Aluminium Composite Panel
Overview
1. What is Aluminium Composite Panel (ACP)
2. Why is ACP a problem
3. The Government Cladding Audit
4. What impact might ACP have on you
5. Q&A
What is ACP
What is ACP
Why is ACP a problem
Why is ACP a problem
Why is ACP a problem
Why is ACP
a problem
Why is ACP a problem
Building & Other Legislation Amendment (Cladding) Legislation
2018
“The Process”
The Process
• 3 Stage Process
• Stage 1
• Cladding Audit Checklist
• Stage 2
• Building Industry Professional Report
• Stage 3
• A Fire Engineer Statement
Compliance “Zone”
Jerry Tyrrell - https://buildingconnection.com.au/2018/07/24/2402/
Compliance “Zone”
https://atkar.com.au/building/choosing-safe-materials/
Stage 1 – Deadline 29 March 2019
Committee Appoints Agent;
Agent:
Complete Stat Dec
Registers Building
Complete Site Inspection
Completes Cladding Checklist
Stage 1 – Deadline 29 March 2019
Committee Appoints Agent;
Agent:
Submits Checklist to QBCC
Submits Checklist to Strata Manager
Strata Manager Store Checklist on Strata
Records for 7 Years
What impact might ACP have on you
Stage 2 – 29 May 2019
Where Cladding Identified in Stage 1
Building Industry Professional Statement
Strata Manager Store Building Industry
Professional Statement on Strata Records for 7
Years
Stage 3 – 3 May 2021
A Fire Engineer Statement about the Building
Fire Safety Risk Assessment
The Building Fire Safety Risk Assessment and
Fire Engineer Statement must be kept for at
least 7 years.
Stage 3 – 3 May 2021
Where the building fire safety risk assessment
states a building is an affected private building, an
owner must:
Display an affected private building notice
Stage 3 – 3 May 2021
Where the building fire safety risk assessment
states a building is an affected private building, an
owner must:
Provide lot owners or tenants with a copy of the
building fire safety risk assessment
What if you don’t comply
Q & A