UNRESTRICTED / ILLIMITÉ

Repair of the NRU

Reactor Vessel:

Technical Challenges and

Lesson Learned

David S. Cox

Atomic Energy of Canada Limited

Chalk River Laboratories

International Conference on Research Reactors:

Safe Management and Effective Utilization

2011 November

Rabat, Morocco

Page 2: AECL corporate power point presentation template - Publications

Chalk River Laboratories

• The NRU Reactor

• Leak location and condition assessment

• Inspection tool development

• Determination of degradation mechanism

• Development of repair methods

• Execution of weld repair

• Lessons Learned

UNRESTRICTED / ILLIMITÉ

Page 3: AECL corporate power point presentation template - Publications

NRU - National Research Universal

• First operation 1957 November

• 200 MW design; current licence limit 135 MW

• Large, versatile research reactor

–R&D support of CANDU® reactor fuel & materials irradiation

–National Research Council Canadian Neutron Beam Centre

• Medical & industrial isotopes

–Benefits more than 76,000 people

internationally each day

–Used for cancer treatment and early

cancer detection, diagnosis of

heart conditions, circulatory system

& other organs

–Mo-99, I-125, I-131, Xe-133, Co-60,

Ir-192

UNRESTRICTED / ILLIMITÉ

• NRU obtained full WANO membership in late 2010

Page 4: AECL corporate power point presentation template - Publications

Cross Section of NRU

UNRESTRICTED / ILLIMITÉ

Page 5: AECL corporate power point presentation template - Publications

UNRESTRICTED / ILLIMITÉ 5

Page 6: AECL corporate power point presentation template - Publications

Heavy Water Leak- 2009 May 14

Upper Deck

Plate

Permanent

Guide Tubes

Calandria

Vessel

Lower

HeaderLeak Site

Vessel

Wall

J-Rod

Annulus

Water

Reflector

Wall

Upper Deck

Plate

Permanent

Guide Tubes

Calandria

Vessel

Lower

HeaderLeak Site

Vessel

Wall

J-Rod

Annulus

Water

Reflector

Wall

Reaching the leak site: • Leak site is 9 m below the deck plate

at the base of the vessel

• Access through 12 cm dia. tubes

• High radiation environment

UNRESTRICTED / ILLIMITÉ

Vessel wall:

8 mm 5052

aluminum

Page 7: AECL corporate power point presentation template - Publications

Visual Inspections in 2009 May

• Minor heavy water leak from the vessel into the

surrounding annulus detected (~5 kg/h)

–Visual inspection determined that the leak site was

in the vessel wall at the bottom of the annulus

–Determined that the heavy water leak was due to

corrosion of the reactor vessel wall from the outside

–Additional areas of corrosion around the base of the

vessel also required remediation

–Decision made to remain shutdown for an extended

period to repair the vessel

UNRESTRICTED / ILLIMITÉ 7

Page 8: AECL corporate power point presentation template - Publications

Leak Site

• Detailed non-destructive

examination of lower

vessel wall performed

–Leak location

determined

accurately

–Widespread

corrosion identified

in the lower portion

of the J-rod annulus

UNRESTRICTED / ILLIMITÉ 8

Reactor

vessel wall Reflector

wall

Water box

Light water

gutter

Lip

Heavy water

gutter

Page 9: AECL corporate power point presentation template - Publications

9

A Closer Look at the Leak Site

Annulus

floor

Vessel

wall

Vessel

wall

Annulus

floor

Area of leak

UNRESTRICTED / ILLIMITÉ

Page 10: AECL corporate power point presentation template - Publications

Condition Assessment of Vessel

Non-destructive examination: • Remote video inspections

• Ultra-sound examination

• Eddy current probes

• Over two million inspection results

• Four phases

One of largest single NDE

inspection campaigns ever

carried out in the nuclear industry.

UNRESTRICTED / ILLIMITÉ

Page 11: AECL corporate power point presentation template - Publications

UNRESTRICTED / ILLIMITÉ

Inspection Tools

Mk-I Mk-II

Page 12: AECL corporate power point presentation template - Publications

12

Phases I & II – Inspection Probes

Phased Array UT

UNRESTRICTED / ILLIMITÉ

Hi-Resolution ET

Page 13: AECL corporate power point presentation template - Publications

UNRESTRICTED / ILLIMITÉ

Mk II Inspection Tool in Mock-Up

8 full-height mockups utilized through outage

Page 14: AECL corporate power point presentation template - Publications

Inspection Teams

Mk I deployment Mk II deployment

UNRESTRICTED / ILLIMITÉ

Page 15: AECL corporate power point presentation template - Publications

15

NRU Annulus Cross-Section

Vessel Wall

Wall-to-Flange Weld

Lip Annulus Floor

Bottom Flange

Gutter Baffle Block

Bottom Plate

UNRESTRICTED / ILLIMITÉ

Page 16: AECL corporate power point presentation template - Publications

Map of Vessel Wall Thickness

16

BR-29/30 Test Weld BR-45

JR-13/17 JR-18

JR-41 JR-30 JR-28 JR-25/27 JR-23 JR-21

UNRESTRICTED / ILLIMITÉ

Page 17: AECL corporate power point presentation template - Publications

Locations to Repair

10 Repair Areas 1. BR-45

2. BR-29/30

3. JR-30

4. JR-28

5. JR-21

6. JR-41

7. JR-18

8. JR-23

9. JR-25/27

10.JR-13/17

17 UNRESTRICTED / ILLIMITÉ

Page 18: AECL corporate power point presentation template - Publications

Tooling to Clean Vessel Wall

Cleaning of the vessel wall:

• Critical step in welding process

• Removal of gibbsite layer from

vessel

• Articulating vacuum to recover

debris

UNRESTRICTED / ILLIMITÉ

Page 19: AECL corporate power point presentation template - Publications

UNRESTRICTED / ILLIMITÉ

Mechanical Cleaning Tool

Tool Head

Delivery Tool Body

Deployment Mechanism

Actuation/ Control Dive

Cups

Deck Plate Quick Disconnect

Page 20: AECL corporate power point presentation template - Publications

UNRESTRICTED / ILLIMITÉ

Cleaning Tool Deployment Arm

Primary carriage

Secondary carriage

Deployment linkage

Deployment arm

Pneumatically operated

tool head

Silicon Carbide

Brush

Thick walled SS tube (Delivery Tool Body)

•Arm has 965 mm horizontal reach

Page 21: AECL corporate power point presentation template - Publications

JR-41 Leak Site After Cleaning

In-Vessel Cleaning completed for all repairs sites and material

sampling locations

UNRESTRICTED / ILLIMITÉ

Page 22: AECL corporate power point presentation template - Publications

Obtaining Samples of the Vessel Wall

UNRESTRICTED / ILLIMITÉ

Page 23: AECL corporate power point presentation template - Publications

Scoop Samples

UNRESTRICTED / ILLIMITÉ

Page 24: AECL corporate power point presentation template - Publications

Welding on Irradiated Material

UNRESTRICTED / ILLIMITÉ

Page 25: AECL corporate power point presentation template - Publications

Coupon Cutting at Leak Site

UNRESTRICTED / ILLIMITÉ

Page 26: AECL corporate power point presentation template - Publications

Corrosion Coupon

UNRESTRICTED / ILLIMITÉ

Page 27: AECL corporate power point presentation template - Publications

Coupon Removed from Vessel Wall

• J-rod Side Heavy Water side

UNRESTRICTED / ILLIMITÉ 27

Page 28: AECL corporate power point presentation template - Publications

Corrosion Mechanism

• J-rod annulus designed to be filled with carbon dioxide

gas and kept dry

• However:

–Aging of CO2 system reduced gas flow

–Light water ingress from reflector leaks into J-rod annulus

–Air ingress from openings in J-rod annulus

–High radiation environment

• Created the conditions for radiolytic production of nitric

acid

• General wastage corrosion in wetted regions, and

localized corrosion at air/water interface

UNRESTRICTED / ILLIMITÉ 28

Page 29: AECL corporate power point presentation template - Publications

Articulating J-Rod

Annulus Vacuum Tool

Near JR-3 position

After

UNRESTRICTED / ILLIMITÉ

Cleaning the Annulus

Before

Page 30: AECL corporate power point presentation template - Publications

Welding Challenges

1. Geometry: 9 m remote through 12 cm diameter

openings, reaching around obstructions in vessel

2. Vessel distortion from heat

3. High radiation fields on tooling

30 UNRESTRICTED / ILLIMITÉ

Page 31: AECL corporate power point presentation template - Publications

Liburdi Welding & Support Tool Set

1. Horizontal weld tool

2. Vertical Weld Tool

3. Horizontal Cleaning & Repair Tool

4. Vertical Cleaning and Repair Tool

5. Patch Deployment Tool

31 UNRESTRICTED / ILLIMITÉ

Page 32: AECL corporate power point presentation template - Publications

32

Liburdi Weld Delivery System

UNRESTRICTED / ILLIMITÉ

Page 33: AECL corporate power point presentation template - Publications

33

Liburdi Weld Delivery System

UNRESTRICTED / ILLIMITÉ

Page 34: AECL corporate power point presentation template - Publications

34

Welding Control Interface

UNRESTRICTED / ILLIMITÉ

Page 35: AECL corporate power point presentation template - Publications

Vertical Welding Tool

UNRESTRICTED / ILLIMITÉ 35

Page 36: AECL corporate power point presentation template - Publications

Weld Design Process

Engineering

Weld

Development

NDE

Structural

FEA

Weld Stress

Analysis #1

Weld Stress

Analysis #2 Weld Map

Crack Examination

Surface/HAZ

Thickness

Lack of Fusion

Volumetric

Fillets/Groove Welds

Vertical Welds

Horizontal Welds

Fillet/Groove Welds

Window Frames

Plates

36 UNRESTRICTED / ILLIMITÉ

Page 37: AECL corporate power point presentation template - Publications

Qualification of the Welding

Cross

Sections

37 UNRESTRICTED / ILLIMITÉ

Page 38: AECL corporate power point presentation template - Publications

38

Test Weld (with Scoop)

UNRESTRICTED / ILLIMITÉ

Page 39: AECL corporate power point presentation template - Publications

Summary of Repair Areas

Site

Weld

Area

(cm2)

Lowest

Elevation

Weld/Plate

(mm)

Min. Wall

Thickness

(mm)

Welding Operations

H/- V

Buildup

(mm)

Backing

Strips/

Structural

Plates

Plate

Build-

up

2nd

Layer

BR-45 45.4 18 7 V-3 N N N

BR-29/30 90.2 18 7 V-3 N N N

JR-30 139.6 25 4 V-3 N N N

JR-28 106.2 65 4 V-3 N N N

JR-21 347.7 15 3 H-3 N N N

JR-41 153.9 0/15 4 H-3 1-BS Y N

JR-18 83.2 25 4 H-3 0 N N

JR-23 433.6 2/35 1-2 H&V-2.5 2-BS 3 mm Y

JR-25/27 619.1 37/60 0-1 H&V-3.0 4-SP N N

JR-13/17 1250.6 5/25 0-1 H&V-4.0

H 3.0

9-SP N N

39 UNRESTRICTED / ILLIMITÉ

Page 40: AECL corporate power point presentation template - Publications

Weld Repair

40 UNRESTRICTED / ILLIMITÉ

Page 41: AECL corporate power point presentation template - Publications

Repair at JR-41 – The Leak Site

UNRESTRICTED / ILLIMITÉ

Backing

strip

placement

Backing

strip

welding

Final Weld Overlay

Page 42: AECL corporate power point presentation template - Publications

Final Repair – JR-13/17

Challenges: • Two through wall

penetrations

• Thinning to less

than 1mm

• Located below and

between two re-

entrant cans

• Large area: W x H

59 cm x 26 cm

10.4” x 23”

42 UNRESTRICTED / ILLIMITÉ

Page 43: AECL corporate power point presentation template - Publications

Challenges - Final Repair

UNRESTRICTED / ILLIMITÉ

Page 44: AECL corporate power point presentation template - Publications

Challenges - Final Repair

UNRESTRICTED / ILLIMITÉ

Page 45: AECL corporate power point presentation template - Publications

Weld Process Map – JR-13/17

45

Patching

Tacking

Verticals

Horizontals

4mm Overlay

3mm Overlay

UNRESTRICTED / ILLIMITÉ

Page 46: AECL corporate power point presentation template - Publications

Weld Stress Analysis

Prediction of loading on vessel seal, and displacement

of vessel wall, in response to weld stresses

UNRESTRICTED / ILLIMITÉ

Page 47: AECL corporate power point presentation template - Publications

Repair at JR-13/17

UNRESTRICTED / ILLIMITÉ

Multiple challenges encountered:

• Plate attachment

• Design change

• Crack repair and re-inspection

Page 48: AECL corporate power point presentation template - Publications

Other Parallel Outage Work

• System Refurbishment Program

–Heavy Water System major maintenance &

inspections

–Process Water maintenance & inspections

–Moderator change (66 Mg heavy water)

– 26 Ci/L replaced with ~ 2.5 Ci/L

–Fuelling Machine major maintenance (Fuel Rod

Flask)

–Installation of seismic supports for loop piping

UNRESTRICTED / ILLIMITÉ 48

Page 49: AECL corporate power point presentation template - Publications

2010 August 17 - Return to Service

49

- Commission approval

to refuel past hold

point: 2010 July 5th

- Return to Service and

high power operation,

safely achieved 2010

August 17

UNRESTRICTED / ILLIMITÉ

Page 50: AECL corporate power point presentation template - Publications

Lessons Learned - Repair

1. Necessary to establish broad design requirements

early for repair tooling and proceed into fab/testing in

absence of final specifications

– Pursued multiple repair methods until final decision made

2. Full size mock-ups that simulated important spatial

constraints for tooling were essential

3. Thermal/mechanical simulations of each weld repair

were necessary to limit plastic strains and protect

vessel seals

4. Practice, practice, practice to establish process control

under conditions in mock-ups that simulate in-vessel

conditions to the extent possible

UNRESTRICTED / ILLIMITÉ 50

Page 51: AECL corporate power point presentation template - Publications

Lessons Learned - Continued

5. Close interaction with Regulatory at multiple levels

provided clarity to licensing requirements

– Protocol signed by CNSC and AECL Presidents

– Defined regulatory deliverables and timeline for approvals

– Transparent process brings certainty

6. Important to provide regular communications to Public

and Stakeholders

– Weekly media updates

– Video presentations

– Website

www.NRUCanada.ca

UNRESTRICTED / ILLIMITÉ 51

Page 52: AECL corporate power point presentation template - Publications

UNRESTRICTED / ILLIMITÉ 52

Key Suppliers to AECL:

• Liburdi Automation

• Promation Nuclear

• Eclipse Scientific

• Equity Engineering

• The Welding Institute

• Goldak & Associates

Page 53: AECL corporate power point presentation template - Publications

Closing Facts

• 40 remote operated tools designed and fabricated for

inspection, sampling, cleaning, repair

• 1 km of weld bead applied

• 3 tonnes of aluminum plate consumed for weld development

and training work (300 plates)

• 4,000 hours of in-vessel inspections

• 2 million NDE inspection results

• 1.8 terabytes of in-vessel video record

• 650 quality surveillance inspections

• 200 reactor assemblies moved/installed

• 73 Stakeholder status updates and 27 information videos

issued to public

• 75,000 unique website visits (www.NRUCanada.ca)