Additional Slides.pptx

Embed Size (px)

Citation preview

Performance Measurement Baseline (PMB)

Parametric estimation example

High Level EstimatesPercentage of base estimateMan-days (Gross)$ per dayCostsProject management15%5540022000Design10%10030030000Coding25%22525062500Testing (ST)10%5025012500Testing (IT)10%5025012500Deployment5%102502500Total100%485156000 2006 Capgemini - All rights reserved8Cost Budgeting example

PERT

PERT Exercise

PERT Exercise solutions

S-Curve to represent Cost baseline

2006 Capgemini - All rights reserved13Quantitive Risk Analysis EMV

Decision Tree Question

Decision Tree Answer