Upload
vudiep
View
214
Download
0
Embed Size (px)
Citation preview
ACKAH & BEMPONG
50th Ghana Institution of Engineers (GhIE) Annual Conference, Koforidua, Eastern Region, Ghana, March 2018
GHIE@50: ENGINEERING GHANA’S SUSTAINABLE DEVELOPMENT
AN APPRAISAL ON THE USE OF GEOFOAM AS GEOTECHNICAL SOLUTION IN CONSTRUCTION
P. Ackah & K. G. Bempong [Associated Consultants Ltd., Accra]
REFEREED PAPER
Geofoam is preferred and increasingly used in engineering applications. This growth is due to the inherent material properties such as low density, good insulation, low hydraulic conductivity, strength and deformation properties that complement soil behaviour. It is also environmentally friendly and relatively cost effective. This paper is an overview of a specific geofoam material called Expanded Polystyrene (EPS), which is a type of rigid plastic foam. EPS is an ultra-lightweight geosynthetic material successfully used in reducing settlement below embankments, reducing lateral pressure on sub structures, and reducing stresses on underground utilities.
Introduction Construction on soft ground pose serious threat to civil engineering structures due to compressibility and low shear
strength of such foundation soils. In roadworks, large volume of suitable material is needed and if not available locally,
the quality material is transported over long haulage distances increasing the total cost of the project. Conventional
methods of filling with earth materials (heavyweight) is done in thin lifts with repeated compaction requiring
considerable time, construction equipment, and tests to ensure adequate level of compaction. In the case of soft soils
condition, after surcharging the soil, significant waiting time is required for dissipation of pore water pressures
subsequently resulting in primary consolidation. The use of lightweight fill on soft ground for mitigation of settlement
and potential instability has become increasingly popular with increased reporting of successful applications.
(Frydenlund & Aaboe 1996; Hovarth 1997; Stark et al. 2000, 2002; Mann & Stark, 2007; Arellano et al., 2010).
Lightweight materials include fly-ash, shredded tires, woodchips and expanded polystyrene (EPS) or extruded
polystyrene (XPS) geofoam. However with the exception of geofoam, these material have higher densities and
variability in their make-up (Foam-Control, 2017).
Table 1: Range in densities of typical lightweight fills (Elragi 2006)
Fill Type Range in Density (kg/𝒎𝟑)
EPS Geofoam 12 to 35
Foamed Concrete 355 to 770
Wood Fiber 550 to 960
Shredded Tires 600 to 900
Expanded Shale and Clay 600 to 1040
Fly-ash 1120 to 1440
Boiler Slag 1000 to 1750
History Geofoam was first used for settlement control in 1972 for the approach to Flom Bridge in Norway (Frydenlund, 1991).
The embankments rested on a 3m thick layer of peat over 10m of sensitive marine clay. Before using EPS geofoam,
ACKAH & BEMPONG
settlement rates of the order of 200-300 mm annually were recorded. Little or no settlement were recorded after
replacing with 1m thick EPS. Due to its success, its use spread to many countries such as USA, Japan and Canada.
In 1989, it was used in the USA for slope stabilization on Highway 160 in the Colorado State. The first EPS geofoam
(15m high) application in Japan was an embankment fill in 1985 (Yamanaka, et al., 1996) where 470 cubic meters
were utilized in the project. (Miki, H., 1996). Germany use of EPS geofoam in highway construction occurred in
March of 1995 to minimize the differential settlement of a bridge approach (Hillmann, 1996). EPS geofoam as a
lightweight fill material was first introduced in 1992 in Malaysia (Mohamad, 1996). Currently, EPS find its use in
road embankment, railway embankments, bridge abutment, widening vertical walls, widening embankments for steep
slopes, protection of structures etc.
Geofoam Geofoam mainly of two types (EPS or XPS) is a block or planar rigid cellular foamed polymeric material used in
geotechnical engineering applications (ASTM D4439). This geosynthetic product is approximately 1% the weight of
soil and less than 10% the weight of other lightweight fill alternatives as presented in Table 1. It can quickly be placed
with no need for compaction or waiting for consolidation to occur. It is flexible, easy to handle and often requires no
special equipment during construction. It is unaffected by adverse weather conditions and moisture. Relatively, the
EPS geofoam is the commonest material choice for most projects due to its cost effectiveness, environmentally
friendly and range of applications (Duskov 1997).
EPS Geofoam Manufacturing Figure 1 shows the processes the raw material or resin used for the molding of EPS geofoam are manufactured. The
end product of the manufacturing process results in EPS beads which are fed to an expansion vessel containing an
agitator and a steam input. The resin beads are expanded into "pre-puffs" by injecting steam. The expanded beads are
then released into a bed dryer to get rid of moisture. The pre-puffs are then stored in fabric storage bags to allow them
to stabilize to atmospheric temperature and pressure. They are then transferred into block mold of various sizes. Steam
is then injected into the mold under controlled pressure to soften the polymer structure of the pre-puff. The heat from
the steam and the applied pressure causes the pre-puffs to further expand. Since the block mold is a confined
environment, the expanding pre-puffs reduce the void space between individual particles and fuse (bond) together to
form an expanded polystyrene (EPS) block. Figure 2 shows the formation stages of EPS geofoam.
ACKAH & BEMPONG
Figure 1: BASF Inc. production method of Styropor
expanded polystyrene (EPS) slabs and blocks.
(Koerner 2005)
Figure 2: Formation stages of geofoam
(adapted after Mandal 2017)
Material Properties and Test Methods Geofoams properties and test methods are grouped into physical, mechanical, thermal and endurance categories. The
physical specification by ASTM standards for the various grades of EPS and XPS is as shown in Table 2. The
commonly manufactured dimensions of geofoam according to the ASTM D6817 is presented in Table 3.
Table 2: Physical property requirements of geofoam (ASTM D6817)
ACKAH & BEMPONG
Table 3: Commonly manufactured dimensions of geofoam by ASTM D6817 (after Koerner 2005)
Dimension(mm) EPS Types XPS Types
Length 1219-4877 1219-1743
Width 305-1219 406-1219
Thickness 25-1219 25-102
Design and Construction Considerations The densities of geofoam is much lower than that of water (1000 kg/m3). This may lead to uplift forces due to buoyancy
effect resulting in failure at the construction stage. Probable solution involves provision of adequate surcharge or
controlling ground water levels to ensure stability against uplift.
Loading-deformation behavior is generally determined by laboratory testing. The compressive strength attained for
geofoams at strain of 1% 5% and 10% are shown in Table 2. It can be observed that compressive strength increases
as density increases. Loading-deformation behavior is affected by temperature, with compressive strength increasing
with decreasing temperature and vice versa (BASF, 1987). Horvath (1994) reported that over a range of temperature
(0-450C), the variation in strength is about ±20% relative to results obtained from laboratory test.
Other than compression, EPS specimens are routinely tested for tension, flexure and shear. The Flexural strength
are used as a quality control test (i.e. how well the expanded polyhedral were fused during manufacture). The flexural
strength increases with density of the material in table 2. Tensile strength of EPS material can be an indication of the
quality of prepuff and any recycled EPS geofoam used. (Horvath 1995b). Tensile properties are similar to that
described by the Flexural strength. EPS fails in tension as a crack on tension side appears at the moment of failure.
EPS geofoam is susceptible to long term creep settlement when a constant stress level is applied. A number of
factors affect the creep behavior of EPS Geofoam, for example density. Creep deformations decrease with density
increase (Sun 1997). To this end, after the I-15 project, Utah Department of Transportation installed instrument arrays
to gather long term performance data of the geofoam fills to inform future designs and construction guidance for
geofoam construction.
The interface shear strength between geofoam to geofoam and geofoam to sand interfaces slightly decreases with
increasing normal stress. A relatively strong adhesive bond developed between that of geofoam surfaces and in place
concrete. The effect of density on interface strength of geofoam is however negligible. During construction, barbed
metal plates or binder plates are sometimes used to attach foam layers to each other to develop more interface shear
resistance. However, tests have showed the plates helped in maintain the blocks in position during placement and not
provide resistance. (Bartlett et al.2000; Sanders et al. 1996). During construction, placing of EPS geofoam must be
accurate. There should be minimum amount of gaps between the individual and successive geofoam layers. The
existence of gaps create stress concentration in the contact areas leading to excessive immediate strains and large
creep. This affect the overall settlement hence decreasing the design life of the pavement structure (Negussey and
Elragi, 2000a).
Polystyrene is inherently hydrophobic, hence preventing the absorption of water due to its closed cell structure.
However, water can enter the small voids between the fused particles. The amount absorbed depends on factors such
as type, density and duration of exposure to moisture. The absorption rate is about 1% per year in volume. (BASF
1978). This level of moisture absorption does not compromise the desired low density feature nor adversely affect the
strength and deformation properties of geofoam. Notwithstanding, increased moisture absorption degrades the thermal
conductivity of geofoam. In designing, conservative allowance is made considering a long term water content in the
EPS by 3-5% by volume which produce increase in thermal conductivity of between 15-25% (Horvath, 1993b). Even
under extreme cases of exposure to water leading to increment in the coefficient of thermal conductivity, EPS remains
an efficient thermal insulator compared to soil.
EPS is a poor conductor of heat (excellent heat insulator) consisting of approximately 98% air and 2% polystyrene
(BASF Corp 1997). Unlike geofoams, the thermal resistance (R-value) of soil and concrete are less than 0.1m3. Factors
such as temperature, density and moisture content significantly affect the R value (Van Dorp 1988; Negussey 1997;
Elragi, 2006).
Exposing geofoam to ultraviolet (UV) leads to discoloration and dusting on the surface. This diminishes the strong
bond (interface strength) between the geofoam and cast in place concrete. Researchers such as (Sheeley 2000; Bartlett
ACKAH & BEMPONG
et al.2000) has reported by removing the degraded surfaces by power washing before concrete pouring re-establishes
adhesion bonding and maximum interface strength.
At the construction stage, EPS geofoam must be protected from high temperatures, concentrated load, combustible
products (eg. carbon dioxide), potential spills of petroleum based fuels and solvents (eg. diesel fuel). EPS would melt
when exposed to temperatures in excess of 1500C. Again it will dissolve upon encountering petroleum products hence
requires a protective cap of concrete (100mm thick) or geomembrane. Since geofoam has no nutritional value (BASF
1990), it does not attract ants, termites and rodents. However, borate is added to geofoam to prevent insect attack and
boring intrusion (eg I-15 project). Flame retardant additive can also be added to EPS beads if desired. Table 4 shows
some of the chemical reagents and corresponding EPS resistant.
Table 4: Selected EPS Resistant Behavior (after Elragi 2006)
Source of Attack Resistant Behavior
Salt Water (Sea Water) Resistant
Alkali Solutions Soaps Resistant
Caustic Soda Solutions Resistant
Bitumen (Air Blown) Resistant
Alcohol Resistant
Micro Organisms Resistant
Paraffin Oil, Vaseline, Diesel Oil Limited Resistance
Petrol (Super grade) Non Resistant
Strong Oxidizing Acids Non Resistant
Fuming Sulphuric Acid Non Resistant
Organic Solvents Non Resistant
Standards and Design Manual Table 5 provides the guide and design considerations of the appropriate EPS geofoam properties. The three standards
for EPS geofoam is ASTM D6817 Standard Specification for Rigid Cellular Polystyrene Geofoam, D7180 Standard
Guide for the Use of EPS Geofoam in Geotechnical Projects and D7557 Standard Practice for Sampling of EPS
Geofoam Specimens. Similarly, some manufacturers also design their own conceptual guides for analysis and design
(Geo Tech 1998). There exist other design manuals for EPS such as Draft European standards (1998), Public Works
Research Institute (1992), Ministry of Construction and Norwegian Road Research Laboratory (1992). Again, Federal
Highway Administration (FHWA) and National cooperative highway research program (NCHRP) have two
documents (FHWA NHI-06-019 and NCHRP Project 24-11) detailing the design procedures for lightweight fills.
Table 5: Selected ASTM Standards for geofoam (after Negussey 1997)
Handling and Installation EPS Geofoam block are large but easy to handle. It can be field cut or trimmed to fit to size by either a chain saw or
hot wire. Material delivery is accompanied by a detailed set of installation drawings from the manufacturer.
Geofoam installation does not require much training but care should be taken not to allow for operation of
equipment directly on the surface of the geofoam fills. Generally, geofoam blocks should be staggered to interlock
Property Standard
Density C-303 , D1622
Thermal Conductivity C-177, C-518
Compressibility D-1621
Flexural C-203
Tensile/Adhesion D-1623
Vapor Transmission E-96
Absorption C-272
Thermal Expansion D-696
Combustion; O2 Index D-2863
Insulation Specification C-578
ACKAH & BEMPONG
so that joints between block layers are not made continuous. Blocks can be interconnected with barbed plates,
gripper plates or suitable adhesive.
Application and Use Major applications of EPS geofoam is based on consideration of its relevant engineering properties, cost, durability
and environmental factors. Horvath (1995) functional classification for EPS are lightweight fill, compressible
inclusion, thermal insulation and small amplitude wave damping. Table 6 presents some selected properties of
geofoam corresponding to an application of geofoam in solving geotechnical problems.
Table 6: Selected EPS geofoam applications (Hovarth 1992)
Application Density Compressibility Damping Insulation Cohesion
Slope stabilization
Embankments
Bridge Approaches
Earth Retaining Structures
Bridge Abutment
Flood Control Levees
Buried Pipes
Railways
Slope Stabilization
Figure 3 shows the use of EPS geofoam in slope stabilization. In a slope stability problem two forces namely driving
and resisting forces are considered. To ensure stability, the driving force is reduced by removing a portion of the
existing soil and replacing it with lightweight EPS geofoam. For a soil with friction, the foam is positioned in a way
to increase the overall factor of safety. This can be achieved by placing the foam fill to take the shape of the slip
surface. NCHRP 24-11 recommends a factor of safety of 1.5 against global slope stability failure to be used for design.
EPS
Original slope
Driving block
Resisting block
Center of rotation
Resisting berm
Figure 3: Slope stabilization using EPS Geofoam
An embankment of height 21m for an emergency truck escape ramp in Hawaii was constructed in 1994 using EPS
geofoam (Mimura and Kimura, 1995). Originally, the project was designed as an earth fill embankment with extensive
geotextile reinforcement and wick drains to overcome stability problems and to reduce settlement. At construction
stage, the pertaining site conditions were found to be worse than expected hence 13500 m3 of geofoam was used as
lightweight fill to replace the earth embankment. In 1997, the reconstruction of Interstate 15 (I-15) in Salt Lake City
Utah, utilized geofoams instead of mechanically stabilized earth (MSE) to improve stability of embankment. This
application of geofoam eliminated stability concerns at the bridge abutments and reduced the construction time by up
to 75% (Barlett et al. 2000).
ACKAH & BEMPONG
Embankment
Large settlements may be experienced upon constructing over soft or loose soils. EPS geofoam can be used to replace
soft soils or in place of heavy fill materials to reduce loading on underlying soils and adjacent structures. In the I-15
project, the design of MSE embankments loads predicted induced primary settlements of about 1m which exceeds all
strain tolerance for buried utilities (Bartlett et al. 2000). Replacement of MSE with EPS geofoam reduced the large
settlement to minimum. It also enabled buried utilities to remain in-place, eliminating possible expensive interruption,
replacement, or relocation. Another application of the EPS geofoam was to mitigate settlement (300mm) of bridge
approach embankments constructed over compressible 30m thick layer of silty clay soils at Maine Turnpike Beech
Ridge overpass (Snow & Nickerson 2014). Another advantage for the geofoam used was to allow the overpass to be
built on a fast-track schedule.
Soft soil
EPS GEOFOAM
pavement
Base
Sand leveling-layer
Concrete slab
Figure 4: Building embankment on soft soil using EPS geofoam.
Foundation
EPS geofoam can be used as a compensating foundation to reduce the load on underlying compressible soils and
minimize building settlement along with potential bearing capacity problems (EPS Industry Alliance, 2012). The
foundation of an emergency staircase of an overpass was reported by Ojima et al 1996. The existing ground was
underlain by soft clay. Deep foundation could not be considered due to the existence of a four meter diameter sewer
pipe below the footing of the staircase. An alternate solution was utilizing 3m height EPS geofoam. In Port-Said,
Egypt the overburden soils is underlain by very thick layer of soft clay. Abdelrahman and Elragi (2006) used a physical
model to study the behavior of EPS with different thickness and densities over soft clay in order to reduce settlement.
They concluded that construction on soft clay which EPS as a lightweight material as replacement material of soft soil
beneath a raft foundation is an effective way to control settlements and moments.
Buried Pipes and Culverts
The low mass density ranging between 10-40 kg/m3 of geofoam reduce vertical and horizontal loads on buried pipes
and culverts under highway fills (Vaslestad, 1990; Sun et al., 2009). The earth pressures imposed on deeply buried
pipelines and culverts is significantly affected by soil arching. In the case of geofoams, “imperfect trench” method
involves installing compressible geofoam inclusion above the relatively rigid pipeline or culvert as shown in figure 5.
ACKAH & BEMPONG
EPS Geofoam
pipe
Ground
Figure 5: Stress reduction on buried pipe utilizing EPS geofoam.
Two full uplift tests conducted by Bartleet & Lingwall (2014) concluded that geofoam cover system developed about
four times less uplift force than that of the corresponding soil backfill. Similar results were reported by Choo et al
(2007), where 30-60 % reduction in lateral soil-pipe forces was recorded when geofoam was used as a lightweight
trench backfill cover for pipe undergoing horizontal displacement.
Retaining and Buried Walls
Geofoam is preferred for compressible inclusions because it is non-biodegradable. Inclusion of EPS geofoam as
backfill behind retaining and buried wall greatly reduces the lateral earth pressure on the structure (Ertugrul &
Trandafir 2011, 2013). For compressible inclusion applications, stiffness of the geofoam in the primary direction of
displacement is the critical property. Hovarth 1998 reported that the minimum EPS density of economical balance
between stiffness and durability is approximately 12kg/m3.
Soil cover or pavement
section
Retaining wall
or Abutment
Drain pipe
Granular backfill
EPS GEOFOAM
Figure 6: Geofoam retaining wall
ACKAH & BEMPONG
Cases of EPS Failures Reported applications of geofoam in geotechnical works include embankment and pavements (Hovarth 1997; Stark
et al. 2000 2002; Frydenlund & Aaboe 1994), slope stability (Mann & Stark 2007; Arellano et al., 2010). However
failures in its project application have also been reported (Horvath 1999; Duskov 1997).
Hovarth (1999) reported on number of failures involving EPS block geofoam used as lightweight fill, primarily for
roads. He attributed the cause of failures to lack of thorough understanding of all factors that must be considered when
designing and specifying block molded EPS as a geofoam product for such applications.
Duskov (1997) reported on the premature pavement failure which occurred in Matlingeweg, Rotterdam. EPS
geofoam was incorporated in the reconstruction of the road to reduce the resulting settlements of the existing subgrade.
Since the settlement were not uniform, a portion of the reconstructed road used only a single layer of EPS
blocks 500 mm thick. The remaining portion used two layers of blocks. One month after the road was opened to
traffic, cracking was observed on the portion of the road with 500 mm thick EPS subbase. Investigation conducted
revealed the EPS blocks had shifted at their joints. Movements between blocks in the vertical (up to 5 mm) and
horizontal (resulting in gaps as much as 20 mm wide ) were found. Movements resulting in failure occurred due
to lack of full contact and interaction between blocks.
A case of unexpected block flotation was reported in Thailand (Hovarth 1999). In Thailand, during the service life
of the project, occurrence of flood caused EPS geofoam used as a fill in pavement structure to float. This damaged the
overlying pavement structures requiring reconstruction.
Cost Analysis Comparison of cost between earth fills and geofoams requires a complete review of the conditions and geometry.
Beyond the easily determined direct costs, less tangible costs (improved life cycle costs to pavement, reduced
construction time, elimination of utility relocation) must also be included in the evaluation. Again other factors such
as availability locally and knowledge in its application may influence the total costing. An attempt is made by Lin et
al (2010) to compare labor and material prices for soil and EPS geofoam. Figure 7-8 adopted after Lin et al (2010)
illustrates the design for 800m long roadway expansion project in Taipei.
Figure 7: Traditional design
ACKAH & BEMPONG
Figure 8: EPS design
In the traditional design, earthen material is required to fill the expansion volume as shown in figure 7. Likewise, EPS
is used as an alternative fill material in figure 8. Table 8-9 compares the cost benefits of using tradition method or
EPS in 800m long roadway expansion project in Taipei.
Table 7: Cost analysis of traditional soil filling.
Item Unit
price
NT$
Retaining wall (Type A, average
H =3.1 m)
Retaining wall (Type B, average
H =3.6 m)
Quantity Price NT$ Quantity Price
NT$ Excavation 111 9.68 m3 1,074 13.84 m3 1,536
Backfill 672 6.08 m3 4,086 8.8 m3 5,914
Permeable material
backfill
500 0.34 m3 170 0.4 m3 200
Rebar f y ≥ 2,800 9,955 0.16 t 1,593 0.14 t 1,394
Foundation
formwork
372 0.8 m2 298 1.18 m2 439
Structure formwork 372 6.21 m2 2,310 7.18 m2 2,671
Concrete 80 kg / cm2 1,520 0.27 m3 410 0.41 m3 623
Concrete 240 kg /
cm2
1,770 2.33 m3 4,124 3.98 m3 7,045
Rail pile, length = 6
m
2,585 1 m width 2,585 —
Energy dissipation
block
256 1-m width 256 1-m width 256
Type B guardrail 1,502 1-m width 1,502 1-m width 1,502
Rebar f y ≥ 4,200 9,998 — 0.13 t 1,300
H-beam, length = 8 m 11,500 — 1-m width 11,500
Backhoe 6,000 0.4 day 2,400 0.4 day 2,400
ACKAH & BEMPONG
Crane 10,000 0.3 day 3,000 0.3 day 3,000
Manpower 2,000 2 manpower-
day
4,000 1.8 manpower-
day
3,600
Total price/m
28,438 NT$/m 43,380 NT$/m
Table 8: Cost analysis of filling with EPS geofoam.
Item Quantity Unit
Unit price NT$
Price NT$
EPS backfill 2 m3 2,200 4,400
H-beam 1 m 11,500 11,500
RC slab 1.5 m2 1,000 1,500
RC foundation 0.5 m3 2,000 1,000
Gravel permeable material 0.5 m3 500 250
Drainpipe 1 m 50 50
Energy dissipation block 1 m 256 256
Type B guardrail 1 m 1,502 1,502
Concrete 240 kg / cm2 1.3 m3 1,770 2,301
Backhoe 0.1 day 6,000 600
Crane 0.05 day 10,000 500
Manpower 0.6 manpower-day 2,000 1,200
Total price/m 25,059 NT$/m
From the analysis, it was observed that the cost for using soil as fill material were higher for both type A & type B.
This was estimated to cost NT$ 28,438/m (US$960.9) and NT$43380 (US$1465.8) respectively. However, the use of
EPS for construction reduced the cost to NT$25,059 (US$846.7).
Conclusion The use of geofoam technology provides varying applications in embankment fill, retaining wall backfill, bridge
abutment, compensating foundation, slope stabilization. The technology is limited because the material cost only is
typically more expensive than soil on a cost-per-unit-volume basis. However, in comparing the overall cost of the
project, for example reduced field installation and construction cost, accelerated construction, minimum field quality
control testing and no relocation of utilities: geofoam is a cost effective alternative and recommended as lightweight
fills over soft ground and protecting underground structures. It is therefore proposed that cheaper and faster ways
Vertical EPS Geofoam embankment fill Bridge pier extending through EPS geofoam fill
ACKAH & BEMPONG
could be employed in difficult construction sites in Ghana with the application and use of Geofoam technology.
Furthermore, it could be employed for reinstating excavations across roads where services are buried to reduce the
possibility of settlement as seen around on our roads.
Protecting buried pipes in transportation infrastructure using EPS Geofoam
Stockpiled EPS Geofoam on site using Backhoe Installing geomembrane over EPS Block on the
Roaring River Slough project, USA.
Figure 9: Some applications of EPS geofoam in construction
ACKAH & BEMPONG
Carousel MALL, Syracuse NY Norway 1987, Extreme flood event
Figure 10: Cases of EPS failures
References
Abdelrahman, G.E. and Elragi, A.F. (2006). “Behavior Improvement of Footings on Soft Clay utilizing
Geofoam,” The 10th Arab Structural Engineering Conference, 13 -15 November, Kuwait.
Arellano, D., Tatum, J. B., Stark, T. D., Horvath, J. S., and Leshchinsky, D. (2010). “A Framework for the
Design Guideline for EPS-block Geofoam in Slope Stabilization and Repair,” Proc., 89th TRB Annual
Meeting, Paper No. 10-2629, Washington, D.C., USA.
ASTM D4439. “Standard Terminology for Geosynthetics” West Conshohocken, United States.
ASTM D6817. “Standard Specification for Rigid Cellular Polystyrene Geofoam,” West Conshohocken, USA.
ASTM D7180. “Standard Guide for the Use of EPS Geofoam in Geotechnical Projects,” West Conshohocken,
USA.
ASTM D7557. “Standard Practice for Sampling of EPS Geofoam Specimens,” West Conshohocken, USA.
Bartlett, S. (2000). “I-15 reconstruction geofoam road embankment design,” Proc., Light Weight Backfill
Construction Method Seminar Paper Corpus, S.L.C., Utah.
Bartlett, S., Negussey, D., Kimble, M. and Sheeley, M. (2000). “Use of Geofoam as Super-Lightweight Fill for
I-15 Reconstruction,” Proc., Transportation Research Board 79th Annual Meeting, TRB Washington, D.C.,
USA.
Bartlett, S.F., and Lingwall, B.N. (2014). “Protection of Pipelines and Buried Structures Using EPS Geofoam,”
Geotechnical Special Publication. DOI: 10.1061/9780784413401.054.
BASF (1978). “Styropor Technical information,” Building construction; Highway construction, Insulation at
earth level; Pavement insulation: Guidelines. Document No. TI-1801e, BASF, Ludwigshafen, Germany.
BASF (1987). “Strength characteristics of EPS thermal insulation,” Technical Bulletin E-3, Parsippany, NJ,
USA.
BASF (1990). “Guidelines for use of EPS board products in building construction,” Technical Bulletin E-I,
Parsippany, N J, USA.
BASF Corp. (1997). “Styropor Technical Information” Technical Information, BASF Corp., Germany.
Choo Y.W., Abdoun, T.K., O’Rourke, M.J. and Ha, D. (2007). “Remediation for Buried Pipeline Systems
under Permanent Ground Deformations,” Soil Dynamics and Earthquake Engineering, vol. 27, pp 1043-
1055.
Draft European Standard (1998). European Committee for Standardization, Brussels.
Duskov, M. (1997). “EPS as a Light-weight Sub-base Material in Pavement Structures,” PhD. Thesis, Delft
University of Technology, Netherlands.
Elias, V., Welsh, J., Warren, J., Lukas, R., Collin, J. G., and Berg, R. R. (2006). Ground Improvement
Methods- Volume I. NHI-06-020.
ACKAH & BEMPONG
Elragi, A. F. (2006). “Selected Engineering Properties and Applications of EPS Geofoam,” Dissertation of
Doctor of Philosophy, State University of New York, New York.
EPS Industry Alliance (2012). “Expanded Polystyrene (EPS) Geofoam Applications and Technical Data,”
Accessed on January 15, 2018 at http://www.civil.utah.edu/bartlett/Geofoam
Ertugrul O.L. and Trandafir A.C. (2011). “Reduction of Lateral Earth Forces Acting on Rigid Non-Yielding
Retaining Walls by EPS Geofoam Inclusions,” ASCE Journal of Materials in Civil Engineering: 0000348
DOI: 10.1061/ (ASCE) MT.1943-5533.
Ertugrul O.L. and Trandafir A.C. (2013). “Lateral Earth Pressure on Flexible Cantilever Retaining Walls
with Deformable Geofoam Inclusion,” Engineering Geology, pp 23-33.
Frydenlund, T. E. (1991). “Expanded Polystyrene-A Lighter Way Across Soft Ground,” Norwegian Road
Research Laboratory, Internal Report, No. 1502, Oslo, Norway.
Frydenlund, T.E. and Aaboe, R. (1996). “Expanded Polystyrene- The Light Solution,” Proc. Intl., Sym. on EPS
Construction Method, Tokyo, Japan, pp. 31-46.
GeoTech, (1998). “Geofoam Compressible Inclusions: A Conceptual Guide to Analysis and Design,” GeoTech
System Corporation, VA, USA
Geofoam (2018). “Foam-Control Geofoam,” Accessed 11 Jan. 2018 at: https://www.geofoam.com.
Geofoam Research Center (2000). “Case History of I-15, Salt Lake City, UT,” Syracuse University Syracuse,
NY.
Hillmann, R. (1996) “Research projects on EPS in Germany: Material Behavior and Full Scale Model
Studies”, Proc. Intl., Sym. on EPS Construction Method, Tokyo, Japan, pp. 105–115.
Horvath, J. S. (1992). “Lite‟ Products Come of Age; New Developments in Geosynthetics” ASTM
Standardization News, American Society for Testing and Material, USA, Vol. 20, No. 9, pp. 50-53.
Horvath, J. S. (1993b). “Geofoam Applications in Residential Construction,” Paper presented at the National
Association of Home Builders 49th Annual Convention & Exposition, Las Vegas, Nevada, USA.
Horvath, J. S. (1995b). “Geofoam Geosynthetic,” Horvath Engineering, P. C., Scarsdale, New York, USA.
Horvath, J. S. (1997). “The Compressible Inclusion Function of EPS Geofoam”, Geotextiles and
Geomembranes 15, (1-3), pp.77-120.
Horvath, J. S. (1998). “The Compressible Inclusion Function of EPS Geofoam: Analysis and Design
Methodologies,” Research Report, (CE/GE–98–2), Manhattan College, NY, USA.
Horvath, J. S. (1999a). “Lessons Learned from Failures Involving Geofoam in Roads and Embankments,”
Manhattan College Research Report No. CE/GE-99-1, Manhattan College, NY, USA.
Koerner, R. M. (2005). “Designing with Geosynthetics,” 5th edition, Pearson Prentice Hall, Upper Saddle
River, New Jersey, 796 pgs.
Lin, L.K., Chen, L.H. and Chen, R. H. L. (2010). “Evaluation of Geofoam as a Geotechnical Construction
Material,” Journal of Material in Civil Eng., Vol. 22 (2):160-170.
Lingwall, B. and Bartlett, S.F. (2007). “Conceptual Design and Modeling: EPS Geofoam Cover System for
Buried Pipelines,” Technical report prepared for Questar Gas Corporation, Salt Lake City, Utah, 22 pp.
Lingwall, B. and Bartlett, S. (2014). “Full-scale testing of an EPS geofoam cover system to protect pipelines at
locations of lateral soil displacement,” Pipelines 2014, pp 605-615.
Miki, H. (1996). “EPS Construction Method in Japan,” Proc. International Symposium on EPS Construction
Method, Tokyo, Japan, pp 1–7.
Mann, G. and Stark, T.D. (2007). “Slope stabilization using Geofoam,” Proc. of Specialty Conference GEO-
Denver, ASCE, Denver, CO, 10p.
Mandal, J.N., 2017. Geosynthetics Engineering: In Theory and Practice. Lecture notes
Mohamad, E. (1996). “History of EPS as embankment fill in Malaysia under PIC and its future,” Proc.
International Symposium on EPS Construction Method, Tokyo, Japan, 257–264.
Mimura, C. S. and Kimura, S. A. (1995). “A Lightweight Solution,” Geosynthetics Conference Proceedings,
Vol. 1, Nashville Tennessee, USA, pp. 39-51.
Negussey, D. (1997) “Properties & Applications of Geofoam,” Society of the Plastic Industry, Inc.,
Washington, D.C., USA.
Negussey, D. and Elragi, A. (2000b) “Strain Rate Effect on the Uniaxial Compression Behavior of EPS
Geofoam,” Internal Report AE2-00, Geofoam Research Center, Syracuse University, Syracuse, NY.
Norwegian Road Research Laboratory (1992). “Expanded polystyrene used in road embankments,” Design,
Construction and Quality Assurance. Form 482E. Oslo.
ACKAH & BEMPONG
Ojima, K., Okazawa, Y., Matunawa, I., Kitada, I., Tutiya, M., Yamaji, H. and Kojima, K. (1996). “Use of EPS
in the Foundations of an Emergency Staircase of an Overpass,” Proceedings of the International Symposium
on EPS Construction Method, Tokyo, Japan, pp. 343-347.
Public Works Research Institute of Ministry of Construction, and Construction Project Consultant, Inc., (1992).
“Design and Construction Manual for light Weight Fill with EPS” The Public Works Research Institute,
Japan.
Sanders, R. L. (1996). “United Kingdom Design and Construction Experience with EPS,” Proceedings of the
International Symposium on EPS Construction Method, Tokyo, Japan, pp. 235-246.
Sheeley, M. (2000). “Slope Stabilization Utilizing Geofoam” Master’s Thesis, Syracuse University, Syracuse,
NY, USA.
Stark, T. D., D. Arellano, J. S. Horvath and D. Leshchinsky (2000). "Guidelines for Geofoam Applications
in Embankment Projects,” Interim (Phase I) Rpt. - NCHRP. Proj. No. 24-11, TRB, Washington, D.C.
Stark, T. D., D. Arellano, J. S. Horvath and D. Leshchinsky (2002).”Guidelines for Geofoam Applications
in Embankment Projects,” Final Rpt. - NCHRP Proj. No. 24-11, TRB, Washington, D.C.
Stark, T. D., D. Arellano, J. S. Horvath and D. Leshchinsky (2004).”Guideline and Recommended
Standard for Geofoam Applications in Highway Embankments,” NCHRP Report 529 (Proj. 24-11), TRB,
Washington, D.C.
Sun, M. (1997). “Engineering behavior of geofoam (expanded polystyrene) and lateral pressure reduction in
substructures,” PhD. Thesis, Syracuse University, Syracuse, NY, USA.
Snow, C. L. and Nickerson, C. R. (2004). “Case Study of EPS Geofoam Lightweight Fill for Settlement
Control at Bridge Approach Embankment,” Proc., Geotechnical Engineer.
Van Dorp, T. (1988). “Expanded Polystyrene Foam as Light Fill and Foundation Material in Road
Structures,” International Congress on Expanded Polystyrene, Milan, Italy.
Vaslestad, J. (1990) “Soil Structure Interaction of Buried Culverts,” Ph. D. Dissertation, the Norwegian
Institute of Technology, Norway.
Yamanaka, H., Onuki, T., Katsurada, H., Kitada, I., Kashima, K., Takamoto, A., and Maruoka, M. (1996).
“Use of vertical wall-type EPS elevated filling (H = 15 m.) for bridge abutment backfill,” Proc. International
Symposium on EPS Construction Method, Tokyo, Japan, pp. 223–233.
Contact details
Name of Principal Author: Priscilla Ackah
Address: Associated Consultants, Box M259, Accra
Tel: +(233)-302-237-528 Fax: +(233)-302-237-500
Email: [email protected]
Name of Second Author: Kwabena Bempong
Address: Associated Consultants, Box M259, Accra
Tel: +(233)-302-237-528 Fax: +(233)-302-237-500
Email: [email protected]