Airport Guideway and Stations and City Center Utilities Relocation Project Oversight Committee Meeting September 19, 2019 Honolulu, Hawaiʻi

Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Airport Guideway and Stations and

City Center Utilities Relocation

Project Oversight Committee Meeting September 19, 2019 Honolulu, Hawaiʻi

Page 2: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

2

Airport Guideway and Stations 53% Complete (54.5% Planned)

Completed To Date: Design progression at 99% (Earned value at 96% due to design resubmittals). 158 drilled shaft foundations completed, 124 columns installed, and 56 spans have been erected. 2,015 pre-cast segments have been cast.

Page 3: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

3

Airport Guideway and Stations 53% Complete (54.5% Planned)

Makalapa (Pearl Harbor Naval Base Station) – 6% Complete

Major Work Remaining

• Conduit installation for communications at Train Control.

• Structural backfill for Faregate.

• Installation of 8-inch waterline – Complete.

• Faregate and End Platform cabinets.

Page 4: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

4

Major Work Remaining

• Sample soil before over-excavation.

• Storm drain installation.

• Demobilize water treatment plant.

Energization Status

• Station – [Date]

• Energization - [Date]

Airport Guideway and Stations 53% Complete (54.5% Planned)

Lelepaua (Honolulu International Airport) – 2% Complete

Page 5: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

5

Major Work Remaining

• Installation of underground conduit from TCCR at Mauka entrance.

• Mauka entrance spread footings formwork and reinforcing in preparation for concrete.

Airport Guideway and Stations 53% Complete (54.5% Planned)

Āhua (Lagoon Drive) – 3% Complete

Page 6: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

6

Major Work Remaining

• Install temporary fencing.

• Reach E: Coordinating AGS activities with waterline installation on Dillingham near GasPro.

• HECO Zone 9: Electrical relocation work.

Airport Guideway and Stations 53% Complete (54.5% Planned)

(Kahauiki) Middle Street Transit Center – 0.2% Complete

Page 7: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

City Center Utilities Relocation

• Estimated Completion: February 2022

• Highlights on Construction Areas: ◦ 1A – Completing 24” water facility ◦ 1B – Evaluating alternatives ◦ 1C – Evaluating alternatives ◦ 2 – Installing drain laterals ◦ 3 – Removing abandoned fuel lines ◦ 4 – Redesigning utility relocations ◦ 5 – Assessing roundabout removal impacts ◦ 6 – Started probing and layout

• Highlights on Elimination Activities: ◦ Working through several options to finalize design

and mitigate original work scope on Dillingham, Halekauwila, and Queen Street.

1A

2

3

5 6

1B

1C

4

Legend (Focus on Dry Relocations): Wet / Road in Progress Construction (% in dark) Pending Approvals/Permits Pending Final Design

On Hold/Pending On Schedule Potential Delay Behind Schedule

Status as of September 5, 2019

Key Issues

Action BIC

Solutions for Constraints / Scope on Dillingham HART

Secure Right of Way HART

Decisions on Design Elements HART

Finalize Designs AECOM

Obtain Utility Approvals AECOM

Provide Timely Permits C&C

Page 8: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

8

Dillingham Wet Tie-In Point 24-inch Water Line

Page 9: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Work completed:

Potholing Sewer jackets within the

roadway Trench patching

Sewer Line GSS1352 Deleted

Dillingham to Kaaahi

9

Page 10: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Work continues: GSS1362 manholes being epoxy coated. Miscellaneous demonstration.

Work completed: Potholing Sewer Jackets Water lines GW1360 and GW1362 Drain line GSD1363 work in DAGS

property. Drain line work on remainder of

GSD1363. Drain Line 1362.1 work in private

property. Sewer line GSS1362 trench stabilization. GSS1362 and laterals. GSD1360 work.

Kaaahi Street to Iwilei Road

10

Page 11: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

11

Kaaahi Street Drain line work

Page 12: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Kaaahi Street Gravity Sewer Work - Completed

12

Page 13: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Sewer line GSS1371

Water line GW1373

Drain line GSD1376 deleted

13

Iwilei Road to North Nimitz Hwy Gravity Sewer Work - Completed

Page 14: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Work continues: HECO F6 grouting completed and

removal ongoing. Miscellaneous demo. Fuel line removal nearing

completion.

Work completed: Potholing Water Line GW1402.

Multiple utility work deleted: Water line GW1379 Sewer line GSS1396 Drain line GSD1393 Sewer line GSS1403 Drain line GSD1403

14

North Nimitz Hwy

Page 15: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

15

Nimitz Fuel Line Removal

Page 16: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

16

Nimitz Unknown Utility

Page 17: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

HECO F6 Grouting Completed and removal ongoing

17

Page 18: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Halekauwila Street

Sewer start up pending pole relocations.

Nan working on temporary pole relocation plan.

18

Page 19: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Queen to Kamakee (Completed)

19

Page 20: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Work continues: Dry utilities potholing underway

but not completed due to some areas being in the sidewalk.

One-Time Review (OTR) plans received and being routed for street usage permit. DTS signature received.

Temporary Traffic Signal Plan (TTSP) submitted, under DTS review.

Work completed: Additional probing completed

6/5/19. Potholing for wet utilities.

Kamakee to Pensacola

20

Page 21: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Pensacola to Piikoi DTS Street Usage permits Pensacola to Piikoi Streets received.

Wet utilities potholing underway Pensacola to Piikoi Street.

One-Time Review (OTR) plans received and being routed for street usage permit, awaiting DTS signature.

Temporary Traffic Signal Plan (TTSP) submitted, under DTS review Traffic Management Plan (TMP) accepted.

Piikoi intersection day Traffic Control Plans (TCP) accepted. Routed to DTS for street usage permit.

21

Page 22: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Task Order 18 (Pt. 1: Pensacola to Piikoi Potholing)

22

Page 23: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

Piikoi to Kona Iki

One-Time Review (OTR) plans received and being routed for street usage permit.

Right of Entry for Brookfield Properties Retail potholing executed.

Traffic Control Plans (TCP) approved by HART.

Potholing underway.

HECO 25kv line located 9/4/19.

23

Page 24: Airport Guideway and Stations and City Center Utilities ...hartdocs.honolulu.gov/docushare/dsweb/Get/Document-23085/...2019/09/19  · Airport Guideway and Stations 53% Complete (54.5%

24