Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
API Case Examples of the Evaluation of the EI VaporPathway Guidance
American Petroleum Institute
Vic Kremesec, Ph. D.Senior Technology Consultant
January 17, 2002
2
Purpose
> To Demonstrate the methodology and reasoning that APImembers will possibly use applying the Draft Guidance.
> To point out areas where we believe the Draft Guidance> Requires revision, e.g.,§ Table 2 and 3 screening criteria do not provide adequate
differentiation of sites; and§ Language that elicits a reasonable site specific analysis;
> Potential consequences of no revision, e.g.,§ Manpower and cost increases.
> To suggest revisions that would make the Screening Criteriain the Guidance able to identify sites those with biodegradablehydrocarbon vapor problems
3
Presentation Overview
> Focus is on Petroleum Hydrocarbons• Chlorinated Compounds are not considered.
> Three Cases will be presented:> Case 1: Immediate Response Required; Long
Term Monitoring Discussed?> Case 2: Indoor/Outdoor Air Sampling; Applicable
Targets and Table 2 Criteria?> Case 3: Soil Gas Measurements; Applicability of
Models and Figure 2 (Table 3) Criteria?
4
Case 1: Immediate Response Required
> Situation:> Likely source an underground line leak> Depth to Water (Product) is 2-3 ft> Soil: sand and fill> Unit Control Room with a subfloor above area of LNAPL
> EI Guidance Questions/Answers> Q1. Volatile Chemicals?
> Yes: gasoline constituents> Q2. Inhabited Building Nearby?
> Yes: Unit Control Room> Q3. Immediate Action Warranted?
> Yes: Odors, Fuel Seeping in sub-floor
5
Actions - Case 1: Immediate Response Required
> Completed Pathway> Immediate Actions:
> Groundwater depressed with a wellpoint system> Sub-floor sealed to eliminate seeping of product> Building air flow pattern altered to sweep subfloor and vent
to outside stack> Building Ventilation upgraded – air is refinery ambient air.> Groundwater depression ceased
> Q7. Monitoring> Insure building ventilation is operating> Check potential seepage> Spot checks with benzene air monitoring meter
6
Case 2: Indoor/Outdoor Air Measurements
> Situation (Work planned 1990, conducted 1991):> Historical leaks in tank farm 150 ft east of property
line> Pumping system near property line, 40 ft from
buildings has drawn product into the trough at afew points at the property line
> Offsite inhabited buildings> Soil: medium sand> No soil impacts above water table> Situation occurs along 4 city blocks
7
Case 2 Site Map
Biovent System
8
Case 2: Indoor/Outdoor Air Measurements, continued.
EI Guidance Questions/Answers> Q1. Volatile Chemicals?
> Yes: BTEX> Q2. Inhabited Building Nearby?
> Yes: Inhabited buildings 30 ft west> Q3. Immediate Action Warranted?
> No: No Odors, No wet basements, No short term safetyconcerns.
> Q4. Exceed Generic Tables?> Possibly?: GW below buildings < 5 ppb benzene (Detection
Limit); LNAPL within 40 ft. of a few buildings.> Potentially conflicting screening criteria
> Q5. Exceed scenario specific criteria?> Possibly?: sandy soil with DTW 5-15ft.
9
Case 2: Indoor/Outdoor Air Measurements, continued.
> Result: Yes, for the sake of further discussion: butCriteria are Overly Conservative> Biodegradation ignored> Indoor Benzene Target Values too conservative> 100x factor too conservative based on experience
with such low groundwater and soil concentrations.> Proceed to Q6. Site Specific Assessment
• Chose Indoor Air Monitoring because a 1991project (soil gas understanding limited) and wantedto address homeowners directly
10
Case 2: Indoor/Outdoor Air Measurements, continued.
> Air Sampling> Benzene was the targeted constituent.> Questionnaire and investigation to identify construction,
ventilation, and indoor sources> 353 sampling visits in 262 homes in winter and spring of
1991 by hygienists> Additional re-sampling in summer and fall and when
requested by occupant> Elevated concentrations generally easily associated with
indoor sources.> Mitigation of some indoor air sources (gas leaks, removal of
stored materials, etc).> Outdoor air samples collected at 5 locations over same
time periods.> Additional sampling conducted in homes along property line
about 4 yr later.
11
Case 2: Indoor/Outdoor Air Measurements, continued.
> Results> Risks associated with indoor air were essentially the same
as risks associated with outdoor air.> Applicable target level was ambient air.> Pathway Incomplete.
> Q7. Monitoring> Tests conducted over the course of a year and then a
resampling several years later indicate no increased risk.> Situation has improved - Pumping and venting have
recovered most of the product.> Thus, continued monitoring has not been performed.
12
Case 2: Indoor/Outdoor Air Measurements, continued.
> In-building testing was not simple:> Multiple samples taken over a year some of which exhibited
occasional high values often linked to indoor sources.> Evaluation required cooperation of resident and a skilled
hygienist.> Community interaction was handled well but could become quite
contentious.> Point is that screening criteria would not have eliminated this site.> The evaluation for Question 6 is likely quite complicated requiring
significant resources (both regulatory and industry) and will slow theEI process.
> Better screening criteria for petroleum hydrocarbons could avoidthis.
> Commitment needed to perform a reasonable site specific analysis
13
Case 3: Soil Gas Profile Measurements
> Situation> Historical leaks in refinery migrated offsite> Offsite inhabited buildings> Fuel constituents in GW> DTW about 20 ft> Soil – wind-blown,silty-sand 5-8 ft; sand and
alluvial sand with gravel below that.
14
Case 3 Site Map With Benzene GW (ppb) And Soil Gas Concentration
<40 ppbvBenzenein Vapor
<200
790 ppb<1
<1
0.5 ppb is the Groundwater , and 40 ppbv is Soil Gas Screening Criteria in Table 2
~400 ft
15
Case 3: Soil Gas Profile Measurements, continued
EI Guidance Questions/Answers> Q1. Volatile Chemicals?
> Yes: BTEX> Q2. Inhabited Building Nearby?
> Yes:> Q3. Immediate Action Warranted?
> No: No Odors, No wet basements, No short term safetyconcerns
> Q4. Exceed Generic Tables?> Yes: GW below occupied buildings exceeds 0.5 ppb
benzene.> Q5. Exceed scenario specific criteria?
> Yes: sandy soil, DTW ~15-20ft, but Figure 2 (Table 3)correction only increases GW to ~ 5.6 ppb.
16
Case 3: Soil Gas Profile Measurements, continued
> Result: Yes, but Criteria are Overly Conservative> Depth and Soil Type do not increase Attenuation
Factor sufficiently above 100x factor.> Biodegradation ignored.
> Proceed to Q6. Site Specific Assessment - Chose Soil Gas Sampling
17
Case 3: Soil Gas Profiles indicate that Benzene Attenuates By a factor of1000, Xylene by a Factor of 100, and Trimethylbenzene by a factor of 10.
These Attenuation Factors would be Multiplied bya Building Attenuation Factor of 1000
Profiles Obtained Near 790 ppb GW well
-16
-14
-12
-10
-8
-6
-4
-2
0
0.0001 0.001 0.01 0.1 1
Normalized Soil Gas Concentration
1,2,4 TrimethylBenzene
Benzene
Xylenes
1,2,4 TMB Predicted
Benzene Predicted
Xylenes Predicted
Predicted Soil Gas Profile Includesthe Attenuation Rate in the Model
18
Case 3: Soil Gas Profile - Results
> Profiles over 2 sampling events indicate an incompletepathway
> No further vapor monitoring performed
> This was not a simple field test and analysis:> Multiple samples were taken which exhibited occasional
variability approaching ~10x.> Evaluation required a skilled individual who could interpret
the variability, fit a model, and write the report.
> Point is that Question 6 could likely become quite complicatedrequiring significant resources (both regulatory and industry)and slow the EI process.
> Better screening criteria for petroleum hydrocarbons couldavoid this.
19
Draft Guidance Screening Criteria for FuelHydrocarbons are Overly Conservative.
> Criteria in Table 2 were calculated:> With a conservative model, that does not include
biodegradation, and generally does not agree with fieldexperience.
> Using overly conservative target concentrations for indoorair
> Using conservative model parameters,> For fuel hydrocarbons sites, the criteria in Tables 2 & 3 will not
differentiate between sites making Q4 and Q5 generallyIrrelevant.
> Most sites will go from Q3 to Q6 almost immediately.> Guidance biased toward detailed site specific analysis
20
Imposed Burdens of Conservative Screening Criteria
> Screening criteria will likely require additionalgroundwater and/or soil gas delineation
> 100 ft distance will increase number of inhabitedbuildings to be evaluated.
> Site specific analysis to determine attenuation factorwill put a significant burden on the resources ofindustry for assessment, analysis, and reporting; andregulatory bodies for review.
> Unnecessary site specific analysis will slow the EIprocess.
> Overemphasis on additional offsite analysis couldunnecessarily alarm neighboring communities.
21
Revision Needed For Biodegradable Species
> Language eliciting a reasonable site specific analysis for theevaluation in Questions 4 through 6.
> We need screening criteria which can differentiate which sitesactually require more site specific analysis.
> Whether these are the criteria:> Proposed by Connor et. al. (2001), or> New ones calculated with realistic values and a quantitative
model.> WORK IS NEEDED
> Application of the 100 ft extended distance criteria needs to bebetter explained
> Guidance on potential conflicts between multiple screeningcriteria is needed.