Upload
pavan2deepuaki
View
217
Download
0
Embed Size (px)
Citation preview
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 1/9
Magazine o Concrete Research, 1995 47 No. 171 June, 119-127
An experimental study of the behaviour of
sleeved bolt connections in precast concreteframes
S . A . M . Mohamed* and C . K . Jolly
U N I V E R S I T YF S O U T H A M P T O N
Sleeved bolt beam-to-column connections have been used
in the precas t concrete industryo r many years. Theyhave
advantages over other jointing methods in component
produ ction, qua lity contro l, transportation and assem bly.
However, there is at present limited information
concerning their detailed structural behaviour under shear
loading. The study reported in this paper was undertakento elucidate the behaviourf such oints under symmetrical
vertical loading. Two series of full-scale tests were
pelformed on sample columns for which the column
geometry and bolt arrangements conformed withsuccessful commercial practice. The first series of tests
was used to investigate the influence of bolt density on
the ultimate load, ailure mode andstifSness o such
connections. The second test series showed the influence
o varying co ncrete strength and the effectiveness of the
confining reinforcement. Full details of these test
programm es are given. The finite element modelling
technique was used to develop three-dimensional models
which were calibrated gainst the test observa tions. These
models subsequently provided complete stress and
deformation distributions within the joi nt components at
intervals up to the ultimate load, and are the subject of
another paper.
Introduction
Thesefrecastoncretemembers by the
construction industry has increased rapidly throughout the
world over the past wo decades. Advantages such as
speed of erection, better quality, dimensional precision
and,aboveall,reduction of costs have made precast
concrete superior to its site-cast counterpart. The
satisfactory performance of arecast structure as a whole,
* University of Southampton, Southampton S09 5NH, UK.
Paper accepted 6 July 1994.
and its economy, depend to a great extent on the proper
selection and design of itsconnections. In skeletal frame
construction, beam-to-column connections are the most
critical part of the structural concept because they must
be capable of transmitting axial forces, shear forces and
bending moments safely and without xcessive deforma-
tion. It is essential to consider their design very carefully
under all stages of the construction process, from
conceptual studies through to construction.
The joints must e capable of easy fabrication,
transportation without damage, rapid and positive locationwhenpositioned by crane; of absorbing construction
tolerances, andyetmust provide a robustand igid
connection when fully assembled. In spite of the wide
variety of beam-to-column connections in use, their
practical design is not overed in detail by current design
codes. Few references, such as thatcompiled by the
Institution of Structural Engineers,' deal with design of
connections.
Sleeved bolt connections are among the most
extensively used. They are popular because
a ) their manufacture is simple and can be varied withoutcausing significant damage to formwork
b ) there are no vulnerable cast-in protrusions to be
damaged during handling and delivery
c ) pre-assembly at ground level of the steel brackets onto
the columns facilitates rapid and positive location of
members during frame assembly, hile retaining the
ability to accommodate tolerances until the frame is
complete
d ) they require little supervision compared with other
types of connection, so they are suitable for site
conditions
e ) they provide connections with high rigidity due to theuse of high-tensile bolts
f, in their,finished form they have no visible protrusion
below the beam lower soffit, whichs sually
119
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 2/9
Sleeved bolt connections in precast concrete frames
Bolt sleeve Grout hole
Fig. 1.
Steel bracket
Precast column
Typical deta ils of a sleeved bolt beam-to-column connection
essential for the architectural and functional
requirement.
Site assembly of the connection
The details of a sleeved bolt connection are shown in
Fig. 1. The steps of assembling the connection are,
briefly, as follows. A group of high-tensile, grade 8 . 8
steel bolts, threaded at both nds, are passed through mild
steel sleeves embedded through the breadthf a reinforced
concrete column. The bolts are also passed through
matching holes drilled in two stiffened steel brackets. A
vertical bolt runs between the upper and lower brackets.
Pairs of brackets on opposite sides of the column are held
in position by the hexagonal nuts on each bolt’s end.
The columns are then raised, positioned and plumbed.
The top bracket and verticalbolt are temporarily removed
by the erector. At this stage, each bracket can serve as
a seat cleat for the incoming beamend. The beams usually
have recessed ends to confine the bracket within their
cross-section. Replacement of the top bracket and vertical
bolt provides stability and torsional restraint to the beam
end. Later, the steel bolts and brackets are surrounded
with expanding grout to provide corrosion and fire
protection.
The research programm e
This paper provides basic research data regarding the
behaviour of sleeved bolt connections under symmetrical
120
vertical shear loading. There are several potential failure
mechanisms.he connection is assembled using
components of several different materials. Material
properties such as concrete strength and yield strengths
of the various steel components (i.e. bolt, sleeve, links
andrackets)anreatlyffect the connection
performance. Geometrical variables such s number, size,
spacing and arrangement of bolts within each joint also
affect the joint’s ultimate capacity.
The precast concrete beams are relatively stiff and can
therefore normally be assumed to apply only a vertical
bearing force on the seat cleat. This bearing force can
cause failures within the notched endof the beams, which
are described fully in an earlier paper.*
The lower bracket is normally designed to resist the
entire bearing force. The brackets themselvesre normally
designed to act rigidly, and are consequently unlikely to
fail under service stresses. The bearing force produces
a large shear load, which s the major action obe
transferred into the column.
Uppermost bolts through the lower bracket must also
be checked to ensure that they can provide a restoring
moment to counter the moment produced by the small
eccentricity from the column face of the bearing force on
the seat cleat. When the connection is under pure shear
loading, the load is transferred from the seat cleat to the
column through the bolts. Bearing of the bolts on thesleeves then transmits the load to the concrete.
Thus, two principal modes of failure are likely tooccur
at the column face at ultimate load, as follows.
Magazine of Concrete Research, 1995 7 No. 171
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 3/9
Mohamed and Jolly
Tensi le forcesin steel l inks
Fig. 2 . Confining force develop ed in the inks near a jo int
a ) The bolt may fail by being sheared off completely:
this is most likely at the root of a thread when the
threaded portion of the bolt extends into the shear
plane.
6 ) Under the application of a concentrated load, the
concrete in the region below theoint level is confined
laterally by the column link einforcement against the
bursting stresses that develop. Another contribution
to this confinement is provided by the bracket’s back
plate, which is compressed against the column face
in this region. None the less, the concrete beneath
the sleeve may crush sufficiently for the sleeve to
deform vertically downwards at the column face.
Bearing of the bolt in the sleeve invert causes lateral
stresses to develop in the concrete as shown in Fig.
2. Horizontal components of these stresses create a
lateral tensile stress in this region. Consequently,
concrete cracks start to develop. At higher loads, the
steel links beneath the sleeve may yield due to these
transverse stresses, and the already cracked concrete
will then fail.
Thus, two full-scale est programmes were undertaken.
Test series A was performed to examine the influence of
bolt density on overall joint behaviour, e.g. failure mode,
ultimate strength and stiffness. Test series B was carried
out to assess the effect of concrete strength and its
confinement on he load-carrying capacityof single-bolted
joints.
Numericalhree-dimensional models were then
developed using the finite element package ANSYS3 to
obtain additional information that could not be observed
or measured experimentally, e.g. stress distribution in themost highly stressed zones at both working and ultimate
loads. The experimental study of theseailure mechanisms
in the column is the subject of this paper.
Magazine of Concrete Research, 1995 47 No. 171
t
Fig. 3. Series A test column geometryandsleeve ocationsdimensions in mm
The tests
All tests were carried out on reinforced columns of
300mm square cross-section. Formwork and sleeve
setting-out dimensions are shown in Fig. 3.
White Portland cement was used in both mixes as it
facilitates crack detection. The concrete had a moderately
high workability, with slump values in the range of
65-76mm.A consistent 40mm concrete cover was
maintained to the longitudinal column reinforcing bars.
Steel tubes 300 mm long with an internal diameter of
27 a 0 mm and a 3 0mm wall thickness were used as
sleeves. This internal diameter was chosen to suit the
24 .0 mm nominal dia. bolts used in all the tests. Each
bolt had a total length of 390 mm. This length, which
included 35 mm threaded on each end, was chosen to
avoid direct contact between the threads and the sleeve’s
inner surface, and to allow for tightening of nuts against
the brackets’ backplates.
Brackets were made from grade 43 steel plates welded
together. Steel webs were designed to carry safely the
anticipated applied shear load. The plates were connected
with continuous fillet welds.
Test series A
In test series A, the number of bolts per joint was the
121
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 4/9
Sleeved bolt connections in precas t concrete frame s
principal experimental parameter. The series was divided
into four tests. Each test involved a joint with a different
number of bolts ranging from one central bolt to four bolts
in horizontal pairs. Vertical and horizontal spacings
between sleeves’ centrelines within each joint were
140 mm and 65 mm respectively. Tests in this series are
identified by a number corresponding to the number of
bolts attaching the seat cleat to the column.
The column used toprovide all specimens in test series
A was reinforced longitudinally with four 25 mm
deformed high-yield steel bars. 8mm dia. steel links, at
50 mm centres, were used along the column height. A
concrete mix was designed with he following proportions
by weight: 1.0: 1. 48:0 .85: 1. 70 :0 .375 (cement-fine
aggregate- 10 mm aggregate-20 mm aggregate-water).
Specimens were damp cured at 20°C for 15 days in a
curing tank.
Test series B
Three tests were carried out on single-bolted joints to
examine the effect of varying the concrete strength and
degree of confinement on the joint’s ultimate load and
failure mode. The joints tested were similar to test 1 in
series A . However, the concrete compressive strength was
reduced by almost half. The degrees of confinement were
low, medium and high and the tests are referred to as L,
M and H respectively.
Columns used in test series B were reinforced with four
16 mm bright mild steel bars. To reduce the strength of
the steel links below the joint’s level, the first two links
in this region were spaced at 50 mm and 175 mm from
the bolt sleeve.A 150mm vertical spacingwas maintained
for the remaining 8 mm steel links in the 1. 0 m high
column. The designed concrete mix adopted for these tests
hadheollowingroportions by weight:
1.59 :0.89 : 1.79: 0.485 (sequence as above). These
columns were air-cured.
To minimize the concrete confinement in test L two
12mm high and3 -0mm thick steel plates were introduced
across the upper andower edges of the brackets’ flat back
plates, between the back plates and the column faces.
These plates actedas packing at both top and bottom edges
of the bracket to createan almost uniform gap into which
the concrete from the face could spa11 under load.
Furthermore, the steel links located immediately beneath
the joint level were reduced in cross-sectional area so that
they yielded at a tensile force equivalent to the link steel
minimum design stress of 250.0 N/mm2.
In test M the brackets were machined flat so that they
were initially in direct contact over their whole area with
the concrete. The steel links’ reduced cross-section
provided the only reduction of confinement.
In test H the back plates of the brackets were left with
their thermally induced curvature from the welding
process, and this provided the maximum confinementpossible to the column face immediately below he sleeve.
Also, the full cross-sectional area of steel links was
retained in this case.
122
Fig. 4 . Equilibrium of orces on a oaded bracket
Additionally, static friction tests were carried out on
the loose brackets against the precast concrete column
faces. For these, a column was laid on its side, and the
brackets in turnwere placed on the horizontal surfaceith
vertical loads applied to them covering the derived range
of interface loads for the in-service brackets. The
horizontal force required to initiate movement was then
measured for each case. The static coefficient of friction
values enabled corrections to the shear load on the bolts,
thus allowing for the effectf friction between the brackets
and precast concrete columns.
When the equilibrium of vertical forces for a loaded
steel bracket is such as that shown in Fig. 4, the applied
vertical load P must equal the sum of the shear forces
carried by the bolts R b plus the frictional force acting
at the column face R f . Top bolts are subjected to a tensile
force T to provide a reaction to the moment resulting from
the eccentricity of applied load from the column face.
Load eccentricity is small in these tests compared with
the backplate height. Consequently, within the range of
geometries investigated, the estimated ratio of the tensile
stress to the shear stress per bolt was not large enough
to cause a significant shear strength reduction. Hence the
effect of the tensile force on the joint ultimate shear
strength has been ignored.
Friction occurs in the lower, compressive contact area
between the backplate of the bracket and the column face.
To obtain the actual shear forces carried by the bolts, anestimated value of the corresponding frictional force
developed in this contactrea was deducted.By satisfying
the moment equilibrium conditions for a loaded bracket,
Magazine of Concrete Research, 1995 47 No. 171
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 5/9
Mohamed and Jolly
a value for the developed compressive force C was
obtained. Then, using the measured friction coefficient
between steel and the precast concrete, a value for the
frictional force could be estimated t each load ncrement.
The load values reported in this paper are per bolt end
cross-section, after the deduction of the corresponding
frictional force. This is to allow direct comparisonbetween results obtained for bolts in different joint tests.
Separate tests were carried out to determine the
compressive and indirect tensile strengths of the concrete,
and the yield strength of the reinforcement used.
Experimental procedure
The column base was arefully centralized in a 1500kN
maximum capacity testing machine. The machine top
platen was denied any free rotation after the application
of the first load increment. This ensured that the applied
load was shared equally between the twobrackets despiteany initial asymmetry.
All tests required deflections to be monitored at the same
positions relative to he brackets. Thus a single frame was
assembled around the joint to hold the measuring equip-
ment in the required positions (see Fig. 5). The frame
was made rom two 6 mm thick U-shaped steel plates fixed
independently to the column top by 12 mm bolts. Each
bolt was threaded into a hole drilled and tapped in the
ends of the main column bars. An 8 mm hole was drilled
and tapped in the U-plates outside the column section.
Four steel rods of 12 mm diameter and 500 mm length
were threaded and connected into these holes. These rodswere also connected at a level below the joint by a closed
steel frame, formed from four 6 mm plates around the
column. This provided a rigid and stable mounting frame
for transducers.
Linear variable displacement transducers were used to
determine the movement of the bolts, the brackets and
the concrete around the test joints. Transducers were
calibrated independently using a micrometer. A Solartron
Orion data logger recorded the deformation data at each
load increment. The following measurements were taken
in each test
a) the downward vertical deflection of the bracket’s
back plate; these measurements were taken as
representative of the bolt’s vertical deflection
b) the bolt’s longitudinal deflection, i.e. its axial
extension
c ) the variation of the concrete’s sideways expansion at
a series of points along both sides of the bracket;
transducers were mounted around the joint, using
purpose-made aluminium channels bolted to a steel
angle; the angle ran horizontally between two of the
vertical steel mounting frame rods, to which it was
fixed.
Loads were applied to the joint brackets through two mild
steel plates300 mm high by 250 mm wide by 40mm thick,
as shown in Fig. 6 . The top surfaces of the plates were
Magazine of Concrete Research, 1995 47 No. 171
160
6 mm thick steel U-plates
Bolts
12 mm dia. steel rod
concrete column
I I I
6 mm thick tiemm thick tie
Fig. 5. Transducermounting framedetails dimensions in
mm)
not less than 50mm higher than the column top to avoid
applying anydirect load on the column. he test procedure
was to apply load increments until the joints were not
capable of supporting any further load. When the
monitored deflections indicatedhe onset of non-linearity,
the load increments were reduced from 50kN to 25 kN.
The progress of any visible crack formation wasmonitored by visual inspection of the joint between load
increments.
Test results
The test results are summarized here. More detailed
results are given in Ref. 4.
Test series A
The observed structural behaviour of a typical series
A joint test can be described as follows. Bedding of the
bolt onto the sleeve invert during the first load increments
gave rise torelatively large vertical deflections. The bolt
also tended to part from the column at one end and was
drawn in to the column face at the other end. On further
123
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 6/9
Sleeved bolt connections in precast concrete frames
Steel tie rod
Steel lo ad in g plate-
Steel bracket
Concrete column-
Bottom platen
--l-
1Fig. 6. Genera l arrangement of the stub column in the test machine
loading, the bolt became well seated against the sleeveinvert, giving rise to an almost constant stiffness for most
of the load range.By the time significant bending moment
had developed due o the small load eccentricity from the
column face, the rotation of the backplate was visible and
resulted in a further gradual increase of axial bolt
deflection. Just before failure, the vertical deflection rate
increased rapidly, with shear deformation of he bolts
visible in the gap created between the column face and
the bracket backplate.
There were no visible cracks around the joints at any
stage in test series A , and correspondingly noappreciable
lateral concrete movement was recorded at any of themonitored levels. Most of the bolts showed a significant
shear deformation at their loaded ends. Examination of
the bolt shanks againsta flat surface also indicated limited
plastic bending about their longitudinal axes. Neither the
bolt sections nor the threads were significantly distorted
by the bearing stresses.
Inspection of the steel components at the end of each
test showed that the upper curved surface of the holes
through the brackets had deformed due to bearing f the
bolts. Yielding of thebracket material had developed the
contact zone into an identifiable trapezoidal area, greatest
next to the column. The topof each hole had consequentlybecome oval in shape. Imprints of the bolt threads were
formed in this trapezoidal area.
Similar evidenceof yield wasapparent within the ends
124
of the sleeves cast into the columns. By compressing thesleeve against the oncrete beneath it at each end, the bolt
had crushed he concrete in this area, and some ocal
spalling occurred as the steel brackets were removed.
However, mostofhe rushedmaterialwasirmly
compacted, andbecamedislodgedonlywhen apped
gently. Friction marks were found at the interface between
the lower parts of the backplates and the corresponding
column faces, and on the areas of compacted, crushed
concrete below each bolt. Fig. 7 shows a photograph of
these marks, which provide qualitative visual evidence
ofhigh pressure and frictional resistance to vertical
deflection of the bracket.The result ofhaving a high concretecompressive
strength and substantial steel link concentration around
the joints in test series A was that shear in the bolts was
the dominant mode of failure. Since all bolts used in the
tests havenominallydentical properties, theoad-
deflection data obtained for the single bolt in test 1 are
compared in Fig. 8 with corresponding data for each bolt
in joints containing numerous bolts.
In test 1 the bolt failed by shearing off at one end, at
an ultimate load of 210 e kN. The failure shear plane
passed hrough he reduced section at the root of he
threads. The other endof hisboltwasalsoseverelydistorted in shear.
Tests 2 and 3 were stopped and the joints deemed to
have failed when they could no longer support the applied
Magazine of Concrete Research, 1995 47 No. 171
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 7/9
load. The ultimate load per bolt in both these joints was
found tobe 177-0 N . Severe shear istortion in he bolts
was clearly visible after the tests.
As the shear plane assed through the threaded portion
of the bolt in tests 1 to 3 , the bolt stress at failure was
calculated using the reduced diameter. he threaded cross-
sectional area is 0 7 times that of the bolt shank for a
standard 24 mm bolt. Based on the reduced area and the
failure loads quoted, the bolt shear stress was calculated
to be 663 1 N/mm2 and 558 -0 /mm2 at failure of joint
1 and of joints 2 and 3 respectively.
Test 4 used brackets that were not fabricated
commercially. A weld fracture in the bracket caused
failure. Thispremature failure occurredat a oad of
120 kN per bolt end, which corresponds to a shear stress
of 379 N/mm2.Thisncident emonstratedhe
importanceof using factory-weldedcomponentsof a
consistent standard to avoid different modes of failure
within joints formed in this way.A repeat of this test using
a commercially fabricated bracket was undertaken
subsequently, and failed at a load of136 kN per bolt end.
The bolt shear stress in this case was calculated to be
430 N/mm2.
Test series B
In test series B bolt shear failures similar to those
500
400
3 300
aY
DE
S 200
TQ
1oc
0
Mohamed and Jolly
Fig. 7. Friction marks on he spalled concrete below ested
sleeves
reported for series A were obtained for tests H and M
again with novisible concrete cracking. However, in test
L a horizontalcrack appeared on both faces of the column
at 88 of the ultimate load for test A . These cracks were
just above the steel link located immediately below the
I
2 4 6 8 10 2
Deflection: mm
Fig. 8. Load-de fec t ion curves for the four tests in series A
Magazine of Concrete Research, 1995 47 No. 171 125
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 8/9
Sleeved bolt connections in precas t concrete frames
joint level. During the following load increment, both
cracks lengthened and propagated at a shallow angle to
their initial direction, and joined together across the
column sides. This was followed by the appearance of
a crack up the column’s vertical centreline, propagating
from both ends of the sleeve. These vertical cracks
extended almost to the base and top of the column as
failure approached. Sudden large deformations showing
lateral expansion were recorded along the column sides
as soon as this cracking occurred.The above result
emphasized the effect of the concrete confinement at the
column face by pressure from the brackets.This confining
pressure provided a significant enhancement of the
concrete compressive strength, which delayed cracking
and crushing in the.critica1 zone, and thereby inhibited
this mode of failure in tests H and M. When the bracket
was removed, there was again crushing and spalling of
the concrete, extending to a depth of 90- 100mm below
the sleeve invert on both column faces.
Other test results
Supplementary tests on control specimens of the
material used for test 1 in series A were carried out on
the same day as the column tests, and gaveaverage values
of 61 .90N/mm2 and 4.05 N/mrn2 or hedirect
compressive and indirect tensile strengths respectively.
Similar control tests for series B gave an average concrete
compressive strength of 3 0 - 5 N/mm2, and indirect
tensile strength of 3 00 N/mm2, on the day of testing.
Four tensile tests on the high-yield steel bars used as links
in the column produced anverage strength of
450.0 N/rnm2.
The static friction test results gave friction coefficients
that were independent of the load, yet varied according
to the contact conditions. The original black steel bracket
used in tests A and H gave a friction coefficient of 0-66.
However, the machined steel face on the back of he
bracket used in test M gave a reduced value of 0.52. The
bracket on painted steel packing, which formedhe contact
in test L registered a coefficient of just 0.2.
Conclusions
Joint shear stiffness is characterized by the slope of the
experimental load-deflection curve. Curves shown in
Fig. 8 illustrate the difference in stiffness for the four
joints tested. Each curve was obtained by taking an
average of the top bolt deflections for that joint. There
is a clear trend for an increase in shear stiffness as the
number of bolts in the joint is increased.
Joint moment stiffness is characterizedby the moment-
rotation curve. A moment M is created at the concrete
face due to the eccentricity of the load from the column.
This moment, which tends to extend the top bolts, is
responsible for the plate rotation9
alues of andwere computed, and are plotted in Fig. 9. These curves
show that the number of bolts per joint also has an effect
on the joint’s rotational rigidity. Once again, joint 1 has
126
the lowest rotational rigidity while oint 4 has the highest.
The almost flat region in the joint 1 curve indicates a
continuous bracket rotation during shear and tension
yielding of the bolt immediately prior to failure.
For the two-bolts joint, the resulting ultimate oad
capacity was found to be about times that of the single-
bolt joint. The three-bolts joint provided anultimate
strength almost2 6 imes thatof the single-bolt oint. Thecorresponding figure for a four-bolts joint is 2-8 .
With high-strength concrete, the joint failure mode was
governed by the bolts yielding in shear. If weaker concrete
is used, as was the case for test series B there isan
increased likelihood that local crushing beneath the sleeves
will permit the sleeves to distort into an ovoid cross-
section with a smaller invert radius. This increases the
lateral forces, and vertical cracks in the concrete are more
likely to develop beneath the joint as seen in test L.
In these tests, most of the bolts showed a significant
shear deformation at their loaded ends prior to failure.
The bolts were made of sufficiently hard material to have
retained their circular cross-section. However, the steel
sleeves yielded substantially at their ends to form ovoid
cross-sections.
Further work
There is a need for a more detailed study of bolt and
sleeve distortions, to allow for construction tolerances.
The single-bolt oint showed a lower stiffness at ll stages
of loading than other joints. The addition of a bolt to a
joint increased its stiffness, but by a decreasing amount
for each successive bolt. This is clear when curves of
joints 3 and 4 are compared in Fig. 8, where the stiffness
of the latter is only slightly higher. The curve for joint
4 showed a slight gain in stiffness during the application
of load. The probable reason for this stiffness change is
that the bolt tolerances will have delayed the full number
of bolts from being in contact with their mounting sleeves
during the early stages of loading. This behaviour also
explains the low initial vertical component of force per
unit vertical deflection until either the bolt or the sleeve
has distorted sufficiently for its vertical diameter to
coincide with the sleeve invert.
A more comprehensive study is also needed of the
variation of strength when the geometry of the bolt holes
is varied. An increase in joint strength can obviously be
achieved by increasing the number of bolts per joint.
However, two factors reduce the benefit gained from the
additional bolts. First, the second and subsequent bolts
do not bear initially on the invert of their sleeves due to
the bolt hole tolerances, and additional lateral forces are
produced. This reduction in benefit appears to e
approximately 30 of the second bolt load capacity and
10 of subsequent bolt capacities. Second, there is a
further reduction of the additional load capacity of about33 if additional bolts are directly beneath each other.
This reduction is caused by the overlap of the stress
contours for the upper bolt with those for the lower bolt.
Magazine of Concrete Research, 1995 41, No. 171
8/14/2019 An Experimental Study of the Behaviour of Sleeved Bolt Connections in Precast Concrete Frames
http://slidepdf.com/reader/full/an-experimental-study-of-the-behaviour-of-sleeved-bolt-connections-in-precast 9/9
Mohamed and Jolly
Rotation: mrad
Fig. 9. Mom ent-rotation curves fo r the tests in series A and B
The reductions quoted apply to he specific configurations
tested, which are identical to those used by one particular
design consultancy.
There is potential for developing a more cost-efficient
joint if the steel link density is reduced. Steel links in the
joint region inhibit the formation of vertical cracks and
are therefore subjected to tensile stresses which may be
high enough to cause yield. Vertical cracking and failure
of the concrete column ensues. A substantial reduction
of link area was necessary to permit this type of failure
in the joints tested. Thicker sleeve walls and strongersleeve material are variations for further study to inhibit
the development of lateral forces in the column.
In addition to the experiments described in this paper,
finite element modelsare being developed that canredict
the different joints' behaviour up o failure. They represent
a potential meansof comparing the strengths of joints with
different geometries without resorting to large numbers
of expensive and time-consuming tests. Further details of
these modelling echniques, which the authors believe are
also applicable to resin-bonded and expanding anchor
bolts, will be given in a subsequent paper.
References
1. INSTITUTIONF S T R U C T U R A LE N G I N E E R S .anual o structural
joints in precast concrete. London 1978.
2 . JO L L Y . K. and PARSAA. Application of finite element design
to precast concrete beams. Proc. nd Int Conf on Computer Aided
Analysis and Designof Concrete Struciures.Pineridge Press New
York, 1990 pp. 61-76.
3 . ANSYS ngineering analysis system theoretical manual version
4.2. Swanson Analysis Systems Pennsylvania PA 1985.
4. MOHAMED . A. M . Behaviour of sleevedboltconnections in
precastconcretebuilding frames. PhD hesis University of
Southampton 1992.
Discussion contributions on this paper hould reach the editor by
29 December 1995
Magazine of Concrete Research, 1995 47 No. 171 127