31
MAJOR ACTIVITIES UNDERTAKEN SINCE LAST WEB UPDATE 1. Following are the important actions undertaken/ completed since last update of 15 Jun 17. 2. Till 15 Jul 17, ten allottees have registered their DUs physical possession of six DUs have also been given to the allottees. 3. Minor defects observed by allottees while taking over DUs have since been rectified. 4. Seepage observed in a few DUs while testing plumbing lines have also been rectified. Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC. 5. Allottees desirous of getting their DUs registered are requested to visit site on Tuesdays or Fridays, after completing other formalities in consultation with the Advocate. Authorized signatory from AFNHB would be available to accompany allottees on Tuesdays and Fridays. AFNHB : JALANDHAR PROJECT : As on 17 Jul 17

AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

MAJOR ACTIVITIES UNDERTAKEN SINCE LAST WEB UPDATE

1. Following are the important actions undertaken/ completed since last update of 15 Jun 17. 2. Till 15 Jul 17, ten allottees have registered their DUs physical possession of six DUs have also been given to the allottees.

3. Minor defects observed by allottees while taking over DUs have since been rectified. 4. Seepage observed in a few DUs while testing plumbing lines have also been rectified. Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC.

5. Allottees desirous of getting their DUs registered are requested to visit site on Tuesdays or Fridays, after completing other formalities in consultation with the Advocate. Authorized signatory from AFNHB would be available to accompany allottees on Tuesdays and Fridays.

AFNHB : JALANDHAR PROJECT : As on 17 Jul 17

Page 2: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

JAL VAYU VIHAR ENTRANCE

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 3: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

PANORAMIC VIEWS OF TOWERS

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 4: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 5: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

PICTURE TAKEN WITH DRONE CAMERA

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 6: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 7: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

INTERNAL VIEW OF DUs BLOCK A1/A2

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 8: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 9: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 10: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 11: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 12: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 13: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 14: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 15: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 16: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 17: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 18: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 19: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 20: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC
Page 21: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

A1 & A2 BLOCKS- (overall completion 99.75 %) Total Floors: - Stilt +9 Total Flats: - 106 (1350 SQ FT EACH) PROGRESS: Rectification of External painting, minor repairs/rectifications works of aluminium works in progress. External painting of Block A would be undertaken during Aug 2017.

Page 22: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

INTERNAL VIEW OF BLOCK B 1

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 23: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

B1- BLOCKS (overall completion 99.75%) Total Floors: - Stilt +8 Total Flats: - 48 (931 SQ FT) PROGRESS: All works completed except final coat of external paint. Same has been planned during last week of Aug 2017.

Page 24: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

COMMUNITY CENTRE

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 25: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

WORK COMPLETED

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 26: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

BASEMENT PARKING

Basement Parking- Progress 99.75%

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 27: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

LANDSCAPING

WORK COMPLETED

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 28: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

SWIMMING POOL

WORK COMPLETED

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 29: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

ROAD WORK

WORK COMPLETED

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 30: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

SUB STATION

WORK COMPLETED

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017

Page 31: AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC

STREET LIGHTS

WORK COMPLETED

PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017