Page 1 ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE CONTRACT DOCUMENTS AND CONSTRUCTION SPECIFICATIONS FOR WINDSOR CRUDE OIL TERMINAL From: Michael Brake, JR Engineering To: All Plan holders and/or Prospective Bidders. The following revisions, additions and/or deletions are hereby made a part of the Contract Documents and plans for the above referenced project as fully and completely as if the same were fully set forth therein: BIDDING REQUIREMENTS Bidders are required to acknowledge receipt of this Addendum by replying to the notification email. REVISIONS TO BID SET PLANS Sheet 10 A liner was added to all non-concrete containment areas. Notes have been added. The flare containment area detail has been updated. Sheet 18 The pavement plan has been revised to have concrete pavement at the unloading area in place of hot mix asphalt pavement. Sheet 18A A joint plan was added to the sheets for detailing the concrete pavement in the unloading area. CLARIFICATIONS The Temporary Transloading plans have been posted on the FTP site for reference. Bidders are not to provide any bids for the items on the temporary plans, except that the bidders shall provide a bid to furnish and install the condensate discharge line from the flare knock tank to the SafeRack. This is included in the Addendum A3 bid schedule. Electrical plans: The existing electrical items are shown in a lighter shade on the plans and the items to be bid are in a bolder line weight. RESPONSES TO BIDDER QUESTIONS 1. In what bid item(s) should we include the borings for the 16” DIP Service Water Relocation as shown on Sheet 29 of 57. The 16” water line relocation shown on Sheet 29 will not be completed with this project. Please disregard Sheet 29. 2. What manufacturer for the 60 gal vertical tank? Manchester or equivalent and must be ASME rated to 200 psi maximum allowable working pressure. 3. What is the PSI on the air system? The owner-supplied air compressor is 150psi max pressure. 4. What is the material for the 2” compressed air line for under SafeRack and on ground? The line is 2” galvanized steel pipe on the ground and under the rack. 5. There are eight LACT tank VAREC measuring devices located on this drawing, who is required to provide and install? The Contractor.

ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

Page 1

ADDENDUM NUMBER A3 – (DATED August 8, 2012)

TO THE CONTRACT DOCUMENTS AND CONSTRUCTION SPECIFICATIONS FOR

WINDSOR CRUDE OIL TERMINAL

From: Michael Brake, JR Engineering

To: All Plan holders and/or Prospective Bidders.

The following revisions, additions and/or deletions are hereby made a part of the Contract Documents andplans for the above referenced project as fully and completely as if the same were fully set forth therein:

BIDDING REQUIREMENTS

Bidders are required to acknowledge receipt of this Addendum by replying to the notification email.

REVISIONS TO BID SET PLANS

Sheet 10A liner was added to all non-concrete containment areas. Notes have been added. The flarecontainment area detail has been updated.Sheet 18The pavement plan has been revised to have concrete pavement at the unloading area in place ofhot mix asphalt pavement.Sheet 18AA joint plan was added to the sheets for detailing the concrete pavement in the unloading area.

CLARIFICATIONSThe Temporary Transloading plans have been posted on the FTP site for reference. Bidders are notto provide any bids for the items on the temporary plans, except that the bidders shall provide a bidto furnish and install the condensate discharge line from the flare knock tank to the SafeRack. Thisis included in the Addendum A3 bid schedule.

Electrical plans: The existing electrical items are shown in a lighter shade on the plans and the itemsto be bid are in a bolder line weight.

RESPONSES TO BIDDER QUESTIONS

1. In what bid item(s) should we include the borings for the 16” DIP Service Water Relocationas shown on Sheet 29 of 57. The 16” water line relocation shown on Sheet 29 willnot be completed with this project. Please disregard Sheet 29.

2. What manufacturer for the 60 gal vertical tank? Manchester or equivalent and must beASME rated to 200 psi maximum allowable working pressure.

3. What is the PSI on the air system? The owner-supplied air compressor is 150psimax pressure.

4. What is the material for the 2” compressed air line for under SafeRack and on ground? Theline is 2” galvanized steel pipe on the ground and under the rack.

5. There are eight LACT tank VAREC measuring devices located on this drawing, who isrequired to provide and install? The Contractor.

Page 2: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

Page 2

6. On the two existing storage tanks, who is required to provide and install VAREC 250automatic tank gauges? The Contractor. The storage tank gauges are notultrasonic, they have floats. The floating roofs of the storage tanks allow forinstallation of the float.

7. For the proving arm connection pipe going to the containment berm, the piping is not shownin bold. Does this need to be included in the mechanical bid? Yes.

8. Is the additional unistrut and all thread shown on the SafeRack to be provided and installed bythe mechanical contractor? Is the unistrut to be galvanized, painted green, or stainless steel?Yes, to be provided by contractor. Galvanized.

9. Is the air eliminator to be installed and provided by the mechanical contractor and what is themanufacturer? Yes, to be provided by contractor, FMC or equivalent.

10. What size are the existing crude oil tanks heights and dimensions? This will help in acquiringthe level transmitter. The existing oil tanks are 60’ in diameter, 48’ high. Thetanks have been drained and cleaned.

11. Is there an access manway on the existing crude oil tanks to install level measuring devices?There are spiral stairways on the tanks with roof access.

12. Addendum No. 9 under product pipe details it says to remove condensate loading arm.SafeRack is shown with loading arm. Please advise. Please disregard the first 9addenda. Current addenda begin with the prefix ‘A’. There will be nocondensate loading arm.

13. Pump house plan shows domestic water system and equipment. Do you want to carry pricingfor all domestic items? Yes, all domestic water service items are included in thebid.

14. Who is going to install the potable water line from pump house to loading platform? Thecontractor will be responsible for the installation of all water lines shown in theplans.

15. When will the remaining control drawings be available? They will be available ibyThursday morning or bidders will be advised to make an allowance for thosesheets.

16. Please provide specifications for 100,000 Gallon steel storage tank structure? Steel storagetank shall meet AWWA D100-96.

17. Please provide specifications for 100,000 Gallon steel storage tank interior & exteriorcoatings? Interior and exterior tank coatings shall meet AWWA D102-11.

18. Please provide specifications for 100,000 Gallon steel storage tank exterior insulation? 2”R16 spray-on polyurethane insulation with steel or aluminum siding forprotection.

19. Please provide specifications for Pump House prefabricated building? Pre-manufacturedmetal building, R30 insulation. Wood buildings are not permitted.

20. Please provide specifications for Air Compressor Shed? Pre-manufactured metalbuilding, R30 insulation. Wood buildings are not permitted.

21. Please provide specifications for Warming Huts? Warming huts are provided with theSafeRack equipment by owner and require installation by the Contractor.SafeRack approval drawings are provided with this Addendum.

22. Please provide a schedule of those items to be painted or receive coatings, and a list of itemsnot to be painted? All steel pipes shall be primed and painted. The followingpaint colors shall be used:

Crude pipes: BlackCondensate pipes: RedVapor pipes: Yellow or OrangeCasing pipes: Same as carrier pipeAbove-ground Domestic pipes: BlueAbove-ground Fire pipes: Black

Any galvanized or insulated pipe shall not be painted.23. Are the Type 3 Barricades existing or to be provided under this proposal? The type 3

barricades are no longer proposed and should be disregarded.

Page 3: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

Page 3

24. Who will construct the temporary loading facility? The temporary facility will beconstructed in advance of the Crude Oil Terminal by a separate contractor.

25. What is the sales tax rate? The site is located in unincorporated Weld Countywhich according to the Colorado Department of Revenue does not have a salestax. The state sales tax is 2.9%.

END OF ADDENDUM NUMBER A3

Page 4: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE COST

Demolition1 Removal of FES 2 EA $ $2 Clearing and Grubbing 4.2 AC $ $3 Removal of Pipe (<30") 9 LF $ $4 Removal of Inlet 2 EA $ $5 Removal of Manhole (Storm) 1 EA $ $6 Removal of Electric Pull Box 1 EA $ $7 Removal of Electric Conduit 146 LF $ $8 Remove Light Fixture [2 per pole] 16 EA $ $9 Remove and Relocate Light Pole 4 EA $ $10 Remove Fence and Gates 755 LF $ $11 Removal of Asphalt 2,405 SY $ $12 Adjust Manhole Grade Ring 2 EA $ $13 Remove Steel Containment Stairways 4 EA $ $

Site Improvements14 Unclassified Excavation (CIP) 7,644 CY $ $15 Anchor Trailer (provided by owner) and Install Utilities 1 LS $ $16 Chain Link Fence (48") 2,135 LF $ $17 5 Foot Gate (Chain link) 4 EA $ $18 Inlet, Type R 1 EA $ $19 Inlet, Type C 2 EA $ $20 Light Pole 8 EA $ $21 Light Fixture, (Overhead) [2 per pole] 30 EA $ $22 Light Fixture, (Flood Lights) 18 EA $ $23 Light Pole Foundations 12 EA $ $24 Reconditioning 9,924 SY $ $25 Recycled Asphalt (Cold Asphalt Pavement) 770 CY $ $26 Concrete Pavement (7.5 Inch) 1,150 SY $ $27 Geomembrane (Impervious Liner, PVC, 40 mil) 1,358 SY $ $28 Aggregate Base Course, Class 6 2,206 CY $ $29 Curb and Gutter, Type 2 (Section IIB) 150 LF $ $30 Bollard 42 EA $ $31 12" RCP (Class 3) 58 LF $ $32 18" RCP (Class 3) 46 LF $ $33 12" RCP FES 2 EA $ $34 Connect to Existing Manhole (Storm) 1 EA $ $35 4" PVC SDR35 (Perforated) 800 LF $ $36 Underdrain Filter Fabric 720 SY $ $37 Aggregate, ASTM C-33 #4 [Underdrain] 30 CY $ $38 Aggregate, ASTM C-33 #57 or #67 [Underdrain] 60 CY $ $39 8" Plug 2 EA $ $40 15" Plug 2 EA $ $41 Patch Hole in Concrete Containment Wall 2 EA $ $42 2" PVC Control Conduit 1 LS $ $43 2" Electrical Conduit 1 LS $ $44 Controls and Control Wiring 1 LS $ $45 Electrical (Elecrtical and Duct Banks) 1 LS $ $

Erosion Control46 Silt Fence 2,256 LF $ $47 Vehicle Tracking Control 1 EA $ $48 Seeding and Mulching 1.6 AC $ $49 Inlet Protection 3 EA $ $50 Outet Protection 1 EA $ $

Compressed Air51 Shed (Air Compressor) 10'x10' 1 LS $ $52 60 Gallon Vertical ASME Air Tank 1 LS $ $53 3/4" Galvanized Steel Pipe (150 Class, Threaded) [Compressed Air] 10 LF $ $54 1" Galvanized Steel Pipe (150 Class, Threaded) [Compressed Air] 128 LF $ $55 2" Galvanized Steel Pipe (150 Class, Threaded) [Compressed Air] 860 LF $ $56 3/4" Liquid Separator 1 EA $ $57 3/4" Pressure Regulating Valve 1 EA $ $58 1" Ball Valve 12 EA $ $59 2" Ball Valve 1 EA $ $60 3/4" Tee 1 EA $ $61 1" Tee 24 EA $ $62 2"x1" Tee 12 EA $ $63 2"x3/4" Reducer 1 EA $ $64 1"-3/8" Bushing 24 EA $ $65 3/8" Quick Connect 24 EA $ $

Windsor Crude Oil TerminalMusket Corporation

Addendum A3 Bid Schedule - August 8, 2012

Windsor Crude Oil TerminalBid ScheduleAddendumA3August 8, 2012 Page 1 of 5

Page 5: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE COST

Domestic Water66 20"x16" Tee (M.J.) 1 EA $ $67 30"x24" Tee (M.J.) 1 EA $ $68 24"x16" Reducer 1 EA $ $69 16"x12" Reducer 2 EA $ $70 12" Gate Valve 3 EA $ $71 3" Meter 1 LS $ $72 7'x9' Precast Vault [3" Meter] 1 EA $ $73 12" PVC (Pressure Class 150) 1,960 LF $ $74 12" 11.25° Bend 2 EA $ $75 12" 45° Bend 2 EA $ $76 12" 90° Bend 3 EA $ $77 12" 45° Vertical Bend 10 EA $ $78 12" Tee 1 EA $ $79 24" Steel Pipe [Casing Pipe] 57 LF $ $80 2" Blow-Off Assembly 1 EA $ $81 3/4" Meter --- EA $ $82 3/4" Meter Pit 1 EA $ $83 1" PVC Schedule 40 39 LF $ $84 2" PVC Schedule 40 468 LF $ $85 1" Copper Service Line 11 LF $ $86 1" Copper Service Line with Heat Trace [SafeRack] 666 LF $ $87 1" 90° Bend 1 EA $ $88 2" 45° Bend 2 EA $ $89 2" 90° Bend 3 EA $ $90 1" Copper Tee 4 EA $ $91 2"x1" Tee 1 EA $ $92 3" Steel Tee 4 EA $ $93 1" I.D. Fiberglass Pipe Insulation 3/4" Thickness 666 LF $ $94 3" Welded Steel Pipe [Casing Pipe] 666 LF $ $95 1" Vertical Riser w/Heat Trace 2 EA $ $96 4" PVC C900 [Casing Pipe] 22 LF $ $

Pump House and Storage97 30'x24'x14' Fabricated Steel Pump House 1 LS $ $98 100,000 Gallon Fire Storage Tank 1 LS $ $99 Fire Storage Tank Level Transducer 1 LS $ $100 Domestic Water Pump 1 LS $ $101 Domestic Pressure Tank 1 LS $ $102 Fire Pump 1 LS $ $103 1/2" Copper Pipe 8 LF $ $104 2" PVC Schedule 40 82 LF $ $105 2" Galvanized Steel Schedule 40 12 LF $ $106 2" 45° Bend 2 EA $ $107 2" Tee 2 EA $ $108 2" Ball Valve 6 EA $ $109 2" Electric Ball Valve 1 EA $ $110 2" Check Valve 4 EA $ $111 2"x1" Reducer 2 EA $ $112 Electric Flow Control Valve 1 EA $ $113 1/2" Pressure Relief Valve 1 EA $ $114 12" Tapping Saddle 1 EA $ $115 1" P.D. Meter 1 EA $ $116 8" DIP Class 350 27 LF $ $117 12" DIP Class 350 15 LF $ $118 12" Gate Valve 2 EA $ $119 12" Check Valve 1 EA $ $120 12" Fire Pressure Relief Valve 1 EA $ $121 2" 90° Bend 7 EA $ $122 8" 90° Bend 4 EA $ $123 12" 90° Bend 4 EA $ $124 12"x8" Tee 2 EA $ $125 2" I.D. Fiberglass Pipe Insulation 2" Thickness with Heat Trace 12 LF $ $126 12" I.D. Fiberglass Pipe Insulation 2" Thickness with Heat Trace 10 LF $ $127 Concrete Splash Block 1 EA $ $

Fire Suppression128 Fire Hydrant 5 EA $ $129 6" DIP Class 350 [Fire Hydrant Lateral] 93 LF $ $130 12" DIP Class 350 [Fire Main] 1,148 LF $ $131 12" 11.25° Bend 4 EA $ $132 12" 45° Bend 7 EA $ $133 12" 90° Bend 2 EA $ $134 12" Tee (M.J.) 2 EA $ $135 12"x6" Reducer 3 EA $ $136 12"x6" Tee (M.J.) 1 EA $ $137 6" Gate Valve 5 EA $ $

Windsor Crude Oil TerminalBid ScheduleAddendumA3August 8, 2012 Page 2 of 5

Page 6: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE COST

Structural138 Install SafeRack, Components, and all Appurtenances 1 LS $ $139 Install LACT Tanks with Compacted Sand Foundation and Grade Bands 8 EA $ $140 Install LACT Tanks Catwalk Structure 1 LS $ $141 Containment Area Wall Buttresses 70 EA $ $142 Screw Piles 1 LS $ $143 F/A Screw Piles --- LF $ $144 Cap Beams and Tie Beams 1 LS $ $145 Concrete Column Stubs and SafeRack Base Plates 76 EA $ $146 Concrete Pad (Propane Tanks) and Anchor Tanks to Pad 1 LS $ $147 Concrete Pad and Anchors (Vapor Combustion Unit) 1 LS $ $148 Concrete Pad and Anchors (LACT Pumps) 1 LS $ $149 Concrete Pad and Anchors (Loading Pumps) 1 LS $ $150 Concrete Pad and Anchors (Warming Huts) 2 EA $ $151 Concrete Pad and Anchors (Water Pump House) 1 LS $ $152 Concrete Pad and Anchors (Fire Tank) 1 LS $ $153 Concrete Pad and Anchors (Air Compressor Shed) 1 LS $ $154 Concrete Pad (Knockout Tanks) 2 EA $ $155 Unloading Area Containment Vault 1 LS $ $156 Containment Wall Extension 1 LS $ $157 Pedestrian Crossings [Steam Trench] 5 EA $ $158 Pipe Crossings [Steam Trench] 1 EA $ $159 Vapor Line Support Tower, Footings, Plates, and Structural Piping 22 EA $ $160 Thrust Blocks (Concrete Base) 66 EA $ $161 Thrust Blocks (Soil Base) 156 EA $ $162 Crude Loading Arm Meter Support 12 EA $ $163 Structural Steel [Pipe Hangers] 2,451 LB $ $164 Pipe Hangers (4") 95 EA $ $165 Pipe Hangers (8") 38 EA $ $

Proving Piping166 4" Welded Steel Pipe (A53B ERW Type E) [Proving Piping] 366 LF $ $167 4" 45° Bend (A53 Grade B) [Proving Piping] 4 EA $ $168 4" 90° Bend (A53 Grade B) [Proving Piping] 4 EA $ $169 4" Tee (A53 Grade B) [Proving Piping] 2 EA $ $170 4"x2" Tee (A53 Grade B) [Proving Piping] 8 EA $ $171 8"x4" Tee (A53 Grade B) [Proving Piping] 6 EA $ $172 2" Ball Valve [Proving Piping] 8 EA $ $173 4" Gate Valve [Proving Piping] 6 EA $ $174 8" Gate Valve [Proving Piping] 3 EA $ $175 2" Welded Steel Pipe (A53B ERW Type E) [Proving Piping Drain Line] 60 LF $ $

Offloading and LACT Piping176 Load Line Container [Offloading Drop] 8 EA $ $177 3" Strainer [Offloading Drop] 8 EA $ $178 3" Plug Valve [Offloading Drop] 8 EA $ $179 3" 90° Bend (A53 Grade B) [Offloading Drop] 8 EA $ $180 3"x4" Tee (A53 Grade B) [Offloading Drop] 4 EA $ $181 3" Check Valve [Offloading Drop] 8 EA $ $182 3" Isloation Adapter [Offloading Drop] 8 EA $ $183 4" Welded Steel Pipe (A53B ERW Type E) [Product Piping] 978 LF $ $184 8" Welded Steel Pipe (A53B ERW Type E) [Product Piping] 180 LF $ $185 4" 22.5° Bend (A53 Grade B) 4 EA $ $186 4" 45° Bend (A53 Grade B) 4 EA $ $187 4" 90° Bend (A53 Grade B) 5 EA $ $188 8" 90° Bend (A53 Grade B) 2 EA $ $189 4" Tee (A53 Grade B) 8 EA $ $190 8" Tee (A53 Grade B) 8 EA $ $191 4" Wye (A53 Grade B) 4 EA $ $192 8" Cross (A53 Grade B) 1 EA $ $193 4"x8" Reducer [LACT Pumps] 4 EA $ $194 4" Flex Coupling w/Limit Rods [LACT Pumps] 4 EA $ $195 4" Gate Valve 14 EA $ $196 8" Gate Valve 12 EA $ $197 4" Check Valve 8 EA $ $198 8" Check Valve 8 EA $ $199 Connect 4" Steel Pipe to LACT Tank [Product Piping] 8 EA $ $200 Install LACT Pumps 2 EA $ $

Loading Arms201 Crude Loading Arm Assembly [Meter provided by owner] 12 EA $ $202 Vapor Loading Arm Assembly 12 EA $ $203 Recovery Loading Arm Assembly 12 EA $ $204 4" Product Hose Assembly 24 EA $ $205 2" Recovery Hose Assembly 12 EA $ $206 2" Vapor Hose Assembly 12 EA $ $207 1" Welded Steel Pipe (A53B ERW Type E) [Crude Arm Vapor Line] 122 LF $ $208 1" Welded Steel Pipe (A53B ERW Type E) [Crude Arm Drain Line] 204 LF $ $209 2" Welded Steel Pipe (A53B ERW Type E) [Crude Arm Drain Line] 204 LF $ $

Windsor Crude Oil TerminalBid ScheduleAddendumA3August 8, 2012 Page 3 of 5

Page 7: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE COST

Vapor Piping210 2" Vapor Hose Assembly [Offloading Drop] 6 EA $ $211 4" Tee [Offloading Drop] 3 EA $ $212 4"x2" Reducer [Offloading Drop] 3 EA $ $213 4" Ball Valve [Offloading Drop] 3 EA $ $214 Connect 4" Steel Pipe to LACT Tank [LACT Vapor Line] 8 EA $ $215 4" Coupling [LACT Vapor Line] 8 EA $ $216 4"x2" Reducing Nipple [LACT Vapor Line] 8 EA $ $217 2" Flame Arrestor [LACT Vapor Line] 8 EA $ $218 2" Vacuum/Pressure Relief Valve [LACT Vapor Line] 8 EA $ $219 2" Check Valve [LACT Vapor Line] 8 EA $ $220 4" Welded Steel Pipe (A53B ERW Type E) [Vapor Line] 921 LF $ $221 4" Welded Steel Pipe (A53B ERW Type E) [Vapor Header] 755 LF $ $222 4" Expansion Coupling with Limit Rods 3 EA $ $223 4" 11.25° Bend [Vapor Line] 2 EA $ $224 4" 45° Bend (A53 Grade B) [Vapor Line] 3 EA $ $225 4" 90° Bend (A53 Grade B) [Vapor Line] 3 EA $ $226 4" 45° Bend (A53 Grade B) [Vapor Header] 2 EA $ $227 4" 90° Bend (A53 Grade B) [Vapor Header] 2 EA $ $228 2"x1" Reducer (A53 Grade B) [Vapor Header] 12 EA $ $229 4"x2" Tee (A53 Grade B) [Vapor Line] 8 EA $ $230 4"x2" Tee (A53 Grade B) [Vapor Header] 16 EA $ $231 4" Tee (A53 Grade B) [Vapor Line] 3 EA $ $232 4" Tee (A53 Grade B) [Vapor Header] 12 EA $ $233 Install Propane Tank Piping to Flare 1 LS $ $234 Install Flare, Components, and all Appurtenances 1 LS $ $235 Knockout Tank (500 Gal) 2 EA $ $236 Knockout Tank Pumps 2 EA $ $

Recovery Piping237 4" Welded Steel Pipe (A53B ERW Type E) [Recovery Header] 768 LF $ $238 4" Welded Steel Pipe (A53B ERW Type E) [Return Piping] 435 LF $ $239 4" Welded Steel Pipe (A53B ERW Type E) [Slop Line] 608 LF $ $240 4" Welded Steel Pipe (A53B ERW Type E) [Recovery Line to Flare] 123 LF $ $241 4" Expansion Coupling with Limit Rods 3 EA $ $242 4" 45° Bend (A53 Grade B) [Recovery Header] 23 EA $ $243 4" 90° Bend (A53 Grade B) [Recovery Header] 4 EA $ $244 4" 45° Bend (A53 Grade B) [Return Piping] 11 EA $ $245 4" 90° Bend (A53 Grade B) [Return Piping] 1 EA $ $246 4" 45° Bend (A53 Grade B) [Slop Line] 15 EA $ $247 4" 90° Bend (A53 Grade B) [Slop Line] 3 EA $ $248 4" 45° Bend (A53 Grade B) [Recovery Line to Flare] 2 EA $ $249 4" 90° Bend (A53 Grade B) [Recovery Line to Flare] 2 EA $ $250 4" Tee (A53 Grade B) [Recovery Header] 17 EA $ $251 4" Tee (A53 Grade B) [Return Piping] 2 EA $ $252 4" Tee (A53 Grade B) [Slop Line] 1 EA $ $253 4"x2" Tee (A53 Grade B) [Recovery Header] 12 EA $ $254 4"x2" Tee (A53 Grade B) [Crude Arm Drain Line] 24 EA $ $255 2"x1" Reducer (A53 Grade B) [Crude Arm Drain Line] 12 EA $ $256 4" Check Valve [Return Piping] 2 EA $ $257 4" Check Valve [Slop Line] 1 EA $ $258 4" Gate Valve [Return Piping] 1 EA $ $259 4" Gate Valve [Slop Line] 1 EA $ $260 Railroad Track Spill Containment Pans 12 EA $ $261 4" PVC SDR35 [Railroad Containment Vault] 26 LF $ $262 Concrete Vault, 6'x6'x6' [Railroad Containment Vault] 1 EA $ $263 Concrete Vault, 12'x6'x6' [Recovery Tank] 1 EA $ $264 Steel Tank, Single Wall (1,000 Gal) [Recovery Tank] 1 EA $ $265 Pump (SafeRack and Railroad Containment Vault) and all Appurtenances 1 LS $ $266 Pumps (SafeRack South Recovery Tank) and all Appurtenances 1 LS $ $

Windsor Crude Oil TerminalBid ScheduleAddendumA3August 8, 2012 Page 4 of 5

Page 8: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE COST

Product Piping267 4" Welded Steel Pipe (A53B ERW Type E) [Crude Header Drain] 50 LF $ $268 4" Welded Steel Pipe (A53B ERW Type E) [Condensate Header Drain] 50 LF $ $269 8" Welded Steel Pipe (A53B ERW Type E) [Product Piping] 868 LF $ $270 8" Welded Steel Pipe (A53B ERW Type E) [Crude Header] 290 LF $ $271 8" Welded Steel Pipe (A53B ERW Type E) [Condensate Header] 690 LF $ $272 10" Welded Steel Pipe (A53B ERW Type E) [Product Piping] 140 LF $ $273 12" Welded Steel Pipe (A53B ERW Type E) [Product Piping] 267 LF $ $274 12" Welded Steel Pipe [Casing Pipe] 296 LF $ $275 18" Welded Steel Pipe [Casing Pipe] 150 LF $ $276 20" Welded Steel Pipe [Casing Pipe] 86 LF $ $277 8" 45° Bend (A53 Grade B) [Product Piping] 6 EA $ $278 8" 90° Bend (A53 Grade B) [Product Piping] 2 EA $ $279 8" 45° Bend (A53 Grade B) [Condensate Header] 22 EA $ $280 10" 45° Bend (A53 Grade B) [Product Piping] 2 EA $ $281 10" 90° Bend (A53 Grade B) [Product Piping] 1 EA $ $282 12" 11.25° Bend (A53 Grade B) [Product Piping] 1 EA $ $283 12" 22.5° Bend (A53 Grade B) [Product Piping] 1 EA $ $284 12" 45° Bend (A53 Grade B) [Product Piping] 3 EA $ $285 12" 90° Bend (A53 Grade B) [Product Piping] 2 EA $ $286 4"x8" Reducer [LACT Pumps] 4 EA $ $287 4" Flex Coupling w/Limit Rods [LACT Pumps] 4 EA $ $288 8"x4" Tee (A53 Grade B) [Crude Header] 14 EA $ $289 8"x4" Tee (A53 Grade B) [Condensate Header] 14 EA $ $290 8"x4" Tee (A53 Grade B) [Return Line to Product Piping] 1 EA $ $291 8" Tee (A53 Grade B) [Product Piping] 3 EA $ $292 8" Tee (A53 Grade B) [Condensate Header] 1 EA $ $293 8" Cross (A53 Grade B) [Product Piping] 1 EA $ $294 8"x10" Tee (A53 Grade B) [Crude Header] 1 EA $ $295 10" Tee (A53 Grade B) 3 EA $ $296 10"x12" Tee (A53 Grade B) 1 EA $ $297 12" Tee (A53 Grade B) 3 EA $ $298 4" Ball Valve [Crude Header] 2 EA $ $299 4" Ball Valve [Condensate Header] 2 EA $ $300 4" Gate Valve [Product Piping] 4 EA $ $301 4" Check Valve [Product Piping] 4 EA $ $302 8" Check Valve [Product Piping] 2 EA $ $303 10" Gate Valve [Product Piping] 4 EA $ $304 10" Check Valve [Product Piping] 3 EA $ $305 12" Gate Valve [Product Piping] 4 EA $ $306 12" Check Valve [Product Piping] 2 EA $ $307 12"x8" Reducer [Product Piping] 3 EA $ $308 10"x8" Reducer [Product Piping] 3 EA $ $309 8" Flex Coupling w/Limit Rods [Loading Pumps] 6 EA $ $310 8" Expansion Coupling w/Limit Rods [Crude Header] 3 EA $ $311 8" Expansion Coupling w/Limit Rods [Condensate Header] 3 EA $ $312 Vacuum Break [Crude Header] 2 EA $ $313 Vacuum Break [Condensate Header] 2 EA $ $314 8" Air Eliminator [Crude Header] 2 EA $ $315 8" Air Eliminator [Condensate Header] 2 EA $ $316 Connect 8" Steel Pipe to Existing Storage Tank 2 EA $ $317 Connect 12" Steel Pipe to Existing Storage Tank 2 EA $ $318 Paint, Primer and 2-part epoxy, for All Above Ground Product, Vapor, and Casing Pipes 1 LS $ $319 Install Loading Pumps [with Density Meter provided by owner] and Remote Speed Controllers 3 EA $ $

Temporary Transloading Plans320 Furnish and Install Condensate Discharge Line from Flare Knock Tank to SafeRack 1 LS $ $

TOTAL COSTBID WRITTEN

IN WORDS:

Contractor Name:

Address:

Phone:

$

Windsor Crude Oil TerminalBid ScheduleAddendumA3August 8, 2012 Page 5 of 5

Page 9: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

Know what's

Page 10: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

Know what's

Page 11: ADDENDUM NUMBER A3 – (DATED August 8, 2012) TO THE

Know what's