Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
ANALYSIS AND INTERPRETATION OF GROUND AND BUILDING MOVEMENTS
DUE TO EPB TUNNELLING
by
Gima V. Mathew
This thesis is presented for the degree of
Doctor of Philosophy
of
The University of Western Australia
School of Civil and Resources Engineering
October 2010
DEDICATED TO
ALMIGHTY GOD
i
ABSTRACT
As the number of tunnels increases to meet the demands of a world with a rapidly
expanding population, the importance of tunnel design and construction efficiencies
also grows; such new efficiencies must ensure minimal damage to nearby existing
structures and facilities. When tunnels are constructed in an urban area, it is important,
at the design stage, that the response of nearby structures can be predicted with
sufficient accuracy. These predictions will affect the choice of tunnelling method and
dictate the form and scope of potential ground improvement measures. While the
‘Gaussian empirical method’ has been shown to provide good estimates of the shape of
the settlement profile in ‘greenfield’ conditions (i.e. where no structures are present),
this method cannot be used to assess structural movements associated with the
tunnelling, for which the profession now generally employs the finite element method.
This thesis investigates the surface (‘greenfield’) and building movements induced by
two bored tunnels in the central business district (CBD) of Perth, Western Australia.
The tunnelling was carried out by an Earth Pressure Balanced (EPB) Tunnel Boring
Machine and the stratigraphy along the tunnel route comprised normally consolidated
dune sand overlying the interbedded layers of alluvial silts, clays and sands. Volume
losses during EPB tunnelling were generally less than 0.29% and, as a consequence,
settlements associated with tunnelling were small and no building damage was
observed.
The greenfield measurements (observed using electro-level beams and settlement pins
in a railway yard) indicated wider tunnelling-induced settlement troughs in soil profiles
comprising a higher proportion of clay layers. Time dependent or consolidation
settlements observed after tunnelling was completed were not significant. Contrary to
expectations, the volume losses associated with the second tunnel boring were less than
those induced during the initial boring. All ‘greenfield’ settlement troughs were of a
Gaussian nature and this form could not be predicted with an acceptable level of
accuracy using both 2D (Plaxis version 9.02) and 3D (Plaxis 3D Tunnel, Version 2.0)
ii
finite element (FE) analyses combined with relatively advanced soil models. Reasons
for the mismatch are discussed in this thesis and ways in which the Gaussian form may
be predicted are investigated.
Observed movement data as well as finite element back analyses for a multi-storey
building in Perth CBD indicated that the stiffness of the building altered the free field
(Gaussian) form of the settlement trough in its vicinity. 2D FE analyses are used to
illustrate how building stiffness and soil type and/stiffness influence the shape of the
predicted settlement trough. A comparison of measurements with predictions suggests
that the FE approach adopted is a reasonable method for assessing soil structure
interaction effects.
To assist the numerical predictions, the thesis also present results from a targeted
laboratory and in-situ test investigation on the upper horizons of the alluvial deposit
found beneath Perth’s dune sand; little information was available on the mechanical
properties of these horizons. The effectiveness of using compensation grouting in sand
to reduce the volume loss due to tunnel boring and the applicability of numerical
methods to model the grouting is also investigated.
iii
TABLE OF CONTENTS
ABSTRACT........................................................................................................................... I TABLE OF CONTENTS .................................................................................................. III TABLE OF FIGURES ...................................................................................................... IX LIST OF TABLES....................................................................................................... XVIII ACKNOWLEDGEMENT ............................................................................................. XXI DECLARATION ......................................................................................................... XXIII SYMBOLS AND ABBREVIATIONS..........................................................................XXV CHAPTER 1 INTRODUCTION.........................................................................................1
1.1 BACKGROUND ...............................................................................................1
1.2 SCOPE OF THIS RESEARCH .........................................................................1
1.3 RESEARCH SITES ...........................................................................................4
1.4 THESIS STRUCTURE......................................................................................5 CHAPTER 2 LITERATURE REVIEW.............................................................................7
2.1 INTRODUCTION .............................................................................................7
2.2 GROUND DEFORMATION ............................................................................7
2.2.1 Failure Mode .....................................................................................9
2.2.2 Centrifuge Model Testing in Sand ..................................................10
2.3 SETTLEMENT PREDICTION METHODS...................................................12
2.3.1 Empirical Method ...........................................................................13
2.3.2 Numerical Prediction ......................................................................15
2.4 BUILDING MOVEMENT DUE TO TUNNEL BORING .............................20
2.4.1 Mode of Building Deformation.......................................................22
2.4.2 Numerical Studies of Interaction Problem......................................25
2.5 COMPENSATION GROUTING ....................................................................28
2.5.1 Numerical Modelling of Compensation Grouting ..........................29
2.6 SUMMARY.....................................................................................................30 CHAPTER 3 GEOLOGY, TUNNELLING AND INSTRUMENTATION ..................32
3.1 INTRODUCTION ...........................................................................................32
3.2 PROJECT DESCRIPTION..............................................................................32
iv
3.3 GEOLOGY AND HYDROLOGY OF THE PERTH REGION......................35
3.4 GEOLOGY AND HYDROLOGY OF THE TUNNEL ROUTE ....................38
3.4.1 Geology...........................................................................................38
3.4.2 Hydrogeology .................................................................................41
3.5 TUNNEL ALIGNMENT AND GROUND CONDITIONS............................44
3.6 SITE INVESTIGATIONS ...............................................................................45
3.7 EARTH PRESSURE BALANCE TUNNEL BORING MACHINE...............48
3.7.1 Ground Anchor Detector.................................................................49
3.7.2 Special Cutters ................................................................................51
3.7.3 Operation in Curved Alignments ....................................................51
3.7.4 Ground Conditioning System .........................................................52
3.7.5 Back Fill Grout System...................................................................52
3.7.6 Advanced TBM Operation Monitoring System..............................52
3.7.7 Muck Volume Measuring System ..................................................52
3.7.8 Internal Grout Ports.........................................................................53
3.7.9 Compressed Air Work Facility .......................................................53
3.8 EPB-TBM TUNNELLING PROCEDURE.....................................................53
3.9 GEOTECHNICAL INSTRUMENTATION AND MONITORING ...............54
3.10 SCHEDULING OF TUNNEL CONSTRUCTION .........................................56 CHAPTER 4 SOIL CHARACTERISATION .................................................................59
4.1 INTRODUCTION ...........................................................................................59
4.2 SUMMARY OF DATA ON SPEARWOOD SAND ......................................59
4.3 LABORATORY INVESTIGATION ON PERTH FORMATION .................63
4.4 SOIL CLASSIFICATION ...............................................................................65
4.4.1 Soil Classification from in-situ Tests..............................................65
4.4.2 Classification based on Laboratory Tests .......................................68
4.4.3 Classification based on Soil Composition ......................................70
4.5 COMPRESSIBILITY ......................................................................................74
4.6 EFFECTIVE STRESS STRENGTH ...............................................................76
4.6.1 Triaxial Tests ..................................................................................76
4.6.2 Simple Shear Tests..........................................................................79
v
4.6.3 Undrained Shear Strength ...............................................................80
4.7 STIFFNESS .....................................................................................................83
4.8 CONCLUSIONS..............................................................................................86
4.8.1 Spearwood sand ..............................................................................86
4.8.2 Perth Formation...............................................................................86 CHAPTER 5 SURFACE SETTLEMENT - GREENFIELD SITE ...............................89
5.1 INTRODUCTION ...........................................................................................89
5.2 GROUND CONDITION .................................................................................89
5.2.1 Ground Condition South of Track 1 ...............................................91
5.2.2 Ground Condition North of Track 5 ...............................................94
5.3 TUNNELLING ................................................................................................97
5.4 INSTRUMENTATION ...................................................................................97
5.4.1 Rail Settlement Points .....................................................................97
5.4.2 Electro Level Beams (EL Beams)...................................................98
5.5 FIELD MEASUREMENT.............................................................................102
5.5.1 Rail Settlement Points (RSPs).......................................................103
5.5.2 EL Beams......................................................................................108
5.5.3 Final Transverse Settlement Troughs ...........................................110
5.5.4 Longitudinal Settlement Profile ....................................................116
5.6 COMPARISON OF TRANSVERSE SETTLEMENT TROUGHS WITH GAUSSIAN APPROACH .............................................................................117
5.7 DISCUSSION ................................................................................................120
5.7.1 Factors Contributing to Heave ......................................................121
5.7.2 Factors Contributing to Settlement ...............................................124
5.7.3 Nature of Settlement Trough.........................................................126
5.7.4 Relationship between i , Tunnel Depth and Tunnel Diameter......128
5.8 SUMMARY...................................................................................................129 CHAPTER 6 GREENFIELD SETTLEMENT-NUMERICAL MODELLING .........131
6.1 NUMERICAL MODELLING .......................................................................131
6.2 SOIL MODELS .............................................................................................131
6.2.1 Hardening Soil Model (HS) ..........................................................131
6.2.2 Hardening Soil Model with Small Strain Stiffness (HSSmall).....133
6.2.3 Mohr-Coulomb Model (MC) ........................................................134
vi
6.3 PARAMETER SELECTION.........................................................................135
6.3.1 Hardening Soil Model (HS Model)...............................................135
6.3.2 Hardening Soil Model with Small Strain Stiffness (HSSmall Model) 139
6.3.3 Mohr Coulomb Model (MC) ........................................................139
6.4 TWO DIMENSIONAL FE ANALYSIS .......................................................140
6.4.1 Hardening Soil Model (HS Model)...............................................143
6.4.2 Hardening Soil Model with Small Strain Stiffness (HSSmall Model) 146
6.4.3 Mohr-Coulomb Model ..................................................................146
6.5 COMPARISON OF THE PREDICTIONS USING DIFFERENT SOIL MODELS .......................................................................................................148
6.6 THREE DIMENSIONAL ANALYSIS (WITH HS MODEL)......................151
Input Parameters ...........................................................................................154
6.6.1 Transverse Settlement Profile .......................................................155
6.6.2 Longitudinal Settlement profile ....................................................158
6.7 COMPARISON OF OBSERVED AND PREDICTED SETTLEMENT TROUGHS.....................................................................................................161
6.7.1 Transverse Settlement Trough ......................................................161
6.7.2 Longitudinal Settlement Trough ...................................................165
6.8 DISCUSSION ................................................................................................166
6.8.1 Effect of K0 on the Predicted Settlement Trough..........................167
6.8.2 Effect of Lining Stiffness Analysis...............................................168
6.8.3 Effect of Stress Reduction around Tunnel ....................................169
6.8.4 Effect of Soil Stiffness on Settlement Trough ..............................172
6.8.5 Stress Changes above the Tunnel during Numerical Analyses ....174
6.8.6 Suggested Approach for Predicting Greenfield Movements (using Plaxis) .................................................................................................176
6.8.7 Interaction Effect of Tunnels ........................................................177
6.9 SUMMARY...................................................................................................179
vii
CHAPTER 7 MALAYSIAN AIRLINES BUILDING- SURFACE AND BUILDING MOVEMENT....................................................................................................................183
7.1 INTRODUCTION .........................................................................................183
7.2 BUILDING DETAILS...................................................................................183
7.3 GROUND CONDITIONS .............................................................................187
7.4 INSTRUMENTATION .................................................................................191
7.4.1 Surface Settlement Pins and Building Settlement Points..............191
7.4.2 EL Beams......................................................................................191
7.5 FIELD MEASUREMENT (SSP AND BSP’) ...............................................192
7.5.1 Final Transverse Settlement Troughs ...........................................193
7.6 BUILDING MOVEMENT (EL BEAMS).....................................................194
7.7 EFFECT OF SOIL STRUCTURE INTERACTION.....................................196
7.8 NUMERICAL ANALYSIS ...........................................................................198
7.8.1 2D FE Analysis .............................................................................199
7.8.2 Transverse Surface Settlement Trough .........................................200
7.8.3 Building Settlement.......................................................................201
7.9 3D ANALYSIS ..............................................................................................202
7.9.1 Transverse Movement of the Building..........................................204
7.9.2 Longitudinal Surface Movement ..................................................205
7.10 DISCUSSION ................................................................................................206
7.10.1 Influence of Building Stiffness on Settlement Trough .................207
7.10.2 Influence of Soil Type or Stiffness on Settlement Trough ...........208
7.10.3 Settlement, Bending Moment and Horizontal Strain Induced on Building due to Different Volume Losses .....................................................209
7.11 CONCLUSIONS............................................................................................212 CHAPTER 8 COMPENSATION GROUTING– WALSH BUILDING .....................215
8.1 INTRODUCTION .........................................................................................215
8.2 BUILDING PROTECTION ..........................................................................215
8.2.1 Compensation Grouting ................................................................216
8.2.2 Building Details and Arrangement of Grouting............................217
8.3 GROUND CONDITION ...............................................................................223
8.4 BUILDING MOVEMENT AFTER CONDITION PHASE GROUTING....227
8.5 TRANSVERSE SETTLEMENT TROUGH (AFTER TUNNELLING).......230
viii
8.5.1 South Side of Building (non-grouted area) ...................................230
8.5.2 North Side of Building (grouted area) ..........................................233
8.5.3 Comparison of Surface Movement at Grouted and Non-Grouted area 234
8.5.4 Building Settlement ......................................................................235
8.6 NUMERICAL MODELLING .......................................................................236
8.6.1 Building Movement after Condition Phase Grouting ...................238
8.6.2 Building Movement after Active Grouting (after tunnelling).......239
8.7 CONCLUSIONS............................................................................................240 CHAPTER 9 OBSERVATIONS, CONCLUSIONS AND RECOMMENDATIONS 241
9.1 INTRODUCTION .........................................................................................241
9.2 OBSERVATIONS AND CONCLUSIONS ..................................................242
9.2.1 Soil Characterisation.....................................................................242
9.2.2 Greenfield Ground Movement ......................................................243
9.2.3 Numerical Modelling of Greenfield Movement ...........................244
9.2.4 Soil Structure Interaction Effect ...................................................246
9.2.5 Numerical Modelling of Soil Structure Interaction ......................246
9.2.6 Compensation Grouting and Applicability of Numerical Modelling 247
9.3 CONTRIBUTIONS TO THE FIELD OF KNOWLEDGE ...........................247
9.4 RECOMMENDATIONS FOR FUTURE RESEARCH................................248 REFERENCES .................................................................................................................251
ix
TABLE OF FIGURES
Figure 1-1 T Bored Tunnels and Research Sites in the Perth CBD.................................. 2
Figure 2-1 Source of Ground Loss (Attewell, 1978) ......................................................... 9
Figure 2-2Observed Failure Mode based on Centrifuge Model Tests............................. 10
Figure 2-3 Volume Loss Calculated from Soil Displacements Compared to Tunnel
Volume Loss (Marshall, 2009).................................................................... 11
Figure 2-4 Profile of Mobilised Lateral Earth Pressure Coefficient on Tunnel
centre line at Different Volume Losses (Jacobsz, 2002)............................. 12
Figure 2-5 Geometry of the tunnel induced settlement trough (after Attewell et
al.,1986)....................................................................................................... 13
Figure 2-6 Transverse Settlement Trough........................................................................ 14
Figure 2-7 Longitudinal Settlement Profile (Franzius, 2003).......................................... 19
Figure 2-8 Predicted Greenfield settlement and Observed Building Settlement of
Mansion House, London (after Frischmann et al., 1994) ........................... 20
Figure 2-9 Building and Subsoil Movement of Buildings in Frankfurt Clay (after
Breth and Chambosse, 1974)....................................................................... 22
Figure 2-10 Building Deformation above Single Tunnel (Mair et al., 1996) .................. 23
Figure 2-11 Layout of Mansion House and Location of Tunnel (Frischmann et al.,
1994)............................................................................................................ 24
Figure 2-12 Settlement profiles for East and West Walls of Mansion House
(Frischmann et al., 1994) ............................................................................ 25
Figure 2-13 Comparison of Damage Estimation Criterion and Damage Levels
(Son and Cording, 2005) ............................................................................. 27
x
Figure 2-14 Example of Interaction Diagram to Assess the Damage for Isotropic
Beam with L/H =1 (Burland, 1995) .............................................................28
Figure 3-1, Bored Tunnel Alignment................................................................................33
Figure 3-2 Eustatic Sea Level Curve for the Past 270,000 Years with Oxygen
Isotope Stages Indicated (Gozzard, 2007)....................................................35
Figure 3-3 Perth Region Generalized Geomorphology (after B Gozzard, 2007) .............37
Figure 3-4 Perth Region Generalized Geology.................................................................38
Figure 3-5 Schematic Geology of the Project Route (Hudson-Smith and Grinceri,
2007).............................................................................................................39
Figure 3-6 Schematic Section Showing Stratigraphic Relationships of Superficial
Formations in the Vicinity of Perth..............................................................40
Figure 3-7 Piezometric Profiles at South End of William Street Station (Leighton
et al., 2004)...................................................................................................42
Figure 3-8 Piezometric Profile along the Project Route (Johnson, I.D., et al.,2007) .......43
Figure 3-9 Old Lakes near Project Alignment ..................................................................45
Figure 3-10 Specifications of EPB-TBM..........................................................................50
Figure 3-11 EPB Tunnel Boring Machine- View on Cutter head.....................................51
Figure 3-12 Schedule of Tunnelling South of William Street Station..............................56
Figure 3-13 Schedule of Tunnelling North of William Street Station..............................57
Figure 4-1 SPT N vs. Depth..............................................................................................61
Figure 4-2 Typical Gradation Curve of the Dune Sand (after Andrews, 1971)................61
Figure 4-3 Relationship between G0 (from SCPTs) and qc Observed in Perth Sand ........62
Figure 4-4 Relationship between G0 (from SCPTs) and qc Observed for Perth
Formation Sand and Spearwood Sand .........................................................63
Figure 4-5 Typical CPT Data at Test Location.................................................................66
Figure 4-6 Ic and ID Indices at the Site..............................................................................68
Figure 4-7 Classification Data; Separate Symbols for each Bore Holes ..........................69
xi
Figure 4-8 Activity Chart and Location of Tested Soil Samples ..................................... 70
Figure 4-9 Colour changes due to Iron on Soil Samples ................................................. 72
Figure 4-10 SEM Images ................................................................................................. 73
Figure 4-11 Oedometer Data for Three Samples ............................................................. 75
Figure 4-12 Stress Paths Measured in CIU Triaxial Compression Tests......................... 77
Figure 4-13 (a) Values of t and s’ at Failure for all Triaxial Tests, (b) Dependence
of Triaxial Friction Angle on Fines Content ............................................... 78
Figure 4-14 Stress Paths Measured in Undrained Simple Shear...................................... 80
Figure 4-15 Undrained Strength Ratios Plotted as a Function of (a) consolidation
stress level and (b) Fines Content................................................................ 81
Figure 4-16 Variation of A (undrained strength ratio at OCR=1) with Fines
Content ........................................................................................................ 82
Figure 4-17 Stiffness Data Measured in CIU Triaxial Compression Tests ..................... 84
Figure 5-1 Geotechnical Investigation Locations near the Railway Tracks .................... 90
Figure 5-2 Borehole Information and Stratigraphical Profile South of the Railway
Tracks .......................................................................................................... 92
Figure 5-3 CPT Profile South of Track 1......................................................................... 93
Figure 5-4 Idealised Soil Profile South of Railway Tracks ............................................. 93
Figure 5-5 Bore Hole Information and Stratigraphical Profiling North of the
Railway Tracks............................................................................................ 95
Figure 5-6 CPT Profile North of Track 5......................................................................... 96
Figure 5-7 Idealised Soil Profile North of Railway Tracks ............................................. 96
Figure 5-8 Variations in the SSP Data over a Period of Two Months for Track3
and Track 5.................................................................................................. 98
Figure 5-9 Typical View of a Horizontal EL Beam......................................................... 99
Figure 5-10 Schematic View of Horizontal EL Beam..................................................... 99
Figure 5-11 Longitudinal and Transverse EL Beams on the Track ............................... 101
Figure 5-12 Closer View of EL Beams on the Track..................................................... 101
xii
Figure 5-13 Schematic View of EL Beam on Railway Tracks.......................................102
Figure 5-14 Transverse Settlement Trough due to Tunnel 1 Boring (RSP) ...................104
Figure 5-15 Transverse Settlement Trough due to Tunnel 2 Boring (RSP) ...................106
Figure 5-16 Relationship between Maximum Heave and Maximum Settlement
Deduced from RSPs ...................................................................................108
Figure 5-17 Transverse Settlement Trough due to Tunnel 1 Boring (EL Beam) ...........109
Figure 5-18 Transverse Settlement Trough due to Tunnel 2 Boring (ELBeam) ............110
Figure 5-19 Final Transverse Settlement Trough for Three Tracks due to Tunnel 1 .....111
Figure 5-20 Final Transverse Settlement Trough for Three Tracks due to Tunnel 2 .....112
Figure 5-21 Transverse Settlement Troughs due to Tunnel 1 and Tunnel 2...................113
Figure 5-22 Combined Transverse Settlement Troughs after Tunnel 2 Boring .............114
Figure 5-23 Typical Longitudinal Profile for Tunnel 1 Boring......................................116
Figure 5-24 Linear Regression Lines for Tunnel 1 Boring............................................118
Figure 5-25 Linear Regression Lines for Tunnel 2 Boring.............................................119
Figure 5-26 Estimated Face Pressure along Northern Bored Tunnel (after Sigl and
Yamazaki, 2007) ........................................................................................121
Figure 5-27 Variation of FP and Horizontal Effective Stress during Tunnel 1 and
Tunnel 2 Boring (Note Tracks 1, 3 & 5 are at approximate chainages
of 138m, 152m and 177m for Tunnel 1 and 146m, 164m and 192m
for Tunnel 2)...............................................................................................122
Figure 5-28 Variation of Grout Volume / Ring .............................................................123
Figure 5-29 Variation of GP and Horizontal Effective Stress during Tunnel 1 and
Tunnel 2 Boring .........................................................................................124
Figure 5-30 Normalised Field Settlement Troughs for Tunnel 1 ...................................127
Figure 5-31 Variation of i with z0 for Tunnels in Sand and Gravels (Mair and
Taylor, 1997) ..............................................................................................128
xiii
Figure 5-32 Relation between i , Tunnel depth and Diameter for Different Ground
Conditions (Peck, 1969) ............................................................................ 129
Figure 6-1 Figure showing the Relationship between G0ref and Strain at Reference
Stress of 100 kPa ....................................................................................... 137
Figure 6-2 North Profile Showing Mesh and Tunnels for 2D FE Analysis................... 141
Figure 6-3 South Profile Showing Mesh and Tunnels for 2D FE Analysis................... 141
Figure 6-4 Transverse Settlement Trough for North and South profiles for Volume
Losses of 0.25% & 0.19%; HS model....................................................... 144
Figure 6-5 Variation of Excess Pore Pressure for North Profile (vl=0.25%) ................ 145
Figure 6-6 Variation of Excess Pore Pressure for South Profile (vl=0.25%) ................ 145
Figure 6-7 Transverse Settlement Trough for North and South profiles for Tunnel
1 (Volume Losses of 0.15% & 0.25%); MC with E=E50.......................... 146
Figure 6-8 Final Transverse Settlement Trough for North and South Profiles; MC
with E=Eur ................................................................................................. 147
Figure 6-9 Transverse Settlement Trough for South Profile; MC with E=Eur............... 148
Figure 6-10 Comparison of the Transverse Settlement Trough Predicted using
Different Soil Models ................................................................................ 149
Figure 6-11 Deformed Mesh using MC (Eur) Model ..................................................... 150
Figure 6-12 Deformed Mesh of the Geometry using HS Model ................................... 150
Figure 6-13 Deformed Mesh of the Geometry using HSSmall Model .......................... 150
Figure 6-14 Geometric Model of the Tunnel Excavation .............................................. 152
Figure 6-15 3D Mesh for the Plaxis Analysis North of the Rail Lines......................... 152
Figure 6-16 3D Mesh for the Plaxis analysis South of the Rail Lines........................... 153
Figure 6-17 Schematic View of the Modelling of Tunnel Boring ................................. 154
Figure 6-18 Deformed Mesh after Excavating Tunnel 1 (North profile, vl=0.25%)..... 155
Figure 6-19 Deformed Mesh after Excavating Tunnel 1 and Tunnel 2 (North
profile, VL=0.25% &0.19%) ..................................................................... 156
xiv
Figure 6-20 Deformation Plane after the Excavation of Tunnel 1 (North profile,
VL VL =0.25%)...........................................................................................156
Figure 6-21 Deformation Plane after the Excavation of Tunnel 1 and Tunnel 2
(North profile, VL =0.25% &0.19%)..........................................................156
Figure 6-22 Transverse Settlement Trough of North and South Profile for Volume
Losses of 0.25% & 0.19%..........................................................................158
Figure 6-23 Typical Longitudinal Settlement Trough ....................................................159
Figure 6-24 Boundary Effect for Longitudinal Trough .................................................159
Figure 6-25 Settlement Trough with Different FP and GP.............................................160
Figure 6-26 Longitudinal Settlement Trough for Different GP and FP..........................161
Figure 6-27 Comparison between Settlement Troughs Predicted for North Profile.......162
Figure 6-28 Comparison between Settlement Troughs Predicted for South Profile.......163
Figure 6-29 Comparison of Normalised Settlements for Tunnel 1.................................165
Figure 6-30 Predicted and Observed Normalised Longitudinal Settlement Trough ......166
Figure 6-31 Settlement Trough with Different K0 Value for North and South Soil
Profile .........................................................................................................168
Figure 6-32 Variation of Surface Movements for Different Lining Stiffness ................169
Figure 6-33 Soil Profile and Location of Tunnel for Parametric Study..........................170
Figure 6-34 Settlement Trough with Different K0 around the Tunnel............................172
Figure 6-35 Settlement Profile with Different Stiffness .................................................173
Figure 6-36 Mobilised Horizontal Earth Pressure ..........................................................173
Figure 6-37 Mobilised Lateral Earth Pressure Coefficient along the Tunnel axis.........175
Figure 6-38 Mobilised Stress and Km near the Ground Surface at RL=10.3m
(section B-B in Figure 6-33) ......................................................................176
Figure 6-39 Comparison of Predicted and Measured Settlement Trough ......................177
Figure 6-40 Interaction Effect of Tunnels using South Profile.......................................178
xv
Figure 6-41 Interaction Effect of Tunnels using North Profile...................................... 178
Figure 7-1 Aerial View of MAS Building ..................................................................... 184
Figure 7-2 Schematic View of the Building and Location of Tunnels .......................... 185
Figure 7-3 Front View of MAS Building....................................................................... 186
Figure 7-4 View Opposite MAS Building ..................................................................... 186
Figure 7-5 Ground and First Floor Plan for MAS Building .......................................... 187
Figure 7-6 Geotechnical Investigation Locations near MAS Building.......................... 188
Figure 7-7 Borehole Information and Stratigraphical Profile Close to the MAS
Building ..................................................................................................... 190
Figure 7-8 CPT Profile................................................................................................... 190
Figure 7-9 Soil Profile and Location of Tunnel near MAS Building ............................ 190
Figure 7-10 EL Beams on the Wall with Transmitter on Each Beam ........................... 192
Figure 7-11 Ground and Building Movement due to Tunnel 1 and Tunnel 2 ............... 193
Figure 7-12 Transverse Surface Settlement Trough for Tunnel 1 and Tunnel 2 ........... 194
Figure 7-13 Movement of Building at Various Times during Tunnelling..................... 195
Figure 7-14 Transverse Building Movement for Tunnel 1 and Tunnel 2 ...................... 196
Figure 7-15 Linear Regression Analysis for Tunnel 1 and Tunnel 2............................. 197
Figure 7-16 Normalised Settlement for Tunnel 1 and Tunnel 2 .................................... 197
Figure 7-17 2D Mesh Showing Tunnels and Building .................................................. 199
Figure 7-18 Observed and Predicted Settlement Trough............................................... 201
Figure 7-19 Measured vs Predicted Settlement of the Building .................................... 202
Figure 7-20 3D Mesh for the Geometry........................................................................ 203
Figure 7-21 Deformed Mesh after Tunnel Boring ......................................................... 203
Figure 7-22 Predicted Movement of the MAS Building as the TBM Passes ................ 204
Figure 7-23 Schematic View of Building and Direction of TBM ................................. 204
Figure 7-24 Transverse Settlement Observed and Predicted by FE Analysis ............... 205
Figure 7-25 Longitudinal Settlement Profile from 3D Analysis.................................... 206
xvi
Figure 7-26 Schematic View of Geometry in z Direction ..............................................206
Figure 7-27 Surface Settlement Trough with Different Building Stiffness ....................208
Figure 7-28 Surface Settlement Trough with Different soil type ...................................209
Figure 7-29 Building Settlement due to Different Volume Losses ................................210
Figure 7-30 Predicted BM due to Tunnelling for Different Volume Losses ..................211
Figure 7-31 Horizontal Strain induced by Tunnel 1 Boring on MAS ............................212
Figure 8-1 Aerial View of the Protected Buildings ........................................................216
Figure 8-2 Front View of Walsh Building ......................................................................218
Figure 8-3 Schematic View of the Location of Building and Tunnel.............................219
Figure 8-4 Church Opposite to Walsh Building .............................................................220
Figure 8-5 Tunnel Alignment and Geotechnical Investigation Locations near
WALSH Building.......................................................................................221
Figure 8-6 Typical Cross-section of Grouting Arrangement ..........................................222
Figure 8-7 Site Setup (top) and Schematic Layout for Grouting (bottom).....................222
Figure 8-8 Schematic View of the Protected Buildings, Grout Ports and Location
of EL Beams on the Building.....................................................................223
Figure 8-9 Borehole Information and Stratigraphical Profile Close to WALSH
Building......................................................................................................225
Figure 8-10 CPT Profile Close to Walsh Building .........................................................226
Figure 8-11 Soil Profile and Location of Tunnel near WALSH Building......................227
Figure 8-12 Movement of Building due to Condition Phase Grouting ..........................228
Figure 8-13 Variation of Grout Volume along the Transverse Direction of the
Building......................................................................................................229
Figure 8-14 EL Beam Location and Zone of Influence ..................................................229
Figure 8-15 Settlement Troughs at Non-Grouted Area for Tunnel 1 and Tunnel 2 .......231
Figure 8-16 Normalised Settlement for Tunnel 1 and Tunnel 2 .....................................232
xvii
Figure 8-17 Location of Tunnels and the Buildings at Non-grouted Area .................... 233
Figure 8-18 Surface movement at Grouted Location (from SSP and BSP data) ........... 234
Figure 8-19 Surface Settlements Due to Tunnel 1 Boring at Grouted and Non-
Grouted Locations ..................................................................................... 235
Figure 8-20 Building Movement due to Grouting and Tunnel 1 Boring ....................... 236
Figure 8-21 Mesh Showing the Location of the Grouting ............................................. 237
Figure 8-22 Observed and Predicted Movement after Condition Phase Grouting. ....... 238
Figure 8-23 Observed and Measured Movement of Building due to Tunnel 1 ............. 239
xviii
LIST OF TABLES
Table 3-1 Construction Methods of the Different Sections of the New Metro Rail
City Project (Part 4B Geotechnical Interpretive Report, 2004) ...................34
Table 3-2 Phases of Site Investigation..............................................................................46
Table 3-3 Main Characteristics of the EPB-TBM ............................................................49
Table 3-4 – Instrument Types and Quantities...................................................................55
Table 3-5 Schedule of Tunnel Construction .....................................................................56
Table 4-1 Relative Phase Composition (wt.%) Derived from XRD Data ........................71
Table 4-2 Properties of Soil Samples Tested in 1-D Compression..................................74
Table 4-3 Approximate Values of ξ for Clays at the St. Georges Terrace Site ................85
Table 5-1 Variation of Heave and Settlement for each Track after the Tunnel
Boring.........................................................................................................107
Table 5-2 Settlement Details of Three Tracks ................................................................115
Table 5-3 Estimated i Values ..........................................................................................120
Table 5-4 Estimated i and K Values at the Three Track Locations ..............................127
Table 6-1 Hardening Soil Model Parameters for North Profile......................................138
Table 6-2 Hardening Soil Model Parameters for South Profile......................................138
Table 6-3 Mohr-Coulomb Model Parameters for North Profile .....................................139
Table 6-4 Mohr-Coulomb Model Parameters for South Profile .....................................140
Table 6-5 Tunnel Details.................................................................................................141
Table 6-6 Volume Losses Specified in Numerical Analyses..........................................142
Table 6-7 Main Features of the Mesh .............................................................................153
xix
Table 6-8 Face Pressure, Grout Pressure and TBM Thrust for 3D Analyses ................ 155
Table 6-9 Input Volume Loss and the Out put Volume Losses..................................... 163
Table 6-10 Combinations of Stress History used for Predicting Settlement Profile...... 167
Table 6-11 Vertical Movement of Tunnel Crown.......................................................... 169
Table 6-12 Different Cases for the Analyses ................................................................. 170
Table 7-1 Surface Settlement Details at MAS Building ................................................ 194
Table 7-2 Input Parameters for the Building Components ............................................ 198
Table 7-3 Face Pressure, Grout Pressure and TBM Thrust used for 3D Analyses........ 203
Table 8-1 Summary of Settlement Troughs at Non-Grouted Area of Walsh
Building ..................................................................................................... 231
Table 8-2 Details of the Building Component ............................................................... 237
xx
xxi
ACKNOWLEDGEMENT
It has been a pleasure and privilege to be part of Geotechnical Research Group at The
University of Western Australia. The research for this dissertation was carried out in the
School of Civil and Resources Engineering during 2005 -2010 and was supported by the
University Postgraduate Award (UPA) and Othman Frank Blakey Scholarship, which are
gratefully acknowledged.
There are many people to thank for their support and encouragement, without whom
this thesis would not have been possible.
First of all, I would like to express my sincere gratitude to my supervisor, W/Prof. Barry
Lehane for his valuable discussions, advices, support and consideration throughout this
research. I have been very fortunate to work with him. I sincerely thank you Barry for
your patience, attention to detail and always having time for discussion.
I would like to thank Binaya, Claire, Natalie and Christine in the Geotechnical
laboratory for helping and making my life easy with laboratory testing. I also thank all
the staff in the general workshop and electronic workshop for their untiring help and
enthusiasm in finishing the job on time.
The help and support provided by Jane, Simone, Monica, Eileen, Lisa and Sharon in the
Civil engineering and COFS office is also acknowledged. My special
acknowledgements are expressed to Wenge and Keith for their friendly and skilful IT
support throughout this research.
I say a great thank you to Natusha for helping me during my stay here. I aso thank
Mostafa for his time and patience for helping me with my laboratory study and lending
me the Plaxis dongle.
I am very grateful for the company of all the research associates, postgraduate students
and visitors in Civil Engineering as well as in COFS, without the support of everybody
xxii
the life would be difficult. I specially thank Lina, Shazzad, Booning, Tarrant, Xuelin,
Bao and Kevin for their valuable help, advice and encouragement whenever in need.
I am very much indebted to Selina for taking care of my children during my research.
She was there for me whenever I needed help. Without you I wouldn’t have been able to
do my research so relaxingly. I also thank Siraj and Sajid for their help and company.
I specially thank Fiona Chow for providing me with journal papers, books and thesis
whenever in need. I also acknowledge the help and support provided by Susan
Governec, Doug Stewart, Eric Hudson-Smith, Raghu, Peter McGough, Michael
Grinceri, Logan, Babu, Suman and Matt Williams.
The help from Leighton Kumagai Joint Venture (LKJV) by providing instrumentation
monitoring data is also greatly acknowledged. I also acknowledge the funding providing
by an Australian Research Council (ARC) linkage grant in association with LKJV to
support this research.
I am also very grateful and sincerely acknowledge the time and effort of all the
examiners evaluating this thesis.
I sincerely thank my husband Joyis and children Joshia,
Denzel and Paulus for their untiring support and
consideration throughout my research. I wouldn’t have
been able to finish this research without Joyis’s help,
patience and support.
I would like to thank my parents, brothers and sister-in-laws for their constant support
and effort throughout this research. I also thank Sony Aunty for coming and helping me
during my delivery time and helping me with the kids. I specially thank my mother-in-
law Rose for her constant prayer for me and support. I also thank all my in- laws for
their love and affection for me and supporting me.
Last but not least I thank almighty God for bestowing me with knowledge and wisdom
to complete the study successfully. When ever I was in need He gave it to me through
somebody.
xxiii
DECLARATION
I hereby declare that, except where specific reference is made to the works of others, the
contents of this dissertation are original and have never been submitted, in part or as a
whole, to any other University for any degree, diploma or other qualifications. This
dissertation is the result of my own work and includes nothing which is the outcome of
work done in collaboration. This dissertation contains no more than 70,000 words and
180 figures.
Gima V. Mathew
October 2010
xxiv
xxv
SYMBOLS AND ABBREVIATIONS
Symbols
c' Cohesion
D Outer tunnel diameter
D1 Outer diameter of the lining
D2 Diameter of the cutter face
e In situ void ratio
emax Maximum void ratio
E Modulus of elasticity of concrete
E’sec= E Drained secant Youngs moduli of soil
E0 Youngs moduli at very small strains
E50 ref Secant stiffness in standard drained triaxial test at reference stress
Eoedref Tangent stiffness for primary oedometer loading at reference stress
Eurref Unloading/reloading stiffness
EA Axial stiffness
EI Bending stiffness
Fr Friction ratio
fs Friction sleeve measurement
G Secant shear modulus
xxvi
G0ref Small strain shear modulus at reference stress
Ic Soil behaviour type index
ID DMT material index
i Transverse horizontal distance from centre-line of the tunnel to
the point of inflection of the settlement trough (also ix)
k_x, k_y & k_z Permeability of the soil in the x, y and z directions
K Trough width parameter (also K1 and K2)
K0nc K0 value for normal consolidation
K0 Coefficient of earth pressure at rest
Km Mobilised earth pressure coefficient
L - Length of each ring
LL Liquid limits
m Power for stress-level dependency of stiffness
Nk Cone factor
p’ Mean effective stress
pa Atmospheric pressure or reference stress
p0 Lift-off pressure
pref Reference confining pressure
p1 Pressure measured at a membrane expansion of 1.1 mm
p’0 Initial mean effective stress
q Deviator stress
qc CPT end resistance
xxvii
qf Maximum deviator stress
Smax Maximum settlement
su Undrained shear strength
Sv Settlement at offset y from the tunnel centre line
S Settlement at a distance x from tunnel centre line
sutc Undrained shear strength in triaxial compression test
suss Undrained shear strength in simple shear test
u0 Ambient pore pressure.
Uy Vertical movement
Ux Horizontal movement
VL Volume loss
Vs Shear wave velocity
Vs Excavated volume
w Water content
y Horizontal distance from the tunnel centre line
Z0 Depth of the tunnel axis below the ground surface
φ' Friction angle
ψ Peak dilation angle
φcv Critical state friction angle
ψm Mobilised dilation angle
φm Mobilised friction angle
xxviii
γsat Saturated unit weight of soil
γunsat Unsaturated unit weight of soil
ψ Angle of dilatancy (o)
ν Poisson’s ratio
ρ Mean density
ξ Constant varies with the nature and age of the deposit,
τxy Shear stress
(Δ/L) Deflection ratio
ν Poissons ratio
γ Shear strain
νur Poisson’s ratio for unloading reloading
σ’3 Minor and intermediate principal effective stresses
σv0 Total vertical stress
σ’v Vertical effective stress.
σ’vy Vertical yield stress
σ’vc Vertical consolidation stress
Abbreviations
1-D One dimensional
AHD Australian Height Datum (Mean Sea Level)
xxix
BSP Building settlement points
CF Coarse fraction
CPT Cone penetration test
DMT Dilatometer test
FC Fine content
POP Past overburden pressure
OCR Overconsolidation ratio
PI Plasticity index
RSP Rail settlement points
SSP Surface settlement pins
SBT Soil behaviour type
TAM Tubes-a-manchettes
xxx
1
CHAPTER 1 INTRODUCTION
1.1 BACKGROUND
The growth of many cities has resulted in the need for underground structures such as
tunnels to provide efficient transportation, water supply, sewage disposal and
communications. To avoid any damage to the overlying structures, efficient and
economic tunnel design and construction methods should be implemented. There are
empirical, numerical and analytical methods to predict the movement associated with
tunnelling. When tunnels are constructed in an urban area, it is important, at the design
stage, that the response of nearby structures can be predicted with sufficient accuracy.
These predictions will affect the choice of tunnelling method and dictate the form and
scope of potential ground improvement measures. The current deformation prediction
approaches are often conservative and can lead to unnecessary expenditure for the
protective measures. A more reliable design method would resolve issues such as
excessive cost and damage to surface or sub surface facilities. The most widely used
‘Gaussian empirical method’ has been shown to provide good estimates of the shape
and size of the settlement profile in ‘greenfield’ conditions (i.e. where no structural
interaction effects are present), this method cannot be used to assess structural
movements associated with the tunnelling. The Finite Element (FE) method is currently
the most popular approach to predict the surface and building movement associated with
tunnelling.
1.2 SCOPE OF THIS RESEARCH
The Perth MetroRail project connecting Perth to Mandurah was a major infrastructural
investment by the Western Australian State Government. In the Perth Central Business
District (CBD), the project consisted of two bored (6.9m outer diameter) underground
rail tunnel, open dive and cut-and-cover tunnel sections and two below ground stations
(Esplanade and William Street Station); these elements are shown in Figure 1-1.
Leighton Kumagai Joint Venture (LKJV) carried out the tunnelling work in the CBD.
2
The stratigraphy of the tunnel route consists mainly of normally consolidated dune sand
(Spearwood Sand) overlying the overconsolidated layers of alluvial silts, clays and
sands (Perth Formation), which are underlain by shale/ siltstone (Kings Park
Formation). Earth Pressure Balanced Tunnel Boring Machine (EPB-TBM) was used to
bore the two tunnels.
Figu
re 1
-1 T
Bor
ed T
unne
ls a
nd R
esea
rch
Site
s in
the
Pert
h C
BD
Gre
enfie
ld si
te
Wal
sh M
AS
Chapter 1 Introduction
3
Although significant portions of the bored tunnels went through the overconsolidated
Perth Formation, no systematic laboratory investigation of the Perth Formation has been
published to date. The design and construction of this project was constrained by the
need to minimise the effect of tunnelling on the existing buildings. As the tunnel was
passing directly underneath some of the buildings along the tunnel route, the potential
for imposition of large ground distortions on these buildings was very high. These
buildings were on shallow footings and compensation grouting was implemented under
some of the buildings to mitigate the effect of tunnelling. Hence the main objectives of
this research are;
1. To study the properties of the Perth Formation in detail by conducting state
of the art laboratory tests on undisturbed soil samples collected from the
research site. The laboratory measurements are subsequently related and
calibrated with in-situ test data to assist in the assignment of material
properties for the numerical analyses.
2. To investigate the effect of EPB tunnelling in the Perth soils. This is attained
by interpreting extensive instrumentation data collected from three adjacent
locations at the greenfield site shown on Figure 1-1. The nature of the
settlement troughs is assessed in detail and compared with the observations
made in the similar ground conditions around the world.
3. To examine the suitability of FE methods to predict the movement
associated with the tunnelling especially in the mixed stratigrapghy present
in Perth CBD. This is achieved by carrying out both 2D and 3D finite
element analyses using the popular Plaxis program.
4. To study the effect of tunnel construction on nearby buildings as well as the
influence of buildings on the observed pattern of surface or building
movements. The vertical ground and building movement at two multistorey
building locations are analysed in detail to study the soil structure interaction
effect.
5. To investigate the applicability of both two dimensional (2D) and three
dimensional (3D) numerical modelling in replicating the soil-structure
interaction effect as observed in the field.
4
6. To study the effectiveness of compensation grouting in sand to reduce the
soil volume loss associated with tunnelling. This is achieved by comparing
the settlement troughs at grouted and non-grouted areas close to each other.
7. To examine the applicability of FE modelling to model the compensation
grouting.
1.3 RESEARCH SITES
The research mainly focused on five monitored sites along the tunnel route and they are,
i) greenfield sites (three adjacent locations in railway track area) ii) Malaysian Airlines
(MAS) building and iii) Walsh building; the locations of the five sites are indicated in
Figure 1-1. The instrumentation was installed and monitored by LKJV. However, at the
MAS building, the author installed EL beams in addition to the instrumentation installed
by LKJV to monitor the movement of the building; LKJV also recorded these EL beam
data. Analyses and interpretation of all the instrumentation data presented here were
carried out independently by the author. The tunnelling took place during the initial
period of the PhD study.
Details of each of the monitored sites are given below.
(i) Greenfield Site (Railway Tracks): Part of the tunnel went underneath five
existing railway tracks. As there were no buildings around this area, this was
considered as a good location to esimate the greenfield movement. The
tunnels were about 11m below ground level and 14.4m apart (centre to
centre) at this location. Out of five tracks, three tracks (Track 1, Track 3 and
Track5) are considered here for the analysis. The tunnels encountered both
the Perth Formation and Spearwood sand at these locations.
(ii) Malaysian Airlines (MAS) Building: This building (constructed in 1929) is
a framed structure having seven storeys and a basement founded on shallow
footing. Full structural details of the building are not available and
assumptions regarding its structural form are based on visual inspection.
This building was about 6m from the centre line of Tunnel 1. The near by
tunnels were at about 18 m below ground level and 10.2m apart. Most of the
Chapter 1 Introduction
5
tunnel’s cross-section is located in the sand and clay layers of the Perth
Formation at this area.
(iii) Walsh building. The Walsh building is heritage listed and has five storeys
and a basement. This building is a steel framed structure encased in concrete,
with secondary reinforced concrete beams. The building is on shallow
footings. The tunnels’ springlines are at about 17m below ground level and
are 10.6m apart (centre to centre) at south side of the building. The
corresponding measurements at north side of the building are 15.45m and
12m. The tunnels are located primarily in silty and clayey layers of the Perth
Formation at this area. Compensation grouting was implemented over the
northern section of the building to mitigate the effects of tunnelling induced
settlements.
1.4 THESIS STRUCTURE
This thesis consists of nine Chapters. Following the introduction, which is Chapter 1,
Chapter 2 presents a review of relevant literature for the thesis topic. This chapter
covers patterns of soil movement as well as volumetric straining and stress changes
above the tunnel crown, as observed in centrifuge model testing. Different approaches
to predict the tunnelling induced ground movements are also discussed. Soil structure
interaction effects are reviewed as are criteria for assessing movement thresholds for
building damage. Current approaches for numerical modelling of compensation
grouting are also evaluated.
Chapter 3 gives the over all description of the MetroRail project (in the Perth CBD
area), tunnelling method and geology & hydrogeology of the tunnel route. The
characteristics of the TBM used to bore the two tunnels and summary of
instrumentation used to monitor the ground as well as building movement are also
detailed.
All the laboratory tests carried out in the alluvial deposits of the upper horizons of Perth
Formation along with the in situ tests carried out as part of the MetroRail project are
reported in Chapter 4. The laboratory measurements are subsequently related and
calibrated with available in-situ test data to assist in the assignment of material
properties in numerical analyses.
6
The surface settlement (‘greenfield’) troughs induced by boring of the two tunnels are
the main focus of Chapter 5. The extensive instrumentation data at three locations close
to each other are analysed thoroughly and compared with the observations in similar
ground conditions around the world. The applicability of the widely used Gaussian
Method to predict the greenfield troughs in the predominantly sandy soils is also
examined in this Chapter.
In Chapter 6, 2D as well as 3D numerical analyses carried out using Plaxis program are
presented that examine the suitability of this (widely used) program to predict the
vertical surface movement (‘greenfield’) associated with tunnelling. The method of
parameter selection (from the laboratory as well as from the field test) for the numerical
modelling is also discussed in detail. The observations from the comparison of predicted
and measured vertical surface movement are also discussed. The (often predicted) wide
and shallow settlement trough is investigated through FE parametric studies in
combination with data from available centrifuge model tests.
The monitored vertical movement at a multi-storeyed building (MAS) location along
the tunnel route is analysed in detail and discussed in Chapter 7. The influence of
surface structures in modifying the surface and the structural movement and the soil
structure interaction effect is also discussed. Both 2D as well as 3D FE analyses were
carried out to study interaction effects. This Chapter also investigates the influence of
building stiffness and soil type and/stiffness on the settlement troughs through
numerical parametric studies.
Chapter 8 assesses the effectiveness of the compensation grouting (hydraulic fracture)
in sand to reduce the volume loss due to tunnelling. The suitability of Finite Element
(FE) program to model compensation grouting is also evaluated.
The main conclusions drawn from Chapter 4 to 8 are summarised in Chapter 9.
Recommendations for future research are also highlighted.
7
CHAPTER 2 LITERATURE REVIEW
2.1 INTRODUCTION
Bored tunnels are constructed either by (i) Shield Tunnelling or (ii) New Austrian
Tunnelling Method (NATM). In Shield Tunnelling, the Tunnel Boring Machine (TBM)
is used to excavate the tunnel and this technique is usually used in soft ground
conditions to prevent ground collapse. The tail of the TBM supports the lining to be
erected and final lining is placed in position as soon as sufficient length is excavated.
The gap between the soil and lining is grouted immediately to reduce the volume loss.
In NATM, the tunnel is excavated in different parts such as the crown, bench and invert.
After each excavation section, the tunnel contour is stabilised by introducing temporary
lining of sprayed concrete. A final lining is installed later if one is required for long
term. The long term lining is usually provided by cast in situ concrete.
Irrespective of the method of construction, the excavation of tunnels induces
movements to the ground and structures in the tunnel vicinity. If the estimated
movement is above the permissible limits (for any given tunnelling method), additional
measures such as grouting are often carried out to improve the strength and stiffness of
the soil near and ahead of the tunnel. This Chapter reviews aspects of direct relevance to
this thesis, namely (i) the mode of ground deformation due to tunnelling, (ii) Settlement
prediction methods, (iii) building movement associated with tunnelling and soil
structure interaction effect and (iv) compensation grouting and its numerical modelling.
2.2 GROUND DEFORMATION
This thesis examines tunnelling-induced ground movement and hence it is worthwhile
to consider the various sources of these movements. In the first instance, it should be
noted that, regardless of the tunnel construction method, excavation induces stress
changes causing displacements and strains around a tunnel. The amount of ground
deformation around a tunnel cross-section is directly related to the additional amount of
8
excavation required to maintain that cross-section. The magnitude of the displacements
caused by the tunnelling is quantified in terms of volume loss VL, which is defined as
the excavated volume of the soil (Vg) in excess of the tunnel volume (V) divided by the
tunnel volume. The magnitude of volume loss varies for different ground conditions and
different tunnelling methods. Figure 2-1 shows the source of ground loss associated
with tunnel boring and each of these is explained below (Cording, 1991; Attewell,
1978).
1. Face loss: For the case of an open face shield tunnelling, this is the movement of
the soil towards the unsupported tunnel face during the tunnel excavation. If an
Earth Pressure Balanced (EPB) or slurry shield machine is used, heave may
develop in front of the cutter face due to excessive face pressure.
2. Shield loss: This is movement due to the radial ground loss around the shield to
fill the gap between the shield and the unsupported soil. This will be more if the
TBM is steering through a curve because of over-excavation.
3. Tail void loss: The erection of lining within the TBM introduces a gap between
the lining and the unsupported soil. The ground lost due to the squeezing of soil
into the void between the lining and the unsupported soil is referred to as the tail
void loss. This can be minimised by grouting the void between the soil and the
lining.
4. Lining loss: This movement is a continued radial loss of soil due to the
deformation of the lining as the overburden pressure is gradually redistributed to
its new equilibrium. If the tunnel comprises thick precast concrete segments, this
movement will be minimal.
5. Consolidation: This is movement due to dissipation of excess pore pressure
developed due to excavation or grouting. These pore pressure changes lead to
effective stress changes and hence additional ground movements over a long
time.
Chapter 2 Literature Review
9
For NATM, only face loss, lining loss and consolidation are applicable. Immediate
or short term deformation is caused by face loss, shield loss, tail void loss and lining
loss and the long term ground deformation is caused by consolidation.
Figure 2-1 Source of Ground Loss (Attewell, 1978)
The final settlement is a combination of the short term (immediate) and long term
(consolidation) settlement. Post construction settlement can be significant, particularly
in the case of tunnels in soft compressible clays (O’Reilly et al., 1991).
2.2.1 Failure Mode
The mode of soil failure (short term settlement) induced by the tunnel construction in
sand and clay is significantly different. The failure mechanisms inferred from centrifuge
model tests are illustrated in Figure 2-2 (a) and Figure 2-2 (b) for clay (Mair, 1979) and
sand (Chambon and Cortè, 1994) respectively. In clays, the failure surface propagates
upwards and outwards from the tunnel invert and becomes significantly wider at the
surface. However, in sand, the failure surface is like a narrow chimney propagating
almost vertically from the tunnel invert to the surface. This same behaviour of sand was
also observed by Potts (1976) in his laboratory model tests.
10
It may be inferred from these trends that the settlement trough that develops at the
ground surface is wider in clays than in sands - as failure approaches.
(a) Clay (Mair, 1979) (b) Sand (Chambon and Corte, 1994)
Figure 2-2Observed Failure Mode based on Centrifuge Model Tests
2.2.2 Centrifuge Model Testing in Sand
In clays, (i.e. in undrained condition), the volume loss calculated from the settlement
trough at any given level above the tunnel does not change with this level (Mair and
Taylor, 1997) and therefore an accurate estimate of volume loss can be obtained from
the surface settlement trough. However, in drained conditions (e.g. in dense sand) where
tunnelling induces volume changes in the soil, the volume loss calculated from the
surface settlement trough will be different at different levels above the tunnel (Cording
and Hansmire, 1975). This is in agreement with the observations of Jacobsz (2002) and
Marshall (2009). They carried out centrifuge tests that modelled tunnelling in sand and
found that under drained condition, estimation of ground loss from the soil displacement
data is complicated because of the soil’s contractive/dilative nature as shown in Figure
2-3. Figure 2-3 illustrates the difference in soil volume loss (ground loss calculated from
the settlement trough) and tunnel volume loss (calculated from the actual volume
extracted from the tunnel model) at different levels above the tunnel. Consequently,
inputting a volume loss (in numerical parametric study) calculated from the observed
Chapter 2 Literature Review
11
surface settlement trough will over predict the greenfield settlements at low volume
losses and under predict the settlements at higher volume losses.
Figure 2-3 Volume Loss Calculated from Soil Displacements Compared to Tunnel
Volume Loss (Marshall, 2009)
Figure 2-4 illustrates the mobilised lateral earth pressure coefficient calculated from the
stress measurements in the centrifuge model testing of sand performed by Jacobsz
(2002). This figure shows higher earth pressure coefficients near the tunnel crown at
250mm depth – which increase as the volume loss increased. Coefficients reduce
sharply with distance above the tunnel crown. However it appears that, for low volume
losses (less than 0.5%), the mobilised earth pressure coefficients are not significantly
varying along the depth of the tunnel axis. Unfortunately these measurements are only
from prototype depth equivalent of 7.5 m (75g test) from the surface.
12
Figure 2-4 Profile of Mobilised Lateral Earth Pressure Coefficient on Tunnel
centre line at Different Volume Losses (Jacobsz, 2002)
2.3 SETTLEMENT PREDICTION METHODS
Methods available for prediction of surface and subsurface settlement trough include the
empirical (Gaussian) method, numerical methods such as Finite element and Finite
difference methods and analytical methods (closed form solutions). Closed form
solutions can provide a rough estimate of ground behaviour although they cannot
accommodate complexities of tunnel construction methods and soil properties such as
anisotropy. Hence numerical methods are becoming increasingly common in
engineering practice. The empirical, 2D and 3D FE methods are considered in this
thesis and each of these is explained in the following sections. It is important to note,
however, that all of these “methods” require the tunnel volume loss as an input
parameter. This volume loss is a function of all the factors discussed in Section 2.2,
many of which depend critically on the construction methodology, TBM excavation
parameters etc. and therefore cannot be predicted numerically or analytically. The
methods therefore predict a distribution of ground movements for a prescribed volume
loss. Designers prescribe volume losses on the basis of case history data reported in the
Chapter 2 Literature Review
13
literature – using, for example similar tunnelling method in a given soil type. Soil
structure interaction can be modelled using the FE methods.
2.3.1 Empirical Method
The development of surface settlement trough ahead of a tunnel heading is illustrated in
Figure 2-5. Peck (1969) and subsequently many other authors have concluded that the
transverse settlement trough, which forms immediately after the tunnel has been
constructed, can be described by a Gaussian distribution curve. Typical view of
transverse settlement trough is shown in Figure 2-6. The vertical settlement along the
transverse direction can be expressed as,
⎟⎟⎠
⎞⎜⎜⎝
⎛ −= 2
2
max 2exp
iySS (2.1)
Where,
S – settlement
Smax - maximum settlement above the tunnel centre line
y– horizontal distance from the tunnel centre line
i – transverse horizontal distance from the centre line to the point of inflection of the
settlement trough.
Figure 2-5 Geometry of the tunnel induced settlement trough (after Attewell et
al.,1986)
14
Tunnel Volume, V
Ground loss at Tunnel, V g
Volume changein ground =ΔVg
Volume loss V L =V g /V
Point of inflection
Dep
th z 0
Volume of settlement trough V s =V g + Δ V g
Smax
i
Figure 2-6 Transverse Settlement Trough
The volume of the transverse surface settlement trough per meter length of tunnel, Vs, can be evaluated by integrating equation 2.1 and may be expressed as:
∫∞
∞−
== max2 SiSdxVs π (2.4)
Although, for the undrained (constant volume) case, the ground loss close to the tunnel
(Vg) will be same as the volume of the surface settlement trough (Vs), this will be
different (see section 2.2.2) for the drained case where shear induced volume changes
within the soil takes place. However the volume loss (VL) is usually approximated as,
4
2DV
V sLπ
= (This is normally expressed as a percentage value) (2.5)
Where D, is the outer tunnel diameter.
Chapter 2 Literature Review
15
A number of empirical correlations have been proposed which relate iy to the tunnel
depth to diameter ratio and soil type. For practical purposes it is often assumed that the
parameter i varies proportionally with z0 (O’Reilly and New, 1982):
0Kzi = (2.6)
Where,
K – a constant called the trough width parameter
z0 – depth of the tunnel axis below the ground surface.
Taking into account of different layers of soil in a soil profile, New and O’Reilly (1991)
suggested the following relationship:
....2211 ++= zKzKi ,
Where,
K1 and K2 are trough width parameter in layer 1 and layer 2 of depth z1 and z2
respectively.
Although the Gaussian approach is simple, the use of this method is limited to
• Single tunnels or multiple tunnels where there is no significant interaction effect.
• Estimate short term ground movement (no consolidation movement)
• Greenfield sites where there are no structural interaction effects.
2.3.2 Numerical Prediction
Because of the limitations of the empirical method (e.g. the effect of structures on
tunnelling cannot be predicted), numerical modelling has increasingly been used to
examine effects of tunnelling. The most widely used numerical method appears is the
Finite Element method (FEM); the Finite Difference Method (FDM) is used
16
occasionally (e.g. using FLAC). The advantages of FEM over the empirical method are
its ability to:
• Deal with complex ground conditions;
• Model realistic soil behaviour;
• Simulate the construction sequence;
• Accommodate the interaction between multiple tunnels;
• Account for adjacent services and structures;
• Simulate immediate and long term conditions;
• Deal with ground treatment (e.g. compensation grouting); and
• Handle complex hydraulic boundary conditions.
The two dimensional and three dimensional Finite Element (FE) method is used to
predict the tunnel induced settlement, as described in the following sections.
Two Dimensional Finite Element Analysis
Tunnel excavation is a three dimensional problem. However three dimensional analyses
require excessive computational resources such as storage space and time of analysis.
Because of these complexities, two dimensional analyses are preferred over three
dimensional analyses. Various methods proposed to take account of the stress and strain
changes ahead of the tunnel in plane strain analysis are the: (i) Gap method (Rowe et
al., 1983), (ii) Convergence-Confinement method (Panet and Guenot, 1982), (iii)
Progressive Softening method (Swoboda,1979), (iv) Volume Loss Control method
(Addenbrooke et al., 1997, Liu et al., 2000, Franzius, 2003)
Three Dimensional Finite Element Analysis
Three dimensional FE analyses would consider the movement of the soil associated
with all the sources described in section 2.2. Different researchers used different
Chapter 2 Literature Review
17
methods to model 3D tunnel construction and the modelling techniques of different
authors were summarised by Wongsaroj (2005). The modelling of shield tunnelling is
complicated as it involves modelling different parameters such as (i) face pressure at the
cutter face of the TBM (to stabilise the soil ahead of the TBM), (ii) movement of the
TBM, (iii) installation of lining at the back of TBM and closing the tail void using
grouting.
The face pressure at the cutter face is often modelled by applying prescribed pressure at
the excavated tunnel face; for example, Komiya et al. (1999) and Mroueh and Shahrour
(2003). The shield losses were modelled in three different ways such as by (i) applying
a percentage stress reduction at the tunnel boundary depending on the length of unlined
tunnel (Mroueh and Shahrour, 2002) (ii) applying a prescribed displacement to the
tunnel boundary (Lee and Rowe 1990a) and (iii) contracting the tunnel boundary
(Koelewijn and Verruijt, 2001). The tail void closure using grouting was modelled by
two methods. The first of these involves applying prescribed displacements or
contraction to the lining (Koelewijn and Verruijt, 2001). In the second method, grouting
is modelled either by applying an outward pressure to the lining (Ezzeldine, 1999) or by
expansion of the lining (Koelewijn and Verruijt, 2001).
Effect of Initial Stress Condition on Predicted Settlement trough
The influence of initial stress history on the predicted settlement trough both in 2D and
3D analyses have been reported by many authors. The predicted settlement troughs
using a higher K0 was often wider and shallower compared to the observed settlement
troughs in the field. Wider settlement troughs were reported by Addenbrooke (1996),
Franzius (2003) and many others for their 2D plane strain analysis even with different
soil models.
Previous literature also shows that width of the settlement trough predicted using 3D
modelling is also wider than observed in the field. Although the tunnelling can be
modelled in a more realistic manner in 3D, various authors such as Guedes de Melo &
Santos Pereira (2000) and Franzius (2003) also predict a wider and shallower trough in
soils with higher K0 values.
18
Franzius (2003) carried out both 2D and 3D FE analysis to study the influence of K0 and
soil anisotropy on the predicted settlement trough. His analyses concluded that, neither
the 3D effect nor the soil anisotropy can account for the wide transverse settlement
trough predicted by FE analyses in a high K0 regime. He found that although the trough
shape can be improved with unrealistically high soil anisotropy, this leads to
significantly higher volume loss. This is because of the reduction in vertical stiffness
due to the increase in horizontal stiffness (to meet certain shear modulus criteria). He
also found that with low K0 the magnitude of settlement and thus the volume loss
predicted was higher in a 3D analysis; he did not, however, comment on the effect of
mobilised strength. Franzius (2003) argues that the K0 value at the tunnel axis has a
significant influence on the nature of surface settlement trough and that a higher
specified K0 value also results in a wider prediction for the longitudinal trough. His 3D
analyses also showed that stabilised longitudinal movements at the start of the geometry
could not be obtained even after excavating a long distance (100m) - both for isotropic
and anisotropic cases; this is shown in Figure 2-7.
Ng and Lee (2005) also demonstrated through their three dimensional analysis (open
face tunnelling) that the surface settlement trough is governed by the combined effect of
stiffness ratio (E’h/E’v) and the K0 value. They found that as E’h increases, the predicted
settlement trough will be deep and narrow due to the mobilisation of small plastic
extension shear zones at the crown and at the invert. They also found that, for a given
stiffness ratio, the computed settlement trough is narrower if K0 is lower.
Chapter 2 Literature Review
19
(a) Isotropic 3D analysis
(b) Anisotropic 3D analysis
Figure 2-7 Longitudinal Settlement Profile (Franzius, 2003)
20
2.4 BUILDING MOVEMENT DUE TO TUNNEL BORING
The ground movements arising from tunnelling are described in section 2.2 and have
been the subject of most previous research. However the movements occurring in built
up areas are less well understood due to the site-specific nature of soil structure
interaction effects. Unfortunately, apart from relatively recent work done on the Jubilee
line extension in London, few published data are avail