Agile & ERP Development at HallmarkChuck Quick

Page 2: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

2

• Project Start – 4th Quarter 2012

• December 2013 Master Data Release – Waterfall

– Positives

– Our Biggest Issue

• Easing our way into Agile

– KANBAN Boards

– Use of Agile Ceremonies

• January 2014 - Phase 2 Kick-off

CRM Implementation - Project History

Page 3: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

3

Phase 2 - What does Agile mean to Us

1. Our highest priority is to satisfy the customer through early and continuous

delivery of valuable software.

2. Welcome changing requirements, even late in development. Agile processes

harness change for the customer's competitive advantage

6. The most efficient and effective method of conveying information to and within a

development team is face-to-face conversation.

7. Working software is the primary measure of progress.

8. Agile processes promote sustainable development. The sponsors, developers,

and users should be able to maintain a constant pace indefinitely.

10. Simplicity--the art of maximizing the amount of work not done--is essential.

Page 4: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

4

Agile Must Dos

Page 5: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

5

FSO Team Structure

Page 6: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

6

Scaled Agile Framework at Hallmark

Page 7: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

7

• Resistance to Change– It is way BIGGER than you think

– (see "The Transition to Agile Methods Requires a Culture Shift From 'Me' to 'We'")

• KANBAN Boards & WIP Limits– Define them & Honor them

• Use of Metrics– Burn-Up Chart

– Budget Burn-Down

– Have the hard conversations up front

• Hold the correct ceremonies – Retrospectives

– Demos

Key Learnings & Challenges

Page 8: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

8

KANBAN Boards

Page 9: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

9

Metrics – Burn Up Chart

Page 10: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

10

Metrics – Budget

Page 11: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

11

Retrospective – Do I have to Go???

Page 12: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

12

Why Conduct Demos

Page 13: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

13

Agile Must Dos

Page 14: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

14

• Master Data Release - Waterfall– 15 Months to deliver value

– Nearly 30,000 Hours of Effort

– Greater than 2,100 Hours of Overtime – (7%)

• Phase 2 - Agile– Averaged 80 days to deliver value

– Greater than 40,000 Hours of Effort

– 1,025 Hours of Overtime – (2.6%)

Review

Page 15: Agile & ERP Development at Hallmark Chuck Quick · 2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage

15

• Agile SAP by Sean Robson

• Gartner – Agile Packaged Applications and ERP Delivery Need Planning and Flexibility to ‘Make the Elephant Dance’

• http://scaledagileframework.com/

• YouTube – Product Owner in a Nutshell

References