An Employer’s and Engineer’s Guide to the FIDIC Conditions of Contract, First Edition. Michael D. Robinson. © 2013 John Wiley & Sons, Ltd. Published 2013 by John Wiley & Sons, Ltd. Appendix G Appendix G Model Form for Submissions to the Engineer for Approval and/or Consent PROJECT Serial No. ENGINEER: (Name) CONTRACTOR: (Name) SUBMITTAL TO THE ENGINEER FOR APPROVAL/ CONSENT/ INFORMATION SUBJECT: Drawings/Method Statement/ Material Samples/ Test Results/ Plant Acquisition/ Q.A. Report/ Programmes/ Health and Safety (Identify One) TITLE: (Specify Title) DETAIL: Drawing No./ Document No./ Sample/ Other CLAUSE(S): ………………………………………………… REF No.: ………………………………………………… ATTACHMENTS: …………………………………………. …………………………………………. DISTRIBUTION: Submitted by ……………………..………… Re-submittal required …………………. Contractor Engineer Date: …………………………. Date: ……………………………….……. Re-submittal by ………………….……….. Approval/consent subject to Contractor corrections as noted …………………… Engineer OTHER: Approval/Consent ……………………... Engineer Date: …………………………………….. 160 Appendices

app7

Embed Size (px)

DESCRIPTION

Engineer

Citation preview

Page 1: app7

An Employer’s and Engineer’s Guide to the FIDIC Conditions of Contract, First Edition. Michael D. Robinson. © 2013 John Wiley & Sons, Ltd. Published 2013 by John Wiley & Sons, Ltd.

Appendix G

Appendix G Model Form for Submissions to the Engineer for Approval and/or Consent

PROJECT Serial No.

ENGINEER: (Name)

CONTRACTOR: (Name)

SUBMITTAL TO THE ENGINEER FOR APPROVAL/ CONSENT/ INFORMATION

SUBJECT: Drawings/Method Statement/ Material Samples/ Test Results/ Plant Acquisition/ Q.A. Report/ Programmes/ Health and Safety (Identify One)

TITLE: (Specify Title)

DETAIL: Drawing No./ Document No./ Sample/ Other

CLAUSE(S): …………………………………………………

REF No.: …………………………………………………

ATTACHMENTS: …………………………………………. ………………………………………….

DISTRIBUTION:

Submitted by ……………………..………… Re-submittal required ………………….Contractor Engineer

Date: …………………………. Date: ……………………………….…….

Re-submittal by ………………….……….. Approval/consent subject toContractor corrections as noted ……………………

Engineer

OTHER: Approval/Consent ……………………...Engineer

Date: ……………………………………..