Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
AFRICAN DEVELOPMENT BANK
CABO VERDE
ECONOMIC GROWTH SUPPORT PROGRAMME - PHASE II (PACE - II)
APPRAISAL REPORT
Translated Document
ECGF/PGCL
October 2017
P
ubli
c D
iscl
osu
re A
uth
ori
zed
P
ubli
c D
iscl
osu
re A
uth
ori
zed
TABLE OF CONTENTS
ACRONYMS AND ABBREVIATIONS .................................................................................................................. i
LOAN INFORMATION ......................................................................................................................................... ii
I. INTRODUCTION: THE PROPOSAL ............................................................................................................ 1
II. UPDATE ON THE COUNTRY’S ELIGIBILITY .......................................................................................... 2 2.1. Criterion 1 – Government’s Commitment to Reducing Poverty .................................................... 2
2.2. Criterion 2 – Political Stability ....................................................................................................... 2
2.3. Criterion 3 – Macroeconomic Stability .......................................................................................... 3
2.4. Criterion 4 –Fiduciary Risk Assessment ........................................................................................ 4
2.5. Criterion 5 – Harmonization .......................................................................................................... 4
III. PROGRAMME for 2016/2017 – PACE-II ...................................................................................................... 5 3.1 Programme Goal and Objective ..................................................................................................... 5
3.2 Programme Components ................................................................................................................ 5
3.3. Programme Outputs and Expected Outcomes ................................................................................ 6
3.4. Progress Towards Fulfilling Conditions Precedent to PACE-II (list of PACE-II triggers defined
under PACE-I) ............................................................................................................................... 9
3.5. Public Policy Dialogue ................................................................................................................. 10
3.6. Loan Conditions – Actions Precedent .......................................................................................... 10
3.7. Application of Best Practice Principles on Conditionality .................................................................... 11
3.8. Financing Needs ........................................................................................................................... 12
IV. PROGRAMME IMPLEMENTATION ......................................................................................................... 12 4.1. Programme Beneficiaries ............................................................................................................. 12
4.2. Implementation, Monitoring and Evaluation ............................................................................... 13
4.3. Financial Management, and Disbursement and Reporting Arrangements ................................... 13
4.4. Procurement ................................................................................................................................. 13
V. LEGAL FRAMEWORK ............................................................................................................................... 13 5.1. Legal Instrument .......................................................................................................................... 13
5.2. Conditions for Bank Intervention ................................................................................................. 14
5.3. Compliance with Bank Group Policies ........................................................................................ 14
VI. RISK MANAGEMENT ................................................................................................................................ 14
VII. RECOMMENDATION ................................................................................................................................. 14
Annex 1 : Government’s Letter of Economic Policy
Annex 2 : Programme Reforms Matrix
Annex 3 : Outcomes of Previous Budget Support Operations in Cabo Verde
Annex 4 : Note on Relations with the International Monetary Fund
LIST OF TABLES
Table 1 : Macroeconomic Indicators
Table 2 : Progress Towards Achieving Logical Framework Output Targets
Table 3 : Progress Towards Achieving Logical Framework Outcome Targets
Table 4 : List of Actions Precedent
Table 5 : Financing Needs
Table 6 : Risks and Mitigation Measures
CURRENCY EQUIVALENTS
September 2017
Currency = Escudo (CVE)
UA 1 = CVE 132.372
EUR 1 = CVE 110.747
USD 1 = CVE 93.656
FISCAL YEAR
1 January - 31 December
WEIGHTS AND MEASURES
1 tonne = 2 204 pounds (lbs)
1 kilogramme (kg) = 2.200 lbs
1 metre (m) = 3.28 feet (ft)
1 millimetre (mm) = 0.03937 inches (”)
1 kilometre (km) = 0.62 mile
1 hectare (ha) = 2.471 acres
i
ACRONYMS AND ABBREVIATIONS
AEO African Economic Outlook
AfDB African Development Bank
BCA Banco Comercial do Atlântico
BSG Budget Support Group
CFRA Country Fiduciary Risk Assessment
CM Council of Ministers
CSP Country Strategy Paper
CVE Cabo Verdean Escudo
DSA Debt Sustainability Analysis
ELECTRA National Electricity Company
ENACOL Empresa Nacional de Combustiveis (National Fuel Company)
FDI Foreign Direct Investment
GAP II Governance Operational Framework and 2013-2017 Action Plan
GDP Gross Domestic Product
GoCV Government of Cabo Verde
GPRSP Growth and Poverty Reduction Strategy Paper
HDI Human Development Index
ICIEG Cabo Verdean Institute for Gender Equality
ICT Information and Communication Technology
IIAG Mo Ibrahim Index of African Governance
IFH Imobiliária Fundiária e Habitat
IMF International Monetary Fund
MF Ministry of Finance
MIC Middle-Income Country
MIC-TAF Middle-Income Countries Technical Assistance Fund
MORABI Cabo Verdean Association for the Empowerment of Women
MPD Movement for Democracy
MSME Micro-, Small- and Medium-sized Enterprises
PAGEPPI Public Corporate Governance and Investment Promotion Support Programme
PAGFP-RSP Public Finance Management and Private Sector Recovery Support Programme
PAICV African Party for the Independence of Cabo Verde
PE Public Enterprise
PEDS Economic Plan for Sustainable Development
PEFA Public Expenditure and Financial Accountability
PEMFAR Public Expenditure Management and Financial Accountability Review
PIP Public Investment Plan
PPP Public-Private Partnership
PPPU Public-Private Partnership Unit
SME Small- and Medium-size Enterprise
SNIP National Public Investment System
STE Economic Transformation Strategy
TACV Transportes Aéreos de Cabo Verde (Cabo Verde Air Transport Company)
TFP Technical and Financial Partner
UASE State Investment Support Unit
WTO World Trade Organisation
ii
LOAN INFORMATION
Client Information
BENEFICIARY : Republic of Cabo Verde
SECTOR : Economic and Financial Governance
EXECUTING AGENCY : Ministry of Finance (MF)
AMOUNT : EUR 20 million
2017 Financing Plan for Budget Support Operations
Source of Financing Amount
AfDB EUR 20 Million
World Bank Not available
Luxembourg EUR 2 Million
European Union EUR 9 Million (programmed)
EUR 7 Million (not programmed)
Portugal EUR 0.5 Million
AfDB Financing Information
Loan Currency: Euros (EUR) [or any other acceptable currency]
Loan type: Total flexibility loan
Maturity: To be determined (up to maximum 25 years)
Grace period: To be determined (up to maximum 8 years)
Weighted average
maturity**: To be determined (depending on amortization profile)
Reimbursments: Half-yearly installments at the end of the grace period
Interest rate: Base rate + Margin on financing cost + Loan margin +
Maturity premium
This interest rate must be greater than or equal to zero.
Base rate : Floating (6 Months EURIBOR revised on February 1st
and August 1st or any other acceptable rate)
A free option is offered to set the base rate
Margin on financing cost:
Margin on the Bank’s financing cost revised on January
1st and July 1st and applied on February 1st and August
1st with the base rate.
Loan margin: 80 base points (0.8%)
Maturity premium: To be determined :
0% if the weighted average maturity <= 12.75
years
0.10% if 12.75 <the weighted average maturity
<= 15
0.20% if the weighted average maturity> 15
years
Opening Commission: 0.25% of the loan amount
Commitment fee:
0.25% per annum of the undisbursed amount. It begins to
run 60 days after the date of signature of the loan
agreement and is payable on the interest payment dates.
Option to convert base
rate * :
Besides the free option to set the base rate, the possibility
is offered to the borrower to return to the floating rate or
to re-fix on all or part of the disbursed amount of his
loan.
Transaction fees are payable
iii
Option of rate ceiling or
tunnel * :
The possibility is offered to the borrower to put a ceiling
or a tunnel on the base rate for all or part of the disbursed
amount of his loan.
Transaction fees are payable
Currency conversion
option *:
The possibility is offered to the borrower to change the
currency of all or part of his loan, whether disbursed or
not, into another loan currency of the Bank.
Transaction fees are payable
Timeframe – Main Milestones (expected)
Activities Dates
Appraisal June 2017
Negotiation September 2017
Approval October 2017
Effectiveness November 2017
Disbursement November 2017
Supervision April 2018
Completion Report November 2018
iv
PROGRAMME SUMMARY
General overview
of the programme
Programme Name: Economic Growth Support Programme - Phase II (PACE-II).
General Schedule: 2017-2018. Financing: EUR 20 million. Operation Instrument:
General Budget Support. Sector: Economic Governance. Goal and objective of the
programme: PACE-II is the second phase of a two programme-based budget support
operations. It aims to consolidate the gains of PACE-I and contribute to sustained
economic growth. The first component of PACE-II focuses on the enhancement of
the effectiveness of public investment through two sub-components, namely: (a)
improvement of public corporate governance and the public investment institutional
and regulatory framework; and (b) modernization of the institutional and regulatory
framework of public-private partnerships. As for the second component, the support
to promote private sector development will focus on: (c) improving the business
environment; and (d) supporting entrepreneurship and the formalization of informal
activities. Expected results : Achieving these operational objectives will: (i) improve
PEFA indicator PI 11 on public investment management (new indicator) to C in 2018;
(ii) improve PEFA indicator PI 12 on public asset management (new indicator) to C
in 2018; (iii) increase the number of signed and on-going PPP projects from 1 in 2012
to 3 in 2017; (iv) increase private sector credit from 5.1% of broad money supply
(M2) in 2014 to over 6% in 2017; (v) improve the average export and import time
from 20 days in 2014 to less than 15 days in 2017; and (vi) increase the number of
new businesses established from about 100 (30% established by women) in 2014 to
more than 200 (30% women-owned) in 2017.
Overview of
country context
Cabo Verde faces several challenges that could hamper its economic growth in the medium term. In the first instance, the country faces a series of structural constraints relating to the small size of its domestic market, the country’s fragmentation (several islands), and the dearth of natural resources over which the authorities have little or no control. In addition to these structural challenges due to nature, there are others that should be addressed by the authorities to ensure sustained growth in the years ahead, namely: (i) control of the debt level by seeking other sources of financing, especially private, and by improving the management of public enterprises and major public investment projects to ensure better achievement of the desired effects in terms of economic growth; (ii) diversification of the economy by creating conditions conducive to the promotion of the private sector. Cabo Verde’s economy has experienced a low level of growth in recent years despite an expansionary fiscal policy through an extensive public investment programme. The deterioration of the international economic environment resulting from the 2008 financial crisis on the one hand, and the 2009 euro crisis, on the other, had a strong negative impact on the country’s economy. After a period of strong growth of 6.6% on average between 2000 and 2008, the country experienced a year of recession in 2009 before returning to an average growth rate of 1.3% between 2010 and 2015. It was only in 2016 that recovery began to gain momentum with a growth rate of about 3.2%. On the whole, the short-term outlook is positive, despite looming major challenges that will impact growth and development in the long term. GDP growth is expected to reach 3.7% in 2017 and 4.1% in 2018.
Lessons learned
With regards to key lessons learned, the following are put forward: (i) the need to strengthen policy dialogue for an enhanced roll-out of structural reforms, (ii) the need to continue rolling out institutional support projects which focus on the same priority issues as budget support and (iii) the need to maintain the common policy reform matrix set-up with partners, and in cooperation with authorities.
Conditions for
continuous
support
Cabo Verde meets all necessary conditions for a Bank engagement through budget support. Regards poverty reduction, the drafting of the new Sustainable Plan for Economic Development (PEDS) is a strong commitment. On the political front, Cabo Verde is one of the most politically stable countries in Africa. The country enjoys good political stability, which has been steadily consolidated over the years thanks to the quality of its democratic system. The macroeconomic criterion is also fulfilled. The country’s macroeconomic framework is subject to regular reviews by the IMF
v
and the Budget Support Group (BSG) which gathers all partners involved in programme support. The latest BSG mission was conducted in June 2017. Macroeconomic stability was confirmed by the IMF and the BSG. Regarding risk, the fiduciary framework assessment conducted by the Bank in Octobre 2016 concluded that the fiduciary risk was moderate and that the public finance management system fulfilled the Bank requirements for budget support operations. Lastly on harmonization, Cabo Verde has made significant progress in implementing the Paris Declaration Principles, thus strengthening aid effectiveness. Aid to Cabo Verde is aligned with national priorities. Since 2006, Cabo Verde’s major bilateral and multilateral donors have harmonized their budget support around a mutually agreed policy matrix. The budget support instrument, which is increasingly taking precedence over project lending in recent years, is used to leverage collaboration with other development partners in the country’s public finance management and sector support.
Policy dialogue
During PACE-II implementation, dialogue with Cabo Verdean authorities will focus on the following areas: (i) improvement of public investment efficiency with emphasis on the continued improvement of public corporate governance and the public investment framework and the PPP modernization framework; and (ii) support for the promotion of private sector development, in general, and for the improvement of the business environment to boost entrepreneurship, in particular. This dialogue will be technically supported by the various institutional support projects currently underway in the PPP and public finance sectors.
vi
Results-Based Logical Framework
Country and Programme Name: Cabo Verde – Economic Growth Support Programme (PACE-II)
Programme Goal: Contribute to creating conditions for sustained economic growth by improving the efficiency of public investment and promoting
private sector development
RESULTS CHAIN
PERFORMANCE INDICATORS MEANS OF
VERIFICATION
RISKS/
MITIGATION
MEASURES Indicators (including CSI) Baseline Target
IMP
AC
T
Improved conditions
for sustained, inclusive
and sustainable
economic growth
GDP growth in real terms 0.6% in 2014 4% of GDP in
2017
PEFA/MF/IMF
Country’s global
competitiveness index 3.7 points (2014) 4 points in 2017
OU
TC
OM
ES
Outcome 1:
Improved public
investment efficiency
PEFA Indicator – PI 11 –
Public investment
management (new PEFA
indicator not previously
assessed)
Not yet assessed
(2014) C (2018)
Risk 1: An
unfavourable
macroeconomic
environment and
exogenous
shocks.
Mitigation
Measures: This
type of risk is the
subject of an on-
going dialogue
with the
authorities, and is
monitored
regularly within
the context of the
BSG that brings
together the TFPs
involved in
programme
support
operations.
Risk 2: The
human capacity of
government
services, although
above the regional
average, is
limited. If this
situation persists,
it could slow
down or even halt
the
implementation of
programme
reforms.
Mitigation
Measures: The
Government is
committed, at the
highest level
(Presidency,
Prime Minister’s
Office, Ministry
of finance, and
PEFA Indicator – PI 12 –
Public asset management (new
PEFA indicator not previously
assessed)
Not yet assessed
(2014) C (2018)
Number of PPP projects
signed by the Government and
under implementation
1 (2012) 3 (2017)
Outcome 2:
Enhanced private
sector development
Credit to the private sector (%
broad money supply – M2)
(CSI)
5.1% of broad
money supply
(M2) (2014)
6.2% of broad
money supply
(M2) (2017)
Import and export timeframe
(days)
20 days to import
and export goods,
respectively
(2014)
Less than 15 days
to import and
export,
respectively
(2017)
Number of new MSMEs
established (% owned by
women)
About 100 new
MSMEs
established and
30% of them
women-owned
(2014)
More than 200
new MSMEs
established and
30% of them
women-owned
(2017)
COMPONENT I – IMPROVEMENT OF PUBLIC INVESTMENT EFFECTIVENESS
OU
TP
UT
S
I.1 – Improvement of Public Corporate Governance and the Public Investment Framework
Development and
operationalization of
the National
Computerized System
for the Prioritization
and Monitoring of
Public Investment
(SNIP)
National Computerized
System for the Prioritization
and Monitoring of Public
Investment (SNIP)
No computerized
system is set up in
2014
SNIP is
operational in
2017
MF
Adoption by the
Council of Ministers
(CM) of the decree on
the use of SNIP
Decree on the use of SNIP
The manual on
project selection
criteria is
available in 2014
The decree on the
use of SNIP is
issued in 2017
Adoption by the CM of
the bill on public
corporate governance
and its implementing
decrees
Bill on public corporate
governance and its
implementing decrees
The 2009 Law on
public enterprises
The bill on public
corporate
governance is
adopted by the
CM in 2015/ the
implementing
decrees are
adopted in 2016
vii
Preparation and
publication of the 2014
and 2015 reports on
the contingent
liabilities of public
enterprises
2014, 2015 and 2016 reports
on the contingent liabilities of
public enterprises
Not yet published
in in 2014
The 2014 report
on the contingent
liabilities of public
enterprises is
available in 2015
and published in
2016. The one for
2015 is available
and published in
2016.
line ministries), to
a process of
structural reforms
which are,
moreover, the
subject of regular
monitoring by
TFPs, particularly
in the context of
the BSG which
holds biannual
joint review
missions.
Risk 3 is political
in nature and
relates to the 2016
elections
Mitigation
Measures: The
Government is
committed, at the
highest level
(Presidency,
Prime Minister’s
Office, Ministry
of finance, and
line ministries), to
a process of
structural reforms
in agreement with
TFPs.
Operationalization of
the public enterprise
monitoring and
evaluation system
(including the six
major enterprises)
Public enterprise monitoring
and evaluation system
(including the six major
enterprises)
Non-existent in
2014
The progress
report on the
operationalization
of the public
enterprise
monitoring and
evaluation system
is available in
2017
I.2 – Modernization of the Public-Private Partnership Framework
Adoption by the CM of
the PPP legislative
decree (replacing the
2005 instrument)
PPP legislative decree
(replacing the 2005
instrument)
Legislative decree
of 2005
The PPP
legislative decree
is adopted by the
CM in 2015
Preparation of the PPP
policy and manual PPP policy and manual
Non-existent in
2014
The PPP policy
and manual are
available in 2016
Setting up of the
pipeline of PPP
operations with at least
3 projects ready for bid
invitations.
Pipeline of PPP operations
with at least 3 projects ready
for bid invitations
Non-existent in
2014
The pipeline of
PPP operations is
set up in 2016
COMPONENT II – SUPPORT FOR THE PROMOTION OF PRIVATE SECTOR DEVELOPMENT
II.1 – Improvement of the Business Environment
Adoption by the CM of
the legislative decree
relating to the General
Regulations of the
Investment Code.
Legislative decree relating to
the General Regulations of the
Investment Code
Non-existent in
2014
The legislative
decree relating to
the General
Regulations of the
Investment Code
is adopted by the
CM in 2016
Revision and adoption
by the CM of the
Investment Tax
Benefit Code
Investment Tax Benefit Code Old Code existing
in 2015
The Investment
Tax Benefit Code
is revised and
adopted in 2016
Operationalization of
the “After Care”
monitoring and
evaluation system for
private investments.
“After Care” monitoring and
evaluation system for private
investments
Non-existent in
2014
The progress
report on the
“After Care”
system for private
investments is
available in 2017
Operationalization of
the external trade one-
stop shop
The external trade one-stop
shop
Non-existent in
2014
The progress
report on the
external trade one-
stop shop is
available in 2017
Operationalization of
the online business tax
return filing system (e-
tax)
Online business tax return
filing system (e-tax)
The system is
operational for the
VAT in 2015
The progress
report on the
operationalization
of the system is
available in 2016
viii
Issuance by the
Ministry of finance
(MF) of the order
relating to the
operation of the State’s
Counter-Guarantee
Fund and the
replenishment of the
Fund to cover the Cabo
Verde Guarantee
scheme.
Order issued by the Ministry
of finance (MF) relating to the
operation of the State’s
Counter-Guarantee Fund and
the replenishment of the Fund
to cover the Cabo Verde
Guarantee scheme.
The Cabo Verde
Guarantee scheme
is set up in 2014
The MF Order is
issued in 2015
Adoption by the CM of
the bill on insolvency
and the revival of
enterprises
Bill on insolvency and the
revival of enterprises
Non-existent in
2015
The bill is adopted
by the CM in 2016
II.2 – Support for Entrepreneurship and Formalization of Informal Activities
Adoption by the CM of
the three
implementing decrees
of the law on the legal
regime of micro- and
small-sized enterprises
(MSEs): (i) decree on
taxation; (ii)
certification; (iii)
conduct of business
activities
Implementing decrees of the
law on the legal regime of
micro- and small-size
enterprises (MSEs)
Non-existent in
2014
The two decrees
(i) and (ii) are
adopted by the
CM in 2015; the
decree on the
conduct of
business activities
is adopted by the
CM in 2016
Establishment and
operationalization of
five incubators (2
tourism, 1 ITC, and 2
agribusiness)
Number of incubators Non-existent in
2014
The five
incubators are
operational in in
2016
Adoption by the CM of
the implementing
decrees of the law on
microfinance
institutions
The implementing decrees of
the law on microfinance
institutions
The law on
microfinance
institutions is
enacted in 2015
The implementing
decrees are
adopted by the
CM in 2016
Financing: AfDB – EUR 20 million
1
I. INTRODUCTION: THE PROPOSAL
1.1.1 Management hereby submits the following proposal and recommendation to grant a
EUR 20 million African Development Bank loan to the Republic of Cabo Verde to finance the
Economic Growth Support Programme – Phase II (PACE-II). PACE-I presented the multi-annual
framework of the programme and provided a list of reform measures considered as indicative triggers
for the second phase (PACE-II). The programme-based approach selected helps to improve aid
predictability and facilitate alignment with the country’s development policies, thus creating conditions
for sustained, sustainable and inclusive growth.
1.1.2 Cabo Verde was adversely impacted by the 2008 global financial crisis followed by the
European debt crisis which caused a steep fall in foreign direct investments (FDIs) and tourism exports
– the country’s major sources of growth – as well as in remittances. After a period of strong growth of
6.6% on average between 2000 and 2008, the country experienced a year of recession in 2009 before
returning to an average growth rate of 1.3% between 2010 and 2015. It was only in 2016 that recovery
began to gain momentum with a growth rate estimated at 3.8% by the IMF, owing to the revival of
tourism and public administration as well as the agricultural sector due to abundant rainfall. The
sluggish growth period from which the country seems to be emerging was accompanied by a rapid
accumulation of public debt. Given that the country is undergoing transition with its traditional donors
and no longer has access to concessional financing, but also in a bid to implement a counter-cyclical
fiscal policy1, the authorities intensified the use of concessional loans to finance infrastructure projects
and other public investments. Thus, debt rose from 71.9% of GDP in 2010 to 125.9% in 2016.
1.1.3 Economic diversification is essential for long-term growth. Lacking natural resources and
economies of scale to sustain a significant manufacturing base, the economy is concentrated in the
services sector. The authorities’ commitment to diversification is reflected in a clear policy to change
the growth paradigm by placing the private sector, which is a source of employment, at the centre of the
economy, as well as economic infrastructure development and management. Cabo Verde still faces a
twofold challenge: (i) reviving economic growth in order to crane itself to the ranks of upper middle-
income countries (MICs) and provide greater opportunities to its population, especially young people
and women; and (ii) maintaining debt sustainability so as to facilitate access to international financial
markets at a lower cost for the continued financing of its development programmes. To address this
twofold challenge, the Government (GoCV) is focusing its efforts on three areas: firstly, streamline the
management of public enterprises whose recurrent deficits required budget subsidies from the
government – a situation detrimental to the balance of public finances; secondly, boost the efficiency
of investments by introducing a National Public Investment System (SNIP) to ensure that projects come
to full maturity, and to streamline the selection of projects to be financed from the public investment
budget under the PPP arrangement; lastly, create conditions conducive to the emergence of a more
buoyant and competitive private sector, particularly by strengthening inclusive entrepreneurship.
1.1.4 PACE aims to support Government’s efforts through operational objectives to change
the economic paradigm. Concretely, this implies improving public corporate governance and the
public investment framework; modernizing the public-private partnership (PPP) framework; improving
the business environment; and promoting entrepreneurship and formalizing informal sector activities
on the basis of the National Strategy for the Transition from Informality to Formality elaborated by the
government with assistance from partners. Though PACE-I was implemented in 2015, PACE-II
implementation was deferred to 2017 due to delays in completing some key indicators. The triggers not
completed in time for presentation to the Board in 2016 were considered to be important given the
macroeconomic situation and the objectives of PACE-II. They concerned public enterprises and
investments identified as key elements for better budgetary consolidation, and ultimately closely related
to the debt issue. The triggers were completed in 2017, thus achieving PACE objectives.
1 Though significant, this effect is not too pronounced insofar as 90% of the investment programme is composed of imports, thus producing a low
multiplier effect.
2
II. UPDATE ON THE COUNTRY’S ELIGIBILITY
2.1. Criterion 1 – Government’s Commitment to Reducing Poverty
2.1.1 PACE’s programme-based support aligns with two national strategic documents. Until end-
2016, Cabo Verde’s development strategy was detailed in its third-generation Growth and Poverty
Reduction Strategy Paper (GPRSP III) 2012-2016. Approved in May 2013, the GPRSP III was the
reference framework for donor operations, and was based on the principles of the country’s long-term
national vision for development expressed in the Economic Transformation Strategy (ETS) since 2003.
The ETS hinges on the use of Cabo Verde’s geo-strategic position to make the country an international
platform/hub for high value-added services and to expand its productive base. The country’s vision is
to build a competitive, highly diversified and viable economy through the development of seven key
areas, namely: (i) tourism; (ii) maritime economy; (iii) air transport; (iv) information technology; (v)
finance; (vi) creative economy; and (vii) agribusiness. For its part, the GPRSP III defines the following
five thrust areas: (1) infrastructure; (2) human capital development; (3) good governance; (4) private
sector support; and (v) global partnership development. It is within this framework that the Bank’s 2014-
2018 Strategy was developed.
2.1.2 In 2017, Cabo Verde embarked on the development of a new strategy, namely the Economic
Plan for Sustainable Development (PEDS). This plan comprises three strategic thrusts. First, it focuses
on the design of a new economic growth model having as sub-components economic diversification,
structural reforms, and the development of islands as economic units. The second thrust relates to the
provision of social services by the State, human capital, the quality of life and the fight against
inequalities. Lastly, the third thrust concerns a new State model focusing on security, justice, defence
and leveraging diaspora. Though the PEDS has not yet been validated, it has reached an advanced stage
and will be approved by end-2017.
2.1.3 The country’s economic performance has contributed, in an inclusive manner, to
improving the population’s living standards. Improvement in the living conditions of the population
over the past decade has resulted in a significant decrease in the poverty rate in recent decades.
According to the latest Household Consumption Survey (2015), 35% of the population lives below the
poverty line and 10.6% in extreme poverty. However, progress has not been uniform, particularly
among the islands and between urban and rural areas. Poverty rates in islands with the best tourist
infrastructure, notably Sal and Boa Vista, are less than half the national average. Significant progress
has been made in education in recent years. However, the challenge facing the educational system is to
address its mismatch with labour market needs. Generally, basic education is efficient (for instance, in
2015, the literacy rate was more than 80%; the girl/boy parity index was balanced in terms of net
enrolment rates, etc.). However, the challenge is to improve its quality and relevance to the needs of the
economy. Almost half of the country’s private enterprises interviewed in 2009 through a World Bank
survey indicated that the poor quality of the labour force impeded their competitiveness, compared with
less than a quarter on average in Africa. Concerning health, with a life expectancy of 75 years, the
quality of life of Cabo Verdeans is higher than the continental average of 60 years. The main health
sector indicators are much higher than those of most African countries. The Human Development Index
(HDI) stood at 0.646 in 2014, slightly above the average of the so-called middle-income countries which
was 0.630. The infant mortality rate dropped from 22 per 1 000 in 2013 to 21 per 1 000 in 2014 and was
estimated to be about 21 per 1 000 in 2015. However, there are wide disparities in access to and quality
of health services. The country’s geographical isolation makes this equation difficult to solve.
2.2. Criterion 2 – Political Stability
2.2.1. Cabo Verde is one of the most politically stable countries in Africa. It is a model of
democracy on the continent. The country enjoys good political stability, which has been steadily
consolidated over the years thanks to the quality of its democratic system established in 1991 and
strengthened over time. In 2016, the country organized three major elections, namely legislative,
presidential and local elections. These elections were won by the Movement for Democracy (MPD)
3
against the African Party for the Independence of Cabo Verde (PAICV). Cabo Verde scored 7.81 out
of 10 on The Economist Intelligence Unit’s Democracy Index in 2015, ranking 32nd out of 167 countries
in the world and 3rd in Africa after Mauritius (18th globally and 1st in Africa) and Botswana (28th globally
and 2nd in Africa). Cabo Verde’s performance is mainly as a result of the quality of its electoral process
(rated 9.17 over 10) and the high level of civil liberties (9.12 over 10). Cabo Verde is widely recognized
among African countries for its good governance. According to the Mo Ibrahim Index of African
Governance (IIAG), in 2016, the country ranked third out of 52 African countries in terms of governance
performance.
2.3. Criterion 3 – Macroeconomic Stability
2.3.1. Cabo Verde’s economy has
experienced a low level of growth in recent
years despite an expansionary fiscal policy
through an extensive public investment
programme. The deterioration of the
international economic environment resulting
from the 2008 financial crisis on the one hand,
and the 2009 euro crisis, on the other, had a
negative impact on the country’s economy.
After a period of strong growth of 6.6% on average between 2000 and 2008, the country experienced a
year of recession in 2009 before returning to an average growth rate of 1.3% between 2010 and 2015.
It was only in 2016 that recovery began to gain momentum with a growth rate of about 3.2%.
2.3.2 The main objective of the Public Investment Programme (PIP), launched in 2008 and
financed by concessional loans, was to stimulate the country’s growth in order to cope with the
global financial crisis. These substantial public investments coupled with the low level of economic
growth and the tightening of global financial conditions (appreciation of the US dollar) which coincided
with the fall in commodity prices, exacerbated the budget deficit and increased public debt. Thus, debt
increased from 71.9% of GDP in 2010 to 125.9% in 2016. Consequently, the country is now facing
difficult conditions due to the high pressure exerted on public finance, worsened by an uncertain external
environment2.
2.3.3. Faced with the high risk of debt distress, despite comfortable levels of debt service
indicators that are below critical thresholds, the new authorities have embarked on a major fiscal
consolidation policy. To address debt pressure, the authorities have undertaken to consolidate public
finance. In 2015, the public deficit was reduced to 4.1% of GDP, compared with 7.9% set in the initial
budget, and to 3.3% in 2016. This level is much lower than the rates of 7.5% and 8.9% respectively in
2014 and 2013. This reduction is due mainly to the efforts made on the revenue side, with a significant
increase in revenue owing to the broadening of the tax base. On the expenditure side, the slimming
down of the public investment programme also contributed to reducing the deficit. Furthermore, efforts
are being made to reduce the fiscal risks associated with inefficient public enterprises. The authorities
are grappling with the challenges posed by some of these cash-strapped enterprises such as the Cabo
Verde Air Transport Company (TACV) and the Real Estate Company (IFH) whose liabilities stand at
about 20% of GDP. As a result, the authorities resolved to restructure TACV, whose monthly deficit
borne by the taxpayer was almost EUR 3 million, by concluding agreements with private companies to
ensure territorial coverage. Indeed, without the privatisation programme, the accumulation of debts
linked to PEs could add-up to the national debt stock leading it to over 140% of GDP in 2018 rather
than allowing it to take a diminishing trend as currently envisaged (Technical Annex 4).
2 The first set of uncertainties is due to the close link between the domestic economy and Europe, particularly the timid recovery of European economies
and uncertainty about the impact of Brexit.
Table 1: Macroeconomic Indicators
2015 2016(e
) 2017(p)
2018(p
)
Real GDP (Growth) 1.5 3.2 3.7 4.1
Real GDP per Capita (Growth) 0.2 2.0 2.5 2.9
Inflation 0.1 -1.6 0.8 1.6
Overall Balance % GDP -4.1 -3.3 -3.0 -1.9
Current Account Balance %
GDP -4.3 -7.2 -8.8 -8.4
Source: AEO 2017
4
2.3.4. On the whole, the short-term outlook is positive, despite looming major challenges that
will impact growth and development in the long term. GDP growth is expected to reach 3.7% in 2017
and 4.1% in 2018. During the first half of 2017, sector developments, changes in confidence indicators,
prospects in the tourism industry and credit to the private sector have been positive. In 2016, credit to
the private sector rose by 2.1%, though still low. Similarly, a reverse trend has been noted in economic
confidence indicators. However, such changes are largely cyclical. Over the past ten years, total factor
productivity in Cabo Verde has decreased, suggesting a reduction in growth levels in the long term.
There is need to implement structural reforms to improve productivity and the private sector profile.
This is in line with the position adopted by the new Government to create a new growth paradigm driven
by the private sector.
2.3.5. The macroeconomic framework is monitored regularly by the IMF and the Budget Support
Group (BSG) which brings together the TFPs involved in programme-based support operations. The
latest BSG review mission was in June 2017. The IMF and BSG confirmed the stability of the
macroeconomic framework, but underscored the need to address the aforementioned challenges. The
IMF mission’s findings emphasize the need to carry on efforts to improve the performance of public
enterprises and significantly accelerate growth in 2017. The debt sustainability analysis (DSA)
conducted by the World Bank and the International Monetary Fund (IMF) in 2016 indicate that external
debt service ratios are comfortable though the stock of debt represents a high risk.
2.4. Criterion 4 –Fiduciary Risk Assessment
2.4.1. The fiduciary framework assessment conducted by the Bank in Octpber 2016 concluded
that the fiduciary risk was moderate and that the public finance management system fulfilled the
Bank requirements for budget support operations. Overall, Cabo Verde’s public finance
management system, which was deemed strong and reliable in the 2008 PEFA report, has further
improved with the implementation of the 2012 PEMFAR recommendations. The consolidation of the
public finance management system was reflected in the latest PEFA using the 2011 methodology
released in May 2015, with an improvement in the scores of 13 indicators, the maintenance of the scores
of 12 indicators and a drop in the scores of 5 indicators. The new Government formed after the 2016
general (local, legislative and presidential) elections has the necessary tools to develop and manage a
new public finance consolidation strategy for 2017-2020. In accordance with the Paris Declaration and
the Accra Forum on Aid Effectiveness, the Bank will continue to support reforms aimed at strengthening
public finance management, procurement and audit systems. To improve the components whose
weaknesses have been highlighted above, the 2013-2017 Fiduciary Strategy recommends the use of
public finance management systems in their entirety to implement programme-based support operations
such as the Economic Growth Support Programme.
2.5. Criterion 5 – Harmonization
2.5.1. Cabo Verde has made significant progress in implementing the Paris Declaration Principles,
thus strengthening aid effectiveness. Aid to Cabo Verde is aligned with national priorities. Since 2006,
Cabo Verde’s major bilateral and multilateral donors have harmonized their budget support around a
mutually agreed policy matrix. The budget support instrument, which is increasingly taking precedence
over project lending in recent years, is used to leverage collaboration with other development partners
in the country’s public finance management and sector support. The BSG members conduct joint
reviews twice a year, which reduces transaction costs and promotes the harmonization of partners’
procedures and processes. Since the start of CSP implementation, the Bank has taken part in all BSG
meetings and is planning to intensify its contributions, especially once the PEFA action plan becomes
the basis for the BSG common matrix. It should be noted that the Bank will chair the BSG as from
November 2017 for a two-year period.
5
III. PROGRAMME for 2016/2017 – PACE-II
3.1 Programme Goal and Objective
3.1.1 Like PACE-I, the main objective of PACE-II is to contribute to creating the conditions
for strong, inclusive and sustainable economic growth in Cabo Verde. This second phase pursues
the same operational objectives as PACE-I, namely: (i) improve public corporate governance and the
public investment institutional and regulatory framework; (ii) modernize the public-private partnership
institutional and regulatory framework; (iii) improve the business environment; and (iv) promote
entrepreneurship and the formalization of informal activities. Achieving these operational objectives
will help to address the major challenges and constraints that Cabo Verde continues to face, namely: (i)
reviving economic growth in order to hoist itself to the ranks of upper middle-income countries (MICs)
and provide greater opportunities to its population, especially young people and women; and (ii)
maintaining debt sustainability so as to facilitate access to international financial markets at a lower cost
for the continued financing of its development programmes.
3.2 Programme Components
3.2.1 PACE-II is a continuation of PACE as it is structured around the same components,
namely: (i) improvement of public investment effectiveness in order to create conditions for sustained
economic growth whose fruits will benefit a greater proportion of Cabo Verde’s population; and (ii)
support for the promotion of private sector development to stimulate the domestic production of goods
and services. These two components are complementary and mutually reinforcing.
Component I: Improvement of Public Investment Effectiveness and the Public Investment
Regulatory Framework
3.2.2. As outlined in PACE-I, this PACE-II component is meant to support reforms aimed at
improving the institutional and regulatory framework of public investments and public corporate
governance, and modernizing the public-private partnership framework as a source of public investment
financing and equity participation in public enterprises.
3.2.3. Context: efficient management of public investments for better control of the country’s debt
level is a key objective for the new authorities. Over the past few years, Cabo Verde has been
implementing an expansionary policy with concessional financing of structuring public infrastructure
investments to improve the country’s growth level. Although these investments have undoubtedly
increased public debt, they are expected to have a positive impact on the economy’s competitiveness
and, hence, foster growth. However, owing to mostly exogenous concurrent shocks, the expected
outcomes have not been commensurate with the level of investments. Financial difficulties faced by the
national carrier (TACV) and the public real estate corporation (IFH) have negatively affected the
budget, thereby increasing the level of contingent liabilities (the contingent liabilities of the two public
enterprises account for about 20% of GDP). To address this situation, the authorities have embarked not
only on progressive budget consolidation to restore the macroeconomic stability required for sustainable
and inclusive growth and employment, but also on prioritizing the implementation of public investment
projects with strong impacts on growth and employment, and accelerating the process of reorganizing
public enterprises with a view to their future privatization (Technical Annex 4).
3.2.4. Implementation of PACE-I: the implementation of PACE-I in 2015 helped to improve public
investment efficiency through the effectiveness of the following actions precedent: (i) adoption of the
bill on public corporate governance; (ii) preparation of the report on the contingent liabilities of public
enterprises for 2014; and (iii) adoption of the legislative decree on public-private partnership (PPP). In
the same vein, GoCV in December 2015 launched the development of a national system project for
prioritizing and monitoring investments. These key actions have contributed to improving public
corporate governance and modernizing the institutional and regulatory framework of PPPs.
6
3.2.5. Reforms supported by PACE-II: the reforms under PACE-I will be deepened by PACE-II
through the implementation of the following: (i) development and operationalization of a national
system for prioritizing and monitoring public investments (SNIP); (ii) preparation of a public investment
manual and adoption of the decree on the effective use of SNIP; (iii) adoption of implementing decrees
of the law on public corporate governance; (iv) publication of the report on contingent liabilities of
public enterprises for 2015 and 2016; (v) development and operationalization of a public enterprise
monitoring and evaluation system covering the six major enterprises; (vi) formulation and preparation
of a PPP policy and manual to make it easier for UPPP staff to understand and manage PPP financing;
and (vii) setting up of a pipeline of PPP operations with at least three projects that are ready for bid
invitations.
Component II: Support for the Promotion of Private Sector Development
3.2.6. As outlined in PACE-I, this PACE-II component is designed to support reforms aimed at
greater promotion of private sector development by improving the business climate and developing
entrepreneurship.
3.2.7. Context: the new authorities have made private sector development the key element of their
development programme. Concerning the business climate, the country has experienced a downturn due
to the stagnation of reforms, ranked 129th out of 190 countries in Doing Business 2017, against 125th
out of 189 countries in 2016. To address this slowdown in reforms, the authorities embarked on changing
the status of Cabo Verde Invest which led to the creation of Cabo Verde Trade Invest in 2016 with
greater emphasis on investment promotion and facilitation.
3.2.8. Implementation of PACE I: the following reforms were implemented under PACE-I: (i)
adoption of the draft legislative decree on the General Regulations of the Investment Code; (ii) issuance
of an order relating to the operation of the State Counter-Guarantee Fund and its replenishment to cover
the Cabo Verde Guarantee scheme; (iii) adoption of the implementing instruments of the law on the
legal regime of micro- and small-sized enterprises, particularly the decree on taxation and the decree on
certification in 2015; (iv) adoption of a tax package (general tax code, tax enforcement code, tax
procedures code, corporate tax code, revision of VAT, etc.); and (v) adoption of the decree on the Public
Procurement Dispute Settlement Commission.
3.2.9. Reforms supported by PACE-II: PACE-II will support the following reforms: (i) adoption of
the revised Investment Tax Benefit Code to lower the threshold of the fiscal framework agreements; (ii)
operationalization of the private investment monitoring and evaluation system (After-Care); (iii)
operationalization of the online business tax return filing system; (iv) operationalization of the one-stop
shop for external trade; (v) adoption of the bill on insolvency and revival of ailing enterprises; (vi)
adoption of the implementing instruments of the law on the legal regime of micro- and small-sized
enterprises, particularly the decree relating to the conduct of business activities; (vii) the establishment
and operationalization of five incubators, two of them in tourism, one in information technology and
two in agribusiness to encourage private initiative; and (viii) adoption of the implementing decrees of
the 2015 law on microfinance institutions to improve access to micro-credit by SMEs.
3.3. Programme Outputs and Expected Outcomes
3.3.1. The implementation of the first phase of the programme (PACE-I) contributed to mitigating
the negative impacts of the global economic slowdown. The effective implementation of PACE-I
reforms helped to create conditions for greater private sector contribution to the country’s growth and
development process. PACE-II reforms mainly seek to consolidate these achievements with a view to
their effective operationalization.
7
Table 2: Progress Towards Achieving the Output Targets Set in the Logical Framework
Outputs - Reforms Achievements
Component I – Improvement of Public Investment Effectiveness
Output I.1 – Improvement of public corporate governance and the public investment framework
Development and operationalization of
the national public investment
prioritization and monitoring system
(SNIP) in 2016/adoption by the Council
of Ministers (CM) of the decree on the
use of SNIP in 2016
Achieved: the preparation of the system started in January 2015. It was not
operationalized in 2016 because the utilization manual was not completed and
the implementing decrees were not approved. These elements were finalized in
2017. The system is being used to prepare the 2018 budget.
Adoption by the CM of the bill on
public corporate governance in 2015
and the implementing decrees in 2016
Achieved: the bill on public corporate governance was adopted by the Council
of Ministers in 2015. The various implementing decrees were approved in
2016.
Preparation and publication of reports
on the contingent liabilities of public
enterprises for 2014 and 2015
Achieved: the reports on the contingent liabilities of public enterprises for 2014
and 2015 were prepared and published in 2016
Operationalization of the public
enterprise monitoring and evaluation
system (comprising the six major
enterprises) in 2017
Achieved: the first contract signed with a consulting firm for the preparation of
this monitoring system was cancelled due to the firm’s poor performance. The
process of recruiting another firm is on-going. The system could only be ready
in the second half of 2017. Given this situation, an alternative trigger was
discussed. The objective of this trigger is to improve the monitoring of State
participation in public enterprises. In November 2016, the Government
established a Public Enterprise Support Unit (Unidade de Acompanhamento do
Sector Empresarial do Estado “UASE” – through Legislative Decree No.
57/2016). UASE is a special unit responsible for providing support to the
Minister in playing the role of State shareholder and intervening in subsidiaries
of State corporations, as well as in the management and coordination of
privatization and public-private partnership (PPP) processes. It is directly
answerable to the Minister of Finance. Based on the legislative decree and the
powers of UASE, this unit fundamentally has the same objectives as the initial
trigger. Thus, the effective establishment and operationalization of UASE were
adopted as the equivalent alternative trigger. The de facto operationalization of
the unit as well as the following evidence have been checked,: (i) approval, by
the Minister of Finance, of USAE’s Action Plan (by a despacho); (ii) approval,
by the Minister of Finance, of USAE’s structure (by a despacho); (iii) approval,
by the Council of Ministers, of USAE’s pipeline of operations (minutes of the
Council of Ministers); and (iv) presentation of the organization chart approved
by the current experts or those being recruited.
Output I.2 - Modernization of the public-private partnership framework
Adoption by the CM of the legislative
decree on PPPs in 2015 (in replacement
of the 2005 instrument)
Achieved: the legislative decree on PPPs was adopted by the CM in 2015.
Formulation and preparation of the PPP
policy and manual in 2016
Achieved: the PPP policy and manual were formulated and prepared in 2016
Establishment of the pipeline of PPP
operations with at least 3 projects that
are ready for bid invitations in 2016
Achieved: a pipeline of operations with more than 3 PPP projects was
established in 2016
Component II – Support for the Promotion of Private Sector Development
Output II.1 – Improvement of the business environment
Adoption by the CM of the legislative
decree on the General Regulations of
the Investments Code in 2015
Achieved: the legislative decree on the General Regulations of the Investment
Code was adopted in 2015.
Revision and adoption by the CM of the
Investment Tax Benefit Code in 2016
Achieved: the Investment Tax Benefit Code was revised in 2016.
Operationalization of the private
investment monitoring and evaluation
system "After-Care"
Achieved: this reform should be steered by CV-Invest which is facing an
internal organization problem. The attachment and the name of CV– Invest
have changed with focus on promotion and facilitation. An “After-Care”
system project has been prepared and approved by CV-Trade Invest’s Board of
Directors. The After-Care system comprises two components. The first is
composed of an interface accessible to investors to provide them with
assistance in the procedures they are required to follow. This aspect has been
finalized. The second component comprises an interface for monitoring
investors’ obligations relating notably to concessions granted by the State. This
interface has not yet been established. While the finalization of the first
8
Table 2: Progress Towards Achieving the Output Targets Set in the Logical Framework
Outputs - Reforms Achievements
component can be considered as 50% achievement of this trigger, an equivalent
alternative trigger was proposed for the second component by focusing on the
database which will feed the computer platform once it is finalized and relying
on the following evidence: (i) presentation of the database on all the investment
projects implemented since 2014, (ii) finalization of the database with
exonerations granted to investors for investments made over the last three
years; and (iii) sharing of the finalized prototype of the platform.
Operationalization of the online
business tax return filing system (e-tax)
in 2016
Achieved: the online business tax return filing system is operational in 2016
Operationalization of the one-stop shop
for external trade
Achieved: to achieve this indicator according to the initial proposal, the
Government must first adopt the World Trade Organization’s trade facilitation
agreements. Article 10 of these agreements deals with the establishment of the
one-stop shop. This element was not accomplished in the first quarter of 2017.
Pending effective ratification, it was decided that emphasis should be laid on
the establishment of the legal and operational structure for the one-stop shop
for external trade that will enable the effectiveness of the one-stop shop once
the legal process is finalized. Thus, this indicator has been achieved and
checked through the (i) submission to Parliament of the request for ratification
of the WTO Agreement on Trade Facilitation, and (ii) the effective
establishment of the National Trade Commission (Resolution of the Council of
Ministers - Regulamentação).
Issuance in 2015 by the Ministry of
finance (MF) of the order relating to the
operation of the State Counter-
Guarantee Fund and its replenishment
to cover the Cabo Verde Guarantee
scheme
Achieved: the Ministry of finance issued the order relating to the operation of
the Fund in 2015.
Adoption by the CM of the bill on the
insolvency and revival of ailing
enterprises in 2016
Achieved: the bill on the insolvency and revival of ailing enterprises was
adopted in 2016.
Output II.2 – Support for entrepreneurship and the formalization of informal activities
Adoption by the CM of three
implementing decrees of the law on the
legal regime of micro- and small-sized
enterprises (MSEs): (i) decree on
taxation in 2015; (ii) certification in
2015; and (iii) conduct of business
activity in 2016.
Achieved: all the implementing decrees of the law on the legal regime of micro-
and small-sized enterprises were adopted between 2015 and 2016.
Establishment and operationalization of
five incubators (2 in tourism, 1 in ICT
and 2 in agribusiness) in 2016
Achieved: more than five incubators were established and operationalized in
2016.
Adoption by the CM of the
implementing decrees of the law on
microfinance institutions in 2016
Achieved: the implementing decrees were adopted in 2016.
Table 3: Progress Towards Achieving the Output Targets Set in the Logical Framework
Indicators Target Achievements/Remarks
Outcome 1 – Improved public investment effectiveness
PEFA indicator– PI 11 – Public investment
management (new PEFA indicator not
previously assessed)
C (2018) Being achieved: considering the
establishment of the public investment
management unit.
PEFA indicator – PI 12 – Public asset
management (new PEFA indicator not
previously assessed)
C (2018) Being achieved: considering the
establishment of the public investment
management unit.
Number of PPP projects signed by the
Government and being implemented
3 (2017) Achieved : Three privatization transactions
were carried out in 2015 (Garantia, BCA and
ENACOL)
Outcome 2 – Enhanced private sector development
Credit to the private sector (% broad money
supply – M2) (CSI)
6.2% of M2 (2016) Achieved: in 2016, credit to the private
sector represented 9.3% of M2
9
Import and export timeframe (days) Less than 15 days to
import and export
respectively (2016)
Achieved: less than 9 to import and 2.3 days
to export in 2016
Number of new MSMEs established (%
owned by women)
More than 200 new
MSMEs established and
30% of them owned by
women (2016)
Achieved: about 2469 MSMEs established
between 2015 and 2016, 46% of them
owned by women between 2015 and 2016
3.4. Progress Towards Fulfilling Conditions Precedent to PACE-II (list of PACE-II triggers
defined under PACE-I)
3.4.1. The evaluation of PACE-I implementation underscored the effective implementation of
the reforms envisaged in 2015 and the significant progress in the implementation of PACE-II
triggers (possible conditions precedent to PACE-II), as agreed in the initial appraisal report. PACE-
I identified 13 triggers for PACE-II: 9 triggers as initially defined were completely implemented in
2016, 1 trigger was implemented late in 2017 and 3 triggers were revised and implemented in 2017.
3.4.2. Concerning Component I, all the 5 planned triggers were satisfactorily implemented.
However, one trigger was implemented late, while another was revisited due to the technical
problems related to its implementation. Firstly, concerning the operational objective of improving
public corporate governance and the public investment framework, GoCV implemented two out of
the four planned triggers on time and the other two were implemented late. The trigger relating to the
development and operationalization of the national public investment prioritization and monitoring
system (SNIP) was not implemented in 2016 owing to delays in developing these electronic tools (§
Table 3). However, it was completed in 2017. The trigger on the operationalization of the public
enterprise monitoring and evaluation system (covering the six major enterprises) was delayed because
the first contract signed with a consulting firm for the preparation of this monitoring and evaluation
system was cancelled as a result of the consulting firm’s poor performance. Given that the objective of
this trigger is to improve the monitoring of State participation in public enterprises, the Bank teams
have initiated a dialogue with the authorities on this point to find an equivalent alternative trigger that
will produce the same or better outcome. In November 2016, the Government established the Public
Enterprise Support Unit (Unidade de Acompanhamento do SectorEmpresarial do Estado “UASE” –
through Legislative Decree No. 57/2016). UASE is a special unit responsible for providing support to
the Minister in playing the role of State shareholder and intervening in subsidiaries of State corporations,
as well as in the management and coordination of privatization and public-private partnership (PPP)
processes. It is directly answerable to the Minister of Finance. UASE replaces the monitoring system in
the sense that it is the institutional framework and provides the human resources required to ensure the
performance of any monitoring system. Based on the legislative decree and the powers of UASE, this
unit fundamentally has the same objectives as the initial trigger. Thus, the effective establishment and
operationalization of UASE constituted an equivalent alternative trigger. Secondly, concerning the
modernization of the public-private partnership framework, the only trigger provided for was
implemented satisfactorily.
3.4.3. Concerning Component II, 6 out of 8 planned triggers were implemented satisfactorily and on
time, while 2 were readjusted to better achieve the set objectives, and implemented. Firstly, concerning
the improvement of the business environment and support for investment promotion and private
sector development, 3 out of 5 planned triggers were implemented on time. The trigger relating to the
operationalization of “After-Care” was partially implemented (50%) at end- 2016 and concerned the
establishment of an interface accessible to investors in order to provide them with assistance in the
processes they are required to follow. The second component of After-Care comprises an interface for
monitoring investors’ obligations relating notably to concessions granted by the State. It was not
implemented. However, it will only be useable once the database on enterprises benefiting from State
counterpart contribution is established (given that the computer tool is only an interface for data use and
monitoring). Thus, it was proposed that focus should be on the database that will feed the computer
platform once it is finalized. Lastly, concerning the trigger relating to the one-stop shop for external
10
trade, the Government must first adopt the World Trade Organization’s trade facilitation agreements.
Article 10 of these agreements deals with the establishment of the one-stop shop. This element was not
accomplished in the first quarter of 2017. Pending effective ratification, it was decided that emphasis
should be laid on the establishment of the legal and operational structure for the one-stop shop for
external trade which was checked through the (i) submission to Parliament of the request for ratification
of the WTO Agreement on Trade Facilitation, and (ii) the effective establishment of the National Trade
Commission (Resolution of the Council of Ministers - Regulamentação). Secondly, concerning support
for entrepreneurship and the formalization of informal activities, all the planned triggers were
completely and satisfactorily implemented.
3.5. Public Policy Dialogue
3.5.1. PACE is a programme-based operation. It aims to consolidate the gains under previous
operations and support the authorities in implementing key structural reforms which, in addition
to previous reforms, will help to create conditions for sustained and inclusive growth. Thus, during
PACE implementation, dialogue with the Cabo Verdean authorities will focus on the following areas:
(i) enhancing public investment effectiveness through emphasis on the continued improvement of public
corporate governance and the public investment framework as well as modernizing the PPP framework;
and (ii) supporting the promotion of private sector development, in general, and the improvement of the
business environment and entrepreneurship, in particular. The dialogue will be sustained technically by
various on-going institutional support projects in the areas of public-private partnership (PPP) and
public finance. Bank engagement in dialogue will be bilateral and through the Budget Support Group
(BSG). Moreover, the Bank will chair the BSG from November 2017 to November 2020. Lastly, it
should be noted that the Bank has held continuous dialogue with the authorities, especially on the
implementation of triggers agreed beforehand and the use of equivalent alternative triggers in a bid to:
(i) address contingencies in terms of implementing public policy actions; and (ii) adjust actions in order
to maximize the expected outcomes. Three triggers were so reviewed.
3.6. Loan Conditions – Actions Precedent
3.6.1. The presentation of this second phase of the budget support operation to the Fund’s Board of
Directors is subject to the implementation of measures precedent. After consultation with the new Cabo
Verdean authorities, 9 out of a total of 13 triggers (potential actions precedent) were selected as actions
precedent to PACE-II. However, some actions precedent where updated in agreement with the
authorities. Indeed, given the time lag in this second phase for 2017, the authorities have exceeded the
expectations of certain preconditions. If, for example, some evidence were based on the presentation of
draft legislation to the Council of Ministers by 2016, they now take the form of laws approved by
Parliament, thus fully meeting the objectives of the program. Others were updated considering delays
experienced following the changes in legislature and government in 2016. Table 4 summarizes PACE-
II measures precedent and the corresponding evidence.
Table 4: List of Actions Precedent Evidence update
General condition precedent - Maintain a stable macroeconomic framework, as reflected by IMF
or TFP Budget Support Group reports or appraisals. Evidence: certified copy of the press release on
the findings of the last IMF mission or a copy of Budget Support Group’s report on the
macroeconomic framework
Trigger confirmed as action
precedent
n/a
Operational Objectives PACE-II Triggers Defined under
PACE-I Actions Precedent to PACE-II
Component I – Improvement of Public Investment Effectiveness
Improvement of public
corporate governance
and the public
investment framework
Adoption by the CM of the
implementing decrees of the law
on public corporate governance
Evidence: certified copy of the
CM statement on the adoption of
the decrees
Trigger confirmed as action
precedent
Copy of the law on the
governance of state
enterprises
Posting of the report on the
contingent liabilities of PEs for
2014 on MF’s website.
Evidence: certified copy of the
Internet page on which the report
on the contingent liabilities of
PEs for 2014 is posted
Trigger confirmed as action
precedent
n/a
11
Modernization of the
public-private
partnership framework
Formulation of the PPP policy and
preparation of the PPP
manual/establishment of the
pipeline of PPP operations with at
least 3 projects ready for bid
invitations
Evidence: certified copy of the
PPP policy and manual/list of the
pipeline of PPP operations with
the confirmation that at least 3
projects are ready for bid
invitations
Trigger confirmed as action
precedent
n/a
Component II – Support for the Promotion of Private Sector Development
Improvement of the
business environment
Revision and adoption by the CM
of the Investment Tax Benefit
Code to lower the investment
threshold eligible for the fiscal
framework agreement
Evidence: certified copy of the
CM statement on the adoption of
the code
Trigger confirmed as action
precedent
Copy of the law approving the
code.
Operationalization of the online
business tax return filing system
(e-tax).
Evidence: progress report on the
operationalization of the system
for the first half of 2016
Trigger confirmed as action
precedent
Copy of the “e-tax” web page
Adoption by the CM of the bill on
the insolvency and revival of ailing
enterprises
Evidence: certified copy of the
CM statement on the adoption of
the bill
Trigger confirmed as action
precedent
Copy of the law on the
insolvency and revival of
ailing enterprises
Support for
entrepreneurship and
the formalization of
informal activities
Adoption by the CM of the
implementing decree of the law on
the legal regime of micro- and
small-sized enterprises (MSEs):
Conduct of business activity
Evidence: certified copy of the
CM statement on the adoption of
the decree
Trigger confirmed as action
precedent
Copy of the law on the fiscal
regime for micro and small
enterprises.
Establishment and
operationalization of five
incubators (2 in tourism, 1 in ICT
and 2 in agribusiness)
Evidence: progress report on the
operationalization of the five
incubators for the first half of
2016
Trigger confirmed as action
precedent
Operationalisation certificate
from the Cabo Verdia
authorities and ADEI’s 2016
report.
Adoption by the CM of the
implementing decrees of the law
on microfinance institutions
Evidence: certified copy of the
CM statement on the adoption of
the decrees
Trigger confirmed as action
precedent
Copy of the law regarding
micro-finance institutions.
3.7. Application of Best Practice Principles on Conditionality
3.7.1. In accordance with the Bank’s policy on programme-based operations3, PACE-II design
took into account the five best practice principles on conditionality. The best practice principles on
conditionality were followed. The activities of development partners were coordinated for better
complementarity of operations in support of the country’s policies through Budget Support Group
reviews conducted in July and November 2016. The programme is fully in line with Cabo Verde’s
national policies and helps to support the country’s remarkable efforts to create sustainable and inclusive
conditions for strong economic growth. The actions precedent selected relate primarily to major
structural reforms aimed not only at consolidating the gains of previous programmes, but also at
significantly contributing to improving public investment effectiveness and promoting a more buoyant
private sector. Furthermore, PACE-II is aligned with the country’s budgetary cycle, thus allowing
GoCV to include it in its 2017 budget.
3 See Ref: ADF/BD/WP/2011/38/Rev.3/Approval of 29 February 2012.
12
3.8. Financing Needs
3.8.1. This programme-based budget support operation
is an integral part of the external financing sources that
will help to bridge the financing gap for the 2017 financial
year. Initially planned for 2016, the operation was supposed to
contribute to addressing a financing need in 2016. Due to its
postponement to 2017, the country had to resort to a higher
(and also more costly) domestic financing of CVE 1.6 billion.
For 2017, the financing needs stand at CVE 28.3 billion,
notably due to immediate costs incurred by the restructuring of
TACV. However, this restructuring is expected, in the medium
term, to enable the State to make substantial savings. As a
result, these needs are higher than originally foreseen (about
CVE 27 billion), mainly due to lower non-fiscal revenues and
an increase in net liabilities. It is within this framework that the
Bank's initial contribution of EUR 15 million has been
increased to EUR 20 million. To meet its need, GoCV resorted
to domestic financing to the tune of CVE 9.4 billion and
external financing of CVE 18.3 billion. Budget support
contribution stands at CVE 7.7 billion in the form of external financing. Thus, the Bank will provide
CVE 2.2 billion. Other partners of the Budget Support Group and the financial market will provide the
rest of the external financing in the form of budget support.
IV. PROGRAMME IMPLEMENTATION
4.1. Programme Beneficiaries
4.1.1. As explained in PACE-I, PACE-II will benefit the entire Cabo Verde population. The
outcomes of sound public investment management and a more developed private sector will improve
the population’s living conditions. Good public corporate governance will lead to the improvement of
the quality of public services provided to users. Efforts to facilitate access to financing and training
aimed at supporting the establishment and development of MSEs will make the private sector more
dynamic and responsive to increased opportunities resulting from the implementation of major public
investment projects. These positive impacts will boost the country’s economic growth for the good of
the entire population. Enhanced structuring of public investment management will not only create
conditions for sustained economic growth, but also contribute to improving the country’s competiveness
and capacity to attract private domestic and foreign investments.
4.1.2. PACE design mainstreamed the gender dimension during consultations with stakeholders,
including the Cabo Verdean Association for the Empowerment of Women (MORABI) and the Cabo
Verdean Institute for Gender Equality and Equity (ICIEG). It emerged from these consultations that
while Cabo Verde ranks high in the World Economic Forum's gender equality index in general, it is
only 115th out of 144 countries in terms of participation and economic opportunities for women.
Economically active women are mainly concentrated in the trade sector (about 1/3rd), 13% as domestic
workers, and 8% in agriculture. All these sectors are characterized by a high rate of informal activities.
Women run about 38% of firms, but only 18% of those with formal accounting. According to
UNWOMEN, policies to promote the private sector do not address substantive issues. Moreover, both
the means and advocacy capacities are insufficient. It is on this basis that PACE intends to have a
positive impact on gender issues, in general, and the status of women, in particular, notably through
major structural reforms that sustain the promotion of entrepreneurship through the operationalization
of incubators in the tourism and agribusiness sectors where women are most active.
Table 5: Financing needs (CVE millions)
2017
A - Total revenues (exc. Grants) 43,156
Fiscal revenue 35,534
Other 7,622
B - Total expenditure 55,487
C- Overall deficit (A-B) -12,331
D - Other net liabilities -7,104
E - Depreciation -8,875
F - Financing needs (C+D+E) -28,309
G - Financing, of which 27,651
Domestic financing 9,318
External Financing, of which 18,333
- Project Loans 10,621
- Partner Development Budget Support 7,713
African Development Bank (loan) 2,205
European Union (grant) 1,764
Portugal (grant) 55
Luxembourg (grant) 220
Others (loans) 3,467
FINANCING GAP -658
Source : GdCV/FMI/BAD
13
4.2. Implementation, Monitoring and Evaluation
4.2.1. The Ministry of finance (MF) will implement PACE. Overall responsibility for the
implementation of the Programme rests with MF which has already satisfactorily managed and
coordinated previous programmes funded by the Bank and other TFPs. It will rely on the National
Directorate of Planning (DNP) for the day-to-day programme management and monitoring. However,
it should be underscored that to ensure a participatory implementation process, all stakeholders will be
involved in programme implementation.
4.3. Financial Management, and Disbursement and Reporting Arrangements
4.3.1. Country Fiduciary Risk Assessment (CFRA): the fiduciary framework assessment
conducted by the Bank in October 2016 concluded that the fiduciary risk was moderate and that
the public finance management system fulfilled Bank requirements for budget support
operations. On the whole, Cabo Verde’s public finance management system, which was deemed strong
and reliable in the 2008 PEFA report, has further improved with the implementation of the
recommendations of PEMFAR 2012. This consolidation of the public finance management system was
highlighted in the last PEFA conducted using the 2011 methodology and published in May 2015, with
an improved score for 13 indicators, the same score for 12 indicators and a drop in the score of 5
indicators. The new Government that emerged from the 2016 general elections (local, legislative and
presidential) has the tools to develop and manage a new public finance consolidation strategy for 2017
– 2020. In accordance with the Paris Declaration and the Accra Forum on Aid Effectiveness, the Bank
will continue to support reforms aimed at strengthening public finance management, procurement and
audit systems. To improve the components whose weaknesses have been highlighted above, the
fiduciary strategy for 2013-2017 recommends the use of public finance management systems in their
entirety for implementing programme-based support operations, such as the Economic Growth Support
Programme (PACE).
4.3.2. Financial management, audit and disbursement mechanism: in compliance with the
fiduciary strategy defined for the 2014 -2018 CSP period, PACE will be entirely managed within
the national public finance management system. Disbursement projections for 2017 are included in the
2017 Appropriation Act. The general compliance report prepared by the Audit Bench on the accounts
of the 2015, 2016 and 2017 financial years will serve as the programme’s audit report. In line with the
programme-based approach, the loan will be disbursed in a single tranche of EUR 20 million to finance
the implementation of the 2017 budget. Once the loan becomes effective and the conditions precedent
to loan disbursement are fulfilled, the single tranche will be disbursed pursuant to the terms of the Loan
Agreement. At the Borrower’s request, the Bank will release funds into a special account denominated
in Euro opened with the Central Bank of Cabo Verde.
4.4. Procurement
Bank financing through an AfDB loan will be in the form of general budget support.
Consequently, its implementation does not raise direct issues of procurement of goods, works and
services. The evaluation of the national procurement system, which is governed by Law No. 88/VIII/2015
of 14 April 2015 on the Public Procurement Code, conducted by the Bank in November 2011, concluded
that Cabo Verde’s procurement regulations are largely compliant with the Bank’s procurement policy
standards, except for a few discrepancies that will be discussed by the Bank and the authorities of Cabo
Verde as part of the evaluation of the Borrower’s procurement system.
V. LEGAL FRAMEWORK
5.1. Legal Instrument
5.1.1. The legal instrument that will be used for this Programme is the Loan Agreement between the
Republic of Cabo Verde (the Borrower) and the African Development Bank (the Bank).
14
5.2. Conditions for Bank Intervention
5.2.1. Conditions precedent to effectiveness: effectiveness of the Loan Agreement shall be subject to
fulfilment, by the Borrower, of the conditions set out in Section 12.01 of the General Conditions Applicable
to Bank Loan and Guarantee Agreements.
5.2.2. Conditions precedent to disbursement of resources for the second phase of the PACE
programme-based operation. In addition to the conditions precedent set out in 5.2.1 above,
disbursement of the loan resources totalling EUR 20 million shall be subject to the following condition:
Provide the Bank with the references of the Treasury bank account opened at the Bank of Cabo Verde
in Praia into which the loan resources will be transferred.
5.3. Compliance with Bank Group Policies
5.3.1. This operation is consistent with two operational priorities of the Bank’s Ten-Year Strategy,
namely: strengthening private sector governance and private sector development. It is also in line with
the Bank’s ‘High 5s’, particularly “improve the quality of life for the people of Africa”. PACE-II, which
is in keeping with the Bank’s CSP 2014-2018, is consistent with the CSP’s Pillar 2 relating to the
strengthening of economic governance in the public and private sectors. PACE is also aligned with the
Bank’s Private Sector Development Policy 2013-2017, especially its Pillar 1 which relates to the
improvement of the business and investment climate. The Programme is also in line with Pillar 2 of the
Bank’s Gender Strategy 2014-2018 on women’s economic empowerment. The reforms supported are
consistent with Pillar 1: "Public Sector Management and Economic Management" and Pillar 3:
"Investment and Business Climate" of the Governance Action Plan 2014-2018 (GAP II). For this
operation, no waiver has been requested in respect of Bank Guidelines.
VI. RISK MANAGEMENT
Table 6 below presents the potential risks and mitigation measures.
Table 6 : Risks and Mitigation Measures
Risks Mitigation Measures
Macroeconomic risk: An unfavourable macroeconomic
situation and exogenous shocks could affect programme
implementation. This situation is even more worrying due
to the high vulnerability of Cabo Verde vis-à-vis the Euro
Zone where recovery seems slightly timid. Level: High
This type of risk is the subject of an ongoing dialogue with
the authorities and is monitored regularly as part of the
activities of the BSG which meets twice a year (May and
November) and the IMF under Article IV. The latest BSG
and IMF analyses point to the achievement of
macroeconomic stability in the country in the medium
term. Moreover, there is need to step up macroeconomic
consolidation efforts, especially on debt reduction and
economic diversification.
Risk related to human capacity: although above the
regional average, the human capacity of government
services is limited. If allowed to persist, this situation could
slow down or even halt the implementation of the reform
programme. Level: Average
To encourage ownership of the reforms to be promoted,
this programme will be accompanied by a number of
technical assistance and capacity building projects,
particularly in the areas of public investment management,
public-private partnerships and the business climate.
VII. RECOMMENDATION
It is recommended that the Board of Directors approve a loan of EUR 20 million in the form of
programme-based general budget support for the Republic of Cabo Verde to finance the Economic
Growth Support Programme-Phase II (PACE-II).
X
Annex 2
CABO VERDE – Economic Growth Support Programme
Matrix of Programme Reforms
Objectives Reforms Indicators
Operational Objectives Intermediate
Objectives 2015 Reforms 2016 Reforms Output Indicators Outcome Indicators
Component I –Improvement of Public Investment Effectiveness
Improvement of public
corporate governance
and the public
investment framework
Modernization of
the public
investment
management
system
Signing of a contract for
the development of the
national public
investment
prioritization and
monitoring system
(SNIP)
Development and
operationalization of the
national public investment
prioritization and
monitoring system (SNIP)
[Trigger1]
The consultancy contract
for the development of
SNIP is signed before
end-2015; and SNIP is
operational before end-
July 2016. .
PEFA Indicator PI 11 on
public investment
management (new PEFA
indicator not previously
assessed):
Tar
Adoption by the Council of
Ministers of the decree
relating to the use of SNIP
The decree on the use of
SNIP is adopted before
end-July 2016
Preparation of a public
investment manual
The manual is prepared
by end-July 2016
Strengthening of
public corporate
governance
The implementing
decrees are adopted
before July 2016
PEFA Indicator PI 12
"Public Assets
Management" :
Publication of the report on
the contingent liabilities of
The report on the
contingent liabilities of
XI
Objectives Reforms Indicators
Operational Objectives Intermediate
Objectives 2015 Reforms 2016 Reforms Output Indicators Outcome Indicators
public enterprises (PEs) for
2014 [Trigger 3]
public enterprises (PEs)
for 2014 is posted on the
MF website before end-
July 2016
Operationalization of the
public enterprise monitoring
and evaluation system
(including the six major
enterprises)
[Trigger 4]
The PE monitoring and
evaluation system is
operational before end-
July 2016
Modernization of the
framework governing
public-private
partnerships
Modernization of
the PPP
framework
Adoption by the Council
of Ministers of the
legislative decree on
PPP (replacing the 2005
instrument)
[Action precedent 3]
Preparation of the PPP
Policy and PPP Manual
[Trigger 5]
The CM adopts the
legislative decree on
PPPs before end-
October 2015; The PPP Policy and
Manual are available
before end-July 2016
Number of PPP projects
signed by the Government
Setting up of the pipeline of
PPP operations with at least
3 projects ready for bid
invitation
[Trigger 5]
The pipeline of PPP
operations is set up
before end-July 2016
Component II – Support for the Promotion of Private Sector Development
Adoption of the
legislative decree on
General Regulations of the Investment Code by
the Council of Ministers
The legislative decree
of General Regulations
on investments is
adopted by the CM
before end-October
The overall Country
Competitiveness Index:
XII
Objectives Reforms Indicators
Operational Objectives Intermediate
Objectives 2015 Reforms 2016 Reforms Output Indicators Outcome Indicators
Improvement of the
business environment
Improvement of
the transparency
and
attractiveness of
the investment
framework
[Action precedent 4] 2015]
Adoption by the CM of
a tax package (General
Tax Code, Tax
Enforcement Code,
Tax Procedure Code,
Corporate Tax Code,
VAT revision),
allowing for better
ownership of the tax
environment by private
enterprises
Revision and adoption of the
Investment Tax Benefit
Code to lower the
investment threshold eligible
for the fiscal framework
agreement [Trigger 6]
The CM adopts the tax
package before end-
October 2015
The Tax Benefit Code
is revised and adopted
by the Council of
Ministers before end-
July 2016
Operationalization of the
After Care system for the
monitoring and evaluation of
private investments
[Trigger7]
The After Care system
for private investments
is operational before
end-July 2016
Facilitation of
administrative
and commercial
procedures
Adoption by the
National Trade
Commission of the
Trade Action Plan for
facilitating trade
procedures
Operationalization of the
external trade one-stop shop
[Trigger 8]
The Action Plan is
adopted before end-
2015;
The one-stop shop is
operational before
end-July 2016
Doing Business Indicator:
Time to import or export
(days)
(2016)
Operationalization of the
online business tax return
filing system (e-tax) (given
that the VAT is already
electronic) [Trigger 9]
The online business tax
return filing system is
operational before end-
July 2016
XIII
Objectives Reforms Indicators
Operational Objectives Intermediate
Objectives 2015 Reforms 2016 Reforms Output Indicators Outcome Indicators
Improvement of
access to
financing and
business legal
procedures
Issuance of the order
relating to the operation
of the State Counter-
Guarantee Fund and its
replenishment to cover
the Cabo Verde
Guarantee scheme
[Action precedent 5]
The order of the
Minister of Finance and
Planning relating to the
operation of the State
Counter-Guarantee
Fund covering the Cabo
Verde Guarantee
scheme is issued before
end-October 2015 Credit to the private sector
(% broad money supply –
M2)
of M2
(2014);
broad money supply (2016)
Adoption by the Council
of Ministers of the
decree relating to the
Public Procurement
Dispute Settlement
Commission
The decree relating to
the Public Procurement
Dispute Settlement
Commission is adopted
by the CM before end-
2015
Adoption by the Council of
Ministers of the bill on the
insolvency and revival of
enterprises
[Trigger 10]
The bill on the
insolvency and revival
of enterprises is adopted
by the CM before end-
July 2016
Support for
entrepreneurship and
formalization of
informal activities
Broadening the
base of
entrepreneurship
and improving
access to micro-
credit
Adoption of two
implementing decrees
of the law on the legal
regime of micro- and
small-sized enterprises
(MSEs) (i) Decree on
taxation (2015); (ii)
Certification (2015)
[Action precedent 6]
Adoption of the
implementing decree of the
law on the legal regime of
micro- and small-sized
enterprises (MSEs): conduct
of business activity [Trigger
11]
The two decrees are
adopted by the CM
before end-October
2015;
The last decree is
adopted before end-July
2016
Number of new MSMEs set
up (% by women):
0 new
enterprises (30% of them
women-owned)
enterprises established
under MSE regime (30% of
them women-owned)
before end-2016
XIV
Objectives Reforms Indicators
Operational Objectives Intermediate
Objectives 2015 Reforms 2016 Reforms Output Indicators Outcome Indicators
Establishment and
operationalization of five
incubators (2 tourism, 1 ICT,
2 agribusiness)
[Trigger 12]
Five incubators are
operational before end-
July 2016
Adoption of implementing
decrees of the law on
microfinance institutions
[Trigger 13]
The implementing
decrees are adopted by
the Ministry of Youth
Affairs before end-July
2016
XV
Annex 3
Outcomes of Previous Budget Support Operations in Cabo Verde
Public Finance Management and Private Sector Recovery Support Programme (PAGF-
RSP): 2011-2012
Improvement of Public Finance Management and Macroeconomic Stability
Bank support helped to: (i) reduce government arrears stock from 16% in 2009 to 0% in 2011 and
2012; (ii) reduce the timeframe for submission to the National Assembly of the General State Account
(CGE) and the Notice of Compliance issued by the Court of Auditors (CoA) from 24 months on
average before 2010 to 12 months in 2012; (iii) increase the number of services covered by the
General State Inspectorate (IGF) from 32 in 2010 to over 46 in 2012; (iv) reduce the average
procurement timeframe from eight months in 2010 to less than three months in 2012; and (v) increase
the cases of dispute handled by the Public Procurement Regulatory Agency (ARAP) according to the
new legislation in force from 50% in 2010 to 100% in 2012. The various reforms introduced are: (i)
availability of a medium-term strategy 2012-2015 for State debt management; (ii) availability of 2009
and 2010 reports on the State’s contingent commitments and liabilities; (iii) availability of the public
finance management system reform programme that emanated from PEMFAR recommendations; (iv)
effective appointment of the remaining members of the Board of the Public Procurement Regulatory
Agency (ARAP) and members of the Dispute Settlement Commission; and (v) availability of ARAP’s
audit report on public procurement contracts awarded in 2010.
Creation of an Enabling Environment for the Revival of the Private Sector
Bank support helped to: (i) improve Cabo Verde’s ranking in the Doing Business report on company
bankruptcy from 183rd out of 183 countries in 2010 to 178th out of 183 countries in 2012; (ii) increase
the number of SMEs registered in the Citizen’s House Network from 913 in 2010 to 1197 in 2012;
and (iii) improve Cabo Verde’s ranking in the Doing Business indicator on getting credit from 152nd
out of 183 countries in 2010 to 97th out of 183 countries in 2012. The various reforms introduced are:
(i) availability and adoption by the Council of Ministers of the new Investment Code; (ii) availability
and adoption by the Council of Ministers of a Tax Incentives Code, compliant with WTO rules; (iii)
introduction of new windows for the Citizen’s House; and (iv) setting up of two new incubators.
Public Corporate Governance and Investment Promotion Support Programme
Phases I and II (PAGEPPI I and II): 2013 - 2014 Improvement of Public Corporate Governance
Structural reforms in the area of corporate governance helped improve the performance of public
enterprises. The Cabo Verde Air Transport Company (TACV) is on track to post a profit this year
(2015). All major public enterprises have signed performance contracts with the State to guarantee
that they will be properly managed. The main achievements are: (i) adoption of statutory instruments
operationalizing the 2009 law on public enterprises, provided for under Section 52 (1) of that law (Lei
No. 47 /VII/2009); (ii) evaluation of the regulatory authorities, preparation and adoption by the
Government of an action plan to review their articles of association for the purpose of reforming these
regulatory bodies, as provided for by Law No. 14/VIII/2012; (iii) production by MF and availability
in 2014 of the annual report on the liabilities of public enterprises for 2013; and (iv) signing of three
additional performance contracts in 2014 between the State and other major public enterprises (ASA,
ENAPOR and EMPROFAC).
Investment Promotion Credit to the private sector is increasing, despite relative stagnation. The main achievements include:
(i) adoption by the Council of Ministers of legislative decrees to operationalize the law relating to the
General Investment Code in order to facilitate the establishment of a one-stop shop for investors; (ii)
adoption of the decree to establish and operationalize the PPP Privatization and Promotion Unit; and
(iii) production in 2013 and 2014 of a report containing criteria for assessing priority investments and
prospective PPP projects.
XVI
Annex 4
NOTE ON RELATIONS WITH THE INTERNATIONAL MONETARY FUND
On November 18, 2016, the Executive Board of the International Monetary Fund (IMF)
concluded the 2016 Article IV consultation with Cabo Verde. A staff visit took place in June
2017. Its conclusions are still to be published.
According to the latest article IV report, Cabo Verde appears to be at the threshold of a recovery
from the growth slowdown of 2012-15. However, the economy remains vulnerable to external
shocks notably from Europe, the main source of tourism revenue, FDI and remittances. The
Public Investment Program, while addressing key infrastructure gaps, has contributed to a
marked rise in public debt (125.8 percent of GDP in 2015). The Debt Sustainability Analysis
indicates that debt risks are high on account of the elevated stock of debt, while debt service
indicators remain comfortable.
Going forward, the IMF is of the opinion that policies should focus on sustaining the growth
momentum while curbing public debt. This would include revaluating the public investment
pipeline with a view to reducing externally financed capital spending, and encouraging the
private sector to take on a larger role in investment and growth. Over the medium term,
continued implementation of the ambitious structural reform agenda is critical to help the
country reap the benefits of the infrastructure investment scaling up.
IMF staffs’ opinion is that Cabo Verde is at a crucial stage in its economic development where
the private sector will need to take over as driver of growth as public investment will gradually
decline. Given the high public debt and several major investment projects at or near completion,
the authorities have decided to gradually phase out the PIP. Private investment needs to take
over as the main growth engine in order to take advantage of the improved infrastructure and
ensure sustained long-term growth. To that end, accelerating the privatization program is an
important step in the right direction. In addition, the authorities need to continue improving the
business climate, enhancing the efficiency of the financial sector, and ensuring private sector
compliance with the new labour code.
Staff forecast an acceleration of the recovery, but vulnerabilities remain. Staff expect growth to
continue to pick up speed and reach about 4 percent in the medium term, powered by tourism
and trade, and supported by FDI, remittances and private sector credit growth. Accelerated
progress on structural reforms could help growth reach an even higher trajectory. However,
vulnerabilities remain. Remittances and tourism growth could be thwarted by the implications
of Brexit on both the UK and the euro area, and credit to the private sector could be held back
by a slow resolution of NPLs.