Upload
dangminh
View
224
Download
1
Embed Size (px)
Citation preview
®
INSIDE THIS ISSUE:
18 BRINGING MILLER CREEK
BACK TO FULL PRODUCTION
26 NEW TOOL ALLOWS
ON-SITE GOVERNOR TESTING
46 HOW MARINE HYDROKINETICS
IS PROGRESSING
Stay Current
Powering UpADDING HYDRO TO AN EXISTING DAM
October 2014
1410hr_C1 1 9/29/14 4:27 PM
10 HYDRO REVIEW / October 2014 www.hydroworld.com
The U.S. Army Corps of Engineers (USACE)
broke ground on Mahoning Creek Dam, a
food control structure that also provides recreational
opportunities in the Allegheny River basin in western
Pennsylvania, in 1939. By 1941, the concrete dam
was fnished. The design included a conduit that
would allow the potential energy of water stored
behind the dam to be used to produce hydroelectric
power. However, the plans to develop hydropower
at this dam were postponed due to steel shortages
associated with the country’s accelerating mobiliza-
tion efforts for World War II.
Seventy-two years later, Enduring Hydro LLC,
a Maryland-based company, fulflled the vision of
those early engineers. In a public-private partnership
with the USACE’s Pittsburgh District and enabled
by the 2009 American Recovery and Reinvestment
Act and Pennsylvania Alternative and Clean Energy
Program, Enduring Hydro constructed a 6-MW
hydroelectric facility utilizing Mahoning Creek Dam.
The Mahoning Creek Hydroelectric Company
Project is located on Mahoning Creek in Armstrong
County, Pa. Mahoning Creek Dam is one of 16
facilities in the USACE’s Pittsburgh District used
to provide food protection to the lower Allegheny
River Valley and upper Ohio River. This concrete
gravity dam is 187 feet high and 926 feet long. The
hydro project includes a 50-foot-high intake structure
attached to the upstream face of the dam equipped
with a removable trashrack and a vertical slide gate. A
secondary penstock closure device, a butterfy valve,
is located in a concrete vault downstream from the
dam. A steel liner pipe was inserted into the existing
conduit through the dam. Water is conveyed from
the dam through a 1,090-foot-long, 10-foot-diameter
buried penstock to the powerhouse containing two
Francis turbines (4 MW and 2 MW) with two
vertical-shaft generating units.
The electricity produced is transferred to West
Penn Power at the nearest point of interconnec-
tion via an underground 1,200-foot-long 25-kV
line. A 10-year power purchase agreement was in
place before construction of the project began with
ground-disturbing activities on Jan. 31, 2013. Com-
mercial operations commenced on Dec. 26, 2013.
The Mahoning Creek project was designed to
Kristina M. Johnson is
chief executive offcer,
Mark Garner is managing
director/hydropower, and
John Collins is executive
vice president and director
of business development
with Enduring Hydro LLC.
John Strough is senior
project manager with
Hydro Consulting &
Maintenance Services Inc.
By Kristina M. Johnson,
E. Mark Garner, John R.
Collins and John Strough
More than 70 years in the making but less than a year in the execution, the 6-MW Mahoning Creek Hydroelectric Project, developed at an existing dam, is now providing clean, reliable power to residents in western Pennsylvania.
N e w D e v e l o p m e n t
1410hr_10 10 9/29/14 4:24 PM
www.hydroworld.com October 2014 / HYDRO REVIEW 11
produce more than 20,000 MWh per year
for more than 50 years, which is enough
energy to power 1,800 homes with 100%
clean electricity. Furthermore, this hydro-
power facility will avoid 20,000 tons of C02,
20 tons of N0x, and 460 grams of mercury
emissions on an annual basis, equivalent to
taking 4,000 cars off the road or planting
1,000,000 fully grown trees with respect to
the reduction in greenhouse gas emissions.
In addition to the above-mentioned
environmental benefts, retroftting non-
powered dams creates well-paying, highly-
skilled crafts jobs, thereby economically
empowering local communities. The project
created more than 100 jobs utilizing local
labor in Armstrong County. The project
developer hired several Pennsylvania frms,
including Hanlon Electric in Monroeville,
Renick Brothers in Slippery Rock, and
Hydro Consulting and Maintenance Ser-
vices Inc. in York.
According to Oak Ridge National Labo-
ratory’s “Assessment of Energy Potential at
Non-Powered Dams in the United States,”
an April 2012 study, there are 45 non-
powered dams in the Commonwealth of
Pennsylvania that could collectively provide
hydropower capacity of 630 MW. From
our experience, if these 45 projects were
developed they potentially could create
more than 10,000 jobs, power 200,000
homes, and take the equivalent of 400,000
cars off the road.
Innovations in the plant design
The hydro project was designed by Mead
and Hunt of Madison, Wisc., under an
original contract with Advanced Hydro
Solutions (AHS) of Fairlawn, Ohio. Endur-
ing Hydro bought Mahoning Creek Hydro-
electric Company, the owner of the 50-year
Federal Energy Regulatory Commission
license, from AHS on July 31, 2012. We
worked closely with Mead & Hunt and
Kleinschmidt Associates of Pittsfield,
Maine, to obtain the Section 404 and 408
permits from the USACE and the 401
Water Quality Certifcate from the Com-
monwealth of Pennsylvania’s Department
of Environmental Protection (PADEP),
which needed to be in place before breaking
ground in January 2013.
During the construction process, an
intake structure on the upstream side of the
dam was installed and then sealed before the
concrete plug downstream was removed,
obviating the need for a cofferdam. A dam
liner pipe was inserted to connect with the
penstock. The project’s penstock, supplied
by Northwest Pipe Co. of Vancouver,
Wash., is 10 feet in diameter and extends
1,090 feet downstream from Mahoning
Creek Dam before bifurcating into two
smaller sections. The bifurcated piece is
located just before the penstock enters the
powerhouse. In total, 54 pieces of 20 feet
in length were placed and welded on site.
The buried penstock bifurcates into
two 110-foot-long sections, one 8-foot-
diameter section and one 6-foot-diameter
section. The hydro plant was designed
so that during low-fow periods, only the
2-MW unit, which can generate power
with a minimum fow of 120 cubic feet
per second (cfs), operates. During the
shoulder periods (fow between 350 and
500 cfs), we expect the 4-MW unit, which
requires a minimum fow of 350 cfs, to
The liner pipe was installed through Mahoning Creek Dam and the opening in the bulkhead plate was cut to
ensure optimal transmission of water stored in the reservoir to the penstock when the roller gate is open.
The Mahoning Creek Hydroelectric Company powerhouse contains a control room and two turbine-generator
units. The 4-MW generator is shown in the foreground and the 2-MW generator is visible in the background.
1410hr_11 11 9/29/14 4:24 PM
http://hydroreview.hotims.com RS #7
12 HYDRO REVIEW / October 2014 www.hydroworld.com
operate. Finally, during the periods when water fows exceed
500 cfs, both the 2-MW and 4-MW units will produce power.
Environmental considerations in the FERC license and the
adaptive management plan with the USACE require a minimum
bypass fow of 60, 40 and 30 cfs, during the low-, shoulder and
high-fow periods, respectively.
All turbine components including the draft tubes, spiral cases,
runner, distributor and shut-off valves were supplied by China
Harbour Engineering Company Ltd. (CHEC) No. 9 of Beijing,
China. The generators, switchgear, and control system were sup-
plied by Hyundai Ideal of Mansfeld, Ohio.
The powerhouse’s switchgear and controls are sensitive, com-
plex technologies. To mitigate the technological risk of installing
separate interfaces in the powerhouse, Enduring Hydro worked
with PCX of Clayton, N.C., to skid-mount the instrumentation
controls prior to installation. PCX integrated various technologies
in their factory and their expert team assembled a comprehensive
skid that was installed in one piece in the powerhouse.
The dam liner pipe was installed and the opening in the bulkhead
plate was cut, ensuring optimal transmission of water stored in
the reservoir to the penstock when the roller gate, supplied by
Steel-Fab of Fitchburg, Mass., is open. The valve vault built just
downstream from the dam liner pipe includes the butterfy valve,
supplied by Henry Pratt Co. of Aurora, Ill. This construction
process required detailed planning and coordination between the
Enduring Hydro team, FERC, and the USACE.
Innovations in the permitting, approval
and construction process
To keep the project on schedule, the Enduring Hydro team worked
diligently to obtain the permits and approvals required from the
The project’s 10-foot-diameter penstock extends 1,090 feet downstream from
Mahoning Creek Dam before bifurcating into two smaller sections just before
the penstock enters the powerhouse.
1410hr_12 12 9/29/14 4:24 PM
ROLLER GATESMahoning Creek Project
Steel-Fab designed and manufactured
a 9 ft. wide x 13 ft. tall roller gate for
The Ruhlin Company for the construction
of Enduring Hydro, LLC's six-megawatt
hydroelectric facility located on the
Mahoning Creek Dam.
■ Jet Flow Gates
■ Bonneted Gates
■ Miter Gates
■ Gate Operating Systems
■ Fixed Cone Valves
430 Crawford St., Fitchburg, MA 01420 USATel 978-345-1112 ■ Fax 978-343-7925
www.steel-fab-inc.com
■ Crest Gates
■ Roller Gates
■ Slide Gates
■ Tainter Gates
■ Floating Bulkheads
The Mahoning Creek Project was designed
by Mead and Hunt, Inc.,whose founder was
involved in the development of the Hoover
Dam. The concrete gravity dam, constructed
in 1941 by the U.S. Army Corps of Engineers,
with a height of 162 feet and a length of
926 feet, impounds Mahoning Creek,
a tributary of the Allegheny River, and
provides flood protection for the lower
Allegheny River Valley and the upper
Ohio River.
http://hydroreview.hotims.com RS #9
14 HYDRO REVIEW / October 2014 www.hydroworld.com
various stakeholders and governing agencies,
including the USACE (Pittsburgh District,
Great Lakes and Ohio River Division, and
headquarters), FERC, PADEP and Pennsyl-
vania Fish and Boat Commission (PAFBC).
To comply with the various regulatory
processes and approvals and maintain
the project’s tight construction schedule,
Enduring Hydro planned the construction
activities in stages. Each stage corresponded
to the receipt of the regulatory approval
over a four month period of time, as shown
in Table 1 on page 16.
The Enduring Hydro team credits the
strong public-private partnership with the
USACE, FERC, PADEP, and PAFBC for
the successful and timely completion of
the project.
Challenges
Enduring Hydro faced several major chal-
lenges while completing the project. First
and foremost was obtaining the necessary
permits and notices to proceed in a timely
manner. Our consultants at Mead & Hunt
and Kleinschmidt Associates were invalu-
able in helping us anticipate and address the
concerns of these key regulatory partners
to obtain all the approvals. This was the
frst greenfeld hydroelectric project built
in Pennsylvania in more than 20 years and
therefore the frst plant built at a USACE
dam post-Hurricane Katrina with the new
408 permit requirement.
The second major challenge was the
narrow site condition. The access point,
from the McRae Furnace Bridge across
a runoff stream from Mahoning Creek to
the dam, was often referred to as a “bowl-
ing alley,” allowing for a single ingress and
egress. This required effcient construction
management in order to maintain the proj-
ect’s tight construction schedule.
A third challenge involved assessing the
geotechnical conditions where the penstock
would be buried, prior to receiving the
notice to proceed on ground-disturbing
activities. Once we had full access to the
site, we discovered that the solid rock
foundation was deeper than originally
anticipated. While the lack of solid rock
led to less rock excavation, it did require
proper flling material to be sourced and
installed to support the penstock. The lack
of rock also required the installation of rock
anchors for the stilling basin wall between
the penstock and the bank of the stilling
basin just downstream of the dam.
Results
As a result of the teamwork and collabora-
tion between Enduring Hydro; its suppli-
ers and vendors; and the USACE, FERC,
PADEP and PAFBC, the project began
commercial operations on Dec. 26, 2013.
Achieving commercial operations prior to
Jan. 1, 2014, allowed the project to qualify
for the 1603 cash-back grant from the U.S.
Treasury. Since commencing commercial
operations, the project has produced about
12,000 MWh of electricity during the frst
half of 2014. We estimate the project will
generate about 20,000 MWh in its frst
year of operation.
1410hr_14 14 9/29/14 4:24 PM
16 HYDRO REVIEW / October 2014 www.hydroworld.com
Effective Nov. 14, 2013, Mahoning
Creek Hydroelectric Project was certifed as
a “Low Impact” facility by the Low Impact
Hydropower Institute (LIHI) Certifcation
Program, an independent non-proft orga-
nization. LIHI certifcation is granted to
projects that comply with LIHI’s rigorous
review process and meet its goals of achiev-
ing required clean energy benefts while
meeting strict environmental standards.
Acknowledgments
The Mahoning Creek Dam powerhouse
is named for E. Mark Garner, a long-time
champion of hydropower throughout his 25
years in the industry. As an engineer, chief
executive offcer, and business leader, he
has advocated for innovation and provided
value engineering to improve hydropower
into the 20th and 21st centuries. Through
his leadership, Mahoning Creek Dam pro-
duced electricity in 2013, carrying out the
vision of the original dam builders from
1939. We would also like to acknowledge
the contributions of David Nammour and
David Fox, project engineers; Jennifer
Mesirow, controller; Ginger Lew, managing
director; Marcus Switzer, compliance and
regulatory; Andrew Longenecker, senior
associate; and Smitha Ramakrishna, analyst,
all part of the Enduring Hydro team. ■
Table 1: Timeline for Acquiring Regulatory Approvals and Permits
Date Event Entity Requirement
7/31/2012Mahoning Creek Hydroelectric purchased from Advanced Hydro Solutions
Enduring Hydro
1/31/2013Permission granted for ground clearing activities at the access road
FERC
2/19/2013Section 401 permit issued — ground clear-ing begins
Pennsylvania Depart-ment of Environmental
Protection (PADEP)
2/26/2013 All private easements secured Enduring Hydro
3/7/2013 Limited Power Permit issued PADEP
3/8/2013 Section 408 and Section 404 permits issuedU.S. Army Corps of Engineers (USACE)
3/12/2013Permission granted to start work on the intake structure, powerhouse and further geotechnical investigation
FERC
3/14/2013 Financing plan approved FERC
3/22/2013
Permission granted to perform land-disturbing activities on USACE property, including site mobilization, access road refurbishment, and powerhouse and tailrace ground clearing
USACE
5/2/2013Final design review meeting with indepen-dent external peer review (IEPR) team at the site
FERC
5/8/2013Limited permission granted to start work on penstock and valve vault
FERC
5/10/2013
Dive plan approved and permission granted to proceed with construction of all activities under "dam" as shown in the "Preliminary Partial Project Construction Schedule"
USACE
5/31/2013
Permission granted to proceed with the rest of the construction activities under "penstock," including work at the intake structure
USACE
8/13/2013IEPR meets at the site to inspect the existing conduit through the dam prior to placement of penstock
FERC
11/13/2013IEPR meets at the site to inspect that con-struction is in compliance with approved plans and specifcations
FERC
12/16/2013IEPR meets at the site for fnal walk-through and inspection prior to plant water-up and commissioning
FERC
12/17/2013Memorandum of agreement signed estab-lishing operational protocols between MCHC and USACE
USACE
12/26/2013Mahoning Creek Hydroelectric Project Commissioned
Enduring Hydro
About Enduring Hydro
The Enduring Hydro team is led
by former U.S. Under Secretary of
Energy Dr. Kristina Johnson, former
chief executive offcer of Voith Hydro
Mark Garner, former chief fnance
offcer of Constellation Energy John
Collins, and former senior counselor to
the White House National Economic
Council Ginger Lew. Working with our
senior associate Andrew Longenecker,
controller Jennifer Mesirow, project
engineers David Nammour and David
Fox and chief of staff Marcus Swit-
zer, this team brought on-line the frst
non-powered dam in Pennsylvania
in more than 20 years. Our team is
committed to helping clean our air
by replacing carbon-based electricity
with environmentally responsible, run-
of-river hydropower at greenfeld and
brownfeld sites.
1410hr_16 16 9/29/14 4:24 PM