Developing crew allocation system for the precast industry using genetic algorithms TeesRep - Teesside's Research Repository Item type Article Authors Al-Bazi, A. F. J. (Ammar); Dawood, N. N. (Nashwan) Citation Al-Bazi, A. F. J. and Dawood, N. N. (2010) 'Developing crew allocation system for the precast industry using genetic algorithms', Computer-Aided Civil and Infrastructure Engineering, 25 (8), pp.581-595. DOI 10.1111/j.1467-8667.2010.00666.x Publisher Wiley-Blackwell Journal Computer-Aided Civil and Infrastructure Engineering Additional Link http://doi.wiley.com/10.1111/j.1467-8667.2010.00666.x Rights Subject to restrictions, author can archive post-print (ie final draft post-refereeing). For full details see http://www.sherpa.ac.uk/romeo/ [Accessed 13/10/2010] Downloaded 8-Feb-2018 14:52:13 Link to item http://hdl.handle.net/10149/112883 TeesRep - Teesside University's Research Repository - https://tees.openrepository.com/tees

Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Embed Size (px)

Citation preview

Page 1: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Developing crew allocation system for the precast industry usinggenetic algorithms

TeesRep - Teesside'sResearch Repository

Item type Article

Authors Al-Bazi, A. F. J. (Ammar); Dawood, N. N. (Nashwan)

Citation Al-Bazi, A. F. J. and Dawood, N. N. (2010) 'Developingcrew allocation system for the precast industry usinggenetic algorithms', Computer-Aided Civil andInfrastructure Engineering, 25 (8), pp.581-595.

DOI 10.1111/j.1467-8667.2010.00666.x

Publisher Wiley-Blackwell

Journal Computer-Aided Civil and Infrastructure Engineering

Additional Link http://doi.wiley.com/10.1111/j.1467-8667.2010.00666.x

Rights Subject to restrictions, author can archive post-print (iefinal draft post-refereeing). For full details seehttp://www.sherpa.ac.uk/romeo/ [Accessed 13/10/2010]

Downloaded 8-Feb-2018 14:52:13

Link to item http://hdl.handle.net/10149/112883

TeesRep - Teesside University's Research Repository - https://tees.openrepository.com/tees

Page 2: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

TeesRep: Teesside University's Research Repository http://tees.openrepository.com/tees/

This full text version, available on TeesRep, is the post-print (final version prior to publication) of:

Al-Bazi, A. F. and Dawood, N. N. (2010) 'Developing crew allocation system for the

precast industry using genetic algorithms', Computer-Aided Civil and Infrastructure

Engineering, 25 (8), pp.581-595.

For details regarding the final published version please click on the following DOI link:

http://dx.doi.org/10.1111/j.1467-8667.2010.00666.x

When citing this source, please use the final published version as above.

This document was downloaded from http://tees.openrepository.com/tees/handle/10149/112883

Please do not use this version for citation purposes.

All items in TeesRep are protected by copyright, with all rights reserved, unless otherwise indicated.

Page 3: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Computer-Aided Civil and Infrastructure Engineering

1

Developing Crew Allocation System for the Precast

Industry Using Genetic Algorithms

Ammar Al-Bazi

Centre for Construction Innovation Research (CCIR), School of Science and

Engineering (SSE), Teesside University, UK

[email protected]

&

Nashwan Dawood

Centre for Construction Innovation Research (CCIR), School of Science and

Engineering (SSE), Teesside University, UK

[email protected]

Abstract:

The Precast Concrete Industry (PCI) is one of the major contributors to the national

economy and can be categorised as labor-intensive industry. It is currently experiencing

shortcomings in terms of delivery products at a competitive cost and time. This is mainly

due to the inefficiencies associate with planning and scheduling of skilled operators

within crews configurations. This paper presents a new strategy for efficient allocation

of crews of workers in the precast concrete industry using Genetic Algorithms-based

simulation modeling. The aim of this study is to develop crew allocation system that can

efficiently allocate possible crews of workers to precast concrete labor-intensive

repetitive processes. Genetic Algorithms (GAs) have been developed to solve this type

of problems. Process mapping methodologies were used to identify and document the

processes involved in producing precast components. Then process simulation was

Page 4: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

2

used to model and simulate all these processes and GAs were tailored to be embedded

with the simulation model for a better search of promising solutions. GAs operators were

designed to suite this type of allocation problem. “Class Interval” selection strategy was

developed to give a greater opportunity for the promising chromosomes to be chosen for

further investigation. Dynamic crossover and mutation operators were developed to add

more randomness to the search mechanism. The results showed that adopting different

combinations of crews of workers had a substantial impact on reducing the process

throughput time, minimizing resources cost, and achieving the required operatives

utilisation.

1. Introduction

„Crew allocation‟ can be defined as the process of assigning crews of workers or operatives to

processes to ensure that they are used in an optimal way. This problem becomes more challenging

when it involves a complex system that shares limited crews. Crew allocation can be a very

complex problem when same operatives are required to be involved in concurrent or

simultaneous processes. The optimal allocation of crews should satisfy minimum clashes or

overlaps between different crew‟s operatives and this should subsequently minimize production

costs and idle time.

Two difficulties can arise in solving this problem: the combinatorial explosion of alternative

crews normally leads to NP-hard optimization problems and the lack of analytical expressions

relating performance functions to solutions usually results in noisy estimates of the performances

(Shi 2000).

There is a lack of applying appropriate techniques that advise on optimal allocation of crews of

workers in the precast industry. It is crucial to plan and manage operatives allocation to ensure

the optimal choice of crews and effective utilization of each crew member have been achieved,

Zhang et. al., (2004).

Page 5: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

3

As one of sophisticated techniques that have been used in solving these kinds of problems, GAs

have been applied to many different optimization problems such as the optimization of traffic

control signals (Teklu et. al., 2007), electrical transmission towers (Mathakari et. al., 2007),

(Cheng et. al., 2009), highway alignment optimization (Kang et. al., 2009), and large

structures (Adeli and Kumar, 1995a&b; Sarma and Adeli, 2000a&b, 2001), as well as

short-term urban traffic flow forecasting (Vlahogianni et. al., 2007), pattern recognition (Lee et

al., 2007), classification of radar targets (Carro-Calvo et. al., 2009), structural control (Jiang and

Adeli,2008), machine learning (Hung and Adeli, 1994), and robotics (Smith et. al., 2007). They

are one of the most promising meta-heuristics algorithms (Alcaraz et. al., 2001). GA technique is

defined as a computational model simulating the process of genetic selection and natural

elimination in biological evolution, (Adeli and Cheng, 1994a&b; Kumar et. al., 2009). In recent

years, various approaches to construction simulation have been advanced such as object

identification and tracking (Chi et. al., 2009) and high speed animation (Rekapalli et. al., 2009).

In this work, GA is designed to be coupled with process-simulation model for further guidance of

the simulation model toward choosing the best processing crew among sets of possible

alternatives. The reason behind choosing GA is its ability to intelligently search through a

solution space for optimal or near optimal solutions. In the crew allocation problem under study,

an intelligent searching algorithm is developed to investigate a large pool of crews, to decide

which set of crews can be allocated to processes in order to minimize labor costs.

In this paper, the developed crew allocation system dubbed “SIM_Crew” was designed to

efficiently allocate crews of workers to the precast industry. In such an industry, there is a high

demand for skilled workforce and skilled operatives costs are relatively high. A “sleeper” precast

manufacturing system was considered as a test of the proposed system. A proper allocation

system will thus ensure minimum throughput time, production costs, and maximum utilization of

resources. A „sleeper‟ precast component is used as a base for rail tracks. „Sleepers‟ are precast

Page 6: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

4

components generally laid transverse to the rails, on which the rails are supported and fixed, to

transfer the loads from rails to the ballast and sub grade below, and to hold the rails to the correct

gauge.

The reminder of the paper discusses the research problem, previous theories concerning crew

planning and scheduling techniques, system architecture of the crew allocation system, process

mapping methodologies, simulation and optimization modeling and finally a real life case study

to validate the model.

2. Research Problem

Due to the fact that the parallel and sequential nature of any labor-driven system is pre-specified,

the labor shared between similar or different tasks is generally allocated according to the

workflow. However, idle times are still not carefully considered and the overall throughput time

or total costs may be longer or higher than expected. In fact, this problem becomes more apparent

when there is significant idle time for a process due to sharing operatives.

Due to the fact that the precast operations are labor-intensive and the required workforce involved

in such industry is highly skilled and costly, optimization of crew allocation in the precast

manufacturing system is needed in order to minimize idle times caused by sharing operatives.

Each production process has a certain pool of crews that can possibly perform the work for each

of the parallel activities. Each crew has a different set of workers “different crew formation” with

a certain process time. Sharing available operatives in different crews will eventually cause

delays.

„Parallel-Repetitive Similar Processes‟ is a realistic example of a resource sharing case. All

production processes in such a layout have a similar sequence, and the same materials are

processed by similar parallel repetitive processes in order to produce the same or different

Page 7: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

5

products in a short cycle time. This kind of production layout can be seen in a job-shop

environment such as seen in the precast concrete industry.

The aim of “SIM_Crew” is to achieve the best allocation of crews to carry out parallel or

sequential processes for any labor-driven facility. The optimal crew allocation will eventually

reduce the clashes between any shared resources, and subsequently lead to minimizing both

operatives costs and process idle times. The system architecture of the crew allocation system

will be described in the next section.

3. Literature Review

Crew planning and scheduling using simulation modeling and optimization technology have been

applied in construction and precast industries. The layout of the operations (parallel/series) and

repeatability of operations involved was crucial when considered in such planning and scheduling

analysis. In this context, the literature review is categorized into two groups:

Repetitive Operations

In this type of layout, crews are often required to repeat the same work in various locations of the

enterprise, moving from one location to another. Many available crew planning and scheduling

systems for repetitive operations have been discussed in the work of Nassar (2005) who

presented a model that uses a spreadsheet based GA models to optimally assign resources to

repetitive activities of construction projects. Ipsilandis (2006) presented a linear programming

parametric model for supporting construction managers decisions, exploring the multi-objective

nature of decision making in repetitive construction projects. The project consisted of six

repetitive units each having six discrete activities repeated in each unit. Lu et. al., (2008)

presented a computer system dubbed “simplified simulation-based scheduling (S3)” to solve the

problem of skilled laborer scheduling in a multi-site, multi-project context. The model consists of

an optimizer using the Particle Swarm Optimizer (PSO) as a stochastic search strategy on a

Page 8: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

6

population of individuals, each representing a possible solution to the problem. Dawood et. al.,

(2007), developed a generic simulation model depicting the operational processes of the precast

concrete production system. Results showed that the smaller the number of human resource

available, the longer will be the lead time and the production costs will be lower. The greater the

number of resources, the shorter the lead time, however, production costs will be greater.

Non-Repetitive Operations

In non-repetitive processes/ activities, crews are often required to carry out non-similar works in

various locations of the project / job-shop. Many available scheduling methods for repetitive

construction projects have been presented in the work of Moselhi et. al., (2007), who proposed a

new methodology utilizing combined GAs and spatial technologies for optimization of crew

formations for earthmoving operations. The designed model is useful for planning, tracking and

control of earthmoving operations. Watkins et. al., (2007), used agent-based modeling methods

simulating space congestion on a construction site to explore the impact of individual interactions

on productivity and labor flow. Li et. al., (1998), presented a methodology for optimizing labor

and equipment assignment for excavation and earthwork tasks using the Genetic Algorithm. A

number of modifications of the basic GAs were achieved to improve the capacity of the

algorithms. Zhang et. al., (2004), developed an optimization methodology which integrates

discrete-event simulation with an heuristic algorithm to optimize dynamic resource allocation for

construction scheduling. Senouci et. al., (2001), presented an optimization formulation for

project scheduling problems with the objective of minimizing the total construction cost. The

developed model considers project scheduling characteristics generally ignored in Adeli and

Karim (1997) including precedence relationships, multiple crew-strategies, and time-cost trade-

off, they addressed resource levelling and resource-constrained scheduling of non-repetitive

activities performed simultaneously. Marzouk et. al., (2004), provides a multi-objective

Page 9: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

7

optimization tool to optimize earthmoving operations using computer simulation and genetic

algorithms. The optimization is aimed at minimizing the time and cost of earthmoving operations.

Marzouk et. al., (2007), presented a special purpose simulation model to capture the uncertainty

associated with bridge construction and results of the model showed that increasing the number

of labor crews shortens the fabrication duration. The above literature study presented many

methodologies and tools used to solve crew allocation problems in both repetitive and non-

repetitive operations layout in construction and precast industries, most of which have focused on

minimizing costs rather than considering the effects of resources utilization on system

performance. Some studies demonstrated the simulation of repetitive processes but the detailed

crew formations of each process were not taken into account. Many systems have not used any

optimization modules for a crew allocation; only running scenarios for improvement were

adopted in such systems. In addition, available performance keys such as costs and utilization

were not calculated to show the effects on system performance. Crew planning and scheduling

systems are incapable of determining worker utilization as they can only produce crew utilization,

so there is a pressing need for advanced systems that can address the utilization issue. The

proposed system presented in this paper, more attention has been given to the worker utilization

factors as they impact labor allocation cost. The next section will describe the research problem

in more detail.

4. Architecture of Crew Allocation System

The purpose of allocating crews is to place the most suitable team of workers for each activity at

minimum allocation cost and best possible performance. Therefore, as a fundamental

requirement, crews should be allocated to new production processes once they are freed from

previous processes. In addition, the performance of alternative feasible crews should be evaluated

in terms of allocation cost and effciency, so that the most efficient one with the minimum cost

Page 10: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

8

and less interruption will be selected for implementation. To meet the above allocation process

objective, a GA based simulation model is proposed, as shown in figure 1.

Figure 1: “SIM_Crew” Architecture

As shown in figure 1, the core of “SIM_Crew” is the simulation model which is integrated with

databases through integration, and a processing module developed by writing special codes to

enable such integration. The optimization engine is designed to be embedded in the simulation

model; solutions are suggested from this engine to be evaluated by the simulation model, and all

results are then stored in the database. During one allocation iteration, the simulation executes

allocation plans: each of them has sets of crews to be allocated to the production processes, while

GA evaluates the performance of the resultant allocation, and based on this, adjusts the decision

variables and selects the most promising once. The main functionality of the optimization engine

is to propose and manipulate solutions to be tested by the simulation model for a better

performance. A number of key performance indicators such as total resource allocation cost,

crew formation utilization, and other fixed resources utilization were used to evaluate the outputs

of the model. An interface mechanism is designed to include size of population, crossover and

mutation strategies, and other entry requirements. As shown in figure 1, the allocation process is

an iterative procedure of progressive improvement.

Page 11: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

9

5. Process Mapping, Simulation and Optimization Modeling

5.1 Process Mapping

All production processes at two production sections are mapped to identify inputs, resources,

constraints affecting each process, and the resulting outputs of each production process. This type

of visual modeling is important to identify the relationships among the production process and the

logic of each process. In order to have a sound understanding of the production life cycle at each

production section, all production processes were studied and mapped. Figure 2 shows IDEF0

diagrams of one of the production lines (four production lines were considered in this study, each

of them with a similar production sequence).

Figure 2: sleeper manufacturing process mapping diagram

The process flow starts from the mold setup process where inputs of this process are defined. The

restrictions imposed on this process are mold and labor availability. The resources required to

carry out the setup process include: an air compressor, a mold, laborers. The second process is to

Page 12: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

10

place strands inside the mold so that the sleepers can be reinforced, as a third process may require

different numbers of strands depending on the type of products (sleepers). The casting process is

then applied to fill the mold with the required amount of concrete and fourthly, the curing process

uses a steaming system to cure the cased sleepers. The curing area capacity and availability of

plastic sheets are the main restrictions on the curing process. Demolding follows the cutting

process, involving cutting off the strands and then demolding sleepers with a special machine.

The finishing of the sleepers is the last process which comprises placing plastic, rubber, and clips

on each sleeper.

All inputs, outputs, constraints, and resources regarding each process are defined to give a clear

idea about the core of each process and how these processes can be related to each other so that

an accurate simulation model can be developed. The following section details the simulation

model developed in this research project.

5.2 Simulation Modeling

The ability of simulation to model physical processes on a computer, incorporating the

uncertainties that are inherent in all real systems, provides an enormous advantage for analysis in

situations that are too complex to model mathematically (Glover, et. al., 1999). As one of the

common methodologies used to simulate real life systems, Discrete Event Simulation (DES) is

used to simulate production processes of the manufacturing system being investigated, as it is a

powerful methodology used to model many real systems as they progress through time. The

primary objective of the developed simulation model is to analyze “what-if” scenarios and

thereby evaluate the allocation of each set of crews of workers to production processes for any

manufacturing system. All inputs, process, and output of the simulation model are mapped in as

introduced in the previous section and more details are explained in the next sections.

Page 13: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

11

- Inputs

Demands and orders specifications have been identified which will be produced in each

production line. Information about orders includes the type of product, quantity needed, the

amount of materials required for each order and resource needed. All production information is

stored in an Excel spreadsheet to be integrated with ARENA using the Data Access Object

“DAO”. All other labor information is stored in Access databases. The skills needed for each

crew for each process have been determined by and possible crews formation.

A crew alternative list for each process has been provided by the production manager (according

to his experience). All sets of possible crews are accommodated into the Access database for

further use. See figure 3:

Figure 3: shows the crew population pool and some crew formation

In figure 3, each crew of workers involves a set of workers that are qualified to carry out a

process. The workers were coded according to their numbers and all related information saved in

the workers‟ pool. The qualification of each worker as well as hourly costs were saved in the

workers‟ pool.

Page 14: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

12

- Process

This includes all the simulated production processes which are introduced in section 5.1.

- Outputs

After running the simulation model the outputs are stored in Excel files for further analysis. Some

of the results are stored in the Access database to check for chromosome duplication. A large

number of text files are created to validate the working of the optimization engine operators. The

parameters evaluated include total resource allocation cost, and crew formation utilization.

Assumption of the Simulation Model

A number of assumptions are used when constructing the simulation model, the purpose of these

assumptions was to simplify the development of the simulation model.

1. Each crew member is intensively involved in carrying out the production process. All

members work together to finalise the process.

2. To begin a production process, all crew members should be available and should be

released at once when that the process is complete.

3. The model is developed based on 24 hour working.

4. Only direct costs are considered in this model

5.3 Optimization Using Genetic Algorithms

The previous section has introduced the simulation model and the objective of this section is to

discuss the optimization technology used in this research and the integration with the simulation

model.

The benefit of using GA is the possibility to search for an optimum or near-optimum allocation of

a crew of workers to each production process. This type of allocation optimizes both cost and

Page 15: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

13

production, under various constraint scenarios related to the availability of workers within a crew.

Figure 4 shows how GA is used to optimize the crew allocation process:

The initial population of chromosomes, each chromosome consisting of a set of crews to be

assigned to processes generates random sets of crews using a Monte Carlo sampling technique.

The most promising chromosomes should always be kept in the top list for easier access and

further selection. For this purpose, the SQL query is set to always select the most promising

chromosomes of a population size. Each pair of chromosomes is then selected to be prepared for

further crossover and mutation purposes. An un-repeatability condition is imposed to avoid any

repetition which might occur by producing two similar chromosomes. This process continues

until the condition regarding the number of generations is satisfied. After each generation, the

population is added to the previous generation‟s population to produce an augmented population

pool. A sorting procedure is then applied on the augmented population pool.

Figure 4: Modified Genetic Algorithms Flowchart

Page 16: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

14

The output of the optimization process represents the possible „set of crews‟ that can be allocated

to each production process. The decision variables are stored in a row vector (string) called a

chromosome, which has a number of elements (genes) representing the number of variables equal

to the number of sets of crews available and possible to allocate. The chromosome was

specifically designed to resolve this type of problem as demonstrated in figure 5.

Figure 5: chromosome representation for the crew allocation problem

In figure 5, each integer number of each gene would give the crew index number of the set of

crew alternatives associated with that gene, i.e; this number would give the index of a crew that

could be used in the solution as each gene has different possible alternatives of crews. A

chromosome is encoded in a decimal way with the chromosome length is representing the

maximum number of processes involved in any labor-driven production facility.

The decision variables are the number of sets of crews available to allocate to each process. To

evaluate each chromosome, a single objective function has been identified and adopted to

minimize labor costs. Many restrictions can be determined which limit production amounts,

alternative crews, and operational hours (shifts). In some situations, a trade-off exists between

idle time and cost (El-Rayes et. al., 2001). In this study, only direct cost is considered as a

substantial cost and GAs have been used productively in a number of studies in order to optimize

costs (Kim and Adeli 2001, Sarma and Adeli 2002).

Page 17: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

15

The objective function is applied to evaluate total resource costs from information identified in

previous job-shop cost records. The equation used to calculate the objective function is:

n

i

iiii RCPUIRCBRCxf1

(1)

Where:

n is the number of labor-driven processes

iBRC : .incurred cost per hour when using a laborer for set of solution i.

iIRC : incurred cost per hour when laborer is idle for set of solution i and

iRCPU : incurred cost per use of fixed or physical resource for set of solution i;

senior skilled bonus can be considered in such cost.

As an initial starting point, a population of solutions (chromosomes) is generated randomly using

Monte-Carlo sampling. Population size and other GA operators‟ parameters influence the

solution and simulation time (Boyabatli 2007). As one of the random sampling techniques, Monte

Carlo is used to select crew alternative for each gene (i.e process). This generates a random

number for each gene which is used to select the alternative crews for each process. The range of

random numbers for each gene can be determined using the following constraint

iii MaxCARMinCA

where

iR is an integer random number for each chromosome i

iMinCA is minimum number of crews alternative in gene i and

iMaxCA is maximum number of crews alternative in gene i

In the proposed model, the user is given the possibility to input the population size. Once the

population is generated, each chromosome is evaluated individually using the developed

simulation model. GA operators are tailored to suit this type of allocation problem. Next, “Class

Interval” selection, “Dynamic Crossover” and “Mutation” Strategies are explained.

Page 18: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

16

The Proposed “Class Interval” Selection Strategy (CISS)

The promising chromosomes with least costs will be given a higher chance of selection, and are

named the “class interval” strategy, which is based on the concept used in the descriptive

statistics. (Healey, 2009)

The top of the minimum costs chromosome will be given higher weighting than others by

calculating the fitness function according to equation (2):

ii xfMaxGx (2)

where

iGx : Fitness function of chromosome i

ixf : Sorted objective function for top promising chromosomes and

Max : The largest cost value in the best promising chromosomes

Repetition of the generated chromosome is not allowed, meaning that all generated chromosomes

should be unique over the evolution process. To construct the chromosome‟s class interval, a

relative fitness function iRGx is calculated using equation 3:

m

i

i

i

i

Gx

GxRGx

1

, i=1,.. m (3)

where

iRGx : Relative fitness function of chromosome i and

:m is the population size

The cumulative relative fitness function is then calculated, as it is useful to determine the desired

class width using equation 4:

iii RGxCRGxCRGx 1 , i > 1 (4)

where

11 GxCRGx

iRGx : Relative fitness function of chromosome i and

iCRGx : Cumulative Relative fitness function of chromosome i

Page 19: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

17

Subsequently, the possible interval of occurance for each chromosome is determined from the

class intervals. The interval associated for each chromosome will represent the chance range of

that chromosome to be selected by any generated (0-1) random variate as in figure 6:

Figure 6: the proposed “class-interval” selection rule

In the proposed selection strategy and after sorting the resulting costs obtained from equation 1 in

ascending order, the chromosomes with minimum costs are selected from the augmented

population pool as the promising pair of chromosomes. The fitness function is then calculated

using equation 2, and the result is sorted in descending order for a better selection at a later stage.

The relative fitness function is calculated using equation 3 as a requirement for constructing the

chromosomes class interval. Cumulative relative frequency is then calculated using equation 4 as

the upper bound of the chromosome‟s opportunity to be selected. The lower boundary can be

identified to represent the possible range of each chromosome to be selected. This strategy is

derived from the class interval concept in descriptive statistics and has been found to be useful for

Page 20: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

18

chromosomes selection. The idea of modifying this concept is to give a greater opportunity for

the promising chromosomes to be selected again. The chromosomes with minimum cost or a

higher fitness function will be given a wider range of interval so random variants will be more

likely to lie within this range.

Dynamic Points Crossover (DPC)

The crossover operation in a conventional GA is based on the exchange of genes between two

fixed length chromosomes when string coding is applied (Zhang et. al., 2005). In the

“SIM_Crew” model, DPC is developed to achieve the best random exchange of genes between

each pair of chromosomes, as shown in figure 7:

Figure 7: the Dynamic-Points Crossover (DPC) strategy

In this type of crossover, random numbers of size (n) are generated to be associated with each

gene; a vertical crossover takes place to exchange or alternate subsequently n gene(s) of the first

chromosome with the opposite gene of the second selected chromosome after satisfying the

condition below:

Page 21: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

19

If the probability of crossing over a gene ≤ the random number associated with that gene, then the

crossing over of that gene is possible.

For example, suppose five random numbers satisfy the swapping condition at genes 2, 4, and 4,

the chosen places or genes will be exchanged between each selected pair of chromosomes.

Dynamic-Points Mutation (DPM)

This mutation operator is similar to the developed crossover operator where random numbers of

size (m) are generated to be attached to each gene. The selected genes are then specified for

further mutation. The possible crew place to carry out a particular process is then generated

randomly for each chosen gene. The mutation process continues until a unique chromosome is

satisfied to be placed into the new population for further testing is shown in figure 8.

Figure 8 the Dynamic Points Mutation (DPM) strategy

After a crossover operator has taken place, each chromosome is then mutated individually. The

same strategy of the Dynamic Crossover can be individually applied to each chromosome and the

Page 22: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

20

same exchange condition can be used to mutate genes. The selected genes can be mutated with its

pool “list of alternative crews” using the Monte-Carlo simulation.

Avoiding of Chromosome Duplication

As solutions (chromosomes) are generated randomly using the GAs operators, the possibility of

repeated solution exists. Such repetition causes additional calculations and subsequently leads to

an increase in the calculation time. In order to avoid duplication of chromosomes during

evaluation and to minimize evaluation time and calculation operations, “one search strategy” is

developed to search for any duplications and to discard any repeated chromosomes. This enables

the “SIM_Crew” engine to evaluate just non-duplicated chromosomes for a faster and better

investigation.

The “one search strategy” enables investigation of the current generation chromosome to check

whether any chromosome is repeated in the chromosome list which is stored in access database.

The non-repeated chromosomes can be stored temporarily in the chromosomes access database

under the (-1) generation number. Defining chromosomes with the (-1) generation number for the

non-duplicate chromosomes eases the discarding of them after copying them to the VBA

database. Figure 9 below shows the “one-search strategy” steps that “SIM_Crew” applies to filter

the resulted chromosomes.

Page 23: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

21

Figure 9: “one search strategy” flowchart for duplication

In this developed flowchart, “one search strategy” is developed to save computation time and

program codes. In one search strategy and after selecting a pair of chromosomes, crossover will

take place by exchanging selected genes using the probabilistic dynamic strategy. To add more

randomness to the crossed-over chromosomes, each chromosome should be mutated individually

with its available list of alternatives for each process using the Monte Carlo (MC) sampling

method. The mutated chromosome will be checked with Access database which involves all

chromosomes generated for all previous populations (population history), then, if the tested

chromosome is duplicated, the mutation process should continue until a unique chromosome is

obtained.

After finding a unique chromosome, a copy of this chromosome should be sent to access database

population list under the (-1) generation number and another copy to the VBA array which

Page 24: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

22

involves all unique chromosomes for the current generation for evaluation purpose. After testing

all chromosomes for duplication, all chromosomes having the (-1) generation number should be

discarded from the access database population history and the VBA array should be prepared to

be fed to the simulation engine for evaluation purposes.

The purpose of the temporary chromosome is to assist checking for duplicated entries while the

next generation is being created. As each chromosome is generated through the crossover

mutation operators, it is stored into the database with a generation number of (-1) a flag that eases

the deletion of non-repeated chromosomes. This means that all past, current and proposed

chromosomes are held in one location, so a single search can check if the new chromosome is a

duplicate.

The “one search strategy” ensures that all chromosomes are unique before evaluating them;

therefore, there is no point to test for repeated chromosomes as it wastes time and computational

efforts.

6. The Case Study

A case study of one of the largest „sleepers‟ products precast concrete industry in the UK was

developed. In this sleeper manufacturing system, the production process involves using a wide

range of different resources, including labor, equipment, and materials. For planning and control

purposes, precast operations are broken down into activities/tasks, so that resources can be

economically allocated and controlled.

The railway sleeper concrete manufacturing system is investigated in this study and is divided

into two main production sections; each having two labor-intensive production lines and shared

resources (labor and machines) are used to carry out job/activity on each production line

alternately. Eight processes including curing are applied to the sleeper.

Two types of multi-skilled workers were used to carry out jobs in the two production lines:

charge workers (multi-skilled workers in charge of operators) and operators (multi-skilled

Page 25: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

23

workers). Each multi-skilled worker has the skills to carry out a number of possible activities,

depending on the accumulated skills of the worker and his/her ability to work on more than one

process.

In production section 2, eleven operators and two charge workers are used to carry out tasks, and

thirteen operators and four charge hands in production section 3. On any of the production lines, a

“reusable mold” is the main resource, which consists of a gang of molds that can be used to

produce either the same or different types of sleeper. A wide range of sleepers are produced by

the production processes presented in figure 2 such as the „G44‟, „5EF28‟, „EG47‟, and „EG47

3R‟. The logic of these production processes was presented by Dawood and Al-Bazi (2009).

Resources assigned to each mold are shared resources (machines, laborers) which are applied to

produce the finished sleeper. The job-shop layout consists of three zones: materials zone,

concrete mix zone, and production zone. In the material zone, all steel wire rolls, plastic spacers,

pandrols, and other finishing accessories are stored nearby to be available when needed. A

number of mechanical resources can be stored in this area after using them.

After a detailed investigation of each process in the company, a simulation model was developed

using ARENA simulation software to simulate the production processes of the sleeper concrete

manufacturing system. All relevant data were collected by conducting onsite visits, using

flowcharts and process maps, interviews and the stop watch technique as relevant data collection

techniques. The crew alternatives for each production process were identified by the production

planner according to the accumulated experience record of a worker as shown in table 1.

Table 1: number of crew alternatives for each process

Page 26: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

24

Sec

tio

n I

D

Lin

e ID

Process ID

Number of

Crew

Alternatives

Sec

tio

n I

D

Lin

e ID

Process ID

Number of

Crew

Alternatives

Pro

du

ctio

n S

ecti

on

2

Pro

du

ctio

n L

ine

1

Setup 4

Pro

du

ctio

n S

ecti

on

3

Pro

du

ctio

n L

ine

1

Setup 3

Run Strand 4 Run Strand 3

Stress 4 Stress 3

Casting 4 Casting 3

Sawoff 3 Sawoff 3

Demolding 4 Demolding 3

Finishing 4 Finishing 3

Pro

du

ctio

n L

ine

2

Setup 4

Pro

du

ctio

n L

ine

2

Setup 3

Run Strand 4 Run Strand 3

Stress 4 Stress 3

Casting 4 Casting 3

Sawoff 3 Sawoff 3

Demolding 4 Demolding 3

Finishing 4 Finishing 3

According to the above table, the possible number of allocation plan is equal to 722,204,136

million which demonstrate the crew allocation problem being investigated to be a combinatorially

complex one. However, more detail about crew formation data and worker details are confidential

and cannot be published in this study.

Twenty-eight production processes divided between four production lines in two production

sections (seven repetitive processes at each) were considered in the 3D simulation model. The

3D simulation model can be used as a communication tool to convey the idea of how a sleeper

production system works and how it performs to avoid costly mistakes as early as possible.

(Anttila, 2005). The purpose of visualization was to verify the simulation model and to provide

production managers with more advanced means of communication. However, the 3D animation

was enough to verify the logic used in constructing the simulation model. See figure 10.

Page 27: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

25

Figure 10: depicts visualization of the sleepers manufacturing system

A set of crews specified to carry out each production process which had been suggested by the

production manager were fed into the system database. Class Interval Selection Strategy (CISS)

was used as a selection strategy, while Dynamic Points Crossover (DPC) and Dynamic Points

Mutation (DPM) were chosen as a crossover and mutation strategy. Fourty generations with a

population of size 20 was used to obtain a stable result. In order to analyze opportunites for

improvement in the sleeper precast concrete manufacturing system, an optimization study will be

conducted in the next section to identify the impact of allocation plans on system performance.

6.1 Running Experimental Work

The objective of this study was to iteratively generate and test possible crew allocation scenarios

which can be evaluated using simulation until the minimum resource allocation cost is found. The

GAs module is used to iteratively generate and evolve allocation scenarios. The simulation

module is then utilized to test the impact of each allocation scenario on the performance of the

manufacturing system in terms of resource utilization and costs.

In most cases, the algorithm converges after 25 generations which takes about 7-8 hours and

requires a memory of 512 MB. The population size is set to be 20 chromosomes. The

chromosomes size is defined to be equal to the number of processes. The probability of crossing

over a gene and mutating a gene is identified to be 0.2, 0.3 respectively (several sets of different

Page 28: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

26

probabilities have been attempted without any significant effects). The probability of mutation is

higher than crossover, as the mutation operator in this system plays a vital role in mutating

repeated chromosomes in order to obtain the unique one.

For the model settings above, a simulation run has been performed to check the functionality of

the proposed system and determine which type of development the model can add to reduced

costs.

6.2 Analysis and Interpretation

The results of the case study are shown in figures 11-15

Figure 11: costs reduction using “SIM_Crew” allocation System

Figure 11 shows that a significant drop in cost takes place after the 2nd generation with slight

cost reductions in a number of generations. The GA dynamic probabilistic operators have

successfully explored more promising solution areas on the mentioned generations. Allocation

cost tends to have no improvement after 25 generations. This best scenario drove the allocation

cost equal to £48300 in which a return of 1.5% (about £300 per five working days) is achieved.

To verify that the GA converges to the optimal solution, we applied the average results to test the

improvement and convergence of the solutions, as in figure 12.

Page 29: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

27

Average Cost for Each Generation

50000

51000

52000

53000

54000

55000

56000

57000

1 4 7 10 13 16 19 22 25 28 31 34 37 40

Generation Number

Co

sts

This figure shows improvement of the solutions over generations: generation by generation the

average solution is improved due to the evolving process available in the algorithm used. The

utilization of fixed resources and labor is optimized in order to identify the optimal utilization that

could minimize the total allocation cost. A sample of two workers from different skills

backgrounds working with a concrete mold has been selected from 47 resources to be presented

in this paper. The best chromosome of each generation is selected to present the optimized

utilization of resources of that chromosome as shown in figures 13-15:

Figure 13: mold utilization optimization using “SIM_Crew”

In figure 13, the utilization of the used concrete mold at section 3 is optimized to determine the

required level of utilization needed for the mold resource to minimize the total production costs.

Fixed resources such as the mold have shown a highly stable utilization because of their

Figure 12: reduction trend in costs using “SIM_Crew” System

Page 30: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

28

continuous use. For laborer resources, one of the operative‟s utilization profiles is shown in figure

14.

Figure 14: operative labor utilization optimization using “SIM_Crew”

In figure 14, the utilization of worker 21 who is an operative laborer working in section 3 is

optimized to determine the required level of utilization needed to minimize the total

manufacturing costs. However, operators have a higher utilization as they are involved in

carrying out most of the manual work. Skilled worker utilization is also calculated as shown in

figure 15.

Figure 15: skilled labor utilization optimization using “SIM_Crew”

In figure 15, the utilization of worker 14, a senior charge worker working in section 3 is

optimized to determine the required level of utilization to minimize the total allocation cost.

Page 31: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

29

Skilled workers are less utilized as their main duty is supervision and guidance. The resources

utilization charts presented in figures 14-15 reveal that utilization of shared the laborer fluctuates

as the objective function seeks to achieve the required resources utilization. The non-shared

resources such as molds have a stable utilization as they are used only by one set of workers at a

time.

Different levels of utilization of each selected resource are shown through many generations, so

the fluctuation of shared resource utilization is remedied by varying the utilization of other

resources to satisfy the desired objective function. The last generation will show the optimized

utilization required to achieve minimum total production costs.

The developed simulation model has not considered other factors as breakdown or mixer

problems. In addition, none of the environmental impacts such as weather have been considered

in this study. These shortcomings can be addressed in future research projects. To summarize the

key points of this work, the next section will be devoted to present this summary. In addition,

future work will be suggested for potential improvement.

7. Conclusions and Future Works

In this paper, a GA-based simulation model to solve the crew allocation problem has been

developed. The proposed algorithm was tested in a real life case study and the results were

compared with the current operating strategy. In addition, a newly developed selection strategy

named “Class Interval” was also applied to evaluate the efficiency of the proposed algorithm in

selecting promising chromosomes.

It has been concluded that the utilization factor has a significant impact on crew allocation cost

through the effect of the idle time factor on the allocation cost. Optimal usage of resources

(labor/machines) in conjunction with a minimized production time can lead to a minimum

allocation cost.

Page 32: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

30

As further developments, the GA-based simulation algorithm may be suitably modified and

employed to solve more complicated crew allocation problems by considering the detailed

modeling of processes with more than one working shift. More factors such as breakdown and

environmental impact will be considered in more detail while developing the allocation system.

The Monte Carlo Simulation can be used to assign a random crew to each process. This type of

heuristic rules can be compared with the results of GAs to check the efficiency of the proposed

allocation strategy.

References

Adeli, H. and Cheng, N.-T. (1994a), "Augmented Lagrangian Genetic Algorithm for Structural

Optimization", Journal of Aerospace Engineering, ASCE, Vol. 7, No. 1, pp. 104-118.

Adeli, H. and Cheng, N.-T. (1994b), "Concurrent Genetic Algorithms for Optimization of Large

Structures", Journal of Aerospace Engineering, ASCE, Vol. 7, No. 3, pp. 276-296

Adeli, H. and Karim, A. (1997). Scheduling/Cost Optimization and Neural Dynamics Model for

Construction. Journal of Construction Management and Engineering, ASCE, Volume 123,

Number 4, pp. 450-458.

Adeli, H. and Kumar, S. (1995a), "Distributed Genetic Algorithms for Structural

Optimization", Journal of Aerospace Engineering, Vol. 8, No. 3, pp. 156-163.

Adeli, H. and Kumar, S. (1995b), "Concurrent Structural Optimization on a Massively

Parallel Supercomputer", Journal of Structural Engineering, ASCE, Vol. 121, No. 11, pp.

1588-1597.

Adeli, H. and Wu, M. (1998), Regularization Neural Network for Construction Cost Estimation.

Journal of Construction Engineering and Management, ASCE, Volume 124, Number 1, pp. 18-

24.

Adeli, H. and Hung, S. L. (1995). Machine learning-neural networks, genetic algorithms, and

fuzzy systems. Wiley, New York.

Page 33: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

31

Adeli, H. and Park, H. S. (1996), Hybird CPN-Neural dynamics model for discrete optimization

of steel structures. Microcomputers in Civil Engineering, 11(5), 335-366.

Alcaraz, J., and Maroto C. (2001). A robust genetic algorithm for resource allocation in project

scheduling. Annals of operations research, Volume 102, Number 1-4, February, pp. 83-109

Anttila, M. (2005). 3D manufacturing simulation-improving the return on investment.

Proceedings 19th European Conference on Modeling and Simulation.

Boyabatli, O. (2007). Parameter selection in genetic algorithms. Journal of Systemic, Cybernetics

and information (JSCI), Volume 2, Number 4, pp. 78-83

Carro-Calvo, L., Salcedo-Sanz, S., Gil-Pita, R., Portilla-Figueras, A., and Rosa-Zurera, M.

(2009), An Evolutive Multiclass Algorithm for Automatic Classification of High Range

Resolution Radar Targets,” Integrated Computer-Aided Engineering, 16:1, pp. 51-60.

Cheng, T.M. and Yan, R.Z. (2009), “Integrating Messy Genetic Algorithms and

Simulation to Optimize Resource Utilization, Computer-Aided Civil and Infrastructure

Engineering, 24:6, pp. 401-415.

Chi, S., Caldas, C.H., and Kim, D.Y. (2009), “A Methodology for Object Identification and

Tracking in Construction based on Spatial Modeling and Image Matching Techniques,”

Computer-Aided Civil and Infrastructure Engineering, 24:3, pp. 199-211.

Dawood, N, Ahmed, R. and Dean, J. (2007) “Modeling of Precast Concrete Production

Operations and Innovations: A Simulation Approach”. Manubuild Conference, Rotterdam, 25-26

April.

Dawood, N. and Al-Bazi, A. (2009) "Using Genetic Algorithms to Improve Crew Allocation

Process in Labour-Intensive Industries”. The 2009 ASCE Workshop on Computing in Civil

Engineering, Texas, Austin, p166-175.

El-Rayes , K., and Moselhi, O. (2001). Optimizing resource utilization for repetitive construction

projects. Journal of Construction Engineering and Management, Vol. 127, No.1, pp. 18-27

Page 34: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

32

Glover, F., Kelly, J.P., and Laguna, M. (1999), New advances for wedding optimization and

simulation, in Proceedings of the 1999Winter Simulation Conference, 255-260.

Healey, F.J. (2009), Statistics: Tool for social research, (8th ed.), Belmont, CA: Wadsworth

Cengage Learning, USA.

Hegazy, T., ASCE, M. and Kassab, M. (2003). Resource optimization using combined simulation

and genetic algorithms. Journal of Construction Engineering and Management, Volume 129,

Issue 6, pp. 698-705

Hung S.L. and Adeli, H. (1994), "A Parallel Genetic/Neural Network Learning

Algorithm for MIMD Shared Memory Machines", IEEE Transactions on Neural

Networks, Vol. 5, No. 6, pp. 900-909.

Ipsilandis, P.G. (2006). Multi-objective optimization in linear repetitive project scheduling.

Operational Research. An International Journal. Volume 6, Number 3, pp.255-269

Jiang, X. and Adeli, H. (2008), “Neuro-Genetic Algorithm for Nonlinear Active Control

of Highrise Buildings, International Journal for Numerical Methods in Engineering, Vol.

75, No. 8, pp. 770-786.

Kang, M.W., Schonfeld, P., and Yang, N. (2009), Prescreening and Repairing in a

Genetic Algorithm for Highway Alignment Optimization,” Computer-Aided Civil and

Infrastructure Engineering, 24:2, pp. 109-119.

Kim, H. and Adeli, H. (2001), “Discrete cost optimization of composite floors using a floating

point genetic algorithm”, Engineering Optimization, Vol. 33, No. 4, pp. 485-501.

Kumar, A. J. S., Arunadevi, J., Mohan, V. (2009). Intelligent Transport Route Planning Using

Genetic Algorithms in Path Computation Algorithms. European Journal of Scientific Research.

Volume 25, Number 3, pp.463-468

Page 35: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

33

Lee, H., Kim, E., and Park, M. (2007), “A genetic feature weighting scheme for pattern

recognition,” Integrated Computer-Aided Engineering, 14:2, pp. 161-171.

Li, H., Love, P., and Ogunlana, S. (1998). Genetic algorithum compared to nonlinear

optimization for labor and equipment assignment. Building Research and Information, Volume

26, Number 6, pp.322-329

Lu, M., Lam, Hoi-Ching, Tang S.L. (2008). Skilled laborer management in handling concurrent

building projects at multiple sites: the bar benders job scheduling problem. First International

Conference on Construction in Developing Countries (ICCIDC-I), August 4-5, Karachi, Pakistan

Marzouk, M. Hisham Zein El-Dein, and Moheeb El-Said. (2007). Application of Computer

Simulation to Construction of Incremental Launching Bridges. Journal of Civil Engineering and

Management, Volume XIII, Number 1, pp. 27-36.

Marzouk , M., and Moselhi, O. (2004). Multi-objective optimization of earthmoving operations.

Journal of Construction Engineering and Management, Vol. 130, No.1, pp. 105-113

Mathakari, S., Gardoni, P., Agarwal, P., Raich, A., and Haukaas, T. (2007), “Reliability-based

Optimal Design of Electrical Transmission Towers Using Multi-objective Genetic Algorithms,“

Computer-Aided Civil and Infrastructure Engineering, 22:4, pp. 282-292.

Moselhi, O., Alshibani, A. (2007), Crew optimization in planning and control of earthmoving

operations using spatial technologies, Journal of Information Technology in Construction, The

International Council for Research and Innovation in Building and Construction, available at:

http://www.itcon.org/cgi-bin/works/Show?2007_7 (accessed 23 February 2009), Vol. 12 pp.121-

37.

Nassar, K. (2005). Evolutionary optimization of resource allocation in repetitive construction

schedules. Journal of Information Technology in Construction (ITcon), Volume 10, pp.265-273

Rekapalli, P.V., Martínez, J.C., and Kamat, V.R. (2009), “Algorithms for Accurate Three-

Dimensional Scene Graph Updates in High Speed Animations of Simulated Construction

Operations,” Computer-Aided Civil and Infrastructure Engineering, 24:3, pp. 186-198.

Page 36: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

34

Smith, J.F. and ThanhVu H. Nguyen, T.H. (2007), “Autonomous and cooperative robotic

behavior based on fuzzy logic and genetic programming,” Integrated Computer-Aided

Engineering, 14:2, pp. 141-159.

Sarma, K. and Adeli, H. (2000a), "Fuzzy Genetic Algorithm for Optimization of Steel

Structures", Journal of Structural Engineering, ASCE, Vol. 126, No. 5, pp. 596-604.

Sarma, K. and Adeli, H. (2000b), "Fuzzy Discrete Multicriteria Cost Optimization of

Steel Structures", Journal of Structural Engineering, ASCE, Vol. 126, No. 11, pp. 1339-

1347.

Sarma, K.C. and Adeli, H. (2001), “Bi-Level Parallel Genetic Algorithms for

Optimization of Large Steel Structures”, Computer-Aided Civil and Infrastructure

Engineering, 16 (5), pp. 295-304.

Sarma, K.C. and Adeli, H. (2002), “Life-Cycle Cost Optimization of Steel Structures”,

International Journal for Numerical Methods in Engineering, Vol. 55, No. 12, pp. 1451-1462.

Senouci, A.B. and Adeli, H. (2001). Resource Scheduling using Neural Dynamics Model of Adeli

and Park. Journal of Construction Engineering and Management, ASCE, Volume 127, Number 1,

pp. 28-34.

Shi, L. (2000). A new algorithm for stochastic discrete allocation optimization. Journal of discrete

Event Dynamic Systems, Volume 10, Number 3, pp.271-294

Teklu, F. Sumalee, A., and Watling, D. (2007), “A Genetic Algorithm for Optimizing Traffic

Control Signals Considering Routing,” Computer-Aided Civil and Infrastructure Engineering,

22:1, pp. 31-43.

Vlahogianni, E.I., Karlaftis, M.G., and Golias, J.C. (2007) Spatio-Temporal Short-Term Urban

Traffic Flow Forecasting Using Genetically-Optimized Modular Networks,” Computer-Aided

Civil and Infrastructure Engineering, Vol. 22, No. 5, pp. 317-325.

Page 37: Al-Bazi, AF and Dawood, NN (2010) 'Developing crew

Al-Bazi & Dawood

35

Watkins, M. Mukherjee, A., Onder, N. and Mattila K. G. (2007). Understanding Labor

Productivity as an Emergent Property of Individual and Crew Interactions on a Construction Site.

Proceedings IGLC-15, July, Michigan, USA.

Zhang H., Li H. (2004). Simulation-based optimization for dynamic resource allocation. Journal

of Automation in Construction Volume 13, pp. 409-420.

Zhang X. and Armstrong, M.P. (2005). Using a genetic algorithm to generate alternatives for

multi-objective corridor location problems. Proceedings of the 8th International Geo-

Computation Conference.