Upload
phungdieu
View
213
Download
1
Embed Size (px)
Citation preview
i
SUMMER INTERNSHIP REPORT
ON
Analysis of Tariff orders of Distribution Utilities issued by
respective SERCs of Haryana, Gujarat and Maharashtra &
Impact of SOP on their tariff
Under the Guidance of
Ms. VARDAH SAGHIR SR. FELLOW, NPTI
Mr. RAVI DESHMUKH (MD) (PPS ENERGY SOLUTIONS LTD.)
By
Sangharsha Arun Kelzare Batch: 2012-14
Roll N0 75 MBA (POWER MANAGEMENT)
Sector-33,
Faridabad – 121003, Haryana (Under the Ministry of Power, Govt. of India)
Affiliated to
MAHARSHI DAYANAND UNIVERSITY, ROTHAK
AUGUST 2013
ii
DECLARATION
I, Sangharsha Arun Kelzare, Roll No. 75, of MBA (Power Management), National Power
Training Institute, Faridabad, completed my summer internship of eight weeks at PPS
Energy Solution, hereby declare that Summer Internship Report titled Analysis of Tariff
orders of Distribution Utilities issued by respective SERCs of Haryana, Gujarat and
Maharashtra & Impact of SOP on their tariff is an original work and the same has not been
submitted to any other institute for award of any other degree.
A Seminar presentation of the Training report was made on August ______________and the
suggestions as approved by the faculty were duly incorporated.
Presentation In-Charge Signature of the Candidate
Counter signed
Director/Principal of the Institute
iii
Acknowledgement
At the outset, I am grateful to PPS Energy Solution Limited for giving me the opportunity to
do my summer internship with them.
I take this opportunity to thank Sh .Ravi G. Deshmukh., besides guiding me PPS Energy
Solution limited he also encouraged and motivated me throughout my summer internship
program. He gave me his valuable time and supported me at each step with his expertise and
provided me all the information required for my project.
I’m also thankful to Ms. Vardah Saghir Sr. Fellow, NPTI for her valuable suggestions.
I also thank Mr. S.K Choudhary (Principle Director, CAMPS), Ms. Manju Mam ( Director,
NPTI) & Ms. Indu Maheswari, (Dy. Director, NPTI), , Dr. Rohit Verma, (Dy. Director,
NPTI), and Ms. Farida Khan for arranging my summer internship program with PPS
Energy Solution Limited and providing assistance and support whenever required.
I duly acknowledge with gratitude the help and cooperation received from the entire PPS
Energy Solution limited.
Sangharsha Arun Kelzare
iv
EXECUTIVE SUMMARY:
Under this study, a comprehensive survey of tariff orders issued by different SERCs was
undertaken and the findings were compiled in a uniform format for all the states. In
particular, the study had attempted to bring out the following:
Comparison of approaches followed by SERCs towards different elements of annual
revenue requirement (ARR).
Compliance attained by the regulated utility with the costs approved and the directives
issued by SERCs.
Examination of regulatory effectiveness w.r.t. such parameters as T&D loss reduction,
extent of tariff rationalization, employee productivity, etc.
Identification of initiatives taken by SERCs that could be replicated in other states
This project is carried out to understand the different approaches adopted by the State
Electricity Regulatory Commissions (SERCs) while analyzing & approving the financial &
operational parameters, treatment of variation in expenses, Multi Year Tariff (MYT) or
annual tariff determination approach & tariff design principles employed for fixing the Retail
tariff for DISCOMs under their jurisdiction.
The enactment of Electricity Act 2003 has provided the legal framework to bring the reforms
in electricity sector. The Act has also empowered & given the responsibilities to the SERCs
to deal with the operational matters related to Distribution of electricity. The Section 61
(Tariff Regulations) & Section 62 (Determination of Tariff) of Electricity Act 2003, notifies
the function of SERCs to determine the tariff for Generation, Transmission, supply &
wheeling charges for electricity, wholesale, bulk or retail tariff as in the case may be, within
their area of jurisdiction. SERCs have issued Tariff Orders for the DISCOMs after analyzing
& approving the Aggregate Revenue Requirement (ARR) of the DISCOMs. This Project is
an attempt to study the approaches adopted by SERCs & their effect on DISCOMs
performance.
v
This Project has analyzed the Distribution ARR & Tariff Orders issued by the 3 SERCs of
States namely Haryana, Gujarat, & Maharashtra during the last five years i.e. from FY 2007-
08 to FY 2011-12.
The objective of the study is analysis of Tariff Orders & Other related Orders of State
Electricity Regulatory Commissions (SERCs) with focus on:
Tariff Rationalization;
MYT – Base Line Data;
Wheeling Charges & Transmission Charges : Separation and
Rationalization;
Subsidy Payment and its Treatment in Tariff;
Power Purchase Cost.
The second part of the project deals with The Standard of Performance of different utilities.
To study the Standard Of Performance of different utilities is that to know whether
the utilities are performing with that standard which are specified by the SERC’Cs
To understand Reliability Indices according to International Standards.
To Study the management tool for implementing reliability indices in different states
vi
Contents 1. ORGANIZATION PROFILE ........................................................................................................ 1
1.1 About the organization ........................................................................................................ 1
1.2 ORGANIZATION SERVICES .................................................................................................... 3
Energy Management .................................................................................................................. 3
Consultancy ............................................................................................................................... 4
Infrastructure Development & Maintenance ............................................................................... 4
Project Management .................................................................................................................. 4
Critical Assessment of PPS Energy Solution Ltd ........................................................................ 4
1.3 SWOT ANALYSIS ................................................................................................................. 5
Strengths ................................................................................................................................... 5
Opportunities ............................................................................................................................. 5
Threats ...................................................................................................................................... 5
2. OBJECTIVE OF PROJECT: ......................................................................................................... 6
3. SIGNIFICANCE OF THE STUDY: ................................................................................................ 7
4. SCOPE OF THE PROJECT: ........................................................................................................ 9
5. INTRODUCTION.................................................................................................................... 11
5.1 REGULATORY PROCESS: ..................................................................................................... 11
5.2 TARIFF APPROACH ADOPTED BY COMMISSIONS: ............................................................... 14
5.3 STATUS OF REFORMS: ........................................................................................................ 16
6. SERCS APPROACH TOWARDS FINANCIAL & OPERATIONAL PARAMETERS: ............................ 17
6.1 ENERGY SALES:................................................................................................................... 18
6.2 POWER PURCHASE: ............................................................................................................ 21
Merit Order Dispatch ............................................................................................................... 28
6.3 DISTRIBUTION LOSSES: ....................................................................................................... 30
6.4 CAPITAL EXPENDITURE: ...................................................................................................... 33
6.5 CAPITAL STRUCTURE: ......................................................................................................... 34
6.6 DEPRECIATION: .................................................................................................................. 34
6.7 RATE OF RETURN (ROE OR ROCE): ...................................................................................... 38
6.8 INTEREST AND FINANCE CHARGES: .................................................................................... 42
6.9 INTEREST ON WORKING CAPITAL: ...................................................................................... 45
6.10 OPERATION & MAINTENANCE EXPENSES: ........................................................................ 48
7. IMPACT OF STANDARD OF PERFORMANCE ON TARIFF ......................................................... 61
7.1 Standards of Performance .................................................................................................. 61
vii
7.2 Title, Extent and Commencement: ................................................................................... 62
8. PARAMETERS OF STANDARD OF PERFORMANCE:................................................................. 64
8.1. RELIABILITY OF THE SYSTEM .............................................................................................. 64
8.2. Exemption......................................................................................................................... 65
8.3 INFORMATION REGARDING LEVEL OF PERFORMANCE: ...................................................... 66
8.4. Handling of complaint: ...................................................................................................... 69
8.5 COMPENSATION: ............................................................................................................... 72
9. EFFECTS OF STANDARD OF PERFORMANCE ON TARIFF: ....................................................... 75
10. CONCLUSION: .................................................................................................................... 77
11. RECOMMENDATIONS: ........................................................................................................ 81
12. REFERENCES:...................................................................................................................... 85
1
1. ORGANIZATION PROFILE
1.1 About the organization PPS is an ambitious company, established by enterprising engineering professionals in
the year 2004. The company offers services pertaining to Energy, Engineering and
Architecture to clients across the globe. PPS team is based in Pune, a city known for
its Software and Engineering talent in India. PPS is a rapidly growing company with a
team of about 100 people which includes highly trained and experienced Techno-
Managers, Analysts, and Engineers & Detailers. In the PPS philosophy, the client
always comes first.
Understanding every clients‟ needs and requirements & to offer customized solutions
is an endeavour undertaken by each one of their employees. PPS prides itself as a
technology driven company. Company believes that use of cutting edge technology
can greatly enhance output & quality, reduce project life cycle & optimize costs in
long run.
Figure 1- Organization setup
PPS values the natural resources and is committed to preserve them. Company
promotes all environment friendly techniques to the maximum extent. As a natural
Energy Consulting
• Cost reduction /Process • Reengineering/Organisation Design
Policy & Regulations
• Regulatory Economics/ PPP Model/Governance
Development Consulting
• Project Advisory/Bid Advisory/Financial Restructuring/Capacity Building/Energy
Efficient Building Advisory
2
corollary of their commitment to the environment & energy efficient structures, the
company entered the energy sector as a service provider to the various arms of the
power industry under the name of PPS Energy Solutions Pvt. Ltd.
PPS Energy Solutions is primarily formed to serve their clients to meet numerous
challenges created by a rapidly growing energy market. They are focused on pro-
viding affordable energy solutions for our clients in energy & power sector.
3
1.2 ORGANIZATION SERVICES
Figure 2- Organization Services
Energy Management Energy Audits PPS Team offer Energy Audits for:
Process Industries Steel, cement, chemical, etc.
Power Distribution Sub stations, switching stations, distribution feeders, etc.
Commercial Buildings Malls, operating plants, offices, hospitals, colleges,
etc.
Generation Units Mini / micro generation utilities
PPS Energy
Energy management
Project Management
Consultancy
Infrastructure Development
& Maintenance
4
Energy Planning & Optimization
PPS do Energy Efficiency studies and provide solutions regarding green
building & lighting simulations.
Consultancy
Power Distribution End to end support in distribution loss reduction, asset
management, formulation of various schemes, DPR & claims for various power
utilities Renewable Energy Complete support to clients for establishing renewable
power generation units Rural Electrification Formulation of DPR & schemes for rural
electrification. Also supporting clients for developing rural electrification
infrastructure. Power Regulation Offer regulatory support to power utility companies,
transmission companies, generation units, utility consumers, industries & power
market etc for filing petitions & sorting out the problems thereof. Power Generation
Formulation of feasibility report, project report, tariff proposals, power purchase
agreements, fund arrangements for Mini and Micro projects.
Infrastructure Development & Maintenance
We offer Engineering, Procurement, Commissioning & Maintenance services in
Power Sector Power Distribution Provide end to end solutions in erection of
distribution substations and allied works. Power Transmission Provide end to end
solutions in erection of EHV lines & allied works. Power Generation Provide end to
end solutions in Micro and Mini power generation units.
Project Management Schedule and budget evaluations Value engineering Constructability reviews
Accuracy checks on cost estimates Monitoring and coordinating daily construction
activities Technical Audits Contract Negotiation and Administration Project Controls
and Scheduling Regulatory Agency Coordination and Negotiation Risk Management.
Critical Assessment of PPS Energy Solution Ltd Through the process of carrying out several assignments over the past many years,
PPS Energy Solution has accumulated considerable analytical and consulting
expertise, backed by the following organisational capabilities:
5
An extensive and organised database on power sectors.
Knowledge of key factors of success in different projects and program.
An ability to research emerging global trends, both in specific countries as well
as in energy sectors, based on primary and secondary data.
Performance benchmarking & Quantitative and financial modeling
Ability to identify the various types of risks in energy area and suggest
appropriate strategies to mitigate the same.
Ability to work in different geographies on its own and through affiliate
partners
1.3 SWOT ANALYSIS
Strengths Core team of expert professionals & excellent work culture.
Targeting untapped markets with best management skills and corporate
strategy
Time bound targeted goals & promotion of all environment friendly
techniques to the maximum extent.
PPS is certified energy auditing firm for carrying all types of energy audit.
Weakness
Company is in the initial stage of growth.
Small team to handle multiple projects.
Opportunities
Vast and growing market for energy conservation and energy audits.
Company can grab lots of government projects.
Create awareness among industries regarding energy efficiency.
Threats
Number of players has started entering this section of power sector.
Growing competition.
6
2. OBJECTIVE OF PROJECT:
This Project has analyzed the Distribution ARR & Tariff Orders issued by 3 State Electricity
Regulatory Commission (SERCs) of the states Haryana, Gujarat & Maharashtra during the
last five years i.e. from FY 2007-08 to FY 2011-12. In the early 2000s, the Govt. of India
introduced a number of reform measures for the power sector. These included the passing of
the Electricity Act 2003, National Electricity Policy & the National Tariff Policy. These
initiatives aimed to create a competitive market place & ensure availability of power at
affordable price. They also aimed to ensure commercial viability of the state utilities &
promote transparency, predictability & consistency as well as competition among the
supplier. This project has carried out with the aim whether these policies have resulted in
achievement of above said objectives as well as tariff rationalization & a reduction in cross
subsidy levels.
Under this study, a comprehensive survey of tariff orders issued by SERCs was undertaken
and the findings were compiled in a uniform format for all the states. In particular, the study
had attempted to bring out the following:
Comparison of approaches followed by SERCs towards different elements of annual
revenue requirement (ARR).
Compliance attained by the regulated utility with the costs approved and the directives
issued by SERCs.
Examination of regulatory effectiveness with respect to such parameters as T&D loss
reduction, extent of tariff rationalization, employee productivity, etc.
Identification of initiatives taken by SERCs that could be replicated in other states
.
This Project aims to analyze different approaches held by respective SERCs to deal with the
performance of different utilities. It deals with the study of what kinds of process are applied
to check whether the utilities are working properly or not.
7
3. SIGNIFICANCE OF THE STUDY:
Under the Electricity (Regulatory) Act, 1998, State Electricity Regulatory commissions were
formed. The SERCs, in exercise of the power vested in it under Section 86 of Electricity Act
2003 and all other power enabling it in on this behalf performs following functions:
To determine the tariff for electricity, wholesale, bulk, grid or retail and for the use of
the transmission facilities
To regulate power purchase, transmission, distribution, sale and supply
To promote competition, efficiency and economy in the activities of the electricity
industry.
To aid and advise the Government on power policy to collect and publish data and
forecasts
To regulate the assets and properties so as to safeguard the public interest
To issue licenses for transmission, bulk supply, distribution or supply of electricity
To regulate the working of the licensees
To adjudicate upon the disputes and differences between licensees.
Section 42 of Electricity Act 2003 notifies open access in Distribution sector. SERCs have
further issued regulations regarding open access, cross subsidy surcharge & wheeling
charges. SERCs have the vital responsibility of rationalization of tariff, as stated in Electricity
Act 2003.
Section 61(Tariff regulations) of Electricity Act 2003 states:
―The Appropriate Commission shall, subject to the provisions of this Act, specify the terms
and conditions for the determination of tariff, and in doing so, shall be guided by the
following, namely:- 17
(d) Safeguarding of consumers' interest and at the same time, recovery of the cost of
electricity in a reasonable manner;‖
The Ministry of Power also issued the National Tariff Policy in January 2006 that states the
following:
“Balancing the requirement of attracting adequate investments to the sector and that of
ensuring reasonability of user charges for the consumers is the critical challenge for the
8
regulatory process. Accelerated development of the power sector and its ability to attract
necessary investments calls for consistent regulatory approach across the country.
Consistency in approach becomes all the more necessary considering the large number of
States and the diversities involved.”
This project is important in a way to study the role of Regulatory Commission in the post
reform period & aftermaths of the enactment of Electricity Act 2003. The enactment of
Electricity Act 2003 has brought radical changes in electricity sector by empowering the
Electricity Regulatory Commissions (CERC & SERC) to deal with most of the operational
functions related to generation, Transmission & distribution of electricity previously carried
out by Govt. The State Electricity Regulatory Commission (SERC) determines the tariff for
Distribution Licensees.
The guidelines framed by the SERCs for Revenue and Tariff filings of licenses which seeks
it‘s calculations related to ARR of each licenses for the ensuing financial year regarding (i)
its expected aggregate revenue from proposed sale under its existing approved tariff; (ii) its
expected cost of service and (iii) its expected revenue gap (if any) and a general explanation
on how it proposes to deal with the revenue gap. The Commission then analyses the data filed
in ARR with previous year‘s trend under the reference of Tariff regulations issued by SERC
with reference to NEP and NTP guidelines as notified under section 3 of Electricity Act 2003.
The energy business is a concurrent business. Being a quasi-judicial autonomous body the
approaches held by SERCs regarding approval of ARR differs. This Project aims to analyze
different approaches held by respective SERCs to approve the required financial &
operational parameters like setting performance parameters, treatment of variation in
expenses, MYT or annual tariff determination approach & Tariff Design Principles etc.
This Project aims to analyze different approaches held by respective SERCs to deal with the
performance of different utilities. It deals with the study of what kinds of process are applied
to check whether the utilities are working properly or not.
9
4. SCOPE OF THE PROJECT:
In this Project, Tariff orders of 3 SERCs of states namely Haryana, Gujarat & Maharashtra
has been analyzed.
The following aspects have been covered while carrying out the analysis of distribution ARR
& Tariff Orders:
Regulatory approach for operational parameters
Regulatory approach for financial parameters
Tariff Design principles & fixation of tariff
MYT & TOD tariff approach
The following aspects have also been dealt with:
1. Status of regulatory reforms;
2. Regulatory approach for revenue requirement including parameters such as:
Sales mix/demand estimation (consumer category-wise);
Process of procurement of power/fuel;
Assessment of technical and commercial loss (for transmission and distribution
system);
Investment/Capex approval criteria – basis and linkage with loss reduction, system up
gradation and reliability;
Debt –Equity ratio;
Depreciation;
Rate of return - Compilation and analysis of the approach (ROE or ROCE) followed
by different SERCs in fixation of tariff;
Interest on loan;
Interest on working capital requirement;
Operation and maintenance;
Renovation and modernization (R&M) (not periodic overhauls);
Power purchase cost including quality and operational criteria for recovery of fixed
cost, variable cost and incentive.
10
2. Tariff Rationalization:
Trend of consumer category-wise tariffs;
Revenue gap – year-wise gap between approved Aggregate Revenue Requirement
(ARR) and actual revenue realization;
3. Subsidy Payment and its treatment in tariff:
Approach and format of communicating the requirement of subsidy by SERCs;
Status of payment of subsidy by State Governments;
Whether SERCs are notifying the tariff without subsidy, which is to be payable by a
consumer in the event subsidy is not paid by the State Government;
Status of consumer category wise/overall subsidy;
11
5. INTRODUCTION
5.1 REGULATORY PROCESS:
The electricity regulator in general has adopted a quasi-judicial approach. Section 27 of the
ERC (Electricity Regulatory Commission) Act, 1998, mandated that the regulator must hear a
person authorized to represent the consumers. Application filed to the commission is now
made available to all parties and the stakeholders are now given an opportunity to comment
on the filled application.
Each year, at the time required by its licence, each licensee shall file with the Commission a
report for each of its Separate Businesses on its expected aggregate revenues from charges
under its currently approved tariff and its expected cost of service. 21
The ARR report shall contain the following information:
The licensee‘s demand forecast by consumer class for the succeeding twelve month
period ensuing financial year and the derivation of the forecast;
A calculation of expected aggregate revenue that would result from the above demand
during the same period under the currently approved tariff by consumer class;
A calculation of the licensee‘s estimated costs of providing the service required by the
level of demand for each consumer class during the same period calculated in
accordance with the financial principles and their applications in the Sixth Schedule to
the Electricity (Supply) Act, 1948 or such other principles the Commission may
prescribe from time to time;
The licensee‘s general explanation of how it proposes to deal with any significant
divergence between the revenue and cost figures provided in subsections (2) and (3)
above; and
Such other information as the Commission may direct from time to time.
The licensee shall furnish to the Commission when required such information, particulars,
and documents as the Commission may require from time to time for the purpose of
validating the report submitted
Once the licensee has provided all the requisite information, particulars, and comments
required by the Commission, the Commission shall notify the licensee of its decision within
the time set forth in the Act.
12
If the Commission determines that a licensee‘s expected revenues differ significantly from
the revenue it is permitted to recover under its licence, it may order the licensee to file an
application again within the specified time to amend its tariffs appropriately.
Tariff applications shall include the following:
(a) Where the proposed date of implementation falls within a financial year for which the
Commission has previously determined a permitted aggregate revenue requirement, the filing
22 of proposed tariff should be accompanied by a copy of the relevant Annual Revenue
Report as submitted by the licensee, plus a copy of the order passed by the Commission in
relation to that report.
Where no determination of a permitted aggregate revenue requirement has been made for the
financial year in which the proposed tariff is to be implemented, the filing of proposed tariff
should be accompanied by the Annual Revenue Report for that financial year.
(b) The information to be provided by the licensee must include:
1. A statement of the current tariff rates and all applicable terms and conditions, and the
expected full-year revenue from the current tariff rates in the year in which the new tariff is to
be implemented.
2. A statement of the proposed tariff rates prices and changes, including a full statement of all
applicable terms and conditions. This statement should be shown in a form appropriate to the
proposed tariff structure. Details should also be supplied of the publicity intended to be given
to new tariff options when they are to be implemented.
3. A statement of the expected full-year revenue of the proposed tariff for the year in which
the tariff is to be implemented.
4. If the proposed tariff is to be introduced after the start of the financial year, a statement of
the proportion of expected revenue and quantities supplied under each proposed rate during
the remaining months of the financial year shall be included.
5. A statement of the estimated change in annual expected revenues that would result from
the proposed tariff changes in the year in which they are to be implemented, stated in Rupees
and percentage terms.
13
6. An embedded cost study detailing functioning, classification, and allocation of the revenue
requirement into consumer classes, and determination of embedded cost-based tariffs, free of
external subsidies and cross-subsidies. The study shall include all relevant details and
methods used in determination of tariffs for each consumer class. If the licensee proposes
cost-based tariffs for all consumer classes, the proposed tariff must be the result of the
embedded cost study.
7. A study of marginal costs of the licensee‘s business, including time-differentiated, short-
term marginal costs by voltage levels and a written explanation of the methods used to
calculate marginal costs. In addition, the statement shall include a comparison of the
percentage of marginal costs recovered by the current and proposed tariff for each tariff class.
8. A written explanation of the rationale for the proposed tariff changes, including
justification of the return on equity being requested.
9. A statement that calculates the amount of cross subsidy in the existing tariffs and in the
proposed tariffs, and compare the two. If the proposed tariffs include a cross subsidy, a
statement is required, as applicable, to show how this complies with any planned transition
period by the Commission.
10. A statement containing full details of the calculation of any subsidy received, due or
assumed to be due from the State Government, the consumers to whom it is directed, and
documentation showing how the subsidy is reflected in the current and proposed tariff
applicable to those consumers. This statement shall also include the tariff calculated without
consideration of the subsidy for those consumers. The subsidy calculations shall also
compare the situation in the year in which the tariff is to be implemented with similar data for
the previous year and, where relevant, the current year.
11. A written explanation, supported by calculations of tariff rates, of any proposed new
tariff.
12. The licensee may, if he so wishes, submit any more recent updates of information
specified in Sections 6, 7 and 8 of the Annual Revenue Report Guidelines available at the
time of the tariff filing.
13. Any other information, as required by the relevant license or specified by the
Commission.
14
If the licensee believes that the amendments being proposed are minor in nature and will not
change significantly either the expected aggregate revenues or the bills of any class of
consumer or customer, the licensee may request waiver of any of the requirements mentioned
above subject to the approval of the Commission. 24 Within 7 days after the Commission has
notified the licensee that it has received all necessary information, the licensee shall arrange
for publication of a notice of its tariff application and send copies to the Commission
Advisory Committee and relevant local authorities in accordance with the Conduct of
Business Regulations. The notice shall include a general description of the tariff amendment
being applied for and its effect on the typical residential consumer‘s bill, and an invitation to
submit written comments and objections to the tariff application to the Commission within 30
days. The licensee shall also post the notification in each of its offices. After receiving all the
comments and objections commission should organize the public hearing process. The time
and venue of the hearing will be advertised by the licensees. In the public hearing licensee
will respond to all the objections raised by the stakeholders. And commission will take the
note of all the objections and responses given by licensees depending on whether it‘s satisfied
or not. After the public hearing process, commission should hold a meeting with state
advisory committee. After considering all the conclusions in this meeting commission should
come out with the final tariff order.
5.2 TARIFF APPROACH ADOPTED BY COMMISSIONS:
The ROR regulation is the traditional approach to regulation. Under this, rates are set so as to
enable a utility reasonable opportunity to recover prudently incurred expenses (including
investment) and a fair return on the remaining cost (the un-depreciated portion) of
investment. So far, states in India follow this approach of regulation in the electricity sector.
Rate-of-return regulation provides the regulated companies with sufficient incentives for
capacity expansion and even creates incentives for overcapitalization1. However, this
approach does not provide incentives for cost savings and efficiency improvements but
rewards over investments unless there is some form of efficiency benchmarking connected to
it. 25
With the move towards MYT regimes, SERCs are trying to move towards Performance
Based Regulation (PBR). PBR mechanism provides more powerful incentives for regulated
firms to reduce costs, improve service quality in a cost effective way, stimulate the
15
introduction of new products and services, and stimulate efficient investment in and pricing
of access to regulated infrastructure services.
Performance based system gives direction to regulated firms. The firms can choose the way
in which they want to meet these targets. The regulator sets the targets for the key
performance parameters of the utility and calculates the tariffs assuming that the targets are
met. If the utility exceeds the targets, it would make profits and if it falls short there is profit
reduction or even loss. PBR makes use of the information advantage. The regulator thus
controls less behaviour and rewards outcomes. However, even in this move towards PBR, it
is observed that adequate flexibility is not being given to the utilities and it does not do away
with the present system of annual review.
16
5.3 STATUS OF REFORMS:
Below in the table Status of reform in the state of Haryana, gujrat and Maharashtra has been
shown:
Source: Tariff Orders of HERC, GERC and MPERC.
STATE UTILITY SECTOR DATE OF
UNBUNDLING
Haryana HPGCL Generation 14-08-1998
HVPNL Transmission 14-08-1998
DHBVNL Distribution 01/07/1999
UHBVNL Distribution 01/07/1999
Gujarat GSECL Generation 01-04-2005
GETCO Transmission 01-04-2005
UGVCL Distribution 01-04-2005
DGVCL Distribution 01-04-2005
MGVCL Distribution 01-04-2005
PGVCL Distribution 01-04-2005
TPL Distribution &
Generation
Maharashtra MSPGCL Generation 06-06-2006
MSETCL Transmission 06-06-2006
MSEDCL Distribution 06-06-2006
17
6. SERCS APPROACH TOWARDS FINANCIAL & OPERATIONAL PARAMETERS:
The ARR parameters are segregated into financial & operational parameters. The ARR
parameters are reviewed by SERCs for regulatory account only i.e. related to regulatory
parameters from the profit/loss account of the previous years.
The operational parameters are as follows:
1. Energy Sales (Consumer category-wise)
2. Power Purchase
3. Assessment of technical & commercial loss
The financial parameters are as follows:
4. Capital Investment / CAPEX
5. Capital Structure ( Debt/Equity ratio)
6. Depreciation
7. Rate of return (ROE or ROCE)
8. Interest on loan
9. Norms on working capital
10. Cost of foreign exchange risk
11. Operation & Maintenance
The Aggregate Revenue Requirement (ARR) is segregated into ARR for Wheeling or
Distribution business & ARR for Retail business. The ARR for wheeling business forms
basis to determine Wheeling charges whereas the ARR for Retail business forms basis for
user end customer tariff.
18
6.1 ENERGY SALES:
Projection of consumer category wise energy sales is essential for estimation of likely
revenue and to determine the quantum of power purchase. Proper estimation of category-wise
energy sales is most essential to arrive at the quantum of power purchase and the likely
revenue by sale of energy. Category wise sale estimation gives an idea about the trends in
consumption pattern, like which category, whether subsidizing or subsidized is showing
either increase or decrease in consumption which is crucial in forecasting category wise
revenue. The present method used by the SERCs is based on actual past sale data (historical
trend method) & future forecasting. The SERCs arrive at energy input or units to be
purchased by grossing up the expected sale with Transmission & Distribution (T&D) losses.
The sale for each DISCOM (actual & approved) for the period under consideration is given in
table below.
19
Electricity sale
(MU)
Name of the
States
Distribution
Licenses
2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 11720 10740 12250 12250 13201 13,084
DGVCL 7974 8181 8307 8307 9,008 8,978
UGVCL 10425 9541 10927 10927 11,474 11,447
MGVCL 4906 4622 5389 5389 5,889 5,860
TPL (AD) 4492 4492 4737.35 4737.35 4770 4995.82
TPL (SD) 2983 2983 2907.18 2907.18 2770.71 2885.18
Haryana DHBVNL 8981.78 9275 9859.56 10835 10854.83 10633
UHBVNL 9281 8717 9461.36 10203 10854.83 9762
Maharashtra MSEDCL 55715 55715 57796 57796 64356 62696
Tpc‐d 2506 2506 2468 2468 2638 2638
Rel‐d 7912 7912 8126 8230
Best 4024 4024 4103 4103 4257 4257
20
Gujarat discoms have projected the future sales on the basis of historical trend. Discoms have
therefore estimated the consumers, connected load and energy sales based on compounded
annual growth (CAGR) trends during the past years. They calculated the compounded annual
growth rate (CAGR) of last three years and on the basis of this rate they gave their future
prediction.
GERC considered last three year CAGR and recent trend (Year on Year growth of last 2
years) while approving the final sales figures for each category.
Haryana discoms have projected consumer category wise energy sales (except agriculture) on
the basis of trend determined by compounded annual growth (CAGR) for various years
which is based on the audited figures for previous years. As Haryana is a energy deficit state,
the actual sales data is therefore restricted to the extent of availability during the respective
years as there exists a large volume of unmet demand. The total saleable units have been
apportioned among different consumer categories in the same ratio as the projected sales.
HERC has followed the Annual Average Growth Rate (ALF) based methodology. The
consumption estimates for each category has been arrived at by applying the average ALF on
the annual average connected load of each consumer category projected on the basis CAGR
of the actual connected load data of past years.
The Maharashtra discoms has submitted that category wise CAGR of past 3 year‘s sales were
taken into account. CAGR for one year, two years have also been worked out. Other factors
like increase in sales due to projected increase in number of domestic consumers under
RGGVY scheme, regularisation of illegal connections etc. have also been taken into account
for additional sales in domestic category. Based on historical trends and the additional sales
expected due to the increase in number of consumers, growth rate higher than CAGR have
been considered in domestic category for the year 2009-10, while for other categories the
sales have been projected based on past 2 years CAGR, while in categories where the growth
had been negative as per CAGR, nominal growth rates have been considered.
MERC also follows the historical trend method by approving the sales figures of licensees
which were based on the CAGR of 2 or 3 years.
21
6.2 POWER PURCHASE: Once the energy requirement is arrived at, the power purchase cost is worked out by applying
merit order dispatch principles for the allocated capacities / PPAs. Cost of power is the most
important item of expenditure for the licensees. Every Commission examines the projected
availability of power from different sources in details & the requirement of sales. In the ARR
power purchase are reckoned only from those sources which have long term contracts with
the DISCOMs.
The rates of power purchased from individual generators are on the basis of their respective
agreements. As regards energy costs for DISCOMs, the methodology adopted is to take the
total energy cost, commonly known as Bulk Supply Tariff (BST), comprising
Energy costs;
Transmission costs;
SLDC charges.
The cost of purchase of power is largely a known parameter. The amount payable by the
distribution licensees is based on power purchase agreements with various generators that
clearly establish the price determination procedure. In case of central power sector units
(CPSU‘s) or other generators supplying power to more than one state, the Central Electricity
Regulatory Commission (CERC) determines tariff. Most of the elements constituting the total
charges i.e. capacity charges, base energy related charges, adjustment to base energy charges
for cost of fuel and other factors, taxes, duties, incentive payments etc. Are known or can be
estimated with a reasonable degree of accuracy.
While approving the cost of power procurement, the Commission determines the quantum of
electricity to be procured, consistent with power procurement plan, from various sources of
supply in accordance with the principle of merit order scheduling and dispatch, based on a
ranking of all approved sources of supply in the order of their respective variable costs, with
certain exceptions, as in the case of Non-Conventional Energy (NCE) projects, Nuclear
projects & some hydro projects accorded by various general and specific orders of the
Commission the status of ‗must-run‘ projects. In order to arrive at the quantum and cost of
power procurement, the Commissions had adopted the Sales Forecast, the Transmission &
Distribution loss trajectory. The power purchase cost is a uncontrollable expenditure item &
is trued up through Fuel Surcharge Adjustment (FSA) mechanism.
22
The relevant clause of National Tariff Policy (Clause 5.3 (h) (4) and Clause 8.2.1 (1)) says:
“Uncontrollable costs should be recovered speedily to ensure that future consumers are not
burdened with past costs. Uncontrollable costs would include (but not limited to) fuel costs,
costs on account of inflation, taxes and cess, variations in power purchase unit costs
including on account of hydro-thermal mix in case of adverse natural events.”
and
“All power purchase costs need to be considered legitimate unless it is established that the
merit order principle has been violated or power has been purchased at unreasonable rates.”
Variations in power purchase costs for the purpose of true-up will rarely occur as the Fuel
Surcharge Adjustment (FSA) formula issued by the Commission attempts to capture both the
price variance and the fuel variance during the course of the year itself. Any further variations
would arise mainly on account of purchases exceeding the limits approved in the Tariff
Order. All extra purchases of power do not automatically qualify for true-up. If the purchases
are for categories where the Commission has fixed a ceiling or quota, extra purchases will not
qualify for true-up.
The SERCs has studied energy availability from State Generating Stations (STS), Central
Generating Stations (CGS), and Independent Power Producers & Non Conventional Energy
(NCE) Sources. The Power purchased units & cost for all DISCOMs is given as in table
below.
23
Power Purchase (MUs)
Name of the States Distribution
Licenses
2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 15289 16362 19229 19229 19741 19,251
DGVCL 10,181 10297 10330 10330 11,063 10843
UGVCL 13,296 12136 13524 13524 14,131 14063
MGVCL 5,967 5967 6678 6678 7,343 7288
TPL (AD) 4566.05* 4584* 5188.57 5188.57 5,406.71 5487.51
TPL (SD) 3076.96 3076.96 2,974.73 3095.72
Haryana DHBVNL 12972 14642 14555
UHBVNL 12192 13788 13362
Maharashtra MSEDCL 78734 78734 79200 77567 87222.83 84641.03
Tpc‐d 2686.83 2688 2651.47 2651.47 2856 2791
Rel‐d 9342.63 9207.57 9919.29 9513.57
Best 4608.38 4547.23 5124 4797.5 4999 4971
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
24
Power Purchase Cost (Lacs) Name of the States Distribution
Licenses
2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 307910 332035 481747 481553 523245 449488
DGVCL 337633 318336 395356 395252 450100 356772
UGVCL 288495 279831 372033 371897 408399 360105
MGVCL 175913 176123 225356 225289 2,45,244 1,90,135
TPL (AD) 142459* 142459* 167702 167702 148617 169075
TPL (SD) 114097 114097 93535 111019
Haryana DHBVNL 307154.2 337683.9 376778.1 391798.1 403679.7 381356.7
UHBVNL 306449.7 321536.2 376779 371421.6 412412.7 361190
Maharashtra MSEDCL 1700600 1698700 1848800 1777400 2134153 198981
Tpc‐d 1,24,945 123949 126884 1270 1260 907
Rel‐d 3,21,954 308379 4,95,622 3,83,823
Best 186636 190099 232367 183704 2480 1681
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
25
The total cost of power purchase estimated by the Gujarat discoms does comprise of the
following components
Cost of the energy or power purchase cost based on PPA allocation and Merit order
despatch
Transmission charges of GETCO and PGCIL
SLDC fees and Charges
Allocated gap / surplus of GUVNL
E-Urja Cost (part of GUVNL Cost)
Once the energy requirement is arrived at, the power purchase cost is worked out by applying
merit order dispatch principles for the allocated capacities / PPAs.
It is submitted by DGVCL that when the erstwhile GEB was unbundled into seven entities, it
was decided by the State Government that Gujarat Urja Vikas Nigam Limited (GUVNL)
shall purchase the entire power requirement from GSECL, Central Generating Companies
and IPPs and shall perform the activity of bulk supplier of power to all the four Distribution
Companies at Bulk supply Tariff.
The State Government envisages uniform retail supply tariff in the four DISCOMs (of the
unbundled GEB). All the four Distribution Companies are incorporated on the basis of zonal
configuration. The consumer profile and consumption profiles are different in the four
Distribution Companies. In view of this, the revenue earning capabilities of each of the
DISCOMs is different. It is, therefore, necessary to build a mechanism in the projections to
bring them to a level playing field. This is proposed to be achieved by differential Bulk
Supply tariff (BST) to each of the DISCOMs. In this way, it would be possible to ensure
uniform retail consumer tariffs in the four DISCOMs.
The BST for DISCOMs includes the cost of power purchase from various generating stations,
the transmission costs of PGCIL, GETCO and the cost of bulk supplier GUVNL. The
revenue from sale of power to the bulk supply licensees i.e. Torrent Power Ahmadabad
Electric Company Limited (TPAL), Torrent Power Surat Electricity Company (TPSL) and
Kandla Port Trust (KPT) is subtracted from the total power purchase cost to arrive at net
power purchase cost to be charged to the four DISCOMs. The amount available for power
purchase with the four DISCOMs is arrived at by subtracting the sum of total expenses of all
the four DISCOMs from the total revenue of the four DISCOMs.
26
The difference between the net power purchase cost and the amount available with the four
DISCOMs indicates the revenue gap. This revenue gap varies from DISCOM to DISCOM.
The bulk supply tariffs for the four DISCOMs are fixed keeping in view the magnitude of the
revenue gap.
GUVNL has discontinued supply of power to Torrent Power Limited (TPL) from August,
2009 pursuant to commissioning of Sugen CCPP. In view of this, capacity retained by
GUVNL for supply of power to TPL‘s Ahmadabad and Surat distribution areas has been
allocated to the four distribution companies of Gujarat viz. DGVCL, MGVCL, PGVCL and
UGVCL with effect from August, 2009.
Prior to unbundling, all the utilities in the State were receiving supply from the pool of
energy in the State grid. The cost of the pooled energy is a weighted average of the
generation costs of individual stations feeding the grid. After unbundling, the distribution
areas of erstwhile GEB which covered the whole state (excluding the distribution areas of the
three private distribution licensees) were divided into four Discoms. These newly created
Discoms do not have a uniform consumer load mix. The agricultural loads (which are
uneconomical and involve high cross-subsidy) are proportionately much higher in PGVCL
and UGVCL. Thus these two Discoms face the problem of inadequate revenue for meeting
their expenditure. To get over this problem, GUVNL has allocated low cost PPAs (stations)
mainly to PGVCL and UGVCL. The high cost PPAs (stations) have been, by and large,
allocated to DGVCL and MGVCL. GUVNL has also retained some of the high cost PPAs
and is showing them as the source of supply to the three distribution licensees.
To an extent, the financial position of the Discoms with unfavourable load mix has to be
buttressed through allocation of low cost PPAs and a larger share of the agricultural subsidy
from the State Government. However, the PPAs allocation seems to have placed an undue
burden on DGVCL and MGVCL. Further, as the high cost PPA allocated to GUVNL are
shown as the source of supply to the three distribution licensees, the cost of supply to them
has become artificially high. As a matter of fact, the three bulk licensees‘ areas are entitled to
a fair share from energy pool of the State at its weighted average cost. After satisfactory
alternative arrangements are made the bulk licensees areas will go out of the State‘s energy
pool. The intent and purpose is to see that the retail consumers of various categories will be
charged, on an average, the same rates all over the State. From the submissions of the
27
Discoms, it is not clear whether PPA allocations have been approved by the State
Government.
During the public hearing, the representative of GUVNL stated that the PPA allocation has
not been approved by the State Government. The Commission too was not informed of the
allocation of capacities / PPAs except the mention of such allocation in the Tariff petitions of
the Discoms. The National Tariff Policy envisages that the concerned State Governments
would address issues relating to the allocation of PPAs. The Commission request the State
Government to carefully consider the question of allocation of PPAs. In Chapter 10, later in
the order, we have dealt with the general question of PPA allocation.
HERC had laid down the following approach in its orders:-
―Where a PPA/MOU exists, costs should be determined accordingly‖.
―In case of CPSU or other generators who are supplying power to more than one
state, where payments are governed by CERC or by Ministry of power Notifications,
tariffs should be forecast following the methodology adopted there‖.
―Where neither PPA nor rulings and Notifications are available for any reason,
projections can be made based on the latest available rates from invoices‖.
―Estimation should be made for various components separately and should use a
reasonable level of escalation in costs for those elements that are expected to undergo
changes.
The commission observes that the licensees have not complied with the general principles of
projecting power purchase costs set in the previous orders of the commission. Consequently,
the commission feels that the best approximation of power purchase cost would be the actual
annual average cost of power from various generating/trading sources.
The average cost of power for the distribution licensee in Haryana works out to Rs.
2.4179/Unit. In case the power purchase cost for the Distribution & Retail Supply (D&RS)
business due to escalation in the tariff of power sourced from CPSUs, fuel price adjustment
claimed by the intra-state generator (HPGCL) or change in the mix of power purchase
allowed by the commission on a projected basis, the licensee shall file FSA application as per
the FSA formula incorporated in the regulations approved by the commission on a half yearly
basis.
28
The Licensees of Maharashtra have submitted that the information provided by them is based
on interactions with Maharashtra Power Generating Co. Ltd (MSPGCL), MS Power
Transmission Company Limited (MSPTCL) and MP Power Trading Company Ltd. (MP 37
Tradeco). In this regard, the Licensees have also claimed that they have taken guidance from
Section 18 of the MERC (Power Purchase and Procurement) Regulations 2004 Revision 1,
2006 (RG-19(I) of 2006) which states that ―The Distribution Licensee shall make long-term
demand and supply availability assessments in consultation with any or all concerned
including state sector Generating Companies, Discoms, private Distribution Licensees,
central sector Generating Companies and Transmission Companies / Regional Electricity
Board, National / Regional Load Dispatch Centres, Central Electricity Authority.
The Distribution Licensees claim that they have considered available information from the
key sector participants for computation of power purchase cost for the purpose of arriving at
revenue requirement. The Distribution Licensees requested the Commission to take due
cognizance of this fact while computing allowable power purchase cost of the Licensees.
The East, West & Central Discoms have calculated the details related to the following items
as per the above allocation:
• Monthly energy available from all sources
• Annual fixed charge and energy charge payable to generators
• Estimated payment to generators on account of incentives, income tax, duties,
etc.; and
• Estimated inter-state transmission charges to be paid.
Merit Order Dispatch
It is submitted by GERC that in order to minimize the power purchase cost, discoms will
have to work out a comprehensive merit order dispatch (MOD) following the same principles
in accordance with the previous tariff order of the Commission from the dispatch available
from its capacity / PPA allocated generating stations.
In Gujarat the Nuclear Power Corporation (NPC) power plants and hydro power plants viz.,
Ukai, Kadana and SSNL hydro and NPC Tara pore have been considered as must run power
plants, and hence they have been excluded from merit order dispatch. The dispatch from
29
individual generating stations is worked out based on the merit order (based on the variable
cost) of each generating unit / station.
The Licensees of Maharashtra have claimed that they have adopted a merit order simulation
on monthly basis by matching monthly energy requirement with monthly 38 availability
based on the variable costs of power from various sources.The licensees have submitted that
while a monthly determination of cost provides an improved estimate over an annual
determination of cost, the actual cost will still differ based on the daily load curve and
variations of actual from projections. The licensees have further submitted that the cost of
such deviations as per different rates be passed on a regular monthly basis through the FCA
formulae proposed which is also in-line with the provision of the Tariff Policy which
specifies (Clause 5.3 (h) (4) and Clause 8.2.1(1)):
"Uncontrollable costs should be recovered speedily to ensure that future consumers are not
burdened with past costs. Uncontrollable costs would include (but not limited to) fuel costs,
costs on account of inflation, taxes and cess, variations in power purchase unit costs
including on account of hydro-thermal mix in case of adverse natural events. "
And "All power purchase costs need to be considered legitimate unless it is established that
the merit order principle has been violated or power has been purchased at unreasonable
rates.
The merit order has also revealed that in some months the availability remained unutilised by
the Discoms even after considering the intra-Discom trade. The Commission suggests that the
Discoms should use this surplus energy for banking with other States so that the shortfall, if
any, in the requirement in the Rabi season could be met from such banked power itself i.e.
without any cost implications. The Commission expects that the Discoms would avail the
opportunity of inter-State trading of surplus power only after fully meeting the demand of
their consumers.
30
6.3 DISTRIBUTION LOSSES:
Every Commission had given its serious thought and careful consideration for high level of
loss incurred by the distribution licensees. The SERCs have taken steps to improve the base
line data either by directing the DISCOMs to conduct various studies or by conducting
sample studies on their own. At first Commissions had fixed loss reduction trajectory. Then
the Commissions had judged the over or under performance of DISCOMs. The gains or
losses due to over or under improvement are to be accrued with Customers as well as the
DISCOMs. To implement open access in distribution, Commissions have asked DISCOMs to
file voltage wise losses so that the open access charges could be calculated. The
Commissions approach can be divided into Distribution losses & AT&C losses.
In case of DISCOMS where Agricultural consumption is predominant especially unmetered
agricultural consumption due care is taken by respective SERCs. The DISCOMs were
inflating the Agricultural unmetered consumption so that they could show lower losses. In
most of the cases the Flat rate Agricultural consumption is measured by LT side metering of
Distribution Transformer. Based on this, the annual per HP Normative consumption is fixed
for the particular period. The trend in actual losses & approved losses is given in tale as
below.
31
Distribution
Losses
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 32.80% 30.22% 32.11% 30.00% 29% 28%
DGVCL 15.45% 15.59% 14.78% 14.45% 13.45% 13.45%
UGVCL 17.31% 16.74% 14.57% 14.57% 14.45% 14.45%
MGVCL 15.86% 16.74% 14.52% 14.52% 14% 14%
TPL (AD) 8.75%* 9.26%* 8.69% 10.43% 10.25% 8.54%
TPL (SD) 5.51% 6.00% 6.00% 5.51%
Haryana DHBVNL 24.52% 28.50% 21.83% 26% 24%
UHBVNL 28.79 28.50% 26.62 26% 24%
Maharashtra MSEDCL 24.09 24.15 22.2 22.2 21.2 18.2
Tpc‐d 2.21 2.21 0.61 2.93 2.93 0.66
Rel‐d 11.04 11 10.25 10.75
Best 10.4 10.27 10.5 10.5 10.5 10
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
32
Gujarat discoms have been very efficient in reducing the distribution losses in their areas.
Gujarat discoms have usually reduced the distribution losses even below the approved figures
given by GERC except in the year 2007-08. Discoms gave the reason that the increase in
losses is attributed to the increased hours of supply to agricultural category during the year,
which has resulted in more off take without any corresponding increase in the sales, as the
consumption being unmetered. GERC said that the increase in loss during 2007-08 cannot be
attributed to increase in supply hours to agricultural sector as the norm of 1700
kWh/HP/annum has margin to absorb the additional energy consumption due to increased
hours of supply. Further the total sales during the years 2005-06, 2006-07 and 2007-08 and
the percentage of consumption by agriculture and HT also do not justify the increase in loss.
The Commission directs that the all the discoms shall maintain the commendable work it has
done during the earlier years in reducing the distribution losses and improve further to
achieve the loss levels fixed by the commission.
HERC has directed the licensee to analyze the phenomenon of zigzag pattern of distribution
losses observed through various circles of the state except Gurgaon in order to verify te
correctness of the data being reported by the licensee to the commission but the licensee has
failed to do so. It is however encouraging to know that losses for FY 2008-09 do indicate
improvement in all the circle with overall distribution losses declining to 21.83% from
24.38% of previous year. HERC states that discoms have not submitted any report on the
special efforts carried out for the reduction of loss on feeders with very high losses as
discoms have filled in the aggregate revenue requirement for the year 2007-08 to spend
heavily to reduce losses.
The Maharashtra State Government has laid down milestones for distribution losses for the
period FY 2006-07 to FY 2010-11. The Commission has computed the energy requirement of
the Licensee on the basis of the GoMs‘s benchmark of distribution losses. The level of
distribution losses has been the major cause of concern year after year. The efforts made in
this regard lack a serious commitment and focus. The Commission while determining the
tariff has been allowing only normative level of losses in accordance with the milestones laid
down by GoMP, however, in this process, the losses above the normative level are borne by
the distribution licensees. The normative losses are those prescribed by the State Government
and are/were definitely achievable. The difference of actual losses and those prescribed
continues to be substantial. As cost of power purchase accounts for 75% to 80% of total cost
incurred by Distribution Licensees, the large difference in actual and normative losses is
33
causing severe strain on financial position of these companies. In a short span of less than 4
years of their creation, these companies appear to have become financially sick. Their
capacity to serve efficiently is constrained by a perennial cash shortage. Despite repeated
directives, the Capex implementation of all Discoms continues to be extremely poor. Even
after 4 years of their coming in existence, an effective planning cell is yet to be formed. Poor
Capex implementation and planning coupled with sharper increase in demand, in the opinion
of the Commission, has further increased the technical loss component in place of its
reduction. Efforts made to reduce commercial losses have neither been adequate nor have
made much impact on the level of these losses. When viewed in the backdrop of
achievements of private and Government owned distribution companies in most of other
States, performance of distribution companies in our State is dismal. The Commission under
section 86(2)(i) of the Electricity Act, 2003, shall separately advise the State Government to
set up a monitoring mechanism for overseeing the Capex planning and implementation,
identification of high commercial loss areas and strategies for reduction of these losses. The
Commission itself shall review the activities and performance related to above areas after
each quarter. The distribution companies are directed to make all out efforts to show definite
improvement lest this malady starts threatening their very existence.
6.4 CAPITAL EXPENDITURE:
After enactment of EA 2003 & unbundling of SEBs the capital expenditure has been
increased. Most of the capital expenditure of state owned Utilities is funded through central
government schemes like APDRP, RGGVY, Rural electrification, System Improvement &
HVDS etc. The state government also through budgetary provisions is funding towards
Capital work. The capital work is necessary to strengthen the T & D network to support the
expected increase in generation by 2012 (considering made availability of supply). Even
Funds in the form of loan are available from World Bank, Asian Development Bank also. In
the initial years (in FY 2004-05 & 2005-06 specially) of tariff petitions the DISCOMs have
proposed huge amount towards capital expenditure. The Regulatory Commissions if had
agreed the Capital expenses would have finally burdened on the consumers. Also comparing
to the lower revenue collection the capital work would have hampered the financial viability
of the DISCOMs. As the trend is set by Commission for approval of CAPEX then the
DISCOMs have also filed more systematic & scheme wise details while seeking approval
from Commission. The Regulatory Commissions have approved the capital expenditures
34
based on historical actual trend in CAPEX capitalized & also the impact of such investment
in reduction in T&D losses.
6.5 CAPITAL STRUCTURE:
Capital Structure includes Debt component & equity component. The utility is allowed to get
reasonable return on the capital investment done. The normative Debt equity ratio is 70:30.
HERC has approved DE ratio of 70:30 for calculating return on capital employed for the
projects for which investment approval is accorded on or after 01/04/2007. And if equity is
higher than 30% then it will be treated as notional loan. But if equity is less than 30% then
actual equity should be taken.
GERC has allowed normative 70:30 DE ratio to calculate ROE. The total capital investment
is divided into normative 70:30 ratio to find out the rate of return. MPERC has also adopted
normative 70:30 Debt equity ratio.
6.6 DEPRECIATION:
Depreciation is directly related to the capital assets. The Original Cost of Fixed Assets
(OCFA) and capitalization of capital works form the basis of the Fixed Assets. For Electricity
industry, the depreciation rates are the rates, notified by the Ministry of Power, Government
of India(rates specified in 1992 & 1994), rates specified by the CERC which are generally
accepted by the SERCs & are issued in their tariff regulations. Depreciation is applied on the
opening balances of the Fixed Assets for the ensuing year at specific rates applicable to
particular assets subject to a limit of 90% of the Fixed Asset value (the balance being treated
as scrap value). In this regard, the crucial factor that varies the computations is the additions
to the Fixed Assets which are entirely dependent on the capitalization of the Capital Works-
in-progress during the year.
35
Depreciation(Rs. in Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 11,235 11438 12697 12793 21530 21809
DGVCL 4,978 5646 5717 5813 9537 9821
UGVCL 7 ,021 7380 7835 7824 12664 12633
MGVCL 4,703 4557 5448 5543 9390 9664
TPL (AD) 10990* 10990* 6148 6148 7555 7471
TPL (SD) 3297 3297 3978 3891
Haryana DHBVNL 9165.3 8485.6 11709.6 8832.8 15173.6 9096.9
UHBVNL 10777.1 10777.1 15825 13914.2 17832.8 12809.8
Maharashtra MSEDCL 40805 38226 45749 40010 55971 43613
Tpc‐d 1404 1404 1601 1602 1879 1729
Rel‐d 4039 4039 4500 4278 4966 4530
Best 51467 48888 57233 50936 62816 49872
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
36
GERC states that the net addition to assets implies the total amount capitalized by the utility
and not the capital expenditure incurred during any financial year. The Commission has
assumed that utility would be able to capitalize the capital expenditure as projected and
accordingly approved the depreciation.
PGVCL has mentioned that depreciation has been calculated based on the rates specified by
CERC for various assets in the power sector including distribution assets. It is found that
depreciation has been calculated taking into consideration the opening balance of assets at the
beginning of the year and proposed capitalisation i.e. additional assets proposed to be brought
into use during the control period. The actual average rate of depreciation worked out to
3.64% and the same rate has been adopted for projections during the control period.
HERC approved depreciation of Rs. 1280.98 million for year 2009-10 to be utilized towards
meeting the capital loans repayment of Rs. 800.36 million. The balance amount of Rs. 480.62
million shall be available with the commission for meeting out any revenue gap that may
emerge in the ARR under consideration. To allay the fears of the interveners that depreciation
is also allowed by the commission on assets not in use it‘s pointed out that the methodology
adopted by the commission for estimating depreciation amount as well as interest during
construction ensures that those assets have entered the income earning stream or likely to be
commissioned during the year as part of the distribution and retail supply business only
qualify for depreciation and the balance forms part of capital work in progress.
In Maharashtra according to the East Discom, depreciation has been computed on the
opening balance of GFA of depreciable assets as per the notified opening balance sheet. The
percentage to which assets in each sub-category is depreciable has been computed as on 31st
May 2005 and has been estimated on the basis of year-wise asset addition data of MPSEB
from 1985-86 to 2004-05.
Further, depreciation on asset added during each year thereafter has been computed on the
basis of projected capitalization in each such year as presented in the section on capital
expenditure of this Order. The Licensee‘s petition does not clarify how each year‘s projected
capitalization has been distributed into different asset classes for the purpose of charging
depreciation. The depreciation has been claimed on the basis of rates notified by the Ministry
of Power under notification S.O.265 (E) dated 27th March 1994. The Licensee has requested
37
the Commission to consider these rates instead of the CERC rates as the CERC rates do not
reflect the lower economic life of distribution assets, as opposed to transmission assets.
The Commission has also noted that West Discom has made depreciation claims based on the
final balance sheet notified by GoMP on 12th June 2008. However, as described earlier, the
Commission has considered the additions done during FY 2008- 09 over the audited figures
of FY 2007-08 as its base for working out depreciation claims which do not contain the
impact of the final opening balance sheet, thus the impact of final opening balance sheet
notified on 12th June 2008 sheets has not been taken into account in this order.
It is important to note here that if the East Discom‘s claims of depreciation are allowed as
such, there is likelihood that depreciation shall be permitted on those assets which are already
depreciated up to 90% of their historical cost. Consequently, the consumers of the East
Discom would pay, through tariffs, depreciation on such assets as well, which cannot be
permitted. Therefore, in absence of any other suitable method, the Commission, acting in the
interests of the consumers, is allowing depreciation to the East Discom based on the
depreciation rate of Central Discom.
With regard to the value of the asset base, the Commission has dwelt at length on the reasons
for not considering the projections of asset addition made by the Licensee for FY 2009-10 as
these appear to be inflated and not in conformity with the past trend. Consequently,
deprecation for FY 2009-10 is not likely to deviate much from the depreciation available for
FY 2008-09. For FY 2009-10 the Commission, has therefore, computed depreciation on the
closing balance of assets existing as on 31st March 2008 plus the progress reported by
Licensees till 31st March, 2009 and no projected asset additions for FY 2009-10 have been
considered.
The MPERC has allowed depreciation rate as per the CERC regulations. For the FY 2004-05
the Commission has utilized the services of an independent CA firm to verify the gross block
and depreciation figures submitted by the Licensee in the Tariff petition with the
corresponding figures in the trial balances maintained by the Licensee. The weighted average
rate of 4.85% proposed for FY 2004-05 is in line with the historic trend of depreciation. From
FY 2006-07 to FY 2008-09 the Commission has allowed CERC rates.
38
6.7 RATE OF RETURN (ROE OR ROCE):
The ROCE is allowed on the Net Capital base (Asset base or regulated rate base) for the
ensuing year. The Capital Base of the Licensees is divided into two parts - the positive part
and the negative part, to derive the net capital base on which a return is provided. The
positive part consists of the original cost of fixed assets (OCFA) excluding consumer
contributions; intangible assets; the original cost of Capital Works-in-Progress (CWIP);
compulsory investments, and working capital. On the negative side are depicted, the
matching financials of the assets created, like Accumulated depreciation, loans from
Government and other approved institutions, consumer deposits by way of security and
amounts outstanding in the Tariffs and Dividends Control Reserve and Development Reserve
at the close of the year. The ROE is allowed on the average of opening& closing equity &
free reserves for the ensuing year. The total capital is normatively divided in the ratio of
70:30 & the equity component is calculated to derive Return on Equity to be allowed.
Gujarat state‘s terms and condition of Tariff states that -
“The tariff shall be fixed in such a manner that a licensee ordinarily in any financial year
will earn a permissible return which shall comprise of 14% on equity invested into capital
expenditure (apportioned to the quantum for the purpose of performing the business
electricity in the present debt equity structure) plus permitted incentives minus penalties
levied under the Act / Regulations for that year.”
39
Return on
Equity(Rs. in
Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 6874 6923 14279 14239 15750 15670
DGVCL 2326 2326 4758 4872 5112 5340
UGVCL 3729 3563 7926 7914 8500 8475
MGVCL 2662 2704 5756 5866 6378 6597
TPL (AD) 20621* 20065* 11352 11352 12688 12744
TPL (SD) 6477 6477 7164 7114
Haryana DHBVNL 0 0 8135.7 0 9681.7 0
UHBVNL 1121.7 426.2 10973 0 12630.8 0
Maharashtra MSEDCL 54518 49936 62927 50994 78171 53383
Tpc‐d 2161 2149 2470 2285 3456 2353
Rel‐d 13391 10506 11960 10543 12700 10860
Best 87923 80026 97482 82806 94327 66596
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
40
Return on Equity as % of ARR(Rs. in Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Gujrat PGVCL 1.490101 2.560782 2.489544
DGVCL 0.6262 1.104288 1.028327
UGVCL 1.123738 1.84514 1.773316
MGVCL 1.275723 2.140183 2.09911
Haryana DHBVNL 1.77055 1.927975
UHBVNL 0.315297 2.299807 2.257464
Maharashtra MSEDCL 2.65 2.60 2.73
Tpc‐d 1.72 1.73 1.98
Rel‐d 4.24 4.61
Best 5.11 3.60 3.98
41
Gujarat discoms generally computed the return on equity @ 14% on average equity based
upon the opening balance of equity and normative additions during the year, which has been
arrived at by considering 30% of the capital expenditure net of consumer contribution and
grants as funded from equity. The Commission has considered the opening equity as per the
provisional accounts.
For the purpose of equity addition during the year, the Commission has considered
capitalised cost instead of capital expenditure as considered by the petitioner. The
Commission has also deducted consumer contribution and Government grants to arrive at the
normative equity portion of allowable capitalised cost.
For the FY 2008-09 the PGVCL has prayed to approve the full amount of return on equity
claimed at the rate of 14% as enshrined in the GERC (Terms and Conditions of Tariff)
Regulations, 2005. In this regard PGVCL has referred to a letter from the Union Minister of
Power, wherein Government of India asked the State Government to ensure full returns on
equity to power utilities vide letter No. 45/2/206 R&R / (P1) / 1039-70 / VIP dated 8th
February 2008. The addition of equity projected for the control period is in accordance with
the sources of funding the capital expenditure. The rate of return of equity projected is 14%
which is as per the GERC Regulatiion.
Tariff regulation of HERC states that RoR regulation of tariffs sets the appropriate rate of
return on capital (both debt and Equity funds). This rate of return should adequately
compensate investors for the risks they assume by committing capital to the power sector or
an individual utility. Thus the return, which investors require on their investment, should at
least be equal to return on other investments with comparable risk factor.
The existing tariff regulations of the commission (HERC) do not provide for any return on
equity but provides foe return on capital base which is negative for year 2008-09 and 2009-10
as submitted by the discoms. Consequently no Return on Equity or Capital Base has been
considered by the commission for these years.
MPERC for FY 2004-05 has allowed 3% reasonable return on the net fixed asset for MPSEB.
From FY 2006-07 to FY 2008-09 the Commission has allowed 14% ROE on net fixed assets.
The Madhya Pradesh Discoms have claimed return at the rate of 14% on equity projected to
be employed in completed assets in FY 2009-10. For computing RoE, the Licensees has
determined the total capitalisation of assets projected during FY 2009-10 and worked out the
42
component proposed to be capitalised from equity funding. The projected equity
capitalization is then compared with normative level of 30% to determine the equity
capitalization eligible for RoE. Commission studied the process of identification of debt and
equity with completed assets. This process results in the total equity identified with GFA as at
the end of FY 2007-08. This is presented in the table below. The Return on Equity as allowed
for FY 2009-10 ARR is then determined by applying the Commission specified rate of 14%
on the total equity identified as allocated to GFA. The Commission is aware that during the
course of FY 2009-10, additional equity shall be infused into the distribution business for the
purpose of creation of assets, which will increase the amount of equity allocated to completed
assets. This, if supported by audited accounts, shall be accounted for in future aggregate
revenue requirements of the Licensee.
6.8 INTEREST AND FINANCE CHARGES:
Approved interest on loans is directly related to the loans taken into the Capital Base
computations. The loans drawn for CAPEX and interest thereon are a pass-through in the
tariffs. The interest rates are computed on the basis of the rates on loans filed by the
Licensees for the current year and the ensuing year. Lease rentals and other finance charges
are also included under this heading. Other finance charges include discounts to consumers,
such as, incentive, etc. The weighted average rate of interest & normative repayments so
worked out is taken to the ARR. The SERCs analyses the source wise break up of loan &
interest thereon. All the Commissions had considered actual loan portfolio & interest to be
paid for such project. Capital projects are being funded from loan, consumer contribution,
depreciation (internal accruals) & Govt. grant & loans etc.
43
Interest & Finance Charges (Rs. in Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 15725 13324 15936 7924 17078 10144
DGVCL 8414 6861 8892 5759 9095 5612
UGVCL 11468 8159 11663 7581 7905 3894
MGVCL 7041 6328 7072 4210 7514 4230
TPL (AD) 4954* 4954* 4839 4839 6076 6190
TPL (SD) 4670 4670 5792 5519
Haryana DHBVNL 5110.4 4366.1 11237 3984.9 5641 8759
UHBVNL 3156.8 3156.8 4008.7 1167.2 3764.1
Maharashtra MSEDCL 44033 43233 63130 49633 112606 53706
Tpc‐d 2239 2515 2983 2546 4580 2652
Rel‐d 12089 10442 14689 11558
Best 4033 2302 5300 2953 3900 3542
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
44
The Commission (GERC) has taken note that Interest and Finance charges approved in MYT
Order had an element of Interest on Working Capital which is claimed separately on
normative basis. The petitioner, while claiming the Interest and Finance charges has deducted
the Interest on Working Capital to avoid the double counting. However, the Commission
feels that it is not a correct approach, rather than deducting Interest on Working capital from
the total Interest and Finance charges the principal loan amount shall be segregated.
Accordingly, the Commission has segregated the opening balance in proportion to the actual
interest paid for capital expenditure and interest paid for financing working capital. The
Commission has considered the interest rate of 10% as considered in MYT Order for
estimating the interest cost for FY 2009-10.
The HERC states that the capitalisation of interest during construction is in accordance with
the AS 16 issued by the Institute of Chartered Accountants of India wherein interest on
borrowed capital is capitalised till the date of commissioning of assets. The date of
commissioning of asset is assumed to be the last day of operation of the year as per the fixed
assets register. Interest on loan component of opening balance of CWIP for FY 2008-09 is
capitalised for the full year and interest on new borrowings for additions to capital works
during FY 2008-09 is capitalised for 6 months that the loans are disbursed uniformly during
the year.
The MERC for the FY 2004-05 to FY 2006-07 has reworked the interest expenses based on
the opening balance sheets available in the provisional transfer scheme and allowable
borrowings and repayments there on. The Commission has considered the investments
capitalized in FY 2004-05 as approved new borrowings for determining the interest
expenditure. The Commission is of the view that the disallowed borrowings would have a
moratorium period of three years and hence considered the repayments as per the
submissions made in the Petition without any adjustments. However, the Commission feels
that there would be linkages between repayments and new borrowings in instances like debt
restructuring etc.
45
6.9 INTEREST ON WORKING CAPITAL:
Working capital is required to maintain cash flow liquid. Usually the SERCs have taken
working capital as a % of O&M expenses, average cost of store & average cash & bank
balance etc. The interest rate for working capital is the short term Prime Lending Rate of
State Bank of India.
The Gujarat discoms have estimated interest on a normative working capital in accordance
with the GERC Tariff Regulations. However, instead of considering Revenues for two
months, revenues of the company for only one month has been considered for projecting the
total working capital during the FY 2009-10. The petitioner has computed the interest on
working capital at current short-term prime lending rate of SBI i.e. 10.25%. Discoms have
further submitted that interest on working capital has been calculated based on the normative
working methodology as specified by the Commission in its Terms and Conditions of Tariff
Regulations. However, instead of considering Revenues for two months, revenues of the
company for only one month has been considered for projecting the total working capital
during the FY 2009-10. The Commission has estimated the working capital as per clause No.
66 of GERC terms and conditions of tariff and accordingly considered the Operation and
maintenance expenses for one month; Maintenance spares @ 1% of the historical cost
escalated @ 6% per annum from the date of commercial operation; and Receivables
equivalent to one months of sales (in line with the same proposed by the petitioner). Further,
the estimation is based on the O & M, historical costs and sales as approved by the
Commission in this tariff order. According to Regulation 20 (v) (b), the Commission, in its
MYT Order dated Jan 17, 2009 has taken the rate of interest on working capital equal to the
short-term prime lending rate of SBI as on 01/04/2004, which was 10.25%.
In Haryana DHBVNL has proposed interest of Rs. 1216.56 million on working capital
borrowing of Rs. 9372.39 million for FY 2008-09. The commission (HERC) allows working
capital borrowings limited to 1 month of ARR as per orders of the Hon‘ble Appellate
Tribunal for Electricity dated 10/11/2006, which works out to approximately Rs. 2800
million.
The MERC has recalculated the interest on working capital FY 2004-05 based on the
principles of FY 2003-04 Tariff Order. Accordingly, working capital has been considered as
0.75*(Current Assets – Current Liabilities), where current assets are 2 months of receivables
and 15 days of generation costs and current liabilities are 1 month of fuel expenses. The
46
Commission has considered interest rate of 10.25% as submitted in the filings, which is the
prevailing Prime Lending Rate (PLR) of State Bank of India as prescribed in the MERC
Tariff Regulations, 2005 to determine the interest on working capital. The same approach
was followed by MERC for FY 2005-06 & FY 2006-07.
MERC states that as per terms & conditions of tariff regulation of Madhya Pradesh, working
capital for supply activity of the Licensee shall consist of:
Power purchase cost of one month and receivables of two months of average billing
reduced by any consumer security deposit,
O&M expenses for one month, and
Inventory (meters, metering equipment, testing equipment are particularly relevant in
case of supply activity) for 2 months based on annual requirement for previous year.
Working capital for wheeling activity of the Licensee shall consist of
O&M expenses for one month, and
Inventory (excluding meters, etc. considered part of supply activity) for 2 months
based on annual requirement considered at 1% of the gross fixed assets for previous
year.
Working capital shall be computed as provided in these Regulations and Rate of interest on
working capital shall be equal to the State Bank of India Advance Rate as on April 1 of the
relevant Year. The interest on working capital shall be payable on normative basis
notwithstanding that the Licensee has not taken working capital loan from any outside agency
or has borrowed in excess of the working capital loan computed on normative basis.
The MERC has recalculated the interest on working capital FY 2004-05 based on the
47
Interest on Working Capital(Rs. in Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 4049 1609 5538 4758 6950 4328
DGVCL 3307 1637 3972 3814 4537 3610
UGVCL 2779 1222 4091 3443 4027 2930
MGVCL 2057 909 2623 2350 2671 2273
TPL (AD) 8545* 6594* 40 2074 3922 2067
TPL (SD) 101 2452 2200 2055
Haryana DHBVNL 2411.3 1327.5 12165.6 1821.9 18746.6 4781.3
UHBVNL 11576.3 1745.7 23270.1 2866.5 30625.5 4462.5
Maharashtra MSEDCL 1053080 1037051 1180683 1083114 1444480 1176085
Tpc‐d 39500 39500 43631 43632 52330 48304
Rel‐d 234739 234739 276238 258889
Best 115700 115700 130900 124400 143500 131000
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
48
6.10 OPERATION & MAINTENANCE EXPENSES:
The O&M expenses have three components.
1. Employee expenses
2. A&G expenses
3. R& M expenses
The employee expenses includes following components.
1. Salaries
2. Overtime
3. Dearness allowance
4. Other allowance
5. Bonus
6. Medical expenses
7. Earned leave encashment
8. Payment under workmen compensation Act
9. Payment to helpers/Employees of storm & monsoon gang
10. Staff Welfare expenses
11. Terminal Benefits
12. Increase in employee cost on account of pay revision
The A&G expenses includes following components.
1. Rent rates & taxes
2. Security arrangement
3. Telephone, Electricity, Water & Postage charges
4. Legal, audit, consultancy & other professional charges
49
5. Travelling, Conveyance & vehicle charges
6. Vehicle license & registration charges
7. Books, periodical, computer stationary & printing stationary
8. Staff expenses
9. Freight
The A&G expenses also include licensee & Expected Revenue Charges (ERC) filing fees &
other purchase related expenses.
The R&M expenses include expenses on maintenance of T&D network. It includes
1. Repairs and maintenance of plant machinery, vehicles, furniture and fixtures, office
equipment, line materials and cables,
2. Transformers and related equipment, meters and metering equipment etc.
The various approached held to estimate the O&M expenses are explained as follows:
Historical Trend Method-
Based on the actual O&M expenses the CAGR is calculated & the O&M expenses are
approved following the trend. The past period whose actual data is available is considered
like data for 3 years, 5 years.
WPI & CPI Indexed costs-
MPERC in its MYT order has calculated O&M expenses permissible towards ARR for each
year of the Control Period using the formula detailed below. The R&M expenses are linked to
the Gross Fixed Assets, while the employee expenses and A&G expenses are linked to an
Inflation Index, as shown below:
(a) O&Mn = (R&Mn + EMPn + A&Gn)* (1 – Xn)
(i) Where, R&Mn = K*GFAn-1;
(ii) EMPn + A&Gn = (EMPn-1 + A&Gn-1)*(INDXn/ INDXn-1); and
(iii) INDXn = 0.55*CPIn + 0.45*WPIn
50
Where
(b) K‘ is a constant (could be expressed in %) governing the relationship between O&M costs
and gross fixed assets (GFA) for the nth year. Value of K will be determined by the
Commission in the MYT Tariff order based on Licensee‘s filing, benchmarking, approved
cost by the Commission in past and any other factor the Commission feels appropriate;
(c) INDXn - Inflation Factor to be used for indexing can be taken as a combination of the
Consumer Price Index (CPI) and the Wholesale Price Index (WPI) for immediately preceding
five years;
(d) EMPn – Employee Costs of the Licensee for the nth year;
(e) A&Gn – Administrative and General Costs of the Licensee for the nth year;
(f) R&Mn – Repair and Maintenance Costs of the Licensee for the nth year;
(g) Xn is an efficiency factor for nth year. Value of Xn will be determined by the
Commission in the MYT Tariff order based on Licensee‘s filing, benchmarking, approved
cost by the Commission in past and any other factor the Commission feels appropriate.
Composite output Formula (Direct linkage to T&D network)-
APERC had carried out a comprehensive benchmarking exercise to arrive at the O&M cost
for each of the licensees for each year of the control period under MYT framework. For this
exercise, the Commission also considered the relative performance of distribution licensees in
other States and of the distribution circles within the State. It was observed from the
comparative benchmarking exercise that the AP DISCOMs are comparatively efficient and
hence the Commission carried out an inter-se comparative benchmarking exercise confined to
the APDISCOMs for the O&M costs. The methodology adopted by the Commission for the
benchmarking exercise is as follows:
Firstly, in line with the performance-based regulation, the Commission finalized the
DISCOM outputs or parameters that would be the cost drivers for O&M expenses. These
parameters comprise energy sold by the DISCOMs, number of consumers served and length
of the lines (as a proxy for expanse) to be maintained by the licensees. Secondly, these
parameters were consolidated into one single output, which is termed as ―Composite
51
Output‖ and the same has been compared with O&M costs across all DISCOMs. The
Composite Output adopted is as follows:
Composite Output = (no. of consumers) a * (energy sales in MU) b * (ckt km of line length)
c,
Where ‗a‘, ‗b‘ and ‗c‘ denote respectively the weight age of 55%, 20% and 25% to the
respective parameters. Similar exercise is carried out by MPERC to determine the O&M
expenses.
The O&M expenses have been dealt by SERCs by different ways. The O&M expenses as
approved & actual are given here below:
The MERC has used CAGR, historical trend based method from the FY 2004-05 to FY 2006-
07. The CAGR for past five year is considered. In MYT orders (for FY 2007-08 to 209-10)
MERC has used WPI & CPI index method.
52
O & M(Rs. in Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 42711 36579 50689 38768 53060 42654
DGVCL 18469 12958 19353 15310 20276 18002
UGVCL 29214 22079 32,792 29,672 34520 32197
MGVCL 23903 19186 27680 20051 29067 29340
TPL (AD) 35366* 34676* 16311 16757 18537 17763
TPL (SD) 7391 8484 9108 8992
Haryana DHBVNL 26732.5 26732.3 39081 35885.6 66095.8 46429.1
UHBVNL 36754.1 35335.1 62121 45860.5 72597.6 49829.3
Maharashtra MSEDCL 252700 240700 323500 293500 354000 320700
Tpc‐d 3515 3263 4228 3465 5658 3672
Rel‐d 51571 49981 54579 53223
Best 25755 22751 27201 24273 29470 25898
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
53
O & M as % of
ARR(Rs. in Lacs)
Name of the States Distribution Licenses 2007-08 2008-09 2009-10
Gujrat PGVCL 9.258613 9.090518 8.386997
DGVCL 4.972176 4.491652 4.07871
UGVCL 8.803667 7.63384 7.201749
MGVCL 11.45515 10.29191 9.566454
Haryana DHBVNL 7.698058 8.50509 13.16205
UHBVNL 10.33116 13.0198 12.97515
Maharashtra MSEDCL 12.2652 13.36446 12.38152
Tpc‐d 2.79857 2.969101 3.247991
Rel‐d 12.26129 12.48947
Best 9.822654 8.193172 9.229565
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
54
55
Employee
Cost(Rs. in
Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 29020 24526 35919 27469 36963 27270
DGVCL 12461 9186 14897 11257 15424 12154
UGVCL 18698 14229 23,436 21,744 24295 23508
MGVCL 16831 12865 20289 14174 21006 21475
TPL (AD) 13774* 13774* 6493 6262 7412 6638
TPL (SD) 3330 3368 3686 3570
Haryana DHBVNL 20218.4 20218.4 26792.9 26548 48574.5 35130.2
UHBVNL 29578 29838.3 54795.2 36572.9 60064.7 41166.1
Maharashtra MSEDCL
Tpc‐d
Rel‐d
Best
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
56
EC as % of ARR
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Gujrat PGVCL 6.290767 6.44168 5.842604
DGVCL 3.354718 3.457455 3.102684
UGVCL 5.63466 5.455803 5.068554
MGVCL 8.066 7.543809 6.913439
Haryana DHBVNL 5.822217 5.830865 9.672929
UHBVNL 8.314039 11.48441 10.73518
Maharashtra MSEDCL
Tpc‐d
Rel‐d
Best
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
57
the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
R&M(Rs. in
Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 8192 6575 7317 6652 8048 9205
DGVCL 3556 1690 2014 2033 2215 3093
UGVCL 7586 4755 5,993 5,091 6593 5397
MGVCL 3846 3987 3917 3298 4309 4240
TPL (AD) 13489* 13489* 7047 7320 7760 7760
TPL (SD) 2155 2651 2810 2810
Haryana DHBVNL 4062.8 4062.6 7719.5 5937.8 9169.3 4662.9
UHBVNL 5299.4 3620.1 3540.4 6514 8734.2 4864.5
Maharashtra MSEDCL
Tpc‐d
Rel‐d
Best
58
R&M as % of GFA
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Gujrat PGVCL 2.825821 2.241343 1.970559
DGVCL 2.761599 1.339648 1.332235
UGVCL 4.210304 2.932929 2.735435
MGVCL 3.232748 2.814907 2.648449
Haryana DHBVNL 3.454753 4.990781 4.616799
UHBVNL 3.388526 1.743649 3.325161
Maharashtra MSEDCL 4.994872 4.89572 4.402969
Tpc‐d 2.291139 2.186519 2.725014
Rel‐d 5.759162 5.099588
Best 2.674157 2.553094 2.418118
59
A&G(Rs. in Lacs)
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Actual Approved Actual Approved Actual Approved
Gujrat PGVCL 5499 5478 7453 4647 8049 6179
DGVCL 2452 2082 2442 2020 2637 2755
UGVCL 2930 3095 3,363 2,837 3632 3292
MGVCL 3226 2334 3474 2579 3752 3625
TPL (AD) 8133* 7413* 2771 3175 3365 3365
TPL (SD) 1906 2465 2612 2612
Haryana DHBVNL 2451.3 2451.3 4568.6 3399.8 8352 6636
UHBVNL 1876.7 1876.7 3785.4 2773.6 3798.7 3798.7
Maharashtra MSEDCL
Tpc‐d
Rel‐d
Best
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
60
A&G as % of ARR
Name of the
States
Distribution
Licenses 2007-08 2008-09 2009-10
Gujrat PGVCL 1.1920375 1.336614 1.2722755
DGVCL 0.6601211 0.566766 0.5304576
UGVCL 0.8829583 0.782892 0.7577275
MGVCL 1.5460113 1.291695 1.2348483
TPL (AD) 0.7058917 0.994252 1.6631834
TPL (SD) 0.527519 0.793374 0.67893
Haryana DHBVNL 0.7058917 0.994252 1.6631834
UHBVNL 0.527519 0.793374 0.67893
* the combined data of TPL(G), TPL(Surat) &TPL(Ahmadabad)
61
7. IMPACT OF STANDARD OF PERFORMANCE ON TARIFF
7.1 Standards of Performance
While reforms are being put in place; the importance of establishing high quality service
rendered to the customer has been realized. The realization has been more acute where
the utilities have to compete with each other for enhancing their customer base. The
private sector utilities have been quick enough to utilize various internationally accepted
tools for quality enhancement. Even, in recently unbundled SEBs, the mechanism for
collecting the data for analysis of Power supply quality do exist, however it is not
standardized and in most of the cases, not fully utilized.
Hence the state regulator has specified the standard of performance applicable to the
distribution Licensees which is based on commonly followed international practices.
Provision in Electricity Act 2003
Section 57, 58 and 59 of Electricity Act 2003 provides that the Appropriate Commission
may, after consultation with licensees and persons likely to be affected, make regulations
regarding standard of performance of a licensee or a class of licensees. It also provides
that if a licensee fails to meet a specified standard, it shall pay compensation to the person
affected by such failure.
Sections 57, 58 and 59 of EA 2003 read as follows:
57. Standard of performance of Licensee
(1) The Appropriate Commission may, after consultation with the licensees and persons
likely to be affected, specify standards of performance of a licensee or a class of
licensees.
(2) If a licensee fails to meet the standards specified under sub-section (1), without any
prejudice to any penalty which may be imposed or prosecution be initiated, he shall be
liable to pay such compensation to the person affected as may be determined by the
Appropriate Commission.
(3) The Compensation determined under sub-section (2) shall be paid by the concerned
licensee within 90 days of such determination.
62
58. Different standards of performance by licensee
The Appropriate Commission may specify different standards under subsection (1) of
section 57 for a class or classes of licensees.
59.Information with respect to levels of performance
(1) Every Licensee shall, within the period specified by the Appropriate
Commission, furnish to the Commission the following information, namely:
a) the level of performance achieved under sub section (1) of section 57
b) The number of cases in which the compensation was made under sub-section (1) of
section 57 and the aggregate amount of compensation.
(2) The Appropriate Commission shall at least once in every year arrange for publication
in such form and manner as it considers appropriate, of such of the information furnished
to it under sub-section (1).
7.2 Title, Extent and Commencement:
Gujrat:
1. These Regulations may be called the Gujarat Electricity Regulatory Commission
(Standard of Performance of Distribution Licensee)Regulations, 2005
2. These Regulations shall be applicable to all Licensees engaged in distribution of
electricity in the State of Gujarat.
3. These Regulations shall come in force from the date of their publication in
the Gazette.
63
Haryana:
1. These regulations may be called the Haryana Electricity Regulatory Commission
(Standards of Performance for the Distribution Licensee) Regulations, 2004.
2. These regulations shall be applicable to all licensees engaged in distribution &
retail supply of electricity in the State of Haryana.
3. These regulations shall extend to the State of Haryana.
4. These regulations shall come into force on the date of their publication in the
Haryana Government. Gazette. The Punjab General Clauses Act 1898 (Act 1 of
1898), as applicable to the state of Haryana shall apply to the interpretation of
these regulations.
Maharashtra:
1. These Regulations may be called the “Maharashtra Electricity Regulatory
Commission (Standards of Performance of Distribution Licensees, Period for
Giving Supply and Determination of Compensation) Regulations, 2010”.
2. (The “Maharashtra Electricity Regulatory Commission (Standards of Performance
of Distribution Licensees, Period for Giving Supply and Determination of
Compensation) Regulations, 2005”are hereby repealed.
3. These Regulations shall extend to the whole of the State of Maharashtra.
4. These Regulations are applicable to all Distribution Licensees, Deemed Licensees,
Retail Supply Licensees, Franchisees and any other agency engaged in
distribution of supply.
5. These Regulations shall come into force from the date of their publication in the
Official Gazette.
64
8. PARAMETERS OF STANDARD OF PERFORMANCE:
The important points which are considered by different SERC’S for the Standard of
performance are as follows:
8.1. RELIABILITY OF THE SYSTEM
The following reliability/outage indices are prescribed by the Institute of Electrical and
Electronics Engineers (IEEE) Standard 1366 of 1998. The Licensee shall compute and report
the value of these indices from 2002-03 onwards:
(a) System Average Interruption Frequency Index (SAIFI): The Licensee shall calculate
the value according to the formula and methodology specified below.
(b) System Average Interruption Duration Index (SAIDI): The Licensee shall calculate
the value according to the formula and methodology specified below.
(c) Momentary Average Interruption Frequency Index (MAIFI): The Licensee shall
calculate the value according to the formula and methodology specified below.
Method to compute Distribution System Reliability Indices:
The Indices shall be computed for the Distribution licensee as a whole by stacking, for each
month, all the 11 KV feeders in the supply area, excluding those serving predominantly
agricultural loads, and then aggregating the number and duration of all interruptions in that
month for each feeder. The Indices would then be computed using the following formula:
Where,
Ai = Total number of sustained interruptions (each longer than 5 minutes) on
ith feeder for the month
Ni = Connected load of ith feeder affected due to each interruption
Nt = Total connected load at 11KV in the Distribution licensee’s supply area
65
n = Number of 11KV feeders in the licensed area of supply (excluding those
Where,
Bi = Total duration of all sustained interruptions on ith feeder for the
month.
Ci = Total number of momentary interruptions (each less than or
equal to 5 minutes) on ith feeder for the month
8.2. Exemption
The standards of performance specified in these regulations shall remain suspended during
Force Majeure conditions such as war, mutiny, civil commotion, riot, flood, cyclone,
lightning, earthquake or other causes beyond the control of the Licensee and strike, lockout,
fire affecting the licensee’s installations and activities.
66
8.3 INFORMATION REGARDING LEVEL OF PERFORMANCE:
Gujrat:
The Licensee shall furnish to the Commission, in a report specified in these
Regulations for every quarterly as well as in a consolidated annual report for each
financial year, the following information as to the Standards of Performance:
o The level of performance achieved as specified in these regulations; and,
o The measures taken by the licensee to improve performance in the areas
covered by these Standards and licensee’s assessment of the targets to be
imposed for the ensuing year.
o Number of cases in which compensation was made and aggregate amount of
compensation.
The Quarterly reports shall be furnished to the Commission within 15 days of the
close of the quarter and the annual report shall be furnished to the Commission within
30 days of the close of the financial year.
The Commission shall, at such intervals, as it may deem fit, direct the Licensee or
otherwise arrange for the publication of the information furnished by licensees under
this regulation in such form and manner as the Commission consider it to be
appropriate.
Haryana:
The Standards of Performance specified shall be the minimum standard of service
with reference to quality, continuity and reliability of services that a licensee shall
achieve in discharge of his obligations as a licensee.
Standards of Performance specified in Schedule I relates to Guaranteed Standards of
Performance for which consumers against whom no arrear is pending on the date of
violation are eligible for compensation in the manner provided in the Schedule I in
case the Licensee fails to achieve the Standards of Performance.
In case of applications requiring supply under agriculture category (Agriculture Pump
sets) licensee’s obligation shall be limited to the number of connections that can be
covered within the target fixed by the State Government for release of agricultural
connections for a financial year. The target for an ensuing year should be fixed and
made public at least 2 months before the commencement of the year. The licensee
shall inform the applicants in writing within 15 days of receipt of applications, if the
67
applicants’ case cannot be covered in the programme of release of Agriculture Pump
set connections fixed for the year.
.Schedule II relates to Overall Standards of Performance, which indicates the level of
performance the licensee shall seek to achieve in the discharge of his obligations as a
licensee.
An Annual Review Committee shall be formed by each Distribution
Licensee and its recommendation shall be submitted to the Commission for
approval. The Commission may modify, upgrade and cancel the requirements from time to
time.
Maharashtra:
The Distribution Licensees shall maintain and submit information on the matters covered
under clauses (a) and (b) of sub-section (1) of Section 59 of the Act to the Forum on a
monthly basis and put up such information on the internet website of the Distribution
Licensee, within a period of thirty (30) days from the end of the month: Provided also that the
Distribution Licensee shall submit information on the matters covered under clauses (a) and
(b) of sub-section (1) of Section 59 of the Act to the Commission on an annual basis, within a
period of thirty (30) days from the end of the financial year: Provided that the information
shall be with respect to the total number of cases of failure to meet each of the standards
specified in these Regulations: Provided further also that the Distribution Licensee shall
separately state the total number of cases where compensation has been paid by it without
dispute and the total number of cases where compensation has been paid in compliance with
an order or direction of the Forum or Ombudsman, along with the total amount of
compensation in each category. Provided further 14.2 The Distribution Licensee shall submit
the information to the Commission on the matters covered under clauses (a) and (b) of sub-
section (1) of Section 59 of the Act on quarterly basis, within a period of thirty (30) days
from the end of the quarter in the forms shown in Annexure I to Annexure VI. 14. 3
68
Content of audit report
The audit report shall address the following specific matters (a) Adherence to procedures and
formats as per regulations; (b) Assessing staff engaged in call centers/complaint handling
centers/customer care centers for their understanding of complaint handling procedures,
quality parameters, and training adequacy for their task; (c) Method of data collection and
management procedures; and (d) Review of relevant records (as per appropriate sampling
procedures) for reliability and accuracy across quality parameters; 14.3.2 The Commission
may authorize the Commission staff or any independent agency(ies) to conduct annual
checks, in order to monitor the compliance of the standards by licensees and submit audit
report to the Commission.
The following procedure shall be adopted for engaging agency (ies):
(a) audit scope and the methodology for carrying out the audit to be set by the Commission;
(b) the Commission will identify and publish panel of approved agency (ies);
(c) Licensee shall nominate an agency from the notified panel of agencies; 21
(d) Licensee shall not engage an agency consecutively for more than two years. They shall
also not engage an agency which is currently their statutory auditor or internal auditor or has
been engaged as a consultant;
(e) audit shall be conducted under an agreement between the nominated agency and licensee;
and (f) remuneration of the audit agency will be paid by the licensee.
Auditing methodology
Grading of the audit report on performance standard submitted by the licensee shall be done
in two parts – reliability and accuracy of the data.
a) Reliability grading The grading system for reporting the reliability of the performance
standards shall be set as under:
Reliability Grade Assessment of Reliability Grade
A Based on proper records with
adequate procedures
B Data has significant procedural
deviations
C Unsatisfactory Data
69
Only if the reliability is of the Grade A, further analysis will be carried out to measure claims
on achievement.
b) Accuracy grading If the data submitted has reliability of Grade A, then further analysis of
data will be carried out to assess accuracy of information provided.
c) Based on the accuracy grade assessment of the information provided on the achievement
of Overall Standards, certain percentage of compensation paid may be allowed in the
ARR by the Commission, set as under:
Accuracy Level Percentage of compensation paid
to be recovered through Annual
Revenue Requirement
+/-2% 100%
+/-5% 85%
+/-10% 70%
8.4. Handling of complaint:
Maharashtra:
The Distribution Licensee shall register every complaint made by a consumer (either verbally
or in writing) in a register / registers or in electronic format to be maintained for this purpose.
The complaint register shall be maintained category wise which will help in finalization of
compensation and reporting performance to the Commission. The licensee shall allot a
number to each complaint which shall be duly communicated to the consumer except in the
case of postal complaints received. However the number shall be communicated to the
complainant in case subsequent to the delivery of postal complaint he/she inquires regarding
the complaint number / status telephonically or in person. 8.11 Licensee shall devise its own
processes at complaint handling centers / call centre(s) / customer care centre(s) / service
centre(s) or any other customer interface channels to handle consumer complaints. The
processes should include the following:
70
(a) registration of complaints by allotting a unique identification number to be called the
complaint number;
(b) Communication to the consumer of the complaint number, date / time of registration of
the complaint and expected complaint resolution time;
(c) Record details of each complaint (As per Annexure III);
(d) Intimate contact details of the next higher authority (including his name, telephone
number and address) to the consumer in case the consumer is not satisfied with the complaint
handling or when requested by him; and
(e) Update and record feedback of the consumer on the action taken along with the total time
taken for resolution of the complaint. 8.12 Licensee shall held consumer service day in each
office once in a month by pre declaration. The complaints received on consumer service day
should also be taken in the complaint register and resolve them as per Regulation.
Gujrat:
1. The licensee is required to maintain standards of performance for supply of electricity to
all consumers in the manner prescribed hereinafter. The limits prescribed in these standards
refer to the maximum time permissible for performance of different activities of consumer
services. It shall be the endeavour of the licensee to provide the best possible services well
within the time limits specified in these Regulations.
2. The licensee shall register every complaint made by a consumer, either verbally or in
writing, regarding failure/interruption of power supply, quality of power supply, meters/meter
boxes/metering system’s service line, payment of bills and other services relating to power
supply, in a register / registers or in electronic format to be maintained for this purpose. A
unique number shall be allotted to each complaint. This complaint number shall be conveyed
to the consumer except in the case of postal complaints received. However the consumer
may, subsequent to the delivery of postal complaint, inquire regarding the complaint number/
status telephonically or in person. The number shall be communicated to the complainant in
such a case. In case of major failure of supply due to tripping of EHV or failure of upstream
power systems, the reason needs to be communicated to the consumer in addition to the likely
restoration time. In such a scenario, such complaints shall be recorded separately under single
complaint number. The licensee shall ensure redressal of all complaints promptly.
71
3. Complaints in respect of supply of electricity covering metering, billing and payment, shall
be made at specified offices of the licensee. Licensee shall convey information of the name of
office(s), address(s) and telephone numbers where the consumer can lodge complaints, with
the electricity bills and also display it at the sub-division offices or equivalent distribution
unit designated by whatever name. If the phone services for recording complaints, if
outsourced by the licensee, the phone numbers of such call centre shall be displayed in
electricity bills and sub-divisional offices. The licensee shall also endeavor to publicise these
contact details through The office where a complaint is registered shall dispose it of and if
any instruction/sanction is to be obtained from a higher authority, it shall be obtained by the
complaint registering office. The complainant is not required to approach such higher
authority. Similarly, in case an outsourced phone service is engaged, such centre itself shall
forward the complaints to the concerned officer. The licensee shall ensure proper compliance
by the outsourced service by arranging visits of its officers to such centers to streamline
responses.
Grievances regarding non-registration of complaints and failure to perform within the time
limits and/or to meet the performance targets, as specified in these Regulations, shall be made
to the concerned officer in-charge of the division or to equivalent distribution unit designated
by any other name. In case of unsatisfactory disposal of grievances/complaint should
be made to the officer in-charge of the circle or equivalent similar functionary by whatever
name designated.
In case a consumer is not satisfied with the disposal of complaint even after taking the issue
at the level of division head / circle head, he can approach the complaint redressal committee
as indicated in sub clause 4.7 below.
4.7 The licensee shall hold regular grievance redressal meetings with consumers. These
meetings shall be open to all consumers. The consumers can also register their complaints in
these meetings. These meetings shall be held in the office of the head of the sub-division or
equivalent distribution unit designated by whatever name on 10th of every month and in the
office of the head of the circle or equivalent similar functionary by whatever name designated
on 20th of the same month. If10th or 20th of a month falls on a Sunday or a public holiday or
a holiday in the State due to any other reason, the meeting shall be held on the next working
day. The schedule of the redressal committee meetings should be displayed at sub-
division/circle/section/zonal offices. Minutes of the subdivision/section level meeting and
action taken report should be available to the head of the circle/zone at the time of meeting to
72
be held on 20th of the same month. The redressal committee shall as far as practicable
dispose of the matter within not more than three meetings
8.5 COMPENSATION:
Gujrat:
1. If a Licensee fails to meet the standards specified, the affected domestic consumer is
entitled to compensation from the Licensee as provided in the annexure
2. Considering the first year of implementation as a transition period, the Commission
permits moratorium on payment of compensation by licensees to consumers during such
period. The Commission will monitor the efforts of the licensees for improvement of their
system and services during this transition period. The moratorium period will end on
30.06.2005.
3. Consumer grievances with regard to non-implementation of standards of performance
according to these Regulations shall be redressed as provided in the Regulations for GERC
(Establishment of Forum for Redressal of Grievances of the Consumers) and GERC
(Establishment of Ombudsman). The compensation to the affected consumers shall be paid
by a licensee automatically following the decision by Redressal Forum/Ombudsman in the
next billing cycle.
4. In order to familiarise consumers of their rights under these Regulations ,the extracts of the
Regulations pertaining to consumer rights should be printed and widely publicized from time
to time through appropriate media.
Haryana:
1.If the Licensee fails to meet the Standards of Performance specified in Schedule I, the
licensee shall pay to the affected consumer against whom no arrear is pending on the date of
violation, the compensation as indicated against each of the Standards of Performance in
Schedule I.
2 The Licensee shall register every complaint of a consumer. The Licensee shall computerise
the registration of every complaint of a consumer through automatic answering machine or
any other such means intimating the complaint number to the consumer automatically.
73
3 The Licensee shall maintain relevant records consumer-wise regarding the Standards of
performance in order to give a fair treatment to all consumers and avoid any dispute
regarding violation of standards
.
4. All payment of compensation shall be made by way of adjustment against existing, current
and/or future bills for supply of electricity.
Provided the compensation shall be paid in Cash/ Demand draft wherever the claimant ceases
to be the consumer of the utility.
Provided that all the compensation shall be made within 90 days from the date of violation of
a guaranteed standard of performance. If the Compensation is not adjustable in the existing,
current and/or future bills of the supply of electricity the same should be paid in cash /
demand draft to ensure that the compensation is paid within 90 days from the date of
violation of a guaranteed standard of performance.
Maharashtra:
1. The minimum compensation to be paid by the licensee to the affected person is specified in
Appendix A of these regulations. Provided, the actual compensation may be decided by the
Commission considering the following factors:
(a) Hardship caused to the consumer; and
(b) Average monthly bill of the consumer.
2. Where the Distribution Licensee finds that it has failed to meet the standards of
performance specified under these Regulations, the Distribution Licensee shall be liable to
pay to the affected person, such compensation as provided in Appendix A to these
Regulations. Provided that any person who is affected by the failure of the Distribution
Licensee to meet the standards of performance specified under these Regulations and who
seeks to claim compensation shall file his claim with such a Distribution Licensee within a
maximum period of sixty (60) days from the time such a person is affected by such failure of
the Distribution Licensee to meet the standards of performance.
Provided that the Distribution Licensee shall compensate the affected person (s) within a
maximum period of ninety (90) days from the date of his claim.
74
3. In case the Distribution Licensee fails to pay the compensation or if the affected person is
aggrieved by non-redressal of his grievances, he may make a representation for the redressal
of his grievance to the concerned Consumer Grievance Redressal Forum in accordance with
the provisions of Maharashtra Electricity Regulatory Commission (consumer grievances
redressal Forum and Electricity Ombudsman) Regulation, 2006 and any amendment thereto
(as in force from time to time)
Provided that in case the claim for compensation is upheld by the Consumer Grievances
Redressal Forum the compensation determined by the Commission in Appendix A to these
regulations will be implemented by the Forum or in case of appeal filed against order of the
Forum before him by the Ombudsman and is to be paid by the concerned Distribution
Licensee. Provided further that such compensation shall be based on the classification of such
failure as determined by the Commission under the provisions of Section 57 of the Act and
the payment of such compensation shall be paid or adjusted in the consumer’s future bills
(issued subsequent to the award of compensation) within ninety (90) days of a direction
issued by the Forum or by the Ombudsman, as the case may be.
75
9. EFFECTS OF STANDARD OF PERFORMANCE ON TARIFF:
The tariff is also depended on the standard of performance of different utilities because of
many reasons,
If the distribution network is not performing upto the mark, then there will be no continuity
of supply and hence the consumer will not get the supply. Though the utilities are providing
supply but it is not reaching to consumer. The utility is asking for the the payment and hence
the tariff is hiking.
The government is providing subsidy to agriculture sector for that they are collecting the
cross subsidy from the domestic sector. But the farmers are not getting that electricity due to
poor distribution system. To provide subsidy, tariff is increasing,
The distribution loses are increasing due to poor distribution infrastructure. The equipments
which are used to produce electricity must perform according to SOP, because if it does not
perform with that, the fuel is wasted. the fuel cost is increasing rapidly.
If the utility does not provide services to consumer, then there may be complaints from the
consumer such as
(A) Interruption in power supply.
(i) Loose connections from pole
(ii) Interruption due to line breakdown
(iii) Interruption due to failure of transformer
Page 30
(B) Quality of power supply
(i) Ordinary case, which requires no augmentation.
(ii) Where augmentation is required.
(C) Meters
(i) Stopped/Defective Meters.
(ii) Billing on average basis for more than two bills
(D) Overhead lines
(i) Loose Wires
76
(ii) Inadequate ground clearance
(E) Bills
(i) For current bills where no additional information is required.
(ii) Where additional information relating to correctness of reading etc. is
required.
(F) Service connections (Domestic & Non Domestic)
(i) Where extension of mains is not required.
(ii) Where extension of mains is required.
(iii) Modification in connected load.
(iv) Name change/reconnection.
(G) Refund of amount due in regard to temporary connection.
(H) Others
77
10. CONCLUSION:
The importance of regulatory practices cannot be underestimated. Assessment of regulatory
practices across countries has shown that independent regulation has promoted investment in
telecommunication services. Results of concession agreements in Latin America in electricity
and roads sector in India have also resulted in attracting fresh investment. However, in India
payment security issues have dominated and regulations have not brought about larger inflow
of private investments. The share of private investment in all segments of electricity supply
remains small. Recent spurt of investment in generation, particularly in Ultra Mega Power
Plants is because it has given greater payment security than was available before. However,
not much activity is being witnessed in distribution segment of electricity supply.
The electricity Act 2003 has become the law of the land. The SERCs have played a positive
role in the after reform period. Their functions especially related to tariff fixation has brought
a positive change in the power sector. SERCs have initiated more public participation &
transparencies in the proceeding. The increased no of objections filed by consumers, NGOs
& several associations proves the increased participation. SERCs have up loaded all their
proceedings, orders discussion paper on their respective websites which are open to
discussion to public.
If we want to get the clear picture of the aftermaths of restructuring & effects of regulatory
governance the overall improvement is seen in following areas in states under consideration;
1. Positive Trend towards reduction in distribution losses.
2. Increased & more focused investment
3. Capacity additions & system strengthening of the power systems
4. Localization & reduction in efficiencies.
5. Improved customer care.
6. Progress in metering, billing, & revenue collection.
7. Increased accountability in DISCOMs.
78
8. The SERCs tariff setting approach is well established & understood by Utilities. So a well
understanding & coordination trend has established in tariff fixing. The SERCs are reviewing
the Utilities performance with the benchmarked one regularly.
The conclusions about operational & financial parameters are given as below.
In case of sale forecasting or demand estimation the historical trend method has proved to be
reasonably accurate and a well accepted method to estimate the number of consumers, the
connected load and the energy consumption where the past data is fairly accurate and the
trends are well established.
Almost all the SERCs have adopted merit order dispatch approach for power purchase.
Prior to reforms, there were minimum efforts to scientifically assess the T&D losses that
were often masked in unmetered (primarily agricultural) consumption. The approaches &
measures taken by SERCs are different. There is no uniform method for measuring & setting
targets for T&D losses.
In cost based regulation capital cost is the most important parameter. THE SERCs have
carefully studied the past assets capitalizations to approve CAPEX.
From a regulatory perspective, depreciation is considered as a small amount of the original
cost of the capital assets, built into the tariff computation every year with a view to providing
the utility a source of funding to repay instalments of debt capital. The refund of capital view
is mainly adopted by SERCs. Advance against depreciation (AAD) is allowed in certain
conditions like where the debt redemption obligation is not matching with the existing
depreciation allowed.
The SERCs differs on the ROCE or ROE approach The ROCE approach is consistent with
the performance based regulations. Normative COD will not work for all companies in India.
Approved interest on loans is directly related to the loans taken into the Capital Base
computations. The loans drawn for CAPEX and interest thereon are a pass-through in the
tariffs.
For the purpose of tariff fixation & identification of cross subsidy the CTS model proves to
be an important tool. The basic objective of the Commission to use the CTS with regard to
tariff design in the Tariff Orders was to build a road map to move towards cost-reflective
79
tariffs. The subsidy given by state government limits SERC from adopting progressive Cost
to Serve model. Due to subsidy SERC cannot increase tariff for subsidized consumers like
Domestic & Agricultural. However regulatory Commissions like in AP & Karnataka have at
least decreased the tariff for HT & other subsidizing categories.
The Indian Power sector has gone through the institutional & structural changes, given the
existing arrangement from SEBS to unbundled DISCOMs. Even the wholesale level
competition has been introduced. Model 4, the retail competition is a logical end point to the
reforms, because Model 4 avoids the potential conflicts & inefficiencies of Model 3,
wholesale competition. If the goal is competition in production model 3 can be sufficient. We
have brought requires the structural & institutional changes at the wholesale level needed for
model 4. However the main hurdle in front of us is elimination of subsidy & cross subsidy.
Looking at the current scenario it will take more time than expected to eliminate the cross
subsidy & subsidy.
The State Government gives subsidy to fill the revenue gap for its state utilities. The main
reason for giving subsidy has political & economical background rather than the
differentiation expected in electricity Act 2003, National electricity policy & National tariff
Policy. The clauses & provisions itself in policy & act looks contradictory.
In Indian power sector, the expensive peak hours with the cheap off peak hours are sold at
one average price. Electricity prices for the consumers are always been bundled- as per
quantity used, but not by when the electricity is used. TOD tariff is applied to mainly HT
industrial & non industrial consumers.
An area of concern is that even after a decade of reform is that realistic valuation of losses is
still lagging. Particularly agriculture consumers, which are still unmetered in most of the
states, are a big cause of distribution losses. Indeed the improvement in feeder metering &
DTC metering is significant, the large portion of unmetered agricultural consumption still
makes actual losses unknown. Somehow the estimated unmetered consumption is masking
the distribution losses.
It has been observed that the basic systems do exist in the utilities. However they can be
sharpened and can be effectively used with advanced technologies.
Minor additions / modifications are necessary for monitoring and improving the system
Reliability.
80
If we want to get the clear picture of the aftermaths of restructuring & effects of Standard of
performance, the overall improvement is seen in the tariff rate.
If the utility follows SOP led by the SERC, then the utilities save the compensation which is
to be given to consumer.
If the services provided by the utilities are provide in the efficient way, then it will be
beneficial to consumer. No complaints will be there from consumer side
81
11. RECOMMENDATIONS:
International experience shows that power sector reforms have been successful in countries
with adequate generation and transmission capacity. This condition is not satisfied in a
number of countries in South Asia. In India too, barring a few states in eastern India and
small Himalayan states like Uttaranchal and Himachal Pradesh which have hydro-electric
sources of power other states suffer from insufficient generation and congestion in the
transmission systems.
PRIVATE INVESTMENT:
The essential conditions for encouraging private investment in a sector are that investors
should be confident that they would get adequate returns. This crucially depends in the
viability of the distribution sector. In Electricity Act 2003 emphasis is given to increasing
competition and enhancing private sector investment, yet power sector is not completely
conducive for private sector investment. Although some regulations e.g. Multi Year Tariff
and Open Access provide some certainty to investors, yet its proper implementation is very
crucial.
INDEPENDENT FUNCTIONING OF REGULATORY COMMISSIONS:
Regulators have been given the key role in reforming the sector. Electricity Act 2003 gives
them wide ranging powers. The functions and powers given to regulators in electricity sector
compare favourably with the best. However, the regulators face the challenge of unfavourable
initial conditions. These include the challenge of dealing with state owned utilities, which
have overwhelming presence in generation and monopoly in distribution and transmission.
In most states these vertically integrated utilities have been unbundled and converted into
corporations. But this has not brought about any change in their management style or
incentive system. They continue to function as administrative bodies that are not responsive
to economic incentives and —for them the concept of cost does not apply. Their concept of
rationality involves following procedures (particularly based on paper work) rather than
taking cost benefit based decisions―. They also do not consider themselves directly
responsible to the shareholders (i.e. tax payers) nor to the consumers but only to the State
Government. In fact in a number of states the Secretary Department of Power is also the
Chairperson of the Power Corporations. Thus, the role of the government as policy maker and
82
that of the corporation as implementing agency is devolved in the same person. It is thus not a
surprise that the accounts in most cases have not been finalized nor were the tariff petitions
filed on time. Despite the change to corporate structure, the provisions of company law
relating to prudent accounting practices and publication of quarterly accounts and finalization
of balance sheets have been given a miss. The structural reforms as envisaged by the
Government of India and enforced by States do not lead to any substantial change either of
the organization or of the administrative nature of the SEB‗s.
EFFICIENT MANAGEMENT OF FUNDS:
The financial institutions that have increased fund flows for generation projects as well as
distribution reform schemes like APDRP and Rajiv Gandhi Grameen Vidyutikaran Yojna
have not insisted on funds releases being conditional or following the company law
provisions or principles of good governance. They are mostly satisfied by the State
Governments tendering a guarantee, despite the fact, that over the years, such guarantees
have not ensured timely payment.
TIMELINESS OF TARIFF ORDERS:
All SERCs should issue tariff orders in time so that tariff structure could be improved and
approved tariff could be implemented without delay.
LOAD FORECASTING & SALES ESTIMATION:
The sale/demand forecasting should be Time of Day (TOD) based so that peak hour demand,
off peak hour demand & the supply for the respective time can be managed in better ways.
Also the methodology adopted for forecasting should be a standard one, and should not vary
through the years.
CAPITAL EXPENDITURE OR INVESTMENT:
The capital work proposed by DISCOMs needs to be scrutinized by independent agencies or
consultancies so that the base line data will be corrected, the technical feasibility will be 78
evaluated correctly & the only useful investment will be done. Also in capital work execution
consultancy expertise needs to be utilized.
83
TOD TARIFF:
The TOD tariff is based on conservation by price response. TOD tariff is applied to mainly
HT industrial & non industrial consumers. It should be given priority to extend MYT to LT
industrial, commercial & high consumption Residential consumers. However the hourly
metering should be cost effective. It should be implemented in the case of
The customer is large electricity user;
The customer‘s price responsiveness ( elasticity of demand) is high; or
The difference between the hourly prices (due to short term & ABT ) & the averaged
price is large.
Recommendations for the Impact of SOP:
The detail study of Standard of performance of distribution utilities is done through the
information available in the annexure. There are many ways in which we can improve the
standard of performance such as improving reliability indices, handling consumer complaints
as early as possible.
1, The most reliable and accurate data management is very important in calculating and
maintaining the reliability indices. For fast, accurate and reliable data management, a power
distribution software solution based on an integration of dedicated GIS and Network analysis
solution will be the right approach.
SCADA
Monitoring of the distribution system on a real time basis and introducing a certain measure
of automation into the distribution system is best achieved with a Supervisory Control and
Data Acquisition system (SCADA). Implementation of SCADA is already initiated in
selected circles in MSEDCL.
Network Information system
Integration of the network mapping and the network analysis software with SCADA will
substantially improve the operating efficiency and consequently customer satisfaction and
will repay its cost over a period of time.
84
It would be ideal to model low voltage network emanating from each and every distribution
transformer. The difficulty is that the network data would be acquired in phases due to the
large number of network entities and the large number of low voltage consumers.
2. Gujrat utilities are one of the most efficient utilities in India. The utilities have also started
keeping the record of standard of performance. The data is recorded on the quarterly year
basis.
85
12. REFERENCES:
TARIFF ORDERS:
1. Tariff Orders issued by CERC, GERC, MERC & HERC from the period 2007-08 to
2009-10
TARIFF REGULATIONS:
1. Tariff regulations issued by CERC, GERC, MERC & HERC.
WEBSITES:
1. www.cercind.gov.in
2. www.herc.gov.in
3. www.gercin.org
4. www.powermin.nic.in
5. www.merc.org
REPORTS:
1. TERI, ―Analysis & compilation of tariff orders‖, TERI report no 2006RP23 May 2007
final report
2. PFC, ―Report on the Performance of The State Power Utilities for the Years 2004-05
to 2006-07‖
3.Standard Of Performance of different state .