Developing crew allocation system for the precast industry usinggenetic algorithms
TeesRep - Teesside'sResearch Repository
Item type Article
Authors Al-Bazi, A. F. J. (Ammar); Dawood, N. N. (Nashwan)
Citation Al-Bazi, A. F. J. and Dawood, N. N. (2010) 'Developingcrew allocation system for the precast industry usinggenetic algorithms', Computer-Aided Civil andInfrastructure Engineering, 25 (8), pp.581-595.
DOI 10.1111/j.1467-8667.2010.00666.x
Publisher Wiley-Blackwell
Journal Computer-Aided Civil and Infrastructure Engineering
Additional Link http://doi.wiley.com/10.1111/j.1467-8667.2010.00666.x
Rights Subject to restrictions, author can archive post-print (iefinal draft post-refereeing). For full details seehttp://www.sherpa.ac.uk/romeo/ [Accessed 13/10/2010]
Downloaded 8-Feb-2018 14:52:13
Link to item http://hdl.handle.net/10149/112883
TeesRep - Teesside University's Research Repository - https://tees.openrepository.com/tees
TeesRep: Teesside University's Research Repository http://tees.openrepository.com/tees/
This full text version, available on TeesRep, is the post-print (final version prior to publication) of:
Al-Bazi, A. F. and Dawood, N. N. (2010) 'Developing crew allocation system for the
precast industry using genetic algorithms', Computer-Aided Civil and Infrastructure
Engineering, 25 (8), pp.581-595.
For details regarding the final published version please click on the following DOI link:
http://dx.doi.org/10.1111/j.1467-8667.2010.00666.x
When citing this source, please use the final published version as above.
This document was downloaded from http://tees.openrepository.com/tees/handle/10149/112883
Please do not use this version for citation purposes.
All items in TeesRep are protected by copyright, with all rights reserved, unless otherwise indicated.
Computer-Aided Civil and Infrastructure Engineering
1
Developing Crew Allocation System for the Precast
Industry Using Genetic Algorithms
Ammar Al-Bazi
Centre for Construction Innovation Research (CCIR), School of Science and
Engineering (SSE), Teesside University, UK
&
Nashwan Dawood
Centre for Construction Innovation Research (CCIR), School of Science and
Engineering (SSE), Teesside University, UK
Abstract:
The Precast Concrete Industry (PCI) is one of the major contributors to the national
economy and can be categorised as labor-intensive industry. It is currently experiencing
shortcomings in terms of delivery products at a competitive cost and time. This is mainly
due to the inefficiencies associate with planning and scheduling of skilled operators
within crews configurations. This paper presents a new strategy for efficient allocation
of crews of workers in the precast concrete industry using Genetic Algorithms-based
simulation modeling. The aim of this study is to develop crew allocation system that can
efficiently allocate possible crews of workers to precast concrete labor-intensive
repetitive processes. Genetic Algorithms (GAs) have been developed to solve this type
of problems. Process mapping methodologies were used to identify and document the
processes involved in producing precast components. Then process simulation was
Al-Bazi & Dawood
2
used to model and simulate all these processes and GAs were tailored to be embedded
with the simulation model for a better search of promising solutions. GAs operators were
designed to suite this type of allocation problem. “Class Interval” selection strategy was
developed to give a greater opportunity for the promising chromosomes to be chosen for
further investigation. Dynamic crossover and mutation operators were developed to add
more randomness to the search mechanism. The results showed that adopting different
combinations of crews of workers had a substantial impact on reducing the process
throughput time, minimizing resources cost, and achieving the required operatives
utilisation.
1. Introduction
„Crew allocation‟ can be defined as the process of assigning crews of workers or operatives to
processes to ensure that they are used in an optimal way. This problem becomes more challenging
when it involves a complex system that shares limited crews. Crew allocation can be a very
complex problem when same operatives are required to be involved in concurrent or
simultaneous processes. The optimal allocation of crews should satisfy minimum clashes or
overlaps between different crew‟s operatives and this should subsequently minimize production
costs and idle time.
Two difficulties can arise in solving this problem: the combinatorial explosion of alternative
crews normally leads to NP-hard optimization problems and the lack of analytical expressions
relating performance functions to solutions usually results in noisy estimates of the performances
(Shi 2000).
There is a lack of applying appropriate techniques that advise on optimal allocation of crews of
workers in the precast industry. It is crucial to plan and manage operatives allocation to ensure
the optimal choice of crews and effective utilization of each crew member have been achieved,
Zhang et. al., (2004).
Al-Bazi & Dawood
3
As one of sophisticated techniques that have been used in solving these kinds of problems, GAs
have been applied to many different optimization problems such as the optimization of traffic
control signals (Teklu et. al., 2007), electrical transmission towers (Mathakari et. al., 2007),
(Cheng et. al., 2009), highway alignment optimization (Kang et. al., 2009), and large
structures (Adeli and Kumar, 1995a&b; Sarma and Adeli, 2000a&b, 2001), as well as
short-term urban traffic flow forecasting (Vlahogianni et. al., 2007), pattern recognition (Lee et
al., 2007), classification of radar targets (Carro-Calvo et. al., 2009), structural control (Jiang and
Adeli,2008), machine learning (Hung and Adeli, 1994), and robotics (Smith et. al., 2007). They
are one of the most promising meta-heuristics algorithms (Alcaraz et. al., 2001). GA technique is
defined as a computational model simulating the process of genetic selection and natural
elimination in biological evolution, (Adeli and Cheng, 1994a&b; Kumar et. al., 2009). In recent
years, various approaches to construction simulation have been advanced such as object
identification and tracking (Chi et. al., 2009) and high speed animation (Rekapalli et. al., 2009).
In this work, GA is designed to be coupled with process-simulation model for further guidance of
the simulation model toward choosing the best processing crew among sets of possible
alternatives. The reason behind choosing GA is its ability to intelligently search through a
solution space for optimal or near optimal solutions. In the crew allocation problem under study,
an intelligent searching algorithm is developed to investigate a large pool of crews, to decide
which set of crews can be allocated to processes in order to minimize labor costs.
In this paper, the developed crew allocation system dubbed “SIM_Crew” was designed to
efficiently allocate crews of workers to the precast industry. In such an industry, there is a high
demand for skilled workforce and skilled operatives costs are relatively high. A “sleeper” precast
manufacturing system was considered as a test of the proposed system. A proper allocation
system will thus ensure minimum throughput time, production costs, and maximum utilization of
resources. A „sleeper‟ precast component is used as a base for rail tracks. „Sleepers‟ are precast
Al-Bazi & Dawood
4
components generally laid transverse to the rails, on which the rails are supported and fixed, to
transfer the loads from rails to the ballast and sub grade below, and to hold the rails to the correct
gauge.
The reminder of the paper discusses the research problem, previous theories concerning crew
planning and scheduling techniques, system architecture of the crew allocation system, process
mapping methodologies, simulation and optimization modeling and finally a real life case study
to validate the model.
2. Research Problem
Due to the fact that the parallel and sequential nature of any labor-driven system is pre-specified,
the labor shared between similar or different tasks is generally allocated according to the
workflow. However, idle times are still not carefully considered and the overall throughput time
or total costs may be longer or higher than expected. In fact, this problem becomes more apparent
when there is significant idle time for a process due to sharing operatives.
Due to the fact that the precast operations are labor-intensive and the required workforce involved
in such industry is highly skilled and costly, optimization of crew allocation in the precast
manufacturing system is needed in order to minimize idle times caused by sharing operatives.
Each production process has a certain pool of crews that can possibly perform the work for each
of the parallel activities. Each crew has a different set of workers “different crew formation” with
a certain process time. Sharing available operatives in different crews will eventually cause
delays.
„Parallel-Repetitive Similar Processes‟ is a realistic example of a resource sharing case. All
production processes in such a layout have a similar sequence, and the same materials are
processed by similar parallel repetitive processes in order to produce the same or different
Al-Bazi & Dawood
5
products in a short cycle time. This kind of production layout can be seen in a job-shop
environment such as seen in the precast concrete industry.
The aim of “SIM_Crew” is to achieve the best allocation of crews to carry out parallel or
sequential processes for any labor-driven facility. The optimal crew allocation will eventually
reduce the clashes between any shared resources, and subsequently lead to minimizing both
operatives costs and process idle times. The system architecture of the crew allocation system
will be described in the next section.
3. Literature Review
Crew planning and scheduling using simulation modeling and optimization technology have been
applied in construction and precast industries. The layout of the operations (parallel/series) and
repeatability of operations involved was crucial when considered in such planning and scheduling
analysis. In this context, the literature review is categorized into two groups:
Repetitive Operations
In this type of layout, crews are often required to repeat the same work in various locations of the
enterprise, moving from one location to another. Many available crew planning and scheduling
systems for repetitive operations have been discussed in the work of Nassar (2005) who
presented a model that uses a spreadsheet based GA models to optimally assign resources to
repetitive activities of construction projects. Ipsilandis (2006) presented a linear programming
parametric model for supporting construction managers decisions, exploring the multi-objective
nature of decision making in repetitive construction projects. The project consisted of six
repetitive units each having six discrete activities repeated in each unit. Lu et. al., (2008)
presented a computer system dubbed “simplified simulation-based scheduling (S3)” to solve the
problem of skilled laborer scheduling in a multi-site, multi-project context. The model consists of
an optimizer using the Particle Swarm Optimizer (PSO) as a stochastic search strategy on a
Al-Bazi & Dawood
6
population of individuals, each representing a possible solution to the problem. Dawood et. al.,
(2007), developed a generic simulation model depicting the operational processes of the precast
concrete production system. Results showed that the smaller the number of human resource
available, the longer will be the lead time and the production costs will be lower. The greater the
number of resources, the shorter the lead time, however, production costs will be greater.
Non-Repetitive Operations
In non-repetitive processes/ activities, crews are often required to carry out non-similar works in
various locations of the project / job-shop. Many available scheduling methods for repetitive
construction projects have been presented in the work of Moselhi et. al., (2007), who proposed a
new methodology utilizing combined GAs and spatial technologies for optimization of crew
formations for earthmoving operations. The designed model is useful for planning, tracking and
control of earthmoving operations. Watkins et. al., (2007), used agent-based modeling methods
simulating space congestion on a construction site to explore the impact of individual interactions
on productivity and labor flow. Li et. al., (1998), presented a methodology for optimizing labor
and equipment assignment for excavation and earthwork tasks using the Genetic Algorithm. A
number of modifications of the basic GAs were achieved to improve the capacity of the
algorithms. Zhang et. al., (2004), developed an optimization methodology which integrates
discrete-event simulation with an heuristic algorithm to optimize dynamic resource allocation for
construction scheduling. Senouci et. al., (2001), presented an optimization formulation for
project scheduling problems with the objective of minimizing the total construction cost. The
developed model considers project scheduling characteristics generally ignored in Adeli and
Karim (1997) including precedence relationships, multiple crew-strategies, and time-cost trade-
off, they addressed resource levelling and resource-constrained scheduling of non-repetitive
activities performed simultaneously. Marzouk et. al., (2004), provides a multi-objective
Al-Bazi & Dawood
7
optimization tool to optimize earthmoving operations using computer simulation and genetic
algorithms. The optimization is aimed at minimizing the time and cost of earthmoving operations.
Marzouk et. al., (2007), presented a special purpose simulation model to capture the uncertainty
associated with bridge construction and results of the model showed that increasing the number
of labor crews shortens the fabrication duration. The above literature study presented many
methodologies and tools used to solve crew allocation problems in both repetitive and non-
repetitive operations layout in construction and precast industries, most of which have focused on
minimizing costs rather than considering the effects of resources utilization on system
performance. Some studies demonstrated the simulation of repetitive processes but the detailed
crew formations of each process were not taken into account. Many systems have not used any
optimization modules for a crew allocation; only running scenarios for improvement were
adopted in such systems. In addition, available performance keys such as costs and utilization
were not calculated to show the effects on system performance. Crew planning and scheduling
systems are incapable of determining worker utilization as they can only produce crew utilization,
so there is a pressing need for advanced systems that can address the utilization issue. The
proposed system presented in this paper, more attention has been given to the worker utilization
factors as they impact labor allocation cost. The next section will describe the research problem
in more detail.
4. Architecture of Crew Allocation System
The purpose of allocating crews is to place the most suitable team of workers for each activity at
minimum allocation cost and best possible performance. Therefore, as a fundamental
requirement, crews should be allocated to new production processes once they are freed from
previous processes. In addition, the performance of alternative feasible crews should be evaluated
in terms of allocation cost and effciency, so that the most efficient one with the minimum cost
Al-Bazi & Dawood
8
and less interruption will be selected for implementation. To meet the above allocation process
objective, a GA based simulation model is proposed, as shown in figure 1.
Figure 1: “SIM_Crew” Architecture
As shown in figure 1, the core of “SIM_Crew” is the simulation model which is integrated with
databases through integration, and a processing module developed by writing special codes to
enable such integration. The optimization engine is designed to be embedded in the simulation
model; solutions are suggested from this engine to be evaluated by the simulation model, and all
results are then stored in the database. During one allocation iteration, the simulation executes
allocation plans: each of them has sets of crews to be allocated to the production processes, while
GA evaluates the performance of the resultant allocation, and based on this, adjusts the decision
variables and selects the most promising once. The main functionality of the optimization engine
is to propose and manipulate solutions to be tested by the simulation model for a better
performance. A number of key performance indicators such as total resource allocation cost,
crew formation utilization, and other fixed resources utilization were used to evaluate the outputs
of the model. An interface mechanism is designed to include size of population, crossover and
mutation strategies, and other entry requirements. As shown in figure 1, the allocation process is
an iterative procedure of progressive improvement.
Al-Bazi & Dawood
9
5. Process Mapping, Simulation and Optimization Modeling
5.1 Process Mapping
All production processes at two production sections are mapped to identify inputs, resources,
constraints affecting each process, and the resulting outputs of each production process. This type
of visual modeling is important to identify the relationships among the production process and the
logic of each process. In order to have a sound understanding of the production life cycle at each
production section, all production processes were studied and mapped. Figure 2 shows IDEF0
diagrams of one of the production lines (four production lines were considered in this study, each
of them with a similar production sequence).
Figure 2: sleeper manufacturing process mapping diagram
The process flow starts from the mold setup process where inputs of this process are defined. The
restrictions imposed on this process are mold and labor availability. The resources required to
carry out the setup process include: an air compressor, a mold, laborers. The second process is to
Al-Bazi & Dawood
10
place strands inside the mold so that the sleepers can be reinforced, as a third process may require
different numbers of strands depending on the type of products (sleepers). The casting process is
then applied to fill the mold with the required amount of concrete and fourthly, the curing process
uses a steaming system to cure the cased sleepers. The curing area capacity and availability of
plastic sheets are the main restrictions on the curing process. Demolding follows the cutting
process, involving cutting off the strands and then demolding sleepers with a special machine.
The finishing of the sleepers is the last process which comprises placing plastic, rubber, and clips
on each sleeper.
All inputs, outputs, constraints, and resources regarding each process are defined to give a clear
idea about the core of each process and how these processes can be related to each other so that
an accurate simulation model can be developed. The following section details the simulation
model developed in this research project.
5.2 Simulation Modeling
The ability of simulation to model physical processes on a computer, incorporating the
uncertainties that are inherent in all real systems, provides an enormous advantage for analysis in
situations that are too complex to model mathematically (Glover, et. al., 1999). As one of the
common methodologies used to simulate real life systems, Discrete Event Simulation (DES) is
used to simulate production processes of the manufacturing system being investigated, as it is a
powerful methodology used to model many real systems as they progress through time. The
primary objective of the developed simulation model is to analyze “what-if” scenarios and
thereby evaluate the allocation of each set of crews of workers to production processes for any
manufacturing system. All inputs, process, and output of the simulation model are mapped in as
introduced in the previous section and more details are explained in the next sections.
Al-Bazi & Dawood
11
- Inputs
Demands and orders specifications have been identified which will be produced in each
production line. Information about orders includes the type of product, quantity needed, the
amount of materials required for each order and resource needed. All production information is
stored in an Excel spreadsheet to be integrated with ARENA using the Data Access Object
“DAO”. All other labor information is stored in Access databases. The skills needed for each
crew for each process have been determined by and possible crews formation.
A crew alternative list for each process has been provided by the production manager (according
to his experience). All sets of possible crews are accommodated into the Access database for
further use. See figure 3:
Figure 3: shows the crew population pool and some crew formation
In figure 3, each crew of workers involves a set of workers that are qualified to carry out a
process. The workers were coded according to their numbers and all related information saved in
the workers‟ pool. The qualification of each worker as well as hourly costs were saved in the
workers‟ pool.
Al-Bazi & Dawood
12
- Process
This includes all the simulated production processes which are introduced in section 5.1.
- Outputs
After running the simulation model the outputs are stored in Excel files for further analysis. Some
of the results are stored in the Access database to check for chromosome duplication. A large
number of text files are created to validate the working of the optimization engine operators. The
parameters evaluated include total resource allocation cost, and crew formation utilization.
Assumption of the Simulation Model
A number of assumptions are used when constructing the simulation model, the purpose of these
assumptions was to simplify the development of the simulation model.
1. Each crew member is intensively involved in carrying out the production process. All
members work together to finalise the process.
2. To begin a production process, all crew members should be available and should be
released at once when that the process is complete.
3. The model is developed based on 24 hour working.
4. Only direct costs are considered in this model
5.3 Optimization Using Genetic Algorithms
The previous section has introduced the simulation model and the objective of this section is to
discuss the optimization technology used in this research and the integration with the simulation
model.
The benefit of using GA is the possibility to search for an optimum or near-optimum allocation of
a crew of workers to each production process. This type of allocation optimizes both cost and
Al-Bazi & Dawood
13
production, under various constraint scenarios related to the availability of workers within a crew.
Figure 4 shows how GA is used to optimize the crew allocation process:
The initial population of chromosomes, each chromosome consisting of a set of crews to be
assigned to processes generates random sets of crews using a Monte Carlo sampling technique.
The most promising chromosomes should always be kept in the top list for easier access and
further selection. For this purpose, the SQL query is set to always select the most promising
chromosomes of a population size. Each pair of chromosomes is then selected to be prepared for
further crossover and mutation purposes. An un-repeatability condition is imposed to avoid any
repetition which might occur by producing two similar chromosomes. This process continues
until the condition regarding the number of generations is satisfied. After each generation, the
population is added to the previous generation‟s population to produce an augmented population
pool. A sorting procedure is then applied on the augmented population pool.
Figure 4: Modified Genetic Algorithms Flowchart
Al-Bazi & Dawood
14
The output of the optimization process represents the possible „set of crews‟ that can be allocated
to each production process. The decision variables are stored in a row vector (string) called a
chromosome, which has a number of elements (genes) representing the number of variables equal
to the number of sets of crews available and possible to allocate. The chromosome was
specifically designed to resolve this type of problem as demonstrated in figure 5.
Figure 5: chromosome representation for the crew allocation problem
In figure 5, each integer number of each gene would give the crew index number of the set of
crew alternatives associated with that gene, i.e; this number would give the index of a crew that
could be used in the solution as each gene has different possible alternatives of crews. A
chromosome is encoded in a decimal way with the chromosome length is representing the
maximum number of processes involved in any labor-driven production facility.
The decision variables are the number of sets of crews available to allocate to each process. To
evaluate each chromosome, a single objective function has been identified and adopted to
minimize labor costs. Many restrictions can be determined which limit production amounts,
alternative crews, and operational hours (shifts). In some situations, a trade-off exists between
idle time and cost (El-Rayes et. al., 2001). In this study, only direct cost is considered as a
substantial cost and GAs have been used productively in a number of studies in order to optimize
costs (Kim and Adeli 2001, Sarma and Adeli 2002).
Al-Bazi & Dawood
15
The objective function is applied to evaluate total resource costs from information identified in
previous job-shop cost records. The equation used to calculate the objective function is:
n
i
iiii RCPUIRCBRCxf1
(1)
Where:
n is the number of labor-driven processes
iBRC : .incurred cost per hour when using a laborer for set of solution i.
iIRC : incurred cost per hour when laborer is idle for set of solution i and
iRCPU : incurred cost per use of fixed or physical resource for set of solution i;
senior skilled bonus can be considered in such cost.
As an initial starting point, a population of solutions (chromosomes) is generated randomly using
Monte-Carlo sampling. Population size and other GA operators‟ parameters influence the
solution and simulation time (Boyabatli 2007). As one of the random sampling techniques, Monte
Carlo is used to select crew alternative for each gene (i.e process). This generates a random
number for each gene which is used to select the alternative crews for each process. The range of
random numbers for each gene can be determined using the following constraint
iii MaxCARMinCA
where
iR is an integer random number for each chromosome i
iMinCA is minimum number of crews alternative in gene i and
iMaxCA is maximum number of crews alternative in gene i
In the proposed model, the user is given the possibility to input the population size. Once the
population is generated, each chromosome is evaluated individually using the developed
simulation model. GA operators are tailored to suit this type of allocation problem. Next, “Class
Interval” selection, “Dynamic Crossover” and “Mutation” Strategies are explained.
Al-Bazi & Dawood
16
The Proposed “Class Interval” Selection Strategy (CISS)
The promising chromosomes with least costs will be given a higher chance of selection, and are
named the “class interval” strategy, which is based on the concept used in the descriptive
statistics. (Healey, 2009)
The top of the minimum costs chromosome will be given higher weighting than others by
calculating the fitness function according to equation (2):
ii xfMaxGx (2)
where
iGx : Fitness function of chromosome i
ixf : Sorted objective function for top promising chromosomes and
Max : The largest cost value in the best promising chromosomes
Repetition of the generated chromosome is not allowed, meaning that all generated chromosomes
should be unique over the evolution process. To construct the chromosome‟s class interval, a
relative fitness function iRGx is calculated using equation 3:
m
i
i
i
i
Gx
GxRGx
1
, i=1,.. m (3)
where
iRGx : Relative fitness function of chromosome i and
:m is the population size
The cumulative relative fitness function is then calculated, as it is useful to determine the desired
class width using equation 4:
iii RGxCRGxCRGx 1 , i > 1 (4)
where
11 GxCRGx
iRGx : Relative fitness function of chromosome i and
iCRGx : Cumulative Relative fitness function of chromosome i
Al-Bazi & Dawood
17
Subsequently, the possible interval of occurance for each chromosome is determined from the
class intervals. The interval associated for each chromosome will represent the chance range of
that chromosome to be selected by any generated (0-1) random variate as in figure 6:
Figure 6: the proposed “class-interval” selection rule
In the proposed selection strategy and after sorting the resulting costs obtained from equation 1 in
ascending order, the chromosomes with minimum costs are selected from the augmented
population pool as the promising pair of chromosomes. The fitness function is then calculated
using equation 2, and the result is sorted in descending order for a better selection at a later stage.
The relative fitness function is calculated using equation 3 as a requirement for constructing the
chromosomes class interval. Cumulative relative frequency is then calculated using equation 4 as
the upper bound of the chromosome‟s opportunity to be selected. The lower boundary can be
identified to represent the possible range of each chromosome to be selected. This strategy is
derived from the class interval concept in descriptive statistics and has been found to be useful for
Al-Bazi & Dawood
18
chromosomes selection. The idea of modifying this concept is to give a greater opportunity for
the promising chromosomes to be selected again. The chromosomes with minimum cost or a
higher fitness function will be given a wider range of interval so random variants will be more
likely to lie within this range.
Dynamic Points Crossover (DPC)
The crossover operation in a conventional GA is based on the exchange of genes between two
fixed length chromosomes when string coding is applied (Zhang et. al., 2005). In the
“SIM_Crew” model, DPC is developed to achieve the best random exchange of genes between
each pair of chromosomes, as shown in figure 7:
Figure 7: the Dynamic-Points Crossover (DPC) strategy
In this type of crossover, random numbers of size (n) are generated to be associated with each
gene; a vertical crossover takes place to exchange or alternate subsequently n gene(s) of the first
chromosome with the opposite gene of the second selected chromosome after satisfying the
condition below:
Al-Bazi & Dawood
19
If the probability of crossing over a gene ≤ the random number associated with that gene, then the
crossing over of that gene is possible.
For example, suppose five random numbers satisfy the swapping condition at genes 2, 4, and 4,
the chosen places or genes will be exchanged between each selected pair of chromosomes.
Dynamic-Points Mutation (DPM)
This mutation operator is similar to the developed crossover operator where random numbers of
size (m) are generated to be attached to each gene. The selected genes are then specified for
further mutation. The possible crew place to carry out a particular process is then generated
randomly for each chosen gene. The mutation process continues until a unique chromosome is
satisfied to be placed into the new population for further testing is shown in figure 8.
Figure 8 the Dynamic Points Mutation (DPM) strategy
After a crossover operator has taken place, each chromosome is then mutated individually. The
same strategy of the Dynamic Crossover can be individually applied to each chromosome and the
Al-Bazi & Dawood
20
same exchange condition can be used to mutate genes. The selected genes can be mutated with its
pool “list of alternative crews” using the Monte-Carlo simulation.
Avoiding of Chromosome Duplication
As solutions (chromosomes) are generated randomly using the GAs operators, the possibility of
repeated solution exists. Such repetition causes additional calculations and subsequently leads to
an increase in the calculation time. In order to avoid duplication of chromosomes during
evaluation and to minimize evaluation time and calculation operations, “one search strategy” is
developed to search for any duplications and to discard any repeated chromosomes. This enables
the “SIM_Crew” engine to evaluate just non-duplicated chromosomes for a faster and better
investigation.
The “one search strategy” enables investigation of the current generation chromosome to check
whether any chromosome is repeated in the chromosome list which is stored in access database.
The non-repeated chromosomes can be stored temporarily in the chromosomes access database
under the (-1) generation number. Defining chromosomes with the (-1) generation number for the
non-duplicate chromosomes eases the discarding of them after copying them to the VBA
database. Figure 9 below shows the “one-search strategy” steps that “SIM_Crew” applies to filter
the resulted chromosomes.
Al-Bazi & Dawood
21
Figure 9: “one search strategy” flowchart for duplication
In this developed flowchart, “one search strategy” is developed to save computation time and
program codes. In one search strategy and after selecting a pair of chromosomes, crossover will
take place by exchanging selected genes using the probabilistic dynamic strategy. To add more
randomness to the crossed-over chromosomes, each chromosome should be mutated individually
with its available list of alternatives for each process using the Monte Carlo (MC) sampling
method. The mutated chromosome will be checked with Access database which involves all
chromosomes generated for all previous populations (population history), then, if the tested
chromosome is duplicated, the mutation process should continue until a unique chromosome is
obtained.
After finding a unique chromosome, a copy of this chromosome should be sent to access database
population list under the (-1) generation number and another copy to the VBA array which
Al-Bazi & Dawood
22
involves all unique chromosomes for the current generation for evaluation purpose. After testing
all chromosomes for duplication, all chromosomes having the (-1) generation number should be
discarded from the access database population history and the VBA array should be prepared to
be fed to the simulation engine for evaluation purposes.
The purpose of the temporary chromosome is to assist checking for duplicated entries while the
next generation is being created. As each chromosome is generated through the crossover
mutation operators, it is stored into the database with a generation number of (-1) a flag that eases
the deletion of non-repeated chromosomes. This means that all past, current and proposed
chromosomes are held in one location, so a single search can check if the new chromosome is a
duplicate.
The “one search strategy” ensures that all chromosomes are unique before evaluating them;
therefore, there is no point to test for repeated chromosomes as it wastes time and computational
efforts.
6. The Case Study
A case study of one of the largest „sleepers‟ products precast concrete industry in the UK was
developed. In this sleeper manufacturing system, the production process involves using a wide
range of different resources, including labor, equipment, and materials. For planning and control
purposes, precast operations are broken down into activities/tasks, so that resources can be
economically allocated and controlled.
The railway sleeper concrete manufacturing system is investigated in this study and is divided
into two main production sections; each having two labor-intensive production lines and shared
resources (labor and machines) are used to carry out job/activity on each production line
alternately. Eight processes including curing are applied to the sleeper.
Two types of multi-skilled workers were used to carry out jobs in the two production lines:
charge workers (multi-skilled workers in charge of operators) and operators (multi-skilled
Al-Bazi & Dawood
23
workers). Each multi-skilled worker has the skills to carry out a number of possible activities,
depending on the accumulated skills of the worker and his/her ability to work on more than one
process.
In production section 2, eleven operators and two charge workers are used to carry out tasks, and
thirteen operators and four charge hands in production section 3. On any of the production lines, a
“reusable mold” is the main resource, which consists of a gang of molds that can be used to
produce either the same or different types of sleeper. A wide range of sleepers are produced by
the production processes presented in figure 2 such as the „G44‟, „5EF28‟, „EG47‟, and „EG47
3R‟. The logic of these production processes was presented by Dawood and Al-Bazi (2009).
Resources assigned to each mold are shared resources (machines, laborers) which are applied to
produce the finished sleeper. The job-shop layout consists of three zones: materials zone,
concrete mix zone, and production zone. In the material zone, all steel wire rolls, plastic spacers,
pandrols, and other finishing accessories are stored nearby to be available when needed. A
number of mechanical resources can be stored in this area after using them.
After a detailed investigation of each process in the company, a simulation model was developed
using ARENA simulation software to simulate the production processes of the sleeper concrete
manufacturing system. All relevant data were collected by conducting onsite visits, using
flowcharts and process maps, interviews and the stop watch technique as relevant data collection
techniques. The crew alternatives for each production process were identified by the production
planner according to the accumulated experience record of a worker as shown in table 1.
Table 1: number of crew alternatives for each process
Al-Bazi & Dawood
24
Sec
tio
n I
D
Lin
e ID
Process ID
Number of
Crew
Alternatives
Sec
tio
n I
D
Lin
e ID
Process ID
Number of
Crew
Alternatives
Pro
du
ctio
n S
ecti
on
2
Pro
du
ctio
n L
ine
1
Setup 4
Pro
du
ctio
n S
ecti
on
3
Pro
du
ctio
n L
ine
1
Setup 3
Run Strand 4 Run Strand 3
Stress 4 Stress 3
Casting 4 Casting 3
Sawoff 3 Sawoff 3
Demolding 4 Demolding 3
Finishing 4 Finishing 3
Pro
du
ctio
n L
ine
2
Setup 4
Pro
du
ctio
n L
ine
2
Setup 3
Run Strand 4 Run Strand 3
Stress 4 Stress 3
Casting 4 Casting 3
Sawoff 3 Sawoff 3
Demolding 4 Demolding 3
Finishing 4 Finishing 3
According to the above table, the possible number of allocation plan is equal to 722,204,136
million which demonstrate the crew allocation problem being investigated to be a combinatorially
complex one. However, more detail about crew formation data and worker details are confidential
and cannot be published in this study.
Twenty-eight production processes divided between four production lines in two production
sections (seven repetitive processes at each) were considered in the 3D simulation model. The
3D simulation model can be used as a communication tool to convey the idea of how a sleeper
production system works and how it performs to avoid costly mistakes as early as possible.
(Anttila, 2005). The purpose of visualization was to verify the simulation model and to provide
production managers with more advanced means of communication. However, the 3D animation
was enough to verify the logic used in constructing the simulation model. See figure 10.
Al-Bazi & Dawood
25
Figure 10: depicts visualization of the sleepers manufacturing system
A set of crews specified to carry out each production process which had been suggested by the
production manager were fed into the system database. Class Interval Selection Strategy (CISS)
was used as a selection strategy, while Dynamic Points Crossover (DPC) and Dynamic Points
Mutation (DPM) were chosen as a crossover and mutation strategy. Fourty generations with a
population of size 20 was used to obtain a stable result. In order to analyze opportunites for
improvement in the sleeper precast concrete manufacturing system, an optimization study will be
conducted in the next section to identify the impact of allocation plans on system performance.
6.1 Running Experimental Work
The objective of this study was to iteratively generate and test possible crew allocation scenarios
which can be evaluated using simulation until the minimum resource allocation cost is found. The
GAs module is used to iteratively generate and evolve allocation scenarios. The simulation
module is then utilized to test the impact of each allocation scenario on the performance of the
manufacturing system in terms of resource utilization and costs.
In most cases, the algorithm converges after 25 generations which takes about 7-8 hours and
requires a memory of 512 MB. The population size is set to be 20 chromosomes. The
chromosomes size is defined to be equal to the number of processes. The probability of crossing
over a gene and mutating a gene is identified to be 0.2, 0.3 respectively (several sets of different
Al-Bazi & Dawood
26
probabilities have been attempted without any significant effects). The probability of mutation is
higher than crossover, as the mutation operator in this system plays a vital role in mutating
repeated chromosomes in order to obtain the unique one.
For the model settings above, a simulation run has been performed to check the functionality of
the proposed system and determine which type of development the model can add to reduced
costs.
6.2 Analysis and Interpretation
The results of the case study are shown in figures 11-15
Figure 11: costs reduction using “SIM_Crew” allocation System
Figure 11 shows that a significant drop in cost takes place after the 2nd generation with slight
cost reductions in a number of generations. The GA dynamic probabilistic operators have
successfully explored more promising solution areas on the mentioned generations. Allocation
cost tends to have no improvement after 25 generations. This best scenario drove the allocation
cost equal to £48300 in which a return of 1.5% (about £300 per five working days) is achieved.
To verify that the GA converges to the optimal solution, we applied the average results to test the
improvement and convergence of the solutions, as in figure 12.
Al-Bazi & Dawood
27
Average Cost for Each Generation
50000
51000
52000
53000
54000
55000
56000
57000
1 4 7 10 13 16 19 22 25 28 31 34 37 40
Generation Number
Co
sts
This figure shows improvement of the solutions over generations: generation by generation the
average solution is improved due to the evolving process available in the algorithm used. The
utilization of fixed resources and labor is optimized in order to identify the optimal utilization that
could minimize the total allocation cost. A sample of two workers from different skills
backgrounds working with a concrete mold has been selected from 47 resources to be presented
in this paper. The best chromosome of each generation is selected to present the optimized
utilization of resources of that chromosome as shown in figures 13-15:
Figure 13: mold utilization optimization using “SIM_Crew”
In figure 13, the utilization of the used concrete mold at section 3 is optimized to determine the
required level of utilization needed for the mold resource to minimize the total production costs.
Fixed resources such as the mold have shown a highly stable utilization because of their
Figure 12: reduction trend in costs using “SIM_Crew” System
Al-Bazi & Dawood
28
continuous use. For laborer resources, one of the operative‟s utilization profiles is shown in figure
14.
Figure 14: operative labor utilization optimization using “SIM_Crew”
In figure 14, the utilization of worker 21 who is an operative laborer working in section 3 is
optimized to determine the required level of utilization needed to minimize the total
manufacturing costs. However, operators have a higher utilization as they are involved in
carrying out most of the manual work. Skilled worker utilization is also calculated as shown in
figure 15.
Figure 15: skilled labor utilization optimization using “SIM_Crew”
In figure 15, the utilization of worker 14, a senior charge worker working in section 3 is
optimized to determine the required level of utilization to minimize the total allocation cost.
Al-Bazi & Dawood
29
Skilled workers are less utilized as their main duty is supervision and guidance. The resources
utilization charts presented in figures 14-15 reveal that utilization of shared the laborer fluctuates
as the objective function seeks to achieve the required resources utilization. The non-shared
resources such as molds have a stable utilization as they are used only by one set of workers at a
time.
Different levels of utilization of each selected resource are shown through many generations, so
the fluctuation of shared resource utilization is remedied by varying the utilization of other
resources to satisfy the desired objective function. The last generation will show the optimized
utilization required to achieve minimum total production costs.
The developed simulation model has not considered other factors as breakdown or mixer
problems. In addition, none of the environmental impacts such as weather have been considered
in this study. These shortcomings can be addressed in future research projects. To summarize the
key points of this work, the next section will be devoted to present this summary. In addition,
future work will be suggested for potential improvement.
7. Conclusions and Future Works
In this paper, a GA-based simulation model to solve the crew allocation problem has been
developed. The proposed algorithm was tested in a real life case study and the results were
compared with the current operating strategy. In addition, a newly developed selection strategy
named “Class Interval” was also applied to evaluate the efficiency of the proposed algorithm in
selecting promising chromosomes.
It has been concluded that the utilization factor has a significant impact on crew allocation cost
through the effect of the idle time factor on the allocation cost. Optimal usage of resources
(labor/machines) in conjunction with a minimized production time can lead to a minimum
allocation cost.
Al-Bazi & Dawood
30
As further developments, the GA-based simulation algorithm may be suitably modified and
employed to solve more complicated crew allocation problems by considering the detailed
modeling of processes with more than one working shift. More factors such as breakdown and
environmental impact will be considered in more detail while developing the allocation system.
The Monte Carlo Simulation can be used to assign a random crew to each process. This type of
heuristic rules can be compared with the results of GAs to check the efficiency of the proposed
allocation strategy.
References
Adeli, H. and Cheng, N.-T. (1994a), "Augmented Lagrangian Genetic Algorithm for Structural
Optimization", Journal of Aerospace Engineering, ASCE, Vol. 7, No. 1, pp. 104-118.
Adeli, H. and Cheng, N.-T. (1994b), "Concurrent Genetic Algorithms for Optimization of Large
Structures", Journal of Aerospace Engineering, ASCE, Vol. 7, No. 3, pp. 276-296
Adeli, H. and Karim, A. (1997). Scheduling/Cost Optimization and Neural Dynamics Model for
Construction. Journal of Construction Management and Engineering, ASCE, Volume 123,
Number 4, pp. 450-458.
Adeli, H. and Kumar, S. (1995a), "Distributed Genetic Algorithms for Structural
Optimization", Journal of Aerospace Engineering, Vol. 8, No. 3, pp. 156-163.
Adeli, H. and Kumar, S. (1995b), "Concurrent Structural Optimization on a Massively
Parallel Supercomputer", Journal of Structural Engineering, ASCE, Vol. 121, No. 11, pp.
1588-1597.
Adeli, H. and Wu, M. (1998), Regularization Neural Network for Construction Cost Estimation.
Journal of Construction Engineering and Management, ASCE, Volume 124, Number 1, pp. 18-
24.
Adeli, H. and Hung, S. L. (1995). Machine learning-neural networks, genetic algorithms, and
fuzzy systems. Wiley, New York.
Al-Bazi & Dawood
31
Adeli, H. and Park, H. S. (1996), Hybird CPN-Neural dynamics model for discrete optimization
of steel structures. Microcomputers in Civil Engineering, 11(5), 335-366.
Alcaraz, J., and Maroto C. (2001). A robust genetic algorithm for resource allocation in project
scheduling. Annals of operations research, Volume 102, Number 1-4, February, pp. 83-109
Anttila, M. (2005). 3D manufacturing simulation-improving the return on investment.
Proceedings 19th European Conference on Modeling and Simulation.
Boyabatli, O. (2007). Parameter selection in genetic algorithms. Journal of Systemic, Cybernetics
and information (JSCI), Volume 2, Number 4, pp. 78-83
Carro-Calvo, L., Salcedo-Sanz, S., Gil-Pita, R., Portilla-Figueras, A., and Rosa-Zurera, M.
(2009), An Evolutive Multiclass Algorithm for Automatic Classification of High Range
Resolution Radar Targets,” Integrated Computer-Aided Engineering, 16:1, pp. 51-60.
Cheng, T.M. and Yan, R.Z. (2009), “Integrating Messy Genetic Algorithms and
Simulation to Optimize Resource Utilization, Computer-Aided Civil and Infrastructure
Engineering, 24:6, pp. 401-415.
Chi, S., Caldas, C.H., and Kim, D.Y. (2009), “A Methodology for Object Identification and
Tracking in Construction based on Spatial Modeling and Image Matching Techniques,”
Computer-Aided Civil and Infrastructure Engineering, 24:3, pp. 199-211.
Dawood, N, Ahmed, R. and Dean, J. (2007) “Modeling of Precast Concrete Production
Operations and Innovations: A Simulation Approach”. Manubuild Conference, Rotterdam, 25-26
April.
Dawood, N. and Al-Bazi, A. (2009) "Using Genetic Algorithms to Improve Crew Allocation
Process in Labour-Intensive Industries”. The 2009 ASCE Workshop on Computing in Civil
Engineering, Texas, Austin, p166-175.
El-Rayes , K., and Moselhi, O. (2001). Optimizing resource utilization for repetitive construction
projects. Journal of Construction Engineering and Management, Vol. 127, No.1, pp. 18-27
Al-Bazi & Dawood
32
Glover, F., Kelly, J.P., and Laguna, M. (1999), New advances for wedding optimization and
simulation, in Proceedings of the 1999Winter Simulation Conference, 255-260.
Healey, F.J. (2009), Statistics: Tool for social research, (8th ed.), Belmont, CA: Wadsworth
Cengage Learning, USA.
Hegazy, T., ASCE, M. and Kassab, M. (2003). Resource optimization using combined simulation
and genetic algorithms. Journal of Construction Engineering and Management, Volume 129,
Issue 6, pp. 698-705
Hung S.L. and Adeli, H. (1994), "A Parallel Genetic/Neural Network Learning
Algorithm for MIMD Shared Memory Machines", IEEE Transactions on Neural
Networks, Vol. 5, No. 6, pp. 900-909.
Ipsilandis, P.G. (2006). Multi-objective optimization in linear repetitive project scheduling.
Operational Research. An International Journal. Volume 6, Number 3, pp.255-269
Jiang, X. and Adeli, H. (2008), “Neuro-Genetic Algorithm for Nonlinear Active Control
of Highrise Buildings, International Journal for Numerical Methods in Engineering, Vol.
75, No. 8, pp. 770-786.
Kang, M.W., Schonfeld, P., and Yang, N. (2009), Prescreening and Repairing in a
Genetic Algorithm for Highway Alignment Optimization,” Computer-Aided Civil and
Infrastructure Engineering, 24:2, pp. 109-119.
Kim, H. and Adeli, H. (2001), “Discrete cost optimization of composite floors using a floating
point genetic algorithm”, Engineering Optimization, Vol. 33, No. 4, pp. 485-501.
Kumar, A. J. S., Arunadevi, J., Mohan, V. (2009). Intelligent Transport Route Planning Using
Genetic Algorithms in Path Computation Algorithms. European Journal of Scientific Research.
Volume 25, Number 3, pp.463-468
Al-Bazi & Dawood
33
Lee, H., Kim, E., and Park, M. (2007), “A genetic feature weighting scheme for pattern
recognition,” Integrated Computer-Aided Engineering, 14:2, pp. 161-171.
Li, H., Love, P., and Ogunlana, S. (1998). Genetic algorithum compared to nonlinear
optimization for labor and equipment assignment. Building Research and Information, Volume
26, Number 6, pp.322-329
Lu, M., Lam, Hoi-Ching, Tang S.L. (2008). Skilled laborer management in handling concurrent
building projects at multiple sites: the bar benders job scheduling problem. First International
Conference on Construction in Developing Countries (ICCIDC-I), August 4-5, Karachi, Pakistan
Marzouk, M. Hisham Zein El-Dein, and Moheeb El-Said. (2007). Application of Computer
Simulation to Construction of Incremental Launching Bridges. Journal of Civil Engineering and
Management, Volume XIII, Number 1, pp. 27-36.
Marzouk , M., and Moselhi, O. (2004). Multi-objective optimization of earthmoving operations.
Journal of Construction Engineering and Management, Vol. 130, No.1, pp. 105-113
Mathakari, S., Gardoni, P., Agarwal, P., Raich, A., and Haukaas, T. (2007), “Reliability-based
Optimal Design of Electrical Transmission Towers Using Multi-objective Genetic Algorithms,“
Computer-Aided Civil and Infrastructure Engineering, 22:4, pp. 282-292.
Moselhi, O., Alshibani, A. (2007), Crew optimization in planning and control of earthmoving
operations using spatial technologies, Journal of Information Technology in Construction, The
International Council for Research and Innovation in Building and Construction, available at:
http://www.itcon.org/cgi-bin/works/Show?2007_7 (accessed 23 February 2009), Vol. 12 pp.121-
37.
Nassar, K. (2005). Evolutionary optimization of resource allocation in repetitive construction
schedules. Journal of Information Technology in Construction (ITcon), Volume 10, pp.265-273
Rekapalli, P.V., Martínez, J.C., and Kamat, V.R. (2009), “Algorithms for Accurate Three-
Dimensional Scene Graph Updates in High Speed Animations of Simulated Construction
Operations,” Computer-Aided Civil and Infrastructure Engineering, 24:3, pp. 186-198.
Al-Bazi & Dawood
34
Smith, J.F. and ThanhVu H. Nguyen, T.H. (2007), “Autonomous and cooperative robotic
behavior based on fuzzy logic and genetic programming,” Integrated Computer-Aided
Engineering, 14:2, pp. 141-159.
Sarma, K. and Adeli, H. (2000a), "Fuzzy Genetic Algorithm for Optimization of Steel
Structures", Journal of Structural Engineering, ASCE, Vol. 126, No. 5, pp. 596-604.
Sarma, K. and Adeli, H. (2000b), "Fuzzy Discrete Multicriteria Cost Optimization of
Steel Structures", Journal of Structural Engineering, ASCE, Vol. 126, No. 11, pp. 1339-
1347.
Sarma, K.C. and Adeli, H. (2001), “Bi-Level Parallel Genetic Algorithms for
Optimization of Large Steel Structures”, Computer-Aided Civil and Infrastructure
Engineering, 16 (5), pp. 295-304.
Sarma, K.C. and Adeli, H. (2002), “Life-Cycle Cost Optimization of Steel Structures”,
International Journal for Numerical Methods in Engineering, Vol. 55, No. 12, pp. 1451-1462.
Senouci, A.B. and Adeli, H. (2001). Resource Scheduling using Neural Dynamics Model of Adeli
and Park. Journal of Construction Engineering and Management, ASCE, Volume 127, Number 1,
pp. 28-34.
Shi, L. (2000). A new algorithm for stochastic discrete allocation optimization. Journal of discrete
Event Dynamic Systems, Volume 10, Number 3, pp.271-294
Teklu, F. Sumalee, A., and Watling, D. (2007), “A Genetic Algorithm for Optimizing Traffic
Control Signals Considering Routing,” Computer-Aided Civil and Infrastructure Engineering,
22:1, pp. 31-43.
Vlahogianni, E.I., Karlaftis, M.G., and Golias, J.C. (2007) Spatio-Temporal Short-Term Urban
Traffic Flow Forecasting Using Genetically-Optimized Modular Networks,” Computer-Aided
Civil and Infrastructure Engineering, Vol. 22, No. 5, pp. 317-325.
Al-Bazi & Dawood
35
Watkins, M. Mukherjee, A., Onder, N. and Mattila K. G. (2007). Understanding Labor
Productivity as an Emergent Property of Individual and Crew Interactions on a Construction Site.
Proceedings IGLC-15, July, Michigan, USA.
Zhang H., Li H. (2004). Simulation-based optimization for dynamic resource allocation. Journal
of Automation in Construction Volume 13, pp. 409-420.
Zhang X. and Armstrong, M.P. (2005). Using a genetic algorithm to generate alternatives for
multi-objective corridor location problems. Proceedings of the 8th International Geo-
Computation Conference.