DESCRIPTION
AirPreheater is one of the most important part of power plant for increasing efficiency of the boiler
Citation preview
5/21/2018 Air PreHeater In thermal power plant
1/15
5/21/2018 Air PreHeater In thermal power plant
2/15
AIR PREHEATER
Air Pre-heater is an auxiliary equipment forsteam boilers. It is a heat exchanger that
absorbs heat from exit flue gas in boilersand transfers the heat to the cold air. Inutility and process boilers it is used to heat
the air required for combustion purposeand to dry and transport coal.
5/21/2018 Air PreHeater In thermal power plant
3/15
TYPES OF AIR PRE HEATERS RECUPERATIVE
-Tubular Heater
-Plate Type Heater-Steam Coiled Heater
REGENERATIVE
-Ljungstrom Air Pre Heater
5/21/2018 Air PreHeater In thermal power plant
4/15
RECUPERATIVE AIR PREHEATER-
In Recuperative type Air Preheater two fluids flow atdifferent temperatures in a space separated by a solid
partition. Heat is transferred by Convection &Conduction through the separating wall.
Tubular Air Preheater, Plate Type Air Preheater &
Steam Coil Air Preheater (SCAPH).
5/21/2018 Air PreHeater In thermal power plant
5/15
TUBULAR APH
Advantages:
Not having any moving parts.Small Nominal leakages of air to gas.
No auxiliary power consumption.
ProblemsLarge for thermal duty.Difficult to clean.Do not allow replacement of damaged heating surface.The ductings for cold and hot air require additionalspace and structural supports compared with theLjungstrom design
5/21/2018 Air PreHeater In thermal power plant
6/15
Ljungstrom Air Pre Heater
In Regenerative type Air Preheater, one heating surface
is exposed at certain intervals of time first to a hotfluid and then to a cold one. The surface of theRegenerative Air Preheater first removes heat from thehot fluid and is itself heated in the process, then the
surface gives up this heat to the cold f luid
5/21/2018 Air PreHeater In thermal power plant
7/15
Application - Air Pre Heater
To heat fresh air usingheat of flue gas for :
Primary Air :
To remove moisture frompulverized coal
Secondary Air :
To assist combustion inboiler
Air Pre Heater,
Vertical Inverted, Trisector
5/21/2018 Air PreHeater In thermal power plant
8/15
COMPONENTS OF RAPH Rotor Rotor Post Modules
Heating elements Bearings Housing Connecting Plates
Sealing Arrangements Drive units Cleaning devices Safety Devices
5/21/2018 Air PreHeater In thermal power plant
9/15
5/21/2018 Air PreHeater In thermal power plant
10/15
HEATING ELEMENTS
End Height OfHeatingElements
Material Description ofElements
Hot 300mm Carbon Steel Double
Corrugated
Inter-1 800mm Carbon Steel DoubleCorrugated
Inter-2 800mm Carbon Steel DoubleCorrugated
Cold 300mm Corrosion resistance steel Notched Plate
5/21/2018 Air PreHeater In thermal power plant
11/15
THRUST BEARING-
5/21/2018 Air PreHeater In thermal power plant
12/15
AIR PRE HEATER
SEALING ARRANGEMENT
Radial Seals
Axial Seals Bypass Seals
Rotor Post Seals
5/21/2018 Air PreHeater In thermal power plant
13/15
Sealing system
5/21/2018 Air PreHeater In thermal power plant
14/15
Ljungstrom Regenerative Air Preheater (RAPH)
Advantages: Significant reduction in overall size and weight.
Easy and economic replacement of heating surfacewith separate cold end and hot end packs.
Problems High Air leakages resulting high fan power.
Dust carry over to furnace is high causing ash erosionof boiler tubes in burner panels
Baskets are subjected to abrasive wear , hencefrequent replacement of the baskets are required.
Prone to air heater fire , the problem is aggravatedduring oil firing
5/21/2018 Air PreHeater In thermal power plant
15/15