1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives Training Objectives Training Objectives Training Objectives We will cover The five factors Safe paver operation Screed set up and what you need to know about your screed Balanced production Controlling segregation 3 Track Drive Track Drive Track Drive Track Drive Advantages Excellent Traction Excellent Flotation Low Ground Pressure Disadvantages Higher production cost = higher initial purchase price and higher maintenance cost over the life of the tractor Less mobile 4 Wheel Drive Wheel Drive Wheel Drive Wheel Drive Advantages Mobility Lower maintenance costs Familiar steering control Job site speed Less base rock disturbance Disadvantages May spin on lose surfaces or heavy tack coated surfaces Risk of tire puncture

Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

1

Asphalt Pavement: The Road to Quality

Paver Operations

Presented by Peter Fredrickson

2

Training ObjectivesTraining ObjectivesTraining ObjectivesTraining Objectives

� We will cover

� The five factors

� Safe paver operation

� Screed set up and what you need to know about your screed

� Balanced production

� Controlling segregation

3

Track DriveTrack DriveTrack DriveTrack Drive

� Advantages

� Excellent Traction

� Excellent Flotation

� Low Ground Pressure

� Disadvantages

� Higher production cost = higher

initial purchase price and higher

maintenance cost over the life of the

tractor

� Less mobile

4

Wheel DriveWheel DriveWheel DriveWheel Drive

� Advantages

� Mobility

� Lower maintenance costs

� Familiar steering control

� Job site speed

� Less base rock disturbance

� Disadvantages

� May spin on lose surfaces or heavy tack coated surfaces

� Risk of tire puncture

Page 2: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

2

5

Pavers Utilizes a Free Floating Screed Pavers Utilizes a Free Floating Screed Pavers Utilizes a Free Floating Screed Pavers Utilizes a Free Floating Screed

PrinciplePrinciplePrinciplePrinciple

That means the screed, which is being towed along by the tractor is lowered and held down onto the mat by its own weight

Its supported by the quality or stability of the

material that it’s laying

6

Five FactorsFive FactorsFive FactorsFive Factors

�The Factors Affecting Screed

Performance

�Methods of Controlling These

Factors

�What the Crew Can Do

7

Factor Number 1Factor Number 1Factor Number 1Factor Number 1

Controlling Mat Thickness

Adjusting the “Angle of Attack”

9

Angle of AttackAngle of AttackAngle of AttackAngle of Attack

Definition:

Angle made by the screed plate to the mat with which it is paving.

Page 3: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

3

10

Changing the Angle of Attack Changing the Angle of Attack Changing the Angle of Attack Changing the Angle of Attack ---- IncreasingIncreasingIncreasingIncreasing

11

Changing the Angle of AttackChanging the Angle of AttackChanging the Angle of AttackChanging the Angle of Attack---- DecreasingDecreasingDecreasingDecreasing

12

Methods of Changing the Angle of AttackMethods of Changing the Angle of AttackMethods of Changing the Angle of AttackMethods of Changing the Angle of Attack

Manual using Depth Crank

Automatically using grade sensors or switching tow point manually

Changing Line of Pull

13

Screed RatioScreed RatioScreed RatioScreed Ratio

1:11:11:11:1 8:18:18:18:1Ratio

Pivot Point

25 mm or

1 inch here

3 mm or 1/8 inch here

Page 4: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

4

14

What is a Tow Length?What is a Tow Length?What is a Tow Length?What is a Tow Length?

Automatic Control

using grade sensors

Tow Point adjustable

Tow Point not

used

Manual Control by

use of depth cranks

Approx 4m (13.5 ft)

15

Screed ReactionScreed ReactionScreed ReactionScreed Reaction

16

New Screed Level

Original

Screed Level

Vertical

Displacement

Reaction of the Screed

Over Five Tow Lengths

0 1 2 0 1 2 0 1 2 0 1 2 3 4 3 4 3 4 3 4 5 5 5 5

Five Tow Lengths

100%100%100%100%

37%37%37%37%

14%14%14%14%

5%5%5%5%2%2%2%2% 0.7%0.7%0.7%0.7%

% of Change Remaining

17

The ‘Key’ to Good

Angle of Attack

Control

• Looking Ahead

• Frequent Depth & Slope Checks

• Smooth Depth Changes

• Avoiding Over-Correction

Page 5: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

5

18

1. Over Correction of Hand or Automatic

Controls

2. Over Sensitive Automatic Controls

3. Worn Screed Components

4. Poor Screed Maintenance

5. Cold Screed

Problems That May Cause Variations in Angle Problems That May Cause Variations in Angle Problems That May Cause Variations in Angle Problems That May Cause Variations in Angle

of Attackof Attackof Attackof Attack

19

• Mat Depth

• Screed Weight

• Material Stability

• Screed Plate Depth (front to back)

Other factors which may affect the Angle of Attack:

Mat & screed temperature, material type, nominal aggregate size,

varying paving speed and varying head of material

Factors Determining the Angle of AttackFactors Determining the Angle of AttackFactors Determining the Angle of AttackFactors Determining the Angle of Attack

20

• Know your alignment - read and mark out the job site

• Correct screed set - up procedure at start

• Make frequent depth and slope checks

• Use automatic controls whenever possible

• Allow screed time to react

• Avoid over- correction

• Constantly monitor screed and material temperature

Summary Summary Summary Summary ---- Angle of AttackAngle of AttackAngle of AttackAngle of Attack

21

The Road to QualityThe Road to QualityThe Road to QualityThe Road to Quality

Factor 2

Head Of Material

Page 6: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

6

22

Head of MaterialHead of MaterialHead of MaterialHead of Material

23

Head of MaterialHead of MaterialHead of MaterialHead of Material

Correct Head of

MaterialRequired Depth

Required Density

Over 90% of all mat faults may be attributed to poor head of material control.

A constant flow of material and a consistent head of material is essential for smooth quality paving

24

Head of Material

Too Low

Increased Depth

Decreased Density

Decreased Depth

Increased Density

Head of Material

Too High

Varying the Head of MaterialVarying the Head of MaterialVarying the Head of MaterialVarying the Head of Material

25

Auger OverloadAuger OverloadAuger OverloadAuger Overload

Page 7: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

7

26

What Happened Here?What Happened Here?What Happened Here?What Happened Here?� A hole in the side of the mat is the first sign of an

empty hopper

27

Head of Material

Control Starts Here

The Receiving

Hopper

The Auger Assembly

To be efficient the system

should remain full and be

running approximately 90% of

the paving time

28

Paving Width and ExtensionsPaving Width and ExtensionsPaving Width and ExtensionsPaving Width and Extensions

29

Always maintain a consistent head of material, level

with the auger shaft is ideal

Have auger/conveyor system running steadily approx.

90% of the time

Keep the conveyors full and hopper at least 1/4 full at all

times

Use feed control sensors

Adjust the ratio dials or flow gates to suit width, depth

and speed

Summary Summary Summary Summary – Head of MaterialHead of MaterialHead of MaterialHead of Material

Page 8: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

8

FACTOR NUMBER 3

Paving Speed

31

Paving SpeedPaving SpeedPaving SpeedPaving Speed

32

Paving SpeedPaving SpeedPaving SpeedPaving Speed

Mat Depth DecreasesMat Depth DecreasesMat Depth DecreasesMat Depth Decreases Mat Depth IncreasesMat Depth IncreasesMat Depth IncreasesMat Depth Increases

Paving Speed IncreasesPaving Speed IncreasesPaving Speed IncreasesPaving Speed Increases Paving Speed DecreasesPaving Speed DecreasesPaving Speed DecreasesPaving Speed Decreases

Ideal paving operationIdeal paving operationIdeal paving operationIdeal paving operation---- Paver operates nonPaver operates nonPaver operates nonPaver operates non----stop throughout the day.stop throughout the day.stop throughout the day.stop throughout the day.

Paving operation runs most efficiently when no waiting time is rPaving operation runs most efficiently when no waiting time is rPaving operation runs most efficiently when no waiting time is rPaving operation runs most efficiently when no waiting time is required equired equired equired

for trucks to arrive with material, and all starts and stops arefor trucks to arrive with material, and all starts and stops arefor trucks to arrive with material, and all starts and stops arefor trucks to arrive with material, and all starts and stops are made made made made

quickly and smoothly.quickly and smoothly.quickly and smoothly.quickly and smoothly.

FACTORS NUMBER 4 & 5FACTORS NUMBER 4 & 5FACTORS NUMBER 4 & 5FACTORS NUMBER 4 & 5

Screed Weight & Material Stability

Page 9: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

9

34

Factors 4 & 5Factors 4 & 5Factors 4 & 5Factors 4 & 5

Material Material

Stability Stability

Screed Weight

35

When the paver stops: Factor 4 becomes the

dominant factor

Mat Marks

36

Factor Affecting the ScreedFactor Affecting the ScreedFactor Affecting the ScreedFactor Affecting the Screed

Factor No 3:

Paving Speed

Factor No 5:

Material Stability

Factor No 4:

Screed Weight

Factor No 2:

Head of Material

Factor No 1:

Angle of Attack

37

Balancing the FactorsBalancing the FactorsBalancing the FactorsBalancing the Factors

Factor No 3:

Paving Speed

Factor No 2:

Head of Material

Factor No 1:

Angle of Attack

Horizontal Resistance to Paving SpeedHead of Material =Angle of Attack +

Any variation in these three factors will affect this balance and may cause undesired screed reactions

Page 10: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

10

The Road to QualityThe Road to QualityThe Road to QualityThe Road to Quality

Feed Systems

39

Material Flow Path Through the PaverMaterial Flow Path Through the PaverMaterial Flow Path Through the PaverMaterial Flow Path Through the Paver

Hopper

Conveyors

Augers

Screed

Fresh Mat

40

Hopper at Least ¼ full

Augers Built to Suit

Width of Screed -

Material Level with

Auger Shaft

Conveyors Kept Filled

Auger/ Conveyor OverviewAuger/ Conveyor OverviewAuger/ Conveyor OverviewAuger/ Conveyor Overview

41

Components of The TractorComponents of The TractorComponents of The TractorComponents of The Tractor� Outboard Auger Drive Left and Right Independent Augers

� Set the auger height at least 2 inch's above the mat depth

Page 11: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

11

42

Components of The TractorComponents of The TractorComponents of The TractorComponents of The Tractor� Center Drive Left and Right Independent Augers

43

Components of The TractorComponents of The TractorComponents of The TractorComponents of The Tractor

� Conveyor Chains � Conveyor Chains/Flow Gates

44

Proper Flow Gate PositionProper Flow Gate PositionProper Flow Gate PositionProper Flow Gate Position

� Only one feed sensor per side is

used with this system

� With this style feed system speeding

up the auger also speeds up the

conveyor

� Adjust the flow gates to maintain

material level at auger shaft height

� For extended paving widths a lower

gate position is required

� This allows material time to be

augured to the outer edges of the

screed without overloading the

center

Gates as installed on older style

pavers

45

Flow Gates or Ratio DialsFlow Gates or Ratio DialsFlow Gates or Ratio DialsFlow Gates or Ratio Dials

Page 12: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

12

46

Independent auger and conveyorIndependent auger and conveyorIndependent auger and conveyorIndependent auger and conveyor drive systems donrive systems donrive systems donrive systems don’t t t t

require flow gates instead ratio dials are used require flow gates instead ratio dials are used require flow gates instead ratio dials are used require flow gates instead ratio dials are used

� Ultrasonic Auger Sensor � Ultrasonic Conveyor Sensors

47

Ratio DialsRatio DialsRatio DialsRatio Dials

� Ratio dials set the head of material

� Unlike the original ultrasonic feed

systems that required moving the

sensor to change the pile height.

� Today's systems allow you to

change the pile heights by simply

turning the ratio dial

� When your paving speed changes

the ratio dials will need to be

adjusted to maintain the proper

head of material, auger and

conveyor speed

� Ratio Dials

48

These Images show the right and These Images show the right and These Images show the right and These Images show the right and

wrong way to mount feed sensorswrong way to mount feed sensorswrong way to mount feed sensorswrong way to mount feed sensors

� The feed sensors send out sound waves and need to be

positioned properly

� They don’t know the difference between asphalt or metal parts

of the paver

� If your auger or conveyor stop working the first thing to check

is the sensor position

49

These Images show the right andThese Images show the right andThese Images show the right andThese Images show the right and

wrong way to mount feed sensorswrong way to mount feed sensorswrong way to mount feed sensorswrong way to mount feed sensors

� Sensors may not work properly when subjected to excessive

heat

� Sensors have a working window, mounting them to close or to

far away can cause problems

Page 13: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

13

50

The Road to QualityThe Road to QualityThe Road to QualityThe Road to Quality

� With ratio dials and split

drive it is possible to short

feed without cutoff plates

� If what you are paving is to

wide to pave at full width,

dial the auger feed down

to off and run just the

conveyor in auto.

51

This Free Floating action provides a smooth surface finish by allowing

the screed to ride over high spots & fill low spots in the base

52

What happens if we attempt to

pave over an uneven base?

We see a condition in the mat known as:

Differential Compaction

53

Creating Differential Compaction Through Spillage

Page 14: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

14

54

Freshly Placed Mat

15% Compaction From Roller

Mat Profile After Compaction is Greatly Improved Compared to the Original

Base Profile

Original Uneven Base

15 m (50 ft)

Leveling Course

Milled Surface

The more layers that are laid: the better the surface finish

Differential CompactionDifferential CompactionDifferential CompactionDifferential Compaction

55

The Road to QualityThe Road to QualityThe Road to QualityThe Road to Quality

� The main components of the screed

� Main screed with adjustable crown

� Hydraulic extensions with slope

� End gates sometimes called edger plates or

wings

� The screed control stations

� Electric, diesel or propane screed plate

heaters

56

Primary Screed FunctionsPrimary Screed FunctionsPrimary Screed FunctionsPrimary Screed Functions

� Lays material to accurate

widths, depths and profiles

� Provides pre-compaction to

the mat

� Smoothes and seals the mat

� Provides the screed

operator with a platform so

he can control screed

position and material flow

rate

57

Flat Surface

Slope Right or Left

Wedge Right or Left

Positive Crown

Negative Crown or Invert

Main Line & Shoulder

Mat Profiles

Page 15: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

15

58

ProfilesProfilesProfilesProfiles

� Flat with extensions at full width

59

ProfilesProfilesProfilesProfiles

� Positive Crown

60

ProfilesProfilesProfilesProfiles

� Positive Crown with Extensions Sloped

61

ProfilesProfilesProfilesProfiles� Negative Crown / Invert

� This is what limits the % of Negative Crown / invert you

can achieve.

Page 16: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

16

62

Screed Designs, A Birds Eye ViewScreed Designs, A Birds Eye ViewScreed Designs, A Birds Eye ViewScreed Designs, A Birds Eye View

Front Front Front Front

Mounted Mounted Mounted Mounted

ExtensionsExtensionsExtensionsExtensions

Rear Mounted ExtensionsRear Mounted ExtensionsRear Mounted ExtensionsRear Mounted Extensions

Direction of travel

Wedge Lock

63

Setting Up the ScreedSetting Up the ScreedSetting Up the ScreedSetting Up the Screed1. Lower screed to reference

2. Center tow points

3. Null screed (Cranks are relaxed)

4. Turn cranks two turns CW or

CCW depending on your brand

of paver (increase AOA)

5. Pave & readjust slowly to correct

depth

64

Know where the screed gaugesKnow where the screed gaugesKnow where the screed gaugesKnow where the screed gauges

are and what they are forare and what they are forare and what they are forare and what they are for

� Extension Slope Crown Extension Height

65

How fast should I pave?

Page 17: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

17

66

Material supply to the hopper

Number and size of trucks

Rolling and compaction rates

Size of the mixing plant

Distance from plant to paver

Mat dimensions

Factors Affecting the Selection of Paving Factors Affecting the Selection of Paving Factors Affecting the Selection of Paving Factors Affecting the Selection of Paving

SpeedSpeedSpeedSpeed

67

The Road to QualityThe Road to QualityThe Road to QualityThe Road to Quality

How does a screed achieve

Pre-Compaction?

68

The Compaction FactorThe Compaction FactorThe Compaction FactorThe Compaction Factor� Percentage of Maximum Theoretical Density – Allow

Approximately 25% or ¼ inch per inch paved.

69

Forward Motion

Screed Weight

Screed HeatingVibration

Angle of Attack

Achieving Pre-Compaction

Page 18: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

18

70

Screed weight is an important factor in the pre-compaction of

the mat, here are some weights of 10’ screeds:

Front Mounted Extensions 6500 – 8000 lbs

Rear Mounted Extensions 8000 – 8800 lbs

Typical Screed WeightsTypical Screed WeightsTypical Screed WeightsTypical Screed Weights

71

Mat QualityMat QualityMat QualityMat Quality

� Also Begins With a Properly Set Screed

72

The Road to QualityThe Road to QualityThe Road to QualityThe Road to Quality Checking Checking Checking Checking

Lead CrownLead CrownLead CrownLead Crown

� Evenly Position Tow Points

� Drop The Screed Onto An Even Surface Null Depth Screws

� Pick The Screed Up Set It on The Safety Supports

� Use a String Line or Straight Edge, Check the Lead Crown to

Tail Crown Relationship

� If Adjustment is Required, You Need to Know How to Separate

the Lead Crown From The Tail

73

Checking Lead CrownChecking Lead CrownChecking Lead CrownChecking Lead Crown� Center Tow point � On an Even Surface Null Depth

Screws

Page 19: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

19

74

SafetySafetySafetySafety

� Before putting any part of your body

under a screed make sure it is

safely supported.

� If you are working with a wheel

paver place blocks under the

screed, to avoid injury in the event

of a tire failure

� Use caution to prevent burning

yourself if the screed has been

preheated

75

Checking Lead CrownChecking Lead CrownChecking Lead CrownChecking Lead Crown

� Using Nylon String Pulled Fiddle String Tight

76

Checking Main Screed Lead Crown at The CenterChecking Main Screed Lead Crown at The CenterChecking Main Screed Lead Crown at The CenterChecking Main Screed Lead Crown at The Center

� Set the tail to flat � Then check the lead, this screed

has an inverted lead crown

77

Release Pins Or Remove The Bolts That Tie Release Pins Or Remove The Bolts That Tie Release Pins Or Remove The Bolts That Tie Release Pins Or Remove The Bolts That Tie

The Crown Together The Crown Together The Crown Together The Crown Together

� After resetting lead crown

this Screed had a 1/32” gap

between the nut and the

String at the front and the

back was flat.

Page 20: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

20

78

Lead CrownLead CrownLead CrownLead Crown

� Lead crown adjustment may be necessary several times over

the life of the screed plate

� Set the lead crown to the manufacturers recommendation

(Not all Screeds Require lead Crown)

� Excess lead crown will greatly reduce the screed plate life

� An inverted lead crown can cause an open texture in the

center of the mat

� To much lead crown can cause an invert at the longitudinal

joints

79

The Road to QualityThe Road to QualityThe Road to QualityThe Road to Quality

�Next Check Extensions

for Parallel

80

Extensions Parallel to the MainExtensions Parallel to the MainExtensions Parallel to the MainExtensions Parallel to the Main� Checking a rear extension screed for

parallel

� As you run the extension out it must

stay level or you will not be able to

pave flat

81

Extensions Parallel to the MainExtensions Parallel to the MainExtensions Parallel to the MainExtensions Parallel to the Main� Checking at the rear of the extension by checking both front and back you can see if

you have any twist in the plate

� A twist can cause an uneven texture in the mat

Page 21: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

21

82

Now Check to see that the Extension Slope is Now Check to see that the Extension Slope is Now Check to see that the Extension Slope is Now Check to see that the Extension Slope is

set properlyset properlyset properlyset properly

� Some screeds will allow you to slope

beyond flat

� In this case knowing that your slope

gauge is set properly is very

important

� Other screeds require the inside of

the extension to have a slight preset

slope to compensate for deflection

� Be careful not to overdue this

adjustment, just like lead crown it

can cause an invert at the

longitudinal joints

� This screed needs the slope stop

adjusted

� If left like this it wont pave flat

83

Strike Off PlatesStrike Off PlatesStrike Off PlatesStrike Off Plates� When paving the front (attitude) of the screed should be 1/8 inch to 1/4 inch higher then the back

� If the screed is riding on its nose and you are doing everything else correctly, it could be that the strike off plate needs to come down a little

� What ever you need the back of the screed to do is what you need to do with the strike off plate

� In other words raising it will raise the tail and lowering it will lower the tail

� Always start with the manufacturers recommendation

84

The Road to QualityThe Road to QualityThe Road to QualityThe Road to Quality

�Safe Paver Operation

85

Safe Paver OperationSafe Paver OperationSafe Paver OperationSafe Paver Operation

Page 22: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

22

86

Safe Paver OperationSafe Paver OperationSafe Paver OperationSafe Paver Operation

87

Night Paving Can Be Especially DangerousNight Paving Can Be Especially DangerousNight Paving Can Be Especially DangerousNight Paving Can Be Especially Dangerous� You HAVE to be able to be seen

88

Discuss Potential Dangers Before Each Discuss Potential Dangers Before Each Discuss Potential Dangers Before Each Discuss Potential Dangers Before Each

ShiftShiftShiftShift� Always look out for each other

89

Safe Paver OperationSafe Paver OperationSafe Paver OperationSafe Paver Operation

Page 23: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

23

90

�Balanced Production

91

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

92

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

93

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

Page 24: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

24

94

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

95

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

96

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

97

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

Page 25: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

25

98

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

99

Balanced ProductionBalanced ProductionBalanced ProductionBalanced Production

� Stick to the plan

� If you know your balanced paving speed should be 35 FPM

� Don’t pave 60 FPM because of a hiccup at the start of the day

� All you will do is allow those first trucks to bunch up and return to close together on the next round

100

Mat Quality?Mat Quality?Mat Quality?Mat Quality?

101

All it took to fix this issue was focusing on All it took to fix this issue was focusing on All it took to fix this issue was focusing on All it took to fix this issue was focusing on

the basicsthe basicsthe basicsthe basics� If the screed person takes care in setting up and adjusting the screed it

will leave no transition lines or blemishes in the mat surface

Page 26: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

26

102

Center Line StreakingCenter Line StreakingCenter Line StreakingCenter Line Streaking

�� Any paver with a center drive auger Any paver with a center drive auger

box may cause center line streaking box may cause center line streaking

when using certain materialswhen using certain materials

�� Adjustment must be made to the Adjustment must be made to the

tractor and the screed to eliminate tractor and the screed to eliminate

these marksthese marks

103

What's wrong with this picture?What's wrong with this picture?What's wrong with this picture?What's wrong with this picture?

104

MTVMTVMTVMTV----windrow pavingwindrow pavingwindrow pavingwindrow paving

105

Other Types of Material Transfer Other Types of Material Transfer Other Types of Material Transfer Other Types of Material Transfer

VehiclesVehiclesVehiclesVehicles

Page 27: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

27

106

Topic 6Topic 6Topic 6Topic 6

�2D Grade and Slope

Control

107

Automatic Grade ControlAutomatic Grade ControlAutomatic Grade ControlAutomatic Grade Control

� Don’t confuse grade

control with slope

control

� Controlling

grade=controlling

elevation or mat

thickness

108

Automatic Slope Control Automatic Slope Control Automatic Slope Control Automatic Slope Control

� Don’t Confuse

Slope Control

With Grade

Control

� Always

Remember

Slope Doesn't

Care About

Yield

109

Ways to Control GradeWays to Control GradeWays to Control GradeWays to Control Grade

� Using a single sonic tracker

mounted to the end gate

Page 28: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

28

110

Ways to Control GradeWays to Control GradeWays to Control GradeWays to Control Grade

� Averaging with a drag ski

111

Ways to Control GradeWays to Control GradeWays to Control GradeWays to Control Grade

� Using a Sonic Averaging ski

112

Laser Systems

Control from a laser reference

Sonic Systems

Control from a physical reference

Slope Systems

Control from a gravitational reference

2D Non-Contacting Systems

� 2D Non Contact Controls2D Non-Contacting Systems

2D Non-Contacting Systems

113

Laser Control - Paving

� Laser Control

Page 29: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

29

114

Segregation Issues

115

Raising the Truck BedRaising the Truck BedRaising the Truck BedRaising the Truck Bed

116

Centerline Segregation

117

Preventing SegregationPreventing SegregationPreventing SegregationPreventing Segregation

Page 30: Advanced Paver Operations - Rocky Mountain Asphalt ...1 Asphalt Pavement: The Road to Quality Paver Operations Presented by Peter Fredrickson 2 Training Objectives We will cover The

30

118

Material Segregation In The HopperMaterial Segregation In The HopperMaterial Segregation In The HopperMaterial Segregation In The Hopper

� The Best Practice Is To Not Raise The

Hopper At All

� If You Are Going To Raise The Hopper

Between Loads, Do it Before The

Hopper Is Empty, You Should Never

Be Able To See The Conveyor Chains

119

1. Select a speed which balances the material delivery

to site and Avoid varying speeds

2. Keep the paver moving, keep stops to a minimum

3. Don’t out pace the rollers

5. Use smooth rapid start and stop techniques

6. Prevent truck to paver contact by using an MTV

7. It takes time to make a level change – Don’t rush or

over correct

8. Always maintain a consistent head of material, level

with the auger shaft is ideal

Summary

120

120

Thank YouThank YouThank YouThank You

A Smooth Combination