Upload
muhammad-umar
View
216
Download
0
Embed Size (px)
Citation preview
7/27/2019 Analysis for civil works
1/11
P/F P.V.C doors of approved quality and manufacturer i/c all
fittings complete as approved and directed by the Engineer
Incharge.
(Analysis for 2 x7=17.5 Sft)
Cost of vinyle door 17.5 Sft @440/Sft 7700/-
Hardware/accessories 450/Each door 450/-
Fitting Charges 350/Each door 350/-
Carriage from market to site of work 300/Each door 200/-
Total 8820/-
Add 20% Contractor profit 1770/-
Total 10620/-
Rate Per Sft 10620/17.5 606.85/Sft
Say 600/Sft
Sub Divisional OfficerProvincial Buildings Sub Division-I
SargodhaExecutive Engineer
Provincial Buildings DivisionSargodha
7/27/2019 Analysis for civil works
2/11
ANALYSIS OF RATE
P/F Non clogging centrifugal pump 3x4 in position of centrifugal pump 0.5 cusecs coupled with
electric motor 05 BHP (Siemens) made head 40 ft i/c bowl assembly impellers pump shaft top set
erection of suspension clumps cable clamps sluice valves reflex valves circuit breaker etc dry running
protection device complete in all respects as approved and directed by the Engineer In charge.
___________
Cost of machinery (Quotation attached) 370000/-
Cost of c conc foundation 5000/-
Total 382000/-
Contractor profit and overhead (11%) 42020/-
Total 424020/-
Say 424000/-
It is certificate that the N.S item. rates as taken in the analysis which are not included in the rate areprevailing market rates and are verified for the market.
Sub-Divisional Officer,
7/27/2019 Analysis for civil works
3/11
Provincial Buildings Sub-Division No. 1,
Sargodha
7/27/2019 Analysis for civil works
4/11
ANALYSIS OF RATE
P/F Water supply centrifugal pump 3x4 in position of centrifugal pump 0.5 cusecs coupled with
electric motor 05 BHP (Siemens) made head 40 ft i/c bowl assembly impellers pump shaft top set
erection of suspension clumps cable clamps sluice valves reflex valves circuit breaker etc dry running
protection device complete in all respects as approved and directed by the Engineer In charge.
___________
Cost of machinery (Quotation attached) 325000/-
Cost of c conc foundation 5000/-
Total 330000/-
Contractor profit and overhead (11%) 36300/-
Total 366300/-
Say 366000/-
It is certificate that the N.S item. rates as taken in the analysis which are not included in the rate areprevailing market rates and are verified for the market.
7/27/2019 Analysis for civil works
5/11
Sub-Divisional Officer,
Provincial Buildings Sub-Division No. 1,
Sargodha
7/27/2019 Analysis for civil works
6/11
7/27/2019 Analysis for civil works
7/11
ANALYSIS OF RATE
P/F Water supply Submersible turbine 0.25 cusecs as approved and directed by the Engineer In charge.
___________
Cost of machinery (Quotation attached) 1000000/-
Cost of c conc foundation 5000/-
Total 1005000/-
Contractor profit and overhead (11%) 110000/-
Total 1115000/-
Say 1115000/-
It is certificate that the N.S item. rates as taken in the analysis which are not included in the rate are
prevailing market rates and are verified for the market.
7/27/2019 Analysis for civil works
8/11
Sub-Divisional Officer,
Provincial Buildings Sub-Division No. 1,
Sargodha
7/27/2019 Analysis for civil works
9/11
7/27/2019 Analysis for civil works
10/11
ANALYSIS OF RATE
P/F of white board size 8x4 and thick made of chip board laminated with Formica i/c beading and
lipping on four sides complete in all respects as approved/directed by the Engineer Incharge.
___________
Unit of Analysis Each of size 8x4
Material
1 Cost of Chip board (8x4) 1050/-
2 Cost of Formica 600/-
3 Cost of adhesive 300/-
4 Cost of beading 24Rft@20/Rft 480/-
5 Cost of lipping 24Rft@15/Rft 360/-
4 Carriage from workshop to site of work 500/-
Total 3290/-
Laboure
1 Laboure for making of white board 500/-
7/27/2019 Analysis for civil works
11/11
2 Laboure for fixing of white board on wall i/c nailing and screwing 200/-
Total 700/-
G Total 3990/-
Contractor profit and overhead (20%) 798/-
Total 4788/-
Say 4788/-
It is certificate that the N.S item. rates as taken in the analysis which are not included in the rate are
prevailing market rates and are verified for the market.
Sub-Divisional Officer,
Provincial Buildings Sub-Division No. 1,
Sargodha