Jan Vorrink
May 19, 2015
Agile Processes Facing increasing challenges off Renewable
Energy Sources integration and Market Coupling
Agile Processes May 19, 2015
Contents • TenneT at a glance
• Challenges
• Introduction
• Theory
• Future Developments
• Risks & Challenges
• Examples
• Questions and Answers / Discussion
Agile Processes May 19, 2015
TenneT at a glance
• Headquarter in Arnhem and
Bayreuth
• Security of supply: 99,9999%
• Efficiënt
• Robust grid
• Fully integrated TSO
• Highly integrated into Europe
First and only cross border
TSO in Europe
Agile Processes May 19, 2015
TenneT at a glance Europe’s first cross-border TSO
Facts & figures
Workforce 2,751 employees
Underlying revenue EUR 2.234 billion
EBIT EUR 620 million
Total assets EUR 12.7 billion
Investments 2014-2023 EUR 20 billion (13,3% of EU total 150 billion)
Total length grid 21,000 km
Number of transformer substations 440
Number of end-users 41 million (7.7% of EU total 532 million)
Number of interconnectors 14
Installed capacity 67 GW
Grid availability 99,9999%
Agile Processes May 19, 2015
Our key tasks Changes
Key tasks and roles of TSOs have changed drastically since TenneT
was established in 1998.
Past Present
• Stable, predictable (price-
driven) energy generation
• Maintenance and (limited)
replacement
• Focus on technology
• Local markets, separate price
zones
• National focus and regulation
• Fluctuating energy generation
(solar/wind)
• Large-scale new construction of
generation and transmission
capacity
• Technology and market
• North-West European market,
price convergence
• Grid planning and regulation at
European level
Agile Processes May 19, 2015
Offshore developments NL A cost reduction of 35 to 40% and achieving the 2023 targets is only
feasible with a structured approach, careful planning and
standardization
• Lower financing costs for TSO
• Double connection
= redundant
= higher efficiency
• Fewer dune crossings:
environmental benefits and cost
reductions
• Standardization, learning effects
and purchasing advantages: cost
reduction
• Prepared for use of 380 kV cable
in the near future
Station also
functions as hub
Wind farm
directly
connected to
station
Centralized
maintenance:
cost reduction
Agile Processes May 19, 2015
Offshore grid expansion GER
Projects Capacity
(MW)
Operational
(planned)
Under construction/awarded
BorWin2 800 (DC) 2015
DolWin1 800 (DC) 2014
DolWin2 900 (DC) 2015
DolWin3 900 (DC) 2017
HelWin1 576 (DC) 2014
HelWin2 690 (DC) 2015
SylWin1 864 (DC) 2015
Nordergründe 111 (AC) 2016
BorWin3 900 (DC) 2019
Total 7,132 2019
EUR 5-6 billion over the next ten years
Agile Processes May 19, 2015
DolWin Beta
Agile Processes May 19, 2015
BorWin Beta
Agile Processes May 19, 2015
SylWin alpha
Agile Processes May 19, 2015
Grid security calculations ready for future changes
• Challenge is less predictable flows and more changing flows
(perhaps different impact caused by micro grids)
• From Day Ahead operational planning towards Intra Day
planning ( the link with the micro grid for planned MW
exchange with higher Voltage level)
• Intra Day processes are running continuously and repeat
hourly
• ENTSO-E is preparing a mandatory Intra day Process for
Continental Europe
• Operational Planning Timeframe goes towards close to real-
time
• SCADA and operational planning process need to become
one continous process
Agile Processes May 19, 2015
SCADA-EMS Development for future changes
• Challenge is less predictable flows and more changing flows
• Operational Planning Timeframe goes towards close to real-time
• Size of the grid with impact on TSO’s area, becomes larger
because of loop and transit flows and multilateral trades and
resulting flows
• SCADA-EMS and operational planning process need to become
one continous process
• SCADA –EMS in the future including functions like:
• Dynamic Line Rating
• Realtime Predictable Voltage stability
• PMU’s and WAMS
• WAMPAC
Agile Processes May 19, 2015
Power System Structure
2000 x 4200 km / 400 GW
1800 km / 50 GW
CE dynamic system analysis & monitoring | W. Sattinger | 11.06.2014 | Page 13 of 20
Agile Processes May 19, 2015
Examples Disturbance in Zeeland, September 2009. Recorded by Amprion.
Agile Processes May 19, 2015
WAMS detects North-South oscillations
Agile Processes May 19, 2015
PMU’s detect loss of DC cable Which causes Voltage and Flow changes but no oscillations
Agile Processes May 19, 2015
Future Developments • Online test phase (on going)
• Increase number of PMUs in the grid
• Identify the need for more PMUs, dependent on application/goal
• Connect to PDCs from other TSOs
• Assessment of Risks & Challenges
• Reliability of communication channels
• Security of data transmission (communication to PDC)
• Defining remedial actions for operations
• Training of operators on dynamics
• Back-office testing of the system
• Integration of PMU information in system operations
• Integration of system dynamics simulations in operational planning
• Integration of dynamic information in the control room (EMS integration)
Agile Processes May 19, 2015
Conclusions & Recommendations
CE dynamic system analysis & monitoring | W. Sattinger | 11.06.2014 | Page 18 of 20
Agile processes are needed in Operational Planning and Realtime processes
Increasing dynamics challenges of interconnected power system operation request detailed analysis:
Enhanced dynamic modelling
Timely well-synchronised and high-resolution measurements
Permanent system monitoring
Comprehensive up-to-date expertise within TSOs
Jan Vorrink
May 19, 2015
Questions and Answers
Liability and copyright of TenneT
Disclaimer
This PowerPoint presentation is offered to you by TenneT TSO B.V. ('TenneT'). The content of the
presentation – including all texts, images and audio fragments – is protected by copyright laws. No part of
the content of the PowerPoint presentation may be copied, unless TenneT has expressly offered
possibilities to do so, and no changes whatsoever may be made to the content. TenneT endeavours to
ensure the provision of correct and up-to-date information, but makes no representations regarding
correctness, accuracy or completeness.
TenneT declines any and all liability for any (alleged) damage arising from this PowerPoint presentation
and for any consequences of activities undertaken on the strength of data or information contained
therein.
Agile Processes May 19, 2015
TenneT is Europe’s first cross-border grid operator for electricity. With about 21,000
kilometres of (extra) high-voltage lines and 36 million end-users in the Netherlands and
Germany, we rank among the top five grid operators in Europe. Our focus is to develop a
North-west European energy market and to integrate renewable energy.
www.tennet.eu