ADDENDUM NO. 2 TO CONTRACT DOCUMENTS EAST 55 TH STREET FLOATABLES FACILITY REHABILITATION CONTRACT FLO-55 FOR THE NORTHEAST OHIO REGIONAL SEWER DISTRICT July 6, 2011 Consisting of 2 pages and 1 attachment: Attachment A Prevailing Wage Rates (24 Pages) ATTENTION BIDDERS: The following, as additions to and modifications in the Contract Documents, will be included in and become a part of any contract that may be executed for the construction of the East 55 th Street Floatables Facility Rehabilitation, Contract FLO-55. Bidders are therefore instructed to take the following into account when rendering any Bid for this work. I. QUESTION AND ANSWER The following are the questions asked subsequent to Addendum No. 1 and answers to those questions: Q1. Please clarify the number of Pre-construction and Monthly Photos to be taken related the spec section 01 1380? A1. The number of photos can be adjusted by the construction supervisor based the current status of the project, but 25 photos shall be the baseline for both the preconstruction and monthly efforts. II. SPECIFICATIONS A. Insert the prevailing wages attached to this addendum into Appendix B.

ADDENDUM NO. 2 TO CONTRACT DOCUMENTS … NO. 2 TO CONTRACT DOCUMENTS EAST 55TH STREET FLOATABLES FACILITY REHABILITATION CONTRACT FLO-55 FOR THE NORTHEAST OHIO REGIONAL SEWER DISTRICT

Embed Size (px)

Citation preview

ADDENDUM NO. 2

TO CONTRACT DOCUMENTS

EAST 55TH STREET

FLOATABLES FACILITY REHABILITATION CONTRACT FLO-55

FOR THE

NORTHEAST OHIO REGIONAL SEWER DISTRICT

July 6, 2011

Consisting of 2 pages and 1 attachment: Attachment A Prevailing Wage Rates (24 Pages) ATTENTION BIDDERS: The following, as additions to and modifications in the Contract Documents, will be included in and become a part of any contract that may be executed for the construction of the East 55th Street Floatables Facility Rehabilitation, Contract FLO-55. Bidders are therefore instructed to take the following into account when rendering any Bid for this work.

I. QUESTION AND ANSWER The following are the questions asked subsequent to Addendum No. 1 and answers to those questions:

Q1. Please clarify the number of Pre-construction and Monthly Photos to be taken related the spec section 01 1380?

A1. The number of photos can be adjusted by the construction supervisor

based the current status of the project, but 25 photos shall be the baseline for both the preconstruction and monthly efforts.

II. SPECIFICATIONS

A. Insert the prevailing wages attached to this addendum into Appendix B.

END OF ADDENDUM NO. 2