Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Embed Size (px)

Citation preview

Page 1: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Appeal of PRS ActionNPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes

Floyd Trefny

Texas Steel Companies

Page 2: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Appeal of PRS Action On October 20, 2011, PRS tabled NPRR351, Calculate and

Post Projected Non-Binding LMPs for the Next 15 Minutes, delaying action to Approve the NPRR Motion to table passed by a very narrow margin

PRS and WMS desire to hold workshops on the full scope of “look ahead SCED” prior to consideration of NPRR 351 First workshop now scheduled for December 5, 2011

NPRR 351 does not implement any functionality of “look ahead SCED” Posts “non-binding” projected LMPs on the MIS

TAC is requested to instruct PRS to either approve or reject NPRR 351 at their next scheduled meeting in November 2011 without further delay

Page 3: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

ERCOT Implementation of NPRR 351

ERCOT intends to implement NPRR 351 using program modules that could be used in the future to support a fully integrated “look ahead SCED”

Program modules would be built to produce “Non-Binding” LMPs as originally called for in NPRR 351

The ERCOT modified NPRR 351 would also add additional posting and information that could be used to study the ability of “look ahead SCED” to project future grid conditions

Will provide Base Point projections for up to an hour into the future via the MIS Certified Area

Page 4: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Proposed Scope Of Real-Time Dispatch (RTD)Summer 2012*

Current Production SCED

Real-Time Dispatch (RTD)

Current SCED Inputs

Additional “Look Ahead”Inputs

Binding MW Dispatch & Binding Prices for SCED interval T

Advisory MW Dispatch & Advisory Prices (LMP only) for SCED interval T+5, …T+60

ICCP & MIS

MIS

* - Slide from ERCOT presentation on Implementation of NPRR 351, October 12, 2011

Page 5: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Funding Approved for NPPR 351

At PRS, ERCOT stated, as part of the Impact Analysis discussion, that funding of NPRR 351 would come from the 2012 project budget already approved by the Board Implementation would build the modules for RT

Dispatch of “look ahead” SCED Initial capital cost of $690-$790k

An additional $290k over the original line item of $500k may be needed from the project budget

ERCOT estimates that it will take up to six months to implement

Page 6: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Urgency Is Needed Language of the NPPR is very broad and not

likely to be changed as a result of WMS and PRS Workshops Likely there will be many more workshops before any consensus

is built on the future features of ‘look ahead” SCED Holding up posting of prices pending detail development of Real

Time co-optimization of Ancillary Services, Real Time unit commitment, Outage anticipation, and other features is not needed to move forward

REPs who plan “time of use” residential products need assurances ERCOT will implement the non-binding postings for summer 2012

Page 7: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Urgency Is Needed (concluded)

Prospects for increasing the Market Offer Cap and/or adding floors to energy offers as part of the Resource Adequacy issues is likely However, without also giving the consumers the

opportunity to reject the prices by limiting consumption is patently unfair to consumers

ERCOT has on several occasions outlined the concepts of look ahead SCED at WMS ERCOT provided examples of look ahead RT Dispatch with

Ramp constraints

Page 8: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

TAC Action

ERCOT’s plan to implement “look ahead SCED” in phases is a good idea Big bang approaches usually bring surprises and unintended

consequences

Building a parallel calculation alongside the current 5 minute SCED, gives opportunity to compare operations scenarios and effects on prices with a “study” look ahead SCED ERCOT staff urged PRS to approve the NPRR as is

TAC should approve a motion to instruct PRS to either approve or reject NPRR 351 at their next scheduled meeting in November 2011

Page 9: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

TAC Motion

TAC encourages WMS and PRS to continue discussions with ERCOT on the details of the “look ahead” SCED through workshops, special meetings, or other means.

TAC instructs PRS to either approve or reject NPRR 351 at their next scheduled meeting on November 17, 2011 and report back to TAC at the December 1, 2011 TAC meeting.

Page 10: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Appendix

Page 11: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Protocol Language of NPRR 351

Page 12: Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies

Protocol Language of NPRR 351

6.5.7.3 Security Constrained Economic Dispatch(6) For each SCED process, in addition to the binding Base Points and LMPs,

ERCOT shall calculate a non-binding projection of the Base Points and Resource Node LMPs, Hub LMPs and Load Zone LMPs at a frequency of every five minutes for at least 15 minutes into the future based on the same inputs to the SCED process as described in this Section, except that the Resource’s HDL and LDL and the total generation requirement will be as estimated at future intervals. The Resource’s HDL and LDL will be calculated for each interval of the projection based on the ramp rate capability over the study period. ERCOT shall estimate the projected total generation requirement by calculating a Load forecast for the study period. ERCOT shall post the projected non-binding Base Points for each Resource for each interval study period on the MIS Certified Area and the projected non-binding LMPs for Resource Nodes, Hub LMPs and Load Zone LMPs on the MIS Public Area pursuant to Section 6.3.2, Activities for Real-Time Operations.