29
A seminar On Validation Of liquid Filling & Sealing Machine By Raju.G 170513886008 1

Ampule filling and_sealing_machine

Embed Size (px)

Citation preview

Page 1: Ampule filling and_sealing_machine

A seminar

On

Validation Of liquid Filling & Sealing Machine

By

Raju.G

170513886008

1

Page 2: Ampule filling and_sealing_machine

Introduction

2

Page 3: Ampule filling and_sealing_machine

Equipment qualification:

• The equipment validation process generally covers following steps..

– User Requirement Specification (URS)

– Design Qualification (DQ)

– Installation Qualification (IQ)

– Operational Qualification (OQ)

– Performance Qualification (PQ)

3

Page 4: Ampule filling and_sealing_machine

Stages of Qualification

4

Page 5: Ampule filling and_sealing_machine

• The previous figure depicts the most commonly used approach to the qualification process as used in the pharmaceutical industry

• It shows a pyramid, which is the best way in which to plan a qualification/validation project

• Investing more time in the first phases will save time and money in later and critical phases

5

Page 6: Ampule filling and_sealing_machine

Who should do Equipment Validation?• The vendor or the user ?— User has the ultimate responsibility for the accuracy of

the analysis results and also for equipment qualification— DQ should always be done by the user— While IQ for a small and low cost instrument is usually done

by the user, IQ for large, complex and high cost instruments

should be done by the vendor— OQ can be done by either the user or the vendor— PQ should always be done by the user because it is very

application specific, and the vendor may not be familiar with

these— PQ should be done on a daily basis

6

Page 7: Ampule filling and_sealing_machine

Validation of Ampoule Filling & Sealing Machine

September 30, 2014 7

Page 8: Ampule filling and_sealing_machine

8

Page 9: Ampule filling and_sealing_machine

September 30, 2014 9

Page 10: Ampule filling and_sealing_machine

Validation Protocol

• The entire process of equipment validation is designed in the form of certain documented formats or protocols

• This helps in systematizing the study of equipment validation

• A validation protocol prepared by engineer or validation specialist

• The protocol sections contain required procedures and forms

10

Page 11: Ampule filling and_sealing_machine

User Requirement Specification

• The user of the equipment has certain requirement about the equipment which he wants to use

• Some of the general requirements may be stated in the form of certain parameters like…– Size of equipment– Speed of equipment– Availability of spares, change part, immediate service at

reasonable cost

11

Page 12: Ampule filling and_sealing_machine

– Low sound generation– Lesser breakdowns– Materials of construction– Auto control system

• This requirements are generally discussed with the suppliers and based on this discussion the selection of the equipment is done

12

Page 13: Ampule filling and_sealing_machine

For example,• In ampoule filling machine, a delivery tube

provided for repetitively forcing a measured volume of liquid through the orifice of delivery tube designed to enter the constricted opening of container

• The size of delivery tube depend on ..– the opening of container– the viscosity & density of liquid– speed of delivery desired

13

Page 14: Ampule filling and_sealing_machine

D.Q. and its Certification

• If we are going to purchase an standard equipment then the preparation of D.Q. dose not become very important because we are accepting the manufacturer's design as it is

• However, if a particular equipment is to be fabricated as per our requirements then the detailed D.Q. document become very important and essential

14

Page 15: Ampule filling and_sealing_machine

• It is advisable to work out the detailed equipment specifications by sitting together with the equipment manufacturer

• It may also be advisable to perform Factory Acceptance Test (FAT) at the manufacturer’s premises before dispatch of the equipment to the purchaser

15

Page 16: Ampule filling and_sealing_machine

Installation Qualification

• “Installation qualification establishes that the instrument is received as designed and specified, that it is properly installed in the selected environment, and that this environment is suitable for the operation and use of the instrument”

16

Page 17: Ampule filling and_sealing_machine

• I.Q involves,

– Verification of approved purchase order– Verification of invoice– Check manufacturer and supplier– Verification of model number and serial number– Checking for any physical damage– Confirm location and installation requirements as per

recommendation of manufacturers– Verify that the utilities required are available– Installation shall be conducted as per instructions provided

in the manual

17

Page 18: Ampule filling and_sealing_machine

• Ensure all relevant documentation is received like,− User manual− Maintenance manual− List of change parts− Electrical drawings

18

Page 19: Ampule filling and_sealing_machine

Operational Qualification• O.Q. is verification of performance of the system without

load• O.Q. section details the tests to be performed on the

equipment to document that it operates correctly• O.Q. involve,

– Verification of alarm control– Perform calibration requirements identified in the manual or

established by the validation team– Operate the equipment at low, medium, and high speed as per

operations manual to verify the operating control– Verify that all switches and push buttons are functioning

properly– Establish procedures (SOP) for operation, maintenance, and

calibration– Establish training program for relevant staff

19

Page 20: Ampule filling and_sealing_machine

Performance Qualification• P.Q. is verification of performance of system with

load• Filling studies will be run on all containers and fill

levels • The containers will be filled in triplicate runs • If a placebo is used, it should have similar physical

characteristics (viscosity, density, foaming) to the actual fill materials

• The study should be run at minimum, maximum and intermittent speeds (in terms of ampoules/minute)

• The filler must handle the containers without damage and without jams

• Accuracy and precision must meet specifications

20

Page 21: Ampule filling and_sealing_machine

• P.Q. of ampoule filling and sealing machine involve,a) Wight variation test

b) Filling volume accuracy

c) Particle Contamination

d) Leaker test

e) Oxygen content

21

Page 22: Ampule filling and_sealing_machine

a)Weight variation test :– In the absence of specific criteria, weight variation

must conform to USP – In summary, all 10 units must be within 85.0 to

115.0% of target content, with a %RSD ≤ 6.0%, or not more than 1 of the 30 units outside of the 85.0 to 115.0% and no units outside of 75.0 to 125.0%, with a %RSD ≤ 7.8%

22

Page 23: Ampule filling and_sealing_machine

b)Filling Volume Accuracy:

The filling accuracy should be within ±% of the adjusted and desired filling volume in accordance with the machine specification.

eg.– Attention limit: ±1%– Action limit: ±2%

23

Page 24: Ampule filling and_sealing_machine

c) Particle Contamination of Ampoules during Filling & Sealing Procedure:– Ampoules should be filled with water for injection

and afterward be inspected on the contamination with particles (particle classes: ≤10 μm and ≤25 μm).

– The inspection can be performed with a particle counter.

24

Page 25: Ampule filling and_sealing_machine

d)Leaker test:– Should capillary pore or tiny cracks be present,

micro-organisms or other contaminants may enter the ampoule, or the content may leak outside.

– Leaker usually detected by submerged ampoule in a deeply colored dye solution (usually 0.5 to 1.0% methylene blue).

– Limitation is that capillaries of about less than 15 um not detected by this method.

25

Page 26: Ampule filling and_sealing_machine

e) Oxygen content,– If the filler produces a nitrogen purge, the

headspace gas should be analyzed for oxygen content

26

Page 27: Ampule filling and_sealing_machine

Requalification

• Requalification of systems and equipment should be done in accordance with a defined schedule

• The frequency of requalification may be determined on the basis of factors such as the analysis of results relating to calibration, verification and maintenance

• There should be requalification after changes • The extent of requalification after the change

should be justified based on a risk-assessment of the change

27

Page 28: Ampule filling and_sealing_machine

References...References...

1) R. A. Nash & A. H. Wachter, “Pharmaceutical process validation”; Third edition

2) Leon Lachman, H. A. Lieberman & J. L. Kanig, “The Theory and Practice of Industrial Pharmacy”; Third edition, Pg. No. - 667 to 674

3) Manohar A. Potdar, “Pharmaceutical Quality Assurance”, Pg. No.- 8.13, 8.14

4) Syed Imtiaz Haider, “Validation Standard Operating Procedure”, Pg. No. - 304 to 307

5) Syed Imtiaz Haider, “Pharmaceutical Master Validation Plan”, Pg. No. – 140

6) http://www.validationworld.com/

September 30, 2014 28

Page 29: Ampule filling and_sealing_machine

September 30, 2014 29