SS+2 days
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 14
7/29/2019 Appendix 11-Updated Schedule
15/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
659 0% Communication Room Ready 0 days Mar 18 '10 Mar 18 '10 0 days NA NA
660 0% Installation of Cable Ladders & Trays 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 124
661 0% Installation of Communication Racks 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 660SS,124
662 0% Installation Of Power Cabling & Grounding 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 661SS,124
663 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 662SS,124
664 0% Testing of UTP Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 663
665 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 20 '10 Mar 21 '10 0 days NA NA 659,99
666 0% Installation of Fiber Patch Panel 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 665,664
667 0% Installation & Configuration of Switches 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 661,665
668 0% Installation of UTP & Fiber Patch cords 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 663,124
669 0% Installation of IP Telephones 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 668,665
670 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 666
671 0% Testing of Fiber Cables 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 670
672 0% Labeling Rack, Patch panels and Switches 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 667,661,663,666
673 0% Interfacing With Overall Network 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 672
674 0% Workshop 5 days Mar 18 '10 Mar 24 '10 0 days NA NA 216,658SS
675 0% Communication Room Ready 0 days Mar 18 '10 Mar 18 '10 0 days NA NA
676 0% Installation of Cable Ladders & Trays 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 124
677 0% Installation of Communication Racks 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 676SS,124
678 0% Installation Of Power Cabling & Grounding 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 677SS,124
679 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 20 '10 Mar 20 '10 0 days NA NA 678SS,124
680 0% Testing of UTP Cables 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 679681 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 20 '10 Mar 21 '10 0 days NA NA 675,100
682 0% Installation of Fiber Patch Panel 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 681,680
683 0% Installation & Configuration of Switches 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 677,681
684 0% Installation of UTP & Fiber Patch cords 1 day Mar 21 '10 Mar 21 '10 0 days NA NA 679,124
685 0% Installation of IP Telephones 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 684,681
686 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 682
687 0% Testing of Fiber Cables 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 686
688 0% Labeling Rack, Patch panels and Switches 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 683,677,679,682
689 0% Interfacing With Overall Network 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 688
690 0% Central Common Area 5 days Mar 21 '10 Mar 27 '10 0 days NA NA 217,674SS+2 days
691 0% Communication Room Ready 0 days Mar 21 '10 Mar 21 '10 0 days NA NA
692 0% Installation of Cable Ladders & Trays 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 124
693 0% Installation of Communication Racks 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 692SS,124
694 0% Installation Of Power Cabling & Grounding 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 693SS,124
695 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 22 '10 Mar 22 '10 0 days NA NA 694SS,124
696 0% Testing of UTP Cables 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 695697 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 22 '10 Mar 23 '10 0 days NA NA 691,101
698 0% Installation of Fiber Patch Panel 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 697,696
699 0% Installation & Configuration of Switches 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 693,697
700 0% Installation of UTP & Fiber Patch cords 1 day Mar 23 '10 Mar 23 '10 0 days NA NA 695,124
701 0% Installation of IP Telephones 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 700,697
702 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 698
703 0% Testing of Fiber Cables 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 702
704 0% Labeling Rack, Patch panels and Switches 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 699,693,695,698
705 0% Interfacing With Overall Network 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 704
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 15
7/29/2019 Appendix 11-Updated Schedule
16/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
706 0% Dining Hall and Kitchen 5 days Mar 23 '10 Mar 29 '10 0 days NA NA 218,690SS+2 days
707 0% Communication Room Ready 0 days Mar 23 '10 Mar 23 '10 0 days NA NA
708 0% Installation of Cable Ladders & Trays 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 124
709 0% Installation of Communication Racks 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 708SS,124
710 0% Installation Of Power Cabling & Grounding 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 709SS,124
711 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 710SS,124
712 0% Testing of UTP Cables 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 711
713 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 24 '10 Mar 25 '10 0 days NA NA 707,102
714 0% Installation of Fiber Patch Panel 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 713,712
715 0% Installation & Configuration of Switches 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 709,713
716 0% Installation of UTP & Fiber Patch cords 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 711,124
717 0% Installation of IP Telephones 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 716,713
718 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 714
719 0% Testing of Fiber Cables 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 718
720 0% Labeling Rack, Patch panels and Switches 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 715,709,711,714
721 0% Interfacing With Overall Network 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 720
722 0% Club House 5 days Mar 23 '10 Mar 29 '10 0 days NA NA 219,706SS
723 0% Communication Room Ready 0 days Mar 23 '10 Mar 23 '10 0 days NA NA
724 0% Installation of Cable Ladders & Trays 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 124
725 0% Installation of Communication Racks 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 724SS,124
726 0% Installation Of Power Cabling & Grounding 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 725SS,124
727 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 726SS,124728 0% Testing of UTP Cables 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 727
729 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 24 '10 Mar 25 '10 0 days NA NA 723,103
730 0% Installation of Fiber Patch Panel 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 729,728
731 0% Installation & Configuration of Switches 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 725,729
732 0% Installation of UTP & Fiber Patch cords 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 727,124
733 0% Installation of IP Telephones 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 732,729
734 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 730
735 0% Testing of Fiber Cables 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 734
736 0% Labeling Rack, Patch panels and Switches 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 731,732,733
737 0% Interfacing With Overall Network 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 736
738 0% Mosque 5 days Mar 23 '10 Mar 29 '10 0 days NA NA 220,722SS
739 0% Communication Room Ready 0 days Mar 23 '10 Mar 23 '10 0 days NA NA
740 0% Installation of Cable Ladders & Trays 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 124
741 0% Installation of Communication Racks 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 740SS,124
742 0% Installation Of Power Cabling & Grounding 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 741SS,124
743 0% Installation & Termination of UTP Patch Panel & Face Pl 1 day Mar 24 '10 Mar 24 '10 0 days NA NA 742SS,124744 0% Testing of UTP Cables 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 743
745 0% Delivery from Warehouse to Building Communication Ro 2 days Mar 24 '10 Mar 25 '10 0 days NA NA 739,104
746 0% Installation of Fiber Patch Panel 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 745,744
747 0% Installation & Configuration of Switches 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 741,745
748 0% Installation of UTP & Fiber Patch cords 1 day Mar 25 '10 Mar 25 '10 0 days NA NA 743,124
749 0% Installation of IP Telephones 1 day Mar 27 '10 Mar 27 '10 0 days NA NA 748,745
750 0% Splicing Of Indoor/Outdoor Fiber Cables 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 746
751 0% Testing of Fiber Cables 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 750
752 0% Labeling Rack, Patch panels and Switches 1 day Mar 28 '10 Mar 28 '10 0 days NA NA 747,741,743,746
MA'ADEN PERMANENT COMMUNICATIONS PROJECT
AL-JALAMID
SBM Page 16
7/29/2019 Appendix 11-Updated Schedule
17/21
ID %Com lete
Task Name BaselineDuration
BaselineStart
BaselineFinish
ActualDuration
Actual Start Actual Finish Predecessors
753 0% Interfacing With Overall Network 1 day Mar 29 '10 Mar 29 '10 0 days NA NA 752
754 6% Wireless Communication 30 days Jan 28 '10 Mar 3 '10 2.4 days Jan 30 '10 NA 146
755 0% Installation of Equipment, Basestation 7 days Jan 28 '10 Feb 4 '10 0 days NA NA 110
756 0% Fixed and Vehicle Radio 8 days Feb 6 '10 Feb 14 '10 0 days NA NA 755
757 13% System Programming 15 days Feb 6 '10 Feb 22 '10 4.25 days Jan 30 '10 NA
758 0% System Programming 7 days Feb 6 '10 Feb 13 '10 0 days NA NA 756SS
759 100% Radio Programming 8 days Feb 14 '10 Feb 22 '10 1 day Jan 30 '10 Jan 30 '10 758
760 7% Communication Tower 30 days Jan 28 '10 Mar 3 '10 2.07 days Feb 13 '10 NA 110
761 100% Soil Testing, Foundation Work 10 days Jan 28 '10 Feb 8 '10 2 days Feb 13 '10 Feb 14 '10
762 0% Concrete Foundation Curing 12 days Feb 9 '10 Feb 22 '10 0 days NA NA 761
763 0% Installation of Tower 8 days Feb 23 '10 Mar 3 '10 0 days NA NA 762
764 0% Communication Cable Installation 5 days Feb 23 '10 Feb 28 '10 0 days NA NA 763SS
765 11% GSM Enhancement 66 days Nov 3 '09 Jan 24 '10 12.68 days Oct 24 '09 NA 114SS
766 100% Overall Site Survey 3 days Nov 3 '09 Nov 5 '09 44 days Oct 24 '09 Dec 19 '09
767 100% Initial Overall Site Survey 2 days Nov 3 '09 Nov 4 '09 2 days Oct 24 '09 Oct 25 '09 35FS+14 days
768 100% Signal Measurement 2 days Nov 3 '09 Nov 4 '09 2 days Oct 24 '09 Oct 25 '09 767SS
769 100% Survey Report 1 day Nov 5 '09 Nov 5 '09 1 day Dec 19 '09 Dec 19 '09 768
770 6% Industrial Buildings 36 days Dec 14 '09 Jan 24 '10 2.19 days Jan 30 '10 NA 146
771 10% Administration Building 36 days Dec 14 '09 Jan 24 '10 3.4 days Jan 30 '10 NA 190,114SS
772 100% Final Site Survey 1 day Dec 14 '09 Dec 14 '09 1 day Jan 30 '10 Jan 30 '10
773 0% Site Ready (Scaffoldings, Ladders, Structure) 2 days Dec 20 '09 Dec 21 '09 0 days NA NA 120
774 0% Passive DAS Installation 3 days Dec 22 '09 Dec 24 '09 0 days NA NA775 0% Cables 2 days Dec 22 '09 Dec 23 '09 0 days NA NA 122,773
776 0% Components (antennas, splitters, couplers) 2 days Dec 22 '09 Dec 23 '09 0 days NA NA 122,773
777 0% Cable Testing 1 day Dec 24 '09 Dec 24 '09 0 days NA NA 775
778 0% Active Installa