45
‘ONSITE WASTEWATER MANAGEMENT REPORTFor: 125 Eltons Rd, Silverdale, NSW CLIENT: Rosano REFERENCE: REF‐16‐3310‐A‐2 DATE: 4 July 2016

‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

   

   

   

‘ON‐SITE WASTEWATER MANAGEMENT REPORT’    

For: 

 125 Eltons Rd, Silverdale, NSW 

              

CLIENT:    Rosano  REFERENCE:    REF‐16‐3310‐A‐2  DATE:        4 July 2016            

Page 2: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

2

 

 

         

   

 

Rhys Allan Starkey          Simon Doberer 

B.Eng (Adv)(Civil)(Hons)        B. Sc (Env.)  

Civil Engineer            Environmental Team Leader               

ENVIROTECH PTY. LTD.         ENVIROTECH PTY. LTD. 

 

 

COPYRIGHT © 2016 

The information, including the intellectual property contained in this document is confidential and 

proprietary to ENVIROTECH PTY. LTD. It may be used only by the person, company or organisation to 

whom it is provided for the stated purpose for which it is provided.  It must not be given to any 

other person, company or organisation without the prior written approval of the Director of 

ENVIROTECH PTY. LTD. ENVIROTECH PTY. LTD. reserves all legal rights and remedies in relation to 

any infringement of its rights in respect of confidential information. 

 

 

Document Management 

Version  Date  Author  Reviewed  Author 

A‐1  16/06/2016  RAS  16/06/2016  SD 

A‐2  04/07/2016  RAS  04/07/2016  SD 

         

  

               

Page 3: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

3

   

TABLE OF CONTENTS  

INTRODUCTION ....................................................................................................................... 4 

Objective ......................................................................................................................... 4 Scope of Works ............................................................................................................... 4 

DESKTOP INFORMATION ........................................................................................................... 5 

SITE ASSESSMENT .................................................................................................................... 7 

Site Assessment Discussion .......................................................................................... 10 

SOIL ASSESSMENT .................................................................................................................. 11 

Soil Assessment Discussion ........................................................................................... 13 

ON‐SITE WASTEWATER MANAGEMENT SYSTEM DESIGN .............................................................. 14 

Site Modifications Recommended ................................................................................ 17 

RECOMMENDATIONS .............................................................................................................. 18 

LIMITATIONS ............................................................................................................................ 20 

………………………………………………………………………………………… 

 

 

Appendix A:  Site Plans 

Appendix C:  Nitrogen & Phosphorus Balance 

Appendix D:  Water Balance     

Appendix E:  Irrigation Descriptions & Standard Drawings 

Appendix F:  Operation & Maintenance Guidelines 

Appendix G:  Water Conservation 

Appendix H:  Beds & Trenches Description & Standard Drawings 

Appendix O:  ETA Bed Standard Drawing 

Appendix T:  Pressure Dosed Beds 

 

 

       

Page 4: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

4

  

INTRODUCTION  

EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater 

management study’ at the above mentioned site address. This report presents the results of 

that study.  

 

Objective 

The objective of the ‘onsite wastewater management study’ is to investigate the relevant 

site, soil, public health and economic factors that can impact on the selection, location and 

design of an on‐site wastewater management system to determine: 

Whether or not the site is suitable for an on‐site wastewater management system 

The best practical on‐site wastewater management system for the specific site and 

proposed development.  

 

This study has been prepared in accordance with: 

Australian Standard AS1547: 2012”On‐site Domestic Wastewater Management” 

Dept. Local Government 1998, On‐site Sewage Management for Single Households, 

Relevant Council Development Control Policies 

 

Scope of Works 

The scope of works undertaken for this site evaluation included: 

- Desktop Study:   An initial investigation to collate relevant information about the site and 

proposed development prior to the site inspection. 

- Site Assessment: An on‐site inspection by an engineer or scientist to record land surface, site 

features, identify potential site constraints and define the most appropriate land application 

area. 

- Soil Assessment: A subsoil investigation by an engineer or scientist to record the soil profile 

and relevant soil properties within the land application area to determine potential soil 

limitations. 

- System Design:  An evaluation of the expected wastewater flowrate, site and soil limitations 

to select, size and position a waste treatment unit and land application system that will 

provide the best practical option. 

- Operation & Maintenance / Construction & Installation Guidelines 

Page 5: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

5

 

 

DESKTOP INFORMATION 

 

Address  125 Eltons Road, SILVERDALE, NSW 

Council  Wollondilly Shire Council 

Proposed Development 

New Wastewater System for: 

Existing Residence 

Existing & Proposed Kennels 

Intended Water Supply Source  Tank water 

Equivalent Population 

Existing Residence ‐ Up to 8 People (4 bedroom 

proposed dwelling) 

Existing Kennels: 

Kennel #2 ‐ 4 Enclosures (Cats) (23.6 m2) 

Proposed Kennel 

Kennel #7 ‐ 6 Enclosures (Dogs) (162.8 m2) 

 

Design Wastewater Allowance  Existing Residence ‐ 145 L / Person / Day 

Proposed & Existing Kennels ‐ 30.3 L / min* 

Design Wastewater Flowrate  Existing Residence – 1,160 L / Day 

Proposed & Existing Kennels ‐ 606 L / Day* 

Rainfall Station  067108 – Badgerys Creek AWS 

Evaporation Station  067068– Badgerys Creek McMasters F.Stn 

 

 

 

 

Page 6: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

6

*Important Note: The operating procedure of the proposed & existing kennels, as 

indicated by the owners, includes the following onsite wastewater procedures: 

 

Twice‐Daily collection of feces, old bones & uneaten food with storage to lined 

and sealed containers prior to disposal via council kerb‐side garbage collection 

Daily mop‐out of kennels 

Daily Wash‐Out of Paved Kennels 

 

Design wastewater allowance was determined in accordance with Hessler and Lehner 

(2009) holding room wash‐down system requirements. 30.3 L/min at 550 kPa is determined 

as the maximum potential flow rate and pressure at which feces will not become 

aerosolised for large animals (dogs and pigs).  

 

Maximum wash‐down time for all proposed caged areas were indicated to take a 

cumulative time of 20 minutes. A daily wash‐down frequency was accommodated in the 

calculation. The total daily wastewater flow rate thereby being 606 L / day.  

 

Hessler, J & Lehner, N 2009, ‘Planning and Designing Research Animal Facilities’, American College of Laboratory

Animal Medicine, 1st Ed, Academic Press, pp. 433‐434, < http://www.sciencedirect.com/science/book/9780123695178>. 

 

   

Page 7: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

7

SITE ASSESSMENT  

This following relevant site features were recorded and given a rating in terms of their 

potential constraints to onsite wastewater management. The three ratings are minor 

limitation, moderate limitation or major limitation. Only those site features that are rated 

as being a major limitation to onsite wastewater management are further discussed in the 

‘Site Assessment Discussion’.  

 

Landform Description  

The landform is described by first dividing an area into landform elements of approximately 

40‐m diameter. A description of these elements is then provided. These landform elements 

define the boundaries of this site assessment.  

 

Element  Slope Class  Morphological Type  Relative Inclination  Instability Risk 

1 Very Gently 

Inclined Simple Slope  Linear  Planar  Very Low 

 

Vegetation 

The vegetation is described by dividing the study area into vegetation elements. Each 

vegetation element has a unique set of properties.  

 

Element  Growth Form  Height Class  Cover Class Structural 

Formation 

A  Grass  Low  Dense  Closed Grassland 

 

Element  Exposure Existing Erosion 

State                 Type 

Landform 

Element (s) 

A  Excellent  Stabilised  ‐  1 

 

 

 

 

Page 8: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

8

 

Overland Flow  

Run‐on and run‐off potential is largely determined by slope, surface cover and soil 

infiltration rate.  

 

Landform element.  Run‐on  Run‐off  Soil ‐ Water Status 

1  Slow  Slow  Dry 

 

Site & Soil Disturbance 

The site assessor noted the following disturbance within the effluent application envelope:  

 Description:    

 

 

 

Rocky Outcrops 

The site assessor noted the following rocky‐outcrops within the effluent application 

envelope: 

 Description:   ‐ 

 

 

 

 

 

 

 

 

 

 

 

 

Other 

None 

Page 9: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

9

 

Setbacks 

The following setbacks from the effluent application area have been proposed after 

considering Appendix R of AS1547:2012 ‘On‐site Domestic Wastewater Management’. This 

Appendix provides a recent guide on how to determine setbacks distances based on site‐

specific constraints identified in this site assessment.  

 

The constraint factors associated with each site feature (refer to Table R1) have been 

qualitatively assessed using Table R2 and a suitable setback then chosen from within the 

range stated in Table R1.  

 

Primary Treatment with Subsoil Disposal 

Site Feature  Setback Range  Constraint Factors  Proposed Setback 

Property Boundaries 6 ‐ 12 m  LOW 

6 m (downslope) 

12 m (upslope) 

Swimming Pools, Driveways 

& Buildings 3 ‐ 6 m  LOW 

3 m (downslope) 

6 m (upslope) 

Permanent Surface Waters  100 m  LOW  > 100 m 

Other Waters  40 m  LOW  40 m 

 

Secondary Treatment with Surface Irrigation 

Site Feature  Setback Range  Constraint Factors  Proposed Setback 

Dwellings  15 m   LOW  15 m 

Property Boundaries & 

Driveways 

3 ‐ 6 m LOW 

3 m (downslope) 

6 m (upslope) 

Swimming Pools  6 m  LOW  N/A 

Paths & Walkways  3 m  LOW  3 m 

Permanent Surface Waters  100 m  LOW  > 100 m 

Other Waters  40 m  LOW  40 m 

Neighbouring Orchard 

(West) 20 m  LOW  >27 m 

 

Page 10: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

10

Site Assessment Discussion 

  

A range of site features that can commonly place limitations on on‐site wastewater 

management have been assessed and classified. All features have been shown to place no 

major limitations to on‐site wastewater management. 

 

   

Page 11: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

11

SOIL ASSESSMENT  

The location of the borehole excavated during the site inspection is shown on the attached 

site plan. Physical and chemical soil properties were recorded on a soil profile log (see 

attached). On each property two boreholes are performed, the first analyses soil features 

listed below, and the second serves a confirmatory borehole. If soil properties found in the 

two boreholes on site differ, then both samples are taken for analysis.  

  

The following properties were recorded for each soil horizon: 

   ‐ Horizon depth and type  ‐ Mottling      ‐ Colour                       

‐ Structural stability                   ‐ Groundwater depth     ‐ Bedrock depth  

‐ Texture                                     ‐ pH        ‐ Phosphorus Sorption 

‐ Electrical Conductivity   ‐ Coarse Fragments  

 

Physical Properties  

In summary, the soil profile is described below:  

Soil Horizon  Depth  Colour  Mottles  Coarse 

Fragments % 

Texture  Structure 

A  200  Brown  ‐  < 10   Loam  Moderate 

B1  900  Brown  Dark Brown, 

Black 

< 10  Clay loam  High 

B2  1200  Grey  Light Brown  < 10  Clay Loam   Moderate 

 

Excavation terminated at:  1200 mm        

Reason:       Refusal at 1200 mm  

Bedrock Depth:    > 1200 mm  

Water Table Depth:    > 1200 mm  

Surface Condition:    Firm  

 

  

Figure 1. –  Bore Hole 1: Soil Sample   

Page 12: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

12

 

Chemical Properties 

 

Soil samples were collected from each major soil horizon and the relevant chemical 

properties are presented below:  

 

Borehole 1 

Horizon  PH  ECe 

(μS/cm) 

A  6.65  228 

B1  6.02  335.4 

B2  5.86  129 

                                                                         (Hanna Instruments, HI 98129, Ref 29713) 

 

Phosphorus Adsorption Capacity (kg / ha):   8,393 

 

Erodability / Erosion Hazard 

 

Soil erodability is the susceptibility of the topsoil to detachment and transport of soil 

particles. It is a characteristic of the soil surface and varies with time, soil / water status and 

land use. Soil erodability classification is stated as low, moderate or high.  

 

Erosion hazard is the susceptibility of an area of land to the prevailing agents of erosion. It is 

a function of climate, soil erodability, vegetation cover and topography. 

 

  Borehole 1 

Erodability  Low 

Erosion Hazard  Slight 

 

Page 13: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

13

Salinity & Drainage 

 

Salinity is the concentration of water‐soluble salts contained within a soil. Increases in soil 

salinity (i.e. salinisation) can occur as a result of irrigation water raising the level of an 

already saline groundwater. Management of potential salinisation problems involve 

ensuring that salts introduced to the soil surface are removed (by crop uptake or subsoil 

leaching) and by ensuring the irrigation area provides adequate subsoil drainage to prevent 

raising of saline groundwaters into root zones.  

 

Drainage is a statement describing the site and soil drainage that is likely to occur most of 

the year. It is influenced by soil permeability, water source, landform description, 

evapotranspiration, slope gradient and slope length. 

 

The drainage of this site should be adequate for the leaching of salts and ensure the 

groundwater level does not reach the root zone.  

 

A major adverse effect of high soil salinity is the restrictive effects on plant growth. 

However, for this site the soil salinity levels (as indicated by the electrical conductivity 

values) are low enough that the adverse effects on plant growth will be minimal.   

   

 

Soil Assessment Discussion 

 

A range of soil properties that commonly place limitations on on‐site wastewater 

management have been assessed and classified. In accordance with the Environmental and 

Health Protection Guidelines all soil properties have been shown to present no major 

limitations to on‐site wastewater management. 

  

Page 14: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

14

ON‐SITE WASTEWATER MANAGEMENT SYSTEM DESIGN  

The design process adopted here involves an evaluation of the expected wastewater flow, 

site limitations and soil limitations, to select, size and position a waste treatment unit and 

land application system that will provide the best practical option.  

 

Existing Residence  

Wastewater Treatment:   

Following certification of the existing wastewater system, this report proposes continued 

use of the existing septic tank & conventional absorption trenches. In the situation that the 

existing system fails, Envirotech recommends wastewater treatment using a NSW Health 

accredited (or equivalent) Aerated Wastewater Treatment System (AWTS) as it will produce 

a high quality effluent produced suitable for irrigation purposes 

 

Effluent Application:    

This report proposes that future effluent application be via a low‐pressure irrigation system.  

EnviroTech recommends all of the following methods of irrigation (presented below as 

numbered options) are suitable for installation on this site.  

 

1. Surface Movable 

2. Fixed / Semi‐fixed Surface Spray Irrigation 

3. Surface Drip Irrigation 

4. Subsurface Drip Irrigation 

 

Any irrigation system must be installed within the proposed irrigation shown on the site 

plan or within the ‘available irrigation envelope’ (if an envelope is shown on your site plan).  

 

The client shall choose whichever of the following irrigation options best suits their needs. 

Before choosing which type of irrigation to install, the client must first consider: 

   + Appendix E (Irrigation Descriptions & Standard Drawings)  

 + Appendix F (Operation & Maintenance Guidelines). 

 

If Council prefers the client install one particular method of irrigation (i.e. only one of our 

recommended options be available to the client) then consultation between client and 

Council may be required.  

Page 15: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

15

 

Effluent Application Area Sizing  

 

A monthly nutrient balance and water balance were modeled to determine the minimum 

land application area with no wet weather storage requirements. The results were as 

follows: 

 

Proposed Design Irrigation Rate (DIR):  3.0 mm / day 

 

Minimum Irrigation Areas: 

Water 

Balance 

Nitrogen Balance 

(Spray Irrigated on 

Slashed Grass) 

Nitrogen Balance 

(Subsurface Irrigation 

Under Mown Lawn) 

Phosphorus Balance  

(Spray Irrigated on Slashed 

Grass) 

Phosphorus Balance 

(Subsurface Irrigation Under 

Mown Lawn 

462 m2  928 m2  352 m2  633 m2  491 m2 

 Note: Minimum effluent disposal area for surface irrigation in Wollondilly LGA = 1500 m2 

    

Page 16: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

16

 

Existing & Proposed Kennels  

Wastewater Treatment:   

Treatment System:   Conventional Septic Tank with Dosing Pump 

 

This report proposes installation of a septic tank to treat the liquid waste produced by the 

kennels. The low cost primary treatment method is appropriate for canine and feline waste 

processing and does not pose any major site or soil limitations. A pump is required to 

distribute the effluent to the appropriate effluent application area. 

 

Recommended Minimum Septic Tank Capacity: 3000 L (Value from AS1547)  

Notes:  

Septic tank capacity calculated in accordance with AS1547: 2012.  

The septic tank must be designed and constructed in accordance with AS1546.1: 

1998.   

 

Land Application System: Pressure Dosed Evapotranspiration Absorption (ETA) Beds  

 

Reasons 

o Suitable for canine & feline effluent disposal 

o Gently to moderately inclined land application area 

o Suitable for clay‐loam soil types 

o Appropriate application area located up‐hill from proposed septic tank 

o Sufficient soil depth beneath ETA Beds 

o Adequate space available with sufficient buffer distances 

 

ETA Bed Sizing Calculations: 

 

Design daily flow rate     = 606 L / Day  

Design Loading Rate in mm/d   = 15 mm / Day (Value obtained from AS1547) 

Total bed area required    = 40.4 m2 

Number of beds required    = 1 

Required Bed Width      = 4 m 

Required Bed Length      = 10.1 m 

 

Please refer to Appendix H for further detailed irrigation descriptions and standard 

drawings. 

Page 17: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

17

  

Site Modifications Recommended   Existing & Proposed Kennel Modifications – Wastewater / Wash‐Down Capture  Infrastructure is to be installed to ensure all wash‐down and wastewater from kennel 

facilities is captured and delivered to the wastewater treatment system. This includes: 

 

Construction of kennel walls and floors with impermeable materials to ensure 

containment of wash‐down / wastewater 

Grading of kennel floors to ensure wash‐down / wastewater is delivered to 

designated capture points 

 Conveyed liquid waste (e.g. by open concrete channels) is to pass through a grease 

/ silt trap before entering the treatment tank to remove solids and animal hair (it is 

preferable that these measures area installed at/in‐line with the collection pits at 

each kennel row) 

All solid wastes including animal feces, old bones & uneaten food is to be collected 

and disposed of as per site Operation Guidelines before kennels are washed down 

 Furthermore, stormwater from kennel roofs and surface flows are to be collected and/or 

diverted away from the wastewater capture, collection and dispersal systems. These 

measures are to be established in a way that meets council stormwater guidelines and does 

not result in soil erosion. 

  

 

Page 18: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

18

RECOMMENDATIONS  

Existing Residence  

- Continued use of the existing septic tank and conventional absorption trench to service 

the existing residence. 

 

If future considerations require the installation of a new wastewater treatment system (e.g. 

due to current system failure), the following is advised: 

 

-  Installation of a NSW Health Accredited Aerated Wastewater Treatment System (AWTS) 

with the capacity to treat the design flowrate (1,160 L/d) to a secondary treatment 

standard with disinfection. 

 

- Installation of a low‐pressure effluent irrigation system. This area shall be designated for 

effluent application only. 

 

- EnviroTech recommends all of the following irrigation types are suitable for installation 

on this site: 

Irrigation System Type  Minimum area Required 

Surface Movable Irrigation  1500 m2 

Semi‐Fixed / Fixed Surface Spray   1500 m2 

Subsurface Drip Irrigation  491 m2 

 

- Before choosing which type of irrigation system to install, the client must consider: 

    + Appendix E (Irrigation Descriptions & Standard Drawings)  

    + Appendix F (Operation & Maintenance Guidelines). 

 

- Once the client’s septic application has been approved, the client shall choose 

whichever of the above options best suits their needs in consultation with Council. 

 

- Further site‐specific irrigation details (for example, accurate sprinkler and distribution 

line positioning within the proposed irrigation area), if required, may be determined in 

consultation with your plumber / irrigation installer. 

 

Page 19: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

19

- Each irrigation system must be installed within the proposed land application area 

shown on the site plan or within the ‘available irrigation envelope’ (if an envelope is 

shown on your site plan).  

 

Existing & Proposed Kennels 

 - Installation of a conventional septic tank designed and constructed in accordance with 

AS1546.1: 1998 with a minimum capacity of 3000 L. This includes installation of a 

dosing pump to distribute the effluent to the application location. 

 

- Construction of a pressure dosed Evapotranspiration Absorption bed (10.1 m × 4 m) in 

accordance with AS1547:2012 which shall cover a minimum designed area of 40.4 m2. 

 

- Installation of the kennel amendments advised in the “Site Modification 

Recommendations” to safely and hygienically convey the liquid waste to the designed 

treatment node.  

 

- Please refer to Appendix H for further detailed beds and trenches descriptions and 

standard drawings for guidance during construction and installation. 

 

- Each application system must be installed within the proposed land application area 

shown on the site plan or within the ‘available effluent disposal envelope’ (if an 

envelope is shown on your site plan).  

 

- The ETA beds shall be maintained in accordance with the attached “Operation and 

Maintenance Guidelines” (Appendix F).   

 

- The setbacks between the proposed land application area and site features should be 

adhered to.  

   

Page 20: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

20

 

LIMITATIONS  

Envirotech Pty Ltd has prepared this report for the exclusive use of our client, for this 

project only and for the purpose(s) described in the report. It should not be used for other 

projects or by a third party. Any party so relying upon this report beyond its exclusive use 

and purpose as stated above, and without the express written consent of Envirotech, does 

so entirely at its own risk and without recourse to Envirotech for any loss or damage.  

 

In preparing this report Envirotech has necessarily relied upon information provided by the 

client and/or their Agents. The results provided in the report are indicative of the sub‐

surface conditions only at the specific sampling or testing locations, and then only to the 

depths investigated and at the time the work was carried out. Under no circumstances can 

it be considered that these findings represent the actual state of the site at all points. 

Subsurface conditions can change abruptly due to variable geological processes and also as 

a result of anthropogenic influences. Such changes may occur after Envirotech’s field testing 

has been completed. 

 

Envirotech's advice is based upon the conditions encountered during this investigation. The 

accuracy of the advice provided by Envirotech in this report may be limited by undetected 

variations in ground conditions between sampling locations. The advice may also be limited 

by budget constraints imposed by others or by site accessibility. 

 

Should any site conditions be encountered during construction that vary significantly from 

those outlined and discussed in this report, Envirotech should be advised and a plan 

outlining the need for potential action developed accordingly. 

 

This report must be read in conjunction with all of the attached notes and should be kept in 

its entirety without separation of individual pages or sections. Envirotech cannot be held 

responsible for interpretations or conclusions made by others unless they are supported by 

an expressed statement, interpretation, outcome or conclusion given in this report. 

 

Page 21: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

21

This report, or sections from this report, should not be used as part of a specification for a 

project, without review and agreement by Envirotech. This is because this report has been 

written as advice and opinion rather that instructions for construction.  

 

                                       

 QDO 035‐6                                                                                Release Date: 19/04/2016 AWTS & Irrigation      Approved By: Daniel Mathew            

Page 22: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’
Page 23: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

NUTRIENT BALANCES

1) Nitrogen Balance

- Design Wastewater Flowrate (L/d): 1160

- Effluent nitrogen concentration (mg/L)1: 20

a) Surface Irrigation, perennial pasture:- Critical Total Nitrogen Loading Rate: (mg/m2/d)2: 25

- Minimum irrigation area1 (m2) 928

b) Subsurface Irrigaiton, mown lawn, clippings removed:- Critical Total Nitrogen Loading Rate: (mg/m2/d)3: 66

- Minimum irrigation area2 (m2) 352

2) Phosphorus Balance

- Design Wastewater Flowrate (L/d): 1160

- Effluent Phosphorus Concentration: (mg/L)1 10

- Phosphorus Sorption Capacity (kg/Ha) 8393

a) Surface Irrigation, perennial pasture:- Critical loading rate (mg/m2/day)2 3

Padsorbed (kg/Ha): 387

Padsorbed (kg/m2): 0.04

Puptake (slashed grass) (mg/m2)2 54750

Puptake (slashed grass) (kg/m2) 0.05475

Pgenerated (kg) 212

Irrigation area required (Pgenerated / (Padsorbed + Puptake):

- Minimum irrigation area1 (m2): 633

b) Subsurface Irrigaiton, mown lawn, clippings removed:- Critical loading rate (mg/m2/day)4 8.3

Padsorbed (kg/Ha): 2798

Padsorbed (kg/m2): 0.28

Puptake (mown grass) (mg/m2) 151475

Puptake (mown grass) (kg/m2) 0.1515

Pgenerated (kg) 212

Irrigation area required (Pgenerated / (Padsorbed + Puptake):

- Minimum irrigation area2 (m2) : 491

1: Typical AWTS Effluent Nutrient Concentrations2: Appendix 6, 'On-site Sewage Management for Single Households', (DLG, 1998)3: (240 kg/Ha/year), Appendix 1 'Designing & Installing On-site Wastewater Systems' (SCA, 2013)4: (30 kg/Ha/year), Appendix 1 'Designing & Installing On-site Wastewater Systems' (SCA, 2013)

Page 24: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

Appendix D: WATER BALANCE / WET-WEATHER STORAGE REQUIREMENT-Nominated Area Method

Parameter Symbol Formula Units Value Weather Station: Precipitation: 067108 – Badgerys Creek AWS

Design Wastewater Flow (Q) L / day 1160 Evaporation: 067068 – Badgerys Creek McMasters F.StnDesign Soil Percolation Rate2 (SPR) mm / month 90

Nominated Irrigation Area1 (A) m2 462

Parameter Symbol Formula Units Jan Feb Mar Apr May Jun July Aug Sep Oct Nov DecDays in Month (D) days 31 28 31 30 31 30 31 31 30 31 30 31

Median Precipitation (MP) mm/month 88.0 85.6 56.4 31.2 28.4 38.1 20.0 20.1 27.9 42.9 58.8 47.6

Mean daily Evaporation (E) mm/day 5.9 5.4 4.4 3.3 2.1 1.7 1.9 2.9 4.0 4.6 5.6 6.5

Crop Factor (C) 0.7 0.7 0.7 0.6 0.5 0.5 0.4 0.5 0.6 0.7 0.7 0.7

Evapotranspiration (ET) (E x C) mm/month 128.0 105.8 95.5 59.4 32.6 23.0 23.6 40.5 66.0 92.7 117.6 141.1

Inputs Symbol Formula Units Jan Feb Mar Apr May Jun July Aug Sep Oct Nov DecMedian Precipitation (MP) mm/month 88.0 85.6 56.4 31.2 28.4 38.1 20.0 20.1 27.9 42.9 58.8 47.6

Effluent Irrigation (EI) (Q x D / A) mm/month 77.8 70.3 77.8 75.3 77.8 75.3 77.8 77.8 75.3 77.8 75.3 77.8

Inputs (I) (EI+MP) mm/month 165.8 155.9 134.2 106.5 106.2 113.4 97.8 97.9 103.2 120.7 134.1 125.4

Outputs Symbol Formula Units Jan Feb Mar Apr May Jun July Aug Sep Oct Nov DecEvapotranspiration (ET) (E x C) mm/month 128 106 95 59 33 23 24 40 66 93 118 141

Design Soil Percolation Rate2 (SPR) mm / month 90 90 90 90 90 90 90 90 90 90 90 90

Outputs (O) (ET+SPR) mm / month 218 196 185 149 123 113 114 130 156 183 208 231

Storage (I - O) -52 -40 -51 -43 -16 0 -16 -33 -53 -62 -73 -106

Cumulative Storage (M) 0 0 0 0 0 0 0 0 0 0 0 0

Storage Requirement (V) Largest M mm 0(VxA) / 1000 m3 0

1: Nominated Irrigation Area to be greater than or equal to the minimum irrigation area determined in the nutrient balances

2: Based on AS1547:2012 Design Irrigation Rates x 4.3 weeks / month

QDO 036‐0                                                                                 Release Date: 10/11/2014

Balances Approved By: Daniel Mathew

Page 25: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

APPENDIX E

Irrigation Descriptions & Standard Drawings

1. Surface Irrigation

1.1) Fixed Surface Spray Irrigation

A fixed spray irrigation system involves fixed and buried distribution lines, with a series of

fixed sprinklers. Generally, pop-ups are the preferred type of sprinkler as they allow the area

to be easily mowed without the risk of damaging sprinkler heads. The sprinklers should be

spaced so as to evenly service the entire irrigation area. They should produce a coarse droplet

to avoid spray drift, and have a plume height less than 400mm and a plume diameter of

approximately 4m.

1.2) Semi-fixed Spray Irrigation

A semi-fixed surface spray irrigation system is recommended on preference to a simple 50m

length of hose. This sort of system partially fixes the sprinklers to the irrigation are while still

preventing effluent application outside of allowable areas. A typical set up might contain the

following:

- A fixed and buried main distribution line(s) to transfer effluent from the tanks to

the nominate irrigation fields.

- A series of take-off points (stand-pipes) spaced evenly within the irrigation fields.

These take-off points may be quick release valves or any other type of vale as

desired by the owners, or recommended by an irrigation expert. At least two take-

off points should be provided per field and should be spaced at least 10m apart.

- A minimum of two flexible, moveable irrigation lines per field each having no less

than three sprinklers on each line. These lines will be connected to the take-off

points on the main line and will be easily detached and moved between the

different take-off points.

Page 26: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

In total the irrigation system would comprise of no less than six sprinklers. The moveable

irrigation lines can be moved between the different take-off points to service different areas

as required. The lines and sprinklers should be moved regularly to ensure even and

widespread application of effluent throughout the entire irrigation area. The setup of the

main distribution line and flexible lines should be designed to ensure that the recommended

buffer distances described below are not compromised.

1.3) Surface Drip Irrigation

Surface drip irrigation involves laying pressure compensated drip lines or leaky pipe within

garden beds, and covered mulch, pine bark or other surface covering. In larger garden beds

several lines may be needed, and a series of manual or automatic switching valves should be

used to select the desired area of irrigation. The irrigation design must ensure that relatively

small areas of garden bed irrigation are not proportionally over-serviced.

The pipes and fittings shall be semi-flexible and robust (polyethylene complying with AS4130

and AS4129 are suitable. UPVC pipes and fittings and garden hoses and fittings are not

suitable).

In-line strainers (150-200 mesh) shall be provided on the pump discharge to protect pipelines

from any effluent solids carried over from the wastewater treatment unit into the irrigation

lines and to facilitate systems servicing.

Inflow of surface and seepage water on to the land application area shall be controlled or

prevented. A cut-off trench or diversion drain may be constructed, if necessary, upslope of

the land application area to divert surface water and groundwater away from the irrigation

area (see Figure 2).

A commissioning test may be carried out after all on-site components including the pump

have been installed.

For spray irrigation the test would include checking the location and coverage achieved by

the spray heads and adjusted to ensure even distribution over the design area.

The test should also involve checking the pumping main to ensure there are no leaks and air

release valve is functioning.

Page 27: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

The presence of buried pipes shall be indicated (e.g. using underground marking tape) or

signage. Signs shall be prominently displayed with the words “Sewerage-effluent pipelines

installed below. DO NOT DIG”.

An installation and commissioning report may be prepared to include the ‘as-built’ details

following construction, the results of the construction inspections and the commissioning

process. This report would be provided to the owner of the wastewater system and to the

approval authority, if required.

2. Sub-surface Irrigation

Subsurface irrigation involves the installation of a series of parallel drip irrigation lines

serviced by a common header line.

The dripper lines (generally 13-16mm diameter) shall be spaced to provide an effective even

distribution of effluent over the whole of the design area (typically 1000mm spacing in clay

soils and 600mm in sandy soils). The effluent is discharged below the surface but within the

potential root zone of the vegetative cover (approximately 100mm below the ground

surface).

Each dripper line comprises of pressure compensated emitters that are typically spaced at

0.6-1.0m along the line. A filter, vacuum breaker valves and flushing valves are installed to

improve performance and longevity of the system.

The effluent filter (typically 150-200 mesh) should be cleaned about every two months.

Vacuum breakers with surface boxes shall be provided to prevent ingress of soil into the

irrigation lines under the effects of negative pipelines pressures. Irrigation lines should be

flushed approximately yearly according to installer’s recommendations. This should be done

during periods of fine weather when the threat of runoff is low.

The pipes and fittings shall be semi-fixed and robust (polyethylene complying with AS4130

and AS4129, or PVC Class 12 complying with as1477 are suitable for header and main pump

pipelines).

Page 28: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

Inflow of surface seepage water onto the land application area shall be controlled or

prevented. A cut-off trench or diversion drain may be constructed, if necessary, upslope of

the land application area to divert surface water and groundwater away from the irrigation

area. (See Figure 1).

A commissioning test may be carried out after all on-site components including the pump

have been installed, but prior to covering the effluent dripper system. The test would check

the effluent dripper system to ensure water flows uniformly from all perforations, that all

flushing valves and other fittings are operating correctly and check the pumping main to

ensure there are no leaks.

An installation and commissioning report may be prepared to include the ‘as-built’ details

following construction, the results of the construction inspections and the commissioning

process. This report would be provided to the owner of the wastewater system and to the

approval authority, if required.

The irrigation area must not be subject to high traffic, to avoid compaction around emitters.

Page 29: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

Standard Drawings SD1: Typical Irrigation Layout Overview

Note:

1. Surface-spray Irrigation (Refer to Standard Drawing SD-2)

2. Subsurface Irrigation (Refer to Standard Drawing SD-3)

3. Surface-drip Irrigation (Refer to Standard Drawing SD-2)

Page 30: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

Standard Drawings SD2: Typical Surface-spray Irrigation

Page 31: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

Standard Drawings SD3: Typical Subsurface Irrigation

Page 32: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

,I \RX OLYH LQ RU UHQW D KRXVH WKDW LV QRW FRQQHFWHG

WR WKH PDLQ VHZHU WKHQ FKDQFHV DUH WKDW \RXU \DUG

FRQWDLQV DQ RQ�VLWH VHZDJH PDQDJHPHQW V\VWHP� ,I

WKLV LV WKH FDVH WKHQ \RX KDYH D VSHFLDO

UHVSRQVLELOLW\ WR HQVXUH WKDW LW LV ZRUNLQJ DV ZHOO DV

LW FDQ�

7KH DLP RI WKLV SDPSKOHW LV WR LQWURGXFH \RX WR

VRPH RI WKH PRVW SRSXODU W\SHV RI RQ�VLWH VHZDJH

PDQDJHPHQW V\VWHPV DQG SURYLGH VRPH JHQHUDO

LQIRUPDWLRQ WR KHOS \RX PDLQWDLQ \RXU V\VWHP

HIIHFWLYHO\� <RX VKRXOG ILQG RXW ZKDW W\SH RI V\VWHP

\RX KDYH DQG KRZ LW ZRUNV�

0RUH LQIRUPDWLRQ FDQ EH REWDLQHG IURP WKH

SDPSKOHWV�

<RXU 6HSWLF 6\VWHP

<RXU $HUDWHG :DVWHZDWHU 7UHDWPHQW 6\VWHP

<RXU &RPSRVWLQJ 7RLOHW

<RXU /DQG $SSOLFDWLRQ $UHD

<RX FDQ JHW D FRS\ RI WKHVH SDPSKOHWV IURP \RXU

ORFDO FRXQFLO RU WKH DGGUHVV PDUNHG RQ WKH EDFN RI

WKLV SDPSKOHW�

,W LV LPSRUWDQW WR NHHS LQ PLQG WKDW PDLQWHQDQFH

QHHGV WR EH SHUIRUPHG SURSHUO\ DQG UHJXODUO\�

3RRUO\ PDLQWDLQHG RQ�VLWH VHZDJH PDQDJHPHQW

V\VWHPV FDQ VLJQLILFDQWO\ DIIHFW \RX DQG \RXU

IDPLO\¶V KHDOWK DV ZHOO DV WKH ORFDO HQYLURQPHQW�

:KDW LV DQ RQ�VLWH VHZDJH

PDQDJHPHQW V\VWHP"

$ GRPHVWLF RQ�VLWH VHZDJH PDQDJHPHQW V\VWHP LV

PDGH XS RI YDULRXV FRPSRQHQWV ZKLFK � LI SURSHUO\

GHVLJQHG� LQVWDOOHG DQG PDLQWDLQHG � DOORZ WKH

WUHDWPHQW DQG XWLOLVDWLRQ RI ZDVWHZDWHU IURP D

KRXVH� FRPSOHWHO\ ZLWKLQ WKH ERXQGDU\ RI WKH

SURSHUW\�

:DVWHZDWHU PD\ EH EODFNZDWHU �WRLOHW ZDVWH�� RU

JUH\ZDWHU �ZDWHU IURP VKRZHUV� VLQNV� DQG ZDVKLQJ

PDFKLQHV�� RU D FRPELQDWLRQ RI ERWK�

3DUWLDO RQ�VLWH V\VWHPV � HJ� SXPS RXW DQG FRPPRQ

HIIOXHQW V\VWHPV �&(6� � DOVR H[LVW� 7KHVH XVXDOO\

LQYROYH WKH SUHOLPLQDU\ RQ�VLWH WUHDWPHQW RI

ZDVWHZDWHU LQ D VHSWLF WDQN� IROORZHG E\ FROOHFWLRQ

DQG WUDQVSRUW RI WKH WUHDWHG ZDVWHZDWHU WR DQ RII�

VLWH PDQDJHPHQW IDFLOLW\� 3XPS RXW V\VWHPV XVH

URDG WDQNHUV WR WUDQVSRUW WKH HIIOXHQW� DQG &(6 XVH

D QHWZRUN RI VPDOO GLDPHWHU SLSHV�

+RZ GRHV DQ RQ�VLWH VHZDJH

PDQDJHPHQW V\VWHP ZRUN"

)RU FRPSOHWH RQ�VLWH V\VWHPV WKHUH DUH WZR PDLQ

SURFHVVHV�

�� WUHDWPHQW RI ZDVWHZDWHU WR D FHUWDLQ VWDQGDUG

�� LWV DSSOLFDWLRQ WR D GHGLFDWHG DUHD RI ODQG�

7KH W\SH RI DSSOLFDWLRQ SHUPLWWHG GHSHQGV RQ WKH

TXDOLW\ RI WUHDWPHQW� DOWKRXJK \RX VKRXOG WU\ WR

DYRLG FRQWDFW ZLWK DOO WUHDWHG DQG XQWUHDWHG

ZDVWHZDWHU� DQG WKRURXJKO\ ZDVK DIIHFWHG DUHDV LI

FRQWDFW GRHV RFFXU�

7UHDWPHQW DQG DSSOLFDWLRQ FDQ EH FDUULHG RXW XVLQJ

YDULRXV PHWKRGV�

6HSWLF 7DQN

6HSWLF WDQNV WUHDW ERWK JUH\ZDWHU DQG EODFNZDWHU�

EXW WKH\ SURYLGH RQO\ OLPLWHG WUHDWPHQW WKURXJK WKH

VHWWOLQJ RI VROLGV DQG WKH IORWDWLRQ RI IDWV DQG

JUHDVHV� %DFWHULD LQ WKH WDQN EUHDN GRZQ WKH VROLGV

RYHU D SHULRG RI WLPH� :DVWHZDWHU WKDW KDV EHHQ

WUHDWHG LQ D VHSWLF WDQN FDQ RQO\ EH DSSOLHG WR ODQG

WKURXJK D FRYHUHG VRLO DEVRUSWLRQ V\VWHP� DV WKH

HIIOXHQW LV VWLOO WRR FRQWDPLQDWHG IRU DERYH JURXQG

RU QHDU VXUIDFH LUULJDWLRQ�

$:76

$HUDWHG ZDVWHZDWHU WUHDWPHQW V\VWHPV �$:76�

WUHDW DOO KRXVHKROG ZDVWHZDWHU DQG KDYH VHYHUDO

WUHDWPHQW FRPSDUWPHQWV� 7KH ILUVW LV OLNH D VHSWLF

WDQN� EXW LQ WKH VHFRQG FRPSDUWPHQW DLU LV PL[HG

ZLWK WKH ZDVWHZDWHU WR DVVLVW EDFWHULD WR EUHDN

GRZQ VROLGV� $ WKLUG FRPSDUWPHQW DOORZV VHWWOLQJ RI

PRUH VROLGV DQG D ILQDO FKORULQDWLRQ FRQWDFW FKDPEHU

DOORZV GLVLQIHFWLRQ� 6RPH $:76 DUH FRQVWUXFWHG

ZLWK DOO WKH FRPSDUWPHQWV LQVLGH D VLQJOH WDQN� 7KH

HIIOXHQW SURGXFHG PD\ EH VXUIDFH RU VXE�VXUIDFH

LUULJDWHG LQ D GHGLFDWHG DUHD�

&RPSRVWLQJ 7RLOHWV

&RPSRVWLQJ WRLOHWV FROOHFW DQG WUHDW WRLOHW ZDVWH

RQO\� :DWHU IURP WKH VKRZHU� VLQNV DQG WKH ZDVKLQJ

PDFKLQH QHHGV WR EH WUHDWHG VHSDUDWHO\ �IRU

H[DPSOH LQ D VHSWLF WDQN RU $:76 DV DERYH�� 7KH

FRPSRVW SURGXFHG E\ D FRPSRVWLQJ WRLOHW KDV

VSHFLDO UHTXLUHPHQWV EXW LV XVXDOO\ EXULHG RQ�VLWH�

7KHVH DUH MXVW VRPH RI WKH WUHDWPHQW DQG

DSSOLFDWLRQ PHWKRGV DYDLODEOH� DQG WKHUH DUH PDQ\

RWKHU W\SHV VXFK DV VDQG ILOWHU EHGV� ZHWODQGV� DQG

DPHQGHG HDUWK PRXQGV� <RXU ORFDO FRXQFLO RU WKH

16: 'HSDUWPHQW RI +HDOWK KDYH PRUH LQIRUPDWLRQ

RQ WKHVH V\VWHPV LI \RX QHHG LW�

5HJXODWLRQV DQG UHFRPPHQGDWLRQV

7KH 16: 'HSDUWPHQW RI +HDOWK GHWHUPLQHV WKH

GHVLJQ DQG VWUXFWXUDO UHTXLUHPHQWV IRU WUHDWPHQW

V\VWHPV IRU VLQJOH KRXVHKROGV� /RFDO FRXQFLOV DUH

SULPDULO\ UHVSRQVLEOH IRU DSSURYLQJ WKH LQVWDOODWLRQ

RI VPDOOHU GRPHVWLF VHSWLF WDQN V\VWHPV�

FRPSRVWLQJ WRLOHWV DQG $:76V LQ WKHLU DUHD� DQG DUH

DOVR UHVSRQVLEOH IRU DSSURYLQJ ODQG DSSOLFDWLRQ

DUHDV� 7KH 16: (QYLURQPHQW 3URWHFWLRQ $XWKRULW\

DSSURYHV ODUJHU V\VWHPV�

7KH GHVLJQ DQG LQVWDOODWLRQ RI RQ�VLWH VHZDJH

PDQDJHPHQW V\VWHPV� LQFOXGLQJ SOXPELQJ DQG

GUDLQDJH� VKRXOG RQO\ EH FDUULHG RXW E\ VXLWDEO\

TXDOLILHG RU H[SHULHQFHG SHRSOH� &DUH LV QHHGHG WR

HQVXUH FRUUHFW VL]LQJ RI WKH WUHDWPHQW V\VWHP DQG

DSSOLFDWLRQ DUHD�

+HDY\ ILQHV PD\ EH LPSRVHG XQGHU WKH &OHDQ

:DWHUV $FW LI ZDVWHZDWHU LV QRW PDQDJHG SURSHUO\�

.HHSLQJ \RXU RQ�VLWH VHZDJH

PDQDJHPHQW V\VWHP RSHUDWLQJ ZHOO

:KDW \RX SXW GRZQ \RXU GUDLQV DQG WRLOHWV KDV D ORW

WR GR ZLWK KRZ ZHOO \RXU V\VWHP SHUIRUPV�

0DLQWHQDQFH RI \RXU VHZDJH PDQDJHPHQW V\VWHP

DOVR QHHGV WR EH GRQH ZHOO DQG RQ�WLPH� 7KH

IROORZLQJ LV D JXLGH WR WKH W\SHV RI WKLQJV \RX

VKRXOG DQG VKRXOG QRW GR ZLWK \RXU V\VWHP�

21�6,7( 6(:$*(

0$1$*(0(17 6<67(06

envirotech3
Text Box
Appendix F: Operation and Maintenance Guidelines
Page 33: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

'2

9 /HDUQ KRZ \RXU VHZDJH PDQDJHPHQW V\VWHPZRUNV DQG LWV RSHUDWLRQDO DQG PDLQWHQDQFH

UHTXLUHPHQWV�

9 /HDUQ WKH ORFDWLRQ DQG OD\RXW RI \RXU VHZDJH

PDQDJHPHQW V\VWHP�

9 +DYH \RXU $:76 �LI LQVWDOOHG� LQVSHFWHG DQG

VHUYLFHG IRXU WLPHV SHU \HDU E\ DQ DSSURYHG

FRQWUDFWRU� 2WKHU V\VWHPV VKRXOG EH LQVSHFWHG DW

OHDVW RQFH HYHU\ \HDU� $VVHVVPHQW VKRXOG EH

DSSOLFDEOH WR WKH V\VWHP GHVLJQ�

9 .HHS D UHFRUG RI GHVOXGJLQJV� LQVSHFWLRQV� DQG

RWKHU PDLQWHQDQFH�

9 +DYH \RXU VHSWLF WDQN RU $:76 GHVOXGJHG HYHU\

WKUHH \HDUV WR SUHYHQW VOXGJH EXLOG XS� ZKLFK

PD\ µFORJ¶ WKH SLSHV�

9 &RQVHUYH ZDWHU� &RQVHUYDWLYH ZDWHU XVH DURXQGWKH KRXVH ZLOO UHGXFH WKH DPRXQW RI ZDVWHZDWHU

ZKLFK LV SURGXFHG DQG QHHGV WR EH WUHDWHG�

9 'LVFXVV ZLWK \RXU ORFDO FRXQFLO WKH DGHTXDF\ RI

\RXU H[LVWLQJ VHZDJH PDQDJHPHQW V\VWHP LI \RX

DUH FRQVLGHULQJ KRXVH H[WHQVLRQV IRU LQFUHDVHG

RFFXSDQF\�

'21¶7

8 'RQ¶W OHW FKLOGUHQ RU SHWV SOD\ RQ ODQG DSSOLFDWLRQ

DUHDV�

8 'RQ¶W ZDWHU IUXLW DQG YHJHWDEOHV ZLWK HIIOXHQW�

8 'RQ¶W H[WUDFW XQWUHDWHG JURXQGZDWHU IRU FRRNLQJ

DQG GULQNLQJ�

8 'RQ¶W SXW ODUJH TXDQWLWLHV RI EOHDFKHV�GLVLQIHFWDQWV� ZKLWHQHUV� QDSS\ VRDNHUV DQG VSRW

UHPRYHUV LQWR \RXU V\VWHP YLD WKH VLQN� ZDVKLQJ

PDFKLQH RU WRLOHW�

8 'RQ¶W DOORZ DQ\ IRUHLJQ PDWHULDOV VXFK DV

QDSSLHV� VDQLWDU\ QDSNLQV� FRQGRPV DQG RWKHU

K\JLHQH SURGXFWV WR HQWHU WKH V\VWHP�

8 'RQ¶W SXW IDWV DQG RLOV GRZQ WKH GUDLQ DQG NHHSIRRG ZDVWH RXW RI \RXU V\VWHP�

8 'RQ¶W LQVWDOO RU XVH D JDUEDJH JULQGHU RU VSD

EDWK LI \RXU V\VWHP LV QRW GHVLJQHG IRU LW�

5HGXFLQJ ZDWHU XVDJH

5HGXFLQJ ZDWHU XVDJH ZLOO OHVVHQ WKH OLNHOLKRRG RI

SUREOHPV VXFK DV RYHUORDGLQJ ZLWK \RXU VHSWLF

V\VWHP� 2YHUORDGLQJ PD\ UHVXOW LQ ZDVWHZDWHU

EDFNLQJ XS LQWR \RXU KRXVH� FRQWDPLQDWLRQ RI \RXU

\DUG ZLWK LPSURSHUO\ WUHDWHG HIIOXHQW� DQG HIIOXHQW

IURP \RXU V\VWHP FRQWDPLQDWLQJ JURXQGZDWHU RU D

QHDUE\ ZDWHUZD\�

<RXU VHZDJH PDQDJHPHQW V\VWHP LV DOVR XQDEOH WR

FRSH ZLWK ODUJH YROXPHV RI ZDWHU VXFK DV VHYHUDO

VKRZHUV RU ORDGV RI ZDVKLQJ RYHU D VKRUW SHULRG RI

WLPH� <RX VKRXOG WU\ WR DYRLG WKHVH µVKRFN ORDGV¶ E\

HQVXULQJ ZDWHU XVH LV VSUHDG PRUH HYHQO\

WKURXJKRXW WKH GD\ DQG ZHHN�

)RU PRUH LQIRUPDWLRQ SOHDVH FRQWDFW� ?

?

?

+(/3 3527(&7 <285 +($/7+

$1' 7+( (19,5210(17

3RRUO\ PDLQWDLQHG VHZDJH PDQDJHPHQW V\VWHPV

DUH D VHULRXV VRXUFH RI ZDWHU SROOXWLRQ DQG PD\

SUHVHQW KHDOWK ULVNV� FDXVH RGRXUV DQG DWWUDFW

YHUPLQ DQG LQVHFWV�

%\ ORRNLQJ DIWHU \RXU PDQDJHPHQW V\VWHP \RX

FDQ GR \RXU SDUW LQ KHOSLQJ WR SURWHFW WKH

HQYLURQPHQW DQG WKH KHDOWK RI \RX DQG \RXU

FRPPXQLW\�

Page 34: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

$HUDWHG :DVWHZDWHU

7UHDWPHQW 6\VWHPV �$:76�

,Q XQVHZHUHG DUHDV� WKH SURSHU WUHDWPHQW DQG

XWLOLVDWLRQ RI KRXVHKROG ZDVWHZDWHU RQ�VLWH LV FULWLFDO

LQ SUHVHUYLQJ WKH KHDOWK RI WKH SXEOLF DQG WKH

HQYLURQPHQW� $:76 KDYH EHHQ GHYHORSHG DV D ZD\

RI DFKLHYLQJ WKLV�

:KDW LV DQ $:76"

$Q $:76 LV D SXUSRVH EXLOW V\VWHP XVHG IRU WKH

WUHDWPHQW RI VHZDJH DQG OLTXLG ZDVWHV IURP D VLQJOH

KRXVHKROG RU PXOWLSOH GZHOOLQJV�

,W FRQVLVWV RI D VHULHV RI WUHDWPHQW FKDPEHUV

FRPELQHG ZLWK DQ LUULJDWLRQ V\VWHP� $Q $:76

HQDEOHV SHRSOH OLYLQJ LQ XQVHZHUHG DUHDV WR WUHDW

DQG XWLOLVH WKHLU ZDVWHZDWHU�

+RZ GRHV DQ $:76 ZRUN"

:DVWHZDWHU IURP D KRXVHKROG LV WUHDWHG LQ VWDJHV LQ

VHYHUDO VHSDUDWH FKDPEHUV� 7KH ILUVW FKDPEHU LV

VLPLODU WR D FRQYHQWLRQDO VHSWLF WDQN� 7KH ZDVWHZDWHU

HQWHUV WKH FKDPEHU ZKHUH WKH VROLGV VHWWOH WR WKH

ERWWRP DQG DUH UHWDLQHG LQ WKH WDQN IRUPLQJ D

VOXGJH OD\HU� 6FXP FROOHFWV DW WKH WRS� DQG WKH

SDUWLDOO\ FODULILHG ZDVWHZDWHU IORZV LQWR D VHFRQG

FKDPEHU� +HUH WKH ZDVWHZDWHU LV PL[HG ZLWK DLU

WR DVVLVW EDFWHULD WR IXUWKHU WUHDW LW� $ WKLUG FKDPEHU

DOORZV DGGLWLRQDO FODULILFDWLRQ WKURXJK WKH VHWWOLQJ RI

VROLGV� ZKLFK DUH UHWXUQHG IRU IXUWKHU WUHDWPHQW WR

HLWKHU WKH VHSWLF FKDPEHU �DV VKRZQ� RU WR WKH

DHUDWLRQ FKDPEHU� 7KH FODULILHG HIIOXHQW LV

GLVLQIHFWHG LQ DQRWKHU FKDPEHU �XVXDOO\ E\

FKORULQDWLRQ� EHIRUH LUULJDWLRQ FDQ WDNH SODFH�

%DFWHULD LQ WKH ILUVW FKDPEHU EUHDN GRZQ WKH VROLG

PDWWHU LQ WKH VOXGJH DQG VFXP OD\HUV� 0DWHULDO WKDW

FDQQRW EH IXOO\ EURNHQ GRZQ JUDGXDOO\ EXLOGV XS LQ

WKH FKDPEHU DQG PXVW EH SXPSHG RXW SHULRGLFDOO\�

5HJXODWLRQV DQG UHFRPPHQGDWLRQV

/RFDO FRXQFLOV DUH SULPDULO\ UHVSRQVLEOH IRU

DSSURYLQJ WKH VPDOOHU� GRPHVWLF $:76V LQ WKHLU

DUHD� 7KH (QYLURQPHQW 3URWHFWLRQ $XWKRULW\ �(3$�

DSSURYHV ODUJHU XQLWV� ZKLOVW WKH 16: 'HSDUWPHQW

RI +HDOWK GHWHUPLQHV WKH GHVLJQ DQG VWUXFWXUDO

UHTXLUHPHQWV IRU DOO $:76V�

$W SUHVHQW $:76V QHHG WR EH VHUYLFHG TXDUWHUO\ E\

DQ DSSURYHG FRQWUDFWRU DW D FRVW WR WKH RZQHU�

/RFDO FRXQFLOV VKRXOG DOVR PDLQWDLQ D UHJLVWHU RI WKH

VHUYLFLQJ RI HDFK V\VWHP ZLWKLQ WKHLU DUHD�

$:76V VKRXOG EH ILWWHG ZLWK DQ DODUP KDYLQJ YLVXDO

DQG DXGLEOH FRPSRQHQWV WR LQGLFDWH PHFKDQLFDO DQG

HOHFWULFDO HTXLSPHQW PDOIXQFWLRQV� 7KH DODUP VKRXOG

SURYLGH D VLJQDO DGMDFHQW WR WKH DODUP DQG DW D

UHOHYDQW SRVLWLRQ LQVLGH WKH

KRXVH� 7KH DODUP VKRXOG

LQFRUSRUDWH D ZDUQLQJ ODPS

ZKLFK PD\ RQO\ EH UHVHW E\

WKH VHUYLFH DJHQW�

0DLQWDLQLQJ \RXU $:76

7KH HIIHFWLYHQHVV RI WKH

V\VWHP ZLOO� LQ SDUW� GHSHQG

RQ KRZ LW LV XVHG DQG

PDLQWDLQHG� 7KH IROORZLQJ LV D

JXLGH RQ JRRG PDLQWHQDQFH

SURFHGXUHV WKDW \RX VKRXOG

IROORZ�

'2

9 +DYH \RXU $:76 LQVSHFWHG DQG VHUYLFHG IRXU

WLPHV SHU \HDU E\ DQ DSSURYHG FRQWUDFWRU�

$VVHVVPHQW VKRXOG EH DSSOLFDEOH WR WKH V\VWHP

GHVLJQ�

9 +DYH \RXU V\VWHP VHUYLFH LQFOXGH DVVHVVPHQW RI

VOXGJH DQG VFXP OHYHOV LQ DOO WDQNV� DQG

SHUIRUPDQFH RI LUULJDWLRQ DUHDV�

9 +DYH DOO \RXU WDQNV GHVOXGJHG DW OHDVW HYHU\

WKUHH \HDUV�

9 +DYH \RXU GLVLQIHFWLRQ FKDPEHU LQVSHFWHG DQG

WHVWHG TXDUWHUO\ WR HQVXUH FRUUHFW GLVLQIHFWDQW

OHYHOV�

9 +DYH \RXU JUHDVH WUDS �LI LQVWDOOHG� FOHDQHG RXW

DW OHDVW HYHU\ WZR PRQWKV�

9 .HHS D UHFRUG RI SXPSLQJ� LQVSHFWLRQV� DQGRWKHU PDLQWHQDQFH�

9 /HDUQ WKH ORFDWLRQ DQG OD\RXW RI \RXU $:76 DQG

ODQG DSSOLFDWLRQ DUHD�

9 8VH ELRGHJUDGDEOH OLTXLG GHWHUJHQWV VXFK DV

FRQFHQWUDWHV ZLWK ORZ VRGLXP DQG SKRVSKRURXV

OHYHOV�

9 &RQVHUYH ZDWHU�

'21¶7

8 'RQ¶W SXW EOHDFKHV� GLVLQIHFWDQWV� ZKLWHQHUV�QDSS\ VRDNHUV DQG VSRW UHPRYHUV LQ ODUJH

TXDQWLWLHV LQWR \RXU $:76 YLD WKH VLQN� ZDVKLQJ

PDFKLQH RU WRLOHW�

8 'RQ¶W DOORZ DQ\ IRUHLJQ PDWHULDOV VXFK DVQDSSLHV� VDQLWDU\ QDSNLQV� FRQGRPV DQG RWKHU

K\JLHQH SURGXFWV WR HQWHU WKH V\VWHP�

8 'RQ¶W XVH PRUH WKDQ WKH UHFRPPHQGHG DPRXQWV

RI GHWHUJHQWV�

8 'RQ¶W SXW IDWV DQG RLOV GRZQ WKH GUDLQ DQG NHHSIRRG ZDVWH RXW RI \RXU V\VWHP�

8 'RQ¶W VZLWFK RII SRZHU WR WKH $:76� HYHQ LI \RX

DUH JRLQJ RQ KROLGD\V

Air

To pumpand landapplicationarea

Sludge Return

Inlet fromhouse

Scum

Sludge

AerationChamber Settling

Chamber

Cross section of an AWTS

DisinfectionChamber

PrimaryChamber

Page 35: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

5HGXFLQJ ZDWHU XVDJH

5HGXFLQJ ZDWHU XVDJH ZLOO OHVVHQ WKH OLNHOLKRRG RI

SUREOHPV VXFK DV RYHUORDGLQJ ZLWK \RXU $:76�

2YHUORDGLQJ PD\ UHVXOW LQ ZDVWHZDWHU EDFNLQJ XS

LQWR \RXU KRXVH� FRQWDPLQDWLRQ RI \RXU \DUG ZLWK

LPSURSHUO\ WUHDWHG HIIOXHQW� DQG HIIOXHQW IURP \RXU

V\VWHP HQWHULQJ D QHDUE\ ULYHU� FUHHN RU GDP�

&RQVHUYDWLYH ZDWHU XVH DURXQG WKH KRXVH ZLOO

UHGXFH WKH DPRXQW RI ZDVWHZDWHU ZKLFK LV SURGXFHG

DQG QHHGV WR EH WUHDWHG�

<RXU $:76 LV DOVR XQDEOH WR FRSH ZLWK ODUJH

YROXPHV RI ZDWHU VXFK DV VHYHUDO VKRZHUV RU ORDGV

RI ZDVKLQJ RYHU D VKRUW SHULRG RI WLPH� <RX VKRXOG

WU\ WR DYRLG WKHVH µVKRFN ORDGV¶ E\ HQVXULQJ ZDWHU

XVH LV VSUHDG PRUH HYHQO\ WKURXJKRXW WKH GD\ DQG

ZHHN�

:DUQLQJ VLJQV

<RX FDQ ORRN RXW IRU D IHZ ZDUQLQJ VLJQV WKDW VLJQDO

WR \RX WKDW WKHUH DUH WURXEOHV ZLWK \RXU $:76�

(QVXUH WKDW WKHVH SUREOHPV DUH DWWHQGHG WR

LPPHGLDWHO\ WR SURWHFW \RXU KHDOWK DQG WKH

HQYLURQPHQW�

/RRN RXW IRU WKH IROORZLQJ ZDUQLQJ VLJQV�

� :DWHU WKDW GUDLQV WRR VORZO\�

� 'UDLQ SLSHV WKDW JXUJOH RU PDNH QRLVHV ZKHQ DLU

EXEEOHV DUH IRUFHG EDFN WKURXJK WKH V\VWHP�

� 6HZDJH VPHOOV� WKLV LQGLFDWHV D VHULRXV SUREOHP�

� :DWHU EDFNLQJ XS LQWR \RXU VLQN ZKLFK PD\

LQGLFDWH WKDW \RXU V\VWHP LV DOUHDG\ IDLOLQJ�

� :DVWHZDWHU SRROLQJ RYHU WKH ODQG DSSOLFDWLRQ

DUHD�

� %ODFN FRORXUHG HIIOXHQW LQ WKH DHUDWHG WDQN�

� ([FHVV QRLVH IURP WKH EORZHU RU SXPSLQJ

HTXLSPHQW

� 3RRU YHJHWDWLRQ JURZWK LQ LUULJDWHG DUHD�

2GRXU SUREOHPV IURP D YHQW RQ WKH $:76 FDQ EH D

UHVXOW RI VORZ RU LQDGHTXDWH EUHDNGRZQ RI VROLGV�

&DOO D WHFKQLFLDQ WR VHUYLFH WKH V\VWHP�

,I \RX ZRXOG OLNH PRUH LQIRUPDWLRQ SOHDVH FRQWDFW�

+(/3 3527(&7 <285 +($/7+

$1' 7+( (19,5210(17

3RRUO\ PDLQWDLQHG $:76V DUH D VHULRXV VRXUFH RI

ZDWHU SROOXWLRQ DQG PD\ SUHVHQW KHDOWK ULVNV�

FDXVH RGRXUV DQG DWWUDFW YHUPLQ DQG LQVHFWV�

%\ ORRNLQJ DIWHU \RXU WUHDWPHQW V\VWHP \RX FDQ

GR \RXU SDUW LQ KHOSLQJ WR SURWHFW WKH

HQYLURQPHQW DQG WKH KHDOWK RI \RX DQG \RXU

IDPLO\�

Page 36: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

/$1' $33/,&$7,21 $5($6

7KH UHXVH RI GRPHVWLF ZDVWHZDWHU RQ�VLWH FDQ EH DQ

HFRQRPLFDO DQG HQYLURQPHQWDOO\ VRXQG XVH RI

UHVRXUFHV�

:KDW DUH ODQG DSSOLFDWLRQ DUHDV"

7KHVH DUH DUHDV WKDW DOORZ WUHDWHG GRPHVWLF

ZDVWHZDWHU WR EH PDQDJHG HQWLUHO\ RQ�VLWH�

7KH DUHD PXVW EH DEOH WR XWLOLVH WKH ZDVWHZDWHU DQG

WUHDW DQ\ RUJDQLF PDWWHU DQG ZDVWHV LW PD\ FRQWDLQ�

7KH ZDVWHZDWHU LV ULFK LQ QXWULHQWV� DQG FDQ SURYLGH

H[FHOOHQW QRXULVKPHQW IRU IORZHU JDUGHQV� ODZQV�

FHUWDLQ VKUXEV DQG WUHHV� 7KH YHJHWDWLRQ VKRXOG EH

VXLWDEO\ WROHUDQW RI KLJK ZDWHU DQG QXWULHQW ORDGV�

+RZ GRHV D ODQG DSSOLFDWLRQ DUHD ZRUN"

7UHDWHG ZDVWHZDWHU DSSOLHG WR D ODQG DSSOLFDWLRQ

DUHD PD\ EH XWLOLVHG RU VLPSO\ GLVSRVHG� GHSHQGLQJ

RQ WKH W\SH RI DSSOLFDWLRQ V\VWHP WKDW LV XVHG� 7KH

DSSOLFDWLRQ RI WKH ZDVWHZDWHU FDQ EH WKURXJK D VRLO

DEVRUSWLRQ V\VWHP �EDVHG RQ GLVSRVDO� RU WKURXJK

DQ LUULJDWLRQ V\VWHP �EDVHG RQ XWLOLVDWLRQ��

6RLO DEVRUSWLRQ V\VWHPV GR QRW UHTXLUH KLJKO\

WUHDWHG HIIOXHQW� DQG ZDVWHZDWHU WUHDWHG E\ D VHSWLF

WDQN LV UHDVRQDEOH DV WKH VROLGV FRQWHQW LQ WKH

HIIOXHQW KDV EHHQ UHGXFHG� $EVRUSWLRQ V\VWHPV

UHOHDVH WKH HIIOXHQW LQWR WKH VRLO DW D GHSWK WKDW

FDQQRW EH UHDFKHG E\ WKH URRWV RI PRVW VPDOO

VKUXEV DQG JUDVVHV� 7KH\ UHO\ PDLQO\ RQ WKH

SURFHVVHV RI VRLO WUHDWPHQW DQG WKHQ WUDQVPLVVLRQ

WR WKH ZDWHU WDEOH� ZLWK PLQLPDO HYDSRUDWLRQ DQG

XS�WDNH E\ SODQWV� 7KHVH V\VWHPV DUH QRW

UHFRPPHQGHG LQ VHQVLWLYH DUHDV DV WKH\ PD\

OHDG WR FRQWDPLQDWLRQ RI VXUIDFH ZDWHU DQG

JURXQGZDWHU�

,UULJDWLRQ V\VWHPV PD\ EH FODVVHG DV HLWKHU

VXEVXUIDFH RU VXUIDFH LUULJDWLRQ� ,I DQ LUULJDWLRQ

V\VWHP LV WR EH XVHG� ZDVWHZDWHU QHHGV WR EH SUH�

WUHDWHG WR DW OHDVW WKH TXDOLW\ SURGXFHG E\ DQ

DHUDWHG ZDVWHZDWHU WUHDWPHQW V\VWHP �$:76��

6XEVXUIDFH LUULJDWLRQ UHTXLUHV KLJKO\ WUHDWHG

HIIOXHQW WKDW LV LQWURGXFHG LQWR WKH VRLO FORVH WR WKH

VXUIDFH� 7KH HIIOXHQW LV XWLOLVHG PDLQO\ E\ SODQWV DQG

HYDSRUDWLRQ�

6XUIDFH LUULJDWLRQ UHTXLUHV KLJKO\ WUHDWHG HIIOXHQW

WKDW KDV XQGHUJRQH DHUDWLRQ DQG GLVLQIHFWLRQ

WUHDWPHQWV� VR DV WR UHGXFH WKH SRVVLELOLW\ RI

EDFWHULD DQG YLUXV FRQWDPLQDWLRQ�

7KH HIIOXHQW LV WKHQ DSSOLHG WR WKH ODQG DUHD WKURXJK

D VHULHV RI GULS� WULFNOH� RU VSUD\ SRLQWV ZKLFK DUH

GHVLJQHG WR HOLPLQDWH DLUERUQH GULIW DQG UXQ�RII LQWR

QHLJKERXULQJ SURSHUWLHV�

7KHUH DUH VRPH SXEOLF KHDOWK DQG HQYLURQPHQWDO

FRQFHUQV DERXW VXUIDFH LUULJDWLRQ� 7KHUH LV WKH ULVN

RI FRQWDFW ZLWK WUHDWHG HIIOXHQW DQG WKH SRWHQWLDO IRU

VXUIDFH UXQ�RII� *LYHQ WKHVH SUREOHPV� VXEVXUIDFH

LUULJDWLRQ LV DUJXDEO\ WKH VDIHVW� PRVW HIILFLHQW DQG

HIIHFWLYH PHWKRG RI HIIOXHQW XWLOLVDWLRQ�

5HJXODWLRQV DQG UHFRPPHQGDWLRQV

7KH GHVLJQ DQG LQVWDOODWLRQ RI ODQG DSSOLFDWLRQ DUHDV

VKRXOG RQO\ EH FDUULHG RXW E\ VXLWDEO\ TXDOLILHG RU

H[SHULHQFHG SHRSOH� DQG RQO\ DIWHU D VLWH DQG VRLO

HYDOXDWLRQ LV GRQH E\ D VRLO VFLHQWLVW� &DUH VKRXOG EH

WDNHQ WR HQVXUH FRUUHFW EXIIHU GLVWDQFHV DUH OHIW

EHWZHHQ WKH DSSOLFDWLRQ DUHD DQG ERUHV� ZDWHUZD\V�

EXLOGLQJV� DQG QHLJKERXULQJ SURSHUWLHV�

+HDY\ ILQHV PD\ EH LPSRVHG XQGHU WKH &OHDQ

:DWHUV $FW LI HIIOXHQW LV PDQDJHG LPSURSHUO\�

$W OHDVW WZR ZDUQLQJ VLJQV VKRXOG EH LQVWDOOHG DORQJ

WKH ERXQGDU\ RI D ODQG DSSOLFDWLRQ DUHD� 7KH VLJQV

VKRXOG FRPSULVH RI ��PP KLJK 6HULHV & OHWWHULQJ LQ

EODFN RU ZKLWH RQ D JUHHQ EDFNJURXQG ZLWK WKH

ZRUGV�

5(&/$,0(' ())/8(17

127 )25 '5,1.,1*

$92,' &217$&7

'HSHQGLQJ RQ WKH UHTXLUHPHQWV RI \RXU ORFDO FRXQFLO�

ZHW ZHDWKHU VWRUDJH DQG VRLO PRLVWXUH VHQVRUV PD\

QHHG WR EH LQVWDOOHG WR HQVXUH WKDW HIIOXHQW LV RQO\

LUULJDWHG ZKHQ WKH VRLO LV QRW VDWXUDWHG�

5HJXODU FKHFNV VKRXOG EH XQGHUWDNHQ RI DQ\

PHFKDQLFDO HTXLSPHQW WR HQVXUH WKDW LW LV RSHUDWLQJ

FRUUHFWO\� /RFDO FRXQFLOV PD\ UHTXLUH SHULRGLF DQDO\VLV

RI VRLO RU JURXQGZDWHU FKDUDFWHULVWLFV

+XPDQV DQG DQLPDOV VKRXOG EH H[FOXGHG IURP ODQG

DSSOLFDWLRQ DUHDV GXULQJ DQG LPPHGLDWHO\ DIWHU WKH

DSSOLFDWLRQ RI WUHDWHG ZDVWHZDWHU� 7KH ORQJHU WKH

SHULRG RI H[FOXVLRQ IURP DQ DUHD� WKH ORZHU WKH ULVN

WR SXEOLF KHDOWK�

7KH KRXVHKROGHU LV UHTXLUHG WR HQWHU LQWR D VHUYLFH

FRQWUDFW ZLWK WKH LQVWDOODWLRQ FRPSDQ\� LWV DJHQW RU

WKH PDQXIDFWXUHU RI WKHLU VHZDJH PDQDJHPHQW

V\VWHP� WKLV ZLOO HQVXUH WKDW WKH V\VWHP RSHUDWHV

HIILFLHQWO\�

/RFDWLRQ RI WKH DSSOLFDWLRQ DUHD

7UHDWHG ZDVWHZDWHU KDV WKH SRWHQWLDO WR KDYH

QHJDWLYH LPSDFWV RQ SXEOLF KHDOWK DQG WKH

HQYLURQPHQW� )RU WKLV UHDVRQ WKH DSSOLFDWLRQ DUHD

PXVW EH ORFDWHG LQ DFFRUGDQFH ZLWK WKH UHVXOWV RI D

VLWH HYDOXDWLRQ� DQG DSSURYHG ODQGVFDSLQJ PXVW EH

FRPSOHWHG SULRU WR RFFXSDWLRQ RI WKH EXLOGLQJ�

6DQG\ VRLO DQG FOD\H\ VRLOV PD\ SUHVHQW VSHFLDO

SUREOHPV�

7KH V\VWHP PXVW DOORZ HYHQ GLVWULEXWLRQ RI WUHDWHG

ZDVWHZDWHU RYHU WKH ODQG DSSOLFDWLRQ DUHD�

Typical Site Layout (not to scale)

Mound to deflectrunon

Road

Grasseddrainageswale

Grasseddrainageswale

Irrigationarea (grass)Reserve area

maintained inlawn

Trees,shrubs

Fence

House

Pool

GroundSlope

Wastewatertreatment

Page 37: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

0DLQWDLQLQJ \RXU ODQG DSSOLFDWLRQ DUHD

7KH HIIHFWLYHQHVV RI WKH DSSOLFDWLRQ DUHD LV

JRYHUQHG E\ WKH DFWLYLWLHV RI WKH RZQHU�

'2

9 &RQVWUXFW DQG PDLQWDLQ GLYHUVLRQ GUDLQV DURXQG

WKH WRS VLGH RI WKH DSSOLFDWLRQ DUHD WR GLYHUW

VXUIDFH ZDWHU�

9 (QVXUH WKDW \RXU DSSOLFDWLRQ DUHD LV NHSW OHYHO E\ILOOLQJ DQ\ GHSUHVVLRQV ZLWK JRRG TXDOLW\ WRS VRLO

�QRW FOD\��

9 .HHS WKH JUDVV UHJXODUO\ PRZHG DQG SODQW VPDOO

WUHHV DURXQG WKH SHULPHWHU WR DLG DEVRUSWLRQ DQG

WUDQVSLUDWLRQ RI WKH HIIOXHQW�

9 (QVXUH WKDW DQ\ UXQ RII IURP WKH URRI� GULYHZD\DQG RWKHU LPSHUPHDEOH VXUIDFHV LV GLUHFWHG DZD\

IURP WKH DSSOLFDWLRQ DUHD�

9 )HQFH LUULJDWLRQ DUHDV�

9 (QVXUH DSSURSULDWH ZDUQLQJ VLJQV DUH YLVLEOH DW

DOO WLPHV LQ WKH YLFLQLW\ RI D VSUD\ LUULJDWLRQ DUHD�

9 +DYH \RXU LUULJDWLRQ V\VWHP FKHFNHG E\ WKH

VHUYLFH DJHQW ZKHQ WKH\ DUH FDUU\LQJ RXW VHUYLFH

RQ WKH WUHDWPHQW V\VWHP�

'21¶7

8 'RQ¶W HUHFW DQ\ VWUXFWXUHV� FRQVWUXFW SDWKV�

JUD]H DQLPDOV RU GULYH RYHU WKH ODQG DSSOLFDWLRQ

DUHD�

8 'RQ¶W SODQW ODUJH WUHHV WKDW VKDGH WKH ODQGDSSOLFDWLRQ DUHD� DV WKH DUHD QHHGV VXQOLJKW WR

DLG LQ WKH HYDSRUDWLRQ DQG WUDQVSLUDWLRQ RI WKH

HIIOXHQW�

8 'RQ¶W SODQW WUHHV RU VKUXEV QHDU RU RQ KRXVHGUDLQV�

8 'RQ¶W DOWHU VWRUPZDWHU OLQHV WR GLVFKDUJH LQWR RUQHDU WKH ODQG DSSOLFDWLRQ DUHD�

8 'RQ¶W IORRG WKH ODQG DSSOLFDWLRQ DUHD WKURXJK WKH

XVH RI KRVHV RU VSULQNOHUV�

8 'RQ¶W OHW FKLOGUHQ RU SHWV SOD\ RQ ODQG DSSOLFDWLRQ

DUHDV�

8 'RQ¶W ZDWHU IUXLW DQG YHJHWDEOHV ZLWK WKH

HIIOXHQW�

8 'RQ¶W H[WUDFW XQWUHDWHG JURXQGZDWHU IRU SRWDEOH

XVH�

:DUQLQJ VLJQV

5HJXODU YLVXDO FKHFNLQJ RI WKH V\VWHP ZLOO HQVXUH

WKDW SUREOHPV DUH ORFDWHG DQG IL[HG HDUO\�

7KH YLVXDO VLJQV RI V\VWHP IDLOXUH LQFOXGH�

� VXUIDFH SRQGLQJ DQG UXQ�RII RI WUHDWHG

ZDVWHZDWHU

� VRLO TXDOLW\ GHWHULRUDWLRQ

� SRRU YHJHWDWLRQ JURZWK

� XQXVXDO RGRXUV

9ROXPH RI ZDWHU

/DQG DSSOLFDWLRQ DUHDV DQG V\VWHPV IRU RQ�VLWH

DSSOLFDWLRQ DUH GHVLJQHG DQG FRQVWUXFWHG LQ

DQWLFLSDWLRQ RI WKH YROXPH RI ZDVWH WR EH

GLVFKDUJHG� 8QFRQWUROOHG XVH RI ZDWHU PD\ OHDG WR

SRRUO\ WUHDWHG HIIOXHQW EHLQJ UHOHDVHG IURP WKH

V\VWHP�

,I WKH ODQG DSSOLFDWLRQ DUHD LV ZDWHUORJJHG DQG

VRJJ\ WKH IROORZLQJ DUH SRVVLEOH UHDVRQV�

Λ 2YHUORDGLQJ WKH WUHDWPHQW V\VWHP ZLWK

ZDVWHZDWHU�

Λ 7KH FORJJLQJ RI WKH WUHQFK ZLWK VROLGV QRW

WUDSSHG E\ WKH VHSWLF WDQN� 7KH WDQN PD\ UHTXLUH

GHVOXGJLQJ�

Λ 7KH DSSOLFDWLRQ DUHD KDV EHHQ SRRUO\ GHVLJQHG�

Λ 6WRUPZDWHU LV UXQQLQJ RQWR WKH DUHD�

)RU PRUH LQIRUPDWLRQ SOHDVH FRQWDFW�

+(/3 3527(&7 <285 +($/7+

$1' 7+( (19,5210(17

3RRUO\ PDLQWDLQHG ODQG DSSOLFDWLRQ DUHDV DUH D

VHULRXV VRXUFH RI ZDWHU SROOXWLRQ DQG PD\

SUHVHQW KHDOWK ULVNV� FDXVH RGRXUV DQG DWWUDFW

YHUPLQ DQG LQVHFWV�

%\ ORRNLQJ DIWHU \RXU VHZDJH PDQDJHPHQW

V\VWHP \RX FDQ GR \RXU SDUW LQ KHOSLQJ WR SURWHFW

WKH HQYLURQPHQW DQG WKH KHDOWK RI \RX DQG \RXU

IDPLO\�

Page 38: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

1. Independent Pricing and Regulation Tribunal of NSW (1996), “water Demand Management: A Framework for Option Assessment’

2. Sydney Water Demand Management Strategy, 1995

APPENDIX G

Water Conservation

Whilst this report is based on AA rate plumbing fixtures, AA rate plumbing would further

conserve limited water supplies and enhance performance of the irrigation, soil and plant

systems. Water saving devices will reduce the volume of water that needs to be applied to

the site, and thus reduce the risk of any runoff.

Using the following water saving devices, the average household’s water consumption can be

reduced from 900L to 750L per day:

- Dual flush 6/3L pan and cistern (average household savings of 93L / Day)1

- AAA rated shower heads to limit flows to 7L/min 1

- AAA rate dishwasher (not more than 19L per wash cycle) 2

- AAA rated washing machine (not more than 22L per dry kg of clothing) 2

Low phosphate, low sodium detergents are recommended to help improve the effluent

quality. Low sodium detergents ensure that the soil structure, and hence its absorption

powders is used as a filler. Therefore, in general, liquid detergents are preferred over powder.

Low phosphorus detergents ensure that optimum plant growth is maintained and that excess

phosphorus is not leached into the environment.

Bleaches, disinfectants and other cleaning compounds can harm wastewater treatment

systems, such as septic tanks, because they kill bacteria that colonise the system and help

treat wastewater. Use these products sparingly and always check that they are sage for septic

systems. Avoid oil, paint, petrol, acids, degreasers, photography chemicals, cosmetic, lotions,

pesticides and herbicides in the wastewater system. Even small amounts of these products

can harm the performance of the onsite effluent management system.

Page 39: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

APPENDIX H

Beds & Trenches Descriptions & Standard Drawings

Absorption Trenches

Australian Standards AS1547:2012 provides design criteria that should be reviewed by the

installer. Trenches shall be constructed having a width of 600mm with a depth of 600mm,

lined with a 300mm radius half rounded plastic drain or similar. The drain shall then be

encased with a 10mm aggregate to a level of 500mm, followed by a topsoil 100m deep placed

up to the existing surface level. Trench length is normally limited to 20m in order to ensure

even distribution of effluent along their extent. An exception may occur in which the trench

is pressure dosed (e.g. by pump or dosing-syphon).

Effluent flow must be distributed evenly to the trench(es) by the use of a distribution box with

‘v’ weirs or similar. In some cases, parallel trenches ay be joined in a cascade fashion so that

overflow from one trench will flow downslope to the next.

If dosed with septic effluent, it is important that the trenches are protected from clogging by

the use of a septic outlet filter. Typical Trench configurations are depicted in Figure 1 & 2

below.

Figure 1. – Conventional Piped Trench (Source: AS1547:2012 Fig. L1)

Page 40: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

Figure 2. – Self-Supporting Arch Trench (Source: AS1547:2012 Fig. L2)

Evapotranspiration Absorption (ETA) Beds / Trenches

Typical cross sections of an ETA land application area are depicted in Figure 3 & 4. A

qualified plumber familiar with the requirements for construction ETA beds should be

employed for building this system.

Note: An LPED line can be used to dose load ETA/ETS bed.

Figure 3. – Conventional ETA Bed/Trench Details (Source: AS1547:2012 Fig. L6)

Page 41: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

Notes:

1. An LEPD can be used to dose load the ETA/ETS trenches.

2. Each ETA/ETS trench is constructed to disperse effluent into downslope topsoil so that plantings can provide assistance by evapotranspiration.

Figure 4. – Conventional ETA Bed/Trench Details (Source: AS1547:2012 Fig. L6)

Good Construction Techniques:

Some General Considerations to follow

1) Excavation

a) Excavation shall not damage the soil by:

- Smearing: Where the soil is smoothed; filling cracks and pores.

- Compacting: Where the soil porosity is reduced.

- Puddling: Where washed clay settles on the base of the bed to from a

relatively impermeable layer.

Note: Cohesive soils, or soils containing a significant quantity of clay, are susceptible to

damage by excavation equipment during construction.

b) The spacing between individual ETA beds shall be not less than 1000mm. Individual bed

length shall be limited to 20m. The total bed length requirement shall be dived into

approximately equal individual bed lengths.

Page 42: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

c) Plan to excavate only when the weather is fine.

d) During wet seasons or when construction cannot be delayed until the weather becomes

fine, smeared soil surfaces may be raked to reinstate a more natural soil surface.

e) When excavating by machine, fit the bucket with ‘raker teeth’ if possible.

f) Avoid compaction by keeping people off the finished bed floor.

g) If rain is forecast, then cover any open beds to protect them from rain damage.

h) Excavate perpendicular to the line of fall or parallel to the contour of sloping ground.

i) Ensure that the bed inverts are horizontal.

2) Pipe Laying

a) A distribution box (or header) shall ensure even flow to each individual bed.

b) Effluent shall be distributed through perforate pipe laid parallel with the horizontal

bottom of the bed. The minimum internal diameter of the pipe shall be not less than

80mm.

3) Pre-Commissioning Test

A pre-commissioning test may be carried-out on pump-dosed systems after all on-site

components, including pump, have been installed but prior to backfilling the effluent-

distribution system in the bed:

Steps:

1. Fill pump to ‘pump-on’ level with potable water

2. Start pump

3. Check effluent distribution pipework to ensure water flows uniformly from all

perforations

4. Record time taken to pump from ‘pump-on’ level to the ‘pump-off’ level. This shall be

approximately 3 minutes.

Page 43: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

5. Follow pump manufacturer’s recommendations for commissioning pump

6. Check pumping main to ensure there are no leaks and that the air-release valve is

functioning

7. Check that the high-water level alarm operates

4) ETA Bed Backfilling

After installation of pipe-work, and any pre-commissioning test undertaken, the distribution

aggregate shall be carefully placed into each bed. This is done so as to avoid damage to the

bed floor, sidewalls and the pipe-work. The ETA profile must be:

- 50mm of sand

- 200mm of ‘no fines’ gravel

- A length of subsoil perforated pipe (100mm diameter)

- A layer of non-woven geo-textile

- 200mm of sand

- 100mm of topsoil high in organic material

- Dense grassland by seeding or turfing

The finished form should be mounded in cross-section to promote runoff of incident rainfall

and to allow for settling. Surface water shall be diverted around the perimeter and upslope

of the land-application area. Rainfall shall be shed from the mounded surface of the ETA beds.

Page 44: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

Design and Installation of On-site Wastewater Systems

147

Standard Drawing 11B – Evapotranspiration / Absorption Bed(not to scale)

Evapotranspiration / Absorption Bed Construction­

Design and Installation of On-site Wastewater Systems

14

inflow and take time to regenerate once higher flows restart. This can result in poor or ineffective treatment in the meantime.

For a proposed dwelling (including dual occupancies) the design wastewater loading must be determined using the ‘Neutral or Beneficial Effect on Water Quality Assessment Guideline 2011’ (Sydney Catchment Authority, 2011) based on:

• the number of potential bedrooms (which can’t change, unlike the number of occupants)

• the nature of the water supply ie whether the dwelling uses town or bore water, or tank water

• the wastewater loading per bedroom based on the nature of the water supply.

Table 2.1 should be used to calculate the daily wastewater load for a dwelling together with any specific requirements of the relevant local council. For other developments (non-dwelling) involving wastewater, refer to the ‘Septic Tank and Collection Well Accreditation Guideline’, (NSW Health, 2001) or other reference source approved by the Sydney Catchment Authority.

Table 2.1 – Design wastewater loading calculations (for a dwelling)

Design wastewater loading for each potential bedroom Reticulated / bore water Tank water

1-2 potential bedrooms 600L/d 400 L/d 3 potential bedrooms 900L/d 600L/d 4 potential bedrooms 1200L/d 800L/d More than 4 potential bedrooms

1200L/d plus 150L for each additional bedroom

800L/d plus 100L/d for each additional bedroom

Source: NorBE Assessment Guideline (Sydney Catchment Authority, 2011). Note: the Sydney Catchment Authority adopts a conservative approach for wastewater design calculations. Water saving fixtures should be standard in all new dwellings. Determine the effluent design loading rates or design irrigation rates using the values for the identified soil description (texture and structure) in Tables L1, M1 and N1 of AS/NZS 1547:2012. Use the conservative design loading rates for septic tanks, absorption trenches and beds.

Septic tanks for residential developments must be at least 3,000 litres. Larger tank capacities must be based on design wastewater loads detailed in Table J1 in AS/NZS 1547:2012. If a spa bath is proposed as part of a development, the minimum septic tank size must be increased by 500 litres.

For greywater-only systems, use a value of 65% of the design wastewater load calculated above. Otherwise greywater systems are treated exactly the same as other wastewater systems.

Linear loading rate for beds, trenches, sand and amended soil mounds The hydraulic linear loading rate is the amount of effluent that the soil around an effluent infiltration system can carry far enough away from the infiltration surface for it to no longer influence the infiltration of additional effluent (Tyler, 2001). It must be used in conjunction with the effluent design loading rates (DLR) from AS/NZS 1547:2012. DLRs assume there is no hydraulically limiting layer beneath the base of the disposal area; the linear loading rate is designed to ensure that the effluent cannot return to the surface as it travels downslope due to the presence of a hydraulically limiting layer.

Cross Section: Evapotranspiration / Absorption (ETA) Bed­

Plan View: Typical Large ETA Bed Layout (applicable only if pressure-dosed)

Plan View: Typical ETA Bed Layout­

A The base of the bed must be level to ensure even distribution of effluent. It must also be scarified to overcome any smearing during excavation. Base levels should be checked with a dumpy / laser level.

B 100 mm slotted PVC pipe. C 20-40 mm distribution aggregate. D 5-10 mm aggregate. E Clean local or imported topsoil (sandy loam to loam). F Allowance for settling after backfilling. G Grass must be established across the construction area as soon as possible. Trench / bed surface should be level or

slightly mounded. H Inspection port on downhill side of the bed. Made from 50 mm PVC pipe with perforations in the aggregate level of the

bed. I Fine sand (0.1 mm). J Bed dimensions are an example only. The basal area of the land application area must be determined according to the

procedures set out in AS/NZS 1547:2012 and this Manual. The location and orientation of the area should be based on a site and soil assessment by a suitably qualified person. The system may comprise a single trench / bed or multiple smaller trenches / beds. It is essential that effluent is distributed evenly to all units on a daily basis.

K Upslope stormwater diversion drain (see Standard Drawing No.10B for design detail). Subsoil drainage may be necessary on particular sites.

L 100 mm PVC gravity dosing pipe. M Gravity splitter box to distribute effluent evenly between two to four separate trenches / beds. Should also be used to

evenly dose multiple pipework within a single trench / bed. N Gravity, siphon or pump fed effluent from treatment system. Note 1 More than two distribution pipes will be required in beds wider than 4,000 mm. Care should be taken with beds wider

than 4,000 mm to ensure a level base.

Standard Drawing 11B - Evapotranspiration / Absorption Bed (not to scale)

147

Page 45: ‘ON SITE WASTEWATER MANAGEMENT REPORT · 2019-12-09 · 4 INTRODUCTION EnviroTech Pty. Ltd. has been engaged by the client to undertake an ‘onsite wastewater management study’

APPENDIX T - Pressure Dosed Beds Source: Design and Installing On-Site Wastewater Systems (SCA, 2012)