Upload
truongminh
View
217
Download
1
Embed Size (px)
Citation preview
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
EMALAHLENI MUNICIPALIY
BID NUMBER ELM/2/6/2017T
PARK DEVELOPMENT IN INDWE
C.3 SCOPE OF WORKS
All definitions, interpretations and general provisions for the General Conditions of Contract for Construction Work (2010) (2nd editions are applicable.
C3.1 Description of the WorksC3.2 EngineeringC3.3 ProcurementC3.4 ConstructionC3.5 ManagementC3.6 Health and SafetyC3.7 Projection Specifications
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
C3.1DESCRIPTION OF THE WORKS
TOPIC ASPECT COMMENTARY
DESCRIPTION OF THE WORKS
Employer’s objectives-
To develop Park for the Indwe Community
Overview of the works-
Park Development of Indwe
Location of the works - Park Development In Indwe
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
C3.2ENGINEERING
ENGINEERING
Design services and activity matrix
-
Works designed by: Emalahleni MunicipalityConcept, feasibility and overall process: Emalahleni MunicipalityBasic engineering and detail layouts to tender stage: Emalahleni MunicipalityTemporary works: Contractor
Drawings
- Drawings provided by the Engineer :T1135/101 Locality PlanT1135/11 Layout Plan 1T1135/12 Layout Plan 2T1135/13 Layout Plan 3T1135/14 Pipe Bedding DetailsT1135/15 Headwall DetailsT1135/16 Contract Sign BoardT1135/17 Kerb Inlet DetailsT1135/18 Concrete Chute DetailsT1135/19 Concrete Channel DetailT1135/20 Typical Cross Sections 1T1135/21 Typical Cross Sections 2
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
C 3.3PROCUREMENT
PROCUREMENTThe Tenderers notice is drawn to the fact that the awarding of this tender will be in terms of the Supply Chain Management Policy of the Emalahleni Municipality and the Standard Conditions of tender as contained in Annexure F of the 28th May 2010 edition of the CIDB Standard for Uniformity in Construction Procurement
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
C3.4CONSTRUCTION
CONSTRUCTIONWorks specifications
Applicable Sections of COLTO
Series 1000 : GeneralSeries 2000 : DrainageSeries 3000: Earthworks and Pavement Layers of Gravel or Crushed Stone.Series 5000 : Ancillary RoadworksSeries 7000 : Concrete Pavements
Particular / generic specifications Refer to PROJECT SPECIFICATIONS
Existing services Known services There is no information regarding known services
Damage to services Contractor to be responsible for damage to services
Site establishment
Services and facilities provided by the employer
None-
Facilities provided by the contractor See PROJECT SPECIFICATIONS
Storage and laboratory facilities See PROJECT SPECIFICATIONS.
Other facilities and services See PROJECT SPECIFICATIONS
Notice boards See PROJECT SPECIFICATIONSWater for construction purposes
-The Contractor must make all arrangements for the procurement, transportation and storage of water required for consumption and construction.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
C3.5MANAGEMENT
MANAGEMENTParticular / generic specifications
See PROJECT SPECIFICATIONS
Planning and programming
Contractor to provide a programme in bar chart form which will remain as the Contract Programme but will also be updated as and when necessary or when instructed by the Engineer
Methods and procedures
Methods and procedures
The Contractor will ensure that the Project Steering Committee is kept fully informed as to where and when work will commence in different areas and what the particular work consists of.All labour is to be recruited from the local communities through the Project Steering Committee and, if required by the communities, rotated in order to share the work throughout the area.
Quality plans and control
Refer to the relevant standards for testing requirements etc.
EnvironmentCare must also be taken to avoid at all costs any contamination of any kind of existing water courses or dams
Testing, completion, commissioning and correction of defects
All testing in accordance with the requirements of the applicable standards must be carried out and approved in the presence of the Engineer before being accepted.Certificates of Practical Completion, Completion, and Final Completion will be issued in accordance with Clause 51 of the General Conditions of Contract and all other conditions detailed in the same Clause will then apply
Recording of weather A rain gauge must be set up and the rainfall recorded on a daily basis
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
Format of communications
A visitors Book must be placed on site which all visitors must be requested to sign.All Site Instructions will be issued in writing in a Site Instruction Book kept on siteAll requests for inspections by the Engineer must be made in writing at least 24 hours prior to being required
Management meetings Site Meetings will be held on a monthly basis at which the Contractor’s representative, representatives of the Project Steering Committee, representatives of the Employer and the Engineer, or his representative will attend.At this meeting the Contractor will be expected to table a marked up programme detailing progress and in the case of falling behind programme reasons why. The Contractor will also be expected to table any items of work which he feels need explanation or further detail.
Daily records All forms included in the Contract Document must be completed at the frequency indicated
Bonds and guarantees A Guarantee will be required as detailed in the Contract Data and Clause 7 of the General Conditions
Payment CertificatesMeasurements for Payment Certificates will be made jointly by the Engineer’s and the Contractor’s representatives.All claims for materials on site must be accompanied by a copy of the tax invoice for that particular item.
Permits Not applicable
Health and Safety
Health and safety requirements and procedures
The tenderers are to submit a provisional Health and Safety Plan with their Tender.
Measures against disease and epidemics
Not applicable
Aids awareness The Contractor will be issued with a HIV/AIDS Specification in the Tender Document
ANNEXES
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
C3.6HEALTH AND SAFETY
FOREWORD: *Complies with Occupational Health and Safety Act No. 85 of 1993 and Construction Regulations of July, 2003.*use as a management tool in order to comply with OH & S Act*Act takes preference over this document*Act must be used as the minimum requirement*contact originator of this document if unclear of anything.
1. TABLE OF CONTENTS *INTRODUCTION*BACKGROUND TO H & S SPECIFICATION*PURPOSE OF H & S SPECIFICATION*IMPLEMENTATION OF H & S SPECIFICATION
2. HEALTH AND SAFETY SPECIFICATION *SCOPE*INTERPRETATION
-Application-Definitions
*MINIMUM ADMINISTRATIVE REQUIREMENTS-Notification of intention to commence construction-P.C’s assignment of 16(2) responsible person-Competence of 16(2)-COID Act-Occupational h & s policy-H & S Organogram-Preliminary Hazard identification and Risk Assessment-H & S Representatives-H & S Committees-H & S Training
-Induction-AwarenessCompetence
-General Record Keeping-H & S Audits, Monitoring and Reporting-Emergency ProceduresFirst Aid boxes and equipment-Accident and incident reporting and investigating-Hazards and potentially hazardous situations- P.P.E.-OH & S Signage-Contractors and sub-contractors-Public and site visitor h & s-Penalties
*PHYSICAL REQUIREMENTS-Existing structures-Edge protection-Stacking of materials-Hazardous chemical substances
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
-Asbestos and asbestos work*PLANT AND MACHINERY
-Construction plant-Fire extinguishers and fire fighting equipment-Hired plant and machinery-Scaffolding / working in elevated positions-Roof work-Formwork and support work-Ladders and ladder work-Electrical installations and portable electrical tools
*OCCUPATIONAL HEALTH-Occupational hygiene-Welfare facilities-Alcohol and other drugs
3.*PRINCIPAL CONTRACTOR COMPLIANCE DATES4.*ASSIGNMENT OF RESPONSIBLE PEOPLE
-Appointment forms5.*GENERAL COMPLIANCE REQUIREMENTS
-Progress meetings6.*PRELIMINARY Hazard identification and Risk Assessment7.*ACKNOWLEDGEMENT OF RECEIPT OF H & S SPECIFICATION
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
COMPANY:
HEALTH AND SAFETY SPECIFICATION
1. INTRODUCTION AND BACKGROUND
The Construction Regulations No. R1010 of 18 th July, 2003, requires the Client to prepare a pre-construction health and safety specification, with all existing risks identified.
PURPOSE OF HEALTH AND SAFETY SPECIFICATION
To assist in achieving compliances with the Occupational Health and Safety Act No. 85 of 1993 and the Construction Regulations of July, 2003, in order to, as far as is practicable, reduce or eliminate incidents or injuries.The Principal Contractor shall use this specification as a basis for the drafting of his and any Contractor’s construction health and safety plans.The Specification sets out the requirements to be followed by all Contractors so that the health and safety of all persons who may be affected by the construction may receive the same priority as other project facets.
IMPLEMENTATION
The health and safety specification forms an integral part of the contract, and the Principal Contractor is required to use it when drawing up his health and safety plan. He must forward a copy to all Contractors at their bidding stage to enable them to prepare their own health and safety plans.
2. HEALTH AND SAFETY SPECIFICATION.
2.1 SCOPEThis specification covers the requirements for eliminating and mitigating incidents and injuries at Company/Site/Project level. The scope addresses legal compliance, hazard identification and risk assessment, risk control, and promoting a health and safety culture on the project. The specification also provides for the protection of those persons other than employees.
2.2 INTERPRETATION.ApplicationThis specification is a compliance document drawn up in terms of the Occupational Health and Safety Act No.85 of 1993, and the Construction Regulations of July, 2003, and is therefore binding.
DefinitionsThe definitions as listed in the Occupational Health and Safety Act and Construction Regulations shall apply.
2.3 MINIMUM ADMINISTRATIVE REQUIREMENTS.
2.3.1 Notification of intention to commence construction work.The Principal Contractor shall notify the Provincial Director of Labour in writing before construction work commences, a copy of which shall be kept in the health and safety file.
2.3.2 Assignment of Principal Contractor’s/Contractor’s responsible person to supervise health and safety on site.The appointments shall be made in writing, a copy of which is to be kept in the health and safety file.
2.3.3 Competence of the responsible person/s.The criteria as stipulated under the definition of “competent” in the Construction Regulations shall apply.2.3.4 Compensation for Occupational Injuries and Diseases Act 130 of 1993.The Principal Contractor shall keep a copy of the letter of good standing with his Compensation Assuror in the health and safety file as proof of registration. Each contractor shall provide a copy of his letter of good standing to the Principal Contractor for the health and safety file.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
2.3.5 Occupational health and safety policy.The Principal Contractor and each Contractor shall submit a health and safety policy signed by its Chief Executive Officer, outlining the Employers objectives and how they will be implemented.
2.3.6 Health and safety organogram.The Principal Contractor and each Contractor shall prepare an organogram detailing each site management health and safety appointment of the competent person.
2.3.7 Preliminary Hazard Identification and Risk Assessment. (HIRA)The Principal Contractor shall cause a hazard identification to be performed by a competent person before the commencement of construction work. The assessed risks shall form part of the construction phase health and safety plan submitted for approval by the Client. The assessment must include:a) a list of hazards and potential hazards;b) a documented risk assessment based on the list of hazards;c) a set of safe work procedures (method statements) to eliminate, reduce or control the risks;d) a monitoring and review procedure as the risks change.
The Principal Contractor shall ensure that all Contractors inform, instruct and train their workers regarding any hazards, risks and related safe work procedures before any work commences and thereafter at regular intervals as conditions change. Contractors are to conduct their own toolbox talks weekly, and submit proof of these talks to the Principal Contractor. Contractors are to conduct risk assessments specific to their operations and submit a copy to the Principal Contractor.
2.3.8 Health and safety representatives.The Principal Contractor and Contractors shall appoint in writing and provide training for health and safety representatives who shall carry out inspections of the workplace, keep records and report all findings to the responsible person, and at health and safety meetings. A representative is required once 20 employees are on site, and one representative for every 50 employees thereafter.
2.3.9 Health and safety committees.The Principal Contractor shall ensure that committee meetings are held monthly and minutes are kept. The responsible person shall chair the meetings and all representatives are to attend. Contractors shall hold their own meetings, with a copy being forwarded to the Principal Contractor’s responsible person.
2.3.10 Health and safety traininga) Induction. The Principal Contractor shall ensure that all site personnel undergo site-specific health and safety induction training before they start work. A record of attendance shall be kept in the health and safety file.b) Awareness. The Principal Contractor shall ensure that on-site toolbox talks take place at least once per week, dealing with risks relevant to the work at hand. Contractors shall provide proof to the Principal Contractor.
2.3.11 General record keeping. The Principal Contractor shall keep and maintain health and safety records to demonstrate compliance with this Specification, with the OH & S Act, and with the Construction Regulations. He shall ensure that all records of incidents/accidents, emergency procedures, training, inspections, audits, etc, are kept in the health and safety file. He shall ensure that all contractors maintain such a file.
2.3.12 Health and safety audits, monitoring and reporting.The Client shall conduct monthly health and safety audits of the work place as well as an audit of the administration of health and safety. The Principal Contractor shall conduct similar audits monthly of any contractor, who will in turn audit any sub-contractor.
2.3.13 Emergency procedures.The Principal Contractor must prepare a detailed emergency procedure for approval by the Client prior to commencement on site. The procedure shall detail the response plan, including:
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
a) list of key competent personnel;b) details of emergency services;c) actions to be taken in the event of an emergency;d) information on any hazardous material/situation.Emergency procedures shall include: fire; chemical spill; injury; damage; hazardous substances; bomb threat; major incident/accident. The Principal Contractor shall advise the Client in writing of any such event, including action taken. A contact list of all service providers (fire dept. ambulance, police, doctor, hospital) shall be available to site personnel.
2.3.14 First aid boxes and first aid equipment.The Principal Contractor shall appoint a certified first aider in writing. A copy of the certificate shall be placed in the health and safety file. An adequately stocked first aid box must be provided by the Principal Contractor, as well as a first aid station. A contractor with 5 or more employees must provide his own first aid box. Where there are 10 or more employees, a certified first aider must be appointed and be on site at all times.
2.3.15 Accident/incident reporting and investigation.The Principal Contractor must investigate all injuries and report to the Client.The P.C. may categorize incidents as follows: incidents; first aid; medical; disabling; fatal. He will detail the procedure to follow for each such event.
2.3.16 Hazards and potentially hazardous situations.The Principal Contractor shall immediately notify any contractors and the Client in writing of any hazardous or potentially hazardous situation that may arise during the performance of construction activities.
2.3.17 Personal Protective Equipment.The Principal Contractor shall ensure that all site employees wear the P.P.E. as identified in the risk assessment. He is to ensure that an adequate supply of P.P.E. is available on request as either replacement for lost items or worn out items. A record is to be kept of issues to each employee. Each contractor is responsible for supplying his own staff with P.P.E.
2.3.18 Occupational health and safety signage.The Principal Contractor must provide adequate on-site signage. Examples are: no unauthorized entry; visitors report to site office; site office; hard hat area; construction vehicles; noise zone; first aid. Signs are to be posted on access routes, entrances, scaffolding, and other risk areas.
2.3.19 Contractors and sub-contractors.The Principal Contractor shall ensure that all contractors comply with this Specification, the OH & S Act, Construction Regulations and any other relevant legislation that may relate to the activities. A contractor shall ensure compliance of any sub-contractor appointed by him.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
2.3.20 Public and site visitor health and safety.The Principal Contractor shall ensure that every person working on or visiting the site, as well as the general public, shall be made aware of the dangers likely to arise from site activities, including the precautions to be taken to avoid or minimize those dangers. Appropriate health and safety notices and signs shall be posted up.Both the Client and the Principal Contractor have a duty in terms of the OH & S Act to do all that is reasonably practicable to prevent members of the public and site visitors from being affected by the construction activities.The site must be suitably hoarded at all times with a limited number of restricted access points. Adequate notices are to be displayed.Hoarding is to be inspected daily and gates locked at the end of each work day.
2.3.21 PenaltiesPenalties may be imposed on Contractors who do not comply with this health and safety Specification.
2.4 PHYSICAL REQUIREMENTS
2.4.1 Existing structures.Any existing structure must be deemed safe by means of a structural inspection and report compiled by a competent person and forwarded to the Client and the Principal Contractor.
2.4.2 Edge protection and penetrations.The Principal Contractor must ensure that all edges and openings are guarded and demarcated at all times until permanent protection is erected. The guards must be constructed of scaffold type tubing, with guardrails, painted yellow, located one meter above floor level.
2.4.3 Stacking of materials.The Principal Contractor must appoint in writing a stacking supervisor and all materials, formwork and other equipment is stacked and stored safely, on level, firm ground, out of access ways and height complying with regulations.
2.4.4 Hazardous Chemical Substances. (h.c.s)The Principal Contractor is to appoint a competent person in writing to control the storage, transport and use of any h.c.s. Material safety data sheets (msds) are to be maintained and available on site. First aiders are to be informed of the presence of h.c.s. and how to treat incidents.
2.4.5 Asbestos and asbestos work.The removal and maintenance of asbestos containing products must be conducted under controlled conditions as specified in the Asbestos Regulations.A set of safe work procedures must be drawn up by the Principal Contractor and submitted to the Client for approval.
2.4.6 Demolition work.A competent person is to be appointed in writing to supervise and control all demolition work on site.A method statement on the procedure to be followed in demolishing the structure is to be developed by a competent person prior to the work being carried out.The Construction Regulations section 12 conditions shall apply.
2.5 PLANT AND MACHINERY
2.5.1 Construction plant.This includes all types of plant used in the construction process, and must comply with the OH & S Act and the Construction Regulations.The Principal Contractor shall appoint a competent person in writing to inspect and record the findings of such inspections.Only authorized competent persons are to operate such machinery. Appropriate p.p.e. and clothing must be provided, used and maintained.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
2.5.2 Fire extinguishers and firefighting equipment.The Principal Contractor and Contractors shall provide adequate, serviced and maintained firefighting equipment, located at suitable locations on site. Appropriate notices and signs must be posted up.
2.5.3 Hired plant and machinery.The Principal Contractor shall ensure that the hired plant and machinery is safe for use and complies with 2.5.1 above.
2.5.4 Scaffolding/working in elevated positions.The Principal Contractor must submit a risk-specific fall protection plan to the Client for approval before any work commences. All scaffolding must comply with SANS 10085 standards.Scaffolding must be declared safe for use by a competent person who has been appointed in writing, with the register being updated weekly, after inclement weather, after alterations, after an accident, and before dismantling.Adequate protection must be provided over a walkway, pavement or public access.The fall protection plan must include a risk assessment and safe work procedures. All persons working at height must be evaluated for physical and psychological fitness. Training must be provided. All openings and edges must be adequately guarded. Workers must be trained in the use of fall harnesses, which must be kept in a good condition.All scaffolding must be complete with guard rails and toe boards and be fully boarded.
2.5.5 Roof work.All roof work must be conducted in accordance with Construction Regulation 8, with a fall protection plan in place.
2.5.6 Formwork and support work.The Principal Contractor shall appoint a competent person in writing to inspect the formwork and support work immediately before, during and after the placement of concrete and thereafter on a daily basis until the removal thereof.Notices and signs are to be posted. Walkways, passages and pavements are to be protected from falling objects.
2.5.7 Ladders and ladder work.The Principal Contractor shall appoint a competent person in writing to inspect all ladders monthly and record such findings in a register. Ladders are to extend one meter above a landing and must be secured at the top and have a secure, non-slip base.
2.5.8 Electrical installations and portable electric tools.The Client must ensure that the Principal Contractor is aware of the position of all electrical power lines. The P.C. must comply with the electrical installation regulations, electrical machinery regulations and the construction regulations. The P.C. shall carry a copy of the Certificate of Compliance. Temporary electrical installations must be inspected weekly. Portable electrical tools are to be visually inspected daily with a register updated monthly.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
2.6 OCCUPATIONAL HEALTH.
2.6.1 Occupational hygiene.Exposure to occupational health hazards in construction is common and Contractors must ensure that proper health and hygiene measures are in place to prevent exposure to such hazards. Prevent inhalation, ingestion, absorption and noise induced hearing loss.
2.6.2 Welfare facilities.The Principal Contractor must supply sufficient toilets (1 per 30 workers), changing facilities, hand wash facilities, soap, toilet paper and hand drying material. There must be safe, clean storage areas for workers to store personal belongings and clean, sheltered eating areas.
2.6.3 Alcohol and other drugs.No alcohol or other drugs will be allowed on site. No one under the influence of alcohol or drugs will be allowed on site. Any person suffering from any illness/condition which may affect his safety on site must report to his supervisor.Disciplinary action is to be taken against anyone found under the influence whilst on site.
3. PRINCIPAL CONTRACTOR COMPLIANCE DATES
Requirement Submission date
a) Health and safety plan Before commencement on site. b) Notification of intention to Before commencement on
Commence construction site. c) Assignment of responsible Before commencement on Persons to supervise site. Construction work.d) Competence of responsible Together with H & S Plan Personse) Occupational health and safety policy Together with H&S Planf) Health and safety organogram Together with H&S Plang) Initial hazard identification Together with H&S Plan And risk assessment
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
4. ASSIGNMENT OF PRINCIPAL CONTRACTOR’S RESPONSIBLE PERSONS
1. Appointment Reference
2. CEO Assignee OH&S Act sect. 16(2)
3. Construction work supervisor CR 6.1
4. Subordinate supervisor CR6.2
5. Health & safety representatives OH&S Act sect. 17
6. Incident investigator GAR 8
7. Risk assessment co-ordinator CR7
8. Fall protection plan co-ord. CR8
9. First aiders GSR 3
10. Scaffold inspector/supervisor SANS 10085 & CR14
11. Scaffold erector GSR13D
12. Formwork/support work CR10
13. Excavation inspector CR11
14. Ladder inspector GSR13A
15. Temporary electrical installation CR22
16. Fire fighting equipment inspector CR27
17. Safety officer CR6.6
18. Demolition Supervisor CR 12(1)
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
5. GENERAL COMPLIANCE REQUIREMENTS
1. Construction health and safety plan. Monthly review.
2. Health and safety file. Open, at meetings.
3. OH&S Act regulations Monthly review.
4 Induction training. Every worker
5. Toolbox talks. Weekly
6. Health & safety reports Monthly.
7. Emergency procedures Monthly.
8. Risk assessments Monthly.
9. Safe work procedures Before start.
10. General inspections. Daily, weekly.
11. List of contractors. Update weekly.
12. Workman’s compensation. Ongoing.
13. Section 37 Mandatary Ongoing.
6. PRELIMINARY RISK ASSESSMENT
(Available from the MBA upon request)
7. ACKNOWLEDGEMENT OF RECEIPT
I, ……………………….., representing…………………………….
Principal Contractor/Contractor, have received the Health and Safety Specification in good order and shall ensure that the Principal Contractor/Contractor and its personnel comply with all obligations/requirements/specifications in respect thereof.
This document is legally binding in terms of Regulation 4(1)(a) of the Construction Regulations 2003.
Signature of Principal Contractor/Contractor………………………………DATE…………………
Signature of Client/Client’s Agent……………………………………………DATE………………….
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
C3.7PROJECT SPECIFICATIONS
CONTENTS
SCOPE
PART A GENERAL
PS1 PROJECT DESCRIPTIONPS2 CONSTRUCTION PROGRAMMEPS3 SITE FACILITIESPS4 WATER, POWER SUPPLY AND OTHER SERVICESPS5 FEATURES REQUIRING SPECIAL ATTENTIONPS6 DRAWINGSPS7 HANDING OVER SITE, SETTING AND CONFIRMING THE SCOPE
OF WORKS WITH THE CONTRACTORPS8 EMPOWERMENT PRINCIPLESPS9 CLEANING CONCRETE PIPESPS10 APPLICABLE STANDARDS AND PARTICULAR SPECIFICATIONS
PART B MATTERS RELATING TO THE STANDARD SPECIFICATIONS
SECTION 1100 DEFINITIONS AND TERMSSECTION 1200 GENERAL REQUIREMENTS AND PROVISIONSSECTION 1300 CONTRACTORS ESTABLISHMENT ON SITE AND
GENERAL OBLIGATIONSSECTION 1500 ACCOMMODATION OF TRAFFICSECTION 1600 OVERHAULSECTION 1700 CLEARING AND GRUBBINGSECTION 1900 DAYWORKSSECTION 2100 DRAINSSECTION 2200 PREFABRICATED CULVERTSSECTION 3400 PAVEMENT LAYERS OF GRAVEL MATERIALSECTION 1500 PITCHING, STONEWORK AND PROTECTION AGAINST
EROSION
PART C PARTICULAR SPECIFICATIONS
SECTION 12000 ENVIRONMENTAL MANAGEMENT PLAN IMPLEMENTATION
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
SCOPE
This project specification is set out in three parts:
Part A : Covers a general description of the project, the facilities available and the requirements to be met.
Part B : Covers variations and additions to standardised COLTO specifications.
Part C : Covers particular specifications that are applicable to the Contract.
The project specifications form an integral part of the Contract documents and supplement the standard specifications.
In the event of any discrepancy with a part or parts of the standard specifications, the schedule of quantities or the drawings, the project specifications shall take precedence.
The standard specifications, which form part of this Contract, have been written to cover all phases of work normally required for road contracts, and they may therefore cover items not applicable to this particular Contract.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
PART A GENERAL
PS1 PROJECT DESCRIPTION
PS1.1 Scope
The contract consists of the upgrading gravel surfaced road including stormwater drainage pipes and structures
PS1.2 Description of Site and AccessThe Site is in the suburb of Sonwabile and Phumlani Township in IndweThe term “Site” as defined in the General Conditions of Contract 2010, will comprise the full road reserve. The “Site” will also include land not provided by the Employer where equipment and/or materials for use in the permanent works of the contract can be stored and/or stockpiled with the provision that the land selected for this purpose be approved by the Engineer. The Contractor must make his own arrangements for the use of such land and must obtain written approval from the owner(s) concerned.
PS1.3 Details of the Contract
The work to be performed as part of this Contract mainly consists of the activities listed below. This list is not necessarily complete nor will it limit the extent of work to be carried out under this Contract.
GENERAL
Establishment of camp on site Accommodation of traffic
ROAD CONSTRUCTION
Clear and grubExcavate to design levels and rip and shape to form roadbedImport and process suitable gravel material to form selected sub grade layerImport and process subbase layer including stabilizationApplication of interlocking paving blocks on sand bedForm concrete lined drainsConstruction of stormwater drainage pipes and structures where necessary including kerbingCleaning existing stormwater pipes and structures
PS2 CONSTRUCTION PROGRAMMEThe time for completion of this Contract is six (3) months
PS3 SITE FACILITIES
PS3.1 Facilities for the Engineer
Site meetings will be held in the Contractor’s site office.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
PS3.2 Sanitary Facilities
The Contractor shall supply chemical toilets for use by his employees and temporary workers and shall be entirely responsible for maintaining such toilets in a clean and sanitary condition to the satisfaction of the Engineer and the health authorities. The number of toilets shall be based on one toilet per fifteen personnel on site and the Contractor shall make his own arrangements and pay all charges for the removal of sewage.
PS3.3 Contractor’s Camp SiteThe establishment of all labour, plant and materials on site and all arrangements in this respect is the responsibility of the Contractor.
The Contractor shall provide within his own on-site facilities, a suitably furnished office or other venue capable of comfortably accommodating a minimum of ten (10) persons at site meetings. The Engineer shall be allowed free use of such a venue for the conducting of any other meetings concerning the Contract at all reasonable times. The cost of providing the above facility will be viewed to be inclusive of the Contractor’s establishment costs.
Before the erection of his camp, office, stores, plant and accommodation units or any facilities, the Contractor shall satisfy the Engineer that he is familiar with and has taken due cognisance of any pertinent local by-laws, availability of services and statutory regulations. The Contractor’s attention is specifically drawn to the regulations pertaining to the accommodation of labourers.
PS3.4 Telephone and Communication Facilities
The Contractor shall provide and maintain a continuous means of on-site communication between his site supervision staff (i.e. the people responsible for the day to day running of the Contract) and the staff of the Engineer’s Representative.
The Engineer and his Representative will use their own cellular and office telephones for this contract. The provision and use of cellular phones for the Contractor’s personnel will be for his own cost.
PS 3.5 Accommodation for EmployeeThe Contractor shall make his own arrangements for the accommodation of his employees. The cost thereof shall be deemed to be included in the rates and amounts tendered for the various items of work.
PS 3.6 SecurityThe Contractor shall be responsible for the security of his own personnel and constructional plant on and around the site of the works and for the security of his camp, and no claims in this regard will be considered by the Employer.
PS4 WATER, POWER SUPPLY AND OTHER SERVICES
The Contractor shall make his own arrangements concerning the supply of water, electrical power and all other services for use at the site camps, as well as for all construction and maintenance purposes. No direct payment will be made for the provision of water, electrical power and other services. The cost thereof shall be deemed to be included in the rates and amounts tendered for the various items of work.
PS5 FEATURES REQUIRING SPECIAL ATTENTION
PS5.1 Public SafetyThe Contractor shall at all times ensure that his operations do not endanger any member of the public or of his own personnel.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
PS5.2 Adjoining Properties
The sites of the Works are surrounded by private properties. The Contractor shall exercise strict control over his employees to ensure that they do not trespass outside the road reserve or interfere in any way with the adjacent owners, tenants and their properties. In addition, the Contractor shall liaise with the owners regarding all matters that may affect them such as the provision of water and the like.
PS5.3 Construction and Maintenance Activities in Confined Areas
It may be necessary for the Contractor to work within confined areas. Except where provided for in the project specifications, no additional payment will be made for work done in restricted areas. The Contractor must note that measurement and payment will be in accordance with the specified cross-sections and dimensions only, irrespective of the method used for achieving these cross-sections and dimensions and that the tendered rates and amounts shall include full compensation for all special equipment and construction / maintenance methods and for all difficulties encountered when working in confined areas and narrow widths, and at or around obstructions, and that no extra payment will be made nor will any claim for additional payment be considered in such cases.
PS5.4 Accommodation of Traffic
The Works will be undertaken in a manner that will minimise the interference with public traffic, consistent with established routine road construction practices. Although inconvenience to road users will be inevitable, the Contractor must ensure that road users have continuous access on and to, a public road.
Temporary road traffic signs shall at all times be displayed at the works as specified on the drawings and in accordance with the requirements of this document, as well as the South African Road Traffic Signs Manual, in conjunction with Manual K56 “Safety at Road works in Rural Areas” and Road Note No. 13 and the Routine Road Maintenance Procedures Manual of the Department of Transport and Roads of the Eastern Cape. The Contractor may not commence constructional activities before adequate provision has been made to accommodate traffic in accordance with the above requirements.
The traffic signs shall be covered or removed when not required at night and over weekends. No diversions are generally required and the Contractor shall regulate the traffic with flagmen and take all precautions necessary to promote the safe and easy flow of traffic on or next to the roadway under repair.
The Contractor, if so instructed in writing, shall nevertheless provide a diversion at places with a high traffic safety risk. Except where otherwise specified, additional payment over and above payment under the payment items included in the Contract, will be made for the construction of the diversion and the additional measures required to control traffic as specified by the Engineer.
Should the Contractor neglect to apply the road traffic safety measures specified without due diligence, the Engineer may temporarily stop the works until the Contractor has rectified the situation.
The Contractor will be responsible for the accommodation of traffic on, and maintenance of the existing roadways used by the public as instructed by the Engineer, from the date of site handover, to the issuing of the Certificate of Completion for the works as a whole.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
No separate payment items have been scheduled for the accommodation of traffic or traffic signage and all these costs will be deemed to have been included in the relevant payment items of the appropriate works.The Contractor must ensure that a competent person, that can act as a Traffic Safety Officer, is present on site at all times to deal will all issues relating to traffic accommodation. This person will, at all times, be responsible for the construction, spacing, placement and maintenance of traffic control devices.
PS5.5 Control Testing
PS5.5.1 Process Control Testing
The Contractor is required to carry out his own control testing. The results of these control tests together with the location of the tests shall be submitted to the Engineer for approval. No payments will be made without this information, unless partial payment is allowed for special items in terms of the project specification.
PS5.5.2 Acceptance Control Testing
The Engineer may order that additional tests be carried out from time to time. A provisional sum is allowed for these additional tests. The cost of any additional tests that might fail, together with the remedial work ordered by the Engineer, will be for the account of the Contractor.
PS5.6 Existing Services The Contractor will, ensure that prior to construction all the necessary Record Drawings and Way-leaves for all services have been obtained and verified on site by the relevant Service Providers in his presence. The Contractor must request in writing the relevant Official to indicate the said services within 48 hours prior to commencement of work, after which the responsibility rests with the Service Department if the services are not indicated to the Contractor as requested.The Contractor shall take whatever extra precautions are required to protect all existing services from damage during the period of the Contract. Any damage to existing services indicated by the relevant service providers or other damage as a result thereof, shall be for the Contractor’s account.
PS5.7 Environmental Management
The Contractor shall be responsible for implementing and managing an Environmental Management Plan in terms of the particular specifications for the borrow pits. The Contractor's authorised agent shall report to the Engineer regarding compliance with the conditions as stipulated in the Environmental Management Plan.
The Contractor shall take the utmost care to minimise the impact of his establishment and other construction activities on the environment.
Trees and shrubs established in the landscaped areas of the road reserve may under no circumstances be disturbed without specific instruction from the Engineer for their removal. Trees and shrubs inadvertently destroyed by the Contractor shall be replaced with the equivalent at the Contractor’s expense.
No separate payment items will be scheduled for the compliance by the Contractor with the EMP. These costs will be deemed to be inclusive of the rates tendered for the works.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
PS5.8 Use of borrow pits
The Contractor is to obtain all gravel wearing course material from the existing or new borrow pits in the vicinity of the project, as instructed by the Engineer. The Contractor is to adhere to the specific requirements contained in the EMP pertaining to work methods in borrow pits.
PS5.9 Construction Regulations, 2003The Contractor shall be required to comply with the Occupational Health and Safety Act, 1993: Construction Regulations, 2003 (the regulations) as promulgated in Government Gazette No 25207 and Regulation Gazette No 7721 of 18 July 2003. Non-compliance with these regulations, in any way whatsoever, will be adequate reason for suspending the Works.
The proposed type of work, materials to be used and potential hazards likely to be encountered on this Contract are detailed in the Project Specifications, the Schedule of Quantities, the Drawings, and in the Employers' health and safety specification (regulation 4(1) of the Construction Regulations 2003), which is bound into the Contract document.
The Contractor shall, in terms of regulation 5(1), provide a comprehensive Health and Safety Plan detailing his proposed compliance with the regulations, for approval by the Employer.
The Contractor shall at all times be responsible for full compliance with the approved plan as well as with the Construction Regulations and no extension of time will be considered for delays due to non-compliance with the abovementioned plan or regulations.
Payment items are included in the Schedule of Quantities to cover the Contractor's cost for compliance with the OHS Act and the abovementioned Regulations.
PS6 DRAWINGS
The reduced drawings that form part of the tender documents shall be used for tender purposes only.The Contractor will be supplied with 3 sets of unreduced paper prints of each drawing free of charge. Any additional prints will be for the account of the Contractor.Only figured dimensions shall be used and drawings shall not be scaled unless so instructed by the Engineer. The Engineer shall supply all figured dimensions omitted from the drawings.Any information in the possession of the Contractor that the Engineer requires in order to complete his as-built drawings, shall be supplied to the Engineer before a Certificate of Completion will be issued.
PS7 HANDING OVER SITE, SETTING OUT AND CONFIRMING THE SCOPE OF WORKS WITH THE CONTRACTORThe entire road reserve within the Local Municipal Area (and indicating any “soft boundaries” if applicable) will be handed over to the Contractor at the commencement of the Contract. The following matters are to be confirmed at the time of handing over and before the commencement of any work :
(i) Confirming position of the site camp and\or any additional temporary site camps that may be required.
. (ii) Supervisory, test control measures and procedures are to be confirmed.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
PS8 EMPOWERMENT PRINCIPLES
PS8.1 Labour Intensive Construction Methods
Labour intensive construction methods) will be utilised where practically possible and feasible. Construction activities that are undertaken using labour intensive methods shall be based on the prevailing statutory minimum wage as determined by the Department of Labour.
PS8.2 Communication with Local Communities
A Project Steering Committee will be formed by the Contractor through the appropriate Local Ward Councillors or existing official structures if required, to act as the communication channel between the Contractor and the residents. This Project Steering Committee will identify a Community Liaison Officer to be appointed by the Contractor. A provisional sum is allowed in the schedule of quantities to cover the cost of the Community Liaison Officer.
The Contractor shall use the Community Liaison Officer as indicated in Section B1231 of Part B, and the Project Steering Committee to timeously reach mutually acceptable employment agreements with the affected communities and to deal with any labour-related issues.
The Contractor must include in his rates for the cost of attending an average of one Project Steering Committee meeting each month. The meetings will not necessarily be during normal working hours and it is accepted that the Contractor tendering for the works is familiar with dealing with communities and understands the implications of keeping the community informed. Minutes of such meetings must be recorded and distributed by the Contractor and the cost is deemed to be included in the rates.
PS8.3 Local LabourShould personnel and labour be required, the Contractor must endeavour to employ labourers, artisans and subcontractors from the community within the Local Municipal Area for the execution and completion of the work.
The Contractor and his sub-contractors shall ensure that they enter into a Contract of Employment with each employee engaged on the labour intensive aspects of this Contract.
PS9 CLEANING CONCRETE PIPESIt is considered likely that existing concrete drainage pipes will be partially or even totally blocked. These must be cleaned by whatever method the Contractor deems fit without damaging the pipes and the rates submitted for the same must be fully inclusive of all plant and materials required.
PS10 APPLICABLE STANDARDISED AND PARTICULAR SPECIFICATIONSThe Standard Specifications for Road and Bridge Works for State Road Authorities (1998 Edition) as prepared by the Committee of Land Transport Officials (COLTO) are applicable to this Contract. It shall however be noted that reference is made in certain of the specifications to other standardised specifications which may or may not be included in this document. Where such specifications are not included, they shall however be deemed to be included in the Contract documents.
The Contractor shall have available for reference on site at all times a full set of the above specifications, together with any other to which they refer. These specifications shall remain the property of the Contractor but shall be made available to the Engineer whenever required throughout the duration of the Contract.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
PART B MATTERS RELATING TO THE STANDARD SPECIFICATIONS
The Standard Specifications for Road and Bridge Works for State Road Authorities 1998, prepared by the Committee of Land Transport Officials, (COLTO), as amended, shall apply to this Contract. The amendments are those issued by COLTO and reproduced below, together with additional amendments as set out herein.
The Routine Road Maintenance and Re-gravelling, as well as the Road Betterment Procedures Manuals, as issued by the Department of Transport and Roads of the Eastern Cape will be referred to as a guideline, for the repair / construction and maintenance activities to be conducted under this Contract.
STANDARD AMENDMENTS TO THE STANDARD SPECIFICATIONS ISSUED BY COLTO
No amendments have been issued.
PROJECT SPECIFICATIONS REFERRING TO THE STANDARD SPECIFICATIONS AND ADDITIONAL SPECIFICATIONS
In certain clauses the standard specifications allow a choice to be specified in the project specifications between alternative materials or methods of construction and for additional requirements to be specified to suit a particular contract. Details of such alternatives or additional requirements applicable to this Contract are contained in this part of the project specifications. It also contains some additional specifications required for this particular Contract.
The number of each clause and each payment item in this part of the project specifications consists of the prefix B followed by a number corresponding to the number of the relevant clause or payment item in the standard specifications. The number of a new clause or a new payment item which does not form part of a clause or a payment item in the standard specifications and which is included here, is also prefixed by B followed by a new number. The new numbers follow on the last clause or item number used in the relevant section of the standard specifications.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
SECTION 1100 : DEFINITIONS AND TERMS
Add the following additional clauses:
“B1156 ACCEPTANCE CONTROLAcceptance control means whatever testing the Engineer carries out over and above the process control testing already carried out in order to decide on the acceptability of any work submitted by the Contractor. Such testing will be carried out at the cost of the Employer in a laboratory approved by him.
B1157 COMMERCIAL SOURCE
An offsite source of materials chosen by the Contractor will also be viewed as a commercial source. The Contractor shall take full responsibility for the quality of all materials and services supplied from commercial sources.
B1158 PROCESS CONTROL
Process control means all testing required to be carried out by the Contractor on the works in order to ensure that the completed permanent works comply with the specifications and drawings. All such testing will be subject to inspection and approval by the Engineer.”
SECTION 1200 : GENERAL REQUIREMENTS AND PROVISIONS
B1204 PROGRAMME OF WORK
Insert the following before the first paragraph:
"A bar chart programme shall be provided showing the various activities in such detail as may be required by the Engineer. The programme shall be updated monthly in accordance with the progress made by the Contractor.
Failure to comply with these requirements will entitle the Engineer to apply a programme based on his own assumptions for the purpose of evaluating claims for extension of time for completion of the works, or for additional compensation."
B1207 NOTICES, SIGNS AND ADVERTISEMENTS
Replace the second paragraph with the following:
“Two (2) contract name boards shall be erected and maintained for the duration of the Contract at points to be indicated by the Engineer. Details of the contract name board are provided in the tender documents
Delete the final paragraph and replace with the following:
“All signboards erected in accordance with the drawings or as approved by the Engineer, shall be removed at the same time as the Contractor’s dis-establishment. Payment under sub-item 13.01 for the final instalment of 15% of the tendered lump sum shall not be made unless all the advertisements, notices and temporary signs have been removed.”
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
B1209 PAYMENT
(b) Rates to be inclusive
In the 3rd line, after the word "quantities", insert "together with the payment of VAT as a separate item,"
Add the following subclause:
"(g) Trade names
Where materials are specified under trade names, tenders must be based on those specified materials. Alternative materials may be submitted as alternative tenders and the Engineer may, after receipt of tenders, approve the use of equivalent materials.”
B1210 CERTIFICATE OF PRACTICAL COMPLETION OF THE WORKS
Add the following paragraph:
“In addition to the listed specified items of work and regardless of the degree of beneficial occupation by the Employer, no sections of the works, individually or collectively, shall be considered for practical completion unless the following criteria have also been met:
In the case of partial completion, the estimated cost to complete the outstanding work shall be less than 2 % of the estimated cost to construct the whole section or sections.
In the case of the whole works, the estimated cost to complete the outstanding work shall be less than 2 % of the tendered value of work plus the cost of any variation or extra work orders, but excluding CPA and VAT.
It must be possible for the Contractor to complete the written list of outstanding items of work within 28 days of the list having been issued to the Contractor.”
B1214 CONTRACTOR'S ACTIVITIES IN RESPECT OF PROPERTY OUTSIDE THE ROAD RESERVE AND OF SERVICES MOVED, DAMAGED OR ALTERED
Add the following to the first paragraph of subclause (d)(ii)
"This is also required with respect to fences, gates, camp sites, bypasses and material spoiled on private property.”
Add the following after subclause (e)
"These written statements, as required in Clause 1214(b)-(e) shall be handed to the Engineer before the final certificate will be issued.”
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
1215 EXTENSION OF TIME RESULTING FROM ABNORMAL RAINFALL
Delete the clause and replace with the following:
“During the execution of the Works, The Engineer’s Representative will certify a day lost due to abnormal rainfall and adverse weather conditions only if less than 30% of the work force and plant on site could work during that specific working day.”
B1229 SABS CEMENT SPECIFICATIONS
Add the following to this subclause:
“Where reference is made in this specification or the standard specifications to the cement specifications, e.g. SABS 471: Portland cement and rapid hardening Portland cement, it shall be replaced with the new specification:
SABS ENV 197-1 "Cement composition, specifications and conformity criteria Part 1: Common cements.”
Furthermore, where reference is made in this specification or the standard specification to a different cement type, the following names will apply and the Engineer will confirm the relevant new name from the table below:
CementGrade
CementType
Approximate old product name
Holcim New Blue Circle
New NPC
New PPC
New Slag-
cement
52,5 CEM 1 Rapid hardening
Rapid Hard Duracast Eagle Super
- -
42,5 R CEM 1 Rapid hardening
- - - Rapo -
42,5CEM 1 OPC * Portland
CementDuratech - OPC -
CEM 1 LASRC - - - LASRC -CEM II A-S PC 15SL - - Eagle
Plus- -
CEM II B-S RH30SL - - Eagle Plus
- -
32,5R - - - - - - -
32,5
CEM II A-V PC 15FA All Purpose Cement
- - Surebuild -
CEM II A-W PC 15FA - - - Surebuild -CEM II A-L - All purpose
cement- - Surebuild -
CEM II B-V or W
PC25FA/PFA C**
- Structrete - Surecrete
-
CEM III A PBFC - BFC Eagle Pro
- PBFC
CEM IIIA RHSL - - - - RHSL
22,5MC 22.5X PFAC *** Multi purpose
cementDurabuild - - -
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
MC22.5X PFAC*** - Buildcrete - - -
12,5MC 12,5 Walcrete Mortar Cement Wallcrete - Masonry -
MC 12,5 Mortacem - - - - -
Notes: * OPC cements previously performed approximately as CEM 1 32,5R products** PC25FA cements under the old standards achieved lower compressive strengths
than the OPC's of the time*** Some PFAC cements meet the new standard for MC 22,5X. Others required
modification before meeting the requirements for MC 22,5X”
Add the following new clauses:
“B1230 DAILY RECORDS
The Contractor shall furnish the Engineer daily with records of work executed by him for each activity. The records shall include information such as description, location, measurement, plant and labour hours, where applicable, and all other information the Engineer may require for the record and measurement purposes.
No separate payment items will be scheduled for the administrative costs incurred by the Contractor to provide the Engineer with the activity sheets and other information that will be required. These costs will be deemed to be inclusive of the rates tendered for the works.
B1231 COMMUNITY LIAISON OFFICER (CLO)
The Community Liaison Officer (CLO) is to be selected by the Project Steering Committee (PSC) and the Employer (through his agent) and appointed by the Contractor. The Contractor shall, however, accept the appointment as part of his management personnel. The duties of the CLO will be:
To be available on site daily during normal working hours and at other times as the need arises. His normal working day and his period of employment will be mutually agreed upon by the Employer and the Engineer accordingly.
To determine, in consultation with the Contractor, the needs of the local labour for relevant training if so required.
To communicate daily with the Contractor and the Engineer to determine the labour requirements with regard to numbers and skill, to identify possible labour disputes and to assist in their resolution.
To attend all meetings in which the community and/or labour is present or is required to be represented. In particular, he will attend the first part of the monthly/site meeting to report on the local community involvement.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
To inform local labour of their conditions of temporary employment and to inform local labourers as early as possible when their period of employment will be terminated.
To attend disciplinary proceedings to ensure that hearings are fair and reasonable.
To keep a daily written record of his interviews and project liaison conducted.
All such other duties as agreed upon between all parties concerned.
A payment item has been allowed for in the Schedule of Quantities for the payment of the CLO.
B1232 COMMUNITY PARTICIPATION
In order to give effect to the need for the participation and transparency in the process of delivering services, the community should participate in the decision making process throughout the duration of the project. This shall be achieved through structured engagement between those responsible for the delivery of the project and the community.
A Project Steering Committee (PSC) which will be a voluntary organization shall be formed from representatives of the Employer, the Engineer, the Contractor, interested and affected parties and the Community / Ward Councillors. The PSC shall meet at least once every month until such time as the PSC or Employer are of the opinion that it could fulfil its tasks by meeting less frequently.
The PSC shall make decisions and recommendations by consensus. If consensus cannot be reached, the decision of the Employer will be final.
The tasks of the PSC will be to:
To identify problems and opportunities that result from the location, construction and operation of the roads.
Keep the community informed of all decisions taken and revisions relating to the Construction Programme.
Keep the community informed with regards to progress being made on a monthly basis. To assist with community liaison and resolution of disputes. To devise fair and transparent procedures that will assist the Contractor in the engagement of
labour. To advise on and monitor labourers’ performance.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
B1233 MEASUREMENT AND PAYMENT FOR CERTAIN GENERAL ITEMS
Payment will be made under this section for certain temporary work items as follows:
Item Unit
B12.01 Community Liaison Officer
(a) Community Liaison Officer cost provisional sum(b) Monthly transport allowance for CLO provisional sum(c) Remuneration of PSC members to attend official meetings provisional sum(d) Handling costs and charges for Contractor for items (a) (b) and (c) percentage (%)
A provisional sum is provided for the cost of community liaison, which will include the salary of the Community Liaison Officer for the duration of the Contract. The Community Liaison Officer may possibly not be required on a full time basis.
Provisional sums are also allowed for the monthly transport allowance for the CLO, as well as for the payment of PSC members for attending official meetings as scheduled by the Engineer. All the above provisional sums will only be expended as instructed by the Engineer and approved by the Employer.
The percentage tendered for handling costs and charges shall cover all additional costs for the Contractor over and above the sums paid under sub items (a), (b) and (c).”
SECTION 1300 : CONTRACTOR'S ESTABLISHMENT ON SITE AND GENERAL OBLIGATIONS
B1303 PAYMENT
B13.01 The contractor’s general obligations
Add the following to subclause (i):
“The Contractor must make allowances for the provision and erection of two(2no.) contract name boards, as per the drawings, in his rate tendered for payment item 13.01(a), Contractor’s General Obligations.
Under this payment item he shall also make allowance for the provision of two labourers to assist the Resident Engineer as and when required for checking and measuring the various items of work.
Add the following after the fourth paragraph:
"Should the combined total tendered for subitems (a), (b), and (c) exceed Error! Not a valid link. of the tender sum (excluding CPA, contingencies and VAT), the tenderer shall state his reasons in writing for tendering in this manner."
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
Add the following at the end of the pay item:
"The amount payable to the Contractor for time related costs arising from extensions of time granted by the Employer, where the Contractor is fairly entitled to such compensation in terms of Clause 45 of the General Conditions of Contract, shall be calculated as follows:
(i) Account shall be taken of all time-related items scheduled in Section 1300, 1400 and 1500.(ii) All pay items for which the unit of measurement is "month" shall be deemed to be based
upon an average of 22 working days per month.(iii) Payment will be made only for items for which the unit of measurement is "month".”
SECTION 1500: ACCOMMODATION OF TRAFFIC
B1502 GENERAL REQUIREMENTS
(f) Approval of temporary deviations
Add the following:
"If, after any temporary deviation has been constructed, any changes are considered necessary or desirable, the proposal shall be submitted to the Engineer for his approval."
(i) Traffic Safety Officer
Add the following subsubclauses:
(ix) “Ensure that all obstructions, soil and gravel heaps, related to the Contractor’s activities be removed before nightfall, where applicable or instructed by the Engineer, and that the roads are safe for night traffic.
Add the following subclauses:
(j) Extension of time for completion
Accommodation of public traffic on the works or any delays caused thereby, as well as any suspensions due to failure by the Contractor to comply with the provisions for the accommodation of traffic, will not be regarded as special circumstances for the extension of time.
B1517 MEASUREMENT AND PAYMENT
Delete the contents of this clause and replace with the following:
“Accommodation of traffic will not be paid for separately and any costs associated with it, unless expressly stated and allowed for, must be included in the rates of the various items where accommodation of traffic is required.”
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
SECTION 1600 : OVERHAUL
B1602 DEFINITIONS
(d) Free-haul distance
Delete “and cut to spoil” in the last sentence.
SECTION 1700 : CLEARING AND GRUBBING
B1704 MEASUREMENT AND PAYMENT
Item Unit
B17.01 Clearing and grubbing hectare (ha)
Add the following:
“Clearing and grubbing for the construction of camp sites shall not be measured separately. Payment shall be regarded as included in the rates tendered for the applicable items for the abovementioned work”.
B17.05 Cleaning out of hydraulic structures
Delete the last sentence of the last paragraph.
SECTION 1900 : DAYWORKS
B1901 SCOPE
This section covers the listing of day work items in accordance with the General Conditions of Contract (Clause 40) for determining payment for work which cannot be quantified in specific units in the schedule of quantities, or work ordered by the Engineer during the construction period which was not foreseen at tender stage and for which no applicable rate exists in the schedule of quantities.
B1902 ORDERING OF DAYWORK
No day works shall be undertaken unless written authorisation has been obtained from the Engineer.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
B1903 MEASUREMENT AND PAYMENT
Item Unit
B19.01 Personnel
(a) Unskilled labour hour (hr)(b) Semi-skilled labour hour (hr)(c) Skilled labour hour (hr)(d) Ganger hour (hr)(e) Flagmen hour (hr)
Item Unit
B19.02 Plant
(a) Tipper Trucks - More than 5 ton hour (h)(b) Loader (0,5m3) bucket hour (h)(c) TLB ( digger loader ) hour (h)(d) Excavator. (20-30 ton) hour (h)(e) Grader (AT 140 G or similar) hour (h)(f) Compactor (Bomag 90) hour (h)(g) Water truck (5000 litre) hour (h)(h) Compressor (air) including hoses and tools (specify) hour (h)(i) Mobile concrete mixers (specify size) hour (h)
Item Unit
B19.03 Materials
(a) Procurement of materials provisional sum(b) Contractor’s handling costs, profit and all other charges in respect of
Item B19.03 (a) percentage (%)
The unit of measurement for items B19.01 and B19.02 shall be the hour for the item of plant or personnel. Non-working hours for transport breakdown, lack of operator or any other reason shall not be measured. The time shall be taken from the time that the personnel and/or plant depart until return.
Measurement shall only be for work instructed and directed by the Engineer, where the Engineer considers no other appropriate rate is available in the schedule of quantities. Prior to the commencement of any work by the labourers described under item B19.01, the Contractor must obtain written consent from the Engineer regarding the classification of all labourers in terms of “unskilled”, “semi-skilled” and “skilled” labourers.
The tendered rates for labour for item B19.01 shall include full compensation to cover overhead charges and profit, leave pay, bonuses, subsistence, allowances, employer’s contributions, additional payment for overtime, where applicable, insurances, housing, site supervision, use of small hand tools and appliances, non-mechanical plant and equipment and consumable stores, for all administrative, supervisory, operative and contingent costs, relating to the supply of personnel.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
The tendered rates for plant for item B19.02 shall be an all-inclusive hire charge for the use of the vehicle and driver or plant/equipment and operator and shall apply only to vehicles plant and equipment nominated in writing by the Engineer, for all administrative, supervisory operative and contingent cost, and profit, relating to the running of the plant.
The unit of measurement for item B19.03(a) shall be the amount actually paid for the procurement of materials to be purchased and shall be made in accordance with the provision of the general conditions of Contract. Only the actual quantities of materials used, as verified by the Engineer, shall be paid for.
The percentage tendered for item B19.03(b) shall be percentage of the amounts actually paid for the procurement of materials as ordered under item B19.03(a) and shall be in full and final compensation in respect of the Contractor's handling costs, profit and all other charges in connection with the procurement and supply of the materials to the point of usage.
The abovementioned tendered rates shall be full compensation for the various items as specified and no further profit shall be paid.”
SECTION 2100 : DRAINS
B2107 MEASUREMENT AND PAYMENT
Item Unit
B21.01 Excavation for open drains cubic metre (m3)
Add the following to the penultimate paragraph:
“The tendered rate shall also include full compensation for trimming the open drains. Only those drains designated by the Engineer for excavation will be measured. Where road bed preparation is specified (section 3400), payment for the formation of side and mitre drains up to the road reserve will be included in the blading or road bed preparation rate. However, where new drains are to be constructed to extend beyond the road reserve limits, payment will be made under this item for the length of drain outside the road reserve.”
Item Unit
B21.02 Clearing and shaping existing open drains cubic metre (m3)
Add the following to the penultimate paragraph:
“The tendered rate shall also include full compensation for trimming the open drains. Only those drains designated by the Engineer for clearing and shaping will be measured.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
SECTION 2200 : PREFABRICATED CULVERTS
B2201 SCOPE
Amend the first paragraph to read:
“This section covers all the activities in connection with the construction of prefabricated units of culverts, together with inlet and outlet structures, manholes and other appurtenant structures.”
B2203 MATERIALS
(b) Portal and rectangular prefabricated concrete culvert units
Add the following:
“Should a pipe unit be specified as half of the standard length, the actual length of the unit will be measured for payment as it is accepted that only certain lengths are available from the manufacturers. The tendered rate for concrete pipe culverts shall also include any additional costs with respect to units that are half the standard length. The standard length of a concrete pipe will be taken as 2,44m or 2,5m depending on supplier. All pipe joints are to be wrapped with U24 Bidem or similar approved material. The cost of the wrapping of the joints will be deemed to be inclusive in the installation rate of the pipe.”
(d) Fine granular material
Add the following:
“Selected material, approved by the Engineer, may be used for the bedding.”
B2212 INLET AND OUTLET STRUCTURES, CATCHPITS AND MANHOLES
(a) Excavation and backfilling
Amend the first paragraph to read as follows :
“The width of excavation shall be the net external dimensions of structure plus 0,5 meter working space along or around the structure. The specifications given elsewhere in this section for backfilling the culverts shall apply mutatis mutandis to inlet and outlet structures, catch pits and manholes. If wet soil Crete is used with vibrators the extra working space can be reduced to 150 mm.”
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
B2212 INLET AND OUTLET STRUCTURES, CATCHPITS AND MANHOLES
Add the following subclause:
“(j) Stone masonry inlet and outlet structures
Where specified by the Engineer, the Contractor shall construct stone masonry headwalls and wing walls at culvert inlets and outlets. Stone masonry work shall be carried out in accordance with the provisions of Series 5000 of these Specifications.
Stone masonry will only be specified, where appropriate, for structures up to 600mm in height or diameter. Reinforced concrete will be specified for larger structures.”
Add the following clause:
B2219 CONSTRUCTION TOLERANCESThe installation of prefabricated pipes, portal and rectangular culverts and ducts shall comply with the requirements stated below:
(a) Level
The permissible deviation from the specified level shall be 20 mm.
(a) Alignment and grade
The permissible deviation of the alignment and grade of each culvert and pipeline shall be 20 mm from the specified line and level, or from the line between culvert or pipe inverts at successive manholes or catch pits, as applicable, when measured over any 7m length, and all such deviations shall be gradual. Reverse falls are unacceptable.”
SECTION 3400 : PAVEMENT LAYERS OF GRAVEL MATERIAL
B3407 MEASUREMENT AND PAYMENT
Item 34.01: Change the second paragraph of the payment description (COLTO page 3400-7) to:
The tendered rates shall include full compensation for procuring from the contractor’s own sources with unlimited overhaul, breaking down, placing and compacting the material, and the protection and maintenance of the layer and the conducting of control tests, all as specified.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
SECTION 5100 PITCHING, STONEWORK AND PROTECTION AGAINST EROSION
B5101 SCOPE
Amend the first the first paragraph to read:
“This section covers the furnishing of materials and the construction of a protective covering in stone pitching, cast in situ concrete pitching, bricks or prefabricated concrete blocks on exposed surfaces such as earth slopes, drains and stream beds, as well as heavier protective layers in the form of riprap and the construction of stone masonry for walls, as well as shown on the drawings or as ordered by the Engineer.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
PART C:PARTICULAR SPECIFICATIONS
Add the following new section (12000):
SECTION 12000 ENVIRONMENTAL MANAGEMENT PLAN IMPLEMENTATION
CONTENTS
B12001 SCOPEB12002 INTERPRETATIONSB12003 OBJECTIVES OF THE ENVIRONMENTAL MANAGEMENT PLANB12004 RESPONSIBILITIES OF THE CONTRACTORB12005 RESPONSIBILITIES OF THE ENVIRONMENTAL CONTROLLERB12006 METHOD STATEMENTSB12007 EXTERNAL AUDITING AND EVALUATIONB12008 ENVIRONMENTAL MANAGEMENT DURING DECOMMISSIONINGB12009 MEASUREMENT AND PAYMENTB12010 MITIGATORY MEASURES REQUIRED BY THE DEPARTMENT OF ECONOMIC AFFAIRS,
ENVIRONMENT AND TOURISM
B12001 SCOPE
This specification covers the requirements for the effective implementation of an Environmental Management Plan. The purpose of the Environmental Management Plan is to translate environmental policy into practise by putting in place workable systems, structures and tools to achieve integrated and consistent environmental management of all environmental initiatives.
B12002 INTERPRETATIONS
B12002.1 Supporting Documents
Where this specification is required for a project, the following documents shall inter-alia be read in conjunction with this specification:
(a) Statutory requirements of the Environment Conservation Act (Act No 73 of 1989) - ECA(b) Statutory requirements of the National Environmental Management Act (Act No 107 of 1998)
– NEMA(c) Statutory requirements of the Mineral and Petroleum Resources Development Act
(MPRDA), Act 28 of 2002.
Note 1 : In the Eastern Cape Province, the ECA and NEMA fall under the authority of the Department of Economic Affairs, Environment and Tourism (DEAT), whilst the MPRDA falls under the authority of the Department of Minerals and Energy (DME).
Note 2 : Environmental Management Plans (EMP’s) relating to road maintenance programmes need to be authorised by the DME in accordance with the requirements of the MPRDA.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
B12002.2 Applications
The provision of this specification shall apply in respect of all Contractors, Subcontractors or any of their site personnel, workforce or suppliers, who are engaged in the execution of the works.
B12003 OBJECTIVES OF THE ENVIRONMENTAL MANAGEMENT PLAN
The Environmental Management Plan, which is in accordance with Environmental Policy of the Province of the Eastern Cape, Department of Roads & Transport is intended primarily as a management tool for the Department, the Consulting Engineers, the Contractor and his Subcontractors.
The Environmental Management plan outlines structures and procedures to be implemented by the Contractor and his Subcontractors to minimise and manage potential negative environmental impacts which the Contractor's construction activities might have on the receiving environment.
B12004 RESPONSIBILITIES OF THE CONTRACTOR
The Engineer shall on commencement of the Project appoint an Environmental Control Officer (ECO) who, in addition to his normal duties, shall have direct responsibility for the implementation and monitoring of the Environmental Management Plan.
The ECO shall liaise with the Engineer and the Contractor, in order to ensure effective implementation of the Environmental Management Plan. The co-operation of the Contractor will be crucial and the ECO shall delegate responsibility for the Environmental Management Plan, through the Engineer to the Contractor.
The Contractor shall be required to submit a detailed Method Statement, outlining how is construction activities will comply with the prescribed procedures of the Environmental Management Plan, to the Environmental Controller for approval.
Specific responsibilities of the Contractor include:
(i) Identifying procedures applicable to the activities he controls.(ii) Compiling Method Statements to meet the procedures and targets.(iii) Submitting Method Statements to the Environmental Controller for approval.(iv) Devising a system for monitoring compliance with Method Statements and procedures.(v) Identifying environmental training needs and implementing the environmental awareness
training program commissioned by the Environmental Controller.(vi) Implementing corrective and preventative actions recommended by the Environmental
Controller.(vii) Review of Environmental Management Plan implementation and effectiveness at weekly site
meetings (with the Environmental Controller).(viii) Ensuring weekly audits of the Environmental Management Plan.
Should the Engineer be of the opinion that the Environmental Management Plan and the conditions of the Method Statement are not being adhered to and the appropriate corrective action is not being implemented, the Engineer, advised by the Environmental Controller, shall be at liberty to instruct to the Contractor to cease the related operations until the Contractor complies with the relevant requirements. The Contractor shall not be entitled to any extension of time for such stoppages
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
B12005 RESPONSIBILITIES OF THE ENVIRONMENTAL CONTROLLER
The Environmental Controller will be responsible for the practical implementation and monitoring of the Environmental Management Plan and he shall report directly to the Engineer in this regard. The Environmental Controller shall on a daily basis inspect and monitor operations on and off site and shall take the necessary action where required to ensure compliance with the requirements of the Environmental Management Plan. The Environmental Controller shall attend all regular site Works meetings for reporting, discussing and reviewing the performance of the Environmental Management Plan (which shall be a standard item on the agenda) and, in addition, shall meet with the Contractor on a weekly basis for the same purpose.
B12006 METHOD STATEMENTS
The Contractor shall be required to submit Method Statements to the Environmental Controller outlining proposed construction activities, phasing and procedures and methods to comply with the targets stipulated in the Environmental Management Plan. Method Statements shall, where applicable, include Site Establishment Drawings with sufficient detail to assess the potential impact of the site facilities or to assess the degree of safeguarding provided against pollution.
Method Statements shall indicate how the procedures will be applied in order to meet the relevant targets and are central to the proper implementation of the environmental Management Plan. It is anticipated that in addition to assessing the systems and performance of the Environmental Management Plan, the external audit will scrutinise the formulation of, and adherence to “Method Statements” in some detail.
Method Statements must be submitted at least 10 days prior to the proposed commencement of related activities and must be approved by the Environmental Controller, in consultation with the Engineer. The Environmental Controller shall keep copies of these Method Statements and letters of approval (including conditions attached) in a Method Statement file.
Any deviations from the approved Method Statements must be submitted to the Environmental Controller for approval and any amendments submitted to the Engineer.
B12007 EXTERNAL AUDITING AND EVALUATION
In order to ensure that the Environmental Management Plan is effectively implemented, it is important that regular external audits of the Environmental Management Plan are conducted. The Engineer shall arrange that these external audits do take place and that a system for addressing any problems identified during these audits, is formulated. The relevant documentation shall be kept and shall be available to the public.
B12008 ENVIRONMENTAL MANAGEMENT DURING DECOMMISSIONING
Environmental Management associated with the decommissioning of this project will ensure that the following items are addressed at closure and during the defects liability period:
(a) All cleared sites are rehabilitated with indigenous grass material(b) All visible alien plants are removed from disturbed sites.(c) All recyclable rubble and waste, for example, scrap metal, bottles, cans and plastics are
collected and disposed of through a registered recycling company.(d) All non-recyclable rubble and solid waste be collected and disposed of at a registered waste
disposal facility.(e) Rehabilitate all borrow pits on completion.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
B12009 MEASUREMENT AND PAYMENT
The Contractor shall not be separately reimbursed or compensated in respect of his compliance with the provisions of this Section B12000 of the Project Specifications. All costs so incurred shall, save and except to the extent provided for in the Schedule of Quantities under SECTION B1300: CONTRACTOR'S ESTABLISHMENT ON SITE AND GENERAL OBLIGATIONS, be deemed to be included in the rates tendered for the various items of work listed in the Schedule of Quantities.The financial guarantee for the rehabilitation of land disturbed by quarrying as per the approved EMP will be returned upon the granting of a Closure Certificate by the DME. This Closure Certificate will comply with the terms of the MPRDA.
B12010 MITIGATORY MEASURES REQUIRED BY THE DEPARTMENT OF MINERALS AND ENERGY
Mitigatory Measures
The mitigatory measures in the EMP are to manage potential environmental impacts arising due to the construction activities as well as the activities of the construction staff.
1. Responsibilities
(a) The Contractor (through the Site Engineer) will:
(i) be held responsible for the implementation of these mitigatory measures, (ii) identify the need and be responsible for the implementation of an environmental
awareness training programme for the construction staff,(iii) supply on request a "Method Statement," which will indicate the procedures to
be applied in order to meet the requirements of any aspect of these mitigatory measures,
(iv) ensure that any problems identified during environmental audits or inspections, are addressed and rectified as soon as reasonably possible.
2. Mitigatory Actions
2.1 Should it be necessary to store materials and equipment on site for short periods, only previously disturbed areas above the 20-year flood level should be used for this purpose.
2.2 Any construction camp set up should be clearly demarcated and secured against theft or vandalism and any toxic materials (cement, oil, petrol, diesel, etc) should be very strictly controlled and secured. Such a construction camp should be above the 50-year flood level and should be completely rehabilitated on completion of construction activities.
2.3 All damaged areas in the riparian zones resulting from construction operations, should be rehabilitated to prevent erosion and undermining of the riverbank.
2.4 All "surplus" soil and rock excavated during construction should be removed from the water course.
2.5 No concrete shall be mixed on the soil surface, all concrete mixers to be placed on trays, and precautions to be taken against contamination of the soil through spillage of pre-mixed concrete.
2.6 Precautions are to be taken against oil spillage from heavy equipment such as compressors and generators, eg through the use of sand or sawdust filled drip trays. All contaminated material (including soil) to be disposed of at a registered waste site.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
2.7 Adequate toilet facilities (eg chemical toilet) shall be provided for workers on site, and all ablutions are to take place in these facilities.
2.8 Scavenger-proof litter containers shall be provided on site and strict control over littering enforced.
2.9 All waste material, including excess construction material, litter and sewerage, shall be regularly removed from site and disposed of at a registered waste facility.
2.10 Strict precautions shall be taken when making open fires.
2.11 No wild animals (fish, birds, snakes, lizards, etc) shall be disturbed unnecessarily in any way.
3.) These mitigating measures are to be read in conjunction with the mitigating measures and recommendations contained in the approved EMP, including any additional recommendations contained in the Record of Decision (ROD) from the DME.
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
MONTHLY REPORT FORMS TO BE COMPLETED BY THE CONTRACTOR
Form Description
MATERIALS ON SITE
OVERALL PROJECT WORKER SCHEDULE
WEEKLY TASK WAGE REGISTER
LOCAL LABOUR AND MATERIAL SCHEDULE
NOTE: THESE FORMS ARE FOR INFORMATION ONLY DURING TENDER STAGE AND WILL ONLY NEED TO BE COMPLETED ON A MONTHLY BASIS BY THE APPOINTED CONTRACTOR ONCE THE CONTRACT IS AWARDED.
THE COMPLETION OF THESE FORMS BY THE APPOINTED CONTRACTOR IS MANDATORY AND PAYMENT CERTIFICATES WILL NOT BE PROCESSED IF THEY ARE NOT ACCOMPANIED BY THE PROPERLY COMPLETED FORMS
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
MATERIALS ON SITE – TRANSFER OF RIGHTS
ELM/5/8/2016T SURFACING OF LADY FRERE INTERNAL ROADS PHASE 1
CONTRACTOR: ……………………………………………………………………………………………………………..
CLAIM FOR PAYMENT NO: …………………………………… DATE: ………………………..
I, the undersigned, ………………………………………………………………………………………
in my capacity as …………………………………………………………………………………………………….
of …………………………………………………………………………………………………….
(hereinafter referred to as “the TRANSFEROR”) (I having been duly authorised hereto by virtue of Resolution of the Board of Directors of the Transferor passed on the . . . . . . . . . . . . . . . . .day of . . . . . . . . . 20. . . . . . . . . .) hereby warrant that the materials and goods listed are the Transferor’s bona -fide property, ownership of which vests in the Transferor, and I hereby transfer, cede and assign all the Transferor’s rights, title and interest in and to the said materials and goods unto and in favour of
………………………………………………………………………………………………………………………..
(hereinafter referred to as “the TRANSFEREE”). Insofar as the Transferor retains actual control of the materials and goods, the right of ownership thereof passes to the Transferee by constitutum possessorium.
This transfer shall become effective upon conclusion of the Transferor receiving payment from the Transferee or from any other person on behalf of the Transferee for the materials and goods as Materials on Site (payment of retention money thereon excluded).
I further confirm that I am fully responsible for all materials and goods listed under this transfer of rights and that they have been insured adequately against all risks and will remain insured until they are built into or used in the permanent works and taken over by the Employer.
TOTAL VALUE OF CLAIM FOR MATERIALS ON SITE IN ACCORDANCE WITH THE ATTACHED LIST :
………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………
……………………………………………………………………………( R ……………………………………………)
SIGNED: …………………………………………………………………………………………………………..
DATE: …………………………………………………………………………………………………………..
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE C3 Scope of Work
PART : 1
CONTRACTOR MONTHLY REPORT
Project No: …………………. Project Name: ………………………….
Contract No: ………………..
Contractor Name: ………………………………………………………………………
Claim No: …………………….. For Period Ending: ………………………………
Date of Report: ……………………………….
The Contractors Monthly Report comprises an integral part of the Contractors Payment Claim and processing of the payment claim is not permitted without this report also being submitted i.e.
“NO REPORT – NO PAYMENT”.
Attachments:Part 2 Overall Project Worker Schedule: Schedule of all local labourers employed since the start of
the project
Part 3 Weekly Task Wage Register
Part 4 Local Labour Schedule
Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE1C3 Scope of Work
19. OVERALL PROJECT WORKER SCHEDULE (local labourers only) Contract No: …………… PART 2Project No. ……………………………….. Project Name: …………………………………………………………………….Month of Report: ………………………………………………. Sheet: ………….. of ………….
Names of all Local Workers employed at any time on the project are to be entered in the table below irrespective of how long they worked on the project.No. Name of Local
LabourerIdentity Number Month
Worker Started
AgeTick if Yes
Place a tick in the box which corresponds to the Gender
andAge of the Worker
Fem
ale
Hea
d of
H
ouse
hold
with
D
epen
dant
s
Dis
able
d
Labo
urer
Sem
i-Ski
lled
Ski
lled
Sup
ervi
sor
Cle
rical
Man
ager
ial
Pro
fess
iona
l
Women Men
Over 25 yrs2A
25 yrs &
under2B
Over 25 yrs2C
25 yrs &
under2D
Totals for this sheetTotals from previous sheetTotals carried forward
(A) (B) (C) (D) (E) (F) (G) (H) (I)(J) (K) (L) (M) (N) = (J+K+L)
20.
Completed by: Name: …………………………… Signature:…………………………… Capacity …………………… Date:…..………..
THE CONTRACTELM/2/6/2017T
PARK DEVELOPMENT IN INDWE1C3 Scope of Work
21. WEEKLY TASK WAGE REGISTER (local labourers only) Contract No: ………………… PART 3
Project No. …………………….. Project Name: ……………………………. Week Ending: ……………………. Sheet:….. of ….Entries in this portion to be completed by Foreman Entries in this portion to be Completed by Contractor
No. Name of local worker
Day Tasks Worked Payment
Mon Tue Wed Thu Fri Sat Sun
Total DAY TASKS
worked this week
Rate per DAY TASK
Total Payment due
to Worker
Workers signature on receipt of
Payment
Date Payment Received by
Worker
Totals This SheetTotals Brought Forward From previous Totals Carried Forward
(A) (B)
Completed by: Name: ……………………. Signature: ………………… Capacity: ……………… Date: …………………….
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
LOCAL LABOUR AND MATERIAL SCHEDULE PART 4Contract No: ……………….. Date of Report: ……………………………….
Project No: …………………. Project Name: …………………………………
Claim No: …………………….. For Period Ending: …………………………….
Contractor Name: ……………………………...………………………………………………
1. Summary of Day Tasks worked and Amount Spent on Local Labour this monthWeek No.
Week Ending Total Day Tasks /
Person Days Worked
Total Amount Paid
(Total of (A) from Form 4
for each week)
(Total of (B) from Form 4 for each
week)1 R2 R3 R4 R5 R6 R
Total R
2. Summary of Amount Spent on Local Labour to date1. Previous Amount Spent on Local Labour (From previous claim) R2. Amount Spent on Local Labour this month (From Total above) R
3. Total Amount Spent on Local Labour to date (3)=(1+2) R
3. Local Labour Schedule Summary of Local Labour Employed No. of local
workers who worked on the project to date(From Part 2)
% of Total
Columns refer to Columns in Part 2
1. Total No. of individual local workers who have worked on the Project (Column N) 100%
10. How many of the Total No. are local youth (25 yrs and under) (Column B & D)
11. How many of the Total No. are local women (Column A + B)
4. Summary of Amount Spent on Material to Date (Cumulative)Item This Month Total to
date1. Material from Local Municipality
2. Material from Local District Municipality3. Material from Outside the Eastern Cape
4. Material from other areas within the Eastern Cape
Total Material
Total material as percentage of contractor expenditure
Total as percentage of contractor budget
5. Training of Local Workers
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
Category of training Name of course No. trained Days trained Comments on
progress
(a) Technical training
for implementation
Bricklaying
Carpentry
Plumbing
Fencing
Plastering
Painting
House Building
Handyman
Electrical
(b) Institutional
training for local
management beyond
construction
(c ) Technical training
for OMM
(d) Institutional
training for
implementation
(e) HIV/ Aids etc.
Other – Please
specify
Total
Completed by: ………………………. …..……………………… …..………………. ……………………….
Name Signature Capacity Date
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
EMALAHLENI MUNICIPALIY
ELM/2/6/2017T
PARK DEVELOPMENT IN INDWE
C.4: SITE INFORMATION
Site information will be finalised at the time of the site meeting and forwarded to all parties involved.
C4.1 Tender Drawings
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
C.4.1:LOCALITY PLAN
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
C4.2:TENDER DRAWINGS
Tender drawings are issued separately in a Book of Reduced Drawings.
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
EMALAHLENI MUNICIPALIY
ELM/2/6/2017T
PARK DEVELOPMENT IN INDWE
C5: APPENDICES
The following documents are attached hereto and form part of the Contract.
Appendix A Annex F (Normative) Standard Conditions of TenderAppendix B Emalahleni Municipality Supply Chain Management PolicyAppendix C Emalahleni Municipality Health and Safety Specification
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
APPENDIX A:ANNEX F (NORMATIVE)
STANDARD CONDITIONS OF TENDER
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
APPENDIX B:EMALAHLENI MUNICIPALITY
SUPPLY CHAIN MANAGEMENT POLICY
THE CONTRACTELM/2/6/201T
PARK DEVELOPMENT IN INDWEC3 Scope of Work
APPENDIX C:EMALAHLENI MUNICIPALITY
HEALTH AND SAFETY SPECIFICATION