Upload
yxp2237
View
221
Download
0
Embed Size (px)
Citation preview
8/3/2019 An Application for Upgrading the Reliability of Electrical System in an Industrial Plant
1/5
The Online Journal on Electronics and Electrical Engineering (OJEEE) Vol. (3) No. (3)
Reference Number: W11-0068 443
An Application For Upgrading The Reliability
of Electrical System in An Industrial Plant
H. Can
Tupras Izmit Refinery, Project Department, Kocaeli, Turkey
Dr. C. Perdahci
Department of Electrical Engineering, Kocaeli University, Kocaeli, Turkey
Abstract-In this paper, respectively, the requirement for
digital protection relays, current status of the industrial
plants, protective functions of digital protection relays,
relay types, electrical equipments and remote monitoring
relays were examined in an industrial plants. A large-scale
industrial plants must be robust to operate efficiently and
without interruption of power network. Unreliable
electrical network can cause unexpected power
interruptions. Interruptions will damage to operate the
plants and these may also cause significant financial loses.
To make reliable electrical system of the plants, provides
important advantages in terms of operation and
maintenance. In industrial plants examined for this
purpose to establish the digital protection relays and
power relays with the method of monitoring via SCADA
system to increase the reliability of an application is
examined.
Keywords-Protection relays, reliability
I. INTRODUCTION
Today one of the most important factors which ensure that
industrial plants have sustainable production is uninterrupted
and high-quality provision of power to the plant. Ill-timed
power failures due to the own structure of the facility and
national network of which it is a part have significant impact
on the production of facility. The power failures also have
significant financial losses. Therefore the less power failures,
the less financial losses there will be.
Another reason of the significant of power failures is that
the interruption experienced during operation can damage
equipment and due to this damage they can be completely
non-operable and in need of repair. If there is no replacementfor the equipment at the facility, the damage can be
multiplied.
Parallel to the experienced technological developments,
large industrial facilities renew their infrastructures so as to
improve the reliability of their electrical systems (1). One of
the best-known methods is to install digital protective relays
on engines, transformers and entry-exit coupling cells and
corrections of failures at minimum location at minimum time.
At large industrial facilities which have protective functions
assigned to digital protective relays, as well as different
voltage levels and a widespread distribution infrastructure,
high-level of protection can be provided with properselectivity efforts; however, failure and measurement data of
these equipment are transferred to SCADA system at main
focus and they can be used in an effective manner; it also
helps optimize the reliability of the facility. In addition, with
the failure record data obtained from relays, the failure
characteristic of the equipment can be generated and potential
failure risks can be estimated for the future [2].
In the industrial facility, which is the reference of thisstudy, protective equipment have been used since its
foundation which have the highest technology. However, there
are no digital protective relays in several engines,
transformers, entry-exit and coupling cells of the facility. This
application covers replacement of current mechanical relays
with digital protective relays and installation of digital
protective relays to those which had no relays on.
II ELECTRICAL SYSTEM of THE FACILITY
Electricity production capacity of the plant is 85MW and
maximum consumption is 57MW; it also has an auto-producer
license. The facility can satisfy all or part of its own electrical
power need from its production; it can also provide theelectrical power needed from outside as it is connected to the
interconnected network. The purpose of the facility in
producing its own electricity is to create alternatives for
meetings its electricity need rather than selling it to third
parties. As can be understood from the single line graphic of
the facility, all busbars have two supplies. The power is being
distributed to three secondary distribution stations at 11kV
and 3.3kV voltage levels from closed switch station. These 6
secondary distribution stations distribute to 14 secondary
stations. The voltage levels of secondary distribution stations
are 11kV or 3.3kV. There are digital protective relays at
engine, transformer, entry-exit or coupling cells; however
these relays have been established at different times and with
different models since the foundation of the facility [3].
1. Current busbars and protective relays
34,5kV, 11kV and 3,3kV distribution stations which
constitute the distribution infrastructure of the facility are
given in Table 1.
8/3/2019 An Application for Upgrading the Reliability of Electrical System in an Industrial Plant
2/5
The Online Journal on Electronics and Electrical Engineering (OJEEE) Vol. (3) No. (3)
Reference Number: W11-0068 444
Distribution
Stations
Voltage
Level
Supplying
Busbar1 9HS-1 34,5kV TEK-2
2 9MMS-1 11kV 9HS-1
3 9MMS-2 11kV 9HS-1
4 9MMS-3 11kV 9HS-1
5 10R-102A 3,3kV 9HS-1
6 10R-6A 3,3kV 9HS-1
7 10R-18A 3,3kV 9HS-1
8 PLANT-5-6-7-8 3,3kV 9MMS-1
9 PLANT-21-25-36 3,3kV 9MMS-1
10 9MS-1 3,3kV 9MMS-1
11 PLANT-6 3,3kV 9MS-1
12 PLANT-73-74 3,3kV 10R-102A
13 10R-102 3,3kV 10R-102A
14 PLANT-33 3,3kV 10R-102A
15 10R-6 3,3kV 10R-6A
16 10R-8 3,3kV 10R-18A
17 47MMS-1 11kV 9MMS-2
18 47MS-1 3,3kV 47MMS-1
19 10MS-1 3,3kV 9MMS-320 63MMS-1 11kV 9MMS-3
21 63MS-1 3,3kV 63MMS-1
Table 1 : Distribution Stations
2. System equipment with digital protective relays
installed
Digital protective relays will be used for the purpose of
protecting several equipment in the facility and improving the
reliability of electrical system. These relays will be installed
on engine feeders, transformer feeders, entry-exit and
coupling cells [3].
Digital protective relays will be installed on 10R-6 and10R-6A power switch building, 10R-102A power switch
building, Plant 25-36 , Plant 5-6-7-8 , Plant 47-48 , Plant 26,
Plant-33, Plt 9 and 34,5kV switch facility engine feeders,
transformer feeders, entry-exit and coupling cells shown in
Table 1 [2].
Digital protective relays have been applied on more than
200 medium-voltage system equipment; those installed on 47-
48 unit are given in Table 2 [3]. 47-48 (Hydrocracker) unit
constitutes one of the most important processes of the facility.
PLANT 47/48 UNIT SWITCH ROOM
CellNo Name Of TheEqupment Description of Equipment
11 kV BUSBAR 47 MMS-1
5L 9GM-601A 11kV 1200kW Pump Motor
4L 47GM-2A 11kV 1550kW Pump Motor
3L 47KM-2A
11kV 3500kW Compressor
Motor
2L
47TMM-1A
Trafosu Fideri 11kV to 3,5kV 6,3MVA
1L Incoming L INCOMING LEFT
0 BUS TIE
0 BUS RISER
1R Incoming R INCOMING RIGHT
2R
47TMM-1B
Transformer
Feeder 11kV to 3,5kV 6,3MVA
3R 47KM-2B
11kV 3500kW Compressor
Motor
4R 47KM-2C
11kV 3500kW Compressor
Motor
5R 47GM-2B 11kV 1550kW Pump Motor
6R 9GM-601B 11kV 1200kW Pump Motor
3,3 kV BUSBAR
11L 47GM-4C 3,3kV 153kW Pump Motor
9L 9KM-601E3,3kV 120kW CompressorMotor
8L 9KM-601C
3,3kV 120kW Compressor
Motor
7L 9KM-601A
3,3kV 120kW Compressor
Motor
6L 47GM-302A 3,3kV 120kW Pump Motor
5L 48KM-1A
3,3kV 315kW Compressor
Motor
4L
47TML-1C
Transformer
Feeder 3,3kV to 0,4kV 2MVA
3L EMPTY
2L
47TML-1A
Transformer
Feeder 3,3kV to 0,4kV 2MVA
1L Incoming L INCOMING LEFT
0 BUS TIE
0 BUS RISER
1R Incoming R INCOMING RIGHT
2R
47TML-1B
Transformer
Feeder 3,3kV to 0,4kV 2MVA
3R
47TML-1D
TransformerFeeder 3,3kV to 0,4kV 2MVA
8/3/2019 An Application for Upgrading the Reliability of Electrical System in an Industrial Plant
3/5
8/3/2019 An Application for Upgrading the Reliability of Electrical System in an Industrial Plant
4/5
The Online Journal on Electronics and Electrical Engineering (OJEEE) Vol. (3) No. (3)
Reference Number: W11-0068 446
87M: Engine differential protection*
*Engine differential protection is not compulsory;
nevertheless, differential protection is recommended on
engines higher than IMW power. Differential protections at
powerful engines bigger than IMW at this facility have been
enabled. Protection functions employed on transformers:
49: Motor Thermal protection
50, 50N: Instant opening
51, 51N: Opening at overflow
Inrush restraint (valid for 50,50N, 51, 51N, 67, 67N functions)
74: Alarm
74TC: Trip Circuit Supervision
87T: Transformer Differential Protection*
*at transformers of 5MVA and higher at the facility 49: used in relays at primary sides of thermal protection
transformers; not enabled on relays at secondary side.
The protection functions defined in digital protection relays
installed on transformer feeders have been enabled and
adjustment values have been given. 67, 67N: Directional
Overflow Protections have been enabled as these generators
exist at 11kV outlets of 34,5/ 11kV transformers in the
facility; which means at facility entrances, and as it is not
possible to feed from TEA and generators alike. In addition,
32G, 32P: Inverse Power Protections are also enabled.
Protection Functions used in the Generators: 27 : Low Voltage Protection
32R: Diverse Power Protection
46 : Current Protection for Negative Component Phase Balance
49 : Thermal Protection
50, 50N : Instant turn-on protection (Short circuit protection)
51, 51N(51G) : Over-current protection (reverse time protection)
59 : Over-Voltage Protection
81 : Low / Excessive Frequency protection
87G : Generator Differantial Protection (G Generator)
3.1 Measurement with Digital Protection Relays
As the digital protection relays to be used also have
measurement functions, the demanded cells will also be
measured. In addition to protection, which is their mainfunction, digital protective relays are able to measure the
current, voltage and frequency values of the cells on which
they are installed this cell can be an engine feeder,
transformer feeder or entry-exit and coupling feeder. In
addition, they can transmit these measured values to SCADA
system, just like they transmit protection functions to SCADA
system. As a result, in addition to their major function which
is protection, these relays used within the Refinery Plant will
transfer such values as the current voltage frequency of the
equipment to which they are installed to the SCADA system
to make the electrical system of the plant more traceable and
reliable, as electrical systems which can be monitored are
always more reliable. Measurements which will be made by
relays are as follows: [2]
Component values with symetry for voltages
Voltages (VL1,VL2,VL3,VL1L2,VLL1L3,VL2L3)
Current power, Reactive power, Visible power (Eachphase seperately and totally)
Aktive and Reactive Energy
Power Factor and Frequency
Working hour gauge, breaker opener gauge
Measuring of average operating temperature in case of
overload
IV. DIGITAL PROTECTION RELAYS USED
A. Local-control multi-functional protective relay 7SJ64
Digital, multi-functional SIPROTEC 4 7SJ64 relays are
multi-faceted devices designed for protection, control and
monitoring of busbar relays. These devices can be used as lineprotection in grounded, low-resistant grounded, non-rounded
or compensated neutral point-structured networks. Devices
are proper for radial, eyed or interconnected networks and
single or multi-edged fed lines. 7SJ64 has been equipped with
engine protection function which can be adjusted for every
size of non-synchronize engines. 7SJ64 has necessary
functions for command of breakers at1 breaker busbars or
monitoring of protective, breaker positions and flat busbar
applications. Therefore the device can be used universally.
7SJ64 provides after-effect protective features for differential
protective arrangements of the lines, transformers, generators,
engines and busbars in all voltage levels.
Protection of non-directional overflow is the basic function
of the device. There are three fixed-time overflow protective
elements and one inverse time overflow protective component
for phase currents and ground current. Several curves at
different standards are provided for inverse-time overflow
protective elements.[5]
B. Differential protective relay 7UT613
SIPROTEC 4 7UT613 digital differential protection
provides a fast and selective short circuit protection for
transformers at all voltage levels, rotary machines, serial and
shunt reactors or short lines and mini busbars consisting of 2
to 5 feeders. In addition, it can also be used as a single-phaseprotection for busbars up to 9 or 12 feeders (depending on the
version). Specific application can be customized which will
ensure the most appropriate adaptation to the protected object.
The major advantage of differential protection principle is
that it can perform instant turn-on at a short circuit failure at
any point within the protected area. The current transformers
at the edges of protected object limits the protected area
towards the network. This certain limit is the main reason for
which the differential protection mechanism shows such an
ideal selectivity. [6].
1. Remote Monitoring of Digital Protective Relays
All established protective relays will be monitored fromPower CC SCADA system which is installed in Plant-9. All
trips, alarms, external data and analogue value signals will be
8/3/2019 An Application for Upgrading the Reliability of Electrical System in an Industrial Plant
5/5
The Online Journal on Electronics and Electrical Engineering (OJEEE) Vol. (3) No. (3)
Reference Number: W11-0068 447
sent to Power CC scada system from these relays. Only the
Power CC in Plant-9 will be controlled by SCADA system
and switch will be opened and closed from there [2].
V. CONCLUSION
As a result of this paper which aimed at improving the
reliability of current electrical system, the system has been
made more reliable with the protection functions from which
digital protective relays are entered. Protective functions have
been parametered as required according to the type and
importance of the equipment to which the relays are
connected, and it has been ensured that the system makes less
trips. In addition, remote monitoring of the system has
allowed for receiving instant information from relays which
turn on or give alarm and thus faster intervention.
In this study, not only the electrical system of the plant hasbeen made more reliable, but the plant also enjoyed several
advantages such as costing, operation and maintenance.
REFERENCES
[1] Xiaoqiang, Z., "Energy&Utilities Control System ofRefinery",2009 third International Symposium on
Intelligent Information Technology Application, 2009,
408-411
[2] etinkaya, B, Akduman, B, Tpra Izmit Role
Koordinasyon Raporu, Siemens A.S., Kocaeli, 2009
[3] TUPRA General Project Design Specification P1,
TUPRA, Kocaeli, 2006
[4] Koruma Rolelerinin Fonksiyon Acklamalar, Siemens E
E&C PTI, Istanbul, 2008
[5] SIPROTEC 7SJ62/64 Kullanm Klavuzu C53000-
G115A-C207-1, SIEMENS AG, Istanbul, 2009
[6] SIPROTEC 7UT613/63x Kullanm Klavuzu V4.60,
SIEMENS AG, Istanbul, 2006