ADDENDUM NO. 2
TO CONTRACT DOCUMENTS
EAST 55TH STREET
FLOATABLES FACILITY REHABILITATION CONTRACT FLO-55
FOR THE
NORTHEAST OHIO REGIONAL SEWER DISTRICT
July 6, 2011
Consisting of 2 pages and 1 attachment: Attachment A Prevailing Wage Rates (24 Pages) ATTENTION BIDDERS: The following, as additions to and modifications in the Contract Documents, will be included in and become a part of any contract that may be executed for the construction of the East 55th Street Floatables Facility Rehabilitation, Contract FLO-55. Bidders are therefore instructed to take the following into account when rendering any Bid for this work.
I. QUESTION AND ANSWER The following are the questions asked subsequent to Addendum No. 1 and answers to those questions:
Q1. Please clarify the number of Pre-construction and Monthly Photos to be taken related the spec section 01 1380?
A1. The number of photos can be adjusted by the construction supervisor
based the current status of the project, but 25 photos shall be the baseline for both the preconstruction and monthly efforts.
II. SPECIFICATIONS
A. Insert the prevailing wages attached to this addendum into Appendix B.