ALTERNATIVE CONTRACTING. ALTERNATIVE CONTRACTING. LUMP SUM DESIGN BUILD CM@RISK. LUMP SUM. Lump Sum. What is it? Project Selection Construction Contract Administration. What is it?. - PowerPoint PPT Presentation

Citation preview

Page 1: ALTERNATIVE CONTRACTING

ALTERNATIVE CONTRACTING

1

Page 2: ALTERNATIVE CONTRACTING

ALTERNATIVE CONTRACTING

LUMP SUMDESIGN BUILDCM@RISK

2

Page 3: ALTERNATIVE CONTRACTING

LUMP SUM

3

Page 4: ALTERNATIVE CONTRACTING

Lump SumWhat is it?Project SelectionConstruction Contract Administration

4

Page 5: ALTERNATIVE CONTRACTING

What is it?Method of Contracting upon which Contractor submits a LS Bid for all work vs. bidding individual Pay Items

Intended to reduce design & contract administration costs

5

Page 6: ALTERNATIVE CONTRACTING

Project Selection“Simple” ProjectsWell Defined ScopeLow risk of unforeseen conditionsLow possibility of changes during all phases

6

Page 7: ALTERNATIVE CONTRACTING

Construction Contract Administration

Payments based on approved payout schedule (SoV)

Inspection Personnel should not be required to document quantities (except for those subject to adjustments i.e. asphalt)

Focus on Inspection, Quality and Conformance with contract

7

Page 8: ALTERNATIVE CONTRACTING

LUMP SUM Project plans preparation

Desired Elements Typical Sections Milling/Resurfacing (and overbuild

where appropriate) details Summary boxes when work not shown

on Plan Sheets Plan Sheets depict existing conditions

& detail work to be performed

Page 9: ALTERNATIVE CONTRACTING

LUMP SUM Project plans preparation

Desired Elements (continued) Plan Sheets detail all work not covered by Typical

Section and/or Design Standards Cross Sections (when shoulder point is moved) Signing/Pavement Marking, Signalization and Lighting

Plans: Include Pay Items for Reference Purposes Only Include Note: “Pay item number provided only for

purpose of describing work to be performed”

Page 10: ALTERNATIVE CONTRACTING

LUMP SUM STANDARD SPECIFICATIONS

2-3.1 – INTERPRETATION OF QUANTITIES (Lump Sum Contracts)

Bidder responsible for determination of quantities

Page 11: ALTERNATIVE CONTRACTING

LUMP SUM STANDARD SPECIFICATIONS

105-2 ADDITIONAL REQUIREMENTS FOR LUMP SUM PROJECTS Job Guide Schedule

Project specific list of materials & quantities

Submit 21 days prior to commencement of construction

Update Monthly

No Commencement until Department Approval

Final JGS at Final Acceptance

Page 12: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0030100LS – Award & Execution of Contract 3-1

For the purpose of award, after opening and reading the proposals, the Department will consider the total Contract Lump Sum Price as the bid. On this basis, the Department will compare the amounts of each bid and make the results of such comparison available to the public. Until the actual award of the Contract, however, the Department reserves the right to reject any or all proposals and to waive technical errors that the Department may deem best for the interest of the State. In the event of any discrepancy in the two entries of the Contract Lump Sum Price, the Department will evaluate the bid based on the lump sum price shown in words.

Page 13: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0040100LS – Scope of Work 4-1 Intent & Scope

LS Contract w/1 Pay Item Listed in Contract

Pay Item Number References superseded by the LS Pay Item

Payment for all work made under LS Pay Item

Pay Adjustments don’t apply (except for those in 9-2)

Page 14: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0040100LS – Scope of Work 4-3.1 General

Defines term “significant change” as Engineer determination

Deletes reference to 125% increase / 75% decrease of “original Contract quantity”

Page 15: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0050501LS – Control of the Work 5-1.1

Adds “All reference to separate payment for individual items of work will not apply. The cost for various items of work will be included and paid for under the Contract Lump Sum Price.”

Page 16: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0060100LS – Control of Materials 6-1.3.3

Establishes material sampling & testing acceptance requirements are in accordance with 105-1 & 105-2 for the following:

Earthwork Base Hot Bituminous Mixtures Portland Cement Concrete Reinforcing Steel Fabricated Metals

Page 17: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0060100LS – Control of Materials 6-1.3.4

Establishes specific certification requirements for QPL Products

Notarized Certification prior to material utilization Manufacturer Letterhead Product Name & Batch Number FPID & Contract Number County Test Result Certification Statement

Page 18: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0060100LS – Control of Materials 6-1.3.5

Establishes specific certification requirements for Non-QPL Products

Notarized Certification prior to material utilization Manufacturer Letterhead Material Identification Material Type FPID & Contract Number County Test Result Certification Statement

Page 19: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0080401LS – Prosecution & Progress 8-7.3.1 – Increased Work

Department may grant time extension when adding new work or providing for unforeseen work rather than overruns in original contract items.

Page 20: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment 9-1.3

Establishes criteria for the determination of Pay Reductions

Page 21: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment (cont.)

9-2.1 Establishes those items included in LS Payment

Furnishing all materials Performing all work Loss / damage arising out of nature of work Overhead Profit Direct / Indirect Cost

Page 22: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment (cont.)

9-2.1.1 Establishes criteria for Fuel Adjustments

on Contracts with an Original Contract Time in excess of 120 Calendar Days

Page 23: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment (cont.)

9-2.1.2 Establishes criteria for Bituminous

Adjustments on Contracts with an Original Contract Time in excess of 365 Calendar Days or more than 5,000 Tons of Asphalt

Page 24: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment (cont.)

9-2.2 Establishes Pay Adjustment criteria for:

Deficiencies (9-2.2.1) Spread Rate (9-2.2.2) Overbuild (9-2.2.3) Foundations (9-2.2.4) Quality (9-2.2.5) Deleted Work (9-2.2.6)

Page 25: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment (cont.)

9-5.5.2 Establishes Partial Payment criteria

Partial Payments less than $5,000 in any one month are not processed

No Partial Payment for aggregate or base material received after paving / base construction begins unless Department suspends paving or base operations

Deletes item bid price limitations placed on: Structural Steel / Precast Pre-stressed Items

(85%) Other Items (75%)

Page 26: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment (cont.)

9-11.1 Establishes Invoice Submittal Requirements:

Contractor prepares Invoice & submits to Engineer

Engineer approves Invoice prior to making payment

Page 27: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment (cont.)

9-11.2 Establishes Invoice Submittal Requirements:

Submit by 12:00 on Monday following estimate cut-off date

Invoice based on work completed Invoice must include:

Contract/FPID/Invoice Number Invoice Date & period covered

Page 28: ALTERNATIVE CONTRACTING

LUMP SUM SPECIAL PROVISIONS

SP0090103LS – Measurement & Payment (cont.)

9-11.2 Establishes Invoice Submittal Requirements (cont):

Basis of Progress Invoice amount: Approximate Quantities Less Previous Payments Less amounts previously retained or withheld

Contract Summary: % dollar value of completed work % of days used based on present Contract Days

Certify: Fuel & Bituminous Gallons Steel weight for Indexed items

Page 29: ALTERNATIVE CONTRACTING

DESIGN-BUILD

29

Page 30: ALTERNATIVE CONTRACTING

Design-BuildAuthorizationProject SelectionCriteriaWarranties

30

Page 31: ALTERNATIVE CONTRACTING

DESIGN-BUILD AUTHORIZATION

31

Page 32: ALTERNATIVE CONTRACTING

Authorization

Design Build (D-B) Contracting Authorization – FLORIDA STATUTES

D-B Major Projects Authorization – 337.11(7) F.S. Buildings Major Bridge Limited Access Facilities Rail Corridor

Estimated cost exceeds $10M

32

Page 33: ALTERNATIVE CONTRACTING

Authorization

Design Build (D-B) Contracting Authorization FLORIDA STATUTES

Minor D-B Projects Authorization –337.025 F.S. Innovative Contracting Statute – Annual Cap

of $120M Minor Bridge Resurfacing (no widening/shoulder work) Projects not covered by 337.11(7) F.S.

Estimated Cost less than $10M

33

Page 34: ALTERNATIVE CONTRACTING

DESIGN-BUILD PROJECT SELECTION

34

Page 35: ALTERNATIVE CONTRACTING

Project SelectionDesign Build (D-B) contracting should be considered on

the following types of projects: Demand an expedited schedule and can be

completed earlier Require minimal Right of Way acquisition and

utility relocation Well defined scope Allow for innovation in the design and/or

construction effort Low risk of unforeseen conditions Low possibility of significant changes

35

Page 36: ALTERNATIVE CONTRACTING

Project SelectionExamples of projects which may be good D-B

contracting candidates: Major Bridges Minor Bridges ITS (computer signalized traffic) Intersection improvement (with known

utilities) Buildings-office building, rest areas,

welcome stations, etc.

36

Page 37: ALTERNATIVE CONTRACTING

Project SelectionExamples of projects which may be good D-B

contracting candidates (continued): Interstate widening Rural Widening Fencing Landscaping Lighting Signing Signalization Guardrail

37

Page 38: ALTERNATIVE CONTRACTING

Project Selection

Examples of projects which may not be good D-B contracting candidates are:

Major bridge rehab/repair with significant unknowns

Rehab of movable bridges

Urban construction/reconstruction with major utilities, major subsoil, R/W or other major unknowns

38

Page 39: ALTERNATIVE CONTRACTING

DESIGN-BUILD CRITERIA

39

Page 40: ALTERNATIVE CONTRACTING

Developing Design-Build Criteria

Adjusted Score or Low Bid?Adjusted Score

• Want (or need) to have input by evaluating the D-B firm and Technical Proposal (prior to bid time)

• Innovation or potential alternatives exist• Scope is more versatile

40

Page 41: ALTERNATIVE CONTRACTING

Developing Design-Build Criteria

Low Bid• Straight forward projects

–(guardrail, noise walls, milling and resurfacing, etc.)

• Scope is well defined

41

Page 42: ALTERNATIVE CONTRACTING

Request for ProposalsMuch of the language is standard from

SCO website

Grading CriteriaDecide what is important

InnovationMaintenance of TrafficAestheticsEnvironmentalSchedule

Assign Points Accordingly42

Page 43: ALTERNATIVE CONTRACTING

43

Two Phase Adjusted Score Design-Build Procurements

• ASDB procurement – Two phase process which combines evaluation scores of– Phase I - Expanded Letters of Interest (ELOI)

– Phase II - Technical proposal

Page 44: ALTERNATIVE CONTRACTING

Evaluate & Score

RFP

Select Design-Builder

Evaluate & Score

Technical Proposals

Award Contract

Short List

ELOI

Two Phase Process

Phase I Phase II

Calculate Lowest Adjusted Score Using

Price Proposal from D-BFirm

44

Page 45: ALTERNATIVE CONTRACTING

Issue Escalation & Resolution

RFP sets a hierarchy for design issues and construction issues to be resolved through a defined chain of command

D-B Firm will be required to set a similar escalation process for both design and construction

45

Page 46: ALTERNATIVE CONTRACTING

Issue Escalation & Resolution

Design Project Manager

Construction Project Mgr

District Design Engineer

District Const. Engineer

Director of Development

Director of Operations

District Secretary

District Secretary46

Page 47: ALTERNATIVE CONTRACTING

STIPENDS

Only on ASDB Projects47

Page 48: ALTERNATIVE CONTRACTING

Stipends for unsuccessful firms

The Department intends to compensate eligible unsuccessful short-listed Firms for submitting a proposal

The eligible unsuccessful short-listed Firms may receive compensation (lump sum) for their efforts in preparing a proposal if the proposal is determined to be responsive

The intent to compensate and the amount of compensation will be noted in the RFP

This decision will be at the discretion of the contracting District or Central Office.

48

Page 49: ALTERNATIVE CONTRACTING

Stipends for unsuccessful firms

Federal funds MAY be used. A Stipend is not intended to compensate the Firms

for the total cost of preparing the proposal package. In return, the Department reserves the right to use

any of the concepts or ideas within the technical proposals, as the Department deems appropriate.

49

Page 50: ALTERNATIVE CONTRACTING

CM@Risk

50

Page 51: ALTERNATIVE CONTRACTING

CM@Risk Agenda

– CM@Risk What is it?

– CM@Risk Contract Structure

– CM@Risk Process

– CM@Risk Advantages

– CM@Risk Project Selection Criteria

51

Page 52: ALTERNATIVE CONTRACTING

CM@Risk • CM@Risk is an integrated team approach

that applies modern management techniques in the planning, design, and construction of a project in order to control time and cost, and to increase the quality and value of the project for the owner.

• Team= owner (Department), the architect/engineer and the construction manager (CM)

• Transportation or building project52

Page 53: ALTERNATIVE CONTRACTING

CM@Risk Contract Structure

CM FIRM(Prime Contractor)

Designer

OWNER

SubContractorsSubContractors

Constructibility

53

Page 54: ALTERNATIVE CONTRACTING

CM@Risk Process

• District hires Designer

• District hires CM Firm used standard consultant selection process– Early in the design phase, 30% plans

– Negotiated CM fee

– CM Fee during Design Phase: 1-1.5% of Construction Cost

– CM Fee during Construction Phase: 4-8% of Construction Cost

54

Page 55: ALTERNATIVE CONTRACTING

CM@Risk Process (continued)

• CM Firm provides construction input throughout design development to minimize risks and improve the schedule

• Construction components for a project may or may not be added by Supplemental Agreement

55

Page 56: ALTERNATIVE CONTRACTING

CM@Risk Process (continued)

• FDOT Prepares and Manages the Design– Constructability reviews by CM during design

to optimize the design and control costs

– CM has no Direct Control over the Design

• CM selected thru Professional Services– Limited to Quality Contractors

– Qualification Based Selection

– Historical Performance of the Contractors is considered

56

Page 57: ALTERNATIVE CONTRACTING

CM@Risk Process (continued)

• CM Firm Responsible for Construction– Guaranteed Maximum Price (GMP) – The

Department pays only for cost of the work, up to GMP.

– Generally prohibit self-perform

– Enhanced control of subcontractor selection

57

Page 58: ALTERNATIVE CONTRACTING

CM@Risk Process (continued)

• The role of the CM is to represent the interests of the owner in all phases of the project.

• The CM is to perform value engineering, cost estimates, and schedule and budget recommendations during the preconstruction phase to assist in determining the best value based on the budget.

58

Page 59: ALTERNATIVE CONTRACTING

CM@Risk Process (continued)

• The CM may provide suggestions for alternate designs, construction materials, and processes.

• The Department will maintain final approval of all proposed changes.

59

Page 60: ALTERNATIVE CONTRACTING

CM@Risk Process (continued)

• During the design phase, usually about 60% plans, the CM will submit a GMP for acceptance by the Owner/ Department.

• The CM warrants that the project will be built not to exceed the GMP and assumes the risk by holding all of the subcontracts to perform the work.

60

Page 61: ALTERNATIVE CONTRACTING

CM@Risk Advantages

• Time– Eliminates Bidding and Contract Execution Time

– Bidding Prior to Completion of Design

– Flexibility to Re-Bid

– Procure materials early

– Reduction in Time Overruns

– Contractor participation can speed up design

– Construction can begin prior to: right-of-way clear, all permits issued, utilities identified or finalized

61

Page 62: ALTERNATIVE CONTRACTING

CM@Risk Advantages• Cost

– Approximately Same Costs (Based on Risk)

– Requires CM Fee

– Claims Reduced, Reduced Cost Overruns

• Risk– Construction Contract between CM and

subcontractors

– Shifted from Owner/Department to CM Firm; subletting the construction work

– Reduce Quantity Risk62

Page 63: ALTERNATIVE CONTRACTING

CM@Risk Advantages (continued)

• Innovation– Excellent Use of Contractor and Designer Linkage

• Technical– Qualifications Based Selection of Best Contractor

– Allows for Significant Changes During Construction

63

Page 64: ALTERNATIVE CONTRACTING

CM@Risk is NOT a standard practice

• Section 337.025 Florida Statutes applies to all project types as part of the innovative practices package and the Department is required to comply with the $120 million annual contracting monetary cap.

64

Page 65: ALTERNATIVE CONTRACTING

CM@Risk is NOT a standard practice• As a result, all projects must have approval

from Central Office.

• All requests should be sent to the State Construction Office for the Chief Engineer’s approval

• On Federally funded projects, the Department must have specific authorization from Federal Highway Administration (FHWA), Special Experimental Projects (SEP)-14.

 

65

Page 66: ALTERNATIVE CONTRACTING

CM@Risk Project Selection

• In selecting a project delivery method, gauge the level of complexity, uniqueness and innovative approaches of a project so as to maintain control of the project.

• No single project delivery strategy is appropriate for all projects and there are some key factors to consider:

66

Page 67: ALTERNATIVE CONTRACTING

CM@Risk Project Selection (continued)

• Size of Project– The more complex and costly a project, the

greater the need for professional management and advice

• Owner Capabilities– Assess in-house capabilities in evaluating

project procurement methods and construction management or use a General Engineering Consultant

67

Page 68: ALTERNATIVE CONTRACTING

CM@Risk Project Selection (continued)

• Time Consideration– If the project needs to be constructed in a

compressed timeframe, methods adaptable to fast-track construction of components can be considered, but weighed against increased cost and risk of fast tracking.

– An unrealistic schedule should not be used on a CM@Risk project. This can drive up the cost.

68

Page 69: ALTERNATIVE CONTRACTING

CM@Risk Project Selection(continued)

• Likelihood of Changes– If the scope of work cannot be defined

adequately upfront or if requirements are likely to change considerably during the project, this factor should be evaluated against potential cost of such changes.

– CM can negotiate better prices subject to owner’s approval and changes can be done in a timely manner to reduce delay claims.

69

Page 70: ALTERNATIVE CONTRACTING

CM@Risk Types of Projects

• Buildings/Vertical construction projects where construction methods and specifications vary between professionals (i.e. architect and construction trades).

• Projects with budget constraints which threaten the delivery of the project and where CM alternatives can help contain the costs.

70

Page 71: ALTERNATIVE CONTRACTING

CM@Risk Types of Projects(continued)

• Projects that allow for innovative funding scenarios

• Complex construction projects where construction input will be most beneficial during the early phases of design.

71

Page 72: ALTERNATIVE CONTRACTING

CM@Risk Types of Projects(continued)

• Major Projects where there is a good balance of risk to reward. Project has significant utility relocations and can be investigated by the CM and the CM can provide insight in the design.

• Corridor Projects

• Bridge Rehabilitation (Bascule)

• Unusual or out-of-the ordinary projects, use of new technology; ITS

72

Page 73: ALTERNATIVE CONTRACTING

CM@Risk

• The Department plans to use CM@Risk for appropriate type projects. Project selection should be coordinated with the State Construction Office.

• CM@RISK should not be considered on the following types of projects: Milling and Resurfacing, Guardrail, Signing, Landscaping, Lighting, Signalization, and Sidewalks

73

Page 74: ALTERNATIVE CONTRACTING

CM@Risk

• Additional information can be found on the State Construction Office website:

http://www.dot.state.fl.us/construction/CONSTADM/CM@Risk/CM@Risk%20Main.htm

74

Page 75: ALTERNATIVE CONTRACTING

QUESTIONS?

75