5
ALL MEMBERS INFORMATION SHEET NO AM-2019/20-001 5 NOVEMBER 2019 Joe Gordon, Head of Contract Services Ext: 4190 Email: [email protected] REPAIRS AND MAINTENANCE 2020 Introduction Following the decision by Housing Committee in April 2019 to insource the Repairs and Maintenance Service, this information sheet provides an update on progress to date. Scrutiny Two groups have been established to deliver and oversee the project. The Project Champions Group (PCPM) has responsibility for operational delivery of the sixteen mini or sub projects, and report into the Mobilisation Governance Meeting (MGM) That is sponsored by the Chief Executive and includes member governance who have responsibility for the Strategic oversight of the project. Project teams are cross departmental to ensure silo working is minimised. Progress Good progress has been made and no major barriers have been encountered to date. We are acutely aware of the inherent risks in respect of TUPE and are monitoring this closely, however, this is largely outside of our direct control or influence. MP Ref Project Heading Key Status Update 1 De-mobilisation Project manager appointed Hannah Perry-Gardiner (started October) HPG will manage projects 1, 2 & 4 Notices served and Transfer of Undertakings (Protection of Employment) Regulations.(TUPE) lists received 2 Mobilisation Mobilisation plan and strategy complete Budget defined and monitored 3 Delivery Brand Tenant groups consulted on ideas for branding Branding was taken to SLT 12 options were presented SLT requested a further logo with a house design House design logo signed off 10 th September Ben Falconer finalising logo for final sign off

ALL MEMBERS INFORMATION SHEET NO AM-2019/20-001 5 … · HPG will manage projects 1, 2 & 4 Notices served and Transfer of Undertakings (Protection of Employment) Regulations.(TUPE)

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ALL MEMBERS INFORMATION SHEET NO AM-2019/20-001 5 … · HPG will manage projects 1, 2 & 4 Notices served and Transfer of Undertakings (Protection of Employment) Regulations.(TUPE)

ALL MEMBERS

INFORMATION SHEET NO AM-2019/20-001 5 NOVEMBER 2019

Joe Gordon, Head of Contract Services Ext: 4190

Email: [email protected]

REPAIRS AND MAINTENANCE 2020 Introduction Following the decision by Housing Committee in April 2019 to insource the Repairs and Maintenance Service, this information sheet provides an update on progress to date. Scrutiny Two groups have been established to deliver and oversee the project. The Project Champions Group (PCPM) has responsibility for operational delivery of the sixteen mini or sub projects, and report into the Mobilisation Governance Meeting (MGM) That is sponsored by the Chief Executive and includes member governance who have responsibility for the Strategic oversight of the project. Project teams are cross departmental to ensure silo working is minimised. Progress Good progress has been made and no major barriers have been encountered to date. We are acutely aware of the inherent risks in respect of TUPE and are monitoring this closely, however, this is largely outside of our direct control or influence.

MP Ref Project Heading Key Status Update

1 De-mobilisation Project manager appointed – Hannah Perry-Gardiner (started October)

HPG will manage projects 1, 2 & 4

Notices served and Transfer of Undertakings (Protection of Employment) Regulations.(TUPE) lists received

2 Mobilisation Mobilisation plan and strategy complete

Budget defined and monitored

3 Delivery Brand Tenant groups consulted on ideas for branding

Branding was taken to SLT – 12 options were presented

SLT requested a further logo with a house design

House design logo signed off 10th September

Ben Falconer finalising logo for final sign off

Page 2: ALL MEMBERS INFORMATION SHEET NO AM-2019/20-001 5 … · HPG will manage projects 1, 2 & 4 Notices served and Transfer of Undertakings (Protection of Employment) Regulations.(TUPE)

ALL MEMBERS

INFORMATION SHEET NO AM-2019/20-001 5 NOVEMBER 2019

Joe Gordon, Head of Contract Services Ext: 4190

Email: [email protected]

Communication strategy completed

SDC Property Care has been adopted as the preferred name for the new service following consultation

4 Company Structure Structure complete

Revised job descriptions completed by first week in November

Consultation and communication commences mid November

5 Policy 90 risk assessments identified – 30 completed

Business plan including drivers being developed – complete in draft mid-November

Business accreditations reviewed – S2020 will seek accreditation in o NICEIC o Safe Contractor o Construction line

6 IT Meetings held with IT regarding the requirements for the depot

Mobile solutions being tested with existing field operatives

Meeting held with CLIK reviewing functionality of interim solution

Corporate infrastructure project is progressing well

7 Commercial & Contract Delivery billing & commercial administration methodology being developed

Price framework being developed

8 Materials & Plant Meetings held with procurement frameworks

Meeting held with direct suppliers such as Travis Perkins and Graftons (Build Base)

Option appraisal for sign off is being developed

9 Warehouse/Depot Cost proposal received for the mezzanine and order raised work commences on site W/C 18 November

Final layouts agreed

Reviewing PV panel options

Office fit out will be tendered W/C 2 November 2019

Target moving in date March 2020

10 Transport Option appraisal complete in draft – preferred manufacturer: Peugeot & Citroen

Meeting with finance to review costs to be confirmed

Option appraisal to be shared with Carbon Neutral Officer for comment – review carbon footprint

Page 3: ALL MEMBERS INFORMATION SHEET NO AM-2019/20-001 5 … · HPG will manage projects 1, 2 & 4 Notices served and Transfer of Undertakings (Protection of Employment) Regulations.(TUPE)

ALL MEMBERS

INFORMATION SHEET NO AM-2019/20-001 5 NOVEMBER 2019

Joe Gordon, Head of Contract Services Ext: 4190

Email: [email protected]

Brexit could impact lead-in times and delivery of vehicles

Final sign off required November 2019

11 Specialist Subcontractors Specialist subcontractor strategy complete

Procurement programme being developed

12 Voids Procurement Tender documents completed

4 voids types o Type A: Whole House Refurb – over 15 days o Type B: Major Void – up to 15 days of work o Type C: Minor Void – between 5 and 10 days of work o Type D: Quick Void – up to 5 days (lock change, compliance & clean)

1 contract – 5 years (3 + 1 + 1)

Tender published 11 October 2019 and returns due 15 November 2019

13 Planned Works Procurement Tender documents complete in draft

Scope of work o Kitchens and bathrooms o External Works (EWI/Render) o Electrical o Roofing o Landscaping / slabbing / fencing

1 contract – 5 years (3 + 1 + 1)

Tender due to be published mid-November 2019

14 Training Training matrix complete in draft – with Joe Gordon and Kev Topping as Heads of Service for sign off

15 Call Centre All current processes mapped

Meeting held with Clik reviewing interface and adaptation of current system

Further meetings to be held with Out of Office (OOH) Support Contractors

16 Compliance All on programme in line with project 5

Meetings are taking place monthly, and project control documents updated on a weekly basis to reflect progress. I have included with this briefing proposed layouts for the new depot, and would welcome any feedback or comment.