38
Jane 1997 Ambient Characterization of the ESF Drift Scale Test Area by Field Air Permeability Measurements Level 4 Milestone SP9512M4 Y.W. Tsang and P. Cook Earth Sciences Division, LBNL I Cyclotron Road, Mailstop: 90-1116 Berkeley CA 94720 1. Introduction Pre-heater test ambient characterization of the Drift Scale Test (DST) area helps to define the initial conditions of the test block, and is essential for the interpretation and analysis of the coupled thermo-hydrological-mechanical-chemical processes associated with the in-situ Drift Scale Test in the Exploratory Studies Facility (ESF). This report deals specifically with the field air permeability measurements of the DST area. The test results provide an estimate of the three- dimensional heterogeneous gas phase permeability structure and fracture connectivity in the block. Since the dominant thermal-hydrological response of the rock mass to the applied heat is the vaporization of pore water near the heat source, and the redistribution of moisture through vapor transport, it is important to develop an understanding of the potential pathways for fluids and gases in the DST block. Characterization by air permeability tests, prior to the onset of heating, provides this information and allows predictive calculations to be made regarding fluid, heat, and gas flow in the block during both the heating and cooling phases of the thermal test. The pre-test characterization data will also serve as a basis for post-test comparison to observe where and what changes in permeability have occurred due to heating and possible thermohydrologic- chemical coupling. Air permeability tests for the DST were carried out in November and December of 1996, and again in February and March of 1997, in available boreholes; that is, those which have been drilled and logged by video, and not yet permanently installed with instrumentation for the heater test proper. During this period, the HD of the DST was still under construction, therefore, the majority of the instrumental boreholes and wing heater boreholes originating from the HD have not yet been drilled. Those available for air permeability tests are fourteen boreholes, each 40 meters (in) in length, all originating from the Access/Observation Drift (AOD that runs parallel to the HD and is separated from the HD by 30 meters. These boreholes are oriented approximately south/north toward the HD, with incline angles ranging from +240 to -22° from the horizontal, I

Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Jane 1997

Ambient Characterization of the ESF Drift Scale Test Area by Field Air PermeabilityMeasurements

Level 4 Milestone SP9512M4Y.W. Tsang and P. CookEarth Sciences Division, LBNLI Cyclotron Road, Mailstop: 90-1116Berkeley CA 94720

1. Introduction

Pre-heater test ambient characterization of the Drift Scale Test (DST) area helps to define theinitial conditions of the test block, and is essential for the interpretation and analysis of thecoupled thermo-hydrological-mechanical-chemical processes associated with the in-situ DriftScale Test in the Exploratory Studies Facility (ESF). This report deals specifically with the fieldair permeability measurements of the DST area. The test results provide an estimate of the three-dimensional heterogeneous gas phase permeability structure and fracture connectivity in theblock. Since the dominant thermal-hydrological response of the rock mass to the applied heat isthe vaporization of pore water near the heat source, and the redistribution of moisture throughvapor transport, it is important to develop an understanding of the potential pathways for fluidsand gases in the DST block. Characterization by air permeability tests, prior to the onset ofheating, provides this information and allows predictive calculations to be made regarding fluid,heat, and gas flow in the block during both the heating and cooling phases of the thermal test. Thepre-test characterization data will also serve as a basis for post-test comparison to observe whereand what changes in permeability have occurred due to heating and possible thermohydrologic-chemical coupling.

Air permeability tests for the DST were carried out in November and December of 1996, andagain in February and March of 1997, in available boreholes; that is, those which have beendrilled and logged by video, and not yet permanently installed with instrumentation for the heatertest proper. During this period, the HD of the DST was still under construction, therefore, themajority of the instrumental boreholes and wing heater boreholes originating from the HD havenot yet been drilled. Those available for air permeability tests are fourteen boreholes, each 40meters (in) in length, all originating from the Access/Observation Drift (AOD that runs parallel tothe HD and is separated from the HD by 30 meters. These boreholes are oriented approximatelysouth/north toward the HD, with incline angles ranging from +240 to -22° from the horizontal,

I

Page 2: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

forming a fan and bracketing the HD. The fourteen holes form two spatial clusters about 20 mapart at their collars along the AOD wall. Within each cluster, the separation of some adjacentboreholes at their collars can be as small as less than one meter. However, since these boreholesform divergent fans from their collars on the rock surface, the separation distances betweenboreholes increase to 30 to 40 m at the bottom of holes. Figure 1 shows the layout of the DSTarea and the location of the 14 holes used for characterization by air permeability tests. The 14holes are identified by bold letter and underlined. Figure la is for the plan view (note that thetrue north makes an angle of 180 with the horizontal, which is generally referred to as the localnorth in the heater test), Figure lb shows an approximately E-W section and the positions of theboreholes at their collars, and Figure Ic shows two N-S sections -- again, only those holes inbold letters and underlined have been drilled during air permeability testing.

For the permeability tests, each borehole was separated by three inflatable packers int.approximately 12 - m sections. Each packed-off zone within the boreholes was instrumented witha sensor to monitor the pressure response. A typical test consisted of injecting air at a constantflow rate in one chosen section, while the pressure response(s) in this and all other packed offsections were monitored. The pressure response in the injection section is used to calculate thelocal permeability, averaged over length of the packed-off zone. The response of pressure in allother packed-off sections will yield information on the connectivity of pneumatic pathwaysbetween these sections and the injection section.

It shall be shown that the local air permeability around each packed section ranges from a low ofless than 1015 in to a high of 2.02 x 10 -12 n? with a geometric mean of 1. X 10 13 m2and a

median of 1.4 x 10 '3 mn. Interference data indicate that fractures are well connected and that aheterogeneous fracture continuum conceptualization is well suited for the DST block.

2. Quality Assurance Status of Data and Soft-.-:ire Used in This Report

All field and laboratory measurements were performed by qualified personnel, with calibratedequipment, under the LBNL QA program. Therefore, all data presented in this report are qualifieddata. The Data Tracking Number for the air permeability tests is DTN: LB970600123142.001.No software was used to generate data for this report. Standard spreadsheets, as well asvisualization and plotting programs, were used to generate graphics for this report. Suchprograms are not subject to QA requirements under QARD Rev. 7.

2

Page 3: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

3. Test Equipment

The air permeability testing equipment consisted of pneumatic packers, pressure sensors, airsupply and control equipment, a flow control unit; different components were connected viaelectronic cabling and flexible tubing. The air supply and control equipment was responsible forproviding dry, clean air under pressure to the flow control unit. The integrated flow control andacquisition system unit used a centralized set of manifolds for injecting and withdrawing gas frompacked off zones of interest, and for monitoring of zone pressure. The electronic control systemwas run using a laptop PC running Labview for Windows® for both control and data collection.The instrumentation interface and software control allowed the user to rapidly reconfigure thesystem in the field for conducting a varied testing program.

Pneumatically inflated packers wcee custom designed for the purpose of characteri7"'c the DSTarea by air injection te..ts. The design was such that up to four packers may be placed in a singleborehole to separate the borehole into four independently observable injection zones. Tbe packersconsisted of a 1/4-inch thick natural gum rubber gland applied over a stainless steel packer body.Length for the packer bodies is 0.61 meters giving a sealing surface of approximately 0.55 metersin length. To allow air injection into, and pressure monitoring for, each zone requires multiplefeedthroughs of stainless tube for each packer: for air injection (1/2-inch OD), packer inflation(1/8-inch OD) and pressure sensor (1/4-inch OD). One of the 1/2" feedthroughs also serves as astructural backbone for the packer string. The innermost of the four packers, i.e., the one closestto the bottom of the borehole, would have a minimum of three feedthroughs, while the fourthpacker to be placed closest to the collar would have a maximum of twelve feedthroughs. Aschematic diagram of a packer string consisting of only two packers is shown in Figure 2. Thepackers were fabricated in two standard sizes, nominally referred to as 3-inch and 4-inch toaccommodate the two standard-size borings, 7.57 cm and 9.60 cm in diameter. To isolate zones inthe wellbore, packers were typically inflated to 35 PSIG (2.41 x 105 Pa).

Pressure measurements were -..ade using Setr. pressure transducers (models C204 and i80)mounted near the collar of each borehole. The transducers monitored the zone of interest througha polyethylene tube connected to a 1/4-inch feedthrough.

Measurements were made using a Keithley 2001 digital multimeter (DMM)W. All data channelswere scanned through a Keithley 7002 Switch Systemr. Data was dumped across an EEE-488bus to a PC laptop. To control and measure the rate at which compressed air was injected, weused Sierra Instruments Series 840*®r mass flow controllers (MFCs) for three flow ranges, 0-10SLPM (standard liter per minute), 0-100 SLPM and two 0-500 SLPM connected in parallel, wereused. The Series 840 MFCs were controlled by a Hewlett Packard E3631 programmable powesupply and monitored using the Keithley DMM. Ambient conditions in the drift w

3

Page 4: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

continuously monitored using Vaisala HMP132Y humidity/temperature probe and an extra Setra

transducer.

4. Testing Procedures

The as-built Cartesian collar coordinates of the of the fourteen boreholes available for air-injection test holes (ESF As Built Survey, personal communication, Douglas Weaver, 1997) areshown in Table 1. The borehole ID numbers are in accordance with the Field Work PackageFWP-ESF-96-003, Revision 3, for thermal testing in the ESF. The as-built coordinatesconvention is that the +Y-axis is along the HD (parallel to the AOD) toward west, +X-axis runstoward north away from the AOD, and the origin (0,0,0) is at the center of the HD on the hot sideof the bulkhead.

Table L The as-built coordinates of the collar and diameter of boreholesBorehole I) X(m) Y(m) Z(m) hole diameter (cm)

45 ESF-HD-ERT-I -28.875 4.577 4.118 7.57

46 ESF-HD-ERT-2 -27.408 4.572 1.533 7.57

47 ESF-HD-NEU-l -29.114 6.385 4.636 7.57

48 ESF-HD-NEU-2 -29.051 6.391 4.042 7.57

51 ESF-ND-NEU-5 -28.993 6.414 2.254 7.57

52 ESF-HD-CEM-l -29.211 8.247 4.540 9.6

53 ESF-HD-CHE-2 -29.232 8.258 4.014 9.6

56 ESF-HD-CHE-5 -29.223 8.248 2.322 9.6

57 ESF-HD-HYD-1 -28.841 10.054 4.748 7.57

69 ESF-HD-CHE-6 -29.199 28.368 6.842 7.57

70 E3-H0D-CHE-7 -29.261 28.373 6.315 7.57

73 ESF-HD-CHE-10 -29.062 28.375 4.546 7.57

75 ESF-HD-HYD-7 -29.306 30.215 6.303 7.57

78 ESF-HD-HYD-10 -29.376 30.191 4.702 7.57

The Y coordinates of the boreholes clearly indicate that the fourteen holes form two spatialclusters at their collars along the AOD wall: one cluster of nine including boreholes 45, 46, 47,48, 51, 52, 53, 56, 57, centered around Y = 7 m; and another cluster of five including boreholes69, 70, 73, 75, 78, centered around Y = 28 m. The video logs of all boreholes in the single heaterblock were reviewed, and the fracture characteristics in each hole were noted. The original testplan for the ambient temperature bulk permeability measurements to estimate the three-

4

Page 5: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

dimensional heterogeneity in the DST block consisted of two phases. The first phase was to usetwo packers to divide each borehole into approximately two equal zones of 20 m in length. Theintention was that data from this first phase testing would probe the heterogeneous permeabilitystructure on a large scale, and would guide in the design of the second phase testing, where fourpackers would be used for each borehole to provide information on a smaller on scale about thepermeability structure. The test plan was modified after viewing of the borehole video logsbecause they showed very extensive sections of voids and fractures, so much so that it wasdifficult to identify locations of intact rock suitable for placement of inflatable packers. Thus itwas decided that each borehole should only be isolated by packers in thirds, with the third packerplaced as close to the collar as feasible. The modified test plan was as follows: the first phase oftesting would involve air injection and pressure response in the two zones closest to the bottom ofthe boreholes (the zones over the wing heater and the heater drift); and the second phase oftesting would involve air injection into the zone nearest the collar, separated by the sc - -ad andthird packer. This zone would also be the farthest from the region of applied heat during thethermal test. Each packed zone is on the order of 12 m; the actual depth of each packer wasadjusted to avoid overlay onto fractured borehole walls. Figure 3 shows the packer positions inthe 14 boreholes, The 3-D view is that of facing east away from the ESF main drift so the HDcentered at X = 0 is to the left and the Access/Observation Drift wall at x - -29 m is to the right.The lengths of the air injection zones L as isolated by packers are tabulated in Table 2. L isdetermined from the borehole lengths (ESF As Built Survey, Personal communication, DouglasWeaver, 1997) and the depth setting of the packers as measured in the field and recorded in thefield notebook. The nomenclature is such that Zone 1 refers to the zone closest to and includingthe bottom of the hole, and Zone 3 refers to the zone closest to the collar of the borehole. In therest of the report, a shorthand notation consisting of the borehole number plus zone will be used,for example, 45-3 will denote Zone 3 in Borehole 45.

Table 2. Lengths of the packed off zones

Borehole ID Lengih of Zone I (in) Length of zone 2 (m) Length of Zone 3 (m)

45 ESF-HD-ERT-I 10.9 11.6 15.4

46 ESF-HD-ERT-2 13.9 11.6 9.1

47 ESF-HD-NEU-I 18.5 11.6 7.6

48 ESF-HD-NEU-2 12.9 14.6 9.1

51 ESF-HD-NEU-S 14.1 13.1 9.3

52 ESF-HD-CHE-I 13.1 11.6 12.3

53 ESF-HD-CHE-2 25.3 11.6 0.0

56 ESF-HD-CHE-5 15.8 10.1 10.6

57 ESF-HD-HYD-1 22.5 11.6 3.2

5

Page 6: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

Borehole ID Length of Zone I (i) Length of zone 2 (m) Length of Zone 3(m)

69 ESF-HD-CHE-6 12.0 11.6 14.2

70 ESF-ED-CHE-7 15.2 11.6 11.2

73 ESF-HD-CHE-10 14.9 11.6 11.1

75 ESF-HD-HYD-7 23.4 11.6 0.0

75 ESF-HD-HYD-7 14.0 11.6 11.9

78 ESF-mD-HYD-o10 13.7 11.6 11.9

It should be noted that in Borehole 53, only two packers were installed because of obstruction byrocks, and for the same reason, the zone closest to the bottom of the hole for Boreholes 47 and 57are exceptionally lone. There are two entries for hole 75. The first is applicable for tests carrieuout in November and December, 1996, Two packers were installed and due to obstruction byrocks in the borehole the first zone closest to the bottom of the hole is 23.4 m. The second entryfor hole 75 is applicable for tests conducted in February and March of 1997. The obstruction wascleared, the packer string was moved downhole and a third packer was installed near the collar.

All the fittings on the feedthroughs on the packer strings were checked for leaks during packerstring installation. To isolate zones in the wellbore, the packers were typically inflated to apressure of 35 PSIG (2.41 x 10' Pa); the pressure within the packers was monitored periodicallythroughout testing. All sensors and equipment such as flow control unit and air supply andcontrol equipment were installed and linked to be controlled by the laptop PC running Labview.Prior to actual data logging, the whole acquisition and control system was tested for properfunctions with all the electronics attached.

In a typical injection test, the injection line to the selected injection zone is connected to the flowcontrol unit. An injection test consists of a period of background monitoring before injection,followed by an injection at constant mass flux .Maintained by the mass flow controller. Aftereither a predetermined interval of time or a steady state response is reached, the injection is haltedand the recovery is monitored. The pressure sensor is sampled during the early part of injectionand recovery every five seconds. The sampling rate is decreased with increasing test duration to aminimum of once every ten minutes for overnight tests or continuous background monitoring.The Labview code used in the data acquisition system allows real time display of test parametersduring testing. Viewing the pressure response of the sensors in different zones of the differentboreholes during each injection test allows preliminary interpretation of the air permeabilitystructure in the test block, and guides the tester in configuring subsequent tests.

6

Page 7: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

5. Air Permeability Estimation

Local permeability was estimated from the steady state pressure response to the air injectiontest. The analytical solution for the steady state pressure response of a constant flow rate injectionin a finite line source is as follows:

PSCQSCI{d PscQQSC n ff

ICL 2 _p2 )Ts 7L(2P, + AP)APTs, I2 1 )SC

Where

k = permeability, m2

Psc = Pressure at standard conditions, 1.013 x I0' Pa

Qsc = flowrate at standard conditions, m3/s

p = dynamic viscosity of air, 1.81 x 0 ' Pa-s at 20° C

L = Length of air injection zone, m

raw = radius of borehole, m

T = temperature of formation, ° K (an average of 24.60 C was assumed for -all tests)

P2 = steady-state pressure, Pa

P. = ambient pressure, Pa

AP = (P2 - P), Pa

Tsc= temperature at standard conditions, 293.160 K

Equation (1) has been used by both LeCain (1995) and Guzman et al. (1996) for the analysis ofsingle hole injection tests in fractured tuff at Apache Leap Research Site, Arizona. It was adaptedfrom the steady-state analytical solution for ellipsoidal flow of incompressible fluid from a finiteline source (Hvorslev, 1951), where L/r 1>> 1 in an infinite medium. The derivation of Equation(1) requires the assumption that air is the only mobile phase within the rock near the test interval,and that it obeys the ideal gas law so that the compressibility is inversely proportional to pressure.A detailed derivation of Equation (1) can be found in LeCain (1995). The same equation has alsobeen applied for the air injection tests for surface-based boreholes at Yucca Mountain (Rousseau

7

Page 8: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

et al., 1996). Equation (1) has its origin in well test analysis for a homogeneous porous medium.

The welded tuff DST test block is a fractured medium and may not be well representedconceptually by a homogeneous porous medium. Furthermore, the proximity of the drifts implies

that the finite line source is not in an infinite medium. Nevertheless, Equation (1) is still valuableas a simple tool of choice to obtain an order of magnitude estimate of the average permeability

values around each borehole, thus providing an initial estimate of the spatial variability of

permeability in the test block. This approach was used in the analysis for the air permeabilitymeasurements for the Single Heater Test (Tsang et al., 1996).

One complete set of estimated permeability values for all the zones of the 14 boreholes is shown

in 3-D in Figure 4. The logarithm of permeability, normalized to the highest value of 2.0 x 10 12

m2 in Borehole 52, Zone 3, is coded in rainbow color,. The same set of estimated permeabilityvalues are tabulated in Table 3.

Table 3. Estimated local permeability for the 41 packed-off zones In 14 boreholes.Borehole ID k(m2) in zone I k(m2) in zone 2 k(m2) in zone 3

45 ESF-HBD-ERT-1 5.8E-14 2.4E-14 4.5E-13

46 ESF-BD-ERT-2 4.UE-15 6.2E-15 9.OE-14

47 ESF-HD-NEU-i 6.lE-14 4.4E-13 4.7E-13

48 ESF-HD-NEU-2 2.4E-14 3.5E-14 3.4E-13

51 ESF-HD-NEU-5 8.8E-16 4.4E-13 4.1E&14

52 ESF-HD-CHE-l L.OE-13 1.2E-13 2.OE-12

53 ESF-HD-CHE-2 l.lE-13 1.3E-12 N/A

56 ESF-HD-CHE-5 l.9E-15 3.4E-14 4.8E-13

57 ESF-HD-HYD-1 2.7E-13 6.1E-14 1.4E-13

69 ESF-HDCHE-6 2.AE-13 9.5E-15 4.9E-13

70 ESF-HD-CHE.7 l.9E-14 4.5E-14 4.2E-13

73 E.,i-HD-CHE-:c 6.6E-14 6.8E-15 L.OE-13

75 ESF-HD-HYD-7 4.9E-13 lAE-13 3.OE-13

78 ESF-HD-HYD-10 5.5E-14 l.1E-14 7.8E-14

In many zones, more than one injection test had been carried out to investigate the sensitivity of

the derived permeability values to different test conditions. Injection tests in some zones were

carried out on different dates to investigate the repeatability of the test. The sensitivity of thederived permeability values to different mass flow rates injected into the same isolated zone were

investigated in several tests. These were carried out sometimes in separate tests, each with its own

constant flowrate, and sometimes within the same test by increasing the constant air flowrate in

8

Page 9: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

discrete steps, so that permeability may be estimated from multiple sets of steady state pressureresponse to the different flowrates. In addition to injecting air into the isolated zones of Table 2,injection tests were also carried out in longer zones by selectively deflating packers in a borehole.Specifically, Packer 1 was deflated in Borehole 45 so that the effective length of hole tested is22.6 m. Similarly, when both Packers I and 2 were deflated, a zone of 38.5 m, almost the entirelength of Borehole 45 isolated by just one packer, Packer 3 (near the collar), was tested. Theestimated values of permeability for all tests are summarized in Table 4 where the first columngives the identification of test, the second column gives the injection flowrate, and the thirdcolumn the estimated permeability. The test data file in the first column is identified by first theborehole number and zone number, then the date of the test, and then the order of the test during

that day.

Table 4 Estimated Permeability values from all Injection tests carred out In the 14 holesTest ID Injection flow rate Q in K (in)

Standard Liters Per Minute(SLPM)

45 zone I (11-21-96 01) 200 4.46E-1445 zonel (3-05-97 03) 80 5.83E-1445 zone2 (12-18-07) 80 2A4E-1445 zone3 (3-05-97 04) 80 4.52E-1345 zone3 (3-05-97 04) 160 3.17E-1345 zone3 (3-05-97 04) 80 2.39E-1345 zone3 (2-28-06) 50 5.35E-1345 zones 1,2 (3-05-97 05) 1 80 5.58E-1445 zones 1,2 (3-05-97 05) 2 80 5A88E-1445 zonesl,2,3 (3-05-97 08) 3 160 1.90E-1345 zonesl,2,3 (3-05-97 08) 1 80 2A.3E-1345 zonesl,2,3 (3-05-97 08) 1 160 1.80E-1345 zonesl,2,3 (3-05-97 08) 1 80 1.43E-1345 zonesl,2,3 (3-05-97 08) 2 80 2.21E-1345 zonesl,2,3 (3-05-97 'R) 2 160 1.63E-1345 zonesl,2,3 (3-05-97 08) 2 80 1.29E-1345 zonesl,2,3 (3-05-97 08) 3 80 2.53E-1345 zones 1,2,3 (3-05-97 08) 3 80 1.54E-1346 zonel (11-21-96 02) 10 4.0SE-1546 zone2 (12-18-02) 20 6.21E-1546 zone3 2-27-05 30 9.04E-1447 zonel (1I1-21-96 05) 300 6.1 IE-1447 zone2 (12-18-06) 100 4.35E-1347 zone3 (2-28-04) 50 4.65E-1348 zone (2 12-18-10) 80 3.52E-1448 zonel (11-22-96 03) 200 2.42E-1448 zone3 (2-28-10) 50 3.35E-1351 zonel (11-21-96 03) 5.00 8.81E-16

9

Page 10: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

Test ID Injection flow rate Q in K (m2)Standard Liters Per Minute(SLPM)

51 zone2 (11-22-96 05) 10 4.43E-1351 zone2 (3-05-97 02) 50 3.87E-1351 zone2 (2-27-03) 100 2.42E-1351 zone3 (2-28-02) 90 4.06E-1452zonel (11-20-9602) 400 1.04E-1352 zone2 (12-18-11) 100 1.16E-1352 zone3 (3-05-97 01) 200 1.59E-1252 zone3 (2-28-08) 50 2.02E-1253 zone 1(11-22-9602) 200 1.12E-1353 zone 1(11-22-96 02) 400 8.87E-1453 zone 1(11-22-96 02) 200 7.30E-1453 zone2 (11-22-96 04) 400 6.12E-12*53 zone2 (3-05-97 09) 400 1.27E-1253 zone2 (12-19-03) 410 6.23E-12*56 zonel (11-21-96 04) 3.00 1.94E-1556 zone2 (12-18-04) 10 3.42E-1456 zone3 (2-28-09) 50 4.79E-1357 zonel (1 1-22-96 01) 500 2.69E-1357 zone2 (12-18-08) 80 6.13E-1457 zone2 (12-19-02) 40 7.63E-1457 zone3 (2-27-01) 100 1.40E-1369 zonel (11-20-96 01) 400 2.12E-1369 zone2 (12-18-03) 50 9.51E-1569 zone3 (3-05-97 07) 150 3.82E-1369 zone3 (2-27-06) 60 4.88E-1370zone I (11-19-9602) 200 1.85E-1470 zone2 (12-18-05) 50 4.51E-1470 zone3 (3-05-97 06) 150 2.72E-1370 zone3 (2-28-05) 50 4.20E-1373 zonel (11-19-96 03) 200 6.64E-1473 zone2 (11-22-96 07) 24 6.79E-15

* The permeability value of over 6 x 10 `2 m2 for 53-2 measured in November and December 1996 is not a reliable

estimation of the permeability of the formation surrounding Zone 53-2. During November and December 1996, two

packers were installed in the 14 boreholes to nominally isolate the last 2/3 length of each boreholes. Due to obstruction

by rock in Borehole 53, the second packer in Borehole 53 is set at about 2 meters from the hole collar. As a result, the

injection zone 53-2 was surrounded by open sections of boreholes from which injected air could escape, which led to

an erroneously large estimate of the permeability. The situation is rectified in February 1997 when a third packer is

placed near the collar of all boreholes. then the pressure response in 53-2 from air injected in 53-2 correctly reflects the

perneability of the rock formation.

10

Page 11: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

Test ID Injection flow rate Q in K (M2 )Standard Liters Per Minute(SLPM)

73 zone2 (12-19-01) 6 5.76E-1573 zone3 (2-28-07) 50 L.OOE-1375 zonel (11-21-96 06) 500 3.59E-1375 zonel (2-28-01) 200 4.89E-1375 zone2 (12-18-01) 100 2.85E-1375 zone2 (2-28-03) 100 1.37E-1375 zone3 (2-27-02) 100 3.03E-1378 zonel (11-19-96 01) 200 5.45E-1478 zone2 (11-22-96 06) 60 1.14E-1478 zone3 (2-27-04) 60 7.79E-14

The results in Table 4 show that typically the estimated permeability of the same zone does notdiffer by more than 30% under different test conditions. This is on the same order of magnitudeas the coefficient of variation of the permeability value estimated from Equation (1) derived froman error analysis (Tsang et al., 1996), where permeability estimates under similar test conditionswere performed for the Single Heater Test. For the Single Heater Test, the coefficient of variation(ratio of the standard error of the calculated permeability to the calculated permeability) was

23%.

The results shown in Table 4 for the air injection into the entire length of Borehole 45 areinteresting. This is the case when Packers I and 2 are deflated, while the pressure sensors of allthree zones remain in the same position as when the three zones were isolated by all inflatedpackers. The nomenclature in Column 1 for this case is 45 zones 1,2,3, and the last numeral in thenomenclature denotes the pressure sensor assigned to the respective zone. The entries in Table 4indicate that the different sensors in the same Borehole 45 do not give the same pressure reading,resulting in different permeability estimates. For the same flow regime, the pressure rise AP isalways lowest for Sensor 3 and highest for Sensor 2. Similarly, the absolute pressur: zeading isalso different throughout the test and follows the same trend, with Sensor 3 registering the lowestabsolute pressure, Sensor 1 slightly higher than that in 3, and Sensor 2 registering the highestabsolute pressure. Both the AP and the absolute pressure readings are consistent with the spatialvariability of permeability within Borehole 45, as Table 3 shows that for the three zones inBorehole 45, zone 3 is most permeable, the permeability in zone I is about an order of magnitudesmaller than that in zone 3, and the permeability in zone 2 is another factor of 2 smaller than thatin Zone 1. These readings therefore indicate that within the borehole, there was dynamicmovement of air from "Zone 2" and "Zone 1" toward Zone 3, confirming the well-known factthat in a heterogeneous formation, the fluid tends to seeks out the least resistive path in the rockformation to flow. Hence in each injection test, flow out into the rock formation most probably

11

Page 12: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

occurs through only a fraction of the packed off zone. Therefore, for zones intersecting veryconductive features, Equation (1) would tend to underestimate the permeability, and the longerthe zone tested, the greater the underestimation.

The frequency distributions of the local permeability values as tabulated in Tables 3 and 4 areshown in Figure 5 in the top and middle graphs. For comparison, the distribution for the airpermeability values from the Single Heater Test block are also shown in Figure 5 in the bottomgraph. Note that the range of air permeability values are quite similar in the Drift Scale Test andthe Single Heater Test. That the variance in the permeability distribution from the SHTcharacterization is considerably larger than that from the DST is understood from the fact that thepacked zones in the DST characterization are on the order of 12 m or longer, while the injectionzones in the characterization for the SHT area are typically 5 to 8 m. The longer the injectionzones, the more averaging occurs, and therefore the narrower the distribution or the smaller thevariance. The statistics of the permeability values from the 14 holes from the DST are: minimum,8.8 x 10 " m; maximum, 2.0 x 10 -12 M2 ; arithmetic mean, 2.4 x 10.1) n2; median, 1.4 x 10 -13 d;

and geometric mean, 1.0 x 10.13 m2.

6. Interference Pressure Responses and Conceptual Model for Gas Flow in DST area

In the previous section, the focus was on the estimates of local permeability from the steady statepressure response in the zone into which air is injected, In this section, the discussion will be onthe pressure response from all the monitoring zones. Figures 6 through 15 show the pressureresponse from a selection of injection tests. A complete set of pressure response from all injectiontests will be submitted electronically and tracked through a TDIF. Figure 6 shows the injectioninto the most permeable zone 52-3 with a local permeability of 2 x 10l12 M2. For all these figures,

the horizontal axis denotes time, the right vertical axis denotes injection flow rate in standardliters ner minute (SLPM), and the left axis denotes the pressure increase from ab'i it, AP, inkPa. The legend on each graph denotes those zones where pressure response is measured, The listis manually sorted, in descending order of steady-state pressure rise, so that the injection zonewill always be at the top of the list. Figure 6a shows that the pressure in the majority of theboreholes rises and falls in response to the constant-flow air injection in 52-3. The information inFigure 6a is partitioned into three groups of steady-state pressure change, from large to small, andpresented again in Figures 6b through 6d. Hence Figure 6b presents all responses where thesteady state AP's have magnitude greater than 20% of the maximum steady-state pressure rise inthe injection zone, Figure 6c presents those that are less than 20% but greater than 6%, and Figure6d those that are less than 6%. Again, the legends list the monitored zones in order of themagnitude of their respective steady state AP. The readers are referred to Figures 1 and 3, which

12

Page 13: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

show the relative position of the injection and monitored zones in following the discussion of theinterference pressure data.

In general, the largest pressure response are in those monitoring zones that are relatively close tothe injection zone 52-3. These are represented in Figure 6b. Figure 6d shows that even thosezones that are tens of meters away from the injection zone communicates with 53-2, although themagnitude of the response is small. There is thus the general trend that the farther apart are theinjection and monitored zone, the smaller the magnitude of pressure response. However, note that57-3, in close physical proximity to 52-3, is listed in Figure 6d, the group of smallest measurablesteady state AP's, indicating the presence of a low permeability barrier between 52-3 and 57-3.

Figure 7 shows the pressure response from injection into 51-1, which is the most impermeablezone tested (with an estimated local permeability of 8.8 x 10 -16 in2). The contrast betw,. .1 Figure7a and 6a is apparent. The pressure builds up in 51-1 almost linearly to 120 kPa even with asmall injection rate of 10 liters per minute, indicating a highly impermeable rock formation.Pressure response down to 0.5% of maximum AP is not detected in any other monitored zone.Figure 7b plots those responses that are smaller than 0.5 % of the maximum AP's, and only twozones can be picked out: in 56-1, which is adjacent and parallel to 5 1-1, and perhaps in 70-2.

Figure 8 shows the injection test in another relatively low permeability zone, 78-2 (k=1.14 x 10 -4m2). Note again the steep pressure rise in 78-2 with the initial injection flowrate of 100 SLPM,and consequently the flowrate was adjusted down in two steps to the final constant rate of 60SLPM. A steady state AP is reached in 78-2. Again, no other interference pressure rise isobserved until the left vertical axis in Figure 8 is reduced to read AP less than 2% of themaximum; then, two pressure response curves from monitored Zones 73-2 and 75-2 appear. Thelarger response is in 73-2, due to the proximity of the two adjacent and parallel zones of 78-2 and73-2.

In Figures 9a and 9b r- shown the injection test in a reasonably permeable zone 75-1 (k = 9 x10 -12 mi). While most of the monitored zones th: register a pressure response are from boreholeswithin the same spatial cluster centered around y = 28 in, there is one exception: Figure 9b showsthat Zone 46-2 in the other cluster, tens of meters away, also responds to the air injection in 75-1.

Figures 10 and 11 show the pressure injection test in Zone 69-3, on two different dates, withdifferent constant flow rates. The data demonstrate that the injection test is quite repeatable. Thelocal permeability of 69-3 is similar to that of 75-1 in Figure 9.

The next example is for injection into 51-2 (k = 2 to 4 x 10 -13 mi) shown in Figure 12. Note thatin Figure 12a, the zones which respond to 51-2 with respective steady-state AP within 10 % ofthat of the injection zone, are parallel zones and therefore in close proximity to 51-2. In addition,

13

Page 14: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

more zones within the same spatial cluster as 51 (collar centered around 7 = 7m) respond withsmaller AP (less than 10 % but greater than 3 % of the AP from injection zone 51-2), as shown inFigure 12b. Figure 12c shows those pressure responses where the steady-state AP is less than 3 %of the maximum AP in the injection zone 51-2; note that the distant Boreholes 73, 75, 78 in theother spatial cluster (hole collars centered around Y = 28 m) now also register pressure rises inresponse to the injection test.

Figure 13 shows the interference pressure data for air injection into Zone 48-3 (local permeability3 x 10 -13 i 2 ). While there are very few zones with a pressure response within 8 % of the

maximum in the injection zone (Figure 13a), numerous zones indeed respond to the injection withAP less than 8% of the maximum AP for Zone 48-3.

Figure 14 shows the interference pressure data from injection in 69-1, which has a localpermeability of 2 x 10 .13 in2 . Note again that while the largest steady-state AP's shown in Figure14a are from boreholes within the same spatial cluster as and parallel to 69-1, distant zones tensof meters away also show pressure response when the vertical axis is scaled down to less than 1%of the maximum AP in Figure 14b. The pressure sensor for 73-1 demonstrates instability asshown in Figure 14a. The sensor was replaced for tests carried out in February and March of1997.

Lastly, in Figure 15, interference pressure data from the air injection into Zone 53-1 arepresented. Zone 53-1 has a local permeability of (0.7 to 1 x 10 -13 M

2), on the order of the

geometric mean of all permeability measured. The constant flow rate is doubled from 200 to 400SLPM during the same test. Again, similar to the previous cases discussed, a large number ofzones respond, not limited only to those that are in close proximity to the injection zone, thoughthe AP is typically small compared to that of the injection zone.

The interference pressure data of the 14 holes tested demonstrate that on the scale of I to 30meters, the fractures are well connected, and the a;- flow in the fractures resembles more that vi'flow through a continuum than flow through a discrete fracture network. Though the localpermeability values of the zones range over several orders of magnitude, most of the flow seemsto be taking place in a medium with an average permeability on the order of a fraction of darcy,and there is no evidence of a large permeability feature that forms a direct connection betweenzones. This is in contrast to the Single Heater Test block, where there is evidence of a largepermeability fracture zone about 4 meters in extent. To illustrate, the pressure responses for an airinjection test in borehole 11 in the Single Heater Test block are shown in Figure 16. In Figure 16awe see the pressure responses from the injection into Borehole 11 and three nearby monitoringBoreholes (28, 29, 31), all parallel to and within a meter of hole 11. Figure 16b indicates thepressure response in five more distant holes: Boreholes 6, 8 and 12 are parallel to 11, andBoreholes 7 and 13 are orthogonal to 11. The pressure data in Figure 16 reveal the presence of a

14

Page 15: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

direct flow path from Borehole 11 to Borehole 6 and 7. In other words, steady-state pressureresponse of almost identical magnitude as that in Borehole 11 is observed in Boreholes 6, 7, eventhough these hole are not spatially close to 11. On the other hand, Boreholes 28, 29, and 31,which are spatially closest to borehole 11, register much smaller pressure increases in response toair injection in Borehole 11. Based on the air injection data, borehole video logs and fracturemapping data, it was determined (Birkholzer and Tsang, 1996) that there is a vertical highpermeability feature (permeability values of darcies) about 4 meters in extent, which intersectsthe Boreholes 11, 2, 6, 8, 12, 7, and 13, while the rest of the Single Heater Test block exhibits alower permeability background. The pressure response in Boreholes 28, 29, 31 are through thelower permeability background. For injection and monitored zones that are closely spaced, thecharacterization data of the DST show the same kind of response exhibited by those of Boreholes28, 29, 31 in the Single Heater Test; when distance between injection and monitoring sectionsincrease to tens of meters, the DST characterization data show a pressure rise of a -uh smallermagnitude. None of :he DST data collected have the same characteristics as those pressureresponses shown in Figure 16b, where distance holes give a pressure response similar inmagnitude to that of the injection zone. The characterization data in the 14 holes from the AODtherefore do not reveal a direct connection on the scale of tens of meters. Rather, the data supportthe conceptualization of the fractures as a heterogeneous continuum.

Summary

Characterization by air permeability tests, prior to the onset of heating, was carried out in theDrift Scale Test block from 14 boreholes collared on the Access/Observation Drift. Conclusionsdrawn from the field measurements are based upon qualified data. Estimate of permeabilityvalues from steady-state pressure response show a range from 8.8 x 10 -16 m2 to 2. x 1012 2in.

These are of the same order of magnitude as those obtained form the Single Heater Test area(Tsang et al., 1996), as well as ,hose obtained Prom surface-based air-injection tosts in verticalboreholes for the Topopah middle non-lithophysal stratigraphic unit (Rousseau et al., 1996).

Consistent with the borehole videos, which indicate that all the boreholes are intercepted bynumerous fractures, the interference air permeability data indicate that the fractures are wellconnected, in that a pressure response to air injection is obtained in most monitoring zones.However, the magnitude of the pressure response is typically small in monitored zones ascompared to that in the injection zone, and a direct connection between two zones by a largefracture such as that found in the Single Heater Test block (Birkholzer and Tsang, 1996) is notevidenced here. This is not inconsistent with the fracture mapping from a Detailed Line Surveyperformed by the USGS/Bureau of Reclamation in the ESF. Sonnenthal and Ahlers (1997)reviewed and analyzed the data to determine the properties and distribution of fractures along the

15

Page 16: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

complete length of the ESF. They showed that more than half of the mapped fractures havelengths below 1 m and an average spacing of .5 m; and while the lengths of the fractures range allthe way to greater than 18 m, the spacing of the fractures increases quickly with their lengths. Infact, the mean spacing between fractures greater than 10 m is 20.9 m (with a standard deviation of25 m). Therefore, the DST block may be conceptualized as a fracture continuum formed by well-connected and mostly "short" fractures. The estimated local permeability values have a geometricmeans of 1 x 10 -1 ni2 and a median values of 1.4 x 1O3 "n 2 . Since a discrete large permeabilityfeature is not found in the set of 14 holes tested, and since in a continuum the fluid flow will seekout the least resistive path while avoiding low permeability regions, the fractures in the DST arewell approximated by a continuum with an average permeability on the order of 10-'3 m2 .

As boreholes in the Heated Drift become available, further air injection tests will be carried out inthem. Detailed interference data will also be obtained from the twelve hydrology holes (57through 61, 74 through 78, 185, 186 ) as shown in Figure 1 after the installation of permanenthigh temperature packers. These future data will help to refine the present conceptual model forthe fracture permeability structure in the DST area.

Acknowledgment

We thank Joe Wang and Jens Birkholzer for their review of the manuscript and comments forimprovement. Assistance from Melani Menendez-Barreto in data handling and graphics isgratefully acknowledged. The contribution from Ray Solbau, Don Lippert and John Clyde in thedesign, fabrication, and installation of field test equipment is invaluable. This work wassupported by the Director, Office of Civilian Radioactive Waste Management, U.S. Departmentof Energy, through Memorandum Purchase Order EA9013MC5x between TRW EnvironmentalSafety Systems. Inc. and the Ernest Orlando Lawrence Berkeley National Laboratory, underContract No. DE-ACO3-76SF00098

References

Birkholzer, J.H. and Y.W. Tsang, 1996. Forecast of thermal-hydrological conditions and airinjection test results of the Single Heater Test. Yucca Mountain Site Characterization ProjectMilestone SP918M4 for WBS 1.2.3.14.2, LBNL, Berkeley, CA. ACCN: MOY-970521-04.

Guzman, A.G., A.M. Geddis, MJ. Henrich, C.F. Lohrstorfer, and S.P. Neuman, 1996. Summaryof air permeability data from single-hole injection tests in unsaturated fractured tuffs at the

16

Page 17: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

Apache Leap Research Site; Results of steady-state interpretation, U.S. Nuclear RegulatoryCommission Report NUREG/CR-6360, NRC, Washington DC.

Hvorslev, MJ., 1951. Time lag and soil permeability in groundwater observations, Bulletin 36,U.S. Army Corps of Engineers, Water Ways Experimental Station, Vicksburg, Michigan.

LeCain, G.D., 1995. Pneumatic testing in 45-degree-inclined boreholes in ash-flow tuff nearSuperior, Arizona, USGS Water Resources Investigations Report 95-4073, USGS, Denver,Colorado.

Rousseau, J.P., E.W. Kwickles, and D.C. Gilles, eds., (in preparation). Hydrogeology of theunsaturated zone, North Ramp area of exploratory studies facility, Yucca Mountain, Nevada,U.S. Geological Survey Water-Resources Investigations Report, U. S. Geological Survey,Denver, Colorado.

Sonnenthal, E., and C.F. Ahlers, 1997. Fracture and fault properties for the LBNL unsaturatedzone flow model, Yucca Mountain Site Characterization Project Milestone SP24UFM4,LBNL, Berkeley, CA. DTN: LB960601233129.001.

Tsang, Y.W., J. Wang, B. Freifeld, P. Cook, R. Suarez-Rivera, T. Tokunaga, 1996. Letter reporton hydrological characterization of the Single Heater Test area in the ESF. Yucca MountainSite Characterization Project Milestone OS327322D1, LBNL, Berkeley, CA. ACCN: MOY-970512-07-B. DTN:LB960500834244.001

17

Page 18: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

Plan View

45 4647 48 49 50 5152 53 54 55'565758596061

A-I62 63

64 65 66 67 6869 70 71 72 7374 Z. 76 77 78

XBO7M02MAR

Figure Ia. Layout of DST area, plan view.

18

Page 19: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

June 1997

Section B-B

I I I I I I--

74-

. I.- I.- 1. . 42

, P, 0, 9: a.

1?: II: V a.

�T�

XBDg74-02491ALR

Figure lb. Layout of DST area, E-W section.

19

Page 20: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

74-§2:64

Section AA-1

76-71-66- -

R0M" x4\Heated,

(0.0.0 Located at thecenteillne of the .ntryko the heated _, _,

77-72-67 ' -

- - - - - ONo Drled yet

78-73-88-83

57-5247

Section AA-2

58-5348

59-5449 …---------_… _-_

% I /

Ro0-- -XJI L -\ Heated /

(0.0,0 Located at thecootealnof the entrykW to heated drit)

Is-

60-55-50 - -' ' '

- - - - -Not DrIled yet

61-56-148XBOO70e-024§Z=R

Figure ic. Layout of the DST area, two N-S sections .

20

Page 21: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Centralizer

1st monitoring zone

Inflatable Packer

2nd monitoring zone

N

Zone 1

\ Injection portPressure monitoring portInflatable Packer

CentralizerZone 2

\ Injection portPressure monitoring port

Inflation line

Injection lines

Pressure monitoring lines

Figure 2. Schematic diagram of a packer string with only two packers.

Page 22: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Characterization of the DST AreaPacker Positions in 14 AOD Boreholes

-- --- -- r-- -- -- -ZI

i I

I--I- I

f

I -Z = = x i W.-Www-I---I iII

IIIi11i

� i-6III

-4 I- I

--k I

-J.1�

I.

I}

Figure 3. Packer positions for the air permeability tests.

22

Page 23: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Local Air Permeability Estimatesnormalized to 2 darcies, color code in logarithm scale

--- - I - - - -- - -

Z

I

OtFI

15��-

IIi

la!r-

5�

I

i

/rDMplay:, 416kog~pdat

0.0-0.2

-0.6 /

-1-U.0

- 1.0-1.2-1.4-1.6-1.8-2-0-Z2-2-4-2.6-2.8-. 0-32

-- t

---- L I- 2t�-- __ I

-L- I-- 4

Figure 4. Local permeability estimates in 41 sections of the 14 AOD boreholes.

23

Page 24: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Ambient Characterization of the ESF Drift Scale Test Area

1.0 -

c 0.8-,o

wX0.40

2L 0.6-

c 0.4-@ -

LL. 0.2 -

0.0 -

1.0-

c 0.8--o

0.6-M

c 0.4-0*

IL 0.2-w

1 6 -15 -14 -13 -12 -11Logarithm of Permeability

Ed DST data (67 measurements)- Gaussian Fit

n(Iog k)- .025+0.68exp-((x+12.74)A2/0.72A2)RI

p I1M VM I U

bY- zV- -At- Z- - J- -- A--IpU.U -I I

-16 -15 -11-14 -13Logarithm of Permeability

-12

C

.0-.1

U)

C0*@3a-

-16 -15 -14 -13 -12 -11Logarithm of permeability

Figure 5. Frequency distribution of permeability values from the DST and SHT areas.

24

Page 25: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from InjecUon In Zone 52-3 (March 5, 1997-01)

4

3.5

3

2.5

a:S

250

200

a

100 &

50

0 i - -'a

9:28:48 9:36:00 9:43:12 9:50.24 9:57:36 10:04:48 10:12.00 10:19:12 1026:24 10:33:36 10:4048

Tnne

Figure 6a. Interference pressure data from injection in 52-3.

Pressure Response m InjectIon In Zone 52-3 (March 5,1997-01)( > 20% of maximum AP)

250

200

150i

100

50

a.

a.

9:28:48 9:36:00 9:43:12 9:5024 9:57:36 10:04:48 10:12:00 10:19:12 10:26:24 10:33:36 10:40:48

TOM

Figure 6b. Interference pressure data (for AP > 20%) from injection in 52-3.

25

Page 26: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection !n Zone 52-3 (March 5, 1997 - 01)(< 20%,> 6% of maximum iP)

~4

150 aI--a

100 I

0 . 1 - - i i i I -

9:28:48 9:36:00 9:43:12 9:50:24 9:57:36 10:04:48 10:12:00 10:19:12 10:2624 10:33:36 10:40:48

Time

Figure 6c. Interference pressure data (for 20% > AP > 6%) from injection in 52-3.

Pressure Response from Injection In Zone 52-3 (March 5, 1997 - 01)

(s 6%. of maximum AP)

FA.'aI

150

100 i

I 010:55:12928:48 9-43:12 9:57:36 10:12:00 102624 10:40.48

Time

Figure 6d. Interference pressure data ( for AP < 6%) from injection in 52-3.

26

Page 27: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection in Zone 51-1 (Nov. 21, 1996 -03)(> 0.5% of maximum ,P)

140

120

100

Do

so

40

20

12

10

I. a

10:33:36 10:40A4 10:48:00 1055:12 11:02:24 11:09:36 tl:15:48 11-24:00 1"1:12 1138:24 11:4536 11: 54a

Figure 7a. Interference pressure data (for AP >0.5%) from injection in 51-1.

Pressure Response from Injection In Zone 51-1 (Nov. 21, 1996 - 03)(< 0.5% Ot maximum AP)

0.3 I

0_;

0

I

a.0.1

--I I~- -56.1j.... 70-21

.2 8

15 V ~~~~~~~~~~~~~~~~~~~~~~~6

I ~~~~4

15 2. .

2

0

Ua

0.

0.C

10Q33:36 10:48:00 11:0224 11:16:48 11:31:12 11:45:36 1:

Time

Figure 7b. Interference pressure data (for AP < 0.5%) from injection in 51-1.

2:00:00

27

Page 28: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection In Zone 78-2 (Nov. 22,1996 - 06)(> 20/ of maximum AP)

140 120

120-100

10080

E IIE

60

40

40

2O ,.... 20 |-0 ~~~~~~~~~~~~~~~~~~~~~~~~0

15:04:19 15:07:12 15:10:05 15:12:58 15:15:50 15:18:43 15:21:36 15:2429 152722

Tnme

Figure 8a. Interference pressure data (for AP > 2%) from injection in 78-2.

Pressure Response from Injection In Zone 78-2 (Nov. 22, 1996 - 06)(< 2% of maximum ,P)

2 120

1.8

1G0

15:06 1 150:2I:00I51:8 1:S50 1:8U 1:1S 549 1:72

1.2

T

iue. 1b Inefeec presur daa(o 6 % ro netoni 82

I ~~~~~~~~~~~~~~~~~400.6

0.4 2

0.2

0 0

15:04:19 15:07.12 15:10:05 I5.12:58 15:15:50 15:18:43 15:21:36 15:24:29 15:2722

lime

Figure 8b. Interference pressure data (for AP < 2%) from injection in 78-2.

28

Page 29: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection in Zone 75-I (Feb. 28,1997- 01)( > 5% of max. AP)

10 250

200

150f

a5

39

50

.4

0 M-1 I I I . O

9:21:36 9:28:48 9:36:00 9:43:12 9:50:24 9:57:36 10:04:48 10:11200

Time

Figure 9a. Interference pressure data (for AP> 5%) from injection in 75-1.

Pressure Response from Injection in Zone 75-1 (Feb. 28, 1997-01)(< 5% of maximum AP)

0.35 250

200

150

100 if

50

7IL

A.'

0 1V ,_ I -_ -. I

9:21:36 9:28:48 9:36.00 9:43:12 9:5024 9:57:36 10:04:48 10:12:00

Tim.

Figure 9b. Interference pressure data (for AP < 5%) from injection in 75-1.

29

Page 30: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection In Zone 69-3 (Feb. 27, 1997 - 06)(I> 5% of maximum AP)

2

IL

a.

1.5

40.

S

30

20

0.5 _X- I........ . 0.

17:57:07 18:00:00 18:02:53 18:05:46 18:08:38 18:11:31 18:1424 18:17:17 18:20:10 1823:02 18:25:55

Tnme

Figure I Oa. Interference pressure data (for AP > 5%) from injection in 69-3.

Pressure Response from Injection In Zone 69-3 (Feb. 27,1997 - 06)(S 5% of maximum SIP)

.70

. 60

. 50

.40 FJ0

iC

. 30 1

. 20

.10

-ZILx

IL.4

17:57:07 18:00:00 18:02:53 18:05:46 18--08:38 18:11:31 18:1424 18:17:17 18:20:10 18:23-.M 18:25:0

Time

FigurelOb. Interferencepressuredata(forAP<5%)frominjectionin69-3.

30

Page 31: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection in Zone 69-3 (March 5,1997 - 07)(I> 3% Of maximum AP)

10

la

a.

180

160

140

120

100

80

60

40

20

_- 40

15:21:36 15:28:48 15:36.00 15:43:12 15:5024 15:57:3615:1424

Time

Figure I1 a. Interference pressure data (for AP > 3%) from injection in 69-3.

Pressure Response from Injection In Zone 69-3 (March 5,1997 - 07)(s 3% of maximum AP)

0.3 -

0

0.25,;

1a0

160

140

120

100

0.2

i 0.15

0.1

0.05

0 I

15:14-24 15:21:36 15:28:48 15:36:00 15:43:12 15:5024 15:57:36

Time

Figure 1 l b. Interference pressure data (for AP < 3%) from injection in 69-3.

31

Page 32: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Iniection In Zone 51-2 (Feb. 27, 1997-03)( > 10 ot rmaximum AP)

12

10t , , I-- --- -- --_-_

8

120

*100

40

20

r6

_^. _r * _^ A

15:36:00 15:43:12 15:5024 15:57:36 16:04:48 16:12:00 16:19:12 16:2624 16:33:36 16:40.48

Time

Figure 12a. Interference pressure data (for AP > 10%) from injection in 51-2.

Pressure Response from Injection In Zone 51-2 (Feb. 27 1997 -03)(< 10%, a 3% of maximum AP)

57-2 100.9 53 1

- -53- 2 o

0.7 - - 5 --47- 2 so

0.6 -- -48- 2

I ~~~~~~~~~~~~~~~~~~~52- 3

O.S ~ I [- - - S&3 604.

FGO

i

I

O, I~ -1 I Io15:36:00 15:43:12 15:5024 15:57:36 16:04:48 16:12:00 16:19:12 16:2624 16:33:36 16:40:48

Time

Figure 12b. Interference pressure data (for 10% > AP > 3%) from injection in 51-2.

32

Page 33: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection In Zone 51-2 (Feb. 27, 1997 -03)(<c 3% of maximum AP)

0.3-52- 2

- -- 45-2

0.25 --- 5

--73- 2

0.2 70- 27S- 752

73- 3

;S 0.15 i '-- 69- 3

--- 7S- 3

0.1 -57-1

N ~~~~~- -52-1

-44 -~~~~~~FLOW

120

z

603

.2

0 -- -=L_ ;_ 0

15:36:00 15:43:12 15:50.24 15:57:36 16:04:48 16:12.00 16:19:12 16:26:24 16:33:36 16:40:48

Time

Figure 12c. Interference pressure data (for AP < 3%) from injection in 51-2.

33

Page 34: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection in Zone 48-3 (Feb. 28, 1997 -10)(> 8% of maximum AP)

6

5

4

T

d, 3G.

2

3:I

o -i l 014:00.58 14:03:50 14:06:43 14:09:36 14:1229 14:15:22 14:18:14 14:21:07 14:24:00 14:26:53 1429:46

Time

Figure 13a. Interference pressure data (for AP > 8%) from injection in 48-3.

Pressure Response from Injection in Zone 48-3 (Feb. 28,1997 -10)(:s 8% of maximum AP)

0.45 60

-47-3

0.4 - -- 57. 2

. . 48-2 50

0.35 -- 56- 3

>-:-.1 1"--'4 1~~~~~~~~~---8-

0.3 51- 3 40

-- 53-1

v0.25 -51

At ~~~~~~~~~~~~~~~~~46- 2 300.2 ~~~~~~~O.2 ~~~~~~~~~~~~~~~~~~~~~~45. 3

Fgr1bInefrn rsuedt(fr <8)foin i 8--.2

0.15 - ~~~~~~~~~~~~~~~~~~~- - - 52-2 2

0.1

0.05 1

0 _ _ _ _ _ _ _ _ _ 014:00:58 14:03.50 14.06:43 14:09:36 14:1229 14:15:22 14:18:14 14:21:07 14:24:00 14:26:53 1429:48

Tkne

Figure 1 3b. Interference pressure data (for AP < 8%) from injection in 48-3.

0

34

Page 35: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response trom Injection in Zone 69-1 (Nov. 20, 1996- 01)(> 1% of maximum AP)

45 450

40 400

35 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ -70-1 35

30 42 13:00__ _ _73-1

-- 70-2 025 FLW 250

a.ur 14a. Inefrnepesr aa(o P )fo neto n6-

* ~P20 200R

153 -~ 150

10 100

5 50

0 0

8:52:48 9:21:38 9:5024 10:19:12 10:48:00O 11:16:48 11:45:36 12:14:24 12.43.12 13:12.00

rimm

Figure 14a. Interference pressure data (for AP > 1%) from injection in 69-1.

Pressure Respons. from InjectionIn Zone 69-1 (Nov. 20, 1996- 01)(c1% of maximum AP)

0.3 450

- 78-1400

- - -73-20.25

---- 78-2350

--57-1

52-10.2 300

48-1

-- 47-1 25

451 200

0.1 FLOW 5

100

0.05 1

50

0 0

Figurel14b. Interference pressure data (forTA'< 1%) from injection in 69-1.-

35

Page 36: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection in Zone 53-1 (Nov. 22, 1996- 02)(a 3% of maximum AP)

60 450

.400

50.350

40 -53-1 30

--- 48-2 20

A. ---- ~~~~~~~~~~~~~~~~~~~~~56-2

d. --- 51-2

20 150

100

10 ~~~~~~~~~...~~...s

0 0

11:31:12 11:45:36 12:0000 12:1424 1228:48 12:43:12 12:57:36 13:12.00 132624 13:40:48

lime

Figure 15a. Interference pressure data (for AP < 3%) from injection in 53-1.

Pressure Response from Injection In Zone 53-1 (Nov. 22. 1998 - 02)( 3% of maximum AP)

1.25 450

400-46-2

1 ~~~~~~~~~~~~~~~~~~~~~~...46-1- -. 5 7-215

____73-2

0.75 --- 78-2 20

S I - - ~~~~~~~~~~~~~~~~~~~~~70-2-

* ---~~~~~~~~~~~~75-20.5

...J

0.25 1'00

50

0 100

11:31:12 11:45:36 12:00001142 1284 12312 2:7 31:00 132624 13:40:48

Figure 15b. Interference pressure data (for AP' < 3%) from injection in 53-1 -

36

Page 37: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

Pressure Response from Injection in Hole 11 (May 28,1996- 04)

3.5

2.5

2

1.5

1200

1000

600 j

240

40D

T0.

200

0 aL _ . - __3:07:12 PM 3.21:36 PM 3:36:00 PM 3:5024 PM 4:04:48 PM 4:19:12 PM 4:33-36 PM 4:48.00 PM 5:0224 PM

Time

Figure 16a. Pressure response from nearby holes from injection in Hole 11 in SHT block.

Pressure Response from Injection In Hole 11 (May 28,1996-04)

1200

1000

4~ SW

400

200

01 M I i i I 4

3.07:12 PM 3:21:38 PM 3:36-CO PM 3:50.24 PM 4:04:48 PM 4:19:12 PM 4:33:36 PM 4:48:00PM 5:0224 PM

TIme

Figure 16b. Pressure response from distant holes from injection in Hole 11 in SHT block.

37

Page 38: Ambient Characterization of the ESF Drift Scale Test Area ... · 3. Test Equipment The air permeability testing equipment consisted of pneumatic packers, pressure sensors, air supply

DRAFT DISCLAIMER

This contractor document was prepared for the U.S. Department of Energy (DOE), but has not

undergone programmatic, policy, or publication review, and is provided for information only.

The document provides preliminary information that may change based on new information or

analysis, and is not intended for publication or wide distribution; it is a lower level contractor

document that may or may not directly contribute to a published DOE report. Although this

document has undergone technical reviews at the contractor organization, it has not undergone a

DOE policy review. Therefore, the views and opinions of authors expressed do no' -ccssarily

state or reflect those of the DOE. However, in the interest of the rapid transfer of information,

we are providing this document for your information.