adjustment sum & contract-slide presentation

Embed Size (px)

Citation preview

  • 8/12/2019 adjustment sum & contract-slide presentation

    1/23

    SBQ 3722 PROFESSIONAL

    PRACTISE IIIADJUSTMENT OF CONTRACT SUM

    & FINAL ACCOUNTBy

    SHAZLYN BT. APIU

    TIMOTHY THOMAS

    RUBBY DEAN

  • 8/12/2019 adjustment sum & contract-slide presentation

    2/23

    QUESTIONS :

    1) DESCRIBE THE WORK PROCESS FOR THE

    SERVICE

    2) UNDERTAKES THE PLANNING & ORGANIZING

    OF ITS SOURCES TO ACCOMPLISH

    3) IDENTIFY THE PROBLEMS AND NECESSARY

    SUGGESTIONS TO IMPROVE

    4) MONITORING MECHANISM

  • 8/12/2019 adjustment sum & contract-slide presentation

    3/23

    ADJUSTMENT OF CONTRACT

    SUM& FINAL ACCOUNT

  • 8/12/2019 adjustment sum & contract-slide presentation

    4/23

    Adjustment of Contract SumThe Certificate adjustments of Contract Sum were introduced for

    the purpose of adjusting the amount of the contract price. The

    total contract price shall be adjusted to take into account any

    additional or lack of the total contract price.

    Adjustment of Final AccountFinal account is an accounts that are provided to show the

    payments that have been made including defects, claimfor damages or extra expenses.

    Final accounts must be provided as soon as possible after the

    contractor to meet its obligations under the contract

  • 8/12/2019 adjustment sum & contract-slide presentation

    5/23

    Adjustment of the contract sum in the final account

    falls under several relevant items which is listed in the

    standard form of contract and conditions

    Sums that are to be Deducted :-

    a) prime cost sumsb) provisional sums

    c) variations that are omissions

    d) any other amount that are to be deducted fromthe contract sum/

  • 8/12/2019 adjustment sum & contract-slide presentation

    6/23

    An important part of the contractors

    quantity surveyors work is the agreement of

    the Final Account.

    Both Clients Quantity Surveyor andContractors Quantity Surveyor to work

    together to produce an agreed statement of

    the amount money to be paid at the end of a

    building contract by the employer to the

    contractor

  • 8/12/2019 adjustment sum & contract-slide presentation

    7/23

    The person who is responsible to prepare the Adjustment of

    Contract Sum and Final Account

    a) Contract Manager

    b) Senior Quantity Surveyor

    Duties:

    a) Re-measurements usually done by the junior Qs.b) Adjustment, VO, Form APK & PHK & negotiation with the

    contractor by the Sr. QS.

    c) Final Account by the Contract Manager

  • 8/12/2019 adjustment sum & contract-slide presentation

    8/23

    Adjustment of Contract Sum includes :

    a) APKArahan Perubahan Kerja

    b) PHK - Pelarasan Harga Kontrak

    c) Provisional Sum

    d) Prime Cost Sum

  • 8/12/2019 adjustment sum & contract-slide presentation

    9/23

    Adjustment of Contract Sum includes

    a) APKArahan Perubahan Kerja

    Continuity of board approval on V.O, APK are required.

    Consist of instructions to be carried out by the Contractor

    Any claim due to this VO will be highlighted in this form.

    S.O and Contractor to signed (if agreed)b) PHK - Pelarasan Harga Kontrak

    After finalized the APK, new contract sum will be adjusted

    accordingly

    All collective APK will be summarized

    Endorsement and agreement from both parties are required

  • 8/12/2019 adjustment sum & contract-slide presentation

    10/23

  • 8/12/2019 adjustment sum & contract-slide presentation

    11/23

    Adjustment of Contract Sum

    d) Prime Cost Sum

    is an allowance that calculated by the consultant for

    the supply of work or materials to be provided by

    a contractor or supplier that nominated by the client.

    The works is awarded to the nominated sub-contractor / supplier. Omit the original PC Sum and

    add the awarded NSCs/NSs contract sum and profit

    and attendance which is allowed in Contract.

    The final adjustment is made after completion of

    works and final cost is ascertained. PC Sums that are

    not used shall be deducted from the Contract Sum.

  • 8/12/2019 adjustment sum & contract-slide presentation

    12/23

    Adjustment of Contract Sum

    e) KKSKelulusan kuantiti Sementara

    is an allowance that calculated by the consultant for

    the supply of work or materials to be provided by

    a contractor or supplier that nominated by the client.

    The works is awarded to the nominated sub-contractor / supplier. Omit the original PC Sum and

    add the awarded NSCs/NSs contract sum and profit

    and attendance which is allowed in Contract.

    The final adjustment is made after completion of

    works and final cost is ascertained. PC Sums that are

    not used shall be deducted from the Contract Sum.

    http://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdf
  • 8/12/2019 adjustment sum & contract-slide presentation

    13/23

    Example PHK Form

    Pelarasan Harga Kontrak

    PHK bagi item Credit for

    Material for the Material

    on Site.

    Pelarasan harga dinilai

    mengikut kiraan yang

    telah ditetapkan.

    http://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdf
  • 8/12/2019 adjustment sum & contract-slide presentation

    14/23

    Example APK Form

    Arahan Perubahan Kerja-

    kerja tambahan untuk

    membekalkan Peralatan

    Elektrik.

    http://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdf
  • 8/12/2019 adjustment sum & contract-slide presentation

    15/23

    Example APK Form

    Arahan Perubahan Kerja-

    kerja tambahan untukmembekalkan Peralatan

    Elektrik.

    Permohonan untuk

    mendapatkan kelulusan

    Perubahan Kerja.

    Di nyatakan huraian kerja,

    anggaran perubahan kerja

    & Penca-punca

    perubahan kerja.

    http://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdfhttp://g/Proffesional%20Pratice%20III-Sem%206/Asiment%20ref/JKR-PHK.pdf
  • 8/12/2019 adjustment sum & contract-slide presentation

    16/23

    Preparation of Adjustment Contract Sum

    Total contract price adjustment certificate must be

    prepared and remove when the total contract priceshould be adjusted. It covers variation order.

    All items in the certificate must be properly filled

    Date is the date the certificate is a certificate signed PP

    Calculation detail of the adjustment must be

    appended except for adjustments due to changes in

    work.

    The certificate must be signed by the PP and theoriginal shall be issued to the contractor.

  • 8/12/2019 adjustment sum & contract-slide presentation

    17/23

    The contractor have to provide the architect or QS with all

    documents necessary for the final account preparation not later

    than 6 months after practical completion. Within 3 months of for

    the architect or QS to prepare the final account sum and send this

    to the contractor

    The area to be cover under preparations of Final Account:

    Variations

    Re-measurement of provisional quantity in the Contract Bills

    NSC account

    Nominated supplier account

    Loss and expense caused by disturbance of the regular processof the works

    Its about sense of finality to the negotiations leading up to the

    agreement of the Final Account between the parties to the

    contract.

    Preparation of Final Account

  • 8/12/2019 adjustment sum & contract-slide presentation

    18/23

    If there a doubt about the accuracy of any the original billed

    items, he can make a request to the QS for work concerned tobe measured on-site.

    Sums to be deducted:

    a) Provisional sums and the value of work for which

    approximate quantities are included in contract bills.b) Variations that are omissions

    c) Amounts allowable to the employer under the fluctuations

    clauses

    d) Any other amount that is required by the contract to be

    deducted from the contract sum.

    Preparation of Final Account

  • 8/12/2019 adjustment sum & contract-slide presentation

    19/23

    Sums to be added:

    a) Total amounts of nominated subcontracts finally adjusted

    b) Where the contractor has tendered for work that was to have

    been performed by a nominated subcontractor and his tender

    has been accepted, the amount of the tender suitably adjustedc) Any amounts due to nominated suppliers, including cash

    discounts of 5 per cent

    d) The contractor's profit on the above amounts

    Preparation of Final Account

  • 8/12/2019 adjustment sum & contract-slide presentation

    20/23

    Variation Orders (VO) are often a cause of contract

    conflicts and may lead to negotiation, mediation /arbitration. It includes changing in design, quantities,

    quality, working conditions, and sequence of work.

    The contractor fails to agree with the valuation of

    work. The disagreement may cause delay in

    certifying the amount of final account.

    There a rate that the contractor had to follow in

    certain specification but the contractor normally putthe item rate uncertain because of strategies.

    Problem faced by the Firm

  • 8/12/2019 adjustment sum & contract-slide presentation

    21/23

    Necessary Suggestions To Improve

    Verify the work progress within one(1) month period.

    Held a meeting at least twice a week to solve small

    problem that occur at site .

    The architect has the authority to order minor changes

    in the work not involving adjustment in the contract

    sum. Such changes shall be done in writing and shall

    bind with owner and contractor.

  • 8/12/2019 adjustment sum & contract-slide presentation

    22/23

    Monitoring Mechanism

    Review actual site practices and processes to control

    expenditure for materials, labor plant/machinery and

    subcontractors.

    External relationship and information; communicating with,

    coordinating with, and influencing related management

    units, stakeholders and clients.

    Internal relationship, including the use of inter-unit

    committees within the same management systems and

    communicating with other individuals

    Monitoring physical, financial, accounting and social effects;

    and Periodic evaluation of performance at indicator events

    and timely adjustment of plans.

  • 8/12/2019 adjustment sum & contract-slide presentation

    23/23

    THANK YOU