Upload
aloha
View
15
Download
0
Embed Size (px)
DESCRIPTION
Antiproton Study Periods. Keith Gollwitzer DOE Tevatron Operations Review March 21, 2006. Simplified Review of Operations/Studies Mode. Stacking 120 GeV protons from MI through P1-P2-AP1 Target producing secondaries Li Lens Negative 8.9 GeV/c secondaries transported via AP2 beam line - PowerPoint PPT Presentation
Citation preview
f
Antiproton Study PeriodsAntiproton Study Periods
Keith GollwitzerDOE Tevatron Operations Review
March 21, 2006
DOE Tevatron Operations Review – Gollwitzer 2
f Simplified Review of Operations/Studies ModeSimplified Review of Operations/Studies Mode
Stacking 120 GeV protons from MI
through P1-P2-AP1 Target producing secondaries Li Lens Negative 8.9 GeV/c secondaries
transported via AP2 beam line Debuncher Ring to compress
phase space (7x )2 & (50x ) in 2s
Transfer via D/A Accumulator stack pbars while
compressing phase space (5x )2 & build a core
Reverse Protons 8GeV protons from MI Transfer line is P1-P2-AP1-AP3 Circulate in Accumulator D/A transfer (really “A/D”) Circulate in (or partial turn
through) Debuncher Extract “up” AP2 towards
target station
AP2
Debuncher
DOE Tevatron Operations Review – Gollwitzer 3
f BackgroundBackground
We had reached the point where the instrumentation and orbit control made it possible to attempt: Determining the orbit offset with respect to the
center of the quadrupoles of the Debuncher ring and the AP2 beam line
Correct the orbit to minimize the orbit-quad center offsets
Set the AP2-Debuncher injection region
Proposed two week period of studies Studies two shifts a day Third shift stack to support a lower luminosity
collider program Set for early December
DOE Tevatron Operations Review – Gollwitzer 4
f Execution – Round 1Execution – Round 1
TeVatron breaks on Monday Nov 21 Scramble to find people for holiday weekend for start of
studies First finished preliminary studies to set procedures to be
used during studies period Institute third shift to investigate D/A beam line
15 days of reverse protons Debuncher: beam-quad center offsets, orbit correction and
centered devices about new orbit• D/A beam line done on owl shifts
AP2 & Debuncher Injection region: scanning and setting strengths of kicker and septum
AP2: beam-quad center offsets & orbit correction 4 days of stacking studies/start-up
Steer secondaries beam onto AP2 reverse proton BPM positions
Center Debuncher devices about beam General tune-up of kickers, RF, cooling systems, etc.
DOE Tevatron Operations Review – Gollwitzer 5
f Preliminary WorkPreliminary Work
Checkout of BPMs Preparation of timeline to
acquire beam without much interruption to ν program
Commissioning of TBT program for D/A into Debuncher for reverse protons
Procedures for extracting reverse protons from the Debuncher into the AP2 beam line
Attempt to minimize the effects of the Debuncher rotator cavities on the injected reverse protons
DOE Tevatron Operations Review – Gollwitzer 6
f Commissioned ItemsCommissioned Items
Debuncher Reverse Proton Turn-By-Turn system Debuncher Reverse Proton partial turn extraction up
AP2 Debuncher Component Centering application Debuncher Orbit-Quad offset procedure AP2 Orbit-Quad offset procedure AP2 Beam Line Correction for reverse protons One-Shot Timeline for establishing circulating
Debuncher beam Admittance measurements from data-logger “Deb Heat Rev p’s to AP2” sequencer aggregate Procedure for setting up the AP2-Debuncher Injection
region Procedure for D/A Beam Based Alignment Accumulator local vertical bump at injection
DOE Tevatron Operations Review – Gollwitzer 7
f Debuncher Work - 1Debuncher Work - 1
Determination of orbit-quad center offset Change quad excitation and look for orbit change 68 quads have shunts
• 10 quads have ability to control excitation alone• The rest are paired symmetrically about mid-point of straight
section Concern about excitation of two quads at one time and
determining offsets for each quad• Did quad excitation orbits for nominal orbits as well as for two
1-bumps per plane– Checked for consistency of change in offset determination
with the change of orbit due to the 1-bumps Vertical Orbit Correction
Attempted global fit to minimize orbit-quad center offsets• Re-checked orbit-quad center offsets: no improvement
– Use of motorized quad stands as correction devices Local orbit corrections to minimize orbit-quad center
offsets• Re-check while working around the ring: all <1mm offset
DOE Tevatron Operations Review – Gollwitzer 8
f Change in Debuncher Vertical OrbitChange in Debuncher Vertical Orbit
Several places the orbit changed by ~1cm Angle change at injection area All vertical trims and a majority of the
motorized quad stands were used to perform the correction
DOE Tevatron Operations Review – Gollwitzer 9
f Debuncher Work - 2Debuncher Work - 2
Horizontal Orbit Correction Injection Region was
only done Horizontal orbit-quad
center offsets determined
Centered motorized devices about orbit Total of 72 motors
Lattice measurements were performed
DOE Tevatron Operations Review – Gollwitzer 10
f Setting Injection RegionSetting Injection Region
Extracted beam up AP2 from Debuncher and determine orbit-quad center for the three down-stream most quads Determined horizontal closed orbit and AP2 orbit are
centered in quads.
Set vertical closed orbit to nestle under the septum
Determine kicker strength to center beam in septum
Determine septum strength to put beam in the center of the three AP2 quads
DOE Tevatron Operations Review – Gollwitzer 11
f AP2 WorkAP2 Work
Able to have reverse protons every 15 seconds Determine downstream AP2 orbit-quad center
offsets Not able to do upstream due to bussed quads and
few BPMs to make offset determination
Corrected orbit to minimize offset Summary of orbit changes for reverse protons
Several places big changes, largest 2cm Large vertical angle at the end of AP2
Lattice measurements Installed new lattice which believed to better
match Debuncher
DOE Tevatron Operations Review – Gollwitzer 12
f AP2 Orbit ChangeAP2 Orbit Change
DOE Tevatron Operations Review – Gollwitzer 13
f Limiting ApertureLimiting Aperture
Running wave pointed to Debuncher transverse Schottkys
Will be discussed more in next talk
DOE Tevatron Operations Review – Gollwitzer 14
f Stacking StudiesStacking Studies
Steered secondaries to the vertical BPM positions found during the reverse proton studies
Steered to horizontal downstream BPM positions Upstream, the momentum distribution affects the
horizontal position
Problems with AP2 orbit “wandering” Traced to 120GeV protons starting with Main Injector Associated with amount of time between cycles
• Consistent cycle time is best Developed auto orbit correction program
• Does 120GeV proton correction• Then does AP2 secondaries correction• Identified need for additional AP2 trims
Centered Debuncher pickups
DOE Tevatron Operations Review – Gollwitzer 15
f Orbit Wandering – Stabilizing OrbitOrbit Wandering – Stabilizing Orbit
H
H
V
V
5mm
10m
m
10m
m
Wandering
Stabilized
AP1 Horiz. AP2 Vert
DOE Tevatron Operations Review – Gollwitzer 16
f Early JanuaryEarly January
Wrote up results from the December studies period
Prepared to install new AP2 trims Prepared to remove Debuncher transverse
Schottkys Determined if had more Debuncher quad
shunt freedom, then be able to change lattice Increase Debuncher admittance Removes Vertical Band 4 Arrays as limiting aperture Control was split for 6 pairs of quads
DOE Tevatron Operations Review – Gollwitzer 17
f Middle of JanuaryMiddle of January
Second TeV failure allowed for more dedicated time Installed two of four AP2 trims Obstruction search of AP2 beam pipe Removed Debuncher transverse Schottkys
• Tune measurements, main function, replaced by stochastic cooling pickups
Reverse protons to correct horizontal Debuncher orbit to quad centers in straight sections
• Correction in arcs would lead to energy change that we were not prepared to do at the time
Installed new Debuncher Lattice• Small change to AP2 lattice for matching
Centered Debuncher Devices about reverse proton orbit
DOE Tevatron Operations Review – Gollwitzer 18
f More JanuaryMore January
TeV repair period allowed Running Wave identified the Extraction Kicker as the
limiting aperture in both planes.• Vertically bumped beam 2mm and essentially achieved
goal• Horizontally could bump beam 8mm and make
admittance larger; but bump in dispersion changes beam energy
– Await shutdown work to motorize the kicker stand Different horizontal orbit also affected Extraction
• Optimized Debuncher EXtraction bump for D/A transfers
– Ramp correctors near end of Debuncher stacking cycle so that cooled smaller beam is closer to septum when kicker fires
• Also tuned extraction kicker and septum strengths to steer beam in D/A beam line
DOE Tevatron Operations Review – Gollwitzer 19
f FebruaryFebruary
Intensity Studies Measurement of intensities through the stacking
cycle• Function of stack cycle time (see next talk)• Function of proton intensity on target (see next slide)
– Also monitored proton beam quality
Accumulator Cooling studies Stacktail and Core systems (future slide)
Accumulator Aperture Investigation for less than two days (next talk)
DOE Tevatron Operations Review – Gollwitzer 20
f Intensity study – 4s cycle periodIntensity study – 4s cycle period
Injected intensity into Accumulator
Intensity end of Debuncher cycle
Intensity at end of AP2
Stacking rate
Proton beam on target
Nor
mal
ized
to B
eam
on
Tar
get a
nd 6
Boo
ster
turn
sCooling was optimized after each change of proton intensity
Many other diagnostics and settings were recorded – Flux to Accumulator is fine – Look to Accumulator Cooling
Early F
ebruary
DOE Tevatron Operations Review – Gollwitzer 21
f Stacktail System and the Core 4-8 GHz SystemStacktail System and the Core 4-8 GHz System
Had been using 4-8 GHz system as a helper for the 2-4 GHz core system. Decided it was time to move to 4-8 GHz. Because the 4-8 GHz core system runs at twice the frequency,
the electrodes are ½ the size so the system has a factor of two smaller momentum reach.
Moving the core closer to Stacktail to accommodate the smaller reach resulted in system instabilities at moderate stacks.
• Several attempts were made and we learned from each
We now : Use the 2-4 GHz core momentum system to augment the hand-
off between the Stacktail and the 4-8 GHz core momentum system
Run the 4-8 GHz core momentum system at MUCH larger gain.• Plans to increase the gain of the system
Run the Stacktail during deposition debunching to pre-form the distribution to match the Stacktail profile
Result: 20.1 mA/hr
Early F
ebruary
DOE Tevatron Operations Review – Gollwitzer 22
f Stacking PerformanceStacking Performance
DOE Tevatron Operations Review – Gollwitzer 23
f Stacking PerformanceStacking Performance
Best stacking for 1 hour for each day
Average Stacking rate for a week
DOE Tevatron Operations Review – Gollwitzer 24
f SummarySummary
We were able to take advantage of the TeVatron failures Two long periods of studies
Due to instrumentation and orbit control upgrades of the past few years, significant progress was done on the Debuncher admittance and progress made on the AP2 orbit How much? Next talk
We understand how to keep the studies on track for the lengthy time period Three study chiefs met 2-3 times daily to access
progress and direction
See an almost 25% increase in stacking See an almost 25% increase in stacking rate.rate.