Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Annual Report: 2017-18
��
�
ANNUAL REPORT
2017-18
BRAHMAPUTRA BOARD
BASISTHA, GUWAHATI
Annual Report: 2017-18
��
�
I
Annual Report: 2017-18
��
�
ANNUAL REPORT OF BRAHMAPUTRA BOARDFOR THE YEAR 2017-18
��������
Chapter– I General Page No
1.1 Brahmaputra Valley and its flood problems; establishment of Board’s office, giving the list of the members of the Board, number of Board’s meetings held and organisational set-up of the Board
89-97
1.2 Establishment of Brahmaputra Board and its Functions 97-98
1.3 High Powered Review Board Meeting 98
1.4 Meetings of Brahmaputra Board 99
1.5 Standing Committee of Brahmaputra Board 99
1.6 Meeting of Advisory Committee of NEHARI 99
1.7 Organizational set up of Brahmaputra Board 99
Chapter-II General Review
2.1 Administration and Organization 108
2.2 Finance, Accounts and Audit 108
2.3 Review in progress of works during 2017-18 109-112
Chapter-III Review of progress in preparation of Master Plan; Survey and Investigation; execution, maintenance and operation of multipurpose dams and other works; drawing up of standards and specifications for construction, operation and maintenance of dams; phased programme for construction by State Governments of all dams and other projects/ schemes incorporated in Master Plan
3.1 Progress of Survey and Investigation and Preparation of Master Plans, Detailed Project Reports (DPR) for Drainage Development Schemes and DPRs of Multi-Purpose Projects
113
3.1.1 Preparation of Master Plan 113-114
3.1.2 Current assignment for preparation of Master Plan 114
3.2 Drainage Development Schemes (DDS) 114-118
3.3 Survey and Investigation of Water Resources Projects 118-121
3.4 Construction Activities 122
3.4.1 Pagladiya Dam Project 122
3.4.2 Construction of Raised Platforms 122-123
3.4.3 North Eastern Hydraulic & Allied Research Institute 123-124
3.5 Flood Management and Anti-erosion Schemes(Implementation of Anti-erosion measures)
124
3.5.1 Anti-erosion measures completed 124
3.5.2. Implementation of Anti-erosion measures underway 125-129
3.6 Monitoring of Schemes under Flood Management Programme of Government of India
129-130
3.7 Review of the Brahmaputra Board Act ,1980 130
Chapter-IV Non-field Activities of the Brahmaputra Board during the year 2017-18
4.1 Complaint Committee on Sexual Harassment and Gender Justice 131
4.2 Vigilance and Disciplinary cases 131
4.3 Participation in Seminar/ Symposium/ Workshop / Training 132
4.4 Progressive use of Hindi 132-133
4.5 Formulation of Citizen’s Charter 134
4.6 Implementation of Right to Information Act-2005 (RTI) 134
4.7 Observance of Swachh Bharat Abhiyaan 134
II
Annual Report: 2017-18
��
�
Chapter-V Activities on Persons with Disabilities
5.1 Implementation of various provisions of persons with disabilities 137
5.2 The details of sanctioned posts and the number of persons with disabilities in various posts in group ‘A’, ‘B’, and ‘C’ against 3% vacancies
137
Chapter- VI Important Meetings during the year 2017-18
6.1.1 Meeting of High Powered Review Board of Brahmaputra Board 138
6.1.2 Brahmaputra Board Meetings 138-140
6.1.3 Standing Committee of Brahmaputra Board Meetings 140
6.2 Important meetings/events attended by Chairman/Vice-Chairman, Brahmaputra Board during the year 2017-8
141
Chapter- VII Annual Accounts and Audit by C&AG Office
7.1 Statement of Accounts 142-164
7.2 Significant Accounting Policies and Notes on Accounts 165-167
7.3 Separate Audit Report on the Accounts of the Brahmaputra Board for the year 2017-18
168-172
7.4 Balance Sheet of Brahmaputra Board Contributory Provident Fund Trust
173-175
LIST OF ANNEXURES
Annexure No.
Title Page No.
I Composition of the Brahmaputra Board 176-177
II Composition of the High Powered Review Board 178
III Organizational Chart of Brahmaputra Board 179
IV Statement of Regular Sanctioned Strength and numbers of Officers/Staff in position along with the status of SC, ST, OBC and PH as on 31.03.2018
180-181
V List of Officer and Staff undergone Training/Seminar/Workshop during 2017-18
182-184
VI List of Officers on deputation to other organization 185
VII RTI Annual Return Information System for the year 2017-18 186
VIII Status of Master Plans 187
IX Status of Drainage Development Schemes 188
X Status of Multipurpose Projects 189
III
Annual Report: 2017-18
��
�
LIST OF PHOTOGRAPHS AND PLATES
Sl. No. Description Page No
1 Jurisdiction Map of Brahmaputra Board 100
2
Bank pitching works by geobags- protection of Masalabari International boarder (Dhubri, Assam)
101
Retirement bund - protection of Mankachar, Kalair-alga scheme
3
63rdSpecial meeting of Brahmaputra Board held on 11th April, 2017 at Guwahati
102
Release of Study Report 1 D model for ‘Beta-Test’ on by IIT-Guwahati at Kaziranga by Hon’ble Union Minister of WR,RD&GR on 30.12.2017
4 Execution of Jengrai DDS, Majuli (24.03.2018) 103
5
64th meeting of Brahmaputra Board held on 29.06.2017 at HQ of Brahmaputra Board
104
65th Meeting of Brahmaputra Board held on 26.12.2017(adjourned)
6
Laying of RCC Porcupines at Majuli Island (16.03.2018)
105 Casting of RCC Porcupine at Neematighat (Jorhat) on 28.02.2018
7
1st Official Language Conference at Guwahati organized by Brahmaputra Board on 07.11.2017
106
Opening ceremony of Vigilance awareness week 2017
8 Spur No. 2 completed during 2017-18 at Majuli 107
9 Observation of Swachh Bharat Abhiyaan 135-136
IV
Annual Report: 2017-18
��
�
GLOSSARY FOR ABBREVIATIONS AND UNITS
ABBREVIATIONS
CWC Central Water Commission
DPR Detailed Project Report
DDS Drainage Development Scheme
IMD India Meteorological Department
GoI Government of India
MoWR,RD&GR Ministry of Water Resources, River Development & Ganga
Rejuvenation
SFC Standing Finance Committee
EFC Expenditure Finance Committee
NHPC National Hydroelectric Power Corporation
NEEPCO North Eastern Electric Power Corporation
EIA Environmental Impact Assessment
R&R Rehabilitation & Resettlement
EMP Environmental Management Plan
MPP Multipurpose Project
CEA Central Electricity Authority
SoI Survey of India
NOC No Objection Certificate
GSI Geological Survey of India
NE North Eastern
NER North Eastern Region
NEC North Eastern Council
NEHARI North Eastern Hydraulic & Allied Research Institute
CWPRS Central Water & Power Research Station
CSMRS Central Soil & Material Research Station
NH National Highway
BTC Bodoland Territorial Council
B & B Brahmaputra & Barak
PAFs Project Affected Families
PAP Project Affected People
PH Physically Handicapped
SC Scheduled Caste
ST Scheduled Tribe
V
Annual Report: 2017-18
��
�
UNITS
Cumec Cubic Meter per Second
Cusec Cubic Feet per Second
ha Hectare
MW Mega Watt
m Metre
sqkm Square Kilometre
ham Hectare metre
km Kilometer
Rs. Rupees
Rupees
ft. Feet
Cu.m Cubic Meter
M. ha Million Hectares
BCM Billion Cubic Meter
VI
Annual Report: 2017-18
�
�
Chapter– I
General:
Brahmaputra Valley and its flood problems; establishment of
Board’s office, giving the list of the members of the Board, number
of Board’s meetings held and organisational set-up of the Board
1.1 Brahmaputra and Barak Valleys and the Rivers of Tripura
1.1.1 Brahmaputra Valley and its flood problems
Brahmaputra, a trans-boundary river is one of the mightiest rivers of Asia. River
Brahmaputra is called Yarlung Tsangpo in Tibet. It emerges from Angsi Glacier, on the
northern side of the Himalayas in Burang County in southwestern part of Tibet
Autonomous Region (TAR) at an altitude of 4877 m. It flows through southern Tibet in
easterly direction for a considerable length, at an average height of 4000 m. At its
easternmost point of the reach, the river bends around Mount Namcha Barwa and
forms the Yarlung Tsangpo Canyon to enter India at Geling (near Tuting). The river
then flows down along the Himalayan foothills for 278 km to enter plains of Assam.
Here, the river is joined by 2 large rivers, Viz Dibang and Lohit at Kobo to form
Brahmaputra. The total length of the river from its source to outfall at Bay of Bengal is
2906 km, 1625 km in Tibet Autonomous Region, 918 km in India (278 km in Arunachal
Pradesh and 640 km in Assam) and 363 km in Bangladesh. The river drains an area of
5,80,000 sq km. An area of 293,000 sq km(50.51%) in Tibet (China), 45,000 sq
km(7.75%) in Bhutan, 194,413 sq km (33.52%) in India and 47,000 sq km(8.1%) in
Bangladesh.
Its basin in India is shared by six states namely, Arunachal Pradesh (41.88%), Assam
(36.33%), Nagaland (5.57%), Meghalaya (6.10%), Sikkim (3.75%) and West Bengal
(6.47%). Fig 1 shows rivers in the Brahmaputra Basin. The Brahmaputra is the
3rdlargest river in the world in terms of its annual discharge and carries highest silt load
amongst rivers of its size.
The Brahmaputra River, termed a moving ocean, is an antecedent snow fed river
which flows across the rising young Himalayan Range. Geologically, the Brahmaputra
is the youngest of the major rivers of the world. In the course of 2906 km journey, the
89
Annual Report: 2017-18
�
�
Brahmaputra receives as many as 22 major tributaries in Tibet, 33 in India and 3 in
Bangladesh.
Fig 1: Brahmaputra River Basin
During its course from Kobo to Dhubri in Assam, about 26 important tributaries on its
north bank and about 13 on south bank join the river. Some of the north bank
tributaries originate from snow clad Himalayas and others from the lower Himalayas.
The total annual flow of the river is about (Avg: 615 BCM/year) BCM at Jogighopa,
which is 29% of the total surface flow of the country. Average width of the
Brahmaputra Valley is 80 km, out of which the river itself occupies about 6 km to 10
km.
The river is braided and unstable in its entire reach in Assam except for a few
locations. The instability of the river is attributed to high sediment charge, steep slope
and transverse gradient. Apart from these, the entire area is in a seismic zone and
quite often receives earthquake shocks of moderate to severe intensity. The problem
further gets aggravated due to landslides caused by high rainfall. Some manmade
avoidable actions in the form of shifting cultivation and non-scientific commercial
exploitation of forest, etc. have also accelerated the process of soil erosion in the
catchments. The silt brought in due to erosion in the hill catchment gets deposited as it
enters into the plains of Brahmaputra Valley due to sudden reduction in slope with the
consequent reduction in the flow velocity and sediment carrying capacity. Due to heavy
deposition of silt, the river frequently changes its course on its way. Excessive silt
deposition has also given rise to braiding and meandering pattern in the alignment of
the river system. ‘Majuli Island’, the largest inhabited river island is located in the
Brahmaputra in upper Assam.
The left bank tributaries of the river Brahmaputra originating from older geological
regions of Arakan hill and Khasi hills with flatter slopes, are more stable as they carry
less sediment of finer size. By hypsometric analysis of the tributaries, it is seen that the
90
Annual Report: 2017-18
�
North bank tributaries indicate
indicate a mature stage. This has given rise to inh
to shift its course towards south and the river flo
along its left bank.
The floods in Brahmaputra Valley is a recurring phenomenon and
large scale devastations
below:
(a) Physiographic condition:
about 80-90 km and confined between hills.
occupies 6-10 km,
foothills. Tea gardens in certain portions of the v
Only the balance area of the valley
lying fields. This adverse topographical feature
vulnerable regions
Fig 2
2 Meteorological situation:
receives very high annual rainfall ranging from 248
during 5 rainy months and to
rainfall is also quite high. Rainfall of more than
valley and rainfall around 70 mm per hour is also n
rainfall in a day,
conditions favour heavy flooding in the valley. Fig
Brahmaputra basin in India.
���
bank tributaries indicate relatively young stage while the South bank tributa
indicate a mature stage. This has given rise to inherent tendency of river Brahmaputra
to shift its course towards south and the river flows by the side of hills at many plac
in Brahmaputra Valley is a recurring phenomenon and
devastations every year. The reasons for floods
Physiographic condition: The 650 km long Brahmaputra valley
and confined between hills. Out of the total width,
, and forest covers a few km of the valley width mostly al
foothills. Tea gardens in certain portions of the valley occupy much of
balance area of the valley is inhabited where cultivation is done mostly in low
lying fields. This adverse topographical feature and settlement of populace in the
vulnerable regions is a major cause for frequent and damaging floods
Fig 2: physiographic condition of the valley
Meteorological situation: Area under Brahmaputra basin in North East region
receives very high annual rainfall ranging from 248 cm to 635, concentrated largely
during 5 rainy months and to a lesser extent, in the 3 pre-monsoon months. Intensity of
rainfall is also quite high. Rainfall of more than 40mm in an hour is frequent in the
valley and rainfall around 70 mm per hour is also not uncommon. As high as 500mm of
has been recorded at several locations. Overall, meteorologi
conditions favour heavy flooding in the valley. Fig. 3 shows the annual rainfall of the
basin in India.
91
relatively young stage while the South bank tributaries
erent tendency of river Brahmaputra
ws by the side of hills at many places
in Brahmaputra Valley is a recurring phenomenon and has been causing
can be summarized as
The 650 km long Brahmaputra valley in Assam is only
Out of the total width, the river itself
orest covers a few km of the valley width mostly along the
alley occupy much of the high land.
inhabited where cultivation is done mostly in low
and settlement of populace in the
for frequent and damaging floods in the valley.
Area under Brahmaputra basin in North East region
cm to 635, concentrated largely
monsoon months. Intensity of
40mm in an hour is frequent in the
ot uncommon. As high as 500mm of
recorded at several locations. Overall, meteorological
. 3 shows the annual rainfall of the
Annual Report: 2017-18
���
�
Fig. 3�
(c) Topographic conditions: The narrow valley of Assam is surrounded by hills. The
main stem of Brahmaputra (Siang) and most tributaries joining it in the valley have high
gradient in these hills. Whenever there is heavy rainfall in the hills, huge quantities of
rain water comes down as runoff to the valley within a short duration due to steep
gradients. As Brahmaputra and these tributaries have flat gradients in the valley, this
water cannot be carried forward immediately. To accommodate itself, the excess
water swells and spreads out overflowing riverbanks and causing floods.
(d) Earthquake and landslides: The NE region is highly seismic and geologically
unstable. As a consequent of these earthquakes, debris and loose earth from the
landslides roll down are washed away by the mountain streams. These are deposited
in the river beds of the valley thus aggrading it. This results in the reduction of the
carrying capacity of Brahmaputra in the subsequent years after a major earthquake
thereby accentuating floods and erosion problem in the valley.
(e) Encroachment of floodplains: In 1940-41, the population density of Brahmaputra
valley was quite low ranging from 9 to 29 person/sq km in different districts of Assam.
As per present trend, population density is 200 person/sq km in the plain areas of
Assam. It has led to increased pressure on the limited land resource of the valley,
encroachment of floodplains and thereby accentuating the flood problem in the valley.
(f) Embankment Breaches: Undoubtedly, embankments have provided reasonable
protection against floods since their construction. However, many of the embankments
are more than four decades old. Maintenance deficit and subsequent higher levels of
floods combined with river bed aggradations has led to breaches of these
embankments causing floods and inundation in protected areas.
Main causes of Erosion in the Brahmaputra Basin
Similar to floods, erosion is an equally, if not more, serious problem. Erosion causes
permanent loss of land to the valley’s agro-based people, turning them into paupers. A
bank line study of the Brahmaputra River carried out with satellite imagery from 1988
92
Annual Report: 2017-18
���
�
to 2015 reveals that there has been a total erosion of 798 sq km against total
deposition of only 208 sq km during this period. Even this deposited land doesn’t have
immediate value as the same can be utilized for agricultural purpose only after the
formation of the top soil, which generally takes several years. Study done in the Master
Plan of main stem of Brahmaputra also reveals that the average erosion between the
years 1954 to 1969 has been about 80.51 sq km with 6000 families losing their land
annually.
In fact, floods and erosion are interrelated. Floods are intricately linked to causes of erosion whereas erosion leads to floods in many cases. The extent of loss due to erosion in the valley varies from year to year depending on the severity of floods.
However, the main reason for erosion by Brahmaputra is that it is an extremely braided river. The characteristic features of a braided river configuration such as Brahmaputra are a wide channel, unstable and poorly defined banks and shallow water. The watercourse consists of a number of entwined channels, divided by islands, which meet, cross and separate again. During floods, the channels are combined, most of the sand bars get submerged and the river appears to be a wide straight unbroken channel.
The main causes which seem to bring about braiding of the Brahmaputra river are:
a. Steep slopes b. An abundant bed load c. Erodible banks and d. A highly variable discharge.
Results of various studies on Erosion in Brahmaputra
It was concluded in the main stem Master Plan that from 1923 and 1954, erosion has happened in 230 Km reach of the Brahmaputra
Study in the Master Plan concluded that erosion was 1927 sq km and deposition was 334 sq km between
Recent Study of satellite imagery by Board reveals erosion was 739 sq km and deposition was 209 sq km from 1988 to 2016
A Study by IITG shows that erosion from 1970s to 1990 in North Bank is 543.72 km2&South bank is 744.06 km2. Deposition during this period was 30.84 km2 in North Bank and 87.56 km2 south bank
93
Annual Report: 2017-18
���
�
PERIOD WISE EROSION & DEPOSITION FOR BRAHMAPUTRA RIVER
Crops grown in the Brahmaputra Valley are paddy, jute, mustard, pulses, wheat and sugarcane. Paddy and jute are mainly grown and harvested during monsoon period. Out of four types of paddy crops viz. the Ahu, Sali, Bao and Boro, which constitute about 92% of the cropped area, the first two namely Ahu and Sali are generally affected by floods. The maximum area affected due to floods in the Brahmaputra Valley (including Barak) during the period 1953-2011 was approximately 6.05 M.ha (Arunachal Pradesh 2010 - 0.3M.ha, Assam1988 - 3.82 M.ha, Manipur 1987- 0.116 M.ha, Meghalaya 1987 - 0.095 M.ha, Mizoram 1993 - 0.541 M.ha, Nagaland 1993 - 0.009 M.ha, Tripura 1963 - 0.33 M.ha and Sikkim 2000 -1.17 M.ha)(Source- CWC report November 2012). The flood damage includes crop damage and the permanent loss of land due to erosion. A number of lives are also lost during each flood.
The flood and river management measures adopted so far in the valley are area specific and mostly of short term structural measures such as construction of embankments, permeable and impermeable spurs, revetments etc. The poor maintenance of the flood management structures generally causes unexpected miseries to the people in case of their failure. The efficacy of these measures especially in the river system of Brahmaputra, which is highly aggrading/ degrading in different reaches, is also debatable. As such, there is a need for constructing storage reservoirs in combination with other structural/ non-structural measures after studying the river behavior using scientific tools.
For management of floods, erosion control and improvement of drainage congestion, Brahmaputra Board has prepared Master Plans of the Brahmaputra main stem and its 39 tributaries and for Majuli Island. There is also a need to implement the various recommendations made in the Master Plans of Brahmaputra sub-basin prepared by Brahmaputra Board. The regional Task Force “B” for flood management in N.E. Region has also submitted its report to the MoWR, RD&GR, which should be taken into consideration for early implementation in a time bound manner.
1.1.2 Barak Valley
The river Barak is a part of the Ganga-Brahmaputra-Meghna system and is the second largest river of the N.E. Region having eight major tributaries. It originates from a hill east of Mouthana at an elevation of about 2840 m in the southern slopes of Nagaland/Manipur. The Barail, Patkai and Lushai hills bound the sub-basin on its three sides. Total catchment area of the Barak sub-basin up to Indo-Bangladesh border is 41,704 sq km out of which 751 sq km lies in Myanmar. The annual flow from Indian catchment is 29.6 BCM at Badarpurghat. The length of the river from its source up-to Bhanga in Karimganj district is 532 km after which the Barak bifurcates into two
���
�����
�����
�����
�����
�����
�����
����
����
�����
� ������
��
�� ���
� ������������
����������
94
Annual Report: 2017-18
���
�
branches known as the Surma and the Kushiara. These two branches enter Bangladesh and again join to form a single river channel and flow up to Bhairab Bazar where it meets with Meghna in Bangladesh.
The river Barak is joined by a number of hill streams on both its banks. Flood occurs frequently in this valley causing extensive damage to lives and properties. In order to manage the problem of flood, erosion and drainage congestion, various measures have been taken from time to time by way of construction of embankments, bank protection and drainage improvement works etc. These measures have provided adequate protection to the people of the valley against low and medium floods. However, in case of high floods, embankments are not able to withstand heavy pressure, consequently number of breaches occur which cause devastating floods in the valley. In order to deal with the problems of flood, bank erosion and drainage congestion, the Brahmaputra Board has prepared Master Plans for the Barak sub-basin and Dhaleswari, one of the major tributaries of Barak.
1.1.3 Rivers of Tripura
There are ten important rivers in Tripura, namely Longai, Juri, Deo, Manu, Dhalai,
Khowai, Haroa, Gumti, Muhuri and Fenni. These rivers causing frequent flood in the
State. Based on investigation and data collected from state Government and various
other Central Agencies, the Brahmaputra Board has prepared Master Plans for all
these rivers and these have been approved by the Central Government. The Master
Plans envisage various structural and non-structural measures to tackle flood, erosion
and drainage congestion problems. The Feni flows through the “No man’s land” of
Indo-Bangla border and its right bank falls in India. The Master Plan of Feni River is
taken up for survey and investigation preparation. Feni river, being the International
95
Annual Report: 2017-18
���
�
Boundary, there are some difficulties in carrying out ‘Survey & Investigation’ works on
account of which preparation of Master Plan is time-consuming.
������������ ����
Rivers System of Tripura
1.1.4 Rivers of Meghalaya
MoWR, RD&GR through Office Memorandum No. 19/2/2010-B&B/3563-3580 dated 3rd
September 2010 constituted a ‘Joint Team’ under the Chairmanship of Chief Engineer
(P&D) (now Chief Engineer-I), Brahmaputra Board in matter related to Integrated
Water Resources Development in the State of Meghalaya. The ‘Joint Committee’
identified 18 rivers of Meghalaya for preparation of Master Plans. Master Plans of 6
rivers out of these have already been approved by Govt of India. Master Plan of 3 sub-
basins formulated by the Brahmaputra Board are in various stages of approval. Out of
the remaining 9 Master Plans, draft Master Plans of Ganol, Waikhyrwi, Umtru and
Umsohryngkew were completed. However, these are under modification as per
suggestion of MoWR,RD&GR.
��������������� ��������������������
Rivers of Meghalaya draining to Bangladesh
96
Annual Report: 2017-18
���
�
1.1.5 Rivers of Sikkim and West Bengal draining into Brahmaputra River
Basin
Teesta, Jaldhaka, Torsa and Sankosh-Raidak are four river systems of Sikkim and
West Bengal that outfall into river Brahmaputra. Master Plans for all the four sub-
basins have been formulated. These four Master Plans have been approved by Board
and were submitted for approval of Government of India after compliance of
observations of MoWR, RD&GR.
1.1.6 Imphal River in Manipur
The Imphal River emerges in the highlands to the west of Kangpokpi and flows
towards the south. Brahmaputra Board is in the process for formulation of a Master
Plan of Imphal River.
1.2 Establishment of Brahmaputra Board and its Functions
The Brahmaputra Board, an autonomous statutory body, was set up under an Act of
Parliament called the ‘Brahmaputra Board Act, (Act 46 of 1980)’ under the then
Ministry of Irrigation (now Ministry of Water Resources, River Development & Ganga
Rejuvenation). The jurisdiction of Brahmaputra Board includes both the Brahmaputra
and Barak Valleys and covers all the States of the North Eastern Region including
Sikkim and part of West Bengal falling under Brahmaputra basin. The Board consists
of 21 Members under the Chairman, Brahmaputra Board (4 full time Members and 17
part time Members), List of Members of the Board appointed under clause (A), (B), (C),
(D) & (E) of sub-section (3) of section (4) is at Annexure-I
Since creation of the Ministry of Development of North Eastern Region (DoNER) and
inclusion of Sikkim and part of West Bengal falling in Brahmaputra Basin within the
jurisdiction of Brahmaputra Board, the Secretary of DoNER; the Secretary, I&FCD,
Sikkim; the Secretary, Irrigation and Waterways Department, West Bengal are included
as Special Invitees in Board meetings along with the Chief Engineer (B&BB), CWC,
Shillong and Adviser (NE), NITI Aayog (former Planning Commission).
The Board started functioning with its Headquarters at Guwahati from 11.01.1982. As
per sub-section (2) of section (3) of the Brahmaputra Board Rules, 1981 Board has
established a Liaison Office at New Delhi.
A High Powered Review Board to oversee the work of the Brahmaputra Board was
constituted with the Union Minister of Water Resources as the Chairman. List of
Members of the High Powered Review Board appointed by the Government of India
97
Annual Report: 2017-18
���
�
vide Resolution No. 2(17)/80/FC/460 dated 19.03.1982 and as amended vide
Resolution No.23/8/925-ER dated 01.10.1992 is at Annexure-II.
1.2.1 Functions of the Brahmaputra Board
The main functions of Brahmaputra Board stipulated in the Act are –
(a) Carry out surveys and investigations in the Brahmaputra Valley (within its jurisdiction)
and prepare Master Plans for the control of floods and bank erosion and improvement
of drainage in the Brahmaputra Valley. The Board shall have regard to the
development and utilization of water resources of the Brahmaputra Valley for irrigation,
hydro power, navigation and other beneficial purposes and shall, as far as possible,
indicate in such plan the works and other measures which may be undertaken for such
development;
The Master Plan shall be submitted to the Central Government as soon as may be
after it has been prepared or, as the case may be revised and the Central Government
shall, after consultation with the State Governments concerned, approve the same
subject to such modifications as it may deem fit.
(b) Formulation of programme, in consultation with State Government(s), for construction /
implementation, in phases, of dams and other projects identified in the Master Plans,
approved by Government of India;
(c) Preparation of Detailed Project Reports and estimates including apportionment of cost
among States in respect of the dams and other projects;
(d) Finalization of standards and specifications for construction, operation and
maintenance of such dams and other projects and;
(e) Construction, operation and maintenance of Multipurpose and other Water Resources
Projects, identified in the Master Plans, on approval of Government of India;
(f) Perform any other function which may be prescribed for the proper implementation of
this Act.
(g) Perform such other functions as are supplemental, incidental or consequential to the
functions specified in section 12 or in clauses (a) to (d), or prescribed under clause (e),
of this sub-section.
1.3 Meeting of High Powered Review Board
9th Meeting of ‘High Powered Review Board’ of Brahmaputra Board was held on
30.12.2017 at Kaziranga, Assam
98
Annual Report: 2017-18
��
�
1.4 Meetings of Brahmaputra Board
3(three) Board meetings were held during the financial year. The 63rd Special meeting
of Brahmaputra Board was held on 11th April 2017 at H. Q. of Brahmaputra Board,
Basistha, Guwahati to discuss the Proposal of Restructuring of Brahmaputra Board
where all the Members representing the States under its jurisdiction participated. The
64thmeeting was held on 29th June 2017 at H. Q. of Brahmaputra Board, Basistha,
Guwahati with normal agenda of functioning of the Board. The 65th meeting was
convened on 26th December 2017 at H. Q. of Brahmaputra Board, Basistha, Guwahati
which was adjourned for want of quorum and the adjourned meeting of Brahmaputra
Board was held on 27th March 2018 at Brahmaputra Board Complex, Basistha,
Guwahati-29.
1.5 Standing Committee of Brahmaputra Board
2(two) meetings 58th & 59th of Standing Committee of Brahmaputra Board were held
during the year on 21.6.2017 (58th) and 26.12.2017 (59th).
1.6 Meetings of Advisory Committee of NEHARI
1st Meeting of Advisory Committee of NEHARI was held on 06.10.2017 under the
Chairmanship of Chairman, Brahmaputra Board at Brahmaputra Board Complex,
Basistha, Guwahati-29.
1.7 Organizational Set-up of Brahmaputra Board
A chart showing the existing organizational set up of the Board is given at Annexure-III.����
99
������������
Annual Report: 2017-18
��
�
���� ��
���� ��
��!"#
���
-�$
���JU
RIS
DIC
TIO
N O
F B
RA
HM
AP
UT
RA
BO
AR
D������� !�!��"� �##���
����
�$� !��%�&��!�'��(���
�)��*+,�+� "�
-��$��(. �"����$. �.� "�
/� 0�����(�/��! �*!�
1�����$��(�����
100
Annual Report: 2017-18
���
�
%��&���'�(��)*���+)�������� �,��(������-�!.)�� /0���(1���2#����-�!(�3���� 4)�$�BANK PITCHING WORKS BY GEOBAGS- PROTECTION OF MASALABARI, INTERNATIONAL BOARDER (Dhubri, Assam)
5�*����6*�����,�����7��-�����8�&9:���+������ 4)�$�RETIREMENT BUND - PROTECTION OF MANKACHAR, KALAIR-ALGA SCHEME
101
Annual Report: 2017-18
���
�
�������;;����<=;>���� ���������������������������� ��!�?@�"��#�$%&��'�63rdSpecial meeting of Brahmaputra Board held on 11th April, 2017 at Guwahati
������@=A;<A<=;>������BC������6�C��(�(�#-����D���(���������(��$����������� ���1���� .E���
���1��� ���&���'�(��9F9F*��������*��G������1*�&*�+*��� �H�I�)J����K�I��I�!LM��;�1��N������
D���ORelease of Study Report 1 D model for ‘Beta-Test’ on by IIT-Guwahati at Kaziranga by
Hon’ble Union Minister of WR,RD&GR on 30.12.2017
102
Annual Report: 2017-18
���
�
��(�)���*���+�#���+�,�!�-�����������*�.�����2<PA=@A<=;Q3EXECUTION OF JENGRAI DDS, Majuli (24.03.2018)
��(�)���*���+�#���+�,�!�-�����������*�.����EXECUTION OF JEGRAI DDS, Majuli
103
Annual Report: 2017-18
���
�
�������<RA=?A<=;>�������������� ���/0������������������������ ��!�12�"���'�64th meeting of Brahmaputra Board held on 29.06.2017 at HQ of Brahmaputra Board
�������<?A;<A<=;>��������������������� ��!�13�"���'� 4�,56 �765th Meeting of Brahmaputra Board held on 26.12.2017(adjourned)
104
Annual Report: 2017-18
���
�
�������8�"���9��9�+"�+"���:�� ��;�����<�=����2;?A=@A<=;Q3�Laying of RCC Porcupines at Majuli Island (16.03.2018)
�
*����">���4��9���7����<QA=<A<=;Q�����9�+"�+"���:�� ��;��������,�� �Casting of RCC Porcupine at Neematighat (Jorhat) on 28.02.2018
105
Annual Report: 2017-18
���
�
�������?@ABBAC?B@�������������� �8��9�� ������������������5��9��D�&��+E�%��1st Official Language Conference at Guwahati organized by Brahmaputra Board on
07.11.2017
+�� ����� F����+G����C?B@����H8>����+�Opening ceremony of Vigilance awareness week 2017
106
Annual Report: 2017-18
���
�
��C�����6�<=;>&;Q��� ��N����S���K��������+����&<�Spur No. 2 completed during 2017-18 at Majuli
107
Annual Report: 2017-18
���
�
Chapter – II
General Review
2.1 Administration and Organization
����������� ���������A High Powered Review Board to oversee the work of the Brahmaputra Board was constituted with the Union Minister of Water Resources as the Chairman, Chief Minister of Assam, Arunachal Pradesh, Manipur, Meghalaya, Mizoram, Nagaland & Tripura and Union Minister / Ministers of State for Finance, Transport, Power, Agriculture, Water Resources,RD&GR, Secretary, Ministry of Water Resources, RD&GR, Chairman, Central Water Commission as Members and Chairman, Brahmaputra Board as the Member-Secretary. Member (RM), CWC is a permanent invitee.
Brahmaputra Board: The Brahmaputra Board was constituted in 1980 by an Act of Parliament Brahmaputra Board Act, 1980 (No. 46 of 1980). The Board consists of the Chairman, Vice-Chairman, General Manager as full time Member, Financial Adviser Ex-officio member and 17 part time Members representing 7 States of the North Eastern Region, North Eastern Council, concerned Ministries of Government of India namely Water Resources, Finance, Agriculture, Power, Surface Transport and Organisations of Government of India, namely Central Water Commission, Central Electricity Authority, India Meteorological Department and Geological Survey of India.
������������������A Standing Committee is also constituted by Government of India with Chairman/Vice-Chairman as Chairman and Member (RM), Central Water Commission, Secretary Water Resources, Government of Assam, Financial Adviser, Brahmaputra Board as Member and General Manager, Brahmaputra Board as Member Convener to examine the Annual Action Plan / Budget Allocation, decide priority of works and exercise the financial power and delegate financial powers.
2.2 Finance, Accounts and Audit
Brahmaputra Board is provided funds under ‘grants-in-aid’ by the Government of India for its works and establishment expenditure. Brahmaputra Board has a Financial Adviser to render advice on all matters relating to finance, maintenance of accounts and to conduct internal audits of Brahmaputra Board. The Financial Adviser is assisted by ‘Finance Wing’ consisting of a Deputy Financial Adviser, Senior Accounts Officer, Accounts Officers and other supporting staff to assist him in these works. Each field Division is provided with a Divisional Accountant/ Junior Accountant to maintain proper accounts of field works and advise the Executive Engineers in account matters. The General Manager shall also exercise the powers and duties as hereinafter prescribed under Rule 16 in the matters pertaining to budget and allocation or re-appropriation of grants. The fund allocations to the Divisions and their expenditure are maintained by the Finance Wing on monthly/quarterly / annual basis.
108
Annual Report: 2017-18
��
�
2.3 Review in progress of works during 2017-18
2.3.1 Survey& Investigation and preparation / updating of Master Plan
a) 5(five) Master Plans of Jaldhaka, Tangani, Simsang, Torsa and Teesta were
submitted to concerned State Governments for views / comments after final
modification. The comments received from State Governments as received have
been attended and appended. Master Plan of Jaldhaka was approved in 64th
meeting of Brahmaputra Board and submitted to Ministry for approval of
Government of India. Master Plans of Tangani, Simsang, Torsa and Teesta were
approved in 65th meeting of Brahmaputra Board and were under process to submit
to the Ministry. It was proposed to modify all the draft Master Plans completed by
Brahmaputra Board in the similar lines.
b) Preparation of new Master Plans will be taken up on completion of modification of draft master plans already prepared.
2.3.2 Drainage Development Schemes (DDS):
Preparation DPR of Depota DDS was cleared by CWC during 2017-18. DPR of
Amjur, Dharmanagar and Demow DDSs were under compliance of observation of
CWC. The 65th meeting of Board held on 27.03.2018 decided to obtain the
required NOC as per condition of Brahmaputra Board Act 1980 from State
Governments before processing for clearance of DPR and subsequent
implementation. Accordingly Water Resources Department, Assam was requested
to issue NOC.
2.3.3 Survey & Investigation and preparation of DPR of Multipurpose Projects including Mini-Micro Projects
a) Kulsi MP Project and Noa-Dehing Dam Project::All technical chapters of both DPRs cleared by CWC & CEA. The DPR of Noa-Dihing Project was included in Agenda of TAC of MoWR, RD&GR held on 12.03.2018, but was not approved by the TAC due to non finalization of implementing agency. The 65th meeting of Board held on 27.03.2018 decided to request the State Government of Assam and Arunachal Pradesh to identify the implementing Agency and source of funding before placing the same in the Technical Advisory Committee TAC) of Ministry for techno-economic clearance of the project.
b) Simsang (Someswari) Dam Project and Jiadhal Dam Project:: Hydrological data collection continued. Topographical survey, geological investigation and construction material survey are in progress. The 65th meeting of Board held on 27.03.2018 decided to complete the remaining Survey & Investigation (S&I) works and DPR preparation through WAPCOS.
c) Killing Dam Project: Hydrological data collection continued. Layout prepared and submitted to CWC for finalization. Observations received from CWC were being attended. Infrastructural development, topographical survey, geological investigation and construction material survey were in progress. In the 65th
meeting of Board held on 27.03.2018 decided to hand over the project to NEEPCO for remaining S&I works and DPR preparation and subsequent implementation.
109
Annual Report: 2017-18
��
�
2.3.4 Feasibility studies for channelization of river Brahmaputra- Mathematical model studies etc.
IIT, Guwahati was entrusted to carry out Mathematical Model Study of River Brahmaputra with emphasis on climate change to understand the river dynamics through a MoU. 1 D study report “Beta-Test” was released during 9thmeeting of HPRB held on 30.12.2017 at Kaziranga, Assam by Hon’ble Union Minister of Water Resources.
2.3.5 Execution of Drainage Development Scheme (DDS):
a) Barbhag DDS: The works of construction of embankment & re-sectioning of channel were completed under revised DPR of Rs. 14.80 crore. Construction of sluice regulator and its associated works were continued. Due to uncontrolled release of ground water in the foundation excavation, a part of the foundation has been modified replacing the RCC cutoff walls by sheet piles during the year. Considering the non-workability condition during monsoon, it was decided to resume the work after the monsoon.
b) Amjur DDS: Revised DPR for Rs. 62.28 crore was under appraisal of CWC. On receipt of techno-economic clearance from CWC, construction of sluice would be taken up. 33.50% of works was completed.
c) Jengrai DDS: Revised estimate for Rs. 523.24 lakh was cleared by CWC. Construction of sluice of Jengrai DDS was in progress and almost 65% of sluice work was completed.
d) Jakaichuk DDS: Works envisaged under the scheme almost completed.
2.3.6 New Drainage Development Scheme proposed to be taken up for execution 2017-18 to 2019-20
Following DDSs were included in the approved Planned Scheme of MoWR,RD&GR “River Basin Management” for continuation of Brahmaputra Board during the period 2017-18 to 2019-20-
Demow, Pola, Dharmanagar, Pota Kalong, Larsing, Nelli and Kalamanijani DDS.
2.3.7 North Eastern Hydraulic and Allied Research Institute (NEHARI):
�
This institute was established under Brahmaputra Board at Rudreswar, North Guwahati as per clause 7 of Assam Accord, and operationalized during 1996. The main functions of NEHARI are material testing, carrying out Hydraulic model studies etc. Facilities such as Hydraulic Laboratory with model trays and flumes and Laboratories for testing soil, concrete, other construction materials and foundation rock exist in the institute. An Advisory Committee of NEHARI was constituted under the Chairmanship of Chairman, Brahmaputra Board with members from CWPRS, CSMRS, CGWB, IITG, WAPCOS, NERIWALAM& NWA-Pune to govern the functions of NEHARI. 1st meeting of Advisory Committee of NEHARI was held on 06.10.2017. Board also signed a MoU with NERIWALAM to utilize the infrastructures of NEHARI for organizing training by NERIWALAM.
110
Annual Report: 2017-18
���
�
2.3.8 Flood Control & Anti erosion works
a) Protection of Majuli Island from floods and erosion works
Continuing the protection works of Majuli Island under Phase –II &III, expenditure
of Rs.129.08 crore has been incurred up to March 2018with Rs. 8.59 crore during
2017-18. Works envisaged under Phase-II&II was completed within the financial
year. With the implementation of works under various phases, the land mass of
Majuli Island has increased from 502.21 sq km to 524.29 sq km from the year
2004 to 2016 as per evidence drawn from satellite imagery data. Thus, 22.08
sqkm of land was successfully reclaimed by Brahmaputra Board in Majuli island.
b) Restoration of Dibang and Lohit Rivers to their original courses at Dhola-Hatighuli
(Avulsion of Brahmaputra at Dholla-Hatighuli Phase-IV)
Work was completed in March 2016 with an expenditure of Rs.56.59 crore. Only
maintenance continued.11villages under Doomduma Revenue Circle in an area of
about 1500 ha was secured from floods from the year 2004 onwards.
c) Restoration of Dibang and Lohit rivers to their original courses at Dhola-Hatighuli,
Phase-V - Conversion of the existing tie bund across the spill channel of river
Dibang in to a full-fledged embankment at Bahbari and construction of new
embankment -Part-A of Phase – V:
DPR for this work has been prepared as per recommendation of TAC-(BB) and
was under appraisal of CWC.
d) Protection of Balat Village in Meghalaya on River Umngi.
Part –I of scheme amounting Rs. 5.63 crore was taken up for implementation
within the administrative approval and completed in January 2016.
DPR for part -II work for Rs. 12.87 crore prepared as per recommendation of TAC-
(BB) was in the final stage of clearance by CWC, Shillong Office.
e) Anti-erosion works for protection of Mankachar, Kalair-alga International Border
area from erosion of river Brahmaputra, Assam.
The area was subjected to severe erosion of river Brahmaputra threatening
the existing IBB link road, border fencing, and border road and adjoining vast
area of Hatsingimari town. Original scheme of Rs 23.79 crore was modified
due to ban on extraction of boulder by Hon’ble High Court of Meghalaya for
Rs. 20.25 crore substituting boulders by Geobag. Status of implementation at
the of the year was as under-
111
Annual Report: 2017-18
���
�
(i) Construction of retirement bund to plug the breach on Indo-Bangla Border
(IBB) Link Road – Completed on 02.08.2017
(ii) Construction of balance work of retirement bund on IBB Road –Commenced
on 12.02.2018 and 65.37%progress achieved
(iii) Bank revetment with geo-bags – Out of three groups, work ordered for one
group and commenced from 10.03.2018 and 33.71% progress achieved. For
the remaining two groups tender processed
f) Anti-erosion measure in Masalabari area near International Border in Assam -
Poor response of tenderer led for repeated retendering for implementation for
which commencement of execution was delayed. The status at the of the year
was:
(i) Supplying and laying of RCC porcupine screens- Work commenced on
16.02.2018 and 20.60% progress achieved
(ii) Bank revetment works - 54.26% completed
g) Anti-erosion measures for bank protection of Bhajaner Cherra, Nishiganj area
under Cooch Behar Block No. II along the left bank of River Mansai in Cooch
Behar District, West Bengal
(i) Administrative Approval and Expenditure Sanction was accorded.
h) Bank protection work at Bhogdebri area on the Right Bank of River Mansai in
Cooch Behar District, West Bengal.
(i) Administrative Approval and Expenditure Sanction was accorded.
2.3.9 Raised Platform
55% of progress was achieved during 2017-18 with overall 91.24% progress in
construction of raised platform at Satrakanara area in Barpeta District, Assam.
NDMA was requested to keep the Brahmaputra Board in the loop for assisting
NDMA for implementation of such schemes in North Eastern Region.
112
������������
Annual Report: 2017-18
���
�
Chapter- III
Review of progress in preparation of Master Plan; Survey and Investigation; execution, maintenance and operation of multipurpose dams and other works; drawing up of standards and specifications for construction, operation and maintenance of dams; phased programme for construction by State Governments of all dams and other projects/ schemes incorporated in Master Plan.
3.1 Progress of Survey and Investigation and Preparation of Master Plans, Detailed Project Reports (DPR) for Drainage Development Schemes and DPRs of Multi-Purpose Projects
3.1.1 Preparation of Master Plans
The Brahmaputra Board had taken up preparation of Master Plans of the main stem
of the Brahmaputra and Barak along with 68 major tributaries of Brahmaputra,
including Majuli Island, River Dhaleswari and rivers of Meghalaya, Manipur and
Tripura in three Parts.
Part River Number Status
Part-I Main stem Brahmaputra River
1 Approved by the Government of India
Part-II Master Plan on Barak River and its tributaries except Dhaleswari
1 Approved by the Government of India
Part-III Master Plan on tributaries of the Brahmaputra and rivers of Tripura including Majuli Island and Dhaleswari
68 o Approved by the Government of India-47
Master Planso Submitted to MoWR,RD&GR for approval
of the Government of India(GoI). Further observations of the Ministry were compiledby Board and approved by 64th and 65th
Adjourned meeting of Board -5 Master Plans
o Submitted to MoWR,RD&GR for approval of the GoI. Further observations of the Ministry were under compliance - 3 Master plans
o Draft Master Plan completed. To be modified further on the lines of latest suggestions of MoWR,RD&GR -5 Master Plans
o New basins identified for preparation of Master Plans- 8 Sub-basins
Total 70
113
Annual Report: 2017-18
���
�
During the year 2017-18
Master Plans of Jaldhaka, Tangani, Simsang, Torsa and Teesta were completed and approved by 64th and 65thMeeting of Brahmaputra Board to submit to the Ministry of WR,RD&GR for approval of Government of India. Master Plans of Kynshi, Umngot and Sankosh-Raidak were under modification.
As these 8 Master Plans were on priority no new Master Plans were finalized by Board during 2017-18.
3.1.2 Current Assignment for Preparation of Master Plans:
The following rivers of Meghalaya were identified for preparation of Master Plans –
1. Waikhyrwi
2. Umtrew
3. Ganol
4. Bugi
5. Dareng
6. Umsohryngkew
7. Umiew
8. Myntdu
9. Lubha
Master Plans of Imphal River, Feni River, Kolodyne and Tuichang were identified for preparation of Master Plans. Preparation of new Master Plan was proposed to be taken up on completion of modification of draft master plans already prepared.
A pictogram of the status of Master Plan is given at Annexure – VIII
3.2 Drainage Development Schemes (DDS)
In the approved Master Plans prepared by Brahmaputra Board 41 drainage congested areas were identified for preparation of detailed project report (DPR).
3.2.1 Completed Drainage Development Schemes:
• Harang Drainage Development Scheme
The scheme with estimated cost of Rs. 30.49 crore is located in Barak Valley on the border of Bangladesh near Badarpur with expenditure of Rs. 33.90 crore and completed during March, 2011and was handed over to WRD, Assam. It benefits 11850 ha of chronically drainage congested areas in Barak Valley, Assam for agriculture.
• East of Barpeta Drainage Development Scheme
The revised estimate for Rs. 2.96 crore was taken up for execution in March, 2009 and completed in June, 2011 with the expenditure of Rs. 2.67 crore. The scheme has already been handed over to WRD, Assam. It benefits 2852 ha of chronically drainage congested areas in Barpeta District for agriculture.
114
Annual Report: 2017-18
���
�
3.2.2 Under Execution:
• Jakaichuk Drainage Development Scheme
The scheme was under execution by Brahmaputra Board since 2008.Works envisaged under the approved estimate completed. The scheme would accrue benefits to an area of2308 ha for agriculture.
• Barbhag Drainage Development Scheme
Brahmaputra Board took up the execution of Borbhag Drainage Development Scheme during the year 2006. Two components of the work - (1) Raising and strengthening of embankment and (2) Re-sectioning of channel have already been completed in March 2012. The DPR was revised to Rs. 14.80 crore incorporating revised design of sluice. The work of remaining part of the scheme construction of the sluice was in progress and 24.94% progress was achieved up to March, 2018with an overall expenditure of Rs 10.40 crore. Due to uncontrolled and unmanageable release of ground water, the design of foundation of the sluice for the remaining part was modified substituting cut-off walls by Sheet Piles for which progress suffered during the year. On completion of the scheme, an area of 4000 ha of chronically drainage congested areas in Nalbari District of Assam will be benefited for agriculture.
• Amjur Drainage Development Scheme
Techno-economic clearance of the scheme for an amount of Rs. 14.15 crore was received in January, 2006. The execution of Amjur DDS was taken up in the year 2006-07. Out of the two components i.e. sluice regulator and embankment, the work for ‘Raising and Strengthening’ of existing embankment was taken up first. The design of sluice was entrusted to CWC and the revised estimate as per approved design is under appraisal of CWC. The scheme will benefit an area of 7200 ha of drainage congested areas in Cachar District, Assam for agriculture.
• Jengrai Drainage Development Scheme
Techno-economic clearance of the scheme for an amount of Rs. 1.49 crore was accorded in 2006. The scheme was taken up by Brahmaputra Board in 2006-07. Out of the two components i.e. sluice regulator and embankment, the work for ‘Raising and Strengthening’ of existing embankment was taken up first and completed. The DPR of the scheme was revised as per actual design of sluice for Rs. 5.23 crore. The overall physical progress of work under Jengrai DDS was 65% and during the year was 35% and expenditure during the year was Rs. 1.56 crore. The work was targeted to be completed by March 2019.On completion of the scheme, an area of 1400 ha would be benefited from drainage congestion.
• Demow Drainage Development Scheme
On accord of techno-economic clearance by CWC, the DPR of Demow Drainage Development Scheme was submitted to Government of Assam for implementation. However, Government of Assam requested Brahmaputra Board to take up the execution of the scheme. The detailed design and construction drawing of the sluice regulator has been done by Brahmaputra Board and the cost estimate of the scheme has been updated for Rs. 22.25 crore which was under techno-economic appraisal. The 65th meeting of Brahmaputra Board held on 27thMarch 2018 decided that further processing of clearance of DPR will be taken up only on receipt of complete NOC from State Government.
115
Annual Report: 2017-18
���
�
� The brief status in respect of 41 drainage congested areas is given below-
Sl. No.
Name of Drainage Scheme
Tributary / Sub-basin Basin
Area affected (sq.km)
State Status (As on 31.03.2018)
I) Schemes cleared by CWC
1 Harang Barak Barak 242
Assam
Execution completed and handed over to WRD, Government of Assam
2 East of Barpeta
Beki-Manas Aie.
Brahmaputra 180
3 Borbhag Pagladiya Brahmaputra 56 Scheme is under execution
4 Amjur Barak Barak 52.5 Revised DPR under techno-economic appraisal.
5 Jengrai Subansiri Brahmaputra 18 Scheme is under execution
6 Jakaichuk Jhanji Brahmaputra 100
7 Kailashahar Manu Manu-deo 18 Tripura Execution suspended due to inability of State Government to provide requisite land
8 Singla Barak Barak 322 Assam
9 Rudrasagar Gumti Gumti 22 Tripura Handed over to State Government of Tripura for execution
10 Demow Disang Brahmaputra 226 Assam Handed over to Govt. of Assam for execution. However, as requested by state included in work programme of XII plan. Working DPR was sent to CWC for techno-economic clearance. IIT Guwahati was requested forconsultancy of detailed design of sluice regulator. However, this will be pursued only after receipt of Mandatory requirement from State.
11 Kalamonijan Kopili (Jugijan & Lankajan)
Brahmaputra 100 Assam DPR Techno-economically cleared. Assam Govt .was requested to issue NOC. Initially, WRD, Assamexpressed its desire to execute the project. 65th meeting of Board decided to obtain specific NOC before processing for clearance of DPR. Taken up with state govt.
12 Nelli Kopili Brahmaputra 32 Assam
13 Pola Pola Barak 71 Assam CWC accorded techno-economic clearance. 14 Depota Depota Brahmaputra 28.36 Assam
II) Schemes under compliance of observations of CWC
1 Dharmanagar Juri Juri 20 Tripura Modified DPR submitted to CWC for techno-economic clearance. DPR re-submitted to CWC after compliance of the observation for TEC.
2 Larsing Barak Barak 35 Assam Under modification complying the observations of CWC.
3 Deroi Disang Brahmaputra 194 Assam DPR under preparation and at compilation stage
116
Annual Report: 2017-18
���
�
Sl. No.
Name of Drainage Scheme
Tributary / Sub-basin Basin
Area affected (sq.km)
State Status (As on 31.03.2018)
4 Pota Kolong Kopili-Kolong
Brahmaputra 100 Assam Preparation of DPR is completed & being submitted to CWC
5 Sonai Kopili-Kolong
Brahmaputra 63
Assam
Field office preparing to submit feasibility report
III) Schemes under preparation of DPR / Awaited from Filed Office
1
Laura-Jamira-Sessa
Buridehing Brahmaputra 300
Assam
Scheme is under formulation of Brahmaputra Board. Field office asked to submit DPR
2 Punir Barak Barak 31
Assam
Under process of formulation of
the scheme on the basis of new
field survey and investigation
3 Ghiladhari Ghiladhari Brahmaputra 144
Assam Joint field visit with State Govt.
officials is proposed
4 Tingrai Buridehing Brahmaputra 11 Assam Field office asked to submit the
status
5 Haria-Nanoi Nanoi Brahmaputra NA Assam Scheme is under formulation of
Brahmaputra Board
IV) Schemes under process of deletion
1 Konwarpur Demow Brahmaputra 112 Assam Under process of deletion
2 Badri Barak Barak 33 Assam
3 Mora-
Dikrong
Dikrong Brahmaputra 26 Assam
4 Sukhsagar Gumti Gumti 50 Tripura
5 Mora-
Pichalamukh
Dikrong Brahmaputra 8 Assam
6 Pakania Ranganadi Brahmaputra 16 Assam
7 Namdang Dikhow Brahmaputra 10 Assam
8 Sisapathar Dikrong Brahmaputra 12 Assam
9 Gelabil Bhogdoi Brahmaputra 5 Assam
10 West of
Barpeta
Beki-
Manas-Aie
Brahmaputra 23 Assam
11 Ghagra Barak Barak 65 Assam
12 Bherekibeel Maridhal Brahmaputra Assam
13 Khatra Barnadi Brahmaputra 15 Assam
14 Batha Nanoi Brahmaputra 40 Assam
V) Schemes already deleted
1 Joysagar Kopili-
Kalong
Brahmaputra 55 Assam Dropped on approval of Board in 53rd meeting of BB2 Rangsai Jinjiram Brahmaputra 147 Assam
3 Sessa Puthimari Brahmaputra 59 Assam
117
Annual Report: 2017-18
���
�
3.2.3 Preparation of Detailed Project Report (DPR)s for Drainage Development Schemes:
During the year, 2017-18 the achievements made by Board in respect of preparation of Drainage Development Schemes are as under:-
DPRs of Depota, Dharmanagar, Pota Kolong and Larsing DDSs were under
appraisal of CWC. Observations of CWC were attended. Depota DDS was cleared
by CWC.
A pictogram of the status of Drainage Development Scheme is given at
Annexure- IX.
3.3 ‘Survey and Investigation’ of Water Resources Projects
'Survey & Investigation' and Preparation of Detailed Project Reports
Brahmaputra Board took up 'Survey & Investigation' of 14 Multipurpose Projects in
Brahmaputra and Barak Basin and in the south flowing rivers of Meghalaya.
3.3.1 Detailed Project Reports (DPRs) Completed
After 'Survey & Investigation' and completion of preparation of Detail Project Reports (DPRs) following projects were under commissioning by various Agencies –
Sl.No Project Implementing Agency/Organization/Government
1 Siang Dam Project (3 dams)
Handed over to NHPC during the year 2000. NHPC informed that Siang Lower was handed over to M/s Jai Prakash Associates Ltd. on 31.03.2009. Siang Middle to M/s Reliance Energy Ltd. (REL) and Siang Upper, was allocated to M/s NHPC by Government of Arunachal Pradesh in February 2009 for preparation of PFR. Further details on the progress of commissioning of these projects have not been received
2 Subansiri Dam Project (3 dams)
Handed over to NHPC during the year 2000. As stated by NHPC the Lower Subansiri is targeted for completion by 2017. Subansiri Middle and Subansiri Upper were handed over to M/s Jindal Power Ltd. on 04.02.2011. Further details on progress of commissioning of these projects have not been received
3 Tipaimukh Dam Project
Handed over to NEEPCO and subsequently handed over to NHPC from NEEPCO
4 Pagladiya Dam Project
The work of Pagladiya Dam Project under execution byBrahmaputra Board has been abandoned due to non-completion of zirat survey by Government of Assam
5 Bairabi Dam Project
Handed to Government of Mizoram, who allotted the work of execution for Bairabi Dam Project to M/s Sikaria Power Ltd., Kolkata on 10.08.2012. It has been intimated by Government of Mizoram that Bairabi Dam Project will be completed in seven years.
118
Annual Report: 2017-18
��
�
3.3.2 Partially Completed Detailed Project Reports (DPRs)
The following four Water Resources Projects located in Arunachal Pradesh and Meghalaya after partial completion of 'Survey & Investigation' by Brahmaputra Board were handed over to other Agency / State Government for completion of the balance Survey & Investigation works and subsequent commissioning.
Sl. No. Name of Project Implementing Agency
1. Dibang Dam project National Hydroelectric Power Corporation
2. Lohit Dam Project (On completion of 'Survey & Investigation')
Government of Arunachal Pradesh
3. Kynshi Stage-I Dam project Government of Meghalaya
4. Kynshi Stage-II Dam project Government of Meghalaya
3.3.3 All technical chapters of the Detailed Project Reports of following 2 (two) Projects were cleared by CWC and CEA
Sl.No. Name of Project Location
1. Kulsi Multipurpose Project Assam on border with Meghalaya Declared as National Project2. Noa-Dehing Dam Project Arunachal Pradesh
3.3.4 Projects under ‘Survey & Investigation’ and formulation of Detailed Project Reports
The following five Water Resources Projects were presently under 'Survey & Investigation'/preparation of DPR in Brahmaputra Board-
Sl.No. Name of Project Location
1. Simsang Dam Project Meghalaya
2.. Jiadhal Dam Project Assam on border with Arunachal Pradesh
3. Killing Dam Project Assam Meghalaya border
• Kulsi Multipurpose Project
The project site is located about 1.5 Km downstream of Ukium, a border village of Assam and Meghalaya. Brahmaputra Board took up the survey and investigation work of Kulsi M.P. project in the year 1997. The installed capacity of the project is estimated as 55 M.W. with a gross command area of about 26000 ha. This project has been declared as a ‘National Project’ by Government of India. All chapters of the DPR was cleared by CEA & CWC. The Assam Government was requested to take over the project for implementation.
• Noa-Dehing Dam Project
The Project site is located about 4 Km upstream of Miao Town in Changlang District of Arunachal Pradesh. The investigation of this project was started in December, 1996. The installed capacity of the project is estimated at 72 MW. This project also
119
Annual Report: 2017-18
��
�
declared as a ‘National Project’. All chapters of the DPR was cleared by CEA & CWC.The Govt. of Arunachal Pradesh was requested to take over the project for implementation.
• Simsang (Someswari) Multipurpose project
The project is located on the Simsang river with the dam site at Rongkhandi near Nangwalbibra Township under East Garo Hills District of Meghalaya. The survey and investigation work of this project was taken up during the year 1997. The tentative installed capacity of this project is estimated as 65 MW.
� Present status-
o Topographical survey mostly completed
o Pre-feasibility report prepared
o Geological investigation in progress - 26 bore holes completed in dam area
o Construction material survey completed
o Two alternate layouts of water conductor system have been proposed by the Board and submitted to the CWC for finalization of one of the alternatives for further investigation.
It was decided to complete the remaining works of Survey & Investigation and DPR
preparation through outsourcing due to acute shortage of manpower in the middle
and higher level of the Engineering cadre in Brahmaputra Board. Accordingly,
decision was taken to entrust the remaining work to WAPCOS.
• Jiadhal Dam Project
Jiadhal Dam project is located about 5 Km upstream of Jiadhalmukh in Assam-
Arunachal Border area. Investigation of this project was taken up in November,
2002. The installed capacity of the project is estimated at 70 MW (tentative). CWC
Design Team has been requested for a field visit to finalize the layout and other
project parameters of the project.
� Present status-
o Topographical survey in progress
o Geological investigation in progress
o Construction materials survey in progress
o EIA& EMP studies are in progress
o Two alternate layouts of the project have been proposed by the Board and
submitted to the CWC for finalization of one of the alternatives.
o It was decided to complete the remaining works of Survey & Investigation and
DPR preparation through outsourcing due to acute shortage of manpower in the
middle and higher level of the Engineering cadre in Brahmaputra Board.
Accordingly, decision taken to entrust the remaining work to WAPCOS.
120
Annual Report: 2017-18
���
�
• Killing Dam Project
The project site is located at Assam-Meghalaya Border on river Killing. Brahmaputra
Board started survey &investigation of this project in November, 2003. The installed
capacity of the project is estimated at 85 MW. The target for completion of the DPR of
this project is 2017-18.
� Present status-
The design team of CWC visited project sites of Killing MP Project on 20th December,
2009 and reviewed the proposed layout. It was suggested by the CWC to carry out
optimization studies based on tentative costs at different dam heights for finalization of
the project parameters. Accordingly, the studies have been carried out and submitted
to CWC for vetting. CWC has broadly agreed to the proposal submitted by the Board
and suggested some additional studies/investigations. The additional
studies/investigations are in progress.
At present, hydrological studies and drilling works for preparation of DPR are in
progress and lay out plan of the project is under finalization.
o It was decided to handover the project to NEEPCO for DPR preparation and
subsequent implementation due to acute shortage of manpower in the middle and
higher level of the Engineering cadre in Brahmaputra Board.
A pictogram of the status is given at Annexure- X.
3.3.4 Survey & Investigation of Mini Hydel Projects
The Brahmaputra Board has taken up the following 3 (three) Mini Hydel projects in
Meghalaya for ‘Survey & Investigation’ and preparation of Detailed Project Reports
(DPRs)-
Sl. Name of Project Status
1 Myntang Mini Hydel Project (20 MW) Survey & Investigation continued
2 Umkhen Stage-I Mini Hydel Project (5 MW) Survey & Investigation discontinued from
May, 2015 3 Umkhen Stage-II Mini Hydel Project (4 MW)
During August, 2012 a team of geologists headed by the Director, Engineering
Geology Division, NER, Shillong visited the dam sites and approved the feasibility of
all the three project sites prima-facie. They have suggested for some more
topographical and river survey works for further studies. Hydrological and Preliminary
Power Potential Studies in respect of these projects were carried out till April 2015.
After April 2015, preparation of DPRs of only Myntang Mini Hydel project continued.
As decided in case of Jiadhal and Simsang, it was also decided to examine DPR
preparation through outsourcing.
121
Annual Report: 2017-18
���
�
3.4 Construction Activities
3.4.1 Pagladiya Dam Project
This project meant for flood moderation to benefit an area of 40000 ha, irrigation to
54,160 ha and incidental power generation of 3 MW, is proposed across Pagladiya
River at Thalkuchi in Baksa District which falls under Bodoland Territorial Autonomous
Districts (BTAD) in Assam. The project envisages construction of 25 m high and 21
km long earth dam with a concrete spillway. The Government of India had sanctioned
the project in January, 2001 at an estimated cost of Rs. 542.90 crore for construction
by Brahmaputra Board.
• Works carried out since 2001
• Pre-construction survey, investigations, studies, design, drawings etc.
• Taking possession of land (956 ha) for Resettlement & Rehabilitation (R&R) purpose
• Construction of project roads, offices, etc.
• Preparation of technical specifications & tender document
• Pre-qualification of contractors for main works
Out of 3238 ha of land required for execution of Pagladiya Dam Project, 956 ha of
land acquired by Government of Assam was made available to Brahmaputra Board.
Due to inability of Government of Assam to acquire the balance 2282 ha of land for
R&R purpose, the work was held up and as per decision of 53rd Meeting of
Brahmaputra Board; all activities were closedw. e. f. 31st May 2013. The Government
of Assam was requested to take over and make necessary arrangement for protection
of 956 ha of land from unauthorized occupation. 26 personnel engaged for watch and
ward of 956 ha of land have been disengaged from 1st June 2013 and no expenditure
incurred by Board since then.
3.4.2 Construction of Raised Platforms
On request from State Government of Assam, Brahmaputra Board has completed
construction of 18 raised platforms at different locations to facilitate logistic support
during flood for humans and livestock. Another raised platform at Satrakanara area in
Barpeta District, Assam was under execution. During 2017-18, 55% of progress was
achieved in execution of the raised platform with overall 91.24% progress upto March
2018.
In the report of performance evaluation study carried out through an independent
agency, it has been advocated to construct more raised platforms for shelter of
marooned people during floods. As per decision of 65thmeeting of Brahmaputra
Board, NDMA was requested to keep the Brahmaputra Board in the loop for assisting
NDMA for implementation of such schemes in North Eastern Region.
The list of places / locations of Raised Platforms constructed by Brahmaputra Board is
as under-
122
Annual Report: 2017-18
���
�
Sl. No
Name No. District Date of Completion
Handing over to State Govt.
1 Bejartari 1 Kamrup(Rural) 25.03.2010 06.06.2011
2 Salmarapam (Toptola) 1 Morigaon 09.04.2011 20.05.2012
3 Garapar 1 Morigaon 09.04.2011 20.05.2012
4 Kapahtoli - 2 Nos 1 Tinsukia
5 Matmora 1 Dhemaji 28.03.2007 12.10.2007
6 Kharubhuj 1 Goalpara
7 3 Raised Platform along L/B of Brahmaputra from Guimara-Nahira area
3 Kamrup (Rural)
2006 16.03.2010
8 Ulubari 1 Morigaon 03.11.2006 20.03.2008
9 Salekpathalighat 1 Majuli Dec’ 2009 31.05.2012
10 Jiakur 1 Kamrup 28.02.2013 09.04.2013
11 Tulsimukh-Kochgaon 1 Nagaon 29.04.2014
12 Atoichuk 1 Majuli August 2013 24.09.2013
13 Dakhinpat 1 Majuli
14 Kharkharijan 1 Majuli
15 Ratanpur Miri 1 Majuli Nov’ 2015
16 Barbalarchar 1 Dhubri Dec’ 2015 20.09.2016
17 Satrakanara
1 Barpeta Work almost
completed
Total 19
3.4.3 North Eastern Hydraulic and Allied Research Institute (NEHARI)
North Eastern Hydraulic and Allied Research Institute (NEHARI) was established in
the year 1996 under Brahmaputra Board, as a follow up ‘Assam Accord’ inked on 15th
August, 1985 in presence of then, Hon’ble Prime Minister of India, late Shri Rajiv
Gandhi. The Institute is situated ina sprawling campus of 44 ha at Rudreswar in North
Guwahati at a distance of 25 km from the main city, far from the madding crowd, on
the hillock in a conducive ambience. The Institute was set up as pioneer laboratory of
North Eastern Region for laboratory testing of soil, rock, concrete and construction
materials for development of water resources and other projects. The Institute has
adequate facility for simulating and understanding river behavior through physical
models.
� Mandate
Undertaking field and laboratory investigations, research and development work of
basic and applied types in 'Geo-mechanics', 'Concrete Technology', 'Soil
Characteristics', 'Construction Materials' and associated issues for development of
hydropower, irrigation and flood control projects.
� Activities
o Hydraulic Physical Model Testing for erosion problem study &river training
o Soil mechanics
o Rock mechanics
o Concrete technology
123
Annual Report: 2017-18
���
�
o Construction material testing
o Geophysical investigations at site
o Sediment/Silt analysis
NEHARI has patronage of Central Soil and Material Research station (CSMRS), New
Delhi and Central Water and Power Research Station (CWPRS), Pune –
Internationally reorganized apex institutes in the field of laboratory testing of soil
construction materials and development of physical and mathematical models in the
field of water resources. Experts/technical hands of NEHARI have initially been
imparted training on the subject by both the above mentioned premier institutes.
During a short span of time, since its inception, NEHARI has successfully completed
laboratory testing of soil and materials during investigation and also during execution
of a number of projects in the water resources development.
Noteworthy among them are Lower Subansiri Hydro-electric Project, Middle Subansiri
Hydro-electric Project, Lower Siang Project, Middle Siang Project, Dibang Dam
Project, Laskar Mintu Project of Meghalaya, Tuirini, Tuipal and Kolodyne H.E. Project
of Mizoram, Dikhu Hydel Project of Nagaland and others. Test reports prepared by
NEHARI have been appreciated by CSMRS.
An Advisory Committee of NEHAR was constituted under the Chairmanship of
Chairman, Brahmaputra Board with members from CWPRS, CSMRS, CGWB, IITG,
WAPCOS, NERIWALAM& NWA-Pune to govern the functions of NEHARI. 1st
meeting of Advisory Committee of NEHARI was held on 06.10.2017. Board also
signed an MoU with NERIWALAM to utilize the infrastructures of NEHARI for
organizing training by NERIWALAM.
3.5 Flood Management and Anti-erosion Schemes
(Implementation of Anti-erosion Measures)
3.5.1 Anti-erosion Measures Completed
Brahmaputra Board has successfully completed the following anti-erosion measures
in Assam Meghalaya and Nagaland –
a. Avulsion of Brahmaputra at Dholla Hatghuli (Renamed as Restoration of rivers Dibang
and Lohit to their original courses) – Phase – I, Phase-II, Phase-III and Phase-IV
b. Protection of Majuli Island from flood and erosion- Immediate measure, Phase-I,
Emergent measures and Phase-II & III
c. Protection of Nagrijuli, Rangia Town, Mukalmua and Barbhag area from floods and
erosion of river Puthimari in Assam
d. Protection of Balat Village from erosion of river Umngi, Meghalaya Part-I.
e. Anti-Erosion measures to protect Kushiabil & Durgajan village in Dimapur of river
Dhansiri(S) in Nagaland
On completion, the above schemes at Sl. No. c. and e. have been handed over to
respective States for routine maintenance.
124
Annual Report: 2017-18
���
�
3.5.2 Implementation of Anti-erosion Measures underway
� Protection of Majuli from floods and erosion
Majuli is the largest inhabited river island in the world. It is situated between latitudes
26º45’N and 27º10’N, and longitudes between 93º40’E and 94º35’E. Majuli has been
the cultural capital and the cradle of Assamese civilization since the 16thcentury.
Shrimanta Sankardeva, a pioneer of the medieval-age neo-vaishnavite movement,
preached a monotheist form of Hinduism called as Vaishnavism and established
monasteries and hermitages known as satras. The satras preserve antiques like
weapons, utensils, jewellery and other items of cultural significance. The inhabitants of
Majuli are mostly tribal - predominantly from the Mishing, Deori and Sonowal Kacharis
tribes. Majuli is also famous for pottery.
Majuli Island has constantly been subjected to erosion by the mighty Brahmaputra.
Responsibility for undertaking anti-erosion works for protection of Majuli Island was
given to Brahmaputra Board in the year 1999. Physical activities on the ground started
in the year 2004.
The total area of the land mass of Majuli Main Island was 502.21 sq km in the year
2004. Since the year 2004, with regular implementation of anti-erosion / bank
protection measures by Brahmaputra Board, the total area of Majuli Island has
increased to 524.29 sq km till the year 2016. Works under Phase-II &III were
completed. Works - such as construction of 5 spurs, river bank revetments in 5
locations, closing of breach at Samahia-Ati, supplying &laying of permeable RCC
porcupine screens/spurs/dampeners, construction of 5 raised platforms in low lying
flood vulnerable areas, construction of nose of 2 check bunds, tie bunds at 2 locations
and spur No. 2 had been completed.
� Financial Implication
Expenditure incurred by Brahmaputra Board on undertaking measures for protection
of Majuli Island from floods and erosion since January 2004 under various Phases is
detailed below-
Sl.No.
Description Estimated Cost
(Rs. in crore)
Actual Expenditure (Rs. in crore)
Remarks
1 Immediate Measures (Year 2004-2005)
6.22 6.09 Completed
2 Phase- I (Years 2005-2011)
56.07 52.63 Completed
3 Emergent Measures (Year 2008)
4.99 4.75 Completed
4 Phase-II & Phase-III 115.99 127.48 (March’18)
Completed
Total 183.27 191.76
125
Annual Report: 2017-18
���
�
� Outcome
The following are the major achievements –
o Raising and Strengthening of 96.2 km of Embankment- Flood problem inside the
embankment system curtained. Internal communication system has been improved.
o Prior to implementation of protection measures there was continuous loss of land of
Majuli Island. Since implementation of protection measures by Brahmaputra Board
trend of land loss got reversed. Particulars on net gain of land mass in Majuli Island
are tabulated below –
A new scheme “Protection of Majuli Island from flood and erosion of river
Brahmaputra” has been approved by Government of India for Rs. 233.57 crore.
Ministry of DoNER funded Rs. 207 crore under NLCPR for implementation of the
scheme. Work amounting to Rs. 160.75 crore was allotted in November 2017.The
Hon’ble Union Minister of Water Resources laid Foundation Stone of the scheme on
29thDecember 2017 and 1.39% progress was achieved during the year.
• Avulsion of Brahmaputra at Dhola-Hatighuli (Restoration of Dibang
and Lohit Rivers to their original courses)
Avulsion of left bank of River Lohit occurred in 1989, at confluence of Lohit with
Dibang - near Dhola-Hatighuli located in Dumdooma, Civil Sub-division of Tinsukia
district due to breach in Saikhowa Bund. The scheme “Avulsion of Brahmaputra at
Dhola-Hatighuli (Measures for diversion of River Dibang to its original course) with
ancillary anti-erosion measures” prepared by Government of Assam was approved by
Ministry of Water Resources, Government of India in the Technical Advisory
Committee (TAC) meeting held in May, 2002 and the Brahmaputra Board was
entrusted with the responsibility for execution of the scheme. Total expenditure of Rs
78.46 crore has so far been incurred by Brahmaputra Board on execution of works
envisaged under Phase-I, Phase-II, Phase-III and Phase-IV as detailed below:
Year Area of Majuli Island
(in sq km) Net Area reclaimed
(in sq km)
2004 502.21 -
2008 506.37 4.16
2011 520.26 13.89
2013 522.73 2.47
2014 523.88 1.15
2016 524.29 0.41
Total land mass gained from 2004 to 2016 22.08
126
Annual Report: 2017-18
���
�
(Rs. in crore)
Sl. No.
Description Estimated Cost
Actual Expenditure
Status
1 Phase-I (January 2003 to July 2004) 10.47 8.87 Completed
2 Phase- II (January 2004 to July 2004) 5.22 4.54 Completed
3 Phase-III(March 2007 to July 2007) 8.47 8.46 Completed
4 Phase-IV (2009-10 to 2015-16) 54.43 56.59 Completed
Total 78.59 78.46
� Outcome
• With construction of 'Tie-Bund', the lands which earlier used to form part of main channel of Dibang River are now completed protected from floods and erosion. The inhabitants of deserted areas have returned back and restarted cultivation in a big way.
• On construction of retirement bund at Hatighuli area on Left bank of Lohit river, 11 villages under Doomduma Revenue Circle in an area of about 1500 ha got protection from floods from 2004 onwards.
Plan Ahead:
Based upon the recommendations of 8thvisit of Standing Committee of Experts DPR of Phase –V was under appraisal of CWC for techno-economic clearance. CWC observed that model studies of works proposed in Phase-V to be carried out. A part of the work proposed under Phase-V for Conversion of the existing tie bund across the spill channel of river Dibang in to a full-fledged embankment at Bahbari and construction of new embankment -Part-A of Phase – V was proposed to implement in 2017-18 separately as per recommendation of TAC-BB was in final stage of techno-economic clearance of CWC.
• Protection of Balat Village in Meghalaya on River Umngi:
Part-I of scheme amounting Rs. 5.63 crore was taken up for implementation and was completed in January 2016. Works envisaged under Phase-I with financial implication of Rs. 4.82 crore were completed.
The DPR for Phase-II works for Rs. 12.87 crore was under final stage of techno-economic clearance of CWC.
• Anti-erosion works for protection of Mankachar, Kalair-Alga International Border area from erosion of river Brahmaputra, Assam-
Mankachar, Kalair-Alga International Border area is located on the south bank of river Brahmaputra in South Salmara, Mankachar District on the westernmost border of Assam. The area is subjected to severe erosion of river Brahmaputra threatening the existing IBB link road, border fencing and border road as well as adjoining vast area of Hatsingimari town. Scheme of Rs 23.79 crore was taken up for implementation.
Original scheme of Rs 23.79 crore was modified due to ban on extraction of boulder by Hon’ble High Court of Meghalaya for Rs. 20.25 crore substituting boulders by Geobag. Status of implementation was as under-
127
Annual Report: 2017-18
���
�
(i) Construction of open portion of retirement bund to plug the breach on Indo-Bangla Border (IBB) Link Road – Completed on 02.08.2017
(ii) Construction of balance work of retirement bund on IBB Road – Commenced on 12.02.2018 and 65.37% progress achieved
(iii) Bank revetment with geo-bags – Out of three groups, work ordered for one group and commenced from 10.03.2018 and 33.71% progress achieved. For the remaining two groups tender processed
• Anti-erosion measure in Masalabari area near International Border in Assam–
Due to poor response of tenderer led for repeated retendering for implementation for which commencement of execution was delayed.
(i) Supplying and laying of RCC porcupine screens- Work commenced on 16.02.2018 and 21% progress achieved
(ii) In the Bank revetment works 54.26% of progress achieved up to March, 2018
• Anti-erosion measures for bank protection of Bhajaner Cherra, Nishiganj area under Cooch Behar Block No. II along the left bank of River Mansai in Cooch Behar District, West Bengal
(i) The DPR of the scheme modified substituting boulder item by geobag
(ii) Administrative Approval and Expenditure Sanction was accorded
• Bank protection work at Bhogdebri area on the Right Bank of River Mansai in Cooch Behar District, West Bengal
(iii) The DPR of the scheme modified substituting boulder item by geobag
(iv) Administrative Approval and Expenditure Sanction was accorded.
� Anti-erosion Schemes proposed to be executed beyond the XII Five Year Plan i.e. from 2017-18 to 2019-2020
o Protection of Majuli Island from Flood & erosion Phase -II & III-Balance work o Protection of Majuli Island from flood and erosion of river Brahmaputra
Rs. 233.57 crore o Development of Infrastructures of Brahmaputra Board for carry out the Work of
protection of Majuli Island o Restoration of Dibang and Lohit rivers to their original courses Phase-V o Restoration of rivers Dibang and Lohit to their original courses Phase-V -
Conversion of the existing tie bund across the spill channel of river Dibang in to a full-fledged embankment at Bahbari and construction of new embankment -Part-A of Phase - V
o Protection of Balat village from erosion of river Umngi in South West Khasi Hills district of Meghalaya -Phase-II
o Anti-erosion measures for protection of areas under severe erosion in Kalair Alga of Mankachar in Assam near International Border from erosion of river Brahmaputra:
128
Annual Report: 2017-18
��
�
o Anti-erosion measures for protection of areas under severe erosion in Masalabari area in Assam near International Border from erosion of river Brahmaputra
o Emergent Anti-erosion works (generic schemes)/Renovation & Restoration of water bodies for irrigation
o Anti-Erosion measures for bank protection of Bhajaner Cherra, Nishiganj area under Cooch Behar Block No. II along the left bank of River Mansai in Cooch Behar district, West Bengal
o Bank protection work at Bhogdebri area on the Right Bank of River Mansai in Cooch Behar district, West Bengal.
o Generic schemes of flood management works
3.6 Monitoring of Schemes under Flood Management Programme of Government of India
The Brahmaputra Board is entrusted with monitoring of scheme under Flood
Management Programme in respect of entire North Eastern Region including Sikkim
and part of West Bengal falling under Brahmaputra Basin since X Plan. Details of
scheme undertaken by Government of India under Flood Management Programme
and monitored by Brahmaputra Board is shown below –
During X Plan
Sl. No.
Name of State Nos of schemes Central Grant released(Rs. in crore)
1 Assam 44 78.8182
2 Arunachal Pradesh 7 16.3755
3 Manipur 4 7.911
4 Mizoram 3 6.1980
5 Tripura 7 12.7635
6 Meghalaya 2 2.635
7 Nagaland 1 3.897
8 Sikkim 3 8.595
9 West Bengal 3 9.01
Total 74 146.2032
� During XI Plan
Sl. No. Name of State Nos of schemes Central Grant released(Rs. in crore)
1 Assam 100 744.901
2 Arunachal Pradesh 21 78.7705
3 Manipur 22 65.0315
4 Mizoram 2 3.4025
5 Tripura 11 20.91115
6 Meghalaya 0 0
7 Nagaland 11 28.965
8 Sikkim 28 82.859
9 West Bengal 6 13.394
Total 201 1038.235
129
Annual Report: 2017-18
��
�
Scheme undertaken by Government of India during X, XI, XII Plan under Flood Management Programme and monitored by Brahmaputra Board is shown below –
Plan No of schemes
Central assistance (Rs in crore)
Remarks
X Plan 74 146.20
XI Plan 201 1063.58 Rs.25,342 crore for spill over schemes of X
plan + Rs.1038.235 crore for XII plan schemes
XII Plan 61 197.27 Rs. 141.8966 crore for spill over schemes of XI
Plan+ Rs. 55.3715 cr. for XII Plan schemes
Beyond XII Plan 266.67 Rs. 21.1753 crore for spill over schemes of XI
Plan + Rs. 245.49427 cr. for XII Plan schemes
3.7 Review of the Brahmaputra Board Act 1980
Hon’ble Union Minister, Water Resources, RD & GR stressed the need for
restructuring of Brahmaputra Board to make it more effective and efficient. Earnest
efforts to restructure Brahmaputra Board were made by Government of India. Initial
move was to restructure Brahmaputra Board into a Basin Authority and then
subsequently into a Corporation. While these exercises were continuing, the Ministry
undertook a new move to restructure the Brahmaputra Board within the ambit of the
“Brahmaputra Board Act, 1980”. Extensive exercise was conducted by the Ministry
involving the top water resources experts in the country with the aim to make
Brahmaputra Board administratively and operationally more efficient. The Ministry has
come out with a robust proposal to restructure the Brahmaputra Board by revamping
of its technical and non-technical cadres within the ambit of Brahmaputra Board Act,
1980. To discuss this restructuring proposal, the 63rd Special Meeting has been
convened on 11.04.2017. Based on this, MoWR, RD and GR recommended the
proposal which was approved by Finance Ministry. The proposal was approved in the
9th meeting of High Powered Review Board of Brahmaputra Board held on 30.12.2017
at Kaziranga, Assam.
130
������������
Annual Report: 2017-18
���
�
Chapter – IV
Non-field Activities of Brahmaputra Board during the year 2017-18
4.1 Complaint Committee on Sexual Harassment and Gender Justice
In pursuance of the Hon’ble Supreme Court’s order passed in connection with the writ petition (Criminal) No.666-70 of 1992 in the case of Visakha - Vs - State of Rajasthan and others, a Complaint Mechanism to deal with such cases in the Board was constituted with seven Committee Members including a Chairperson and Member Secretary. The Committee came into force from 31.12.1997.
During the year the committee did not hold any meeting as there was no complaint from any employee.
4.2 Vigilance and Disciplinary Cases
Board has a vigilance wing headed by a Superintending Engineer as Chief Vigilance
Officer with Executive Engineer (Vigilance), one Asstt. Executive Engineer (Vig.) and
one Jr. Engineer (Vig.). The break-up of vigilance / disciplinary cases in respect of
different categories of officers and staff is given below-
Table Showing Vigilance and Disciplinary Cases during the year 2017-18 (As on 31.03.18)
Sl. No. Particulars of cases
Category of Officer/staff
Group ‘A’ Group ‘B’ Group ‘C’
1 No. of cases pending in the beginning of the year
06 02 Nil
2 No. of cases added during the year 0 0 Nil
3 No. of cases disposed during the year 01 01 Nil
4 No. of cases pending at the end of the year
05 01 Nil
4.2.1 Vigilance Week
Brahmaputra Board observed the Vigilance Awareness Week 2017 from 30.10.2017to
04.11.2017. During the Vigilance Week, some activities were performed by displaying
banners & posters in prime locations and organizing (i) Essay completion, (ii) Drawing
& Painting competition and (iii) Debate competition on vigilance matter along with
open session.
131
Annual Report: 2017-18
���
�
4.3 Participation in Seminar / Symposium / Workshop / Training
4.3.1 The list of Officers / Officials deputed for training and those participated in Seminar/
Symposium / Workshop / Training during the year 2017-18 is furnished at Annexure-V.
4.3.2 The list of officers on deputation /Loan to other organization during the year 2017-18
is furnished at Annexure-VI
4.4 PROGRESSIVE USE OF OFFICIAL LANGUAGE, HINDI
�
1. Hindi Fortnight celebration : With a view to promote the Official Language Hindi in the
official activities and to create an congenial atmosphere of Hindi amongst the officers
and staff of the Board, Hindi Fortnight was celebrated in the Board HQ, Guwahati from
8th September to 22nd September 2017 in the Board’s HQ at Guwahati. On the occasion,
10 nos. competitions in Hindi viz,- Tippan/Aalekhan, Noting/Drafting, Computer
Tangkan, Kavita Aavriti, Shrutlekhan, Ashu Bhashan, Ashu pathan, Ashu lekhan,
Prasnottari, Nibandh lekhan, Sulekhan etc. were organized and participants were given
cash prizes. Total Rs.13,200/- were given for the events. On the occasion, Brahmaputra
Board awarded cash prizes to 3 offices under the Board for their outstanding
implementation of OL Hindi. The amount of cash prizes were Rs.3000/- 1st prize, Rs.
2000/- 2nd prize and Rs.1000/-3rd prize.
Hindi day was celebrated in all field offices of the Board in different dates between 8th to
22nd September 2017.
2. Hindi Correspondence: The Board achieved an overall target of progress upto 43.81%
during the year which is declined 14.6% in comparison to 58.41% of the last year in
originating correspondence in Hindi. Keeping in view the declined progress, various
measures were adopted to increase the progress in a regular way. The Board also
suggested all concerned to take all possible follow up actions to achieve the prescribed
target in this regard.
3. Hindi Workshop : Concerted efforts were made for successful implementation of the
Official Language Policy of the Govt. of India and to create awareness amongst the
employees to execute their skill in using Hindi in office work 4(four) Hindi Workshops
were organized during the year as mentioned below :
Date Training Hours Number of nomination Number participated
02.06.2017 6 Hrs. 20 16
08.08.2017 3 Hrs. 26 26
27.12.2017 6 Hrs. 17 10
27.03.2018 6 Hrs. 20 13
Total 21 Hrs. 83 nos. 65 nos.
132
Annual Report: 2017-18
���
�
4. Town Official Language Implementation Committee’s meeting: The Nalbari Town
Official Language Implementation Committee under the Chairmanship of
Superintending Engineer, Nalbari Circle, Nalbari hold its 7th TOLIC meeting on 1st
December,2017 and review the progress of OL implementation of member offices.
The Assistant Director (OL) represented the Brahmaputra Board and attended 2 (two)
TOLIC (PSU) meetings held on 24.07.2017 and 15.12.2017 at Guwahati Refinery,
Guwahati. Board also participated in the Official Language exhibition during the meeting
on 15.12.2017.
5. Training in Hindi: During the year 8 employees have passed Hindi Pragya training
course and they have been given one year increment in the form of personal pay and
also awarded Rs. 2400/- (each) cash as cash award. During the session January to May
2018 Board established a part time training centre in HQ and nominated 24 employees
to the Parangat course. The training held regularly.
6. Seminar on the Official Language Hindi: Asstt. Director (OL), Brahmaputra Board
represented the Brahmaputra Board and presented paper in the seminar on the topic of
‘Global village mein Rajbhasha Hindi ka safar” organized by the Town Official Language
Implementation Committee (PSU) held on 23.03.2018 at Guwahati Refinery.
7. Meeting of the Official Language Implementation Committee (OLIC): The OLIC
meeting of the Brahmaputra Board met 3 (three) times during the year i. e. on
02.06.2017, 08.08.2017, 27.12.2017 & 27.03.2018. Review of the progressive use of
Official Language Hindi in the HQ as well as field offices were made and measures were
identified for the effective implementation of Hindi. Sub Committee’s meeting were also
organized in field offices.
8. Hindi Inspection: To oversee the implementation of OL Hindi, following Subordinate
field offices where the working in Hindi was below the performance level were also
inspected by the HQ office during the year. All suggestive measures were given to
speed up the implementation of OL Hindi.
Sl. No. Date of
inspection
Name of Office
1 12.05.2017 O/o Executive Engineer, Lakhimpur Division., North
Lakhimpur
2 22.11.2017 O/o Executive Engineer, Nagaon Division, Nagaon
3 25.01.2018 Jalpaiguri Division, Jalpaiguri, North Bengal
4 12.02.2018 O/o Executive Engineer, Lakhimpur Division, North
Lakhimpur
5 27.02.2018 O/o Executive Engineer, Nalbari Division, Nalbari
6 27.02.2018 O/o Superintending Engineer, Nalbari Circle, Nalbari
133
Annual Report: 2017-18
���
�
4.5 Formulation of Citizen Charter
The Citizen’s Charter in respect of Brahmaputra Board has been prepared and
uploaded in the official website www.brahmaputraboard.gov.in
4.6 Implementation of Right to Information Act 2005 (RTI)
In pursuance of the Government of India, MoWR letter No. 31/15/2004-IT/B&B/200
dated. 22.12.2005, the Right to Information Act, 2005 had been introduced in
Brahmaputra Board on 31.12.2005. After introduction of the Right to Information Act-
2005, the Brahmaputra Board had notified all relevant information pertaining to
Brahmaputra Board and also published the same in its website as a part of
administration and implementation of the Act. The information in the website is being
updated from time to time complying the directives and provision of the Right to
Information Act - 2005.
The Annual Return Information System for the year, 2017-18 is at Annexure-VII.
4.7 Observance of Swachh Bharat Abhiyan and Mass Awareness
Activities under Tribal Sub-Plan for Water Conservation during the
year 2017-18.
The Prime Minister of India had given a call for “Swachh Bharat” as a mass movement
to realize Gandhiji’s dream of a clean India by the 150th birth anniversary of Mahatma
Gandhi in 2019. Brahmaputra Board had participated in the “Swachh Bharat Mission”
(Clean India campaign) and taken action as follows –
A) During the year 2017-18, Swachh Bharat Abhiyaan was observed in the Brahmaputra
Board by organizing and observing following programme:-
(a) Cleaning of Water Bodies was done during the period 16th to 31st march 2018
S No. Water Bodies Locations District
1 Pond within the Assam
Engineering College campus
at Jalukbari
Jalukbari, Guwahati Kamrup
2 Hatkhola Pond, Nalbari Nalbari Nalbari
3 Tinikunia Pukhuri, Gopalbazar,
Nalbari
Gopalbazar, Nalbari Nalbari
4 Arnabeel, Sibbari, Silchar Sibari, Silchar Cachar
5 Sankar Misson Pond Nagaon Nagaon
6 Khalihamari Pond Khalihamari, Dibrugarh Dibrugarh
7 Subansiri Sevashram Pond,
Khelmati, Lakhimpur
Khelmati, Lakhimpur Lakhimpur
8 Pond at Natun Kamalabari
Satra, Majuli
Majuli Majuli
134
������������
Annual Report: 2017-18
���
�
��/������I9+9��!�+J�)CLEAING AT HEAD QUARTERS COLONY
�+���KD���<��!����<�8����-��������9�-� �������������*�������L9��!�+J�;CLEANING OF WATER BODY
POND AT ASSAM ENGINEERING COLLEGE CAMPUS, JALUKBARI, GUWAHATI
135
Annual Report: 2017-18
���
�
�+���KD���<��!����<�8����-��������9�-� �������������*�������L9��!�+J�;CLEANING OF WATER BODY
POND AT ASSAM ENGINEERING COLLEGE CAMPUS, JALUKBARI, GUWAHATI
136
Annual Report: 2017-18
���
�
Chapter – V
Activities on Persons with Disabilities
[ The Persons with Disabilities (Equal Opportunities, Protection of Rights
and Full Participation) Act, 1995]
5.1 Implementation of various provisions on persons with disabilities
The physically challenged persons are given facilities, concession and relaxation at the time of test / interview as per rules. The relevant rosters as prescribed by the Government are also maintained for indicating the reservation of disabled persons. 3% of posts / vacancies (1% each for orthopedic, blind &hearing handicapped) are reserved to be filled up from physically handicapped persons. The recruitment of physically challenged is under process for fulfillment of three percent quota by Brahmaputra Board. Periodic reports on the progress achieved are being sent regularly to the MoWR, RD&GR. The Brahmaputra Board is looking forward for improving the existing facilities / concessions available to the disabled persons. Board is ready to give preference to products / manufactures of disabled persons for its official uses whenever such products come to the notice of Board’s authority.
5.2 The details of sanctioned posts and the number of persons with disabilities in various posts in group ‘A’, ‘B’, and ‘C’ against 3% vacancies are as below -
As on 31.03.2018
Sl. No.
Group of posts
Sanctioned Strength
Post reserved for disabled
persons
Present position
Remarks.
1 Group ‘A’ 82 Nil Nil There is no direct recruitment post in Group – A.
2 Group ‘B’ 190 4 Nil The total direct recruitment post of Group – B is 141
3 Group ‘C’ 356 8 6
The total direct recruitment post of Group – C is 255
Total 628 12 6
Establishment – Administration
The sanctioned and filled positions as on 31.03.2018 in Brahmaputra Board are furnished in the following table –
Sl. No. Post Sanctioned Post
Post filled up
Post vacant
1. Group – A 82 27 55
2. Group – B 190 128 62
3. Group- C 356 189 167
Total 628 344 284
Detail status of the above list is shown in the enclosed Annexure-IV
137
Annual Report: 2017-18
���
�
Chapter- VI
Meeting during the year 2017-18
Important Meetings of the Brahmaputra Board
6.1 Meetings of Brahmaputra Board
6.1.1 High Powered Review Board:
6.1.1.1 9th Meeting of High Powered Review Board of Brahmaputra Board:
The 9th meeting of High Powered Review Board (HPRB) of Brahmaputra Board was
held on 30th June, 2017 at Kaziranga, Assam under Chairmanship of Hon’ble Union
Minister of Water Resources, River Development & Ganaga Rejuvenation.
Important Decision taken by HPRB:
• Confirmation of the Minutes of 8th Meeting of HPRB of Brahmaputra Board at New
Delhi on 19.6.2015
• Ratified the decision to implement the scheme “Protection of Majuli Island from flood
and erosion of river Brahmaputra Board” funded by MoDoNER Rs. 207 crore
• Rratified all the decisions of 63rdSpecialmeeting of Brahmaputra Board held on
11thApril, 2017
• Approved restructuring of Brahmaputra Board and advised that funds should be
largely spent for works and establishment costs have to be optimised
• Agreed to drop the proposal to convert Brahmaputra Board into an Authority or
Corporation
• Approved the establishment of Brahmaputra Board office complex in Majuli and
entrust the works to NPCC, a PSU under the Ministry
• Approved that the preparation of Master Plans, Feasibility Reports and DPRs for
development of the complete Brahmaputra basin be also given to WAPCOS, a PSU
under the Ministry, who may partner with leading global organizations working in the
field of integrated water management
6.1.2 Brahmaputra Board Meeting:
The 63rdSpecial, 64th and 65th(adjourned) meetings of Brahmaputra Board were held
during the year 2017-18. The 63rd special meeting was held on 11th April, 2017, 64th
meeting was held on 29.06.2017 and 65th (adjourned) meeting was held on 27th March
2018 at Brahmaputra Board HQ, Guwahati.
138
Annual Report: 2017-18
��
�
Important decisions taken by Brahmaputra Board:
6.1.2.1 63rd Special meeting;
� Confirm the Minutes of 62nd meeting of Brahmaputra Board held
on30.01.2017 at Guwahati.
� Recommend the detail Proposal of Restructuring of Brahmaputra
Board with 9 Regional Offices and re-organizing the engineering
cadre to a pyramidal structure.
� Recommend to restructure the Post of Chief Engineer -II
� To develop Infrastructure of Brahmaputra Board to accommodate
Office and residence of employees
6.1.2.2 64thmeeting:
• Confirmation of the Minutes of 63rd Special meeting of Brahmaputra
Board held on11.04.2017 at Guwahati, Assam
• Ratification of the decision of 58th Meeting of Standing Committee of
Brahmaputra Board
• Approval of Annual Accounts of Brahmaputra Board for the year 2016-17
• Approval of Annual Report of Brahmaputra Board for the year 2016-17
• Approved Master Plan of Jaldhaka
• To recommend drop the proposal to Convert Brahmaputra Board into an
Authority or Corporation
• Approved to accord a MOU with Deltares, Netherlands on “joint interest
in the development of a long-term scientific and technical cooperation in
the field of water resources, river basin management, in Brahmaputra
Basin and other river basins under the jurisdiction of Brahmaputra Board
in North Eastern Region of India (herein after referred as the ‘Region’)
disaster risk reduction and others in order to increase the exchange of
information, knowledge, technology and scientific and applied
experience, as well as implementation of joint projects”.
6.1.2.3 65th meeting:
• Confirmation of the Minutes of 64thMeeting of Brahmaputra Board held
on 29thJune, 2017 at Guwahati, Assam
• Ratification of the decision/approval of 59th Meeting of Standing
Committee of Brahmaputra Board
• Approved Master Plan of Tangani, Teesta, Torsa and Simsang
139
Annual Report: 2017-18
��
�
• Development of infrastructure of Brahmaputra Board at Majuli by
NPCC
• Awarding consultancy to WAPCOS for remaining works of
investigation and preparation of DPR of Multipurpose Projects
• Preparation of flood control and anti – erosion schemes through
WAPCOS for all rivers in BTAD area
6.1.3 Standing Committee Meeting
The 58thand 59th meetings of Standing Committee of Brahmaputra Board
were held during the year 2017-18. The 58th meeting of Standing Committee
of Brahmaputra Board was held on 21.06.2017 at Conference Hall,
Brahmaputra Board, Basistha, Guwahati and the 59thmeeting of Standing
Committee of Brahmaputra Board was held on 26.12.2017 at Conference
Hall, Brahmaputra Board, Basistha, Guwahati. The decision / approval of the
58thand 59thmeetings of Standing Committee of Brahmaputra Board were
ratified in the 64thand 65thmeeting of Brahmaputra Board, respectively.
Important decisions of Standing Committee:
6.1.3.1 58thmeeting:
(a) Action Plan of Brahmaputra Board for the year 2017-18
(b) Budget Estimate of Brahmaputra Board for the year 2017-18
(c) Approved Estimates for –
i. 3rd Revised estimate for Survey and Investigation of Killing (Umiam) M.P.
Project
ii. R&M of various assets of Brahmaputra Board for the year 2017-18
6.1.3.2 59th Meeting:
Development of Infrastructure of Brahmaputra Board at Majuli
140
Annual Report: 2017-18
���
�
6.2 ���������������� ���������������������������������
������������������� !" #���
�Sl.No
Meetings / events Attended by
1. One day Conference on “Sediment Management in Indian Rivers” held on 17.3.2017 at CSMRS Auditorium, New Delhi
Chairman
2. Attended 63rd Special meeting of Brahmaputra Board held on 11.04.2017 at Guwahati
Chairman
3. Attended 58th Standing Committee meeting of Brahmaputra Board held on 21.06.2017 at Guwahati
Chairman
4. Attended 64th meeting of Brahmaputra Board held 29.6.2018 Chairman
5. Meeting undertaken by Chairman with Senior officers of Brahmaputra Board on various issues pertaining to Brahmaputra Board on 28.8.17 at Guwahati
Chairman
6. Meeting undertaken by Chairman with Senior officers of Brahmaputra Board on various issues pertaining to Brahmaputra Board on 23.09.17 at Guwahati
Chairman
7. Meeting taken on formulation of Action Plan in respect of point No.20.13 of the minutes of Review meeting held on 16.09.2016 to review the implementation status of Bodo Accord on 5.10.2017 at Office chamber of JS(PP), MoWR, RD&GR, New Delhi
Chairman
8. Attended 1st meeting of Advisory Committee for NEHARI, Brahmaputra Board held on 6.10.2017 at Guwahati
Chairman
9. Attended the meeting of Parliamentary Standing Committee on Subordinate Legislative of Lok Sabha held on 30.10.2017 at Taj Vivanta, Guwahati
Chairman
10. Presided over the 59th Standing Committee meeting of Brahmaputra Board held on 26.12.2017 at Guwahati
Chairman
11. Attended in Foundation Stone Laying Ceremony of Protection of Majuli Island from Flood and erosion & Construction of Brahmaputra Board at Majuli on 29.12.2017
Chairman
12. Attended in 9th High Powered Review Board meeting of Brahmaputra Board held on 30.12.2017 at Borgos, Kaziranga, Assam
Chairman
13. Visited Majuli and meeting taken with representatives of M/s T.K. Engineer Pvt. Ltd and officers of Brahmaputra Board on 25.3.2018
Chairman
14. Attended 65st (adjourned) meeting of Brahmaputra Board held on 27.3.2018 at Guwahati
Chairman
141
������������
Annual Report: 2017-18
���
�
Chapter – VII
Annual Accounts and Audit
7.1 Statement of Accounts
The statements of annual accounts of Brahmaputra Board for the year 2017-18 are given in a tabular form at page no142 to 167 .in this chapter.
7.1.1 Audit: The position of audit objections raised by internal as well as external audit is furnished as under-
Position of Outstanding Audit Paras of Inspection Report of Internal Audit as on 31.03.2018
Sl
NoName of the Office
Outstanding as on 01.04.2017
Para raised during the year 2017-18
Para settled during the year 2017-18
Balance as on 31.03.2018
Guwahati Circle 0 7 4 3
Guwahati Division 5 10 10 5
Barak Valley Division 38 8 30
Agartala Division 1 1
Nagaon Division 3 5 8
Liaison Office 0 0
North Guwahati Circle 4 4
North Guwahati Division 7 7
Nalbari Circle 2 10 3 9
Nalbari Division 6 6 4 8
Jalpaiguri Division 2 2
Jorhat Circle 9 5 4
Lakhimpur Division 15 11 26
Majuli Division 9 9
Roing Division 8 8
Total 109 49 34 124
142
Annual Report: 2017-18
���
�
Position of Outstanding Paras of PAG (Audit) & Principal Director of Audit as on 31.03.2018
Investment Pattern of Brahmaputra Board Contributory Provident
Fund Trust Account as on 31.03.2018
Brahmaputra Board has invested the CPF amount conforming to Govt. Guidelines i.e. 5.66 % in Central Govt. Securities and 94.34 % in Govt. Financial institutions/Nationalized Banks.
The Investment pattern of Brahmaputra Board CPF Trust for the year ended on31st March' 2018 is given below:
Sl.No. Name of Organisation Amount Invested up to 31-3-2018 % of Investment
1 IDBI Bank Rs 4,80,39,000.00 6.81
2 Union Bank of India Rs 34,41,30,000.00 48.79
3 Syndicate Bank Rs 16,42,29,999.97 23.28
4 Bank of India Rs 1,98,00,000.00 2.81
5 NESF Bank Rs 1,00,00,000.00 1.42
6 Central Bank of India Rs 6,93,00,000.00 9.83
7 Allahabad Bank Rs 99,00,000.00 1.40
8 Nabard Rs 2,98,81,000.00 4.24
9 Govt. Loan/Bond Rs 1,00,00,000.00 1.42
Total Rs 70,52,79,999.97
Sl. No
Name of the Office Outstanding para as on 01.04.2017
Para raised during the year 2017-18
Para settled during the year 2017-18
Balance as on 31.3.2018
1 Head Quarter Office 32 11 11 32
2 Guwahati Circle 3 2 1
3 Guwahati Division 10 5 5
4 Barak Valley Division 51 2 49
5 Agartala Division 10 8 7 11
6 North Guwahati Circle 9 2 7
7 North Guwahati Division 23 7 16
8 Nagaon Division 8 4 4
9 Roing Division 23 10 11 22
10 Nalbari Circle 0 0
11 Nalbari Division (&Rangia Division)
23 14 9
12 Jalpaiguri Division 19 2 17
13 Jorhat Circle 2 1 1
14 Lakhimpur Division 11 3 8
15 Majuli Division 15 1 14
16 Liaison Office 6 2 4
Total 245 29 74 200
143
Annual Report: 2017-18
���
�
Government of India Ministry of Water Resources
River Development & Ganga Rejuvenation
ANNUAL ACCOUNTS 2017-18
BRAHMAPUTRA BOARD BASISTHA, GUWAHATI-29
Annual Report: 2017-18
���
�
144
Annual Report: 2017-18
���
�
145
Annual Report: 2017-18
���
�
146
Annual Report: 2017-18
���
�67147
Annual Report: 2017-18
��
�
148
Annual Report: 2017-18
��
�
149
Annual Report: 2017-18
���
�
150
Annual Report: 2017-18
���
�
151
Annual Report: 2017-18
���
�
152
Annual Report: 2017-18
���
�
153
Annual Report: 2017-18
���
�
154
Annual Report: 2017-18
���
�
155
Annual Report: 2017-18
���
�
156
Annual Report: 2017-18
���
�
157
Annual Report: 2017-18
��
�
158
Annual Report: 2017-18
��
�
159
Annual Report: 2017-18
��
�
160
Annual Report: 2017-18
��
�
161
Annual Report: 2017-18
��
�
162
Annual Report: 2017-18
��
�
163
Annual Report: 2017-18
��
�164
Annual Report: 2017-18
��
�
165
Annual Report: 2017-18
��
�
166
Annual Report: 2017-18
��
�
167
Annual Report: 2017-18
�
�
Separate Audit Report on the Accounts of the Brahmaputra Board,
Guwahati, Assam
For the year 2017-18
Annual Report: 2017-18
�
�
7.3 Separate Audit Report of the Comptroller and Auditor General of India on the Accounts of Brahmaputra Board, Guwahati for the year ended 31st March 2018
1. We have audited the attached Balance Sheet of Brahmaputra Board Guwahati as at
31 March 2018 and the “Income and Expenditure Account/Receipts and Payment
Account” for the year ended on that date under Section 19(2) of the Comptroller and
Auditor General’s (Duties, Power and Conditions of service) Act, 1971 read with
Brahmaputra board Act, 1980 (No 46 of 1980). These financial Statements include
the accounts of the Board and its 15 Division/Circle/Liaison office including Board.
These financial statement are the responsibility of the Brahmaputra Board’s Our
responsibility is to express an opinion on these financial statement based on our
audit.
2. This separate Audit Report contains the comments of the Comptroller and Auditor
General of India (CAG) on the accounting treatment only with regard to classification
conformity with the best accounting practices. Accounting standards and disclosure
norms, etc. Audit observations on financial transactions with regard to compliance
with the Law, Rules and Regulations (Propriety and Regularity) and efficiency-cum-
performance aspects etc, if any are reported through Reports/CAG’s Audit Reports
separately.
3. We have conducted our audit in accordance with the auditing standards generally
accepted in India. These standards require that we plan and perform the audit to
obtain reasonable assurance about whether the financial statements are free from
material misstatements. An audit Includes examining, on a test basis, evidences
supporting the amounts and disclosure in the financial statement. An audit also
includes assessing the accounting principles used and significant estimates made
management, as well as evaluating the overall presentation of financial statements.
We believe that our audit provides a reasonable basis for our opinion.
4. Based on our audit, we report that:
i) We have obtained all the information and explanations, which to the best of our
knowledge and belief were necessary for the purpose of our audit:
ii) The Balance Sheet and Income and Expenditure Account/Receipt and Payment
Account dealt with by this report have been drown up in the format approved by
the ministry of Finance, New Delhi.
iii) In our opinion, proper books of accounts and other relevant records have been
maintained by the Brahmaputra Board, Guwahati as required under Section 19(2)
of the Brahmaputra Board Act in so far as it appears from our examination of such
books.
iv) We further report that:
A. Balance Sheet
A. 1 Liabilities
168
Annual Report: 2017-18
��
�
Capital Fund (Schedule 1): Rs. 545.85 crores
As per Notes and Instruction for Schedules contained in Annexure-E of Uniform Format of Accounts, amounts received as grants or assistance or retained by the entity to be utilized for specific or earmarked purposes and remaining to be expended/utilized for the specific purpose for which these are intended, are required to be disclosed under Schedule 3 Earmarked/Endowment Funds.
During 2017-18 the Board received Rs.100.00 crore in two installments1 from the Ministry of DoNer for incurring expenditure the project “Protection of Majuli Island from Flood and Erosion of river Brahmaputra” costing Rs.233.57 crore subject to compliance of certain terms and conditions2. The Board however exhibited the above grants received from DoNer with the regular grant received from its ministry i.e. Ministry of Water Resource, River Development & Ganga Rejuvenation and entire fund of 100.00 crore had been added with Capital Fund. Since the above fund released by Ministry of DoNer for a specific project and are subject to compliance by the Board of certain stipulated terms and conditions, the entire fund should have been shown as ‘Earmarked/Endowment Funds‘ in a separate schedule. Thus, due to mixing up of the grants released by DoNER with the fund released by MoWR, RD&GR, Capital Fund of the board was overstated to the extent of Rs.100.00 crore with corresponding understatement of ‘Earmarked/Endowment funds’ to the same extent as on 31 March 2018.
B General.
1. In the year 2017-18 MoWR, RD & GR sanctioned a total budget outlay of Rs. 102.62
crore for the Board under ‘River Basin Management’ Scheme duly segregating the fund
under recurring head of Rs.59.17 crore and under non-recurring head of Rs.43.45 crore
in its sanction letter. The Board, however, had not shown the recurring grant of Rs.59.17
crore as income in the Income &Expenditure Account instead shown entire grant in
Balance Sheet as on 31.03.2018 (Schedule-1 Capital Fund) by disclosing it in Schedule-
13 Significant Accounting Policies and Notes on Accounts that the entire grant were
treated as Capital Grants as no classification was made in the sanction of grant by the
Ministry. Thus, due to non-consideration of recurring grant of Rs.59.17 crore as income
in the Income & Expenditure Accounts, “Excess of Expenditure over Income” was
overstated by Rs.59.17 crore as on31 March 2018.
2. As per Uniform Format of Accounts applicable for Central Autonomous Bodies, provision
for liability towards ‘Gratuity payable on death/retirement’. ‘Superannuation Pension’ and
‘Accumulated Leave Encashment’ of employees should be provided for and depicted in
Schedule of Current Liabilities and Provisions. The Board, however, did not make any
provisions for Gratuity, Superannuation pension and Accumulated Leave Encashment
while preparing the accounts for the rear 2017-18.
3. Non- Provisioning of NPS:
As per Ministry of Finance Office Order New Pension Scheme (NPS) had to be introduced in Central Autonomous Bodies w.e.f. 01 January 2004 for employees joined from January 2004 onwards and the process of shifting over to NPS architecture was to be completed by 31 January 2009. However, the Board had neither collected contributions from the concerned Staffs nor made any provisions for the Board contribution towards NPS in Its Balance Sheet as on 31 March 2018.
4. Board has adopted the depreciation rate as per Companies Act instead of Income tax
Act as prescribed in Uniform format of accounts.
1 Rs. 30.00crore and Rs. 70.00 crore 2 Clause 3 of the sanction letter of the fund
169
Annual Report: 2017-18
��
�
C. Grants-in-aid The Board had an unspent balance of grants-in-aid of Rs.0.45 crore as at 31st March 2017 During the year 2017-18, the Board received grants-in-aid- of Rs.202.17 crore3
Against the total grants-in-aid of Rs. 202.62 crore3, the Board utilizes Rs.84.73 crore4
Against the and balance of Rs.117.89 crore5 remained unutilized as on 31 March 2018.
D. Management letter
Deficiencies which have not been included in the Audit Report have brought to the notice of the Chairman, Brahmaputra Board, Guwahati through a management letter issued Separately for remedial/corrective action.
v). Subject to our observations in the preceding paragraphs we report that the Balance Sheet and income and Expenditure Account/Receipt and Payment Account dealt with by this report are in agreement with the book of accounts.
vi). In our opinion and to the best of our information and according to the explanations
given to us, the said financial statement read together with the Accounting Policies and Notes on Accounts, and subject to the significant matters stated above and other matters mentioned in Annexure to this Audit report give a true and fair view in conformity with accounting principles generally accepted in India .
a. In so far as relates to the Balance Sheet of the state of affairs of the Brahmaputra
Board as at 31 March 2018;
b. In so far as it relates to Income and Expenditure Account of the deficit for the year
ended on that date.
For and on behalf of the C &AG of India Place: New Delhi
Director General of Audit (Scientific Departments)
3 MoWR, RD & GR: Rs. 102.17 crore and DoNER: Rs. 100 crore 4 MoWR, RD & GR: Rs. 83.13 crore and DoNER: Rs. 1.60 crore 5 MoWR, RD & GR: Rs. 19.49 crore and DoNER: Rs. 98.40 crore
170
Annual Report: 2017-18
��
�
Annexure I to Separate Audit Report
1. Internal Audit: The Board has 15 field units. Coverage of internal audit was
inadequate During the last three year internal Audit was conducted in respect of
only 6 field unit in 2015-16; six7 field units in 2016-17 and one8 field in 2017-18
2. System of Internal control:
(i) Inadequate supervision on maintenance of register of postage stamp:
The Board maintains two Stock Registers for Postage Stamp one maintained
by the Board Head Office and other maintained by O/o the Chief Engineer-II
Though there was a system of monthly verification of closing balance of
stamps, these verifications were not done regularly with proper certificate and
conducted belatedly.
(ii) Weakness of Internal control system
(a) Consumable stores: As per Uniform Format of Account applicable for the
Central Autonomous Bodies, Current Assets include ‘Inventories” which
comprise inter alia Consumables other than machinery parts.
As per Schedule-11 other Administrative Expenses etc of Income and
Expenditure Account for the year ended 31.03.2018, total expenditure of Rs.
0.36 crore was incurred during 2017-18 for procurement of Printing and
Stationery items. Though there was a closing balance of the consumable
stores9 remaining with the Board’s HQ and its 15 field units as on 31 march
2018, the Board did not depict the value of the said closing balances of
consumable stores in Schedule-5 Current Assets, Loans Advances etc.
Consequently, the actual consumption of stores was not correctly reflected in
the expenditure side of the Income and Expenditure Account for the year
ended 31 March 2018.
(b) Postage Stamp: As per the Board’s certificate the closing balance of postage
stamp as on 31March 2018 was R.3,098.00 However, the Board did not depict
the amount of closing balance of postage stamp in the Schedule-5 Current
Assets, Loans and Advances etc. of Balance Sheet as on 31 March 2018.
Further, stamp valuing Rs. 10.000.00 purchased in March 2018, was neither
utilized during the year 2017-18 nor entered in the stock register as on 31
March 2018. Consequently, the actual consumption of stamps was not
correctly reflected in the expenditure side of Income and Expenditure Account.
3. System of Physical Verification of fixed Assets: Physical verification of fixed assets had been conducted in respect of the Board’s Head Quarter for the year
6 Majuli Division 7 Nagaon Division,Guwahati Division,Guwahati Circle, Nalbari Division,Lakhimpur Division and Nalbari Circle 8 North Guwahati Division 9 42004.5 nos, Stationery items’ 29326 nos,of Printing materials and 37 nos of Cartidges
171
Annual Report: 2017-18
��
�
2017-18 However, the Board could not furnish whether the same was conducted by its 15 Circles/Division/Units for the year 2017-18
4. System of Physical Verification of Inventories: Physical verification of inventories had been carried out in respect of the Board’s Head Quarter for the year 2017-18 However, the Board could not furnish whether the same was carried out by its 15 Circles/Divisions/Units for the year 2017-18
5. Non-provisioning of liabilities: As per Uniform Format of Account for Central
Autonomous Bodies, the central autonomous bodies are required to prepare as annual accounts as per accrual system. Further, as per instructions and Accounting Principles No.6 under Annexure-D of uniform Format of Accounts, provision shall be made for all known liabilities and losses even though the amount cannot be determined with substantial accuracy.
The Board did not make any provision for the expenditure/liability viz. salary/allowance of the employee electricity/telephone charges, contractual labour payment etc. which were pertaining to the year 2017-18, however paid in 2018-19.
Dy. Director (E.A.)
172
Ann
ual R
epor
t: 20
17-1
8
��
�
BR
AH
MA
PU
TR
A B
OA
RD
::
GU
WA
HA
TI-
29
BR
AH
MA
PU
TR
A B
OA
RD
CO
NT
RIB
UT
OR
Y P
RO
VID
EN
T F
UN
D T
RU
ST
BA
LA
NC
E S
HE
ET
AS
AT
31S
T M
AR
CH
'2018
(
Fig
ure
s i
n R
up
ees)
Pre
vio
us
Yea
r
as
on
31.0
3.2
017
C
AP
ITA
L &
LIA
BIL
ITIE
S
Cu
rren
t Y
ea
r a
s o
n
31.0
3.2
018
P
rev
iou
s Y
ea
r a
s
on
31.0
3.2
017
A
SS
ET
S
Cu
rren
t Y
ea
rs a
s o
n
31.0
3.2
018
123,0
5,2
58.1
2
EM
PL
OY
EE
S C
ON
TR
IBU
TIO
N
242,1
6,7
65.1
2
INV
ES
TM
EN
T:
1892
,75,4
36
.52
EM
PL
OY
ER
'S C
ON
TR
IBU
TIO
N1959
,41,6
35
.52
7115
,99,0
00
.00
i)
Fix
ed
Dep
osit w
ith
Bank
7052
,79,9
99
.97
1656
,62,8
24
.66
VO
LU
NT
AR
Y C
ON
TR
IBU
TIO
N
1684
,01,3
72
.66
446,0
7,8
13.5
1
ii)
Inte
rest
Accru
ed
o
n
Fix
ed
D
eposit
478,2
1,2
37.5
1
CU
RR
EN
T L
IAB
ILIT
IES
AN
DP
RO
VIS
ION
: 47,9
9,2
12.8
4
LO
AN
S
AN
D
AD
VA
NC
ES
T
OS
UB
SC
RIB
ER
S
67,2
6,6
38.8
4
3533
,43,2
04
.00
Inte
rest
Pa
yab
le t
o S
ubscri
bers
3320
,52,2
68
.00
CA
SH
AT
BA
NK
:
578,7
9,6
37.0
3
EX
CE
SS
OF
IN
CO
ME
OV
ER
123,7
7,2
09.4
9
i)
Un
ion B
ank o
f In
dia
178,9
7,5
94.5
0
EX
PE
ND
ITU
RE
598,2
5,0
08.0
150,8
3,1
24.4
9
ii) ID
BI
Bank
27,1
1,5
78.4
9
7784
,66,3
60
.33
TO
TA
L:
7804
,37,0
49
.31
7784
,66,3
60
.33
TO
TA
L:
7804
,37,0
49
.31
Junio
r A
ccounta
nt
Deputy
Fin
ancia
l A
dvis
er
Bra
hm
aputr
a B
oard
173
Ann
ual R
epor
t: 20
17-1
8
��
�
BR
AH
MA
PU
TR
A B
OA
RD
::
GU
WA
HA
TI-
29
BR
AH
MA
PU
TR
A B
OA
RD
CO
NT
RIB
UT
OR
Y P
RO
VID
EN
T F
UN
D T
RU
ST
INC
OM
E A
ND
EX
PE
ND
ITU
RE
AC
CO
UN
T F
OR
TH
E Y
EA
R E
ND
ED
ON
31
ST M
AR
CH
'2018
(F
igu
res in
Ru
pees)
AS
ON
31
ST
MA
RC
H'1
7
EX
PE
ND
ITU
RE
A
S O
N31
ST M
AR
CH
'18
A
S O
N31
ST
MA
RC
H'1
7
INC
OM
E
AS
ON
31
ST
MA
RC
H'1
8
540,8
8,6
34.0
0 T
O I
NT
ER
ES
T P
AY
AB
LE
TO
B
Y I
NT
ER
ES
T F
RO
M B
AN
K:
12,9
8,1
87.0
0
S
UB
SC
RIB
ER
S
538,7
0,5
77.0
0
12,6
6,1
83.0
0
i)
Savin
g B
ank A
/C
5
18.0
0 T
O B
AN
K C
HA
RG
ES
649.0
0
560,1
3,6
82.2
9
ii) F
ixed D
eposit R
eceip
t 5
45,1
8,4
09.9
8
31,9
0,7
13.2
9 T
O
EX
CE
SS
O
F
INC
OM
E
OV
ER
(A
ccru
ed
In
tere
st)
EX
PE
ND
ITU
RE
CA
RR
IED
O
VE
R T
O B
AL
AN
CE
SH
EE
T
19,4
5,3
70.9
8
572,7
9,8
65.2
9
TO
TA
L:
558,1
6,5
96.9
8
572,7
9,8
65.2
9
TO
TA
L:
5
58,1
6,5
96.9
8
Junio
r A
ccounta
nt
Deputy
Fin
ancia
l A
dvis
er
Bra
hm
aputr
a B
oard
174
Ann
ual R
epor
t: 20
17-1
8
��
�
BR
AH
MA
PU
TR
A B
OA
RD
::
GU
WA
HA
TI-
29
BR
AH
MA
PU
TR
A B
OA
RD
CO
NT
RIB
UT
OR
Y P
RO
VID
EN
T F
UN
D T
RU
ST
R
EC
EIP
TS
AN
D P
AY
ME
NT
S A
CC
OU
NT
FO
R T
HE
YE
AR
EN
DE
D O
N 3
1S
T M
AR
CH
'201
8
��
��
��
���������������������������� �
�
�����������
���������
���������
����������������������
�����������
���������
���������
������������������������
������������ �!����"�
��
������
���
���
�����!������������ #����"�
��
�����������
� ������������������ �
��
����
���
���
�� �������
��!�"�#$���%"�&
���
������
����
���
�
���'��������
�� ������������
����(����
��� �
���
�'�������
��� �)�����* ��� � �
���+��
!)�
����
����
���
�'����
����
���
�����
����
���
������!������������ #����"�
��
�����
����
���
�����!������������� #�����
���
����
����
���
�� �)"����"���
��,�"�����
"%�
������
����
���
��
'���
����
���
��$�!#������������ #�����
���
����
��'
���
��� �)"������ "��"-��
��������
#���
����
����
���
������������ ��!�������%��%$���������
��
������
����
���
������!������������� #����"�
��
��# ���� ����
���
����������
�� �)"����"���
��,�"�����
"%�
������
����
���
���
����'���
���� ����&�%�%�������'���� ��(�
���
����'���
����
��� �)"������ "��"-��
��������
#���
����
����
���
������
����
���
��������������%�����# ����)�
��
�'���
����
���
���$�!#������������ #�����
���
����
����
���
� �����������!�����!������
���
����
����
���
���'�����������%$���������$���������
��
��'���
�� ��(���������
���
����
��# ���� ����
���
�'��������
� ���!������ �!����"�
��
#��������$���*��%+#����������
��
�����
���
���
� ������������������ �
���
'���
����
���
����!����������)'���%��'�!�
���
����
����
���
���'�������
�� ������������
����(����
��� �
��
������'���
���
�����
����������������������&�%�
��
��
��
�%�������
���
���'���
����
��
��
����''
����
��
����������������� ��("�
��
��
��
�� �*�.��-����
��/0��
���'��'����
��
��
�
��� �)�1 %
�( �
�����2 3 ����
������
��'�
�'�
�����
���
�'�
��
��
�,-,./�.,0123������!"�
��1��.��.�-323/��,-,./�.,0123������!"�
��1��.��.�-323/�
Jun
ior
Accounta
nt
Deputy
Fin
ancia
l A
dvis
er
Bra
hm
aputr
a B
oard
175
Annual Report: 2017-18
��
�
ANNEXURES
-
- -
Annual Report: 2017-18
�
�
-Composition of the Board Appointed Under Clause - A, B, C, D and E of Sub-Section (3) of Section (4) of Brahmaputra Board Act (46 of 1980)
A Full Time Member
Sl. No.
Designation of members Name of members Tenure
1 Chairman, Brahmaputra Board
Shri Sanjay Kundu Additional Charge
2 Vice Chairman, Brahmaputra Board
Shri P. M. Scott Additional Charge
3 General Manager, Brahmaputra Board
Vacant Vacant from 01.07.14
4 Financial Adviser, Brahmaputra Board
Dr. M. Ariz Ahammed Additional charge From 22.11.16 to March 2018
B Part Time Member
Sl. No.
Designation of member Representing State/Organization
1 Secretary to the Government of Assam, Water Resources Department
To represent the Government of Assam
2 Chief Engineer, PWD(R), Government of Meghalaya
To represent the Government of Meghalaya
3 Chief Engineer, Irrigation & Flood Control Department, Government of Nagaland.
To represent the Government of Nagaland
4 Chief Engineer, PWD (WR), Government of Tripura
To represent the Government of Tripura
5 Chief Engineer, Irrigation & Flood Control Department, Government of Manipur
To represent the Government of Manipur
6 Chief Engineer, Water Resources Department, Government of Arunachal Pradesh
To represent the Government of Arunachal Pradesh
7 Chief Engineer (Civil), Power and Electricity Department, Government of Mizoram
To represent the Government of Mizoram.
8 Financial Adviser, North Eastern Council, Shillong
To represent the North Eastern Council, Shillong
9 Joint Secretary, Soil Conservation and Land Resources, Ministry of Agriculture.
To represent the Ministry of Agriculture, Government of India
10 Commissioner (B&B), Ministry of Water Resources, Government of India
To represent the Ministry of Water Resources, Government of India
11 Financial Adviser, Ministry of Water Resources, Government of India
To represent the Ministry of Finance, Government of India
12 Joint Secretary (H), Ministry of Power, Government of India
To represent the Ministry of Power, Government of India
13 Chief Engineer, Inland Waterways Authority of India, Government of India
To represent the Ministry of Surface Transport, Government of India,
14 Member (RM), Central Water Commission
To represent the Central Water Commission 176
Annual Report: 2017-18
�
�
Sl. No.
Designation of member Representing State/Organization
15 Member (HE), Central Electricity Authority
To represent the Central Electricity Authority
16 Deputy Director General, Geological Survey of India , North Eastern Region
To represent the Geological Survey of India
17 Director General of Meteorology, India Meteorological Department, Government of India
To represent the India Meteorological Department, Government of India
C Special Invitee
1 The Adviser (NE), NITI Aayog, Yojana Bhawan, Sansad Marg, New Delhi
2 The Chief Engineer (B & BBO), Central Water Commission, Shillong
3 The Secretary, Irrigation and Waterways Department, Government ofWest Bengal, Jalasampad Bhawan, Salt Lake, Kolkata
4 The Secretary, Water Resources & River Development Department, Government of Sikkim, Gangtok
5 The Secretary, Department of Development of North Eastern Region (DoNER), Vigyan Bhawan Annex, Maulana Azad Road, New Delhi
6 The Director, North Eastern Space Application Centre, Government of India,Department of Space, Umium-793 103, Meghalaya
ANNEXURE-II 177
Annual Report: 2017-18
����
�
Composition of the High Powered Review Board appointed by the Government of India Vide Resolution No. 2(17)/80-FC/460 Dated 19th March, 1982 and as Amended Vide Resolution No. 23/8/92-ER/1798 Dated 1st October, 1992
1 Union Minister for Water Resources Chairman
2 Chief Minister of Assam or a Cabinet Minister duly authorized by him
Member
3 Chief Minister of Manipur or a Cabinet Minister duly authorized by him
Member
4 Chief Minister of Meghalaya or a Cabinet Minister duly authorized by him
Member
5 Chief Minister of Nagaland or a Cabinet Minister duly authorized by him
Member
6 Chief Minister of Tripura or a Cabinet Minister duly authorized by him
Member
7 Chief Minister of Mizoram or a Cabinet Minister duly authorized by him
Member
8 Chief Minister of Arunachal Pradesh or a Cabinet Minister duly authorized by him
Member
9 Union Minister / Minister of State for Finance
Member
10 Minister of State for Water Resources
Member
11 Union Minister / Minister of State for Energy
Member
12 Union Minister / Minister of State for Agriculture.
Member
13 Union Minister / Minister of State for Surface Transport
Member
14 Secretary, Ministry of Water Resources, Government of India
Member
15 Chairman, Central Water Commission
Member
16 Chairman, Brahmaputra Board
Member-Secretary
17 Member (RM), Central Water Commission
Permanent Invitee
178
Ann
ual R
epor
t: 20
17-1
8
����
�
179
Ann
ual R
epor
t: 20
17-1
8
����
�
AN
NE
XU
RE
-IV
Sta
tem
en
t o
f R
eg
ula
r S
an
cti
on
ed
Str
en
gth
an
d N
um
bers
Po
sit
ion
of
Off
icers
/S
taff
an
d F
ield
Sta
ff
Po
sit
ion
of
SC
/ S
T /
OB
C a
nd
PH
as o
n 0
1.0
4.2
018
�!����������������
���#�)��
���#�) �
���#�)��
����!��
��4 4� �
�55��67���� )��89�8:6;��
�55��67���� ),�
�55��67���� )��
���������%�
���������
�62����6�7�6�
#��������� �����
���������%�
���������
�62����6�7�6�
#��������� �����
���������%�
���������
�62����6�7�6�
#��������� �����
��,�
��0�
-�/�
����
3��1�
���
�,�����0��-�
�/�
���
����3�,1�,��,,�,��,0�
,-�
�����
"%4��5
�%�6"���
7++�3 �
��3�,%
��-�
8�������7++�3 �
��
-�0�
����
����
��
,/�
�/�
����
����
��
0-����
����
����
��
�/�
�)����
3 �$
��-�
,�,�
����
����
����
����
����
�/�
3���
����
���3�
��!����
��-�$��-�
/���
����
���
���
-���
���
����
/���
���
���,�
��$�"���$
��-�
,�,�
����
����
-�0�
����
����
��,�
����
����
�1�
��*,�
"��� �%��-�
��-
��
"���)� �%� �
7++�3 ��
��,�
����
����
��1�
����
����
�0�
1���
����
��,0�
���1 3,��. �
��-
��
"��
�)� �% �
7++�3 ��
���
3���
���
�����
�0���
���
�
���10�
/����
�'�
���
������
������!<�
�,�
��
����
���
���31�
����
���
���
���
���-/�
����
���
���
���
���
/,��
�03�
180
Ann
ual R
epor
t: 20
17-1
8
����
�
An
nexu
re-I
V (
A)
ST
AT
EM
EN
T O
F R
EG
UL
AR
SA
NC
TIO
NE
D S
TR
EN
GT
H A
ND
NU
MB
ER
S I
N P
OS
ITIO
N O
F O
FF
ICE
RS
/ S
TA
FF
AN
D F
IEL
D S
TA
FF
AL
ON
G
WIT
H T
HE
PO
SIT
ION
OF
SC
/ST
/OB
C/P
H
AS
ON
01-0
4-2
018
�!�
���������������
���#�)��
���#�) �
���#�)��
����!�
��4 4� �
�55��67���� )��89�8:6;��
�55��67���� ),�
�55��67���� )��
���������%�
���������
�62����6�7�6�
#��
���
���
� ��
���
���������%�
���������
�62����6�7�6�
#��
���
���
� ��
���
���������%�
���������
�62����6�7�6�
#��
���
���
� ��
���
��,�
��0�
-�/�
����
3��1�
���
�,�
���
�0�
�-�
�/�
���
���
�3�
,1�
,��
,,�
,��
,0�
,-�
��
�9=��7�87�6�
>�
��?��78��87�'���
��
����
����
����
��
,1�
���
����
����
��
�0�
,0�
����
����
��
-��
8�������7++�3 �
����
����
����
��,�
����
����
-���
����
����
3�
9�-����3 �
��1�
����
����
��1�
����
����
,���
����
����
0�
5 �
%:,�
"� "��
1�1�
����
����
,���
����
����
0���
����
����
/�
����!�
-�0�
1���
1�1�
,/�
�/�
/���
��1�
0-�
���
����
0���
�/�
�)����
3 �$
��-�
,�,�
����
����
����
����
����
�/�
3���
����
���3�
��!����
��-�$��-�
/���
����
���
���
-���
���
����
/���
���
���,�
��$�"���$
��-�
,�,�
����
����
-�0�
����
����
��,�
����
����
�1�
��
;�"������"3� �
��1�
����
����
��,�
����
����
-���
����
����
3�
<�"���=�����"3� �
����
����
����
��1�
����
����
,���
����
����
0�
=,&
�������
�"3� �
����
����
����
����
����
����
-�0�
����
����
��
<��>�
"����"3� �
1�1�
����
����
,�,�
����
����
,���
����
����
0�
����!�
��,�
1�1�
��1�
��-��
1�1�
��1�
�0�
�3�
��1�
0�1�
,0�
��
=,&
������(
�.������
����
����
����
�1�
-���
����
���3�
3���
����
���1�
<�"���=���(�.��
,�,�
����
����
/�,�
����
����
0�,�
���
����
�,�
<�-
����(�.��
��1�
����
����
-�,�
���
����
�,�
���
����
����
���
<��>�
"��(�.��
����
����
����
���
-��
����
�����
�-�
����
���
�1�
?�@,���(
�.��
����
����
����
��-�
����
���
3�-�
����
����
���
8������,
"�(�.��
����
����
����
/���
����
����
�1�
����
����
�����
2���-
�(�.��
��1�
����
����
���
0��
����
����
����
��
��,1�
��"���9��� ��(�.��
����
����
����
�1�
����
����
�����
3���
���
��,0�
/-�
"�����(�.��
����
����
����
��,�
����
����
-���
���
����
3�
;�����-,
"��(�.��
����
����
����
0���
����
����
/���
����
���
���
����!�
���
3���
1�,�
1����
�0��0�
��,,�
1��10�
/�����
�����
������
������%�����!�<�
�,�
,3�
,,��
����
-�1�
�31�
��1�
��-�
,��
/����
1��-/�
�31�
�����,3�
���
���
/�/,��
�03�
181
Annual Report: 2017-18
����
�
ANNEXURE-V
LIST OF OFFICERS WHO ATTENDED TRAINING/SEMINAR/WORKSHOP DURING THE YEAR 2017-18
S.N Name Detail of Seminar/Workshop/
Training/Course attended
Place of training
Period of training
1 Pranab Jyoti Sarma, JE Public Procurement E-Procurement,Govt, E-market place (G eM) E-market place (GeM)
IT & PR,New Delhi
19- 21 April,2018
2 Durgadhar Das, JE
3 Iltaf Hussain, Secretary Office management & RTI Brahmaputra Board
HQs, Guwahati
29.11.2017
4 Chan Mohan Das,SE
5 Dhrubajyoti Borgohain,SE
6 Gaya Prasad Singh,SE
7 Joy Barman,SE
8 Mrs. Jyotika Pegu,CVO
9 N.N. Deka,D.F.A
10 Hemanta Gogoi,EE
11 Dina Nath Bujarbaruah,SE
12 J. C. Mazumdar,EE
13 Ranjit Saikia,EE
14 Mukul Ch. Lahkar,EE
15 Brajendra Kr.Talukdar,AEE
16 Sailendra Kr. Talukdar,AEE
17 M. Koirala, AD (OL)
18 Abhijit Boruah,A.O
19 D.N. Kalita,AEE
20 Kanakeswar Goswami,SO
21 D.K. Das ,Sup Gd-I
22 S.K. Boruah,AG-I
23 K.C.Kotoky,AG-I
24 Kishor Sarma,UDC
25 Paresh Sarma,UDC
26 Joy kanta Sarma,UDC
27 Prabin Borah ,JE
28 Deepak Kr. Das,JE
29 A.R. Borah,UDC
30 Biswajit Bose ,JE
31 T. Chakraborty,JE
32 N.C. Basumatary ,JE
33 N.Chetia,JE
34 Anjan Kr. Dutta,JE
35 J.J. Saikia,JE
36 Ranjan Rai,JE
37 Milon Sengupta,JE
38 Kishor Kr. Das ,JE
39 Sachindra Kalita,UDC
40 Basanta Deka,UDC
41 T. Ahmed ,UDC
42 S.C. Boruah,UDC
43 N.K. Dutta,Jr. Actt
44 Dipak kr. Das ,Jr. Actt
45 Jayanta Das,Jr. Actt
46 Simanta Hazarika,Jr. Actt
182
Annual Report: 2017-18
����
�
S.N Name Detail of Seminar/Workshop/
Training/Course attended
Place of training
Period of training
47 Dilip Kr. Deka,Jr. Actt
48 Smt. Anupama Seal,LDC
49 Ms. Anupama Handique,LDC
50 Rajiv Bhagawati,LDC
51 Nokul Changami,LDC
52 Imtaz Khanikar, LDC
53 Prafulla Deka , LDC
54 M. Basumatary,LDC
55 Pranabjyoti Sarma,JE Gem & GFR,2017 NIFM,Faridabad
21 -22 August 2017
56 NN Deka, DFA Public Procurement under GFR 2017
ISTM New Delhi 57 Ranjit Kr Saikia, EE
58 Shymal Deka ,EE World water Summit Convention Centre NDCC New Delhi
22.3.2018
59 Durgadhar Das, JE
60 Rajkumar Thakur, JE
61 Iltaf Hussain, Ex Sec Deliberation of interim report of Expert Committee Management of NE regions Water resources
Guwahati 23.4.2018
62 D.J. Borgohai ,CE
63 Ranjit Deka,EE
64 D.J Borgohai SE(P) Brahmaputra River Basin Conclave
Guwahati university
12-13 Feb 2018 65 Ranjit Deka,
66 Bhaskar Choudhury,AEE
67 Asit Chaturvedy Dy CE National Conference Cum Roadshow on waterway A gateway in North East
Guwahati Hotel Redission Blue
22-23 May 2017
68 Joy Burman SE (P)
69 D J Borgohai,CE Proper Management of North East India Water Resources
70 Ranjit Deka,EE
71 Iltaf Hussain,Sec Expanding tradable benefits of transboundary water promoting navigational uses of Inland waterways in Ganga & Brahmaputra
Dhaka Bangladesh
10.8.2017
72 GP Singh,SE Technical level meeting on water resources matters
Dhaka Bangladesh
18.5.2017
73 Bharati Patowary Baruah SE
State Consultation on MSP on River Bank erosion in Brahmaputra River Basin
OX FAM IndiaIIT,Ghy
23.4.2018
74 Mrinal Sarma EE
75 TC Borah Organisational development oriented training
IIM Ahmadabad 76 GP Singh
77 PC Saloi
78 R K Saikia
79 Dipak Saikia
80 Ranendra Kalita
81 MKB Singh
82 Alemwati Longkumer Hydrological Sciences and disaster Management
NERIWALM,Tezpur
8-9 March 2018 83 Kishore Kumar Das
84 Ranjan Rai
85 Roushanara Begum
86 Sanjiv Barman
87 GP Singh,SE, Impact Assesment for policy CEF ASC of 15-16 Feb
183
Annual Report: 2017-18
����
�
S.N Name Detail of Seminar/Workshop/
Training/Course attended
Place of training
Period of training
88 Shymal Deka,EE makers India New Delhi
2018
89 Sanjay Kumar Kundu, Launch Workshop on Proper management of WRm in North East
World Bank/Donear,New Delhi
18.12.17
90 PM Scott
91 CM Das
92 DJ Borgohai
93 D Bujarbaruah
94 Dipak Saikia
95 Shri Chan Mohan Das Leadership Motivation and ethical governance
Brahmaputra Board HQs, Guwahati
11.9.2017
96 Dhrubajyoti Borgohain
97 Gaya Prasad Singh
98 Joy Barman
99 Thaneswar Bora
100 Hemanta Gogoi
101 Prahlad Saloi
102 Deben Sarma
103 Dipak Saikia
104 Dina Nath Bujarbaruah
105 Jatin Chandra Mazumdar
106 Ramesh Panowar
107 Mrs. Bharati Patowary Baruah
108 Nripendra Nath Deka
109 Mukul Ch. Lahkar
110 Brajendra Kr. Talukdar
111 Ranendra Kalita
112 M.K. B. Singh
113 Atul Sarma
114 Sailendra Kr. Talukdar
115 Kulendra Kr. Bhagawati
116 Hari Prasad Saikia
117 Anil Kumar Deka
118 Bhaskarjyoti Choudhury
119 Ranjit Deka
120 Shymal Deka,EE Country focused training course on integrated Water Management in Water Resources Development
Japan JICA 26th Nov to 16th Dec & 21st Jan to 10th Feb 2018
121 Ranjit Deke,EE
122 Bhaskar jyoti choudhury,EE
123 Alemwati Long kumer,JE -Do- II phase
-do- 21st January 2018 to 10th February 2018
124 Paragjit Sarma,JE
184
Annual Report: 2017-18
����
�
ANNEXURE- VI
List of Officers on deputation to other organization (As on 31.03.2018)
Sl.No.
Name & designation Name of the Organization Period of deputation
1 Shri Dharanidhar Bharali Jr. Engineer N.F. Railway 19.12.2014to till date
Detail Officials of Brahmaputra Board Working on Loan up to 31.03.2018
S.N. Name of employee Designation Date of joining in CWC/ CGWB
1 Sri Arnav Barman Jr. Engineer 15.11.2016
2 Sri Dayananda Hatibaruah Jr. Engineer 02.11.2016
3 Sri Deepak Kumar Jr. Engineer 10.11.2016
4 Sri Jayanta Thakuria Jr. Engineer 11.11.2016
5 Sri Kartik Ghosh Jr. Engineer 16.11.2016
6 Sri Kripamoy Das Jr. Engineer 04.01.2016
7 Sri Lalbabu Roy Jr. Engineer 15.11.2016
8 Sri Madhurjya Kr. Borah Jr. Engineer 05.11.2016
9 Sri Palash Thakuria Jr. Engineer 18.11.2016
10 Sri Suren Bhagawati Jr. Engineer 16.11.2016
11 Sri Vinay Kumar Jr. Engineer 08.11.2016
12 Sri Jyotish Ch. Lahkar UDC 10.11.2016
13 Sri Padma Nath Saikia LDC 07.11.2016
14 Sri Richard Chand Jr. Engineer 03.01.2017
15 Sri Munindra Kr. Barman Jr. Engineer Not yet joined
16 Sri Bhogeswar Borchetia Jr. Engineer 02.01.2017
17 Sri Bharat Ch. Debnath Jr. Engineer
18 Sri T.D. Purkayastha Jr. Engineer
19 Sri Joyeep Das Jr. Engineer 07.01.2017
20 Sri Anupam Nath Jr. Engineer 09.01.2017
21 Miss Likirani Bhoi Jr. Engineer 10.01.2017
22 Sri Gautam Kr. Bhattacharjya Jr. Engineer
23 Sri Nabin Ch. Bora Jr. Engineer 03.01.2017
24 Sri Hemanta Saikia Jr. Engineer 10.01.2017
25 Sri Noor Alam Jr. Engineer 10.01.2017
26 Sri Numal Ch. Kuli Jr. Engineer 12.01.2017
27 Sri Chikon Baruah Tracer 23.01.2017
28 Sri Ghana Kanta Sonowal Blue Printer Not yet joined
29 Sri Chandan Deka UDC 13.01.2017
30 Sri Nil Ratan Singh Driver 06.01.2017
31 Mrs. Yane Mibang Chowkidar 12.01.2017
32 Sri Nripendra Nath Haloi W/C Boatman
33 Sri Ajmal Ali Driver
34 Sri Farukh Ahmed Mazumder Peon
35 Sri Jahir Uddin Barlaskar Peon
36 Sri Jitendra Prasad Jr. Engineer 23.02.2017
185
Annual Report: 2017-18
���
�
ANNEXURE-VII
RTI Annual Return information system for the year 2017-18
Ministry / Department / Organization: Brahmaputra Board, Basistha, Guwahati-29
Year: 2017-18 (Up to 31.03.2018)
Progress Report in 2017-18
Opening Balance As on 01.04.2017
No. of application received during the year as transfer from other PAs
Received during the year (including cases transferred to other Public Authority)
No. of cases transferred to other Public Authorities -U/S 6(3)
Decisions where requests/ appeals rejected
Decisions where requests/ appeals accepted
Requests 1 18 14 1 Nil 22
First appeals
Nil Nil Nil Nil Nil Nil
No. of cases where disciplinary action taken against any Officer Nil
No. of CAPIOs designated No. of CPIOs designated No. of AAs designated
16 1 1
No. of items of various provisions invoked while rejecting requests
Relevancy sections of RTI Act, 2005
Section 8 (1) Sections
a b c d e f g h i j 9 11 24 Other
Nil Nil Nil Nil Nil Nil Nil Nil Nil 1 Nil Nil Nil Nil
Amount of charges collected (in Rs.)
Registration fees Additional fees and any other charges
Penalties amount
230 Nil Nil
186
Annual Report: 2017-18
���
�
ANNEXURE- VIII
Status of Master Plan as on 31.03.2018
A. Approved by Govt of India1. Brahmaputra Main Stem- Part-I 42. Dhansiri (North) 2. Barak & its tributaries-Part-II 43. Barnadi 3. Buridehing 44. Buroi 4. Dikhow 45. Brahmajan 5. Dhansiri 46. Beki-Manas-Aie 6. Kopilli Kollong 47. Dudhnoi-Krishnai 7. Puthimari 48. Bargang 8. Ranganadi 49. Tipkai 9. Gumti B. Once Board Approved. Further
modified as per suggestion of MOWR,RD&GRApproved by 64
th and 65
thmeeting of
Board
10. Pagladiya 11. Noa-nadi
12. Dikrong 50. Jaldhaka 13. Muhuri 51. Tangani 14. Jia-Bharali 52. Torsa 15. Manu 53. Teesta 16. Champamati 54. Simsang 17. Disang C. Board Approved. Under further
modification as suggested byMOWR,RD&GR
18. Jinary
19. Na-Noi 55. Umngot 20. Juri 56. Sankosh - Raidak 21. Burima 57. Kynshi 22. Dhalai D. Draft completed. Further to be modified
as suggested byMOWR,RD&GR 23. Jiadhal 24. Bharalu 58. Ganol 25. Lohit 59. Waikhyrwi 26. Majuli island 60. Umtru 27. Khowai 61. Umsohryngkew 28. Ghiladhari E. Sub-Basins identified for preparation of
Master Plans29. Jinjiram 30. Dhaleswari 62. Dareng 31. Moridhal 63. Bugi 32. Jhanji 64. Umiew 33. Subansiri 65. Myntdu 34. Gaurang 66. Lubha 35. Haora 67. Imphal River 36. Gabharu 68. Feni River 37. Gadadhar 69. Kolodyne 38. Bhogdoi 70. Tuichang 39. Belsiri 40. Kulsi-Deosila 41. Depota Total - 70
�
�
��
�
�� �����������������������������������������������������
����������������������������������������
��������������� �!"����#�������������$�%�������������������������&&�������
���'"()*)�+�)$�������������,��������,-���������&����
#����"����#�������������$�.�����������������������������
��&&���������'"()*)�+�)
���������������$�%�����������������������#������������
��&&����������'�()*)�+�)��������&����� -
��� #��������������������������������� /
187
Annual Report: 2017-18
�
Status of DDS as on 31.03.2018
A. Completed and handed over to WRD, Assam: i) Harang ii) East of Barpeta
B. Scheme under execution:i) Barbhag ii) Amjur iii) Jengrai iv) Jakaichuk
C. Execution suspended due to inability of State to provide land: i) Kailashahar ii) Singla
D. Handed over to State Governments:i) Rudrasagar – Tripura.ii) Kalamonijan - Assamiii) Nelli- Assam
E. TEC accorded by CWC:i) Depota ii) Pola
F. DPR under revision for execution:i) Demow
G. Deleted by Board :i) Joysagar ii) Rongsai iii) Sessa
H. Under compliance of observations of CWC: i) Pota Kolong ii) Deroi iii) Larsing iv) Dharmanagar
��
�
0
�
0
�,
�
����
Status of DDS as on 31.03.2018
Completed and handed over to WRD, I. Under preparationcollection in Field Office:i) Sonai
ii) Laura-Jamira-Sessa
iii) Punir
iv) Ghiladhari
v) Tingrai
vi) Haria-Nanoi
Scheme under execution:
Execution suspended due to inability of
Handed over to State Governments: J. Schemes under process of deletion: i) Konwarpur
ii) Badri
iii) Mora-Dikrong
iv) Sukhsagar
v) Mora-Pichalamukh
vi) Pakania
vii) Namdang
viii) Sisapathar
ix) Gelabil
x) West of Barpeta
xi) Ghagra
xii) Bherekibil
xiii) Khatra
xiv) Batha
execution:
Under compliance of observations of
A. Completed and handed over to WRD,
B. Scheme under execution:
C. Execution suspended due to inability of State to provide land:
D. Handed over to State Governments:
E. TEC accorded by CWC:
F. DPR revised for execution:
G. Deleted by Board :
H. Under compliance of observations of CWC:
I. Under preparation of DPR / Data collection in FieldOffice:
J. Schemes under process of deletion:
188
ANNEXURE- IX
Under preparation of DPR / Data d Office:
Sessa
Schemes under process of
Pichalamukh
West of Barpeta
WRD, Assam:
Execution suspended due to inability of State to
Handed over to State Governments:
Under compliance of observations of CWC:
Under preparation of DPR / Data collection in Field
Annual Report: 2017-18
�
Status of MPP
A. DPR completed and handed over to other organisation
i) Dihang (Siang) Dam Project ii) Subansiri Dam Projectiii) Dibang MP Project iv) Tipaimukh Dam Projectv) Bairabi Dam Project
B. DPR completed and taken u
Pagladiya Dam Project
C. All Chapters of DPR cleared by CWC & CEA
i) Kulsi Multipurpose Projectii) Noa-Dihing Multipurpose Project
D. DPR partially completed and handed over to other o
i) Dibang Dam Project ii) Lohit Dam Project
E. Project initially under Brahmaputra Board handed ovGovt. of Meghalaya:
i) Kynshi Stage ii) Kynshi Stage
F. Under Survey & Investigation:i) Jiadhal Multipupose Projecti) Killing Dam Projectii) Simsang Multipurpose project
�
0
�
�
����
Status of MPP as on 31.03.2018
DPR completed and handed over to other organisations:
hang (Siang) Dam Project - Handed over to NHPC Subansiri Dam Project- Handed over to NHPC Dibang MP Project - Handed over to NHPC Tipaimukh Dam Project- Handed over to NEEPCO
Dam Project – Handed over to Govt. of Mizoram
DPR completed and taken up for execution:
Pagladiya Dam Project- Closed due to inability to provide land for constru
All Chapters of DPR cleared by CWC & CEA :
Kulsi Multipurpose ProjectDihing Multipurpose Project
DPR partially completed and handed over to other organisations:
Dam Project - Handed over to NHPC Lohit Dam Project - Handed over to private developers by Arunachal Govt
Project initially under Brahmaputra Board handed over to private developer by Govt. of Meghalaya:
Kynshi Stage –I Dam project Kynshi Stage –II Dam Project
Under Survey & Investigation:Jiadhal Multipupose ProjectKilling Dam ProjectSimsang Multipurpose project
-
�$��1)��������������������������������������&������
-
#$��1)�����������������2�����������3��������
4$�����4������������1)�������������4(4�+�45���
�$�.������������+��������&������
5$��1)���������������������������������������������
��&����������� �
%$�1��6��������������������#�����������#�����������
����������������������������$����'�&�������
189
ANNEXURE- X
Closed due to inability to provide land for construction
rganisations:
Handed over to private developers by Arunachal Govt.
er to private developer by
�$��1)��������������������������������������&�����������
#$��1)�����������������2�����������3��������
4$�����4������������1)�������������4(4�+�45��� �
�$�.������������+��������&������ 0
5$��1)����������������������������������������������
%$�1��6��������������������#�����������#�����������������
����������������������������$����'�&������� �