2021 CAMA Project Update | Mayor Dave Bronson
An Update on the Computer
Assisted Mass Appraisal (CAMA)
System Upgrade Project
September 10th, 2021
2021 CAMA Project Update | Mayor Dave Bronson
Who Is Here Today?Tyler Technologies:
• Jared Angell (Implementation Manager)
• Robert Goodman (Project Manager)
Pango Technologies:
• Justin Martin (Project Manager for MOA)
Municipality of Anchorage:
• Marc Dahl (Director of IT)
• Jack Gadamus (Municipal Assessor)
• Dan Moore (Municipal Treasurer)
2
2021 CAMA Project Update | Mayor Dave Bronson
MOA Project Team
Project Sponsors:
Travis Frisk, Chief Fiscal Officer
Jack Gadamus, Municipal Assessor
Dan Moore, Municipal Treasurer
Project Team:
Justin Martin, Project Manager for MOA (Pango Technology)
Myron Heil, Mainframe Supervisor (MOA)
Sandra Fern, Business Analyst (MOA)
David Counts, Business Analyst (Pango Technology)
Blythe Easterly, Business Analyst (Pango Technology)
3
2021 CAMA Project Update | Mayor Dave Bronson
What is CAMA?
• Computer-Assisted Mass Appraisal (CAMA)
• Supports: Property Appraisal & Tax Billing
• 30 year-old technology
– Runs on a mainframe
– Difficult to find technical support for old
system
– No longer supported by the vendor
– Any system change is a HUGE effort
4
2021 CAMA Project Update | Mayor Dave Bronson
CAMA Upgrade Project Overview
5
• Using the software vendor to perform the upgrade – Tyler Technologies
• Installing and configuring the latest version of the software – “iasWorld”
• Moving off the mainframe and will run on a virtual Microsoft server
• Upgrade is following an “off the shelf” philosophy – changing business
process instead of customizing code
• Will allow the MOA to adapt more readily to future assessment/tax
changes
• Current Go-live estimate: Q1 2022
2021 CAMA Project Update | Mayor Dave Bronson
CAMA Upgrade Project Timeline
6
2019 2020 2021
Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4
Phase 5Go-Live
Phase 1Initiate/Plan
Phase 3Build/Validate
1 3
42
Phase 4Test/Train
MOA Kick-off
Phase 2Assess/Define
ProjectCloseout
Q1 Q2 Q3
2021 CAMA Project Update | Mayor Dave Bronson
Omnibus Ordinance, AO 2020-96
7
Personally
owned
Mobile
Homes will
be exempt
Commercial
aircraft will be
subject to a flat
tax based on
weight
Business
Property
Assessment
Returns will add
a penalty to
non-filers
Property Tax Due
Date will get
extended to
month end
Property Tax
Refunds will allow
money to transfer
between
accounts
The ordinance was passed to maximize taxpayer equity, government efficiency, and process improvement for new CAMA system
AO 2021-64 AO to better
define
commercial
aircraft
2021 CAMA Project Update | Mayor Dave Bronson
Current CAMA Operating Costs—OIT
Budget
• OIT spends $750k/year operating supporting mainframe
• Continue to spend $750k through 2021
• Continue to spend $230k iasWorld maintenance and support
• 2022, OIT plans to retire the mainframe.
• $750k less $231k annual maintenance cost for new Tyler System,
expect an operational savings of $500k to start in 2022
8
2021 CAMA Project Update | Mayor Dave Bronson
Post Go-Live
• Expect an operational savings of $500k post Go-Live
• Increased taxpayer transparency
• Increased flexibility
• Project work will continue post Go-Live
– Continue to learn/grow with the new system
– Several modules will be implemented post Go-Live
9
2021 CAMA Project Update | Mayor Dave Bronson
Increased Taxpayer Transparency(Post Go-Live!)
Category Capability in Legacy CAMA System
Capability in New CAMA System
Maps Yes Yes
Land Information Limited Yes
Improved Information Yes Yes
Valuation History Partial (3 yrs) Yes
Sketches No Yes
Permit Information No Yes
Electronic Fund Transfer Basic Streamlined
Smartfile* No Yes
Sales Comparison Grids Basic Yes
Mailing Address Yes Yes
10
y
*Smartfile involves online
fillable forms and includes:
• Appeals
• Personal Property Business
filings
• Exemptions
2021 CAMA Project Update | Mayor Dave Bronson
Enhanced Flexibility (Post Go-Live!)
• Empowering the end user
– Better queries
– Less reliance on IT: more user-friendly configurations
• Experts at our fingertips post go-live
– Tyler Technologies has been in the industry for 80 years. We will continue
to receive updates and upgrades in the future
• Common Technology
– Easier to find labor that allows us to modify the system and integrate
with other business platforms
11
2021 CAMA Project Update | Mayor Dave Bronson
Post Go-Live! Projects
The work isn’t over after we go-live
12
Field MobileField Mobile allows an
appraiser to access,
verify, and edit
property information in
the field
Sketch Sketch will be ready
out of the box, but we
will transition to the
new sketch process
over the coming years
Ongoing Training
and Integration
Training users and revisiting
our business processes will be
an ongoing process.
2021 CAMA Project Update | Mayor Dave Bronson
Timeline of the CAMA Upgrade Project in 2022
Maintain legacy system
13
Decomission legacy system
Field Mobile
Transition to iasWorld Sketch (during re-inspections)
Go-Live!
Work flow Process
Stabalize w/Tyler’s support
2021 CAMA Project Update | Mayor Dave Bronson
Thank You