Activity Name OriginalDuration
Start Finish
Preparation and processing of the twelvth floor of th 76 31-Mar-15 14-Jun-15
General 76 31-Mar-15 14-Jun-15Dates (Milestones) 76 31-Mar-15 14-Jun-15
Project Start 0 31-Mar-15Establishing ELEC., Plumbing and HVAC 0 24-Apr-1550% Of Work Done 0 16-May-1580% Of Work Done (Painting Finished) 0 04-Jun-15Project End 0 14-Jun-15
General Works 76 31-Mar-15 14-Jun-15Site Mobilization 3 31-Mar-15 02-Apr-15Demolish & Dismantle Works 3 31-Mar-15 02-Apr-15Licenses and Permissions 7 31-Mar-15 06-Apr-15Delivering Project 1 14-Jun-15 14-Jun-15
Surveying Works 1 03-Apr-15 03-Apr-15Surveying Works 1 03-Apr-15 03-Apr-15
Technical Office Works 5 04-Apr-15 09-Apr-15Arch WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit Arch WSD 5 04-Apr-15 08-Apr-15Material Submittal 5 04-Apr-15 08-Apr-15Arch WSD approval 0 09-Apr-15 09-Apr-15Material Approval 0 09-Apr-15 09-Apr-15
Elec. WSD 5 04-Apr-15 09-Apr-15Prepare & Submit Elec. WSD 5 04-Apr-15 08-Apr-15Material Submittal 5 04-Apr-15 08-Apr-15Electrical WSD approval 0 09-Apr-15 09-Apr-15Material Approval 0 09-Apr-15 09-Apr-15
HVAC WSD 5 04-Apr-15 09-Apr-15Prepare & Submit HVAC WSD 5 04-Apr-15 08-Apr-15Material Submittal 5 04-Apr-15 08-Apr-15HVAC WSD approval 0 09-Apr-15 09-Apr-15Material Approval 0 09-Apr-15 09-Apr-15
Plum. WSD 5 04-Apr-15 09-Apr-15Prepare & Submit Plumping WSD 5 04-Apr-15 08-Apr-15Material Submittal 5 04-Apr-15 08-Apr-15Plumbing WSD approval 0 09-Apr-15 09-Apr-15Material Approval 0 09-Apr-15 09-Apr-15
Architectural Work 66 09-Apr-15 13-Jun-15Masonary Work 3 09-Apr-15 11-Apr-15Kitchen & Bathrooms Insulation 1 12-Apr-15 12-Apr-15Plastering 3 27-Apr-15 29-Apr-15Files Room Strengthening 4 30-Apr-15 03-May-15Floor Work 43 30-Apr-15 11-Jun-15
Mosaic Tiles Flooring Installation 5 30-Apr-15 04-May-15
28 04 11 18 25 02 09 16 23 30 06 13 20April 2015 May 2015 June 2015
14-Jun-15
14-Jun-1514-Jun-15
Project StartEstablishing ELEC., Plumbing and HVAC
50% Of Work Done80% Of Work Done (Painti
Project E14-Jun-15
Site MobilizationDemolish & Dismantle Works
Licenses and PermissionsDeliverin
03-Apr-15, Surveying WorksSurveying Works
09-Apr-15, Technical Office Works09-Apr-15, Arch WSD
Prepare & Submit Arch WSDMaterial SubmittalArch WSD approvalMaterial Approval09-Apr-15, Elec. WSD
Prepare & Submit Elec. WSDMaterial SubmittalElectrical WSD approvalMaterial Approval09-Apr-15, HVAC WSD
Prepare & Submit HVAC WSDMaterial SubmittalHVAC WSD approvalMaterial Approval09-Apr-15, Plum. WSD
Prepare & Submit Plumping WSDMaterial SubmittalPlumbing WSD approvalMaterial Approval
13-Jun-15, Masonary Work
Kitchen & Bathrooms InsulationPlastering
Files Room Strengthening11-Jun-15, Flo
Mosaic Tiles Flooring Installation
Preparation and processing of thetwelvth floor of the headquarters in
Garden CityMaster Schedule
ADIB Time Schedule V4 03-APR-2015 Page 1 of 3 Project Management DepartmentMisr Contraco Group
Activity Name OriginalDuration
Start Finish
Ceramic Flooring Installation 5 30-Apr-15 04-May-15Marble Flooring Installation 5 30-Apr-15 04-May-15HDF Flooring Installation 4 06-Jun-15 09-Jun-15HPL Flooring Installation 4 06-Jun-15 09-Jun-15Finishing Marble Flooring 4 06-Jun-15 09-Jun-15Vinyl Flooring 4 06-Jun-15 09-Jun-15Carpet Installation 2 10-Jun-15 11-Jun-15
Wall Work 26 30-Apr-15 25-May-15Marble Walls Installation 4 30-Apr-15 03-May-15MDF Walls Installation 4 30-Apr-15 03-May-15Ceramic Cladding Installation 4 30-Apr-15 03-May-15Gypsum Galvanized Studs 4 05-May-15 08-May-15Gypsum Cladding Installation 3 09-May-15 11-May-15Skirting Installation 2 24-May-15 25-May-15
Partitions 32 09-May-15 09-Jun-15Gypsum Partitions Installation 4 09-May-15 12-May-15Bathroom Partitions Installation 4 09-May-15 12-May-15Wooden Partitions Installation 3 24-May-15 26-May-15Glass Partitions Installation (Securit) 3 31-May-15 02-Jun-15HPL Bathroom Partitions Installation 3 07-Jun-15 09-Jun-15
Doors & Windows 6 24-May-15 29-May-15Metal Doors Installation 3 24-May-15 26-May-15Wooden Doors Installation 3 24-May-15 26-May-15Wooden Frames Installation 2 25-May-15 26-May-15Wooden Crossings Installation 2 25-May-15 26-May-15Alumital Windows Installation 2 28-May-15 29-May-15
Ceiling Work 25 12-May-15 05-Jun-15Galvanized Steel Sub-structure for Gypsum Board 5 12-May-15 16-May-15Gypsum Board Installation 4 17-May-15 20-May-15Ceiling Tiles Installation 4 17-May-15 20-May-15Finishing Plastic Painting for Ceiling 4 02-Jun-15 05-Jun-15
Stairs Work 39 30-Apr-15 07-Jun-15Stairs Marble Installation 4 30-Apr-15 03-May-15Stairs Marble Finishing 1 04-May-15 04-May-15Handrail Installation 2 06-Jun-15 07-Jun-15
Painting 24 21-May-15 13-Jun-15Establishing Painting 7 21-May-15 27-May-15Finishing Walls Painting 3 02-Jun-15 04-Jun-15Accessories & Wallpaper Works 2 12-Jun-15 13-Jun-15
External Work 6 09-May-15 14-May-15Rolling Shutter 6 09-May-15 14-May-15
Rolling Shutter Installation 5 09-May-15 13-May-15Rolling Shutter Testing 1 14-May-15 14-May-15
28 04 11 18 25 02 09 16 23 30 06 13 20April 2015 May 2015 June 2015
Ceramic Flooring InstallationMarble Flooring Installation
HDF Flooring InstHPL Flooring InstFinishing Marble Vinyl Flooring
Carpet Installa25-May-15, Wall Work
Marble Walls InstallationMDF Walls InstallationCeramic Cladding Installation
Gypsum Galvanized StudsGypsum Cladding Installation
Skirting Installation09-Jun-15, Partitio
Gypsum Partitions InstallationBathroom Partitions Installation
Wooden Partitions InstallationGlass Partitions Installation (
HPL Bathroom Pa29-May-15, Doors & Windows
Metal Doors InstallationWooden Doors InstallationWooden Frames InstallationWooden Crossings Installation
Alumital Windows Installation05-Jun-15, Ceiling Work
Galvanized Steel Sub-structure for Gypsum BoardGypsum Board InstallationCeiling Tiles Installation
Finishing Plastic Paintin07-Jun-15, Stairs Wor
Stairs Marble InstallationStairs Marble Finishing
Handrail Installation13-Jun-15,
Establishing PaintingFinishing Walls Painting
Accessorie14-May-15, External Work14-May-15, Rolling Shutter
Rolling Shutter InstallationRolling Shutter Testing
Preparation and processing of thetwelvth floor of the headquarters in
Garden CityMaster Schedule
ADIB Time Schedule V4 03-APR-2015 Page 2 of 3 Project Management DepartmentMisr Contraco Group
Activity Name OriginalDuration
Start Finish
MEP 53 13-Apr-15 04-Jun-15Plumping 50 13-Apr-15 01-Jun-15
Fixing Drainage & Feeding pipes 2 13-Apr-15 14-Apr-15Testing Pipes 1 15-Apr-15 15-Apr-15Sanitary Fixtures Installation 1 31-May-15 31-May-15Testing & Commisioning 1 01-Jun-15 01-Jun-15
Electrical Works 53 13-Apr-15 04-Jun-15Main Power Feeder 2 13-Apr-15 14-Apr-151st. Fix Installation (Pipes Installation) 12 15-Apr-15 26-Apr-152nd Fix Installation (Wire Pulling) 12 15-Apr-15 26-Apr-15Cable Tray Installation 5 21-Apr-15 25-Apr-15Distribution Pannels Installation 3 31-May-15 02-Jun-15Sockets Installation (including data & telephone) 1 31-May-15 31-May-15Lighting Fixture Installation 2 02-Jun-15 03-Jun-15Testing & Commisioning 1 04-Jun-15 04-Jun-15
HVAC 52 13-Apr-15 03-Jun-15Indoor Units 2 13-Apr-15 14-Apr-15Duct Work & Insulation 2 15-Apr-15 16-Apr-15Freon Installation 2 17-Apr-15 18-Apr-15Drainage System 2 19-Apr-15 20-Apr-15Fresh Air & Exhaust Air Fans Installation 2 21-Apr-15 22-Apr-15Outdoor Units Connection 2 23-Apr-15 24-Apr-15Grills Installation 2 31-May-15 01-Jun-15Thermostate Installation 1 02-Jun-15 02-Jun-15Testing & Commisioning 1 03-Jun-15 03-Jun-15
28 04 11 18 25 02 09 16 23 30 06 13 20April 2015 May 2015 June 2015
04-Jun-15, MEP01-Jun-15, Plumping
Fixing Drainage & Feeding pipesTesting Pipes
Sanitary Fixtures InstallationTesting & Commisioning
04-Jun-15, Electrical WorkMain Power Feeder
1st. Fix Installation (Pipes Installation)2nd Fix Installation (Wire Pulling)
Cable Tray InstallationDistribution Pannels Installat
Sockets Installation (including dLighting Fixture Installation
Testing & Commisioning03-Jun-15, HVAC
Indoor UnitsDuct Work & Insulation
Freon InstallationDrainage System
Fresh Air & Exhaust Air Fans InstallationOutdoor Units Connection
Grills InstallationThermostate Installation
Testing & Commisioning
Preparation and processing of thetwelvth floor of the headquarters in
Garden CityMaster Schedule
ADIB Time Schedule V4 03-APR-2015 Page 3 of 3 Project Management DepartmentMisr Contraco Group