Activity Name Original Duration Start Finish Preparation and processing of the twelvth floor of th 76 31-Mar-15 14-Jun-15 General 76 31-Mar-15 14-Jun-15 Dates (Milestones) 76 31-Mar-15 14-Jun-15 Project Start 0 31-Mar-15 Establishing ELEC., Plumbing and HVAC 0 24-Apr-15 50% Of Work Done 0 16-May-15 80% Of Work Done (Painting Finished) 0 04-Jun-15 Project End 0 14-Jun-15 General Works 76 31-Mar-15 14-Jun-15 Site Mobilization 3 31-Mar-15 02-Apr-15 Demolish & Dismantle Works 3 31-Mar-15 02-Apr-15 Licenses and Permissions 7 31-Mar-15 06-Apr-15 Delivering Project 1 14-Jun-15 14-Jun-15 Surveying Works 1 03-Apr-15 03-Apr-15 Surveying Works 1 03-Apr-15 03-Apr-15 Technical Office Works 5 04-Apr-15 09-Apr-15 Arch WSD 5 04-Apr-15 09-Apr-15 Prepare & Submit Arch WSD 5 04-Apr-15 08-Apr-15 Material Submittal 5 04-Apr-15 08-Apr-15 Arch WSD approval 0 09-Apr-15 09-Apr-15 Material Approval 0 09-Apr-15 09-Apr-15 Elec. WSD 5 04-Apr-15 09-Apr-15 Prepare & Submit Elec. WSD 5 04-Apr-15 08-Apr-15 Material Submittal 5 04-Apr-15 08-Apr-15 Electrical WSD approval 0 09-Apr-15 09-Apr-15 Material Approval 0 09-Apr-15 09-Apr-15 HVAC WSD 5 04-Apr-15 09-Apr-15 Prepare & Submit HVAC WSD 5 04-Apr-15 08-Apr-15 Material Submittal 5 04-Apr-15 08-Apr-15 HVAC WSD approval 0 09-Apr-15 09-Apr-15 Material Approval 0 09-Apr-15 09-Apr-15 Plum. WSD 5 04-Apr-15 09-Apr-15 Prepare & Submit Plumping WSD 5 04-Apr-15 08-Apr-15 Material Submittal 5 04-Apr-15 08-Apr-15 Plumbing WSD approval 0 09-Apr-15 09-Apr-15 Material Approval 0 09-Apr-15 09-Apr-15 Architectural Work 66 09-Apr-15 13-Jun-15 Masonary Work 3 09-Apr-15 11-Apr-15 Kitchen & Bathrooms Insulation 1 12-Apr-15 12-Apr-15 Plastering 3 27-Apr-15 29-Apr-15 Files Room Strengthening 4 30-Apr-15 03-May-15 Floor Work 43 30-Apr-15 11-Jun-15 Mosaic Tiles Flooring Installation 5 30-Apr-15 04-May-15 8 04 11 18 25 02 09 16 23 30 06 13 20 April 2015 May 2015 June 2015 14-Jun-15 14-Jun-15 14-Jun-15 Project Start Establishing ELEC., Plumbing and HVAC 50% Of Work Done 80% Of Work Done (Painti Project E 14-Jun-15 Site Mobilization Demolish & Dismantle Works Licenses and Permissions Deliverin 03-Apr-15, Surveying Works Surveying Works 09-Apr-15, Technical Office Works 09-Apr-15, Arch WSD Prepare & Submit Arch WSD Material Submittal Arch WSD approval Material Approval 09-Apr-15, Elec. WSD Prepare & Submit Elec. WSD Material Submittal Electrical WSD approval Material Approval 09-Apr-15, HVAC WSD Prepare & Submit HVAC WSD Material Submittal HVAC WSD approval Material Approval 09-Apr-15, Plum. WSD Prepare & Submit Plumping WSD Material Submittal Plumbing WSD approval Material Approval 13-Jun-15, Masonary Work Kitchen & Bathrooms Insulation Plastering Files Room Strengthening 11-Jun-15, Flo Mosaic Tiles Flooring Installation Preparation and processing of the twelvth floor of the headquarters in Garden City Master Schedule ADIB Time Schedule V4 03-APR-2015 Page 1 of 3 Project Management Department Misr Contraco Group

ADIB Time Schedule V4.0

Embed Size (px)

Citation preview

Page 1: ADIB Time Schedule V4.0

Activity Name OriginalDuration

Start Finish

Preparation and processing of the twelvth floor of th 76 31-Mar-15 14-Jun-15

General 76 31-Mar-15 14-Jun-15Dates (Milestones) 76 31-Mar-15 14-Jun-15

Project Start 0 31-Mar-15Establishing ELEC., Plumbing and HVAC 0 24-Apr-1550% Of Work Done 0 16-May-1580% Of Work Done (Painting Finished) 0 04-Jun-15Project End 0 14-Jun-15

General Works 76 31-Mar-15 14-Jun-15Site Mobilization 3 31-Mar-15 02-Apr-15Demolish & Dismantle Works 3 31-Mar-15 02-Apr-15Licenses and Permissions 7 31-Mar-15 06-Apr-15Delivering Project 1 14-Jun-15 14-Jun-15

Surveying Works 1 03-Apr-15 03-Apr-15Surveying Works 1 03-Apr-15 03-Apr-15

Technical Office Works 5 04-Apr-15 09-Apr-15Arch WSD 5 04-Apr-15 09-Apr-15

Prepare & Submit Arch WSD 5 04-Apr-15 08-Apr-15Material Submittal 5 04-Apr-15 08-Apr-15Arch WSD approval 0 09-Apr-15 09-Apr-15Material Approval 0 09-Apr-15 09-Apr-15

Elec. WSD 5 04-Apr-15 09-Apr-15Prepare & Submit Elec. WSD 5 04-Apr-15 08-Apr-15Material Submittal 5 04-Apr-15 08-Apr-15Electrical WSD approval 0 09-Apr-15 09-Apr-15Material Approval 0 09-Apr-15 09-Apr-15

HVAC WSD 5 04-Apr-15 09-Apr-15Prepare & Submit HVAC WSD 5 04-Apr-15 08-Apr-15Material Submittal 5 04-Apr-15 08-Apr-15HVAC WSD approval 0 09-Apr-15 09-Apr-15Material Approval 0 09-Apr-15 09-Apr-15

Plum. WSD 5 04-Apr-15 09-Apr-15Prepare & Submit Plumping WSD 5 04-Apr-15 08-Apr-15Material Submittal 5 04-Apr-15 08-Apr-15Plumbing WSD approval 0 09-Apr-15 09-Apr-15Material Approval 0 09-Apr-15 09-Apr-15

Architectural Work 66 09-Apr-15 13-Jun-15Masonary Work 3 09-Apr-15 11-Apr-15Kitchen & Bathrooms Insulation 1 12-Apr-15 12-Apr-15Plastering 3 27-Apr-15 29-Apr-15Files Room Strengthening 4 30-Apr-15 03-May-15Floor Work 43 30-Apr-15 11-Jun-15

Mosaic Tiles Flooring Installation 5 30-Apr-15 04-May-15

28 04 11 18 25 02 09 16 23 30 06 13 20April 2015 May 2015 June 2015

14-Jun-15

14-Jun-1514-Jun-15

Project StartEstablishing ELEC., Plumbing and HVAC

50% Of Work Done80% Of Work Done (Painti

Project E14-Jun-15

Site MobilizationDemolish & Dismantle Works

Licenses and PermissionsDeliverin

03-Apr-15, Surveying WorksSurveying Works

09-Apr-15, Technical Office Works09-Apr-15, Arch WSD

Prepare & Submit Arch WSDMaterial SubmittalArch WSD approvalMaterial Approval09-Apr-15, Elec. WSD

Prepare & Submit Elec. WSDMaterial SubmittalElectrical WSD approvalMaterial Approval09-Apr-15, HVAC WSD

Prepare & Submit HVAC WSDMaterial SubmittalHVAC WSD approvalMaterial Approval09-Apr-15, Plum. WSD

Prepare & Submit Plumping WSDMaterial SubmittalPlumbing WSD approvalMaterial Approval

13-Jun-15, Masonary Work

Kitchen & Bathrooms InsulationPlastering

Files Room Strengthening11-Jun-15, Flo

Mosaic Tiles Flooring Installation

Preparation and processing of thetwelvth floor of the headquarters in

Garden CityMaster Schedule

ADIB Time Schedule V4 03-APR-2015 Page 1 of 3 Project Management DepartmentMisr Contraco Group

Page 2: ADIB Time Schedule V4.0

Activity Name OriginalDuration

Start Finish

Ceramic Flooring Installation 5 30-Apr-15 04-May-15Marble Flooring Installation 5 30-Apr-15 04-May-15HDF Flooring Installation 4 06-Jun-15 09-Jun-15HPL Flooring Installation 4 06-Jun-15 09-Jun-15Finishing Marble Flooring 4 06-Jun-15 09-Jun-15Vinyl Flooring 4 06-Jun-15 09-Jun-15Carpet Installation 2 10-Jun-15 11-Jun-15

Wall Work 26 30-Apr-15 25-May-15Marble Walls Installation 4 30-Apr-15 03-May-15MDF Walls Installation 4 30-Apr-15 03-May-15Ceramic Cladding Installation 4 30-Apr-15 03-May-15Gypsum Galvanized Studs 4 05-May-15 08-May-15Gypsum Cladding Installation 3 09-May-15 11-May-15Skirting Installation 2 24-May-15 25-May-15

Partitions 32 09-May-15 09-Jun-15Gypsum Partitions Installation 4 09-May-15 12-May-15Bathroom Partitions Installation 4 09-May-15 12-May-15Wooden Partitions Installation 3 24-May-15 26-May-15Glass Partitions Installation (Securit) 3 31-May-15 02-Jun-15HPL Bathroom Partitions Installation 3 07-Jun-15 09-Jun-15

Doors & Windows 6 24-May-15 29-May-15Metal Doors Installation 3 24-May-15 26-May-15Wooden Doors Installation 3 24-May-15 26-May-15Wooden Frames Installation 2 25-May-15 26-May-15Wooden Crossings Installation 2 25-May-15 26-May-15Alumital Windows Installation 2 28-May-15 29-May-15

Ceiling Work 25 12-May-15 05-Jun-15Galvanized Steel Sub-structure for Gypsum Board 5 12-May-15 16-May-15Gypsum Board Installation 4 17-May-15 20-May-15Ceiling Tiles Installation 4 17-May-15 20-May-15Finishing Plastic Painting for Ceiling 4 02-Jun-15 05-Jun-15

Stairs Work 39 30-Apr-15 07-Jun-15Stairs Marble Installation 4 30-Apr-15 03-May-15Stairs Marble Finishing 1 04-May-15 04-May-15Handrail Installation 2 06-Jun-15 07-Jun-15

Painting 24 21-May-15 13-Jun-15Establishing Painting 7 21-May-15 27-May-15Finishing Walls Painting 3 02-Jun-15 04-Jun-15Accessories & Wallpaper Works 2 12-Jun-15 13-Jun-15

External Work 6 09-May-15 14-May-15Rolling Shutter 6 09-May-15 14-May-15

Rolling Shutter Installation 5 09-May-15 13-May-15Rolling Shutter Testing 1 14-May-15 14-May-15

28 04 11 18 25 02 09 16 23 30 06 13 20April 2015 May 2015 June 2015

Ceramic Flooring InstallationMarble Flooring Installation

HDF Flooring InstHPL Flooring InstFinishing Marble Vinyl Flooring

Carpet Installa25-May-15, Wall Work

Marble Walls InstallationMDF Walls InstallationCeramic Cladding Installation

Gypsum Galvanized StudsGypsum Cladding Installation

Skirting Installation09-Jun-15, Partitio

Gypsum Partitions InstallationBathroom Partitions Installation

Wooden Partitions InstallationGlass Partitions Installation (

HPL Bathroom Pa29-May-15, Doors & Windows

Metal Doors InstallationWooden Doors InstallationWooden Frames InstallationWooden Crossings Installation

Alumital Windows Installation05-Jun-15, Ceiling Work

Galvanized Steel Sub-structure for Gypsum BoardGypsum Board InstallationCeiling Tiles Installation

Finishing Plastic Paintin07-Jun-15, Stairs Wor

Stairs Marble InstallationStairs Marble Finishing

Handrail Installation13-Jun-15,

Establishing PaintingFinishing Walls Painting

Accessorie14-May-15, External Work14-May-15, Rolling Shutter

Rolling Shutter InstallationRolling Shutter Testing

Preparation and processing of thetwelvth floor of the headquarters in

Garden CityMaster Schedule

ADIB Time Schedule V4 03-APR-2015 Page 2 of 3 Project Management DepartmentMisr Contraco Group

Page 3: ADIB Time Schedule V4.0

Activity Name OriginalDuration

Start Finish

MEP 53 13-Apr-15 04-Jun-15Plumping 50 13-Apr-15 01-Jun-15

Fixing Drainage & Feeding pipes 2 13-Apr-15 14-Apr-15Testing Pipes 1 15-Apr-15 15-Apr-15Sanitary Fixtures Installation 1 31-May-15 31-May-15Testing & Commisioning 1 01-Jun-15 01-Jun-15

Electrical Works 53 13-Apr-15 04-Jun-15Main Power Feeder 2 13-Apr-15 14-Apr-151st. Fix Installation (Pipes Installation) 12 15-Apr-15 26-Apr-152nd Fix Installation (Wire Pulling) 12 15-Apr-15 26-Apr-15Cable Tray Installation 5 21-Apr-15 25-Apr-15Distribution Pannels Installation 3 31-May-15 02-Jun-15Sockets Installation (including data & telephone) 1 31-May-15 31-May-15Lighting Fixture Installation 2 02-Jun-15 03-Jun-15Testing & Commisioning 1 04-Jun-15 04-Jun-15

HVAC 52 13-Apr-15 03-Jun-15Indoor Units 2 13-Apr-15 14-Apr-15Duct Work & Insulation 2 15-Apr-15 16-Apr-15Freon Installation 2 17-Apr-15 18-Apr-15Drainage System 2 19-Apr-15 20-Apr-15Fresh Air & Exhaust Air Fans Installation 2 21-Apr-15 22-Apr-15Outdoor Units Connection 2 23-Apr-15 24-Apr-15Grills Installation 2 31-May-15 01-Jun-15Thermostate Installation 1 02-Jun-15 02-Jun-15Testing & Commisioning 1 03-Jun-15 03-Jun-15

28 04 11 18 25 02 09 16 23 30 06 13 20April 2015 May 2015 June 2015

04-Jun-15, MEP01-Jun-15, Plumping

Fixing Drainage & Feeding pipesTesting Pipes

Sanitary Fixtures InstallationTesting & Commisioning

04-Jun-15, Electrical WorkMain Power Feeder

1st. Fix Installation (Pipes Installation)2nd Fix Installation (Wire Pulling)

Cable Tray InstallationDistribution Pannels Installat

Sockets Installation (including dLighting Fixture Installation

Testing & Commisioning03-Jun-15, HVAC

Indoor UnitsDuct Work & Insulation

Freon InstallationDrainage System

Fresh Air & Exhaust Air Fans InstallationOutdoor Units Connection

Grills InstallationThermostate Installation

Testing & Commisioning

Preparation and processing of thetwelvth floor of the headquarters in

Garden CityMaster Schedule

ADIB Time Schedule V4 03-APR-2015 Page 3 of 3 Project Management DepartmentMisr Contraco Group