All LTA Work Instruction

Embed Size (px)

Citation preview

  • 7/24/2019 All LTA Work Instruction

    1/89

    WHAT YOU NEED TO KNOW FOREFFECTIVE PREPARATION FOR

    DEVELOPMENT WORKS

    Organised by

    Development & Building Control Division

  • 7/24/2019 All LTA Work Instruction

    2/89

    Workshop TopicsWorkshop Topics

    Preparation of Street Plan andPreparation of Street Plan and

    Street Plan LodgementStreet Plan Lodgement Pointers on Covered LinkwayPointers on Covered Linkway

    ProposalsProposals Quality Traffic SchemeQuality Traffic Scheme

    Good Tips for Designing ParkingGood Tips for Designing Parking

    Places & SpacesPlaces & Spaces

    Permit for Works on Public StreetPermit for Works on Public Street

  • 7/24/2019 All LTA Work Instruction

    3/89

    Preparation of Street PlanPreparation of Street Plan

    and Street Plan Lodgementand Street Plan Lodgement

    Organised by

    Development & Building Control Division

  • 7/24/2019 All LTA Work Instruction

    4/89

    To share on LTATo share on LTAs requirements fors requirements for

    street plan submissionstreet plan submission

    To help participants prepare qualityTo help participants prepare quality

    plan submission for quicker approvalplan submission for quicker approval

    To share on requirements & benefitsTo share on requirements & benefits

    of street plan lodgementof street plan lodgement

    Objectives

  • 7/24/2019 All LTA Work Instruction

    5/89

    Submission Stages of Street Works

    Proposals (General Overview)

    Development Control StageDevelopment Control Stage

    Street Plan StageStreet Plan Stage

    Certificate of Statutory Completion StageCertificate of Statutory Completion Stage

    Maintenance Period of 12 monthsMaintenance Period of 12 monthsIf New Street (s)

    is/are constructed

    Handing Over StageHanding Over Stage

    Street Plan StageStreet Plan Stage

  • 7/24/2019 All LTA Work Instruction

    6/89

    ee--Submission proceduresSubmission procedures

    Street Plan presentationStreet Plan presentation

    Tactile ti les (BFA)Tactile ti les (BFA)

    Utility crossingUtility crossing

    Zone of InfluenceZone of Influence

    Frequent Errors Made (FEM)Frequent Errors Made (FEM)

    LTALTAs Reference Materialss Reference Materials

    Lodgement of Street PlanLodgement of Street Plan

    Scope of Presentation for PreparationScope of Presentation for Preparation

    of Street Plan and Lodgementof Street Plan and Lodgement

  • 7/24/2019 All LTA Work Instruction

    7/89

    LTA ISSUES DC

    CLEARANCE

    PE SUBMIT STREET PLANS

    FOR BP CLEARANCE

    QP MAKES

    AMENDMENTS

    START

    DEVELOPMENT

    PROPOSAL

    COMPLY WITH

    LTA

    REQUIREMENTS?

    YES

    NO

    PE APPLY FOR

    CSC CLEARANCE

  • 7/24/2019 All LTA Work Instruction

    8/89

  • 7/24/2019 All LTA Work Instruction

    9/89

    Within 30 Days PE submits StreetPlan to LTA

    via e-Submission

  • 7/24/2019 All LTA Work Instruction

    10/89

    How do you make a Street Plan

    e-submission ?

    How do you make a Street Plan

    e-submission ?

    How do you make a Street Plan

    e-submission ?

    Form LTA-DBC_ROADS.XFD

    PROJECT-PROFILE.XFD

    SUBMISSION.XFD

    Street Plan

    Written Permission and Approved Layout Relevant documents as stated in Section IIIof the e-form LTA-DBC_ROADS.XFD

    Site Photos of development frontage, etc Structural design calculations of concretestructures

    Checklists and documents related toproposal

  • 7/24/2019 All LTA Work Instruction

    11/89

    ee--FormForm

    LTALTA--DBC_ROADS.XFDBC_ROADS.XFD

    Select Street PlanSelect Street Plan

  • 7/24/2019 All LTA Work Instruction

    12/89

    ee--FormForm

    LTALTA--DBC_ROADS.XFDBC_ROADS.XFD

    completecomplete

    declaration indeclaration in

    SECTION IIISECTION III

    comments /comments /

    clarifications related toclarifications related to

    the submissionthe submission

  • 7/24/2019 All LTA Work Instruction

    13/89

    ee--FormForm

    LTALTA--DBC_ROADS.XFDDBC_ROADS.XFD

    For resubmission ofFor resubmission ofstreet plans / prestreet plans / pre--

    consultation, enquiriesconsultation, enquiries

    and etcand etcSelect GENERALSelect GENERAL

    CORRESPONDENCECORRESPONDENCE

  • 7/24/2019 All LTA Work Instruction

    14/89

    ee--FormForm

    LTALTA--DBC_ROADS.XFDDBC_ROADS.XFD

    comments / clarifications oncomments / clarifications onthe submissionthe submission

  • 7/24/2019 All LTA Work Instruction

    15/89

    Endorsement of LTAEndorsement of LTAs Generals General

    Requirements (for DC & BP)Requirements (for DC & BP)

    Endorsements are not consistent

    Need not be endorsed on plan

    Requirements are in the e-form

    LTA- DBC_ROADS.XFD

  • 7/24/2019 All LTA Work Instruction

    16/89

    Written Permission

  • 7/24/2019 All LTA Work Instruction

    17/89

    Street Plan will have

    Entrance

    culvert

    Site Plan including a Location Plan

    Certified topographical survey plan

    Layout of road, road reserve lines in

    accordance with the RLP

    Entrance culvert details Longitudinal Section

    Cross Section Street Lighting Plans

    Road Elements Label

    Table for the Standard Road Elements

    NOTE DESCRIPTION DRAWING NO.

    1 PEDESTRIAN GRATING ( WITH CHEQUER PLATE) LTA/RD/SD99/GRA/2

    2 TYPE K2 PC.C KERB LTA/RD/SD99/KER/1

    3 FOOTPATH RAMP (SIDE ROAD) LTA/RD/SD99/KER/9

    4 FOOTPATH RAMP (DRIVEWAY) LTA/RD/SD99/KER/10

    5 CAST-IN-SITU BOX CULVERT LTA/RD/SD99/DRA/2

    6 ALUMINIUM RUNG LTA/RD/SD99/DRA/4

    7 PRECAST U-DRAIN AND SLABBED OVER U-DRAIN LTA/RD/SD99/DRA/5

    8 PC.C DROP-INLET CHAMBER LTA/RD/SD99/DRA/7

    9 FLEXIBLE PAVEMENT (TYPE III) FOR LOCAL ACCESS LTA/RD/SD99/PAV/4

    10 SOIL AERATION LTA/RD/SD99/PNR/2&3

    REFERENCE TO STANDARD DETAILS OF ROAD ELEMENTS (LTA 2000)

  • 7/24/2019 All LTA Work Instruction

    18/89

    How would a complete Street Planlook?

  • 7/24/2019 All LTA Work Instruction

    19/89

    Complete Set of Street Plans

    LOCATION PLAN CROSS SECTIONS

    TABLE OF

    ROADELEMENTS

    SITE PLAN

    ROAD RESERVE LINE

    & BOUNDARY LINE

  • 7/24/2019 All LTA Work Instruction

    20/89

    Longitudinal Section Plan

    LONGITUDINAL SECTION

    Top of culverttop of drain slab

    Extg road edge level

  • 7/24/2019 All LTA Work Instruction

    21/89

    Cross sectionCross section

    cross fall and components to be shown in the sectionscross fall and components to be shown in the sections

    1:40 fall 1:30 fall

  • 7/24/2019 All LTA Work Instruction

    22/89

    CRD-01

    Typical Cross Section for Entrance

    Culvert

    1200 DRAIN CUM FOOTPATH

    150 700 WIDE 150

    BOX CULVERT

    SLOPE GRADIENT < 1 : 10

    E d t t t f d

  • 7/24/2019 All LTA Work Instruction

    23/89

    End treatment of covered

    drain and open drain

    Railing at the

    end of

    covered drain

    Footpath

    link

    Footpathlink

  • 7/24/2019 All LTA Work Instruction

    24/89

    End treatment of covered

    drain and open drain

    Railing at the

    end of

    covered drain

    Footpath

    link

    Footpath

    link

    D i l t h b d

  • 7/24/2019 All LTA Work Instruction

    25/89

    Drop-inlet chamber and

    scupper drain

    Drop-inlet

    chamber

    C t l ti t l

  • 7/24/2019 All LTA Work Instruction

    26/89

    Location of drop-inlet

    chamber

    Correct location to place

    drop inlet chamber

  • 7/24/2019 All LTA Work Instruction

    27/89

    DropDrop--inlet chamberinlet chamber

    Direction of Traffic

    Hinge

  • 7/24/2019 All LTA Work Instruction

    28/89

    Lamp posts and sign postLamp posts and sign post

    Lamp post

    Street sign

    Lamp post

    F t th t l l f

  • 7/24/2019 All LTA Work Instruction

    29/89

    Footpath at splay corner, clearance of

    lamp post and signs from kerb

    600 mm

    Clearance from

    edge of plate

    600 mm

  • 7/24/2019 All LTA Work Instruction

    30/89

    600mm

    600mm

    from edge of signplate above

    Close up view of clearance

  • 7/24/2019 All LTA Work Instruction

    31/89

    Tabulating the road elements

  • 7/24/2019 All LTA Work Instruction

    32/89

    How are road elements labelled?

  • 7/24/2019 All LTA Work Instruction

    33/89

    Enlarged area of Label

    Note 7-soil aerationNote 2-drop-inlet chamber

    Note 7 soil aeration

    Note 2 drop-inlet chamber

  • 7/24/2019 All LTA Work Instruction

    34/89

    Tabulation of Elements

    Drg Nos from STANDARD DETAILS OF ROAD ELEMENTS

  • 7/24/2019 All LTA Work Instruction

    35/89

    Stan

    dard

    DetailsM

    E

    N

    M

    E

    N

    T

    Improve provision for barrier freeImprove provision for barrier free

    Elderly friendly road related facilitiesElderly friendly road related facilities

    To inform crossing boundariesTo inform crossing boundaries

    for the visually impaired personfor the visually impaired person

    Footpath Ramps at Pedestrian

    Crossings

  • 7/24/2019 All LTA Work Instruction

    36/89

    Tactile Tiles on footpath rampsTactile Tiles on footpath ramps

    25mm drop25mm dropHomogeneous Tiles (robust & durable)

    as Decision Tactile Tiles

    Yellow coloured tiles provides a good contrastwith concrete footpath in low light intensity

    condition (at night)

    Main improvements to Standard Details

  • 7/24/2019 All LTA Work Instruction

    37/89

    Main improvements to Standard Details

    of Footpath Ramps at Entrance

    Driveway

    Footpath

    ramp level

    flushed

    with road

    level

    (25mm

    dropremoved)

    Install 600mm wide

    colour contrasting decision tactile tiles

    600m

    m

    600m

    m

    wid

    ewid

    e

    300mm from300mm from

    road edgeroad edge

    300mm300mm

    300mm

    300mm

  • 7/24/2019 All LTA Work Instruction

    38/89

    Photo of Footpath Ramps across driveway

    Tactile tiles

    Entrance drivewayEntrance driveway300mm

    Tactile tiles

    Entrance drivewayEntrance driveway

    300mm

  • 7/24/2019 All LTA Work Instruction

    39/89

    New Footpath Ramp Details at Side Road

    Decision tactileDecision tactile

    tilestiles

    S

    ideroad

    S

    ideroad

    1:40

  • 7/24/2019 All LTA Work Instruction

    40/89

    Photo of Footpath Ramps at Side Road

    Side roadSide road

    Tactiletiles

    Flushlevel

  • 7/24/2019 All LTA Work Instruction

    41/89

    300mm300mm

    900mm

    Tactile Tiles for Curved Footpath Ramps

    A minimum of 2 set of tactile tiles to be laidA minimum of 2 set of tactile tiles to be laid

    300mm from kerb (staggered)300mm from kerb (staggered)

  • 7/24/2019 All LTA Work Instruction

    42/89

    300mm300mm

    Tactile Tiles for Junction Ramps

    A minimum of 2 set of tactile tiles to be laidA minimum of 2 set of tactile tiles to be laid

    300mm from kerb (staggered)300mm from kerb (staggered)

  • 7/24/2019 All LTA Work Instruction

    43/89

    Structural calculations and

    details of retaining wall, entranceculvert, cross culvert etc within

    the road reserves are to besubmitted

  • 7/24/2019 All LTA Work Instruction

    44/89

    Utility Pipes Crossing

    Footpath Slab

  • 7/24/2019 All LTA Work Instruction

    45/89

    Guideline on

    Utility Services

    Crossing footpath

  • 7/24/2019 All LTA Work Instruction

    46/89

    Typical Details of

    Water Pipe Crossing

    Sectional View

    Independent r.c.

    slab for the pipe

    Road reserve line

  • 7/24/2019 All LTA Work Instruction

    47/89

    Typical Details of

    Water Pipe Crossingr.c.slab maintained

    by utility agency

    Identification

    plate

    Road reserve line

    Utili ty agency submits undertaking letter to LTA

  • 7/24/2019 All LTA Work Instruction

    48/89

    Typical Details of

    Gas Pipe Crossing

    Independent r.cslab for the pipe

    Sectional View

    Road reserve line

  • 7/24/2019 All LTA Work Instruction

    49/89

    Details for larger diameter

    gas pipes

    Utility agency submits undertaking letter to LTA

    Independent r.cslab for the pipe

    Utilityagency

    submits

    undertaking letter

    toLTA tomaintainthe

    independent slab

    Independent slab to be maintained by

  • 7/24/2019 All LTA Work Instruction

    50/89

    Details for gas

    pipes which are

    50mm and smaller

    Independent slab to be maintained by

    util ity agency

    Utility agency submits undertaking

    letter to LTA to maintain the channel

  • 7/24/2019 All LTA Work Instruction

    51/89

    Zone of Influence

  • 7/24/2019 All LTA Work Instruction

    52/89

    Where is the Zone of Influence?Where is the Zone of Influence?

    When is method statement, soilWhen is method statement, soil

    investigation & site monitoring required?investigation & site monitoring required?

    45

    road

    45

    Zone of Influence is where the line drawn 45Zone of Influence is where the line drawn 45

    fromfrom

    the lowestthe lowest point of excavationpoint of excavation

    Road

    Reserve

    Line

    RoadR

    eserve

    Line

    45

    45

    road

    Method Statement & site monitoring required whenMethod Statement & site monitoring required when

    zone of influence falls within road reservezone of influence falls within road reserve

    Not RequiredNot Requiredbut PE stil l requiredbut PE stil l required

    to monitor siteto monitor site

    RequiredRequired

    Basement 1

    Basement 2Basement 1

  • 7/24/2019 All LTA Work Instruction

    53/89

    Slope Failure / Adjacent Ground may sink or subsideSlope Failure / Adjacent Ground may sink or subside

    Danger to road users & vehicular trafficDanger to road users & vehicular traffic

    Excavation Works beside RoadExcavation Works beside Road

    If NOT suitably designed and supervised,

    N ti ff t f E ti W kN ti ff t f E ti W k

  • 7/24/2019 All LTA Work Instruction

    54/89

    Negative effects of Excavation WorksNegative effects of Excavation Works

    F t E M d (FEM)F t E M d (FEM)

  • 7/24/2019 All LTA Work Instruction

    55/89

    Frequent Errors Made (FEM)Frequent Errors Made (FEM)

    Incorrect e-form attached

    e.g. old CORRESPONDENCE.XFD instead ofthe LTA-DBC_ROADS.XFD

    Resubmission not using GeneralCorrespondence

    Written Permission not submitted

    Location Plan with insufficient road

    information

    F t E M d (FEM)F t E M d (FEM)

  • 7/24/2019 All LTA Work Instruction

    56/89

    Frequent Errors Made (FEM)Frequent Errors Made (FEM)

    Missing cadastral lots information

    Road Reserve line not indicated

    Tactile tiles together with 25mm drop

    Tactile tiles placed at the edge of footpath

    ramp

    Layout of tactile tiles not correct

    F t E M d (FEM)F t E M d (FEM)

  • 7/24/2019 All LTA Work Instruction

    57/89

    Annotations not made with reference to the

    table for standard details

    Unsuitable choice of colours used, making

    plan viewing difficult

    Submit street plan prior to DC Clearance

    Submit street plan instead of lodgement

    Frequent Errors Made (FEM)Frequent Errors Made (FEM)

    F t E M d (FEM)F t E M d (FEM)

  • 7/24/2019 All LTA Work Instruction

    58/89

    Connection of existing & proposed footpath

    not shown

    Cross fall stil l showing 1:36

    Unnecessary endorsement of the LTA

    requirements on plans

    Frequent Errors Made (FEM)Frequent Errors Made (FEM)

    Steep Entrance Approach

  • 7/24/2019 All LTA Work Instruction

    59/89

    Steep Entrance Approach

    Gradient improved

    Steep Ramp

    Incorrect Design of Footpath

  • 7/24/2019 All LTA Work Instruction

    60/89

    Incorrect Design of Footpath

    Railing erected &

    grooves on footpath

    Steep footpath

    P bli ti & G idP bli ti & G id

  • 7/24/2019 All LTA Work Instruction

    61/89

    Street Works Proposal related to

    Development Works

    Publications & GuidesPublications & Guides

    Available in the LTA &Available in the LTA &

    Corenet WebsitesCorenet Websites

    Development & Building Control

    http://www.lta.gov.sg/dbc/index_dbc_other.htmhttp://www.lta.gov.sg/dbc/index_dbc_other.htm

    http://www.corenet.gov.sg/einfo/http://www.corenet.gov.sg/einfo/

    St d d D t il f R dSt d d D t il f R d

  • 7/24/2019 All LTA Work Instruction

    62/89

    Standard Details of RoadStandard Details of Road

    ElementsElements

    Available in the Corenet Website underAvailable in the Corenet Website underCORENET eCORENET e--Information SystemInformation System

    http://www.lta.gov.sg/dbc/index_dbc_other.htmhttp://www.lta.gov.sg/dbc/index_dbc_other.htm

    http://www.corenet.gov.sg/einfo/http://www.corenet.gov.sg/einfo/

    P bli ti & G idP blications & G ides

  • 7/24/2019 All LTA Work Instruction

    63/89

    Materials & Workmanship SpecificationsMaterials & Workmanship Specifications

    for Civil & Structural Worksfor Civil & Structural Works

    Can be obtained from theCan be obtained from the

    LTA websiteLTA website

    Publications & GuidesPublications & Guides

  • 7/24/2019 All LTA Work Instruction

    64/89

    Publications and ReferenceGuides in the Website

  • 7/24/2019 All LTA Work Instruction

    65/89

    __ _ _ __ _T

    website

    ebsite

    Click on Regulations

    Click on

    Street proposals

    Click on Development Control & Regulations

    Click on

    Street proposals

    __ _ _ __ _T

    website

    ebsite

  • 7/24/2019 All LTA Work Instruction

    66/89

  • 7/24/2019 All LTA Work Instruction

    67/89

  • 7/24/2019 All LTA Work Instruction

    68/89

  • 7/24/2019 All LTA Work Instruction

    69/89

    Civil Design Criteria

    Architectural Design Criteria

    Standard Details of Roads Elements

    Circulars

  • 7/24/2019 All LTA Work Instruction

    70/89

    Lodgement of Street PlanLodgement of Street Plan

  • 7/24/2019 All LTA Work Instruction

    71/89

    ObjectivesObjectives

    To share on theTo share on the

    Requirements of LodgementRequirements of Lodgement

    Benefits of LodgementBenefits of Lodgement

    Scope of Presentation forScope of Presentation for

  • 7/24/2019 All LTA Work Instruction

    72/89

    Scope of Presentation forScope of Presentation for

    Lodgement of Street PlanLodgement of Street Plan

    Flow Chart for Lodgement of Street PlanFlow Chart for Lodgement of Street Plan

    Types of Development that can be LodgedTypes of Development that can be Lodged

    Lodgement via CorenetLodgement via Corenet

    Advantages of LodgementAdvantages of Lodgement

    What you cannot LodgeWhat you cannot Lodge

    Flow Chart for Lodgement of Street PlanFlow Chart for Lodgement of Street Plan

  • 7/24/2019 All LTA Work Instruction

    73/89

    Flow Chart for Lodgement of Street PlanFlow Chart for Lodgement of Street Plan

    QP (Civil) preparesQP (Civil ) prepares

    the street plans forthe street plans for

    BP ClearanceBP Clearance

    QP (Civil) lodges the street plans with LTAQP (Civi l) lodges the street plans with LTA

    LTA issue an auto generated acknowledgement letterLTA issue an auto generated acknowledgement letter

    Development Control (DC) ApprovalDevelopment Control (DC) Approval

    On completion of works,On completion of works,

    PE request for CSC clearance (inspection by LTA)PE request for CSC clearance (inspection by LTA)

    LTA grant CSC Clearance.LTA grant CSC Clearance.

    Can be Lodged ?Can be Lodged ?

    Yes

    No

    Types of Developments thatTypes of Developments that

  • 7/24/2019 All LTA Work Instruction

    74/89

    Can be LodgedCan be Lodged

    (not affected by road reserve lines)(not affected by road reserve lines)::

    ResidentialResidential (all types(all types)) IndustrialIndustrial

    Educational InstitutionsEducational Institutions

    Places of WorshipPlaces of Worship

    Health and Medical Care EstablishmentsHealth and Medical Care Establishments

    Sports and Recreation CenterSports and Recreation Centerss Civic and Community InstitutionsCivic and Community Institutions

    Conservation BuildingConservation Building

    R id ti l ( ll t )R id ti l ( ll t )

  • 7/24/2019 All LTA Work Instruction

    75/89

    Residential (all types)Residential (all types)

    Detached Semi- Detached

    Condominium Residential Apartment

    Industrial (Factory Warehouse)Industrial (Factory Warehouse)

  • 7/24/2019 All LTA Work Instruction

    76/89

    Industrial (Factory, Warehouse)Industrial (Factory, Warehouse)

    Educational InstitutionsEducational Institutions

  • 7/24/2019 All LTA Work Instruction

    77/89

    Primary Schools

    Secondary Schools

    ITE, Polytechnic,University

    Places of WorshipPlaces of Worship

  • 7/24/2019 All LTA Work Instruction

    78/89

    Places of WorshipPlaces of Worship

    TempleTemple

    ChurchMosque

    Ci i & C it I tit tiCivic & Community Institution

  • 7/24/2019 All LTA Work Instruction

    79/89

    Community Club

    Civic & Community InstitutionCivic & Community Institution

    Police Headquarters

  • 7/24/2019 All LTA Work Instruction

    80/89

    Conservation Building

    Lodgement via CorenetLodgement via Corenet

  • 7/24/2019 All LTA Work Instruction

    81/89

    Lodgement via CorenetLodgement via Corenet

    AttachmentsAttachments required for Lodgement of Streetrequired for Lodgement of Street

    Plan via Corenet :Plan via Corenet :

    Street PlanStreet Plan

    Development Control (DC) ClearanceDevelopment Control (DC) Clearance

    Written Permission (WP) from URAWritten Permission (WP) from URA

    ee--FormForm

  • 7/24/2019 All LTA Work Instruction

    82/89

    LTALTA--DBC_ROADS.XFDDBC_ROADS.XFD

    LodgementLodgement

    Select LodgementSelect Lodgement

  • 7/24/2019 All LTA Work Instruction

    83/89

    PE must completePE must complete

    the declarationthe declaration

  • 7/24/2019 All LTA Work Instruction

    84/89

    Advantages of LodgementAdvantages of Lodgement

  • 7/24/2019 All LTA Work Instruction

    85/89

    Advantages of LodgementAdvantages of Lodgement

    Faster clearanceFaster clearance

    (Immediate reply generated from system)(Immediate reply generated from system)

    Expedite the process of the entireExpedite the process of the entire

    developmentdevelopment

    No resubmissionNo resubmission

    What you cannot LodgeWhat you cannot Lodge

  • 7/24/2019 All LTA Work Instruction

    86/89

    What you cannot LodgeWhat you cannot Lodge

    Plans involvingPlans involving

    Traffic PlanTraffic Plan

    New Street under S18 of SWANew Street under S18 of SWA

    Development with road widening plotsDevelopment with road widening plots

    Provision or modification of road relatedProvision or modification of road relatedfacil ities (facilities (egeg. covered linkways, b. covered linkways, bus stop)us stop)

    Entrance approach steeper than 1:10Entrance approach steeper than 1:10

    NonNon--standard design of entrance culvertstandard design of entrance culvert

    Completed Lodged CasesCompleted Lodged Cases

  • 7/24/2019 All LTA Work Instruction

    87/89

    8m wide entrance access

    New slab-overdrain / footpath

    Connection to existing

    footpath

    Type B aluminium

    alloy railings

    Completed Lodged CasesCompleted Lodged Cases

    Random ChecksRandom Checks

  • 7/24/2019 All LTA Work Instruction

    88/89

    Random ChecksRandom Checks

    LTA would carry out random checks on theLTA would carry out random checks on the

    lodge Street Planslodge Street Plans

    If details of Street Works do not comply withIf details of Street Works do not comply with

    LTALTAs guidelines, a written direction to thes guidelines, a written direction to the

    QP (Civil) will be issuedQP (Civil) will be issued

    Any deviation discovered during CSCAny deviation discovered during CSCinspection, the PE will have to demolish theinspection, the PE will have to demolish the

    completed works and reconstruct the Streetcompleted works and reconstruct the Street

    WorksWorks

  • 7/24/2019 All LTA Work Instruction

    89/89