Agenda School updates District wide updates

Recycling report to county- Bruce Craig Energy star update- Wade Brosius

Energy conservation project Overview- Mike Hanson, CM3 building solutions Project energy savings and environmental impact-

Wade Energy education tools- Pat Dunn

Wrap up and next steps

Page 2: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

School Updates

Bethel High School Middle School GVES Concord

Page 3: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

County recycling Report 32.23 tons of single stream recycling Reduction of 1 trash and 1 recycling dumpster at Bethel Springs GVES and Concord school  -  2 recycling dumpsters and 1 trash

dumpster GVHS and Concord  - looking into possibility of reducing the # of

trash dumpster pulls and increasing # of recycling dumpster pulls

Garage products recycled Antifreeze      720 pounds Batteries      2,435 pounds Radiators          40 pounds Oil filters      1,200 pounds Used oil        8,640 pounds

Page 4: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

Energy Star

My Portfolio: Wade Brosius  February 11, 2013 - 11:57:38 

AM  Total Buildings: 5  

Facility Name Current Rating (1-100)

Current Site Energy Intensity

(kBtu/Sq. Ft.)

National Median Site EUI (kBtu/Sq.

Ft.)Current Total Site Energy Use (kBtu)

Change from Baseline: Adjusted

Energy Use (%)

Change from Baseline: GHG

Emissions (MtCO2e)

Bethel Springs ES 89 51.8 80.3 4,664,377.34 -38 -303.7Concord ES 58 48.3 52 6,419,078.29 -28.5 -350.93Garnet Valley ES 92 53.4 89.6 5,992,781.35 -33 -247.2Garnet Valley High School 63 64.9 73.2 17,351,602.69 -31.8 -951.62Garnet Valley Middle School 75 66.4 80.9 12,805,059.56 -25.8 -470.22Group Total       47232899.23   -2323.67

Page 5: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

Energy Conservation Project Project Goals

Reduced Energy Consumption Reduced Operating Costs State of the Art Equipment w/ Extended Warranties Make All Buildings DDC Controlled Standardized Equipment District Wide Address Long Lingering Capital Needs

Page 6: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

Performance Contracts

Benefits of PC – streamlined process, more GVSD control

PCs streamline process for energy projects – reduces cost & time, allows for implementing more comprehensive project w/ immediate improvement in occupant conditions

Gives on site facilities staff more input to design and better control of final product

Project lowers operating costs by reducing energy use and replacing high maintenance cost equipment

Project fully completed in 2013 with minimal disruption

Page 7: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

Project Highlights 12,344 fixtures impacted including 536 outdoor lights Lighting based on occupancy thru sensors & energy

education New high-efficiency chillers at four schools Digital control upgrades district wide New high-efficiency water heaters

Page 8: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

Scope HS MS GVES CES BSES

Lighting Retrofit X X X X X

Energy Education X X X X X

ATC Recommissioning X X X X X

DDC Controls X X X X X

Roof Replacement X

Building Envelope X X X X X

Chiller Replacement X X X X

Vending Machine Controls X X X X X

Water Fountain Controls X X X X X

Boiler Controls X X X X

Graphics Upgrade X X X X X

Demand Control Ventilation, VFDs

X X X X

Simplified Pumping X

DHW Replacement X X X X

Added AC X X

Gas Line X

Page 9: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

Project Energy Savings Approx. 3.5 million kWh

2650 Metric Tons GHG

http://www.epa.gov/cleanenergy/energy-resources/calculator.html

Page 10: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

Energy Savings  ANNUAL OPERATING COSTS USING EXISTING SYSTEM ENERGY COST---------------------------------- $ 4,696  MAINTENANCE COST------------------------- $1800 TOTAL COST------------------------------------ $6496  ANNUAL OPERATING COSTS USING LED SYSTEM ENERGY COST-----------------------------------$472 MAINTENANCE COST-------------------------$0 TOTAL COST------------------------------------ $472  SAVINGS----------------------------------------- $6024  

BEFORE AND AFTER:

In the auditorium of the Middle School, 150- and 250-watt incandescent quartz lamps were replaced by 17- and 24-watt LED lights. The new LEDs enhance the appearance of the auditorium and maintain or improve light levels, but will significantly cut the energy consumption while eliminating obsolete technology and reducing maintenance costs. 

   

Middle SchoolAuditorium

Page 11: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

District Wide Energy Education

Partnership w/ Practical Energy Solutions School specific faculty meetings Help tying your existing curriculum to project goals Monthly reporting of results to schools “Nothing Saves More Than OFF”

Page 12: Agenda School updates District wide updates Recycling report to county- Bruce Craig Energy star update- Wade Brosius Energy conservation project Overview-

Next Steps

Goals for next meeting Meeting date