AL-BATRA RFI"S SURVEYING S.NO DATE PROJECT DESCRIPTION REV 1 6/29/2010 AL-BATRA Level for Excavation in All Building 0 2 6/29/2010 AL-BATRA Level for Excavation in All Building 1 3 7/21/2010 AL-BATRA Level for Excavation in Main Building & Service Building 0 4 7/21/2010 AL-BATRA Termite Control Under Foundation 0 5 7/1/2010 AL-BATRA Termite Control Under Foundation 1 6 8/7/2010 AL-BATRA Coordinates & Level for Foundation in Main & Service Building 0 7 8/7/2010 AL-BATRA Steel for Foundation in Main Building & Service Building 0 8 8/9/2010 AL-BATRA Surveying + Shuttering Work for Foundation in Main & Service Bldg 0 9 8/11/2010 AL-BATRA Steel for Foundation in Main Building & Service Building 1 10 8/15/2010 AL-BATRA Compaction Test Before Pouring Boundary Wall 0 11 8/24/2010 AL-BATRA Surveying for Column Neck in Main Building & Service Building 0 12 8/24/2010 AL-BATRA Surveying for PCC for Water Tank & Holding Tank 0 13 8/25/2010 AL-BATRA Surveying for Column Neck in Main Building & Service Building 1 14 8/25/2010 AL-BATRA Compaction Test for Water Tank & Holding Tank Before Casting 0 15 8/28/2010 AL-BATRA Compaction Test for Boundary Wall 0 16 8/31/2010 AL-BATRA Compaction Test for Holding Tank,Water Tank and Boundary Wall 1 17 9/2/2010 AL-BATRA Compaction Test for Holding Tank,Water Tank and Boundary Wall 1 18 9/2/2010 AL-BATRA Surveying Work for Boundary Wall,Water Tank and Holding Tank 0 19 9/5/2010 AL-BATRA Termite Control Before Casting 0 20 9/18/2010 AL-BATRA Surveying Foundation Boundary Wall 0 21 9/28/2010 AL-BATRA Axis for Boundary Wall 0 22 9/28/2010 AL-BATRA Axis for Boundary Wall 1 23 10/11/2010 AL-BATRA Coordinates for Water Tank & Holding Tank 0 24 10/13/2010 AL-BATRA Axis for Column Neck Fence 0 25 11/3/2010 AL-BATRA Level for Slab in Holding & Water Tank 0 26 11/10/2010 AL-BATRA First Layer of Compaction around Foundation 0 27 11/21/2010 AL-BATRA First Layer of Back Filling Around Foundation 0 28 11/27/2010 AL-BATRA Compaction Test for 1st Layer around Foundation 0 29 11/28/2010 AL-BATRA Compaction Test for 2nd Layer around Foundation 0

AL-BATRA

Embed Size (px)

Citation preview

Page 1: AL-BATRA

AL-BATRA RFI"SSURVEYING

S.NO DATE PROJECT DESCRIPTION REV STATUS1 6/29/2010 AL-BATRA Level for Excavation in All Building 0 REJECT2 6/29/2010 AL-BATRA Level for Excavation in All Building 1 APPROVED3 7/21/2010 AL-BATRA Level for Excavation in Main Building & Service Building 0 APPROVED4 7/21/2010 AL-BATRA Termite Control Under Foundation 0 REJECT5 7/1/2010 AL-BATRA Termite Control Under Foundation 1 REJECT6 8/7/2010 AL-BATRA Coordinates & Level for Foundation in Main & Service Building 0 REJECT7 8/7/2010 AL-BATRA Steel for Foundation in Main Building & Service Building 0 REJECT8 8/9/2010 AL-BATRA Surveying + Shuttering Work for Foundation in Main & Service Bldg 0 APPROVED9 8/11/2010 AL-BATRA Steel for Foundation in Main Building & Service Building 1 APPROVED

10 8/15/2010 AL-BATRA Compaction Test Before Pouring Boundary Wall 0 REJECT11 8/24/2010 AL-BATRA Surveying for Column Neck in Main Building & Service Building 0 REJECT12 8/24/2010 AL-BATRA Surveying for PCC for Water Tank & Holding Tank 0 REJECT13 8/25/2010 AL-BATRA Surveying for Column Neck in Main Building & Service Building 1 APPROVED14 8/25/2010 AL-BATRA Compaction Test for Water Tank & Holding Tank Before Casting 0 REJECT15 8/28/2010 AL-BATRA Compaction Test for Boundary Wall 0 REJECT16 8/31/2010 AL-BATRA Compaction Test for Holding Tank,Water Tank and Boundary Wall 1 REJECT17 9/2/2010 AL-BATRA Compaction Test for Holding Tank,Water Tank and Boundary Wall 1 APPROVED18 9/2/2010 AL-BATRA Surveying Work for Boundary Wall,Water Tank and Holding Tank 0 APPROVED19 9/5/2010 AL-BATRA Termite Control Before Casting 0 APPROVED20 9/18/2010 AL-BATRA Surveying Foundation Boundary Wall 0 APPROVED21 9/28/2010 AL-BATRA Axis for Boundary Wall 0 REJECT22 9/28/2010 AL-BATRA Axis for Boundary Wall 1 APPROVED23 10/11/2010 AL-BATRA Coordinates for Water Tank & Holding Tank 0 APPROVED24 10/13/2010 AL-BATRA Axis for Column Neck Fence 0 APPROVED25 11/3/2010 AL-BATRA Level for Slab in Holding & Water Tank 0 APPROVED26 11/10/2010 AL-BATRA First Layer of Compaction around Foundation 0 REJECT27 11/21/2010 AL-BATRA First Layer of Back Filling Around Foundation 0 REJECT28 11/27/2010 AL-BATRA Compaction Test for 1st Layer around Foundation 0 APPROVED29 11/28/2010 AL-BATRA Compaction Test for 2nd Layer around Foundation 0 APPROVED

Page 2: AL-BATRA

30 11/30/2010 AL-BATRA Compaction Test for 3rd Layer around Foundation 0 APPROVED31 12/1/2010 AL-BATRA Compaction Test for 4rd Layer around Foundation 0 APPROVED32 12/2/2010 AL-BATRA Compaction Test for 3rd Layer of Boundary Wall around Foundation 0 APPROVED33 12/4/2010 AL-BATRA Compaction Test for 5th Layer around Foundation 0 APPROVED34 12/5/2010 AL-BATRA Compaction Test for 6th Layer around Foundation 0 APPROVED35 12/7/2010 AL-BATRA Compaction Test for 7th Layer around Foundation 0 APPROVED36 12/9/2010 AL-BATRA Compaction Test for 8th Layer around Foundation 0 APPROVED37 12/11/2010 AL-BATRA Compaction Test for 9th Layer around Foundation 0 APPROVED38 12/15/2010 AL-BATRA Level of Slab for Water Tank 0 APPROVED39 12/15/2010 AL-BATRA Level of Slab for Holding Tank 0 APPROVED40 12/15/2010 AL-BATRA Level of Blinding for Grade Beam in Main,Service Building & Boundary Wall 0 APPROVED41 12/20/2010 AL-BATRA Termite Control Under Grade Beam for Main,Service Bldg and Boundary Wall. Back Side and Right Side 0 APPROVED

42 12/25/2010 AL-BATRA Termite Control Under Grade Beam for Main Building and Service Building 0 APPROVED43 12/28/2010 AL-BATRA Axis & Coordinate for Boundary Wall 0 APPROVED44 12/28/2010 AL-BATRA Axis, Level and Coordinate for Grade Beam in Main & Service Building 0 APPROVED45 1/4/2011 AL-BATRA Axis and Dimension for Column Main Building & Service Building 0 APPROVED46 1/9/2011 AL-BATRA Axis and Level For Boundary Wall 0 APPROVED47 1/9/2011 AL-BATRA Dimension for Columns in Main,Service Building & Boundary Wall 0 APPROVED48 1/10/2011 AL-BATRA Level for Staircase for Main Building 0 APPROVED49 1/18/2011 AL-BATRA Surveying for First Floor Slab Main Building 0 REJECT50 1/22/2011 AL-BATRA Surveying for Roof Floor Slab Service Building 0 APPROVED51 1/23/2011 AL-BATRA Level for Main Building Slab 0 APPROVED52 1/25/2011 AL-BATRA Repairing of Surface in Water Tank & Holding Tank 0 REJECT53 1/25/2011 AL-BATRA Level for Roof Slab of Service Building 0 APPROVED54 1/26/2011 AL-BATRA Repairing of Surface in Water Tank & Holding Tank 1 APPROVED55 1/27/2011 AL-BATRA Axis for Columns of First Floor Main Building 0 APPROVED56 1/30/2011 AL-BATRA Repairing Surface of Holding Tank 2 APPROVED57 2/3/2011 AL-BATRA Repairing External Surface of Holding Tank & Water Tank 0 REJECT58 2/6/2011 AL-BATRA Surveying for Roof Slab Main Building 0 APPROVED59 2/6/2011 AL-BATRA Repairing External Surface of Holding Tank & Water Tank 1 REJECT60 2/8/2011 AL-BATRA Repairing External Surface of Holding Tank 1 APPROVED61 2/9/2011 AL-BATRA Surveying for Roof of Main Building 0 APPROVED

Page 3: AL-BATRA

62 2/24/2011 AL-BATRA Axis & Level for Generator Room and Boundary Wall Foundation 0 APPROVED63 2/24/2011 AL-BATRA Backfilling & Compaction Test under Slab on Grade in Service Building 0 APPROVED64 2/26/2011 AL-BATRA Backfilling & Compaction Test for Main Building 0 APPROVED65 2/26/2011 AL-BATRA Backfilling & Compaction Test Around Water Tank First Layer 0 APPROVED66 2/26/2011 AL-BATRA Backfilling & Compaction Test Around Water Tank Second Layer 0 APPROVED67 2/26/2011 AL-BATRA Backfilling & Compaction Test Around Water Tank Third Layer 0 APPROVED68 2/26/2011 AL-BATRA Backfilling & Compaction Test Around Water Tank Fourth Layer 0 APPROVED69 2/28/2011 AL-BATRA Footing & Neck Column for Generator Room 0 APPROVED70 2/28/2011 AL-BATRA Footing Boundary Wall 0 APPROVED71 3/5/2011 AL-BATRA Termite Control Under Slab on Grade in Main Building 0 APPROVED72 3/5/2011 AL-BATRA Termite Control Under Slab on Grade in Service Building 0 APPROVED73 3/17/2011 AL-BATRA Backfilling & Compaction Test for Boundary Wall 0 APPROVED74 3/19/2011 AL-BATRA 2nd Layer Backfilling & Compaction Test in fornt side Boundary Wall 0 APPROVED75 3/19/2011 AL-BATRA 3rd Layer Backfilling & Compaction Test in fornt side Boundary Wall 0 REJECT76 3/21/2011 AL-BATRA Level for Roof Slab of Holding Tank 0 APPROVED77 3/21/2011 AL-BATRA First Layer Backfilling & Compaction Test in Fornt side Boundary Wall 1 APPROVED78 3/23/2011 AL-BATRA 2nd Layer Backfilling & Compaction Test in Fornt side Boundary Wall 1 APPROVED79 3/23/2011 AL-BATRA 3rd Layer Backfilling & Compaction Test in Fornt side Boundary Wall 1 APPROVED80 3/23/2011 AL-BATRA Testing for Water in Holding Tank 0 APPROVED81 3/28/2011 AL-BATRA Dimension for Fornt Side Boundary Wall 0 APPROVED82 4/6/2011 AL-BATRA Dimension Axis for Boundary Wall Column 0 APPROVED83 4/9/2011 AL-BATRA Protection Layer for Holding Tank 0 APPROVED84 4/9/2011 AL-BATRA 1st Layer Backfilling & Compaction Test Around Holding Tank 0 APPROVED85 4/9/2011 AL-BATRA 2nd Layer Backfilling & Compaction Test Around Holding Tank 0 APPROVED86 4/10/2011 AL-BATRA 3rd Layer Backfilling & Compaction Test Around Holding Tank 0 APPROVED87 4/10/2011 AL-BATRA 4th Layer Backfilling & Compaction Test Around Holding Tank 0 APPROVED88 4/10/2011 AL-BATRA 5th Layer Backfilling & Compaction Test Around Holding Tank 0 REJECT89 4/11/2011 AL-BATRA Repairing for Surface in 2nd Holding Tank 0 APPROVED90 4/13/2011 AL-BATRA 1st Line Masnory Block Work in Boundary Wall 1 REJECT91 4/13/2011 AL-BATRA 2nd Layer Epoxy Water Proofing in Holding Tank 0 APPROVED92 4/18/2011 AL-BATRA Plates in Column in fornt Side Boundary Wall 0 REJECT93 4/28/2011 AL-BATRA Level for Generator Room Slab 0 APPROVED

Page 4: AL-BATRA

94 6/14/2011 AL-BATRA Shmedit Hummer Test for Electrical Room 0 REJECT95 7/9/2011 AL-BATRA Level for Inverted Beam of Boundary Wall 0 APPROVED96 7/9/2011 AL-BATRA Level for Inverted Beam of Parapet Main Building & Service Building 0 APPROVED97 7/19/2011 AL-BATRA Level & Coordinate for Drainage Manhole 0 APPROVED

Page 5: AL-BATRA

AL-BATRA RFI"SCONCRETE

S.NO DATE PROJECT DESCRIPTION REV STATUS1 7/21/2010 AL-BATRA Level for Blending Concrete in Main Building & Service Building 0 APPROVED2 7/21/2010 AL-BATRA Casting of PCC for Main Building & Service Building 0 REJECT3 8/7/2010 AL-BATRA Casting of PCC for Holding Tank & Water Tank 0 REJECT4 8/9/2010 AL-BATRA Coordinates & Level for Holding Tank & Water Tank 0 REJECT5 8/9/2010 AL-BATRA Shuttering for Footing in Main Building & Service Building 0 APPROVED6 8/11/2010 AL-BATRA Casting of Foundation in Main Building & Service Building 0 APPROVED7 8/15/2010 AL-BATRA Casting of Foundation in Main Building & Service Building 0 REJECT8 8/15/2010 AL-BATRA Casting of Foundation in Main Building & Service Building 2 APPROVED9 8/18/2010 AL-BATRA Reinforcement for Column Neck in Main Building & Service Building 0 APPROVED

10 8/24/2010 AL-BATRA Shuttering for Columns Neck in Main Building & Service Building 0 REJECT11 8/24/2010 AL-BATRA Shuttering for Water Tank & Holding Tank 0 REJECT12 8/25/2010 AL-BATRA Shuttering for Columns Neck in Main Building & Service Building 1 REJECT13 8/30/2010 AL-BATRA Shuttering for Columns Neck in Main Building & Service Building 2 APPROVED14 9/2/2010 AL-BATRA Form Work for Boundary Wall,Water Tank and Holding Tank 0 REJECT15 9/4/2010 AL-BATRA Form Work for Boundary Wall,Water Tank and Holding Tank 1 APPROVED16 9/5/2010 AL-BATRA Casting for Column Neck in Main & Service Building 0 APPROVED17 9/5/2010 AL-BATRA Blinding Foundation for Boundary Wall 0 APPROVED18 9/5/2010 AL-BATRA Blinding for Water Tank & Holding Tank 0 APPROVED19 9/20/2010 AL-BATRA Shuttering & Steel for Boundary Wall 0 APPROVED20 9/21/2010 AL-BATRA Casting Foundation for Boundary Wall 0 REJECT21 9/30/2010 AL-BATRA Steel for Remaining Footing Boundary Wall West Side Continous Footin 0 REJECT22 9/30/2010 AL-BATRA Shuttering for Remaining Footing Boundary Wall West Side Continous Footing 0 REJECT23 10/4/2010 AL-BATRA Steel for Remaining Footing Boundary Wall West Side Continous Footing 1 APPROVED24 10/4/2010 AL-BATRA Shuttering for Remaining Footing Boundary Wall West Side Continous Footing 1 APPROVED25 10/9/2010 AL-BATRA Casting of PCC Screed above Water Proofing Membrane in Water & Holding Tank 0 REJECT26 10/9/2010 AL-BATRA Casting of Foundation for Boundary Wall 0 REJECT27 10/10/2010 AL-BATRA Casting of PCC Screed above Water Proofing Membrane in Water & Holding Tank 1 APPROVED28 10/10/2010 AL-BATRA Casting of Foundation for Boundary Wall 1 APPROVED29 10/14/2010 AL-BATRA Steel for Foundation for Water & Holding Tank 0 REJECT

Page 6: AL-BATRA

30 10/14/2010 AL-BATRA Steel for Boundary Wall 0 APPROVED31 10/17/2010 AL-BATRA Shuttering for Water & Holding Tank 0 REJECT32 10/18/2010 AL-BATRA Shuttering for Water & Holding Tank 1 APPROVED33 10/23/2010 AL-BATRA Shuttering for Boundary Wall 0 APPROVED34 10/27/2010 AL-BATRA Casting for Foundation For Water & Holding Tank 0 APPROVED35 10/27/2010 AL-BATRA Casting Column Neck Boundary Wall 0 APPROVED36 10/27/2010 AL-BATRA Casting Boundary Wall (Wall) 0 APPROVED37 11/2/2010 AL-BATRA Steel for Walls of Holding & Water Tank 0 REJECT38 11/4/2010 AL-BATRA Repairing Walls for Boundary Walls 0 APPROVED39 11/8/2010 AL-BATRA Steel for Water & Holding Tank Walls 1 APPROVED40 11/9/2010 AL-BATRA Shuttering for Water Tank Walls 0 APPROVED41 11/11/2010 AL-BATRA Shuttering for Holding Tank Walls 0 APPROVED42 11/11/2010 AL-BATRA Casting for Walls of Holding Tank & Water Tank 0 APPROVED43 11/20/2010 AL-BATRA Tie Rod Holes after Filling Neto Mortar Outside & Inside Walls of Water & Holding Tank. 0 REJECT44 12/15/2010 AL-BATRA Shuttering of Blinding for Grade Beam in Main,Service Building &Boundary Wal 0 APPROVED45 12/15/2010 AL-BATRA Steel for Slab of Water Tank 0 APPROVED46 12/15/2010 AL-BATRA Steel for Slab of Holding Tank 0 APPROVED47 12/16/2010 AL-BATRA Shuttering for Water Tank 0 APPROVED48 12/16/2010 AL-BATRA Shuttering for Holding Tank 0 APPROVED49 12/20/2010 AL-BATRA Casting Blinding for Grade Beam Main,Service Building and Boundary Wall. Back & Right Side 0 APPROVED50 12/21/2010 AL-BATRA Casting for Water Tank & Holding Tank Slab 0 APPROVED51 12/22/2010 AL-BATRA Casting Blinding for Grade Beam Main,Service Building and Boundary Wall. Back & Right Side 1 REJECT52 12/25/2010 AL-BATRA Casting Blinding for Grade Beam Main Building and Service Building 0 APPROVED53 12/25/2010 AL-BATRA Steel for Grade Beam of Boundary Wall 0 APPROVED54 12/28/2010 AL-BATRA Shuttering for Grade Beam of Boundary Wall 0 REJECT55 12/28/2010 AL-BATRA Steel for Grade Beam of Main Building 0 REJECT56 12/28/2010 AL-BATRA Steel for Grade Beam of Service Building 0 REJECT57 12/28/2010 AL-BATRA Shuttering for Grade Beam of Main Building 0 APPROVED58 12/28/2010 AL-BATRA Shuttering for Grade Beam of Service Building 0 APPROVED59 12/29/2010 AL-BATRA Casting Grade Beam for Main, Service Building and Boundary Wall 0 REJECT60 12/30/2010 AL-BATRA Shuttering for Grade Beam of Boundary Wall 1 APPROVED61 12/30/2010 AL-BATRA Steel for Grade Beam of Main Buildin 1 APPROVED

Page 7: AL-BATRA

62 12/30/2010 AL-BATRA Steel for Grade Beam of Service Building 1 APPROVED63 12/30/2010 AL-BATRA Casting of Boundary Wall 1 APPROVED64 12/30/2010 AL-BATRA Casting Grade Beam for Service Building & Main Building 1 APPROVED65 1/2/2011 AL-BATRA Casting Grade Beam for Service Building & Main Building 2 APPROVED66 1/6/2011 AL-BATRA Steel for Ground Floor Columns for Main Building 0 APPROVED67 1/6/2011 AL-BATRA Steel for Ground Floor Columns for Service Building 0 APPROVED68 1/6/2011 AL-BATRA Steel for Ground Floor Columns for Boundary Wall 0 APPROVED69 1/9/2011 AL-BATRA Shuttering for Ground Floor Columns for Boundary Wall 0 APPROVED70 1/9/2011 AL-BATRA Shuttering for Ground Floor Columns for Service Building 0 APPROVED71 1/9/2011 AL-BATRA Shuttering for Ground Floor Columns for Main Building 0 APPROVED72 1/9/2011 AL-BATRA Shuttering for Staircase Main Building 0 APPROVED73 1/9/2011 AL-BATRA Steel for Staircase Main Building 0 APPROVED74 1/11/2011 AL-BATRA Casting Columns in Main Building , Service Building and Boundary Wall 0 APPROVED75 1/18/2011 AL-BATRA Shuttering for First Floor Slab in Main Building 0 APPROVED76 1/23/2011 AL-BATRA Steel for Main Building Slab 0 APPROVED77 1/23/2011 AL-BATRA Shuttering for Service Building Slab 0 APPROVED78 1/25/2011 AL-BATRA Steel for Slab in Service Building 0 APPROVED79 1/26/2011 AL-BATRA Casting First Floor Slab of Main Building 0 APPROVED80 1/26/2011 AL-BATRA Casting Roof Slab of Service Building 0 APPROVED81 1/29/2011 AL-BATRA Steel for Columns of Second Floor Main Building 0 APPROVED82 1/30/2011 AL-BATRA Shuttering for Columns of Second Floor Main Building 0 APPROVED83 1/31/2011 AL-BATRA Casting Columns of Second Floor in Main Building 0 REJECT84 2/2/2011 AL-BATRA Casting Columns of Second Floor in Main Building 1 APPROVED85 2/6/2011 AL-BATRA Shuttering for Second Slab in Main Building 0 APPROVED86 2/10/2011 AL-BATRA Steel for Second Slab in Main Building 0 APPROVED87 2/12/2011 AL-BATRA Casting for Second Slab in Main Building 0 APPROVED88 2/24/2011 AL-BATRA Steel for Footing of Front Elevation Boundary Wall 0 APPROVED89 2/24/2011 AL-BATRA Steel for Footing of Electrical Room 0 APPROVED90 2/24/2011 AL-BATRA Shuttering for Footing in Elevation Pipe of Boundary Wall 0 APPROVED91 2/24/2011 AL-BATRA Shuttering for Footing of Electrical Room 0 APPROVED92 2/24/2011 AL-BATRA Shuttering for Blinding in Second Holding Tank 0 APPROVED93 2/26/2011 AL-BATRA Casting for Footing of Boundary Wall 0 APPROVED

Page 8: AL-BATRA

94 2/26/2011 AL-BATRA Casting for Generator Room Footing 0 APPROVED95 2/26/2011 AL-BATRA Casting for Blinding of Holding Tank 0 APPROVED96 2/28/2011 AL-BATRA Steel for Neck Column of Front Elevation of Boundary Wall 0 APPROVED97 2/28/2011 AL-BATRA Steel for Neck Column of Electrical Room 0 APPROVED98 3/1/2011 AL-BATRA Shuttering for Neck Column of Electrical Room 0 APPROVED99 3/1/2011 AL-BATRA Shuttering for Neck Column of Front Side of Boundary Wall 0 APPROVED

100 3/5/2011 AL-BATRA Casting Blinding Concrete under Slab on Grade in Main Building 0 APPROVED101 3/5/2011 AL-BATRA Casting Blinding Concrete under Slab on Grade in Service Building 0 APPROVED102 3/5/2011 AL-BATRA Casting Screed Concrete in Second Holding Tank 0 APPROVED103 3/5/2011 AL-BATRA Casting Neck Column in Front Side of Boundary Wall 0 APPROVED104 3/5/2011 AL-BATRA Casting Neck Column in Electrical Room 0 APPROVED105 3/5/2011 AL-BATRA Casting Screed Concrete for Upper Water Tank 0 APPROVED106 3/8/2011 AL-BATRA Steel for slab grade in service building 0 APPROVED107 3/8/2011 AL-BATRA Steel for slab grade in Main Building 0 APPROVED108 3/8/2011 AL-BATRA Steel for foundation in second holding tank 0 APPROVED109 3/9/2011 AL-BATRA Casting Slab on Grade in Main building 0 APPROVED110 3/9/2011 AL-BATRA Casting Slab on Grade in Service Building 0 APPROVED111 3/9/2011 AL-BATRA Casting Foundation in Holding Tank 0 APPROVED112 3/13/2011 AL-BATRA Steel for wall Holding Tank 0 APPROVED113 3/16/2011 AL-BATRA Shuttering for wall in Second Holding Tank 0 APPROVED114 3/16/2011 AL-BATRA Casting for wall in Second Holding Tank 0 APPROVED115 3/21/2011 AL-BATRA Steel for Slab in Holding Tank 0 APPROVED116 3/23/2011 AL-BATRA Casting for Roof Slab in Holding Tank 0 APPROVED117 3/27/2011 AL-BATRA Steel for Grade Beam in Fornt Side Boundary Wall 0 REJECT118 3/28/2011 AL-BATRA Steel for Grade Beam in Fornt Side Boundary Wall 1 APPROVED119 3/29/2011 AL-BATRA Shuttering for Grade Beam in Fornt Side Boundary Wall 0 APPROVED120 3/30/2011 AL-BATRA Casting for Grade Beam in Fornt Side Boundary Wall 0 REJECT121 3/30/2011 AL-BATRA Steel for Trench in Electrical Room 0 APPROVED122 3/31/2011 AL-BATRA Casting for Trench in Electrical Room 0 APPROVED123 3/31/2011 AL-BATRA Casting for Grade Beam in Front Side Boundary Wall 1 APPROVED124 4/6/2011 AL-BATRA Steel of Column in Fornt side Boundary Wall 0 APPROVED125 4/10/2011 AL-BATRA Steel for Wall of Trench 0 APPROVED

Page 9: AL-BATRA

126 4/10/2011 AL-BATRA Shuttering for Wall of Trench 0 APPROVED127 4/17/2011 AL-BATRA Shuttering for Grade Beam of Electrical Room 0 APPROVED128 4/17/2011 AL-BATRA Steel for Grade Beam of Electrical Room 0 APPROVED129 4/18/2011 AL-BATRA Shuttering for Column in fornt Side Boundary Wall 0 APPROVED130 4/18/2011 AL-BATRA Casting for Grade Beam of Electrical Room 0 REJECT131 4/23/2011 AL-BATRA Steel for Columns of Electrical Room 0 APPROVED132 4/23/2011 AL-BATRA Shuttering for Columns of Electrical Room 0 APPROVED136 4/24/2011 AL-BATRA Casting Columns of Electrical Room 0 APPROVED137 4/28/2011 AL-BATRA Steel for Roof Slab of Electrical Room 0 APPROVED138 4/28/2011 AL-BATRA Shuttering for Roof Slab of Electrical Room 0 APPROVED139 5/8/2011 AL-BATRA Casting for Roof Slab of Electrical Room 0 REJECT140 7/9/2011 AL-BATRA Shuttering of Inverted Beam of Parapet Main Building & Service Building 0 APPROVED141 7/9/2011 AL-BATRA Steel of Inverted Beam of Parapet Main Building & Service Building 0 APPROVED142 7/9/2011 AL-BATRA Steel for Inverted Beam of Boundary Wall 0 APPROVED143 7/12/2011 AL-BATRA Casting of Inverted Beam of Parapet Main Building & Service Building 0 APPROVED144 7/12/2011 AL-BATRA Casting for Inverted Beam of Boundary Wall 0 APPROVED145 8/2/2011 AL-BATRA Steel for Manholes in Main Building 0 APPROVED146 8/21/2011 AL-BATRA Steel for Manholes 0 APPROVED147 8/21/2011 AL-BATRA Shuttering for Manholes 0 APPROVED148 10/20/2011 AL-BATRA Checking for Slope of Foam Concrete in Main Building & Service Building 0 APPROVED149 AL-BATRA Steel for Assembly Area Between Main Building & Service Pavement & Steps

Page 10: AL-BATRA
Page 11: AL-BATRA

AL-BATRA RFI"SMECHANICAL

S.NO DATE PROJECT DESCRIPTION REV STATUS1 11/7/2010 AL-BATRA Water Tank Mechanical Work 0 APPROVED2 11/7/2010 AL-BATRA Holding Tank Mechanical Work 0 APPROVED3 12/15/2010 AL-BATRA Ventilation Pipes in Water & Holding Tank 0 APPROVED4 12/28/2010 AL-BATRA Roof Drain for Main & Service Building 0 REJECT5 12/30/2010 AL-BATRA Roof Drain for Main & Service Building 0 APPROVED6 1/24/2011 AL-BATRA Mechanical Work for Ground Floor Slab Main Building 1 APPROVED7 1/24/2011 AL-BATRA Mechanical Work for Ground Floor Slab Service Building 1 APPROVED8 2/9/2011 AL-BATRA Mechanical Work for Roof Floor Main Building 1 APPROVED9 2/14/2011 AL-BATRA Mechanical Work Under Slab on Grade for Service Building 0 APPROVED

10 2/19/2011 AL-BATRA Internal Work in Main Building 0 REJECT11 2/24/2011 AL-BATRA Internal Work in Main Building 1 APPROVED12 2/28/2011 AL-BATRA Sleeves for Main Building 0 APPROVED13 3/8/2011 AL-BATRA Work Under slab Concrete (gully trap fixing ) 0 APPROVED14 3/14/2011 AL-BATRA Mechanical Work in Holding Tank 0 REJECT15 3/22/2011 AL-BATRA First Floor Bathrooms mechanical work 0 REJECT16 4/10/2011 AL-BATRA First Floor Bathrooms mechanical work 1 REJECT17 4/28/2011 AL-BATRA Electrical Room Roof Drain 0 APPROVED18 8/21/2011 AL-BATRA Ground Floor Water Supply Hot & Cold Water Main Building 0 REJECT19 9/21/2011 AL-BATRA External Work Piping (Manholes) 0 APPROVED20 10/9/2011 AL-BATRA Mechanical Work for Ground Floor Water Supply Lines and AC Drain Main Building 0 APPROVED21 10/15/2011 AL-BATRA Mechanical Work Roof Drain Fixation On The Roof 0 APPROVED22 10/22/2011 AL-BATRA AC Drainage Pipe Network Installation on Ground Floor Main Building 0 APPROVED23 10/22/2011 AL-BATRA AC Drainage Pipe Network Installation on Ground Floor Service Building 0 REJECT24 10/22/2011 AL-BATRA External Water Supply Piping Network Installation 0 REJECT25 11/19/2011 AL-BATRA Mechanical Work for Drainage Pipe Layout Backside of Service Building 0 REJECT26 12/11/2012 AL-BATRA Drainage Pipe installation (External) at the Back of Service Building Going to Holding Tank2 0 APPROVED

27 12/29/2011 AL-BATRA Fuel Tank Black steel piping connection 0 REJECT28 12/29/2011 AL-BATRA High level water supply pipes(Hot&Cold) prior to ceiling closing in Ground floor Main Bldg 0 REJECT29 12/29/2011 AL-BATRA High level water supply pipes (Hot&Cold) prior to ceiling closings in First floor Main Bldg 0 REJECT

Page 12: AL-BATRA

30 12/29/2011 AL-BATRA High level water supply pipes (Hot&Cold) prior to ceiling closings in Ground floor Service Building 0 REJECT

Page 13: AL-BATRA

AL-BATRA RFI"SELECTRICAL

S.NO DATE PROJECT DESCRIPTION REV STATUS1 8/7/2010 AL-BATRA Earthing Work in Footing & Neck Column in Main & Service Bldg 0 REJECT2 8/9/2010 AL-BATRA Earthing Work in Footing & Neck Column in Main & Service Bldg 1 APPROVED3 10/19/2010 AL-BATRA Electrical Work For Boundary Wall 0 REJECT4 10/20/2010 AL-BATRA Electrical Work For Boundary Wall 1 APPROVED5 11/8/2010 AL-BATRA 3x63 UPVC Pipe & 2x25mm for Electrical Work in Pump Room 0 APPROVED6 11/13/2010 AL-BATRA Foundation Grounding Network 0 APPROVED7 12/26/2010 AL-BATRA Boundary Wall Lights 0 APPROVED8 1/25/2011 AL-BATRA First Fix Fire Alarm System for Ground Floor Slab Main Building 0 APPROVED9 1/25/2011 AL-BATRA First Fix AV System for Ground Floor Slab Main Building 0 APPROVED

10 1/25/2011 AL-BATRA First Fix Security System for Ground Floor Slab Main Building 0 APPROVED11 1/25/2011 AL-BATRA First Fix Communication System for Ground Floor Slab Main Building 0 APPROVED12 1/25/2011 AL-BATRA First Fix Lighting System for Ground Floor Slab Main Building 0 APPROVED13 1/26/2011 AL-BATRA First Fix Lighting System in the Slab of Service Building 0 APPROVED14 1/26/2011 AL-BATRA First Fix Fire Alarm System in the Slab of Service Building 0 APPROVED15 1/26/2011 AL-BATRA First Fix A V System in the Slab of Service Building 0 APPROVED16 1/26/2011 AL-BATRA First Fix Communication System in the Slab of Service Building 0 APPROVED17 1/26/2011 AL-BATRA First Fix Security System in the Slab of Service Building 0 APPROVED18 2/10/2011 AL-BATRA First Fix Fire Alarm System For First Floor Slab of Main Building 0 APPROVED19 2/10/2011 AL-BATRA First Fix AV System For First Floor Slab of Main Building 0 APPROVED20 2/10/2011 AL-BATRA First Fix Security System For First Floor Slab of Main Building 0 APPROVED21 2/10/2011 AL-BATRA First Fix Communication System For First Floor Slab of Main Building 0 APPROVED22 2/10/2011 AL-BATRA First Fix Power System For First Floor Slab of Main Building 0 APPROVED23 2/10/2011 AL-BATRA First Fix Lighting System For First Floor Slab of Main Building 0 APPROVED24 2/22/2011 AL-BATRA Electrical Main UPVC Pipes 0 REJECT25 2/24/2011 AL-BATRA Electrical Main UPVC Pipes 0 APPROVED26 3/31/2011 AL-BATRA Extension for Conduct in Boundary Wall 0 APPROVED27 8/20/2011 AL-BATRA First Fix Fire Alarm System in Block Wall Ground Floor Service Building 0 APPROVED28 8/20/2011 AL-BATRA First Fix Security System in Block Wall Ground Floor Service Building 0 APPROVED29 8/20/2011 AL-BATRA First Fix Communication System in Block Wall Ground Floor Service Bldg 0 APPROVED

Page 14: AL-BATRA

30 8/20/2011 AL-BATRA First Fix Power System in Block Wall Ground Floor Service Building 0 APPROVED31 8/20/2011 AL-BATRA First Fix AC Power System in Block Wall Ground Floor Service Building 0 APPROVED32 8/20/2011 AL-BATRA First Fix Lighting System in Block Wall Ground Floor Service Building 0 APPROVED33 9/19/2011 AL-BATRA Parapet Light in Main Building Roof Floor 0 APPROVED34 9/19/2011 AL-BATRA Parapet Power Socket in Main Building Roof Floor 0 APPROVED35 9/19/2011 AL-BATRA AC Isolator in Roof Floor Main Building 0 REJECT36 9/19/2011 AL-BATRA First Fix for First Floor Lighting System in Block Walls 0 APPROVED37 9/19/2011 AL-BATRA First Fix for First Floor Power Socket in Block Walls 0 APPROVED38 9/19/2011 AL-BATRA First Fix for First Floor AC Power System in Block Walls 0 APPROVED39 9/19/2011 AL-BATRA First Fix for First Floor Fire Alarm System in Block Walls 0 APPROVED40 9/19/2011 AL-BATRA First Fix for First Floor AV System in Block Walls 0 APPROVED41 9/19/2011 AL-BATRA First Fix for First Floor Communication System in Block Walls 0 APPROVED42 9/19/2011 AL-BATRA First Fix for First Floor Security System in Block Walls 0 APPROVED43 10/9/2011 AL-BATRA First Fix for Lighting System in Block Wall in Ground Floor Main Building 0 APPROVED44 10/9/2011 AL-BATRA First Fix for AV System in Block Wall in Ground Floor Main Building 0 APPROVED45 10/9/2011 AL-BATRA First Fix for AC System in Block Wall in Ground Floor Main Building 0 APPROVED46 10/9/2011 AL-BATRA First Fix for Security System in Block Wall in Ground Floor Main Building 0 APPROVED47 10/9/2011 AL-BATRA First Fix for Communication System in Block Wall in Ground Floor Main Bldg 0 APPROVED48 10/9/2011 AL-BATRA First Fix for Power System in Block Wall in Ground Floor Main Building 0 APPROVED49 10/9/2011 AL-BATRA First Fix for Fire Alarm System in Block Wall in Ground Floor Main Building 0 APPROVED50 10/15/2011 AL-BATRA Looping for AC System in Roof Floor Main Building 0 APPROVED51 10/15/2011 AL-BATRA Looping for Parapet Light System in Roof Floor Main Building 0 APPROVED52 10/15/2011 AL-BATRA Looping for Power System in Roof Floor Main Building 0 APPROVED53 10/19/2011 AL-BATRA Looping for Power System in First Floor Main Building 0 APPROVED54 10/21/2011 AL-BATRA Power System Ground Floor Service Building Electrical Piping on Floor Slab Prior for Concrete Screed 0 APPROVED55 10/21/2011 AL-BATRA Power System First Floor Main Building Electrical Piping on Floor Slab Prior for Concrete Screed 0 APPROVED56 11/12/2011 AL-BATRA Electrical & Low Current Manholes in Piping Instalation Layout in Between Main Bldgg & Generator Room Manholes 0 APPROVED

57 11/12/2011 AL-BATRA Power System for First Fix Installation (Boxing & Conduiting) for Generator Room 0 APPROVED58 11/12/2011 AL-BATRA Lighting System for First Fix Installation (Boxing & Conduiting) for Generator Room 0 APPROVED59 11/12/2011 AL-BATRA AC System for First Fix Installation (Boxing & Conduiting) for Generator Room 0 APPROVED60 11/12/2011 AL-BATRA Fire Alarm System for First Fix Installation (Boxing & Conduiting) for Generator Room 0 APPROVED61 11/12/2011 AL-BATRA Communication System for First Fix Installation (Boxing & Conduiting) for Generator Room 0 APPROVED

Page 15: AL-BATRA

62 11/12/2011 AL-BATRA Security System for First Fix Installation (Boxing & Conduiting) for Generator Room 0 APPROVED63 12/29/2011 AL-BATRA AV System Cables for all Rooms prior to Ceiling closings in Ground floor Main Building 0 APPROVED64 12/29/2011 AL-BATRA Fire Alarm System Cables for all Rooms prior to Ceiling closings in Ground floor Main Bldg 0 APPROVED65 12/29/2011 AL-BATRA Communication System Cables for all Rooms prior to Ceiling closings in Ground floor Main Bldg 0 APPROVED66 12/29/2011 AL-BATRA Secrity System Cables for all Rooms prior to Ceiling closings in Ground floor Main Bldg 0 APPROVED67 12/29/2011 AL-BATRA Lighting System Cables for all Rooms prior to Ceiling closings in Ground floor Main Bldg 0 APPROVED68 12/29/2011 AL-BATRA Lighting System Cables for all Rooms prior to Ceiling closings in First floor Main Building 0 APPROVED69 12/29/2011 AL-BATRA AV System Cables for all Rooms prior to Ceiling closings in First floor Main Building 0 APPROVED70 12/29/2011 AL-BATRA Fire Alarm System Cables for all Rooms prior to Ceiling closings in First floor Main Bldg 0 APPROVED71 12/29/2011 AL-BATRA Communication System Cables for all Rooms prior to Ceiling closings in First floor Main Bldg 0 APPROVED72 12/29/2011 AL-BATRA Security System Cables for all Rooms prior to Ceiling closings in First floor Main Building 0 APPROVED73 12/29/2011 AL-BATRA Security System Cables for all Rooms prior to Ceiling closings in Ground floor Service Bldg 0 REJECT74 12/29/2011 AL-BATRA Communication System Cables for all Rooms prior to Ceiling closings in Ground floor Service Bldg 0 REJECT75 12/29/2011 AL-BATRA Fire Alarm System Cables for all Rooms prior to Ceiling closings in Ground floor Service Bldg 0 APPROVED76 12/29/2011 AL-BATRA AV System Cables for all Rooms prior to Ceiling closings in Ground floor Service Building 0 REJECT77 12/29/2011 AL-BATRA Lighting System Cables for all Rooms prior to Ceiling closings in Ground floor Service Building 0 REJECT78 12/29/2011 AL-BATRA Lighting of Pole Installation 0 APPROVED79 1/2/2012 AL-BATRA Security System Cables for all Rooms prior to Ceiling closings in Ground floor Service Bldg 1 APPROVED80 1/2/2012 AL-BATRA AV System Cables for all Rooms prior to Ceiling closings in Ground floor Service Building 1 APPROVED81 1/2/2012 AL-BATRA Lighting System Cables for all Rooms prior to Ceiling closings in Ground floor Service Bldg 1 APPROVED

Page 16: AL-BATRA

AL-BATRA RFI"SWATERPROOFING

S.NO DATE PROJECT DESCRIPTION REV STATUS1 9/21/2010 AL-BATRA WaterProofing for Foundation+Column Neck for First Layer 0 REJECT2 9/26/2010 AL-BATRA DampProof for Foundation+Column Neck for First Layer 0 APPROVED3 9/26/2010 AL-BATRA DampProof for Foundation+Column Neck for Second Layer 0 REJECT4 10/10/2010 AL-BATRA WaterProofing Membrane for Water& Holding Tank Under Foundation 0 APPROVED5 10/10/2010 AL-BATRA Primer Coats in Water Tank & Holding Tank 0 APPROVED6 10/10/2010 AL-BATRA First Layer of Water Proofing Membrane For Holding & Water Tank 0 APPROVED7 10/10/2010 AL-BATRA Second Layer of Water Proofing Membrane For Holding & Water Tank 0 APPROVED8 11/4/2010 AL-BATRA First Layer of Water Proofing for Boundary Wall 0 REJECT9 11/7/2010 AL-BATRA First Layer of Water Proofing for Boundary Wall + Column Neck for Boundary Wall 0 APPROVED

10 11/7/2010 AL-BATRA Second Layer of Water Proofing for Boundary Wall + Column Neck + Boundary Wall for Main & Service Building 0 APPROVED

11 1/29/2011 AL-BATRA Starting First Coat of Epoxy Proofing for Water Tank 0 APPROVED12 2/1/2011 AL-BATRA Starting Second Coat of Epoxy Proofing for Water Tank 0 APPROVED13 2/8/2011 AL-BATRA First Layer of Waterproofing in Water Tank 0 APPROVED14 2/12/2011 AL-BATRA External Waterproofing in Water Tank Second Layer 0 APPROVED15 2/14/2011 AL-BATRA Waterproofing for Water Tank Protection Layer 0 REJECT16 2/15/2011 AL-BATRA First Coat of Waterproofing for Grade Beam in Service Building 0 APPROVED17 2/15/2011 AL-BATRA Second Coat of Waterproofing for Grade Beam in Service Building 0 APPROVED18 2/21/2011 AL-BATRA First Layer of Waterproofing for Grade Beam in Main Building 0 APPROVED19 2/21/2011 AL-BATRA Second Layer of Waterproofing for Grade Beam in Main Building 0 APPROVED20 2/28/2011 AL-BATRA First Layer of Waterproofing for Ground of Second Holding Tank 0 APPROVED21 2/28/2011 AL-BATRA Second Layer of Waterproofing for Ground of Second Holding Tank 0 APPROVED22 3/14/2011 AL-BATRA First Layer Water Proofing for Footing & Neck Column in front side Boundary Wall 0 APPROVED23 3/14/2011 AL-BATRA Second Layer Water Proofing for Footing & Neck Column in front side Boundary Wall 0 APPROVED24 3/16/2011 AL-BATRA First Layer Epoxy Proofing for Holding Tank 0 APPROVED25 3/17/2011 AL-BATRA 2nd Layer Epoxy Proofing for Holding Tank 0 APPROVED26 3/31/2011 AL-BATRA First Layer External Water Proofing in First Holding Tank 0 APPROVED27 4/6/2011 AL-BATRA First Layer External Water Proofing in 2nd Holding Tank 0 APPROVED28 4/7/2011 AL-BATRA 2nd Layer External Water Proofing in First Holding Tank 0 APPROVED29 4/11/2011 AL-BATRA 1st Layer internal Epoxy Water Proofing 2nd Holding Tank 0 APPROVED

Page 17: AL-BATRA

30 7/14/2011 AL-BATRA First Layer of Waterproofing for Manholes 0 APPROVED31 7/6/2011 AL-BATRA Protection Layer of Waterproofing for Manholes 1 APPROVED32 10/2/2011 AL-BATRA First Layer of Waterproofing for Manholes 0 APPROVED33 10/2/2011 AL-BATRA Protection Layer of Waterproofing for Manholes 0 APPROVED34 10/2/2011 AL-BATRA Waterproofing for Manholes 0 APPROVED35 11/20/2011 AL-BATRA Membrane Waterproofing for Roof Slab of Main Building 0 APPROVED36 11/20/2011 AL-BATRA Membrane Waterproofing for Roof Slab of Service Building 0 REJECT37 11/21/2011 AL-BATRA Membrane Waterproofing for Roof Slab of Service Building 1 APPROVED38 11/21/2011 AL-BATRA Waterproofing for Electrical Manholes 0 APPROVED39 11/21/2011 AL-BATRA Waterproofing for Service Building Manholes 0 APPROVED40 11/26/2011 AL-BATRA Waterproofing Under Tiles in Toilet (G-12, F-04, F-14) 0 REJECT41 11/26/2011 AL-BATRA Waterproofing Under Tiles in Kitchen of Main Building & Service Building 0 REJECT42 11/28/2011 AL-BATRA Waterproofing for Kitchen & Toilet of Ground & First Floor Main Building,Ground Floor for Service Building 0 APPROVED

43 12/4/2011 AL-BATRA Roof Insulation - Separation Sheets in Main Building & Service Building 0 APPROVED44 12/4/2011 AL-BATRA Roof Insulation - Thermal Rigid Insulation in Main Building & Service Building 0 APPROVED

Page 18: AL-BATRA

AL-BATRA RFI"SFINISHING

S.NO DATE PROJECT DESCRIPTION REV STATUS1 10/23/2011 AL-BATRA Ceramic Tiles in First Floor Main Building 0 APPROVED2 10/31/2011 AL-BATRA Porcaline Tiles in Service Building 0 APPROVED3 12/3/2011 AL-BATRA Granite Tiles for First & Ground Floor Of Main Building 0 APPROVED4 12/13/2011 AL-BATRA Acoustic Tiles 60x60 False Ceiling Suspension System for All Rooms of Main Building, Except for Wet Areas 0 REJECT

5 12/13/2011 AL-BATRA Acoustic Tiles 60x60 False Ceiling Suspension System for All Rooms of Service Building, Except for Wet Areas 0 REJECT

6 12/20/2011 AL-BATRA Granite Cladding for Boundary Wall 0 REJECT7 12/26/2011 AL-BATRA Stone Shield Paint Sample External (Building Elevation Finish) 0 APPROVED8 12/26/2011 AL-BATRA Royal Acryl Paint Sample (Boundary Wall Finish) 0 APPROVED9 1/9/2012 AL-BATRA Curbstone for Site Work 0 APPROVED

10 1/9/2012 AL-BATRA Pavement Work for Site Work 0 APPROVED11 1/9/2012 AL-BATRA Granite Fixing for Internal Stairs at Main Building 0 APPROVED12 12/9/2012 AL-BATRA Ceramic Wall Works of Ground Floor Main Building 0 APPROVED13 1/9/2012 AL-BATRA Ceramic Wall Works at Service Building 0 APPROVED14 1/9/2012 AL-BATRA Stone Shield at Main Building 0 REJECT15 1/9/2012 AL-BATRA Stone Shield at Service Building 0 REJECT16 1/14/2012 AL-BATRA Curbstone for Site Work 0 APPROVED17 1/14/2012 AL-BATRA Pavement Work for Site Work 0 APPROVED18 1/14/2012 AL-BATRA Granite Fixing for Internal Stairs at Main Building 0 APPROVED19 1/14/2012 AL-BATRA Ceramic Wall Works of Ground Floor Main Building 1 APPROVED20 1/14/2012 AL-BATRA Ceramic Wall Works of First Floor Main Building 1 APPROVED21 14-Jan AL-BATRA Stone Shield at Main Building 1 APPROVED22 1/14/2012 AL-BATRA Stone Shield at Service Building 1 APPROVED23 1/14/2012 AL-BATRA Granite Cladding for External Elevation at Main Building 0 APPROVED24 1/14/2012 AL-BATRA Granite Skirting for External Elevation at Service Building 0 APPROVED25 1/14/2012 AL-BATRA Granite Cladding for Entrance Lobby at Main Building 0 APPROVED26 2/1/2012 AL-BATRA Handrail for Internal Stairs at Main Building 0 REJECT27 2/1/2012 AL-BATRA Acoustic Tiles False Ceiling at Ground Floor Main Building 0 APPROVED28 2/1/2012 AL-BATRA Acoustic Tiles False Ceiling at First Floor Main Building 0 APPROVED29 2/1/2012 AL-BATRA Acoustic Tiles False Ceiling at Service Building 0 APPROVED

Page 19: AL-BATRA

30 2/1/2012 AL-BATRA Gypsum Board False Ceiling at Main Building 0 APPROVED31 2/1/2012 AL-BATRA Gypsum Board False Ceiling at Service Building 0 REJECT30 10/31/2011 AL-BATRA Door Frames in Main & Service Building 0 APPROVED31 8/23/2011 AL-BATRA Preperation for Internal Plaster for Parapet in Main & Service Building 0 APPROVED32 8/23/2011 AL-BATRA Preperation for External Plaster Boundary Wall 0 APPROVED33 9/11/2011 AL-BATRA External Plaster for Boundary Wall 0 APPROVED34 9/11/2011 AL-BATRA Preperation for Plaster in Service Building 0 APPROVED35 9/11/2011 AL-BATRA Internal Plaster for Parapet in Main Building & Service Building 0 APPROVED36 9/27/2011 AL-BATRA Internal Plaster in Service Building 0 APPROVED37 9/27/2011 AL-BATRA Plaster Preperation in First Floor Main Building 0 APPROVED38 1/18/2011 AL-BATRA Plaster Preperation for Ground Floor Main Building 0 REJECT39 10/20/2011 AL-BATRA Plaster Preperation for Ground Floor Main Building 0 APPROVED40 10/31/2011 AL-BATRA Plaster Accessories for External Elevation in Service Building 0 REJECT41 1/12/2011 AL-BATRA First Coat of Paint for Service Building 0 APPROVED42 11/14/2011 AL-BATRA First Coat of Paint for Internal Walls of Ground & First Floor Main Building 0 APPROVED43 11/17/2011 AL-BATRA Second Coat of Paint for Internal Walls of Ground & First Floor Main Building 0 REJECT44 11/20/2011 AL-BATRA Second Coat of Paint for Internal Walls of Ground & First Floor Main Building 1 APPROVED45 11/30/2011 AL-BATRA Groove Work in Main Elevation of Main Building from Axis 1 to 2 0 APPROVED46 12/3/2011 AL-BATRA Plaster Accessories of Main Elevation of Main Building Between Axis 5 & 4 0 APPROVED47 12/3/2011 AL-BATRA Plaster Accessories of East Elevation 0 APPROVED48 12/6/2011 AL-BATRA External Plaster Accessories Right Side Elevation of Main Building 0 APPROVED49 12/13/2011 AL-BATRA Plaster Preperation for Service Building 1102 0 APPROVED

Page 20: AL-BATRA
Page 21: AL-BATRA
Page 22: AL-BATRA

AL-BATRA RFI"SBLOCK WORK

S.NO DATE PROJECT DESCRIPTION REV STATUS1 AL-BATRA Crushing for Block Approval Al-Mohalib Factory (Al Manar) 0 REJECT2 8/7/2011 AL-BATRA Block for Ground & First Floor in Main Building 0 REJECT3 8/7/2011 AL-BATRA Block for Ground & First Floor in Service Building 0 REJECT4 8/7/2011 AL-BATRA Blocks for Boundary Wall 0 REJECT5 8/13/2011 AL-BATRA Block for Ground & First Floor in Main Building 1 APPROVED6 8/13/2011 AL-BATRA Block for Ground FLOOR Service Building 1 APPROVED7 8/13/2011 AL-BATRA Blocks for Boundary Wall 1 APPROVED8 3/23/2011 AL-BATRA First Line Block in Boundary Wall 0 APPROVED9 5/7/2011 AL-BATRA First Line of Block in Service Building 1 APPROVED

10 5/29/2011 AL-BATRA Block Work for Three Side of Boundary Wall 0 REJECT11 4/23/2011 AL-BATRA First Line of Block in Boundary Wall 0 APPROVED12 4/23/2011 AL-BATRA First Line of Block in Service Building 0 REJECT13 4/23/2011 AL-BATRA First Line of Block in Main Building 0 APPROVED