Sponsored by the U.S. Department of Defense © 2004 by Carnegie Mellon University Version 1.0 page 1 Pittsburgh, PA 15213-3890 Carnegie Mellon Software Engineering Institute An Acquirer’s Guide to Navigating Contractor Data Jeannine Siviy Wolf Goethert Robert Ferguson Software Engineering Measurement & Analysis Initiative

An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

Embed Size (px)

Citation preview

Page 1: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

Sponsored by the U.S. Department of Defense© 2004 by Carnegie Mellon University

Version 1.0 page 1

Pittsburgh, PA 15213-3890

Carnegie MellonSoftware Engineering Institute

An Acquirer’s Guide toNavigating Contractor DataJeannine SiviyWolf GoethertRobert Ferguson

Software Engineering Measurement & Analysis Initiative

Page 2: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 2

Carnegie MellonSoftware Engineering Institute

Trademarks and Service Marks® Capability Maturity Model, Capability Maturity Modeling, Carnegie Mellon, CERT, CERT Coordination Center, CMM,and CMMI are registered in the U.S. Patent and TrademarkOffice by Carnegie Mellon University.

SM Architecture Tradeoff Analysis Method; ATAM;CMM Integration; CURE; IDEAL; Interim Profile; OCTAVE; Operationally Critical Threat, Asset, and Vulnerability Evaluation; Personal Software Process; PSP; SCAMPI; SCAMPI Lead Assessor; SCAMPI Lead Appraiser; SCE; SEI; SEPG; Team Software Process; and TSP are servicemarks of Carnegie Mellon University.

Page 3: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 3

Carnegie MellonSoftware Engineering Institute

Objectives

Establish a view of the acquirer and supplier/contractorroles and responsibilities.

Show how measurement and analysis skills for internaldevelopment can be recast for acquisition and contractingenvironments.

Address a prevalent question in the acquisitioncommunity:• How can we conduct causal analysis when we no

longer control the collection processes and/or data?

Page 4: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 4

Carnegie MellonSoftware Engineering Institute

Outline

Acquisition roles & responsibilitiesMeasurement & analysis methodsIllustration• background• monitoring and oversight: progress analysis

SummaryReferences

Page 5: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 5

Carnegie MellonSoftware Engineering Institute

Responsibility and AuthorityMeasuring project and product success is the same whether theproject is internal or contracted:• on schedule• at cost• with required functionality• without defects

The acquiring program manager’s “circle of influence” and “circle ofcontrol” is different than the development project manager’s.• development project manager addresses project execution• acquisition program manager executes new set of processes• acquisition program manager should leverage development

knowledge to manage the contract methodically, rationally, andknowledgeably

Page 6: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 6

Carnegie MellonSoftware Engineering Institute

Roles and Information Exchange

Status Information

Develop,Customize,Integrate• systems• software• COTS

Supplier /Developer

Directions, CorrectionsDirections, Corrections

Deliverables

Interim Documents, Tangibles

Acquirer

Pre-award activities

Post-award activities

• RFP prep.• Contract Award

Contractual Handshake

Functional & Quality

Requirements

Functional & Quality

Requirements

SubContractors

SEPG / SAPG SEPG

• MonitorProjectProgress

• EvaluateDeliver-ables

Page 7: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 7

Carnegie MellonSoftware Engineering Institute

Measuring Project, Product, Process

Processes

Products•Supplier Produced

•Acquisition Organization Produced

ContractualHandshake

Exchange ofindicators /informationfor tracking,monitoring,direction, etc.

Acquirer

Pre-awardactivities

Post-awardactivities

Supplier

Develop,Customize,Integrate• systems• software• COTS

Project•Schedule

•Cost

•Requirements satisfaction

(status, projection, trend)

(status, projection, trend) •Quality (amount of rework)

•Quality (amount of rework)

Relationship•Roles (changes)

•Invoicing (payment)

Page 8: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 8

Carnegie MellonSoftware Engineering Institute

Responsibilities After ContractAward

DeliverablesDocuments- SRD- SDP- Measurement

Plan- SDD

Status Reports- Schedule- Cost- Testing

Final Product

Evaluate Quality ofDeliverables

Monitor and Oversight - Schedule & Progress - Resources & Costs - Developer’s Processes

ACQUIRER

Acquirer Responsibilities(Post-Contract Award)

Contractor

Developthe

System

Page 9: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 9

Carnegie MellonSoftware Engineering Institute

Monitoring & Oversight

Acquirer'sEvaluationCriteria

Acquirer’sAnalysis& ReviewProcess

Status Information

- schedule progress- budget status- test results- process results, such as inspections- process compliance

Measurable Results (Examples)

• contractor effort actual vs. plan• contractor schedule actual vs. plan• defects reported

• description, severity, class, type• size, complexity of the work product

Indicators

Page 10: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 10

Carnegie MellonSoftware Engineering Institute

Evaluating Quality of Deliverables

Acquirer’sEvaluationcriteria

Acquirer’sInspectionor ReviewProcess

Documentsto review- SRD- SDP- Meas Plan- SDD

Measurable Results (Examples)

• defects discovered• description, severity, class, type

• size of the work product

• effort invested in the inspectionprocess

• time spent during the inspectionactivities

Indicators

FinalDeliverables

Process

Products

Page 11: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 11

Carnegie MellonSoftware Engineering Institute

Outline

Acquisition roles & responsibilitiesMeasurement & analysis methodsIllustration• background• monitoring and oversight: progress analysis

SummaryReferences

Page 12: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 12

Carnegie MellonSoftware Engineering Institute

Sources for Measures

Goals Questions MeasuresIndicators

Goal-Driven (Software) Measurement (GDM)

USER DEFINES INDICATORS & MEASURES

Based On:• what’s needed to manage the User’s goals• decisions and decision criteria related to managingthe user’s goals

(GQIM)

Practical Software & Systems MeasurementCommon

IssueArea

MeasurementCategory

Measures

PREDEFINEDPREDEFINED PREDEFINED

Page 13: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 13

Carnegie MellonSoftware Engineering Institute

Data Analysis Dynamics

Getting Started• Identify the goals• Black box process view• Is the data right?• Do I have the right data?

Decision point:• If the data is not perfect, do I

move forward or obtain betterdata?

Initial Evaluation• What should the data look like?• What does the data look like?• Can I characterize the process,

product, problem?

Decision point:• Can I address my goals

right now?• Or is additional analysis

necessary? at the same ordeeper level of detail?

• Can I move forward?

Moving Forward• Further evaluation• Decompose data, process

Decision point:• Do I take action?• What action do I take?

Repeat until root cause found, attarget with desired variation

[DAD 03]

Page 14: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 14

Carnegie MellonSoftware Engineering Institute

Performance Analysis Model

TechnicalAdequacy

DevelopmentPerformance

Growth andStability

Resourcesand Cost

Schedule andProgress

ProductQuality

CustomerSatisfaction

[PSM 00]

Page 15: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 15

Carnegie MellonSoftware Engineering Institute

Performance Analysis Checklist 1Single indicator issues:• Do actual trends correspond to planned trends, such as

progress, growth, and expenditures? How big is thevariance?

• Does the variance appear to be gradually growing eachmonth?

• Are actual values exceeding planned limits, such asopen defects, changes, and resource utilization?

[PSM 00]

Page 16: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 16

Carnegie MellonSoftware Engineering Institute

Performance Analysis Checklist 2Integrated indicator issues:• Is the source of the problem evident?

- Change in functionality, unplanned rework, etc.• Are growing problems in one area a leading indicator of

other problems later in the project?- Requirements creep impact on schedule

• Do multiple indicators lead to similar conclusions?- Lack of progress correlates with low staffing

• Does other project information contradict performanceresults?- Milestones being met but open defect counts are

increasing

[PSM 00]

Page 17: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 17

Carnegie MellonSoftware Engineering Institute

Outline

Acquisition roles & responsibilitiesMeasurement & analysis methodsIllustration• background• monitoring and oversight: progress analysis

SummaryReferences

Page 18: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 18

Carnegie MellonSoftware Engineering Institute

IllustrationThis illustration is based on an organization that is• maintaining an existing product, a blend of COTS, and

internally developed code• pursuing the acquisition of a replacement product

Their acquisition includes two contracts:• requirements development• product design, code, and test

This illustration will focus on• analyzing project execution data (Contract 2)

Page 19: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 19

Carnegie MellonSoftware Engineering Institute

Monitoring & Oversight

Contract 2 has been awarded.• supplier is developing the product in two builds

The contractor has just notified you that the project hasboth cost and schedule slippage.

What do you do?

Page 20: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 20

Carnegie MellonSoftware Engineering Institute

Contractor Information

Contractor information:• provides data per your contractual agreement• also provides additional data if you ask*• uses measurement data to help monitor development• has defined processes and monitors compliance• analyzes software trouble reports to identify process

improvements• average software process maturity

*Typically, If the RFP does not require the data, the contractor is not obligated to provide it. In thiscase study, the acquirer and contractor have a good working relationship and the contractor is willingto share data beyond what the RFP specifies.

Page 21: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 21

Carnegie MellonSoftware Engineering Institute

Action: Management Review

Meet with development contractor to:• Find out what is happening.• Find out why it is happening.

What decisions/actions could be taken based upon thedata presented?• to correct the slippage• to prevent further slippage

Postulate future consequences of these decisions

Identify actions that could have been taken earlier toprevent the slip

Page 22: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 22

Carnegie MellonSoftware Engineering Institute

TechnicalAdequacy

DevelopmentPerformance

Growth andStability

Resourcesand Cost

Schedule andProgress

ProductQuality

CustomerSatisfaction

Use model to guide analysis.• Step 1: Confirm Problem (Cost & Schedule Slippage)

Performance Analysis Model

Page 23: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 23

Carnegie MellonSoftware Engineering Institute

Schedule & Progress IndicatorsCost

EV

PV

AC

J F M A M J J A S O N D J F M A M J J A S O N D

2002 2003

PV: Planned ValueAC: Actual CostEV: Earned Value

PV: Planned ValueAC: Actual CostEV: Earned Value

} Cost Var. = EV - AC

Sched Var. = EV - PV

}

EV

PV

AC

Cost

EV

PV

AC

J F M A M J J A S O N D J F M A M J J A S O N D

2002 2003

PV: Planned ValueAC: Actual CostEV: Earned Value

PV: Planned ValueAC: Actual CostEV: Earned Value

} Cost Var. = EV - AC

Sched Var. = EV - PV

}

EV

PV

AC

Est. Requirements

Architecture

Build 1DesignAssembly & TestIntegration & Ver.

Build 2DesignAssembly & TestIntegration & Ver.

Product Integration

Formal Qual. Test

J F M A M J J A S O N D J F M A M J J A S O N D2002 2003

Life cycle Activities

Tool tips:

The top two charts weremade in Excel andmanually manipulated.

The Gantt chart can begenerated using anyscheduling software.

Components Completing A&T

0

10

20

30

40

50

60

S O N D J F M A M J J A

Planned Actual

As of Jul 03

Build 1 Assembly & Test Build 2 Assembly & Test

2002 2003

A&T = Assembly and Test

Page 24: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 24

Carnegie MellonSoftware Engineering Institute

What We Learned

From Schedule and Progress indicators• cost and schedule slippage -- EV chart• activities taking longer than planned -- Gantt chart• assembly and test behind schedule -- components

completion chart

What does this mean?• confirms we have a problem

Page 25: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 25

Carnegie MellonSoftware Engineering Institute

Resources and Cost Indicators

Analysis/Probing Questions• Is the staff allocation

contributing to theproblem (too many, toofew, wrong time frame)?

• What is rate of staffturnover?

• How does actual staffcompare to planned staffallocation?

TechnicalAdequacy

DevelopmentPerformance

Growth andStability

Resourcesand Cost

ProductQuality

CustomerSatisfaction

Schedule andProgress

Page 26: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 26

Carnegie MellonSoftware Engineering Institute

Resources and Cost Indicators

0

5

10

15

20

25

30

35

40

45

Jan

Mar May Ju

l

Sep

Nov Jan

Mar

May Ju

l

Sep

Nov

Nu

mb

er o

f S

taff

Planned

Actual

2002 2003

Turn Over

Key Pers.

Others.

Tool tip: This chart was made in Excel and manually manipulated.

Plan 2 3 3 3 9 9 11 12 22 23 23 22 22 22 22 15Actual 3 3 4 5 5 5 6 9 9 11 11 15 18 19 19 20 20 30 30

Prg

Plan 1 1 1 3 3 2 2 5 5 7 8 8 8 8 5Actual 3 3 3 3 3 3 3 3 5 5 5 5 5 5 5 5 5 5 5Tester

Page 27: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 27

Carnegie MellonSoftware Engineering Institute

What We Learned

From Resources and Cost Indicators• staffing did not follow planned level

- too many at beginning of project- testers and programmers used to fill in for analysts

and designers => high re-training costs- high turnover rate => training & getting up-to-speed

costs

What does this mean?• cost overrun due partly to staffing problems

Page 28: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 28

Carnegie MellonSoftware Engineering Institute

Growth and Stability Indicators

Analysis/Probing Questions• Are the requirements stable?• What is the code growth?• Is functionality being

transferred from build 1 tobuild 2? If so, how does thiseffect the delivery date?

TechnicalAdequacy

DevelopmentPerformance

Growth andStability

Resourcesand Cost

ProductQuality

CustomerSatisfaction

Schedule andProgress

Page 29: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 29

Carnegie MellonSoftware Engineering Institute

2002 2003Feb Mar Apr May Jun Jul Aug Sep Dec Mar Jul

Req Changes 10 11 6 14 10 8 4 14 4 1 5Complexity Low Low Low Low Low Low Low Low Low Low LowResources (staff-days)

4 5 3 2 4 2 3 3 2 1 2

0

20

40

60

80

100

120

140

AddedReq.

Total Req.

Nu

mb

er o

f R

equ

irem

ents

J F M A M J J A S O N D J F M A M J2002 2003

J

Build 1

Build 2

As of Jul 03

Requirement Changes Information

Tool tip: This chartcan be generatedin Excel followedby manual editingusing the drawingtoolbar

Page 30: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 30

Carnegie MellonSoftware Engineering Institute

Growth and Stability IndicatorsSize Growth02

Jul

Jan

02

Mar

02

May

02

Sep

02

Nov

02

Jan-

03

Mar

03

May

03

Jul0

3

Sep

03

Lin

es o

f C

od

e

0

100

200

300

400

500

600

Plan

Actuals

Build 1

Build 2

In 1

00K

As of Jul 03

Requirements per Build

Contractor’s Explanation:• Functions deferred to later buildbecause of unanticipatedcomplexity

Tool tip: This chart was made in Excel andmanually manipulated.

Nu

mb

er o

f R

eq.

As of Jul 03

0

10

20

30

40

50

60

70

80

90

Build1

Build2

Original PlanReplan 1ActualNot Done

Page 31: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 31

Carnegie MellonSoftware Engineering Institute

What We LearnedFrom Growth and Stability Indicators• requirement changes are of low complexity but will

have some ripple effect• code production below planned value• functionality being deferred from build 1 to build 2

attributed by contractor to unanticipated complexity

What does this mean?• expect further cost and schedule growth due to low

code production and increased number of functions tobe implemented in Build 2

• expect an impact on completion date due to functionsdeferred to Build 2

• expect the possibility of a “Build 3” proposal

Page 32: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 32

Carnegie MellonSoftware Engineering Institute

Product Quality Indicators

TechnicalAdequacy

DevelopmentPerformance

Growth andStability

Resourcesand Cost

ProductQuality

CustomerSatisfaction

Schedule andProgress

Analysis/Probing Questions• Are the defined processes

being followed?• What is the rate of closure for

trouble reports?• What type of trouble reports

are being detected? In whatphase?

Page 33: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 33

Carnegie MellonSoftware Engineering Institute

Product Quality Indicators

STR Status: Open vs. Closed

0

100

200

300

400

500

600

700

800

900

J F M A M J J A S O N D J F M A M J J A S O N D

Open

Closed

Delta

As of Jul 03

20032002

Build 1

Build 2

Tool tip: This chart was made in Excel and manually manipulated.

0

50

100

150

200

Open (200)

Closed (400)

Priority1

Priority2

Priority3

Priority4

Priority5

Nu

mb

er o

f S

TR

s

Open and Closed STRs

Showstopper Nit

Tallies on Jul 03

Cumulative

Page 34: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 34

Carnegie MellonSoftware Engineering Institute

Classifying Trouble Report Defects

0 5 10 15 20 25

DocumentationSyntax

Build, package

Assignment

Interface

Checking

Data

Function

System

Environment

Percent of Defects

Def

ect

Typ

e

Types that codeinspections wouldhave been expectedto catch

Page 35: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 35

Carnegie MellonSoftware Engineering Institute

What We Learned

From Product Quality Indicators• STRs being opened faster than they’re being closed• Code inspections should have found defect types

What does this mean?• Code inspection process allowed large number of

defects to slip through.

Page 36: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 36

Carnegie MellonSoftware Engineering Institute

Development PerformanceIndicators

TechnicalAdequacy

DevelopmentPerformance

Growth andStability

Resourcesand Cost

ProductQuality

CustomerSatisfaction

Schedule andProgress

Analysis/Probing Questions• Are the defined processes

being followed?• Are any defined processes

being skipped?

Page 37: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 37

Carnegie MellonSoftware Engineering Institute

Development PerformanceIndicators

Process Compliance

50556065707580859095

100

Jan-

02F

eb-0

2M

ar-0

2A

pr-0

2M

ay-0

2Ju

n-02

Jul-0

2A

ug-0

2S

ep-0

2O

ct-0

2N

ov-0

2D

ec-0

2Ja

n-03

Feb

-03

Mar

-03

Apr

-03

May

-03

Jun-

03Ju

l-03

Aug

-03

Sep

-03

Oct

-03

Nov

-03

Dec

-03

Per

cen

tag

e

Build 1

Build 2

As of Jul 03

0 25 50 75 100

Documentation

SQACSCI Int. & Testing

Code & Unit Testing

Config. Mgt

Req. Analysis

Rework

Process

% Completion

Detailed Design

As of Jul 03Process Compliance

Funct. Int. & Testing

Inspections

Prelim. Design

Tool tip: This chart was made in Excel and manually manipulated.

Page 38: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 38

Carnegie MellonSoftware Engineering Institute

What We Learned

From Development Performance Indicators• adherence to defined process decreased over time• stopped doing inspections

What does this mean?• defects usually detected during code inspections

allowed to slip through• impact on cost and schedule due to rework

Page 39: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 39

Carnegie MellonSoftware Engineering Institute

Reasons for SlippageStaffing problems:• too many at beginning of project• below planned level during most of development

- noting that productivity increased dramatically• high turnover rate

Process compliance:• stopped doing inspections• allowed errors to leak to later phases

Requirements changes after Build 2 code and unit test

Conclusion:• expect further cost and schedule growth due to low code

production and increased number of functions to beimplemented in Build 2

Page 40: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 40

Carnegie MellonSoftware Engineering Institute

Possible ActionsDeveloper Actions• replan based on current performance• get staffing under control

- verify the skills balance of resources- do not decrease staffing to conform to “planned”

staffing, particularly if that would decrease thenumber of programmers

• restart inspections- code- test cases

Acquirer Decision Options• use contract labor (additional costs)• deliver smaller size - less functionality• accept schedule slip

Page 41: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 41

Carnegie MellonSoftware Engineering Institute

What if Data is Not Available?Data may not be available because• contractor does not collect this level of data• contractor not required by contract to report it

Using process compliance data as an example, how mightmissing this data affect conclusions, actions, and project results?• corrective action might have adjusted staffing• it would not have addressed the skipped inspections which

allowed errors to leak to later phases, resulting in increasedcost and schedule

A possible action to infer process compliance• could check data on results of code inspections (if data is

specified on contract)

Lesson learned: specify in contract what type of data to bereported in status reports

Page 42: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 42

Carnegie MellonSoftware Engineering Institute

Prevention

Cost & Schedule Slippage

Visible indicators of underlyingproblems

Staffing issues

Requirement changes

Root causes of problems

Functionality being deferred

Decreased process compliance

(skipped inspections)

Developers “corrective” actions

TechnicalAdequacy

DevelopmentPerformance

Growth andStability

Resourcesand Cost

ProductQuality

CustomerSatisfaction

Schedule andProgress

The performance analysis model is a guide to root cause.Understanding root cause leads to prevention.

Unanticipated complexity

Inability to process STRs

Direct causes of problems

Page 43: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 43

Carnegie MellonSoftware Engineering Institute

Outline

Acquisition roles & responsibilitiesMeasurement & analysis methodsIllustration• background• monitoring and oversight: progress analysis

SummaryReferences

Page 44: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 44

Carnegie MellonSoftware Engineering Institute

Roles and Information Exchange

Status Information

Develop,Customize,Integrate• systems• software• COTS

Supplier /Developer

Directions, CorrectionsDirections, Corrections

Deliverables

Interim Documents, Tangibles

Acquirer

Pre-award activities

Post-award activities

• RFP prep.• Contract Award

Contractual Handshake

Functional & Quality

Requirements

Functional & Quality

Requirements

SubContractors

SEPG / SAPG SEPG

• MonitorProjectProgress

• EvaluateDeliver-ables

Page 45: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 45

Carnegie MellonSoftware Engineering Institute

Measuring Project, Product, Process

Processes

Products•Supplier Produced

•Acquisition Organization Produced

ContractualHandshake

Exchange ofindicators /informationfor tracking,monitoring,direction, etc.

Acquirer

Pre-awardactivities

Post-awardactivities

Supplier

Develop,Customize,Integrate• systems• software• COTS

Project•Schedule

•Cost

•Requirements satisfaction

(status, projection, trend)

(status, projection, trend) •Quality (amount of rework)

•Quality (amount of rework)

Relationship•Roles-Changes

•Invoicing-payment

Page 46: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 46

Carnegie MellonSoftware Engineering Institute

SummaryKey acquisition responsibilities (after contract award):• monitoring and oversight• inspecting, reviewing, and understanding documents and

other work products

Post-contract award success depends on pre-contract awardactivities• building measurement expectations into contracts• establishing good partnerships and working relationships with

contractors

Measures and indicators across landscape are interrelated• use the Performance Analysis Model as your navigation guide• always use multiple indicators

Measure products, processes, projects, relationships

Page 47: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 47

Carnegie MellonSoftware Engineering Institute

Contact InformationWolf GoethertSoftware Engineering InstituteMeasurement & Analysis InitiativeEmail: [email protected]

Jeannine SiviySoftware Engineering InstituteMeasurement & Analysis InitiativeEmail: [email protected]

Robert FergusonSoftware Engineering InstituteMeasurement & Analysis InitiativeEmail: [email protected]

Page 48: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 48

Carnegie MellonSoftware Engineering Institute

References 1Note: URLs valid as of tutorial delivery date.

[DAD 03] Siviy, Jeannine and William Florac, Data Analysis Dynamics, Half Day TutorialDelivered at SEPG 2003, Boston, MA

[GQIM 96] Goal-Driven Software Measurement--A Guidebookhttp://www.sei.cmu.edu/publications/documents/96.reports/96.hb.002.html

[PSM 00] Practical Software and Systems Measurement A Foundation for Objective ProjectManagement, Guidebook, version 4.0b, Practical Software and SystemsMeasurement Support Center, U.S. TRACOM-ARDEC, AMSTA-AR-QA-A, PicatinnyArsenal, NJ, Website: www.psmsc.com, October 2000

Page 49: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 49

Carnegie MellonSoftware Engineering Institute

Reading & Resources 1

Note: URLs valid as of tutorial delivery date.

Practical Software and Systems Measurement (PSM)• reference for the Performance Analysis Model• reference lists of measures to consider• http://www.psmsc.com

Goal Driven Measurement (GDM) andGoal-Question-Indicator-Metric (GQIM)• front end for selecting most relevant PSM measures• used for developing context-specific indicators, particularly

“success indicators”• “Goal-Driven Software Measurement--A Guidebook”

http://www.sei.cmu.edu/publications/documents/96.reports/96.hb.002.html

Page 50: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 50

Carnegie MellonSoftware Engineering Institute

Reading & Resources 2

Note: URLs valid as of tutorial delivery date.

Defense Acquisition University (DAU) Deskbook• http://deskbook.dau.mil/jsp/default.jsp• provides information about regulatory references, mandatory

and discretionary references by service branch, and severalknowledge repositories

Guidelines for Successful Acquisition and Management ofSoftware-Intensive Systems,http://www.stsc.hill.af.mil/resources/tech_docs/index.html

Acquisition Centers of Excellence• Air Force, for instance ESC Hanscom

- http://esc.hanscom.af.mil/ESC-BP/• Navy

- http://www.ace.navy.mil/public/html/

Page 51: An Acquirer's Guide to Navigating Contractor Data · [PSM 00] © 2004 by Carnegie Mellon University Version 1.0 page 15 Carnegie Mellon ... The Gantt chart can be generated using

© 2004 by Carnegie Mellon University Version 1.0 page 51

Carnegie MellonSoftware Engineering Institute

Reading & Resources 3

Note: URLs valid as of tutorial delivery date.

Project Management Body of Knowledge (PMBOK®)• proven, traditional project management practices and

innovated, advanced practices with more limited use• Project Management Institute Guide to the PMBOK contains

the generally accepted subset of knowledge and practicesthat are applicable to most projects most of the time- http://www.pmi.org/info/PP_StandardsExcerpts.asp- http://www.pmi.org/info/PP_PMBOK2000Excerpts.asp