15
B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org 1 “Interconnectivity: Update on the status and foreseeable development in regional electricity interconnections” Republic of Belarus Zorich Andrey, Head of Strategic Development and External Investment Cooperation, Ministry of Energy of the Republic of Belarus INOGATE Regional Seminar on Security of Supply and Interconnectivity Brussels, Belgium, 10 th December 2015

“Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org

1

“Interconnectivity: Update on the status and foreseeable development in regional electricity interconnections”

Republic of Belarus Zorich Andrey, Head of Strategic Development and External Investment Cooperation, Ministry of Energy of

the Republic of Belarus

INOGATE Regional Seminar on Security of Supply and Interconnectivity Brussels, Belgium, 10th December 2015

Page 2: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

2

• Installed capacity of the Belarus energy system:

Total: 10 035 MW SPA “Belenergo”: 41 TPPs of capacity 9 298.2 MW and: 23 HPPs of capacity 26.3 MW 1 wind farm of capacity 1.5 MW 206 unit-plants of consumers, capacity 709 MW

• Length of power lines, total: 238.915 K km overhead 35-750 kV power lines 35.677 K km overhead 0,4-10 kV power lines 203.238 K km • Cable power lines 36.055 K km

Page 3: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

2013 (actual)

2014 (actual)

2015 (actual)

Generation of electricity by power plants of the SPA “Belenergo” (B kWh)

28.515 31.602 31.873

Heat generation (M Gcal) 35.989 34.376 34.253

Electricity import (B kWh) 6.716 3.826 2.803

Electricity export (M kWh) 346,010 508,246 0

Electricity consumption (brutto, mln. kWh) 37,694 38,035 38,537

KEY PERFORMANCE INDICATORS of the SPA «BELENERGO»

Page 4: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

Existing electricity interconnections

4

Условные обозначения :

Электростанция

Атомная станция

ПС 110 кВ

ПС 220 кВ

ПС 330 кВ

ПС 750 кВ

110 кВ

220 кВ

330 кВ

750 кВ

Page 5: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

2. Through capacity of the power networks of the energy systems of the Republic of Belarus with neighbouring

countries

5

1400 МВт – export, 2200 МВт - import 1000 МВт – export,

1200-1400 МВт - import

140 МВт (export)

900 МВт – export, 900 МВт - import

Page 6: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

Enhancing electricity connections between Belarus and Poland by power lines and back-to-back stations construction

Россь

ГРЭС-15

Брест-2 Lublin

Белосток Нарев Милосна

Козелице

Wolka Dobrynska

Wisznice Parczew

Biala Podl. Sitmicka Lukov Lubartow

Janow Podl. Hotowczyce

Tosice

Mosciska Plock

Ostrowiec

ОЭС Беларуси

ВЛ отключена

ВПТ Необходимо строительство ВЛ Барановичи-330 Гродно Южная Белорусская АЭС

Lобщ=98,8 км

Lобщ=117,5 км

Lобщ=27,7 км

80 км 37,5 км

56,25 км 42,5 км

12,5 км 15,2 км

12,5 км 15,2 км

ВПТ

110 кВ 220 кВ 330 кВ 400 кВ

Page 7: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

Enhancing electricity connections between Belarus and Poland by construction of a 400 kV power line Ross – Narev with

back-to-back station will allow to:

7

Increase the through capacity of Belarus – Poland section by about 7 times. Establish technical possibility for electricity export/import to/from Belarus/Poland of 5 B kWh annually. Modernise and develop the interface with minimum costs and within a short period and considering a possibility of usage of 220 kV Ross – Bielostok power line

Page 8: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

Volume of power network construction and capital investments under project of 400 kV lower line Ross –

Narev with a back-to-back station

Description Value

In the Republic of Belarus

Volume of electricity network construction 330-400 kV(km) 37.5 Capital investments (USD M) 165

In Poland

Volume of electricity network construction, 400 kV (km) 80 Capital Investments (USD M) 40 TOTAL

Volume of electricity network construction, 330-400 kV (km) 117,5 Project implementation Costs (USD M) 205

Page 9: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

Prospective sources of project financing

9

Internal funds of the Stakeholders Credits by the commercial banks Resources of International organisations

Page 10: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

Key challenges/ obstacles related with investments

10

Political environment Lack of guaranteed volumes of electricity

purchase/sale

To implement the project at the initial stage the stakeholders have to:

• Conduct a joint analysis of technical decisions in terms of compliance with national and EU

• Develop the justification of investments for representing its outcomes to the authorities

Page 11: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

11 11

Prospective scheme of the UES of Belarus for 2020

ВИТЕБСК

ЛУКОМЛЬСКАЯ ГРЭС

ОРША

МОГИЛЕВ КРИЧЕВ

ГОМЕЛЬ

ЖЛОБИН

СВЕТЛОГОРСК

МОЗЫРЬ

КАЛИЙНАЯ

СЛУЦК

МИКАШЕВИЧИ

ПИНСК БЕРЕЗОВСКАЯ ГРЭС БРЕСТ-2

РОССЬ

ГРОДНО ЛИДА

МИНСК СЕВЕРНАЯ

МИРАДИНО

БАРАНОВИЧИ 330

СТОЛБЦЫ

ПОЛЬША

ЛИТВА

РОССИЯ

УКРАИНА

ПОЛОЦК

СМОРГОНЬ

ИВАЦЕВИЧИ

БОРИСОВ

ТЭЦ-4

ИГНАЛИНСКАЯ АЭС

ТЭЦ-23

ТЭЦ-7

ТЭЦ-26

ТЭЦ-24

СМОЛЕНСКАЯ АЭС

АЛИТУС

ВИЛЬНЮС

ТАЛАШКИНО

ТЭЦ-14

БРЕСТ-1

ГРОДНО ЮЖНАЯ

ЧЕРНОБЫЛЬСКАЯ АЭС

ЧЕРНИГОВ

ТЭЦ-21

НОВОСОКОЛЬНИКИ

ЖЛОБИН ЗАП.

ТЭЦ-22

ТЭЦ-3

ОС

ИП

ОВ

ИЧ

И

ЛАПИЧИ

ТЭЦ-5

ПОСТАВЫ

ЦЕНТРОЛИТ

МО

ЛО

ДЕ

ЧН

О

БЕЛОРУССКАЯ

МИНСК ВОСТОЧНАЯ

ДУБ. ЛЕС

МОГИЛЕВ СЕВЕРНАЯ

КОЛЯДИЧИ

ГСМ

В. ДОБРЫНЬСКА

БЕЛОСТОК

Belarus – Ukraine Section

Page 12: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

12 12

Indicative values of through capacities for 2020

Page 13: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

13 13

Belarus – Poland

Page 14: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

14 14

Belarus - Lithuania

Page 15: “Interconnectivity: Update on the status and foreseeable ... · BUILDING PARTNERSHIPS FOR ENERGY SECURITY1. “Interconnectivity: Update on the status and foreseeable development

THNAK YOU!

Mr. Zorich Andrey Mikhailovich, Head of Unit on Strategic Development and External Investment Cooperation, Ministry of Energy, Republic of Belarus

[email protected]

INOGATE Technical Secretariat and Integrated Programme in support of the Baku Initiative and the Eastern Partnership energy objectives