31
Translated Document AFRICAN DEVELOPMENT BANK GROUP SENEGAL WATER AND SANITATION SECTOR PROJECT - PSEA DEPARTMENT OWAS April 2014

AFRICAN DEVELOPMENT BANK GROUP · PDF fileAFRICAN DEVELOPMENT BANK GROUP ... Dakar and Ziguinchor, estimated at 250,000, ... 3.1 +125 000 (65 000 women) in 2018 . v

Embed Size (px)

Citation preview

Translated Document

AFRICAN DEVELOPMENT BANK GROUP

SENEGAL

WATER AND SANITATION SECTOR PROJECT - PSEA

DEPARTMENT OWAS

April 2014

TABLE OF CONTENTS

Acronyms ......................................................................................................................................... i

Project Summary……………………………………………………………………………… iii

Management’s report and recommendation to the board of directors concerning

the ADF loan and RWSS grant to senegal for the water and sanitation sector project 1

I- STRATEGIC THRUST AND RATIONALE .................................................................... 1

1.1 Project Linkages with Country Strategy and Objectives ............................................ 1

1.2 Rationale for Bank's Involvement ................................................................................. 1

1.3 Aid Coordination ......................................................................................................... … 2

II- PROJECT DESCRIPTION 3

2.1 Project Components .................................................................................................... 3

2.2 Technical Solutions Adopted and Alternatives Considered ........................................ 3

2.3 Project Type ................................................................................................................ 4

2.4 Project Cost and Financing Arrangements .................................................................. 6

2.5 Project Target Area and Beneficiaries ........................................................................ 6

2.6 Participatory Approach ............................................................................................... 6

2.7 Bank Group Experience and Lessons Reflected in Project Design ............................ 7

2.8 Key Performance Indicators ........................................................................................ 7

III- PROJECT FEASIBILITY ................................................................................................. 8

3.1 Financial and Economic Performance......................................................................... 8

3.2 Environmental and Social Impact ............................................................................... 8

Environment.................................................................................................................. 8

Climate Change............................................................................................................ 9

Gender.......................................................................................................................... 9

Social........................................................................................................................... 10

Involuntary Resettlement............................................................................................... 10

3.3 Sector Monitoring and Evaluation............................................................................... 10

IV. IMPLEMENTATION................................................................................. 11

4.1 Implementation Arrangements ................................................................................ 11

4.2 Project Monitoring and Evaluation ......................................................................... 13

4.3 Governance.............................................................................................................. 13

4.4 Sustainability ........................................................................................................... 14

4.5 Risk Management .................................................................................................... 15

4.6 Knowledge Building ............................................................................................... 16

V- LEGAL FRAMEWORK ............................................................................................. 16

5.1 Legal Instrument ..................................................................................................... 16

5.2 Conditions for Bank Intervention ....................................................................... 16

VI- RECOMMENDATION ................................................................................................... 17

Annex 1: Comparative Socio-economic Indicators of Senegal…………………………… .......... I

Annex 2: Table of AfDB Portfolio in Senegal ................................................................................ II

Annex 3: Key Related Projects Financed by the Bank and Other Development Partnerss .......... III

Annex 4: Map of Project Area ........................................................................................................ IV

Annex 5 : Summary Presentation of Procurement procedures ..................................................... V

i

Currency Equivalents

(December 2013)

UA 1 = CFAF 740.68

Fiscal Year

1 January – 31 December Weights and Measures

1 ton (t) = 2,204 pounds 1 millimetre (mm) = 0. 03937 inch

1 kilogram (kg) = 2.204 pounds 1 kilometer (km) = 0.62 mile

1 meter (m) = 3.28 feet 1 hectare (ha) = 2.471 acres

Acronyms and Abbreviations

ABEDA Arab Bank for Economic Development in Africa

ADF African Development Fund

AFD French Development Agency

AfDB African Development Bank

ANSD National Agency for Statistics and Demography

ASUFOR Borehole Users’ Association

AWF African Water Facility

BTC Belgian Technical Cooperation

CSP Country Strategy Paper

DA Department of Sanitation

DEM Directorate of Operations and Maintenance

DGPRE Directorate of Management and Planning of Water Resources

DH Department of Hydraulics

DWS Drinking Water Supply

EA Executing Agencies

EIB European Investment Bank

EIG Economic Interest Grouping

IEC Information, Education and Communication

IGA Income Generating Activity

IsDB Islamic Development Bank

IWRM Integrated Water Resources Management

MDGs Millennium Development Goals

MHA Ministry of Water and Sanitation

NGO Non-Governmental Organization

OFOR Rural Boreholes Board

ONAS National Sanitation Board

PA Project Area

PEPAM Millennium Drinking Water and Sanitation Programme

PRSES Sector Monitoring and Evaluation Strengthening Plan

PSE Senegal Economic Emergence Plan

PSEA Water and Sanitation Sector Project

RAP Resettlement Action Plan

RWSSI Rural Drinking Water Supply and Sanitation Initiative

SNDES National Strategy for Economic and Social Development

UNIFEM United Nations Development Fund for Women .

WB World Bank

WSS Water Supply and Sanitation

ii

LOAN INFORMATION

Client information

BORROWER/GRANTEE: Republic of Senegal

EXECUTING AGENCY: PEPAM Coordination Unit (PEPAM- CU)

Financing Plan

Source Amount (UA Million) Instrument

ADF 20 Loan

RWSSI 5.34 (EUR 6 million) Grant

Government 13.66 Counterpart

contribution

Beneficiaries 0.49 Contribution

TOTAL COST 39.49

Key AfDB Financial Information

ADF Loan Currency: Unit of Account (UA)

RWSSI Grant Currency : EUR

Description Rural Areas Urban Areas

Economic Analysis ERR : 34.53%

NPV : CFAF 29.16 billion

ERR : 23.08%

NPV: CFAF 12.85 billion

Financial Analysis FRR : 12.20%

NPV : CFA F 316 million

Timeline – Main Milestones (Expected)

Concept Note Approval

November 2013

Project Approval April 2014

Effectiveness July 2014

Completion July 2018

Last Disbursement December 2018

Last Reimbursement December 2054

iii

PROJECT SUMMARY

1. Project Overview: The Water and Sanitation Sector Project (PSEA) is part of the Millennium

Drinking Water and Sanitation Programme (PEPAM), launched by Senegal in 2005, to ensure the

achievement of the Millennium Development Goals. It comprises (i) a rural component designed to

improve access to drinking water supply and sanitation by the populations of the Louga, Kaffrine and

Tambacounda Regions, in continuation of the two previous Bank operations and (ii) an urban

component to rehabilitate and extend the Dakar and Ziguinchor sanitation networks. Furthermore, the

project will help improve the sector’s governance through: (i) the establishment of an appropriate

monitoring and evaluation mechanism; (ii) implementation of the action plan for integrated water

resources management; and (iii) support to privatized management of rural drinking water facilities. Its

implementation will span 4 years. Its total cost, excluding taxes and customs duties is estimated at UA

39.49 million.

2. The project’s direct beneficiaries are the rural populations of the Louga, Kaffrine and

Tambacounda Regions, estimated at 500,000 and the urban populations in the districts concerned in

Dakar and Ziguinchor, estimated at 250,000, thus representing a total of 750,000, 52% of whom are

women. In the project area, it will contribute towards: (i) improving the drinking water supply and

sanitation (DWSS) access rate; (ii) reducing by at least one half, cases of malaria and diarrheal

diseases; (iii) lowering health-related expenses; and (iv) creating approximately 5,000 temporary jobs

and 500 permanent jobs, of which 2,500 and 300 for women and youth.

3. Needs Assessment: The two previous Bank projects have helped improve rural drinking water

and sanitation access rates in the three target Regions (Louga, Kaffrine and Tambacounda). However,

wide access-rate disparities remain, with some Regions still showing rates of below 45% for drinking

water and 30% for sanitation, against a national average of 81.2% and 35.6%, respectively. In urban

areas, antiquated and inadequate sewage and storm water drainage systems account for the heavy wet

season floods recorded, that have claimed human lives and caused substantial property damage. In

September 2012, the Government organized a donor roundtable to support the funding of PEPAM’s

financing gap and implementation of the Emergency Phase of the Ten-Year Flood Control Programme,

targeting amongst others, the cities of Dakar and Ziguinchor. Furthermore, (i) the weakness of the

existing monitoring and evaluation system; (ii) the delay in implementing the Integrated Water

Resources Management (IWRM) Action Plan and (iii) limited private sector involvement in the sub-

sector in rural areas constitute major constraints on the sector’s development.

4. Bank’s Added Value: The Bank was PEPAM’s lead donor in rural areas with the financing of

two operations (in 2005 and 2009). In 2001, it also funded the rehabilitation and extension of the

Cambérène waste water treatment station. It has played a lead role in attracting donors to the sector and

its experience from financing previous urban and rural projects is reflected in the design of the present

project. Its experience will also benefit the country by enhancing the sector’s monitoring and evaluation

system.

5. Knowledge Management: The PSEA and Sector monitoring and evaluation mechanisms to

be used will generate relevant information on the project’s impact and will permit proper overall

monitoring of PEPAM activities. The knowledge acquired will inform the Bank’s future operations.

iv

RESULTS-BASED LOGICAL FRAMEWORK

REPUBLIC OF SENEGAL : Water and Sanitation Sector Project (PSEA)

Project Objective`0: To boost for the long term, access to drinking water and sanitation in rural (Louga, Kaffrine, and Tambacounda Regions) and urban (Dakar and Ziguinchor) areas

RESULTS CHAIN

PERFORMANCE INDICATORS

MOV

RISKS/

MITIGATION

MEASURES Indicator (including CSI) Baseline Target

Improved living conditions

for the Senegalese people

1. Access to drinking water (% rate)

2. Access to improved sanitation systems (% rate)

3. Poverty rate (%) 4. Prevalence of malaria (%)

5. Prevalence of diarrheal diseases (%)

1. 81.2% (rural) and 90.1%

(urban)

2. 35.6% (rural) and 62.4 % (urban)

in 2012

3. 46.7 % (national) in 2011 4. 3%. in 2013

5. 4.8% in 2013

1. 95% (rural) and 100% (urban) in 2025

2. 80% (rural) and 90% (urban) in 2025

3. 37.89 % (National) in 2018 4. 1.5 % in 2018

5. 2.16 % in 2018

Sources: SNDES

/ PES Information

System

ANSD reports

OU

TC

OM

E

Outcome 1: Improved

access to safe drinking

water and sanitation in

Louga, Kaffrine and

Tambacounda

1.1 Persons served by improved sources (including

women) 1.2 People with access to improved sanitation

(including women)

1.3 Rate of functionality of DWS systems (%)

1.1 4.26 million (2.22 million

women) 1.2 1.87 million (0.97 million

women)

1.3 95%

1.1 4. 41 million (2.29 million women)

in 2018 1.2 2.07 million (1.08 million women) in

2018

1.3 100% in 2018

Sources:

Reports from

MHA, ANSD,

project activity reports and annual

sector review.

National and

regional WASH surveys ASUFOR Statutes

and Rules and Regulations

Risks

- Delay in mobilizing national counterpart

contribution

- Delays in completing

sanitation works

- Imbalance of

operating accounts in

the sanitation sector

Mitigation Measures

- State’s firm

commitment to

financing sanitation (SNDES / PES)

Outcome 2: Improved

access to sanitation in

Dakar and Ziguinchor

2.1 Persons having access to connections and sanitation services (including women) (PEPAM)

2.2 Performance of sanitation networks (rate in %) (Volume of waste water collected and disposed

of against volume of waste water produced)

2.1 4.524 million (2.352 women)

2.2 Less than 40% in Dakar and

non-existent in Ziguinchor

2.1 4.774 million (2.482 million) in 2018

2.2 At least 60% in Dakar and at least

80% in Ziguinchor

Outcome 3: Improved

hygiene behaviour in the

project area

3.1. People making hand washing a habit (%) (including women)

3.1 Not available (to be collected via household surveys)

3.1 +125 000 (65 000 women) in 2018

v

Outcome 4: Improved

technical viability and

governance of the sector.

4.1 Establishment of a monitoring and evaluation

mechanism for the sector

4.2 Existing ASUFOR having delegated

production and operation to the private sector

(in %)

4.3 Percentage of women in positions of

responsibility in ASUFOR

4.1 0

4.2 0

4.3 30%

4.1 1 M&E mechanism in 2018

4.2 66% in 2018

4.3 50 %

ASUFOR Statutes and Rules and

Regulations

-Establishment of a mechanism to monitor

and mobilize the

counterpart contribution (SNFO /

PEPAM-CU)

- Better targeting of

businesses by keeping

a list of efficient

contractors

-Review of ONAS financial model

OU

TC

OM

ES

Component A

1. Rural DWSS and urban sanitation infrastructure

provided .

Component B

2.1 Support to IWRM

2.2 Support to sector reform

2.3 Strengthening sector M&E

2.4 Capacity building for

women and stakeholders

1.1 Number of boreholes

1.2. Number of water supply systems

1.3. Number of water supply systems rehabilitated

1.4. Urban sanitation networks (ml)

1.5. Number of pumping stations

1.6. Number of wastewater treatment plants

1.7. Number of household connections

1.8. Number of household latrines and public

toilets

1.9 Number of jobs (including for women)

2.1 Studies on the IWRM

2.2 Studies on sector reform

2.3 Strengthening M & E

2.4 Number of female community workers trained

1.1. 0

1.2. 0

1.3. 0

1.4. 0

1.5. 0

1.6. 0

1.7 0

1.8 0

1.9 0

2.1 0

2.2 0

2.3 0

2.4 0

1.1 20

1.2 20

1.3 10

1.4 23 km in Dakar (including 3 km in

the stormwater network), 22 km in

Ziguinchor

1.5 1 in Dakar, 1 in Ziguinchor

1.6 1 in Ziguinchor

1.7 7 250

1.8 17 000 household latrines and 40

public toilets

1.9 5000 temporary and 500 permanent

(respectively 2500 and 300, women)

2.1. Studies validated (water management

plans, hydrogeological and hydrological studies)

2.2 Studies on sector reform validated

2.3 The 14 sector M & E actions implemented

2.4 150 female community workers trained

Sources:

Reports from

MHA, EDS, project activity

reports

PEPAM’s annual

sector review

Bank’s

supervision

mission reports

Risk

- Delays due to poor

performances of construction

contractors;

Mitigation Measures

- Raising level of selection criteria in

competitive bidding

and efficient procurement

allotments.

vi

COMPONENTS

KE

Y A

CT

IVIT

IÉS

COMPONENT A : Infrastructure Development: UA 28.68 million

COMPONENT B : Institutional and Reform Support: UA 7.57 million

COMPONENT C : Project Management: UA 2.57 million

Total Project Cost UA 39.49 million

ADF LOAN: UA 20.0 million Government : UA 13.66 million

RWSSI GRANT: UA 5.34 million Beneficiaries : UA 0.49 million

Project Implementation Schedule

Years 2014 2015 2016 2017 2018

Activities / Months T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4

PRIOR TO START-UP

Board Presentation /Approval

Publication of General Procurement Notice

Signature of Protocol and Loan Agreements

Effectiveness

Conditions Precedent to 1st Disbursement

Launching Mission

RURAL DWS

Procurement

Execution of Works

Works supervision and Inspection

RURAL SANITATION

Procurement

Execution of Works

Works Supervision and Inspection

URBAN SANITATION

Procurement for Dakar

Execution of Works for Dakar

Works Supervision and Inspection for Dakar

Procurement for Ziguinchor

Execution of Works for Ziguinchor

Works Supervision and Inspection for Ziguinchor

INFORM. EDUC. COMMUNIC. (IEC)

Procurement

Information, Education and Information

Activities

vii

IWRM ACTIVITES

Procurement

PMU Management Plan of basins (BA and BS)

Hydrogeological and Hydrological Studies (VS and CT)

Popularization of Instruments and Training

SECTOR MONITORING AND EVALUATION

Procurement

Study and Establishment of Sector Monitoring and Evaluation

REFORM SUPPORT

Miscellaneous Activities

PROJECT COORDINATION AND MONITORING

Procurement

Institutional Support

Project Coordination and Monitoring

ANNUAL ACCOUNTS AUDIT

COMPLETION REPORT

Preliminary

Activities

Works

Miscellaneous

Activities

Project Accounts Audit

Procurement

Supervision

Project Monitoring

1

MANAGEMENT’S REPORT AND RECOMMENDATION TO THE BOARD OF

DIRECTORS CONCERNING THE ADF LOAN AND RWSSI GRANT TO SENEGAL

FOR THE WATER AND SANITATION SECTOR PROJECT

Management submits the following report and recommendation on a proposed ADF loan of UA 20

million and RWSSI grant of UA 5.34 million to the Republic of Senegal to finance the Water and

Sanitation Sector Programme.

I Strategic Thrust and Rationale

1.1 Project Linkages with Country Strategy and Objectives

1.1.1 The Water and Sanitation Sector Project (PSEA) is designed to improve the living conditions

of the Senegalese people. It is fully in line with the objectives and thrusts of Senegal’s Economic

Emergence Plan (PSE) under the National Economic and Social Development Strategy (SNDES

2013-2017), adopted on 8 November 2012, notably as concerns Thrust 2 "Human Capital, Social

Protection and Sustainable Development", and Thrust 3 "Governance, Institutions, Peace and

Security" (see paragraph A.1 of technical Annexes).

1.1.2 The PSEA is consistent with the Bank’s intervention strategy in the country (Country Strategy

Paper, CSP 2010-2015), as revised in April 2013, in particular its Pillar 2 "Management of Natural

Resources (including water) and Resilience”. It is fully consistent with the Bank’s Ten-Year

Strategy (2013-2022) and its new Gender Strategy (2014-2018). It does contribute towards

achieving two major objectives of the Ten-Year Strategy by addressing three of its five operational

priorities, notably infrastructure development, improved governance and support to private

sector development. In terms of gender, the project is in line with Pillar 2 of the Strategy, namely

"Economic Empowerment". Indeed, in addition to access to drinking water and sanitation services,

it will contribute towards (i) strengthening women’s involvement in the management of the public

drinking water service in rural areas, (ii) creating jobs for women and youth, and (iii) training on

Information, Education and Communication (IEC). Lastly, the project is consistent with (i) the

strategy of the Rural Drinking Water Supply and Sanitation Initiative (RWSSI), (ii) the Bank’s

urban development strategy and (iii) the Integrated Water Resources Management policy.

1.2 Rationale for Bank’s Involvement

1.2.1 With the implementation of PEPAM, the country has made great strides in rural drinking

water supply access, whose rate rose from 69.5 % in 2006 to 81.2% in 2012. However, wide intra-

regional access-rate disparities remain, including where the Bank’s first two sub-programmes were

undertaken. Some yet unreached districts (départements) in the said Regions still show low rates of

access to safe drinking water and sanitation services, standing at below 45% and 30% respectively,

as against a national average of 81.2 % for water and 35.6 % for sanitation. This project will

contribute towards correcting such disparities (A.5 Technical Annexes).

1.2.2 In the wet season, Dakar and Ziguinchor witness heavy rains which heighten the poor

sanitation as well as flood intensity and frequency, causing loss of human lives and significant

property damage. This situation, which in the past led to riots, is due to an antiquated and deficient

sewage and stormwater drainage network that is extremely dysfunctional.

2

With the ongoing densification and extension of drinking water supply networks in Ziguinchor, the

rehabilitation/extension of sewerage networks has become a priority.

1.2.3 In terms of sector governance, the continued implementation of the Integrated Water

Resources Management (IWRM) Action Plan developed by Senegal since 2004 remains a priority,

for: (i) ensuring enhanced knowledge of water resources; (ii) adequate catering for the country’s

water needs; and (iii) making proposals for integrated and sustainable management of resources.

Additionally, despite all the progress achieved with the advent of PEPAM in 2005, the sector’s

current monitoring and evaluation system remains partial, disparate and insufficiently

institutionalized. Data on DWSS, hygiene-related behaviours, water resources and sector efficiency

remain unreliable, insufficiently disaggregated and incomplete (A.5.6 Technical Annexes). These

weaknesses hinder investment planning and good governance in the sector. Moreover, they

constrain the implementation of ongoing reforms, notably in terms of public-private partnership.

The PSEA will contribute towards removing these two major constraints.

1.3 Aid Coordination

1.3.1 The sector’s leading donors are ADB, World Bank, EU, AFD, JICA, BOAD and Belgian

Technical Cooperation. Their positioning by sub-sector (rural and urban) is an appropriate approach

to meet the numerous needs and balance financing (see paragraph A.7 of the Technical Annexes).

The Bank plays a key role in the sector, mainly in the rural sub-sector. With the opening of the

country office, the Bank has enhanced its role in sector dialogue.

Table 1.3 : Aid Coordination

*The percentages represent the respective shares of each donor in the overall amount of UA 623. 8 Million

1.3.2 Donor coordination is done through PEPAM, a unified framework for intervention in the

sector. Annual reviews are held to provide updates on the programme’s implementation status and

synergize the actions of technical and financial partners. Such coordination is reinforced by the

establishment of the Consultative Group of donors with an urban and a rural platform to facilitate

internal dialogue and ensure better articulation of interventions in the sector.

Sector or sub-sector*

Scope*

GDP Exports Labour

Drinking Water and Sanitation NA NA NA

Stakeholders – Public Expenditure Over the Period 2005 -2012

Government Donors Percentage (%)

UA 102.4 million

14.4 %

UA 623.8 million

85.6 %

AfDB 15 %

IDA 11%

EU 10 %

JICA 8 %

AFD 6%

BOAD 5%

Level of Aid Coordination

Existence of thematic working groups Yes

Existence of a global sector programme Yes

Role of AfDB in aid coordination * Member

3

In terms of monitoring and evaluation, sector coordination among key development partners will be

revitalized around the sector’s Monitoring and Evaluation Enhancement Plan (PRSES 2013-2017),

resulting from the workshop organized by the Bank during the PSEA appraisal mission. The Bank

will provide leadership in the Plan’s implementation process (see A.5.6 of the Technical Annexes).

II. Project Description

2.1 Project Components

Table 2.1.1: Project Components

2.2 Technical Solutions Adopted and Alternatives Considered

2.2.1 For the rural component, the technical solutions adopted are those used under PEPAM. For

the urban component, technical solutions are based on sanitation master plans financed by EIB and

AWF, for Dakar and Ziguinchor respectively.

2.2.2 For the rural component, the technical solutions are similar to those used in the two Bank-

financed rural DWSS sub-programmes.

Component

Name

Cost Estimate

(UA million)

Description of Components

A Development of

DWS and

Sanitation

Infrastructure

16.75

(42.4 %)

11.93

(30.2 %)

This component comprises two sub-components:

1. Rural DWS and Sanitation Infrastructure, including Supervision: (i)

Drilling of 20 boreholes; (ii) Drilling/Rehabilitation of 30 multi-village

DWSS systems; (iii) Extension of water supply systems; (iv) Building

of 17,000 household latrines and 40 public toilets; (v) Provision of

7,250 individual connections; and (v) Works supervision and

monitoring.

2. Urban Sanitation Infrastructure, including Supervision: (i) Renewal

of 20 km of network; (ii) Extension of 3 km of sewerage networks; (iii)

Construction of 22 km of new sewerage networks; (iv) Construction of

2 pumping stations and two sewage treatment plants; (ii) Works

supervision and monitoring.

B Institutional and

Reform Support

7.57

(19.2 %)

This component comprises:

(i) IEC in rural and urban areas; (ii) Support to rural and urban reform; (iii)

Support to IWRM implementation; (iv) Enhancement of the sector’s

monitoring and evaluation system; (v) Gender and social ; (vi) Capacity

building for women and stakeholders; and (vii) technical support to the

executing agencies.

C PSEA Management 2.57

(6.7 %)

This component comprises all the administrative and financial management

activities of the sub-project, namely: (i) Support to the functioning of the

PEPAM coordination unit and executing agencies; (ii) Technical and financial

monitoring of the project; (iii) Project monitoring and evaluation; (iv) Project

auditing; and (iv) Studies and monitoring of environmental aspects of the

PSEA.

Resettlement Action

Plan (RAP)

0.67

(1.7 %)

The preparation of the abridged RAP follows encroachment by the Ziguinchor

treatment plant on some farmlands.

4

For the DWS, they consist in the construction/rehabilitation of multi-village systems, comprising

boreholes, water towers and pumping equipment with the extension of networks to villages that are

far between and providing individual connections and standpipes. The options of drilling boreholes

by locality and human-powered water pumps were ruled out given the excessive cost of the former

and the ineffectiveness of the latter. For sanitation, the options consist in providing household

latrines and public toilets at public centres, with priority to health centres and schools. The use of

sewerage networks and mini-networks was not considered appropriate given the low volume of

water consumed.

2.2.3 Regarding sanitation in Dakar, the decision was taken to replace the antiquated networks

and construct new networks to enable people to connect to the existing public system. Additionally,

the wastewater pumping capacity will be strengthened with the construction of a new pumping

station. In targeted neighborhoods, semi-offsite sanitation is more suitable than on-site sanitation

systems due to the existence of the sewerage network.

2.2.4 The Ziguinchor Sanitation Master Plan (PDAZ) is based, inter alia on: (i) the construction

of on-site sewer disposal systems in difficult-access areas; and (ii) the choice of off-site and semi-

offsite sanitation in areas where technical conditions are conducive to the connection of wastewater

networks to a treatment plant (WWTP). Given the favourable technical conditions (accessibility,

housing type, etc.) in the targeted areas, this project has opted for the off-site sanitation system.

2.3 Project Type

The PSEA was designed as a standalone investment operation.

2.4 Project Cost and Financing Arrangements

2.4.1 The total cost of the PSEA, net of tax, is estimated at UA 39.49 million of which UA 20.57

million in foreign exchange (52%) and UA 18.92 million in local currency (48%). This estimate is

based on the unit price of recent projects and includes 5% and 3% provisions for physical

contingencies and a price escalation, respectively. Detailed cost tables are shown at B.2 of the

Annexes.

5

Table 2.4.1: Project Cost Estimate by Component

Table 2.3.2: Sources of Financing [in UA million]

Sources of Financing Total Cost % total

ADF 20.00 50.65

RWSSI Fund 5.34 13.91

Government 13.66 34.20

Beneficiaries 0.49 1.24

TOTAL COST 39.49 100.00

2.4.2 The Project will be financed by (i) an ADF loan of UA 20 million ( 50.65 % of total cost );

(ii) an RWSSI grant of UA 5.34 million (13.91 % of total); (iii) the Government to the tune of UA

13.66 million (34.20 % of total); and (iv) Beneficiaries to the tune of UA 0.49 million (0.84% of

total). The ADF will finance 57 % of the cost of urban sanitation activities, 32 % of the cost of rural

activities and the entire project management cost. The RWSSI fund will co-finance: (i) the

construction of household latrines, public toilets and private connections; (ii) rural works

supervision and IEC; (iii) Support to the establishment of monitoring and evaluation of the sector

and reforms; and (iv) training of women and sector stakeholders. The Government’s contribution

will partially finance the Infrastructure Development and the Institutional and Reform Support

components as well as all costs related to compensation for the construction of the Ziguinchor

treatment station. The beneficiaries will contribute only to the financing of household latrines and

individual connections. The breakdown of financing by activity is given in paragraph B2 of the

Technical Annexes.

Components UA Million

% in FE FE Cost LC Cost Total Cost

A. Infrastructure Development

Rural DWSS infrastructure 9.24 6.27 15.51 60

Urban sanitation infrastructure 7.19 3.86 11.05 65

B. Institutional and Reform Support

Support to IWRM 0.22 1.24 1.46 15

Support to rural reform 0.05 0.57 0.62 8

Support to urban reform 0.03 0.35 0.38 8

IEC, Gender, sector M & E, Environment 1.58 2.36 3.94 40

Support to executing agencies and stakeholders 0.12 0.49 0.61 2

C. Project Management

Project management 0.61 1.63 2.24 27

Implementation of ESMP 0.01 0.13 0.14 10

Total Base Cost 19.05 16.90 35.94 53

Physical and Financial Contingencies 1.52 1.35 2.88

Total Cost 20.57 18.25 38.82

Resettlement Action Plan (RAP) 0.67 0.67

TOTAL COST 20.57 18.92 39.49 52

6

Table 2.4.3: Project Cost by Expenditure Category

Expenditure Category UA Million

% in FE FE Cost LC Cost Total Cost

GOODS 0.79 1.01 1.80 43.75

WORKS 15.18 10.12 25.30 60.00

SERVICES 4.54 4.67 9.21 49.17

OPERATION 2.48 2.48 0.00

Total Cost, including Contingencies 20.51 18.28 38.8 52.84

Resettlement Action Plan (RAP) 0.67 0.67 0.00

TOTAL COST 20.51 18.98 39.49

Table 2.4.4 Expenditure Schedule by Component (UA million)

Components 2014 2015 2016 2017 2018

A. Infrastructure Development

5.25 10.59 7.69 4.91

B. Institutional and Reform Support 0.078 2.74 2.81 1.29 0.93

C. Project Management 0.49 0.51 0.51 0.51 0.51

Resettlement Action Plan (RAP 0.67

Total Cost 1.25 8.50 13.90 9.49 6.35

2.5 Project Target Area and Beneficiaries

The project covers the Louga, Kaffrine and Tambacounda Regions for rural DWSS and for urban

sanitation the cities of Dakar and Ziguinchor. The direct beneficiaries of the project are 500,000

people in rural areas and 250,000 people in urban areas, representing a total of 750,000 people of

whom 52 % are women. The main project outcomes are:

(i) improved DWSS access rate , (ii) reduction by at least 50% of malaria and 55% of diarrheal

disease cases, (iii) lower health expenditure; (iv) creation of over 5,000 temporary jobs and 500

permanent jobs for women and youth.

2.6 Participatory Approach during Project Identification, Design and Implementation,

including by the Private Sector and Civil Society

2.6.1 A participatory process was used throughout the project formulation, notably during (i) the

development of local water and sanitation plans by rural communities; (ii) the conduct of the rural

component studies in the three Regions; and (iii) updating of the Dakar and Ziguinchor sanitation

master plans. At all these stages, the populations were consulted on the proposed technical

solutions. In preparation and appraisal missions important work sessions were held with the

beneficiaries, which helped secure their support for the project but also identified capacity building

actions based on needs expressed by households, local authorities, Rural Borehole Users

Associations (ASUFOR ) and women's and youth associations. Regarding sector monitoring and

evaluation, consultations were held with the various project executing agencies, the Coordination

Unit and development partners. They enabled (i) preparation of a detailed status report with an

analysis of key gaps and priority needs; and (ii) the holding, on the sidelines of the appraisal

mission, of an information sharing workshop involving all the sector stakeholders to define the

Sector Monitoring and Evaluation Enhancement Plan (PRSES 2013-2017).

7

2.6.2 Concerning of the Ziguinchor wastewater treatment plant which will affect some rice

farms, public consultations were held at the commune with the affected communities, NGOs and

elected officials through which their support for and participation in the project were secured. The

participatory approach will be maintained at all stages of the implementation of PSEA activities.

Community volunteers will be identified to report on project activities.

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 The performance of the Bank's portfolio in the country is deemed satisfactory with an

overall rating of 2.49 in 2012, up from 2.01 in 2009. Regarding the DWSS sector, the last two

Bank-financed operations under PEPAM performed satisfactorily. The first sub-programme,

approved in 2005 was closed in 2010, exceeding set targets. The second one approved in 2009,

shows a physical implementation rate of 90 % for a disbursement rate of 75%. Its closing date is 31

December 2014.

2.7.2 However, the various portfolio reviews have highlighted the major constraints on the

implementation of projects in the country, namely: (i) unavailability of technical studies prior to

appraisal; (ii) the absence of a common approach to IEC in the DWSS sector to facilitate

sensitization and make it effective; (iii) the poor performance of rural sanitation SMEs; and (iv) a

weak DWSS monitoring and evaluation system. The design of this operation has reflected these

lessons through: (i) the availability of recent technical studies; (ii) adoption of a common approach

to IEC; (iii) preparation of a list of companies selected on the basis of their performance in the last

two operations; and (iv) financing of capacity building activities for the establishment of an

appropriate monitoring and evaluation system.

2.8 Key Performance Indicators

2.8.1 To monitor the project, the current monitoring and evaluation system of PEPAM-CU will

be used by the M&E expert who will work with the Executing Agencies. The performance

indicators selected are: (i) number of boreholes drilled; (ii) number of multi-village water supply

systems provided; (iii) number of household latrines constructed; (iv) number of rural individual

connections; (v) number of urban pumping stations and treatment plants built; (vi) length of urban

sanitation networks provided; (vii) number of permanent jobs created; (viii) number of female

community volunteers trained; (ix) number of studies validated and actions implemented under the

various sector support programmes (IWRM, Reforms, sector Monitoring and Evaluation, etc. ) .

8

III. Project Feasibility

3.1 Economic and Financial Performance

Table 3.1 : Key economic data

ERR: Rate of return NPV: Net Present Value

3.1.1 The costs used to calculate economic profitability are those relating to investment costs,

excluding taxes and provision for price increases as well as maintenance costs and other operating

expenses. The key economic benefits are: (i) the economic value of the additional volume of water

produced; (ii) health-related budget savings of beneficiaries due to lower prevalence of waterborne

diseases; (iii) education budget savings due to fewer health-related school failures; (iv) temporary

and permanent jobs created during the construction of the facilities; and (v) savings on the water-

fetching time which is used gainfully. On this basis, the economic rate of return of the project’s

rural component is estimated at 34.53%, while that of the urban component stands at 23.08% with

Net Present Values (NPV) of CFAF 29.16 billion and CFAF 12.85 billion respectively. These rates

surpass the opportunity cost of capital estimated at 10%. Therefore, the project is economically

viable (see Annex B7).

3.1.2 The project’s EIRR sensitivity was analyzed in relation to: (i) 10% increase in investment

costs; (ii) 10% reduction in health-related benefits; (iii) 10% decrease in terms of time saved; and

(iv) 10% decrease in flood-mitigation benefits. For each of these assumptions, the internal rate of

return remained higher than the opportunity cost of capital and the NPV remained positive. Indeed,

the EIRR ranged from 34.53% to 34.11% for rural areas and 23.08% to 13.07% for urban areas,

while the NPV remained positive ranging from CFAF 29.16 billion to CFAF 28.37 billion francs

for rural areas and from CFAF 12.85 billion to CFAF 12.84 billion for urban areas.

3.2 Environmental and Social Impact

3.2.1 The project is classified in Category 2 under the Bank’s environmental classification given

its significant contribution towards improving the living conditions of people who will henceforth

enjoy improved access to drinking water and sanitation. A strategic environmental assessment of

the project was conducted leading to the development of an Environmental and Social Management

Plan (ESMP). Besides the piping, the Ziguinchor sanitation component comprises a pumping station

and a lagooning plant which were the subject of a comprehensive environmental and social

assessment (CESA) validated by the authorized services of the country. Based on the findings of the

CESA, the project appraisal mission proposed the development of an abridged Resettlement Action

Plan (abridged RAP) in accordance with the Bank’s safeguard policies to specifically address the

encroachment of the treatment plant on some farmland located within its easement. Summaries of

the strategic environmental assessment as well as the abridged RAP have been validated and posted

on the Bank’s website.

Description Rural Areas Urban Areas

Economic Analysis ERR : 34.53%

NPV : CFAF 29.16 billion

TRE : 23.08

NPV : CFAF 12.85 billion

9

3.2.2 The project will have significant positive impacts on the environment concerning: (i)

improved quality of life of populations; (ii) increased public awareness of hygiene and management

of DWSS facilities; (iii) better protection of sanitation facilities; and (iv) improved water resources

management

3.2.3 Its negative impacts associated with the construction phase are notably: (i) constraints to

mobility; (ii) noise and dust raised by vehicles; and (iii) risk of accidents. (See Section B.8 of

Technical Annexes). These negative impacts are easily mitigated by the ESMP measures (see

details in paragraph B.8 of the Technical Annexes).

3.2.4 The total cost of the ESMP is estimated at UA 0.142 million. It will be implemented in

conjunction with all stakeholders. The project will sign an agreement with the Department of the

Environment and will be assisted in the Regions by the Regional Divisions of the Environment and

Classified Establishments (DREEC) located in its area of intervention. The latter will carry out the

environmental monitoring.

Climate Change

3.2.5 Key Issues: The main issues identified are irregular recharge of groundwater due to rainfall

disruption, water quality and flooding.

3.2.6 Mitigation: The project includes studies on IWRM for better knowledge of resources and

establishment of a water resources and quality monitoring mechanism. Sewerage networks will be

put in place and the separation of "sewage" and “rainwater" networks will facilitate stormwater

drainage.

Gender

3.2.7 A detailed analysis of the socio-economic and Gender situation is presented in Annex B8.2. In

its design, the project paid special attention to increasing women’s representation in decision-

making within the borehole users’ association (ASUFOR), which is among the crucial elements of

the management of the rural drinking water service. In the various ASUFORs that will be set up for

the management of boreholes drilled under the project, women will occupy at least 50 % of

management positions, against a national average currently estimated at 30 %. To ensure their

effective participation in these bodies, the project will finance specific training cycles for them as

well as for youth on administrative, technical, financial and accounting management of rural

drinking water and sanitation facilities. In view of the transfer of maintenance and construction of

rural motorized boreholes to the private sector, these actions will foster future involvement of

women and youth in this sector. Additionally, the project will have an impact on (i) improving

women's income with the recruitment and training of 150 female community workers responsible

for IEC activities and (ii) improving the attendance rates of young people with the reduction of the

time devoted to fetching water. For better monitoring, the programme will strengthen IEC activities

and involve the Ministry in charge of Women and Gender.

10

3.2.8 In urban areas, capacity building is planned for associations and for women’s and youths’

Economic Interest Groupings (EIG) on solid waste collection, conveyance and management. An

NGO or specialized IEC firm will be hired for this purpose. The support will cover training in IEC

and maintenance of facilities, equipment and materials (wheelbarrows, brooms, shovels,

motorcycles, bicycles, gloves, boots, shovels, mufflers, rakes, etc.), to enable the associations and

EIGs to better raise public awareness on the protection of the works and to ensure their

sustainability in Dakar and Ziguinchor. Community leaders will be sensitized on hygiene and

trained on gender issues.

Social

3.2.9 Besides providing sufficient water, the project will benefit health, education and

employment. It will gradually decrease malaria prevalence from 3% to 1.5%. It will also help

reduce the prevalence of certain diseases such as diarrhea and typhoid. The prevalence of these

diseases in the project area is respectively 4.8% and 3.8%. The project is expected to create 5,000

temporary jobs (3,000 rural and 2,000 urban) and 500 permanent jobs (300 urban and 200 rural),

with average monthly salaries of CFAF 70 000 and CFAF 60,000 respectively.

Involuntary Resettlement

3.2.10 The Ziguinchor priority sanitation programme will entail small-scale resettlement (less

than 200). The treatment plant south of the city, within the limits of the municipality (commune),

may encroach on farmland most of which has been abandoned. An abridged RAP will be developed

by the Senegalese party and approved by the Bank. It will take into account compensation in

accordance with the country’s regulations and the Bank’s environmental and social protection

policies.

3.3. Sector Monitoring and Evaluation

3.3.1. The inadequacy of the sector’s monitoring and evaluation system referred to in paragraph

1.2.3 needs to be corrected to ensure the availability of reliable, timely and sufficiently

disaggregated data and foster efficient investment planning as well as information and good

governance in the sector. This will be done through the support provided for under PSEA but also

through coordination with other development partners on the Sector Monitoring and Evaluation

Enhancement Plan (PRSES 2013-2017).

3.3.2 Specific support of this project includes 14 actions from PRSES 2013-2017. These focus

on : (i) the definition/update of performance and outcome indicators for the sector; (ii) capacity

building for data collection, processing and storage at the central and decentralized levels (with, for

instance national and regional WASH surveys among households in collaboration with the National

Statistics and Demography Agency); (iii) harmonization and integration of sub-systems and

databases managed by different actors in a centralized monitoring and evaluation system (e.g.

within the framework for the establishment at DGPRE of the Integrated System of information on

Water );

11

(iv) development of information from monitoring and evaluation of the sector through support to

sector reviews and an impact assessment study (impact of drinking water and sanitation services on

health, education, employment, etc.).

3.3.3 The main outcomes expected from these actions are: (i) enhanced monitoring and

evaluation capacity of decentralized institutional structures (EAs); (ii) better coverage of rural areas;

(iii) more regular supply of information on sanitation and hygiene practices; and (iv) improved

collaboration between the Ministry responsible for the sector (MHA) and the National Statistics and

Demography Agency (ANSD) on data collection. (See paragraphs A.5.6 and A.8 Technical

Annexes).

IV. Implementation

4.1 Implementation Arrangements

4.1.1 Like the two Bank-financed sub-programs, the various PSEA components will be

implemented under PEPAM, through the PEPAM Coordination Unit (PEPAM-CU) which will

carry out the coordination as well as the administrative and financial management of the project,

monitoring of cross-cutting issues and steering of the monitoring and evaluation of the sector. The

Department of Economic and Financial Cooperation (DCEF) and the Investment Department (DI)

will monitor the financial execution of the project (See paragraph B.3 Technical Annexes).

4.1.2 The Water Resources Department (DH) and the Operations and Maintenance Department

(DEM) will be Project Owners for the drinking water component. The Sanitation Department (DA)

will be Project Owner for the rural sanitation component. The National Sanitation Authority

(ONAS) will be Project Owner for the urban sanitation component (Dakar and Ziguinchor). The

Water Resources Management and Planning Department (DGPRE) is responsible for activities and

studies on IWRM. At regional level, the implementation of the PSEA will be supported by

decentralized services of the sector. The evaluation of the coordinating body and the various

executing agencies (see paragraph B5.3 of the Technical Annexes) concluded that the experience

and performance of these structures in project management are satisfactory. Projects are completed

on schedule. Furthermore, sub-annual interim and annual financial statements are produced on time

and have been certified by the auditors without qualification. The Government will undertake to

maintain the current staff of PEPAM - CU.

4.1.3 Steering Committee: The existing PEPAM Steering Committee will ensure articulation

between activities under the project and the actions of other PEPAM components as well as

consistency with sector policies. This Steering Committee will coordinate all project stakeholders

(central and decentralized, civil society, local communities, private sector, consumer associations,

NGOs, etc.). At the regional level, the project will provide support for the establishment of

platforms for dialogue as well as for monitoring and evaluation.

12

4.1.4 Goods and Services Procurement Procedures: Procurements financed from Bank

resources will be done in accordance with national procedures for national competitive bidding

(Goods and Works), pursuant to Decree No. 2011-1048 of 27 July 2011 on the procurement code.

This provision follows the conclusions of the assessment of Senegal’s national procurement

procedures, conducted by the Bank in March 2010.

4.1.5 Procurements will comply with the Bank’s Rules and Procedures (May 2008 edition,

revised in July 2012) and will use the Bank’s standard documents for international competitive

bidding (goods and works) and recruitment of consultants through short listing. The General

Procurement Plan (GPP) has been prepared for a period of 18 months, according to a Bank model.

The details and GPP are presented in the Technical Annexes (B.5). A summary of the procurement

terms and conditions is also given in Annex 5 of this report.

4.1.6 Financial Management: The financial management system (budget, accounting policy

and procedures, internal control, financial reporting, disbursements and flow of funds and external

audit) used satisfactorily for the management of previous sub-programs of the Bank will be

maintained for the implementation of PSEA. Thus, the PEPAM-CU will be responsible for financial

management with qualified, competent and experienced personnel. The annual financial statements

including a balance sheet and an income and expenditure table will be developed from the

accounting software in place, based on the accounting standards and principles of the OHADA

accounting system. During the year, progress reports will be produced quarterly (within 45 days of

the end of the quarter), including budget execution reports. PEPAM- CU will process all the

accounts and it will systematically receive accounting records from the executing agencies.

However, the procedures manual will be updated to include new PSEA activities.

4.1.7 Disbursements: The main methods of disbursement of Bank resources will be

reimbursement, direct payment and revolving fund. The disbursement letter and the

training/retraining of staff at the launch the project will specify how these disbursement methods

will operate. To operationalize the revolving fund, two special accounts operating under the

signature of the Director of Investment or his representative will be created, including one for the

ADF loan and the other for the RWSSI grant. Additionally, two sub-accounts operating with the

joint signatures of the Coordinator and the Administrative and Financial Manager (AFM) of

PEPAM, receiving resources from special accounts will be created to settle some of the expenditure

eligible for the revolving fund. Counterpart resources will be included in the Consolidated

Investment Budget (CIB) and mobilized in time for the financing of project activities. Regional

accounts will be opened in private banks to collect contributions from the project beneficiaries. All

these accounts will operate with the joint signatures of the Coordinator and the AFM.

4.1.8 Financial and Accounting Audit: To meet the requirements of controlling the use of

project resources, an annual financial audit will be conducted throughout the project duration by an

independent audit firm selected through competitive bidding. The terms of reference of the audit

will be subject to prior approval by the Bank. The audit cost shall be financed from Bank resources.

The accounting audit report should reach the Bank within six months of closure of the fiscal year.

The auditor recruitment process shall begin within six months of the Project launch.

13

4.2 Project Monitoring

4.2.1 PEPAM – CU will be responsible for project monitoring and shall prepare quarterly progress

reports, using Bank formats, on the status of the physical and financial implementation of the

project. The project outputs will be monitored through the indicators identified in the logical

framework. The monitoring and evaluation expert of PEPAM – CU, will monitor all activities, on

the basis of the mechanism already in place and in collaboration with the focal points of the

executing agencies. Ministries that are members of the Steering Committee will also be expected to

conduct regular monitoring of outputs. Furthermore, under IEC, documents (photos, documentaries,

etc.) will be prepared regularly during the different phases of the project (before, during and after

construction) to ensure good visibility of actions. The country office will follow up and maintain

dialogue on sector policy and governance.

4.2.2 At the Bank, the project will be monitored through: (i) semi-annual supervision missions;

(ii) quarterly progress reports submitted by the PEPAM – CU; and (iii) annual audit reports to be

submitted by the PEPAM – CU no more than six months of the end of each fiscal year.

4.2.3 The project implementation milestones are given below:

Table 4.2.1: Implementation Milestones

4.3 Governance

4.3.1 The national economic and fiduciary environment does not pose any significant risk. The

national procurement system and procedures are largely compliant with international standards.

Control institutions (Audit Court, General State Inspectorate and National Anti-Corruption

Authority-OFNAC) exist and regularly produce public finance management reports. The

involvement of relevant State entities and different executing agencies in the management of

projects augur well for leadership and management. The Investment Department (DI) of the

Ministry of Finance is responsible for disbursements and participates annually in the Bank’s

portfolio review where financial management issues are addressed.

4.3.2 However, the sector’s good governance still hinges on the continuation and completion of

reforms initiated in 1996 by the Government and reaffirmed with the advent of PEPAM in 2005.

Indeed, in a bid to improve the service quality of rural drinking water supply, the key measures

envisaged are: (i) delegation of maintenance and production services to the private sector;

Period Milestones Monitoring Activities / Feedback Loop

04/2014 Loan/Grant Approval AfDB/ ADF Board

07/2014 Loan/Grant Effectiveness Signature of Grant Agreement and Non-objection of ADF

08/2014 Satisfaction of 1st disbursement conditions Non- Objection by ADF/Launching Mission

05/2015 Establishment of control firm and IEC firm Non-Objection by ADF and Contracts signed

07/2015 Start of works Non-Objection by ADF and Contracts signed

04/2015 Start of studies on reforms Non-Objection by ADF and Contracts signed

07/2015 Start of studies on IWRM Non-Objection by ADF and Contracts signed

03/2016 Validation of studies Validation workshops

04/2018 End of works Works completion reports, Missions

14

(ii) establishment of a public body to organize the maintenance of rural water infrastructure, see to

the management of rural water supply facilities and organize support and advice to operators; and

(iii) establishment of a regulatory mechanism. In this connection, the country has been divided into

three zones (North, Central and South) for the transfer to private operators of drinking water

production activities and maintenance of facilities. The process of choosing operators for the

Central zone is ongoing with the support of the World Bank. PSEA will support this reform with the

finalization of the framework for concession of a public service (PSC) for the South zone and

support to the establishment of the rural boreholes Authority (OFOR).

4.3.3. Furthermore, the limited availability of reliable, timely and sufficiently disaggregated data

on important aspects such as: water quality, gender, access to sanitation, hygiene-related behavior

affect governance of the sector. The actions planned by the Bank, in coordination with the

Government and other development partners within the context of the 2013-2017 PRSES contribute

towards establishing an efficient monitoring and evaluation system.

4.4 Sustainability

4.4.1 The Senegalese Government’s commitment to implementing this project is the prime

guarantee of sustainability. Indeed, the social tension created by recent floods and the special

situation of the Ziguinchor Region are major concerns for the Government, hence its significant

contribution to the financing of this project.

4.4.2 Regarding the rural component, the sustainability of project outcomes essentially depends

on the ability of private operators and ASUFOR to ensure efficient operation and proper

maintenance of the works. Technically, the water supply systems adopted under the project have

been designed to offer service levels matching users’ demand and payment capacity. The sale of

water by volume is practised in most pump-operated rural drinking water supply systems with a

performance rate estimated at 80%. The current statutes of ASUFOR fix the selling price of water at

CFAF 400 per m3, which is widely accepted by the population. An examination of the estimated

operating account of a mini-network (Annex B7) shows that operating costs are covered by revenue,

leaving a margin to cover the costs of operation, maintenance and servicing, including the renewal

of small equipment. The other element of sustainability of investments is based on the successful

implementation of Rural Water supply subsector reform, which provides for the institutionalization

of support to and counselling of the ASUFORs, management of the assets entrusted to the

commercial and industrial-type public entity (OFOR) and the definition of a regulatory mechanism.

4.4.3 Priority sensitization activities for behaviour change and training on management of

DWSS facilities will be implemented and will contribute to the durability of facilities. Similarly,

new databases that will emanate from actions to enhance the sector’s monitoring and evaluation

system will enhance monitoring of facilities, thus helping to ensure their sustainability.

4.4.4. For the urban component, the sustainability of investments depends primarily on the

capacity of ONAS to efficiently operate and maintain the facilities that will be provided. However,

ONAS has a chronic operating deficit estimated at CFAF 1,138 billion in 2012.

15

This deficit is due to the combined effects of (i) low investment in an antiquated network resulting

in high operating and maintenance costs and (ii) the low level of the sanitation fee. Thus, the rate of

coverage of operating expenses by the sanitation fee dropped from 70 % over the 2009, 2010, and

2011 three-year period to 65 % in 2012. The current ONAS sanitation fee (excluding operating

subsidies) stands at CFAF 51.6 as against a break-even price estimated at CFAF 66. The persistence

of this situation poses a problem of financial viability and even survival for ONAS. Accordingly, in

December 2013, a memo on the revision of the tariff policy in the water and sanitation sector was

prepared by the Ministry of Water Supply and Sanitation and submitted to the Government. This

revision is based on (i) a reduction in the volume of the social bracket of water from 20 to 18 m3;

and (ii) raising the sanitation fee by 40%, from CFAF 51.6 to CFAF 65.8. This would generate for

ONAS additional resources of CFAF 1, 623 billion and thus ensure its financial stability.

Additionally, the project will ensure the sustainability of investments through: (i) a reduction in

maintenance costs of the networks built or rehabilitated by ensuring greater private sector

involvement in the form of outsourcing and delegation of the operation of networks and stations

managed by ONAS; and (ii) a study on urban sanitation financing mechanisms. Furthermore, with

the construction of a new sewerage, Ziguinchor city will have a better sanitation network, thus

providing ONAS with additional sanitation fees that will increase coverage of maintenance and

servicing costs.

4.5 Risk Management

4.5.1. Risks: The main risks of the project concern: (i) delays in mobilizing the national

counterpart contribution which represents 34 % of the project cost; (ii) weak capacity of local

companies to implement rural sanitation works; and (iii) delays in implementing measures to

improve the financial health of ONAS.

4.5.2 Mitigation measures: (i) delays in mobilizing the national counterpart contribution:

Besides the Government's commitment, this risk is mitigated by the excellent outcomes of the

recent Paris Conference on financing Senegal’s Economic Emergence Plan. Furthermore, a

monitoring mechanism for the mobilization of the counterpart contribution involving the Country

Office and the PEPAM-CU has been set up; (ii) weak capacity of local companies to implement

rural sanitation works: To mitigate this risk, a list of efficient contractors has been drawn up based

on experience from the two previous Bank projects. Additionally, the procurement strategy adopted

was based on an efficient allotment and the raising of recruitment criteria to ensure the engagement

of competent contractors; and (iii) delays in implementing measures to improve the financial health

of ONAS: This risk is mitigated by the fact that the Government, in agreement with donors, has

raised the reform of the sector to a top priority,. Under the project, the Government will undertake

to: (i) adjust tariffs for drinking water and sanitation services for the period 2014-2018; and (ii)

implement the approved recommendations that stem from the study on financing mechanisms.

16

4.6 Knowledge Building

4.6.1 The implementation of the project will provide knowledge regarding: (i) the impact and

effects of DWSS interventions and IEC on the living conditions of beneficiaries; (ii) the use of

IWRM as a means of economic development; (iii) public-private partnership in the water and

sanitation sector; and (iv) the preparation of a guide to environmental monitoring of sanitation

projects.

4.6.2. The definition of key impact indicators prior to project start-up and impact assessment at

the end of the activities will help produce useful information on the outcomes and impact of the

project as a basis for future operations. The lessons learnt from the project will be included in the

periodic reports as well as in the project completion report and will serve as references for both the

Government of Senegal and the Bank.

V. Legal Framework

5.1. Legal Instrument

A loan agreement will be signed between the Republic of Senegal (the Borrower), on the one hand,

and the African Development Fund (the "ADF"), on the other. Similarly, a memorandum of

understanding will be signed between the Republic of Senegal (the "Grantee"), on the one hand, and

the African Development Bank and the ADF (on behalf of the RWSSI Fund), on the other.

5.2 Conditions for the Bank’s Intervention

A. Conditions Precedent to Effectiveness of the ADF Loan and RWSSI Grant:

This loan shall become effective subject to fulfillment by the Borrower, to the satisfaction of the

ADF, of the conditions laid down in Article 12.1 of the General Conditions. The RWSSI grant shall

become effective upon its signature.

B. Conditions precedent to first disbursement of the Loan and Grant: After the entry into

force, the first disbursement of the Loan and Grant resources shall be subject to fulfillment of the

following conditions to the satisfaction of the Fund:

(i) supplying evidence of the opening of special accounts in banks deemed acceptable

by the ADF, to receive the loan and grant resources; and

(ii) supplying to the ADF, evidence of the appointment of national and regional

counterparts of executing agencies (DH, DGPRE, DA, DEM and ONAS), together

with their respective CVs, which would have been approved beforehand by the Bank.

C. Other conditions: In addition, the Grantee/Borrower shall, to the satisfaction of the Fund;

supply the ADF with evidence of the compensation of persons affected by works on the water

treatment and purification station, prior to the start of the Ziguinchor sanitation works.

17

D. Undertakings: The Grantee/Borrower shall undertake to:

(i) include in the Finance Act each year, the counterpart contribution required for the

financing of the project;

(ii) maintain the personnel of the PEPAM Coordinating Unit;

(iii) make effective, the adjustment of drinking water and sanitation tariff for the period

2014-2018; and

(iv) implement the recommendations adopted following the study on urban sanitation

funding mechanisms.

5.3. Compliance with Bank Policies

The project complies with all applicable Bank policies.

VI. RECOMMENDATION

Management recommends that the Boards approve the proposal to grant an ADF loan of UA 20

million and award an RWSSI grant of EUR 6 million to the Government of Senegal, to finance the

Project described above, under the terms and conditions set forth in this report.

I

Annex 1: Comparative Socio-economic Indicators of Senegal

Year Senegal Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2011 197 30 323 98 458 35 811Total Population (millions) 2012 13,7 1 070,1 0,0 0,0Urban Population (% of Total) 2012 42,8 40,8 47,1 78,0Population Density (per Km²) 2012 64,9 34,5 69,8 23,5GNI per Capita (US $) 2012 1 040 1 604 3 795 37 653Labor Force Participation - Total (%) 2012 40,5 37,8 68,7 72,0Labor Force Participation - Female (%) 2012 43,9 42,5 38,9 44,5Gender -Related Dev elopment Index Value 2007-2011 0,457 0,525 0,694 0,911Human Dev elop. Index (Rank among 187 countries)2008-2012 154 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2009-2011 29,6 40,0 20,6 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2012 2,9 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 3,6 3,4 2,6 0,7Population < 15 y ears (%) 2012 43,5 40,0 28,5 16,4Population >= 65 y ears (%) 2012 3,0 3,6 6,0 16,6Dependency Ratio (%) 2012 84,3 77,3 52,6 49,2Sex Ratio (per 100 female) 2012 96,1 100,0 103,3 94,3Female Population 15-49 y ears (% of total population) 2012 24,4 49,8 53,3 45,6Life Ex pectancy at Birth - Total (y ears) 2012 63,3 58,1 68,2 77,7Life Ex pectancy at Birth - Female (y ears) 2012 64,7 59,1 70,1 81,1Crude Birth Rate (per 1,000) 2012 38,1 33,3 21,4 11,3Crude Death Rate (per 1,000) 2012 7,7 10,9 7,6 10,3Infant Mortality Rate (per 1,000) 2012 49,6 71,4 40,9 5,6Child Mortality Rate (per 1,000) 2012 74,3 111,3 57,7 6,7Total Fertility Rate (per w oman) 2012 5,0 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2006-2010 370,0 415,3 240,0 16,0Women Using Contraception (%) 2012 13,9 34,5 62,4 71,4

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2010 5,9 49,2 103,7 291,9Nurses (per 100,000 people)* 2004-2009 42,0 133,0 168,7 734,3Births attended by Trained Health Personnel (%) 2006-2010 65,1 53,7 64,3 ...Access to Safe Water (% of Population) 2011 73,4 67,8 86,5 99,1Access to Health Serv ices (% of Population) 2000 90,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2011 51,4 40,2 56,8 96,1Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 0,7 4,6 0,9 0,5Incidence of Tuberculosis (per 100,000) 2011 136,0 234,6 146,0 23,0Child Immunization Against Tuberculosis (%) 2011 95,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 82,0 76,5 83,7 93,5Underw eight Children (% of children under 5 y ears) 2006-2011 19,2 19,8 17,0 1,4Daily Calorie Supply per Capita 2009 2 479 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010-2011 3,5 5,9 2,9 7,4

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2009-2012 86,2 107,0 107,8 102,7 Primary School - Female 2009-2012 89,0 103,1 106,2 102,3 Secondary School - Total 2009-2012 42,1 46,3 66,4 100,4 Secondary School - Female 2009-2012 40,3 41,9 65,1 100,0Primary School Female Teaching Staff (% of Total) 2009-2012 30,6 39,2 58,6 81,3Adult literacy Rate - Total (%) 2009 49,7 71,5 80,2 …Adult literacy Rate - Male (%) 2009 61,8 78,4 85,9 …Adult literacy Rate - Female (%) 2009 38,7 64,9 74,8 …Percentage of GDP Spent on Education 2008-2010 5,6 5,3 4,5 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 20,0 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 0,7 0,6 0,4 -0,2Forest (As % of Land Area) 2011 43,8 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,4 1,2 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Senegal

october 2013

0102030405060708090

2004

2005

2006

2007

2008

2009

2010

2011

2012

Infant Mortality Rate( Per 1000 )

Senegal Africa

0

200

400

600

800

1000

1200

1400

1600

1800

2003

2004

2005

2006

2007

2008

2009

2010

2011

GNI Per Capita US $

Senegal Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

2004

2005

2006

2007

2008

2009

2010

2011

2012

Population Growth Rate (%)

Senegal Africa

111213141516171

2004

2005

2006

2007

2008

2009

2010

2011

2012

Life Expectancy at Birth (years)

Senegal Africa

II

Annex 2: Table of AfDB Portfolio in the Country

(Portfolio of Active National Projects as at 31 January 2014)

Date Amount Amount

Disbur

sement Closing

Sector / Operation

of

Approval Approved Disbursed Rate Date

(UA m.) (UA m.) (%)

RURAL/AGRICULTURE

1 ● Support to Small-scale Irrigation (PAPIL II) 26-Jan.-11 8.40 6.03 71.81

31-Dec.-

14

2 ● Support to Development of Casamance (PADERCA) 19-Oct.-05 20.00 15.78 78.91 19-Dec.-

14

3 ● Feeder Roads Project in Support of the National

Programme for Local Development (PPC/PNDL) 17-Jul.-13 15.00 0.00 0.00

31-Dec.-18

4 ● Guiers Lake Restoration Project (PREFELAC) -ADF

- GEF

4-Sept.-13

4-Sept.-13

15.00

0.85

0.00

0.00

0.00

0.00

31-Dec.-

18

31-Dec.-18

5 ● Food Security Support Louga Matam Kaffrine - ADF

- GAFSP

26- Apr.-13 26- Apr.-13

2.00 26.06

0.00 0.00

0.00 0.00

31-Dec.-

18 31-Dec.-

18

Sub-total /Average 87.85 21.81 24.82

INFRASTRUCTURE

6 ● Rural Electrification 13-Oct.-04 9.58 3.68 38.42 31-Oct.-15

7 ● Dakar-Diamniadio Highway 15-Jul.-09 45.00 43.59 96.86 31-Dec.-

14

Sub-total /Average 54.58 47.27 86.60

WATER AND SANITATION

8 ● Rural DWSS Programme (PEPAM II) 18-Feb.-09 30.00 21.81 72.70 31-Dec-14

9 ● Ziguinchor Sludge Collection and Management (AWF) 23-Apr.-13 1.11 0.00 0.00 31-Dec-15

Sub-total /Average 31.12 21.81 70.25

SOCIAL

10 ● Project in Support the Promotion of Youth and

Women’s Employment (PAPEJF) 23-Oct.-13 21.19 0.00 0.00 31-Dec-18

11 ● Virtual University of Senegal Support Project (PAUVS) 19-Dec.-13 3.38 0.00 0.00 31-Dec-18

Sub-total /Average 24.57 - 0

GOVERNANCE

12 ● Inclusive Growth and Economic Competitiveness

Support Programme (PACICE) 19- Jun -13 25.54 25.54 100.00

31-Dec.-

14

13 ● Private Sector Promotion Support Project (PAPSP) 10-Sept.-12 4.04 0.61 15.11 30-Jun-16

Sub-total /Average 29.58 26.15 88.4

TOTAL / AVERAGE 227.7 117.04 51.5

III

Annex 3: Key Related Projects Financed by the Bank

and Other Development Partners of the Country

Donors Amount

(Billion CFAF) Projects Status

Luxemburg 2.5 National Institutional Support Programme

(PAEX)- SEN030 Part 2

Ongoing

Luxemburg 0.4 Programme SEN026 – Monitoring and

Evaluation Component

Closed

Luxemburg 2.5 National Institutional Support Programme

(PAEX)- SEN030 Part 2

Ongoing

EU 18 PEPAM-EU Starting

World

Bank

28 PEPAM-IDA Ongoing

AfDB 11 Dakar City Sanitation Project (PAVD) Closed in

2008

AfDB 20 PEPAM-AfDB, phase 1 Closed in

2010

AfDB 23 PEPAM-AfDB, phase 2 Ongoing

IV

Annex 4: Project Area Map

KEY Rural areas drinking water supply and sanitation

component

Urban areas sanitation component

ADB-PSEA PROJECT AREA

V

Annex 5: Summary Presentation of Procurement Procedures

Expenditure Categories under the Project

In UA million

Use of

NPP

Use of Bank

Rules and

Procedures

Contracts

not

Financed

by the

Bank

Total

1. WORKS

1.1. Construction of 20 New Boreholes 1.166 (0.816)

1.166 (0.816)

1.2. Construction works of 30 Multi-village DWS

and Network Extension on 10 sites 7.77 (5.440) 7.77 (5.440)

1.3 Sanitation works in Almadies in Dakar 0.351(0.245) 0.351(0.245)

1.4. Sanitation works in Dakar and Ziguinchor 9.780 (5.365) 9.780 (5.365)

1.5. Construction of 40 Public Toilets 0.174 (0.157) 0.174 (0.157)

1.6. Construction of 17 000 Individual structures

and Connections 5.978 (2.890) 5.978 .890)

2. GOODS

2.1. Equipment for New DWS Systems and Existing

Boreholes 0.758 (0.653) 0.758 (0.653)

2.2. Vehicles and Motorcycles 0.37 (0.185) 0.37 (0.185)

2.3. IT Equipment and Software 0.044 (0.044) 0.044 (0.044)

2.4. Office Furniture 0.027 (0.027) 0.027 (0.027)

2.5. Technical Equipment for the Implementation of

the EIS - IWRM 0.109 (0.109) 0.109 (0.109)

2.6. Collection Equipment for Women and Youth 0.135 (0.135) 0.135 (0.135)

3. SERVICES

3.1 Control and Supervision of Rural and Urban

DWS and Sanitation Works 2.547 (1.286) 2.547 (1.286)

3.2. Technical and Environmental Studies on the

Hann- Fann Collector Pipes 1.166 (0.933) 1.166 (0.933)

3.4. IEC for Rural and Urban DWS and Sanitation 2.044 (1.02) 2.044 (1.02)

3.5. Study on Impacts and Inter-sector Relations 0.131 (0.131) 0.131 (0.131)

3.6. Studies on the IWRM 1.575 (1.259) 1.575 (1.259)

3.7. Studies on Urban Reform 0.364 (0.328) 0.364 (0.328)

3.8. Studies on Rural Reform 0.583 (0.524) 0.583 (0.524)

3.9. Project Audit 0.0437 (0.0437) 0.0437 (0.0437)

3.10. Agreement Signed with ANSD 0.256 (0.256) 0.256 (0.256)

3.11. Studies for the Development of the Sector 0.160 (0.160) 0.160 (0.160)

3.12. Individual Consultants (Training, Monitoring

and Evaluation) 0.677 (0.677) 0.677 (0.677)

OPERATION, including DEEC Agreement 2.57 (2.57) 2.57 (2.57)

TOTAL 4.58 (4.20) 34.24 (21.14) 38.82 (25.34)

NB: ( ) The figures in brackets are the amounts financed by the ADF and RWSSI