16
1 ADDENDUM #1, August 17, 2017 Texas A&M Civil Engineering Concrete Lab Renovation Project 17020, SSC No 2016-01438 Notice to all bidders: This Addendum forms a part of the Contract Documents and modifies the Specifications and Drawings dated 7 August 2017 to the extent noted hereinafter. All parties of interest shall take careful note of this Addendum so that proper allowance is made in all computations, estimates and contracts and so that all trades affected are fully advised in the performance of work that will be required by them. A. Specifications: 1. Revise Section TABLE OF CONTENTS: a. Add Section 230501 DEMOLITION FOR HVAC. b. Revise Section 233000 to AIR TEMPERING SYSTEMS AND EQUIPMENT. c. Omit Section 234000 HVAC DUCT & EQUIPMENT CLEANING. 2. Section SSC SPECIAL CONDITIONS: a. Add the following to the end of Paragraph 7: “The crane boom cannot swing over occupied buildings or adjacent sites.” 3. Section 000100 INDEX TO DRAWINGS: a. Add Drawing Sheet number E0.3 ELECTRICAL SPECIFICATIONS. b. Revise Drawing numbers ED2.1, ED2.2, and ED2.3 to ED1.1, ED1.2, and ED1.3. c. Add Drawing Sheet number M4.3 MECHANICAL SECTIONS. 4. Section 012300 ALTERNATES: a. Revise item 3.1.G.2 as follows: “Alternate Bid: All work to prepare existing room for the new environmental chamber, including mechanical, electrical and plumbing services, into Storage 109A. The environmental chamber is to be provided and installed by the Owner.” 5. Section 075419 POLYVINYL-CHLORIDE (PVC) ROOFING: a. Revise item 1.10.A.2 as follows: “Warranty Period: 20 years from date of Substantial Completion.” B. Drawings: 1. Drawing G1: Add drawings M4.3 Mechancial Sections and E0.3 Electrical specifications to the Index to Drawings. Revised drawing is attached. 2. Drawing D1.1: Revised drawing is attached. a. Add General Demolition Note #7 as follows: ”Refer to Sheet A2.1 for Alternate Bid Schedule.” b. Add General Demolition Note #8 as follows: “Remove concrete pads and anchor bolts at removed wave tank. Grind smooth with concrete floor surface. Approximately (26) 8”x8” pads.” c. Add General Demolition Note #9 as follows: “Remove VCT flooring from the classrooms (109B). This includes grinding floor to remove adhesive.” d. Add General Demolition Note #10 as follows: “Remove existing classrooms seating that is bolted to the floor. This includes cutting all bolts flush with the floor and grinding smooth.” e. Revise note to Detail 1/D1.1 to read as follows: “Sawcut and remove 24” x 24” area of concrete block for new access hatch – at existing clean-out elevation. f. Add note to Detail 1/D1.1 to read as follows: “Remove glass panel for temporary dust evacuation duct.” 3. Drawing D1.2: Revise the size of the second floor slab opening for ductwork penetrations as shown on the attached drawing. 4. Drawing A2.1. Revised drawing is attached. 08-17-2017 308 N. Bryan Ave. Bryan, TX 77803 P (979)821-2635 F (979)775-8224 www.arkitex.com

ADDENDUM #1, August 17, 2017 Texas A&M Civil … · Texas A&M Civil Engineering Concrete Lab Renovation Project 17020, ... ”Refer to Sheet A2.1 for ... 21. Drawing M5.3

  • Upload
    hakhanh

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

1

ADDENDUM #1, August 17, 2017 Texas A&M Civil Engineering Concrete Lab Renovation Project 17020, SSC No 2016-01438 Notice to all bidders: This Addendum forms a part of the Contract Documents and modifies the Specifications and Drawings dated 7 August 2017 to the extent noted hereinafter. All parties of interest shall take careful note of this Addendum so that proper allowance is made in all computations, estimates and contracts and so that all trades affected are fully advised in the performance of work that will be required by them. A. Specifications:

1. Revise Section TABLE OF CONTENTS: a. Add Section 230501 DEMOLITION FOR HVAC.

b. Revise Section 233000 to AIR TEMPERING SYSTEMS AND EQUIPMENT.

c. Omit Section 234000 HVAC DUCT & EQUIPMENT CLEANING. 2. Section SSC SPECIAL CONDITIONS:

a. Add the following to the end of Paragraph 7: “The crane boom cannot swing over occupied buildings or adjacent sites.”

3. Section 000100 INDEX TO DRAWINGS: a. Add Drawing Sheet number E0.3 ELECTRICAL SPECIFICATIONS. b. Revise Drawing numbers ED2.1, ED2.2, and ED2.3 to ED1.1, ED1.2,

and ED1.3. c. Add Drawing Sheet number M4.3 MECHANICAL SECTIONS.

4. Section 012300 ALTERNATES: a. Revise item 3.1.G.2 as follows: “Alternate Bid: All work to prepare

existing room for the new environmental chamber, including mechanical, electrical and plumbing services, into Storage 109A. The environmental chamber is to be provided and installed by the Owner.”

5. Section 075419 POLYVINYL-CHLORIDE (PVC) ROOFING: a. Revise item 1.10.A.2 as follows: “Warranty Period: 20 years from date

of Substantial Completion.” B. Drawings:

1. Drawing G1: Add drawings M4.3 Mechancial Sections and E0.3 Electrical specifications to the Index to Drawings. Revised drawing is attached.

2. Drawing D1.1: Revised drawing is attached. a. Add General Demolition Note #7 as follows: ”Refer to Sheet A2.1 for

Alternate Bid Schedule.” b. Add General Demolition Note #8 as follows: “Remove concrete pads

and anchor bolts at removed wave tank. Grind smooth with concrete floor surface. Approximately (26) 8”x8” pads.”

c. Add General Demolition Note #9 as follows: “Remove VCT flooring from the classrooms (109B). This includes grinding floor to remove adhesive.”

d. Add General Demolition Note #10 as follows: “Remove existing classrooms seating that is bolted to the floor. This includes cutting all bolts flush with the floor and grinding smooth.”

e. Revise note to Detail 1/D1.1 to read as follows: “Sawcut and remove 24” x 24” area of concrete block for new access hatch – at existing clean-out elevation.

f. Add note to Detail 1/D1.1 to read as follows: “Remove glass panel for temporary dust evacuation duct.”

3. Drawing D1.2: Revise the size of the second floor slab opening for ductwork penetrations as shown on the attached drawing.

4. Drawing A2.1. Revised drawing is attached.

08-17-2017

308 N. Bryan Ave. Bryan, TX 77803 P (979)821-2635 F (979)775-8224 www.arkitex.com

2

a. Revise ALTERNATE BID SCHEDULE as shown. b. Revise drawing to show temporary lab exhaust location on the North

side of the existing Lab. c. Revise 2 notes in Classroom 109B to read, “Re-install salvaged

projector and projector screen.” d. Add notes to Detail 1/A2.1 as follows: “16"x16" concrete pilaster with #4

vertical reinforcement in each cell. Dowel into existing concrete block wall with #4 dowels 12" long. Space at 24" O.C. vertical, 6" embed into existing. Grout cells solid in new and existing. “

e. Add notes to Detail 1/A2.1 as follows: “Revise access door swings to open into Storage/Shop 114C and Storage 114B.”

f. Revise drawing to show Aggregate Storage roof has decreased in size to allow for Dust Collector. Structural members and base have been omitted at grid line B.

5. Drawing A2.2 Revised drawing is attached. a. Revise GENERAL NOTES, Note 13 to read as follows: Refer to 1/A2.1

for Alternate Bid Schedule. b. Add notes to Detail 1/A2.2 as follows: “Patch wall at removed pull

station.” c. Revise Detail 1/A2.2 to reflect increased size of the mechanical chase.

6. Drawing A3.1. Revised drawing is attached. a. HVAC outside air intake and notes are shown on details 1/A3.1 and

2/A3.1 b. Note has been added regarding temporary enclosure at dust

evacuation duct penetration at the window. 7. Drawing A4.1. Revised drawing is attached.

a. Revise Detail 8/A4.1 to show change in chase size. 8. Drawing Sheet A5.1. Revised drawing is attached.

a. Add note at on Detail 1, door #104 “Fixed H.M. transom above, RE 10/A5.1”

b. Add Detail 10/A5.1 INTERIOR OPENING TYPE (ALTERNATE #3) 9. Drawing Sheet A5.2. Revised drawing is attached.

a. Add Detail 18/A5.2 INTERIOR HOLLOW METAL PANEL HEAD 10. Drawing Sheet A8.1

a. Omit Detail 2/A8.1 11. Drawing S1.1, Details 1 and 6: Revise Aggregate Storage roof structure to omit

one bay. Revised drawing is attached. 12. Drawing S1.2, Detail 2. revise the size of the floor slab opening for the HVAC

chase. The revised drawing is attached. 13. Drawing S3.1, Details 1, 4, 5, 6: Revise Aggregate Storage roof structure to

omit one bay. Revised drawing is attached 14. Drawing M2.1 – MECHANICAL FIRST FLOOR RENOVATION PLAN

a. Changed Keyed Note #14 � b. Added Keyed notes 16-20. � c. Added Terminal Unit TU-6 to base bid package. � d. Changed Air Devices ‘A’ and associated ductwork in Room 109B � e. Added open end and manual damper to end of Dust Collection exhaust

duct run. � f. Tagged Type ‘G’ grilles. � g. Moved temporary exhaust fan EF-1T. �

15. Drawing �M2.2 – MECHANICAL SECOND FLOOR RENOVATION PLAN a. Changed Keyed note #1 b. Changed direction of OA Intake gooseneck.

16. Drawing M3.1 – MECHANICAL FIRST FLOOR PIPING PLAN a. Added Terminal Unit TU-6 to base bid package. � b. Changed size of branch piping to TU-1 and TU-2 � c. Added Keyed note #6 �

17. Drawing �M4.1 – MECHANICAL PARTIAL PLANS – ALTERNATE 1A

3

a. Changed SA duct routing in 1/M4.1 18. Drawing �M4.2 – MECHANICAL PARTIAL PLANS – ALTERNATES 2 & 3

a. Changed Keyed Note #10 b. Added Keyed Note #15 � c. Added removal of Terminal Unit TU-6 to scope of Alternates 2 & 3 �

19. Drawing �M4.3 – MECHANICAL SECTIONS a. Added sheet M4.3

20. Drawing T�M5.2 – MECHANICAL DETAILS a. Changed Exhaust Plenum dimension in detail 3/M5.2

21. Drawing �M5.3 – MECHANICAL DETAILS a. Changed detail 1/M5.3 b. Added detail 4/M5.3

22. Drawing M6.1 – MECHANICAL CONTROLS a. Corrected detail titles for 1/M6.1 and 3/M6.1 � b. Changed detail 2/M6.1. �

23. Drawing M5.3 – MECHANICAL SCHEDULES a. Added note #10 to Dust Collector Schedule � b. Deleted HW Re-Heat Coil section from Air Handling Unit Schedule � c. Added TU-6 to VAV Terminal Unit Schedule � d. Added Note #5 to VAV Terminal Unit Schedule � e. Changed manufacturer and model info for TU-1 and TU-2 on VAV

Terminal Unit Schedule � f. Added HW Re-heat coil info toe VAV Terminal Unit Schedule � g. Changed Air Device Types ‘A’ and ‘E’ on Air Device Schedule. �

24. Drawing �E0.2 – ELECTRICAL SPECIFICATIONS (Division 28 Fire Alarm) a. Update sheet number to E0.3.

25. Drawing �ED1.1 – LIGHTING DEMOLITION FIRST FLOOR PLAN a. Clarify keyed note.

26. Drawing �ED1.2 – ELECTRICAL DEMOLITION FIRST FLOOR PLAN a. Revise call out of “Fan Coil Unit” to “Terminal Unit”

27. Drawing E1.1 – LIGHTING FIRST FLOOR RENOVATION PLAN a. Provide an additional wall switch in Classroom 109B near southwest

door. � b. Provide clarification on a few keyed note call outs. � c. Provide weatherproof cover on light switches in Concrete Lab 109. �

28. Drawing E1.2 – LIGHT SECOND FLOOR RENOVATION PLAN a. Provide notes on sheet to indicate that ceilings in adjoining spaces to

the project area are not accessible. � b. Relocate lighting dimmer controller and emergency control unit to avoid

conflict with new mechanical chase. � 29. Drawing E2.1 – ELECTRICAL FIRST FLOOR RENOVATION PLAN

a. Revise electrical service to EF-1T and DC-1. � b. Include TU-6 to base bid and remove TU-6 from scope under Additive

Alternate #2. � 30. Drawing E2.2 – ELECTRICAL SECOND FLOOR RENOVATION PLAN

a. Provide notes on sheet to indicate that ceilings in adjoining spaces to the project area are not accessible.

31. Drawing �E6.1 – ELECTRICAL ONE LINE DIAGRAM a. Revise electrical service to EF-1T and DC-1.

32. Drawing E7.1 – ELECTRICAL SCHEDULES a. Updated Panel 1LF to indicate panel must have a NEMA 12 enclosure

rating. b. Update wall pack light fixture W27 lumen output. �

33. Drawing P0.3 SPECIFICATIONS was omitted from the printing. It is attached. 34. Drawing �PD1.1 – PLUMBING FIRST FLOOR DEMOLITION PLAN

a. Changed Keyed Note #3

4

b. Changed Keyed Note #7 � c. Added 1-1/2” DCW line to be re-routed � d. Moved demo of piping to demolished exhaust hood to scope of

Alternate #2 � 35. Drawing �P2.1 – PLUMBING FIRST FLOOR RENOVATION PLAN

a. Added Keyed Note #11 b. Changed Fire Protection Notes ‘D’ & ‘I’ � c. Added 1-1/2” DCW line to be re-routed to Emergency Eye

Wash/Shower � d. Added Emergency Eye Wash/Shower EES-1

36. Drawing P4.1 – PLUMBING PARTIAL PLANS – ALTERNATES 1, 1A, & 2 a. Changed Keyed Notes #1, #3, #6 � b. Added Keyed Notes #7, #8, #9, and #10 � c. Changed Fire Protection Notes ‘D’ & ‘I’ � d. Changed Routing of new Roof Drains for Alternates #1 and #1A as

shown in 1/P4.1 and 3/P4.1 � e. Moved demo of piping to demolished exhaust hood to scope of

Alternate #2 in 4/P4.1 � f. Changed extent of lab gas, vacuum, water, and compressed air piping

demolition shown in �4/P4.1 � 37. Drawing �P4.2 – PLUMBING PARTIAL PLANS – ALTERNATES 3 & 5

a. Changed Fire Protection Notes ‘D’ & ‘I’ 38. Drawing P5.1

a. Added Emergency Eye Wash/Shower EES-1 to Plumbing Fixture Schedule �

b. Changed detail 1/P5.1 and Detail 2/P5.1. � END OF ADDENDUM 1

308 N. Bryan Ave. Bryan, TX 77803 P (979)821-2635 F (979)775-8224 www.arkitex.com

Revisions

Number Date

The

Arkitex Studio, Inc.

Project 17020 August 7, 2017

Reno

vatio

n to

TAM

U C

ivil

Engi

neer

ing

Conc

rete

Lab

Texa

s A

&M

Uni

vers

ity, C

ivil

Engi

neer

ing

Bldg

. #03

25 -

Colle

ge S

tatio

n Ca

mpu

s

8/17/17

INDEX TO DRAWINGSNo scaleRefer to: all drawings1ABBREVIATIONS

No scaleRefer to: all drawings4

00 Cover sheet GENERAL G1 General information DEMOLITION D1.1 First Floor Demo Plan D1.2 Second Floor Demo Plan ARCHITECTURAL A2.1 First Floor Plan, Aggregate Storage Plan A2.2 Second Floor Plan A3.1 Building Elevations A4.1 Details A5.1 Schedules A5.2 Details A6.1 Wall Sections A6.2 Wall Sections/Details A8.1 First Floor RCP A8.2 Second Floor RCP A9.1 Roof Plan STRUCTURAL S1.1 Foundation Plan and Details S1.2 Foundation Plan and Details S3.1 Framing Pan and Details S3.2 Framing Plan and Details S3.3 Framing Details MECHANICAL M0.0 Mechanical symbols, abbrev and general notes MD1.1 Mechanical first floor demolition plan M2.1 Mechanical first floor renovation plan M2.2 Mechanical second floor renovation plan M3.1 Mechanical first floor piping plan M4.1 Mechanical partial plans - Alternate 1A M4.2 Mechanical partial plans - Alternates 2 and 3 M4.3 Mechanical Sections M5.1 Mechanical details M5.2 Mechanical details M5.3 Mechanical details M5.4 Mechanical details M6.1 Mechanical controls M6.2 Mechanical controls M7.1 Mechanical schedules

Q.T.QTR.

Quarry tileQuarter

V.B.V.C.T.

VERT.VEST.V.I.F.V.W.C.

Venetian blindVinyl composition tile

VerticalVestibuleVerify in FieldVinyl wall covering

W.W/W.C.WD.

WestWithWater closetWood

PT.PTD.P.V.C.PVMT.

PART.PBD.P.C.C.PL.P.LAM.PLAS.PLYWD.PNL.POL.PR.

P.S.F.P.S.I.

PRE-FIN.

PointPaintedPolyvinyl chloridePavement

PartitionParticle boardPre-cast concretePlatePlastic laminatePlasterPlywoodPanel(-ing)PolishPair

Pounds per square footPounds per square inch

Pre-finish(-ed)

R.R/ARAD.R.D.

REF.REFG.REINF.REQD.RESIL.REV.RM.R.O.

RECEPT.

Riser(s)Return airRadiusRoof drain

ReferenceRefrigeratorReinforce(-d,-ing)Require(-d)ResilientReviseRoomRough opening

Reception

S.S/ASAN.S.C.SCHED.S.D.SECT.SHWR.SHT.SIM.SL.SPEC.

SQ.S.SK.S.ST.STA.STD.STL.STOR.

SURF.SUSP.

SYM.SYS.

STRUCT.

SPEC'D.

SVC.

SouthSupply airSanitarySolid coreScheduleSoap dispenserSectionShowerSheetSimilarSlopeSpecification(-s)SpecifiedSquareService sinkStainless steelStationStandard, stainedSteelStorage

SurfaceSuspended

SymmetricalSystem

Structure(-al)

Service

Angle

Channel

Center line

Diameter or round

Perpendicular

Pound or number

And

#

&

CL

ClosetClearConcrete masonry unitColumnConcreteConditionConstruction(-ed)ContinuousCorporationCorrugatedCarpetCurtain rodCountersinkCeramic tileCubic feet (foot)

Cubic inch (es)

Catch basinCementCeramicCounter flashingCubic feet per minute

Cabinet

Corner guardCoat hookCast ironControl jointCeiling

Cubic yard (es)

CLO.CLR.C.M.U.COL.CONC.COND.CONST.CONT.CORP.CORR.CPT.C.R.CS.C.T.CU. FT.

CU. IN.CU. YD.

CAB.C.B.CEM.CER.C.FLASH.C.F.M.C.G.C.H.C.I.C.J.CLG.

Anchor BoltAboveAir conditioningAcousticalArea drainAddendum

Above finished floorAggregateAir handling unitAllowanceAlternateAluminumAnodizedApproximate(ly)Architect(-ural)AsphaltAutomaticAuxiliaryAverage

Additional

APPROX.

A.B.ABV.A/CACOUS.A.D.ADD.

A.F.F.AGG.A.H.U.ALLOW.ALT.ALUM.ANOD.

ARCH.ASPH.AUTO.AUX.AVG.

ADD'L.

EastEachExpansion bolt

Electric water cooler

Electric hand dryer

ElevationElectric (-al)EmergencyEnclosureEqualExhaust

ExpansionExterior

Expansion joint

Existing

E.EA.E.B.

E.W.C.

E.H.D.

ELEV.ELEC.EMER.ENCL.EQ.EXH.

EXP.EXT.

E.J.

EXIST.

I.D.IN.INCL.INSUL.INT.INV.

Inside dimensionInchInclude(-ing)InsulationInteriorInvert

JAN.JST.JT.

JanitorJoistJoint

LAM.

LAV.LB.LKR.L.L.H.L.L.V.

L.PT.LT.LTL.LVL.LVR.

Laminate(-d)

LavatoryPoundLockerLong leg horizontalLong leg vertical

Low pointLightLintelLevelLouver

FAB.F.A.F.D.FDN.F.E.F.E.C.

F.H.C.F.H.R.F.HYD.FIN.F.L.FLASH.FLEX.FLR.FLUOR.FT.FTG.FURR.FUT.F.W.C.

Fabric (-ate, -ated)Fire alarmFloor drainFoundationFire extinguisherFire extinguisher cabinet

Fire hose cabinetFire hose rackFire hydrantFinish(-ed)Flow lineFlashingFlexibleFloorFluorescentFoot (Feet)FootingFurredFutureFabric wall covering

GA.GALV.G.B.G.C.G.I.GL.GR.GYP.

GaugeGalvanize(-d)Grab barGeneral contractorGalvanized ironGlass, glaze(-d,-ing)GradeGypsum

HDWD.HDWR.H.M.HORIZ.H. PT.HR.HT.HTG.HVAC

H.H.B.H.C.

HardwoodHardwareHollow metalHorizontalHigh pointHourHeightHeatingHeating, ventilation and air conditioning

HighHose bibHandicapped

MATL.MAX.

M.B.MAS.

M.C.MECH.

MED.

MTL.

MEZZ.MFR.M.H.MIN.MIR.MISC.MLDG.M.O.MTD.

MTG.MULL.

MEMB.

MaterialMaximum

Machine boltMasonry

Medicine cabinetMechanical

Medium

Metal

MezzanineManufacturerManholeMinimumMirrorMiscellaneousMouldingMasonry openingMounted

MountingMullion

Membrane

N.N.I.C.NO.NOM.N.T.S.

NorthNot in contractNumberNominalNot to scale

OH.

O.A.O/AO.C.O.D.OFF.

OPNG.OPP.OZ.

Overhead

OverallOutside airOn centerOutside diameterOffice

OpeningOpposite (hand)Ounce

BoardBuildingBlockBlockingBeamBench mark

BottomBasement

BD.BLDG.BLK.BLKG.BM.B.M.

BOTT.BSMT.

Built-up roofingB.U.R.

By othersBO

DoubleDetailDrinking fountainDouble hungDiagonalDiameterDimensionDivisionDownDoor opening

DoorDishwasherDowelDownspoutDrawing (-s)Drawer

DBL.DET.D.F.D.H.DIAG.DIAM.DIM.DIV.DN.D.O.

DR.D.W.DWL.D.S.DWG.DWR.

DampproofingDP

T.T.B.T.C.T.D.T.D.R.TEL.TEMP.T&GTHK.THRES.T.P.

T.SL.T.O.S.T.T.D.TYP.

TreadTowel barTop of curbTowel dispenserTowel dispenser receptacleTelephoneTemperedTongue and grooveThick(-ness)ThresholdTop of pavement

Top of slabTop of steelToilet tissue dispenserTypical

TRTD Treated

U.N.O. Unless noted otherwiseUR. Urinal

GRAPHIC SYMBOLSNo scaleRefer to: all drawings2

MATERIAL SYMBOLSNo scaleRefer to: all drawings3

Rigid insulation

Glass - large scale

Glass - small scale

Insulation

Acoustical tile or board

Plaster on metal lath

Metal - large scale

Plywood

Finish wood

Dimensional lumber - continuous

Dimensional lumber - blocking

Gypsum board

Earth

Concrete

Brick

Concrete masonry units

Stone

Mortar, grout, sand

1 of 1

G1

N

Plan North

North arrow

Elevation

Wall section

Building section

Partition type

Door number

Window type

Finish type, alternate window type

Column line reference

Center line

Hidden line

4 / A3.1

4 / A3.1

4 / A3.1

Detail reference

Interior elevation

Break lineB

B

Section detail4 / A3.1

R.9

Keynote, toilet accessory2323

AA

138 A

138 A

WW

1

Elevation marker

Elevation marker325.00'

Top of parapet± 125'-3 1/2" (V.I.F.)

66Revision number

4 / A3.1

4 / A

3.1

4 / A3.1

4 / A

3.1

4 / A

3.1

4 / A3.1

4 / A

3.1

15B A4.1

VICINITY MAPNo scaleRefer to: all drawings5

TAMU Civil Engineering Concrete Lab Building #325

SSC

No.

201

6-01

438

KEY PLAN - FLOOR 1Scale: 1" = 40'-0"Refer to: all drawings7

Lab renovation. Refer to 1/A2.1

KEY PLAN - FLOOR 2Scale: 1" = 40'-0"Refer to: all drawings8

(ALTERNATE BID #1) Balcony enclosure. Refer to 1/A2.2

CODE REVIEW6

Existing building code review: 1982 Southern Building Code and 1981 NFPA 101 Lab building classified as B business and Type II construction First floor sprinklered. First floor area 19,948 gross, 16,509 net Second floor area 18,100 gross, 14,922 net Existing stairs are 4'-6” wide. Current Code 2015 IBC and 2015 NFPA 101 Occupant load at Concrete Lab = 1780 sf gross, 1178 sf net at 50 sf net/occ = 24 occupants Ocupant load at Classroom = 1172 sf at 30sf/occ = 40 occupants

(half to north and half to south = 20 each direction) Total load in Concrete Lab = 24 plus 20 = 44 occupants = 1 exit required. Second floor load: 4 Labs = 3469 sf at 30 sf/occ = 116 occupants

(half exit down the exterior stairs = 58) Study Lounge = 1058 sf at 30 sf/occ = 36 Total load at Second Floor = 36 + 58 = 94 occupants exiting down exterior stairs. 0.3” width per occupant = 28.2” of stair width required.

ELECTRICAL E0.0 Electrical legend and general notes E0.1 Electrical specifications E0.2 Electrical specifications E0.3 Electrical specifications EE2.1 Lighting first floor demolition plan ED2.2 Electrical first floor demolition plan ED2.3 Electrical second floor demolition plan E1.1 Lighting first floor renovation plan E1.2 LIghting second floor renovation plan E2.1 Electrical first floor renovation plan E2.2 Electrical second floor renovation plan E5.1 Electrical details E6.1 Electrical one line diagram E7.1 Electrical schedules E7.2 Electrical schedules PLUMBING P0.0 Plumbing symbols, abbreviations and general notes P0.1 Plumbing specifications PD1.1 Plumbing demolition plan P2.1 Plumbing first floor renovation plan P4.1 Plumbing partial plans - Alternates 1, 1A, and 2 P4.2 Plumbing partial plans - Alternates 3 and 5 P5.1 Plumbing details & schedules

Refer to: all drawings No scale

1

1 Addendum 08/17/2017

1

308 N. Bryan Ave. Bryan, TX 77803 P (979)821-2635 F (979)775-8224 www.arkitex.com

Reno

vatio

n fo

r

TAM

U C

ivil

Engi

neer

ing

Conc

rete

Lab

Revisions

Number Date

The

Arkitex Studio, Inc.

Project 17020 August 7, 2017

Texa

s A

&M

Uni

vers

ity, C

ivil

Engi

neer

ing

Bldg

. #03

25 -

Colle

ge S

tatio

n Ca

mpu

s

SSC

No.

201

6 - 0

1438

8/17/17

xx

x

110B

110

111

112 113A

110A

111A

WOMEN

MEN

ELEV

STORAGE AREA

109A

114B

114C

109

114

109C

109B

ASPHALT LAB

CONCRETE LAB

STORAGE

STORAGE

STORAGE/SHOP

OFFICE

CLASSROOM

MECHANICAL

LAB

EXISTING BUILDING

UP

UP

113

109 A

STAIR

CORRIDOR

CORRIDOR

(NIC)

(NIC)

(NIC)(NIC)

(NIC)

(NIC)

(NIC)

(NIC)

(NIC)

(NIC)

(NIC)

FIRST FLOOR REFLECTED CEILING PLANScale: 1/8"=1'-0"1NORTH

Plan North A8.10' 5' 10' 20'

Flush mounted fixture 2'x4'

Exit Light

LEGEND

Exposed structure

2x2 Ceiling Tile

Return air

Supply diffuser

12'-0" AFF

11'-4" AFF

Tinius Olsen dust collecting hood duct

GENERAL NOTES

1.

2.

3.

4.

Refer to electrical drawings for lighting fixture schedule. Existing exterior lighting to remain unchanged unless noted otherwise on plan. Patch and repair floor, walls, and ceiling materials at locations where items or portions of building are removed; typical. Note: Not all exit lighting is shown on Reflected Ceiling Plan, refer to Electrical for lighting schedule.

5.

6. 7.

8.

Building is fully sprinklered to meet the State of Texas fire protection standards. Sprinkler contractor shall submit layout drawing to architect and Owner for review prior to commencing work. Refer to sheet 4/A5.1 for finish schedule. Refer to Mechanical and Electrical drawinsg for light fixture and grille schedules. Center celing tile or grid in room as shown. Unless noted otherwise, center elements in ceiling tiles.

Refer to 1/A2.1

10 of 12

Utility wall mounted fixture

Reinstall projectors

Supports for electrical extension cord reels. Refer to 2/A8.1. Typical of 8; verify locations with Owner.

EXTENSION REEL SUPPORT DETAILScale: 1 1/2"=1'-0"2 Refer to 1/A8.1

1

1 Addendum 08/17/2017

110B

109A

114B

114C

109 B

114

109C

113

110

111

112113A

110A

111A

109B

109 A

WOMEN

MEN

ELEV

UP

UP

T

M2.1

MECHANICALFIRST FLOOR

RENOVATION PLAN

Texas R

egis

tere

d E

ngin

eering F

irm

F-1

4781

9805 W

hithorn

Drive

Housto

n, T

exas 77095

Em

ail:

S

JS

imon@

Ram

irez-S

imon.c

om

Phone: (8

32)

261-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Re

no

va

tio

ns t

o

TA

MU

Civ

il E

ngin

eering C

oncre

te L

ab

Te

xa

s A

&M

Un

ive

rsity,

Civ

il E

ng

ine

erin

g B

ldg

. #

03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Co

lleg

e S

tatio

n C

am

pu

s

GENERAL NOTES KEYED NOTES

Addendum 08/17/2017

UP

GENERAL NOTES KEYED NOTES

Texa

s R

egis

tere

d E

ngin

eerin

g Fi

rm F

-147

8198

05 W

hith

orn

Driv

eH

oust

on, T

exas

770

95E

mai

l: S

JSim

on@

Ram

irez-

Sim

on.c

omP

hone

: (83

2) 2

61-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Ren

ovat

ions

to

TAM

U C

ivil

Eng

inee

ring

Con

cret

e La

bTe

xas

A&

M U

nive

rsity

, Civ

il E

ngin

eerin

g B

ldg.

#03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Col

lege

Sta

tion

Cam

pus

M2.2MECHANICAL

SECOND FLOORRENOVATION PLAN

Addendum 08/17/2017

110B

109A

114B

114C

109 B

114

109C

113

110

111

112113A

110A

111A

109B

109 A

WOMEN

MEN

ELEV

UP

UP

M3.1MECHANICAL

FIRST FLOOR PIPINGPLAN

Texa

s R

egis

tere

d E

ngin

eerin

g Fi

rm F

-147

8198

05 W

hith

orn

Driv

eH

oust

on, T

exas

770

95E

mai

l: S

JSim

on@

Ram

irez-

Sim

on.c

omP

hone

: (83

2) 2

61-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Ren

ovat

ions

to

TAM

U C

ivil

Eng

inee

ring

Con

cret

e La

bTe

xas

A&

M U

nive

rsity

, Civ

il E

ngin

eerin

g B

ldg.

#03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Col

lege

Sta

tion

Cam

pus

GENERAL NOTES KEYED NOTES

Addendum 08/17/2017

T

GENERAL NOTES KEYED NOTES

114C

T

114C

114C

Texas R

egis

tered E

ngin

eerin

g F

irm

F-14781

9805 W

hithorn D

riv

e

Housto

n, T

exas 77095

Em

ail: S

JS

imon@

Ram

irez-S

imon.c

om

Phone: (832) 2

61-1420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Re

no

va

tio

ns t

o

TA

MU

Civ

il E

ngin

eerin

g C

oncrete

Lab

Te

xa

s A

&M

Un

ive

rsity,

Civ

il E

ng

ine

erin

g B

ldg

. #

03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Co

lle

ge

Sta

tio

n C

am

pu

s

M4.1

MECHANICAL

PARTIAL PLANS

ALTERNATE 1A

Addendum 08/17/2017

109A

114B

114C

114

109C

113

109B

WOMEN

UP

109A

114B

114C

114

109C

113

109B

UP

T

T

109B

M4.2

MECHANICALPARTIAL PLANS

ALTERNATES 2 & 3

Texas R

egis

tere

d E

ngin

eering F

irm

F-1

4781

9805 W

hithorn

Drive

Housto

n, T

exas 77095

Em

ail:

S

JS

imon@

Ram

irez-S

imon.c

om

Phone: (8

32)

261-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Re

no

va

tio

ns t

o

TA

MU

Civ

il E

ngin

eering C

oncre

te L

ab

Te

xa

s A

&M

Un

ive

rsity,

Civ

il E

ng

ine

erin

g B

ldg

. #

03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Co

lleg

e S

tatio

n C

am

pu

s

GENERAL NOTES KEYED NOTES

Addendum 08/17/2017

M4.3

MECHANICALSECTIONS

Texa

s R

egis

tere

d E

ngin

eering F

irm

F-1

4781

9805 W

hith

orn

Drive

Houst

on, T

exa

s 7

7095

Em

ail:

S

JSim

on@

Ram

irez-

Sim

on.c

om

Phone: (8

32)

261-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Re

no

vatio

ns

to

TA

MU

Civ

il E

ngin

eering C

oncr

ete

Lab

Te

xas

A&

M U

niv

ers

ity,

Civ

il E

ng

ine

erin

g B

ldg

. #

03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Co

lleg

e S

tatio

n C

am

pu

s

GENERAL NOTES

KEYED NOTES

Addendum 08/17/2017

SCALE: N.T.S.

SLOT PLENUM DETAIL3

SCALE: N.T.S.

CANOPY ENCLOSURE FOR TINIUS OLSEN MACHINE DETAIL2

SCALE: N.T.S.

EXTRACTION ARMS FOR CONCRETE MIXERS DETAIL1

SCALE: N.T.S.

CONDENSATE DRAIN PIPING 5

SCALE: N.T.S.

GRILLE CONNECTION DETAIL 6

UNISTRUT

HANGER RODTHREADED STEEL3/8" DIAMETER ALL

TRAPEZE OR P-30001-1/2" x 1-1/2' x 1/8" ANGLE

DUCT

SCALE: N.T.S.

DUCT SUPPORT DETAIL7

SCALE: N.T.S.

DUCT BRANCH TAKE OFF 9

SCALE: N.T.S.

DUCT PENETRATION THROUGH ROOF4

SCALE: N.T.S.

ROUND DUCT HANGER8

Texa

s R

egis

tere

d E

ngin

eerin

g Fi

rm F

-147

8198

05 W

hith

orn

Driv

eH

oust

on, T

exas

770

95E

mai

l: S

JSim

on@

Ram

irez-

Sim

on.c

omP

hone

: (83

2) 2

61-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Ren

ovat

ions

to

TAM

U C

ivil

Eng

inee

ring

Con

cret

e La

bTe

xas

A&

M U

nive

rsity

, Civ

il E

ngin

eerin

g B

ldg.

#03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Col

lege

Sta

tion

Cam

pus

M5.2MECHANICAL

DETAILS

Addendum 08/17/2017

REFER TOSPECIFICATIONSFOR DUCTWORK

BOLT BAND TOUNISTRUT CHANNEL ONBOTH SIDES

SCALE: N.T.S.

DUCT SUPPORT ON EXTERIOR GRADE DETAIL1

MINIMUM 6'-8" ABOVEFINISHED GRADE

EXHAUST DUCT 1" GALVANIZED STEEL BANDAROUND DUCTWORK

DUCT GALVANIZEDSTEEL SADDLE

SCALE: N.T.S.2

4" X 12 GAUGE 4-BOLTCORNER BRACKET IN12 GAUGE UNISTRUT(TYPICAL)

TO ROOF DETAILWIND LOADING BASE SUPPORT INSTALLATION

GALVANIZED UNISTRUT.COORDINATE SIZE WITHDUCT SUPPORTMANUFACTURER

190"

72"

SCALE: N.T.S.

AIR HANDLING UNIT DETAIL

1. THIS DETAIL SHOWS GENERAL ARRANGEMENT OF A/C UNIT COMPONENTS ONLY.2. COIL CONNECTION SIDE LOCATIONS AND ACCESS DOOR SWING LOCATIONS SHALL BE COORDINATED WITH PROJECT

SPECIFIC CONDITIONS.3. CONDENSATE SHALL DISCHARGE TO APPROVED PLUMBING FIXTURE INSIDE OF BUILDING. CONDENSATE DRAIN SHALL

SLOPE TOWARDS DRAIN.4. ALL ACCESS DOOR SHALL BE 18" MINIMUM WIDTH PER TAMU STANDARDS.

N O T E S:

3

SD

SADUCT MOUNTED SMOKE DETECTOR

(ONLY FOR UNITS 2000 CFM OR ABOVE)

OA

TRANSITION ASREQUIRED

DUCT MOUNTED SMOKEDETECTOR

SD

PLAN VIEW

ELEVATION VIEW

MIX AIR DAMPER

FILT

ER

S S

EC

TIO

N

PLE

NU

M F

AN

S

INTA

KE

PLE

NU

M S

EC

TIO

N

AC

CE

SS

SE

CTI

ON

CO

OLI

NG

CO

IL S

EC

TIO

N

HE

ATI

NG

CO

IL S

EC

TIO

N

AC

CE

SS

SE

CTI

ON

REFER TO PLAN FORCONDENSATE DRAIN ROUTING

TRANSITION ASREQUIRED

SCALE: N.T.S.

CONCRETE LAB SUPPLY AIR VALVE DETAIL4

Texa

s R

egis

tere

d E

ngin

eerin

g Fi

rm F

-147

8198

05 W

hith

orn

Driv

eH

oust

on, T

exas

770

95E

mai

l: S

JSim

on@

Ram

irez-

Sim

on.c

omP

hone

: (83

2) 2

61-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Ren

ovat

ions

to

TAM

U C

ivil

Eng

inee

ring

Con

cret

e La

bTe

xas

A&

M U

nive

rsity

, Civ

il E

ngin

eerin

g B

ldg.

#03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Col

lege

Sta

tion

Cam

pus

M5.3MECHANICAL

DETAILS

Addendum 08/17/2017

LA

AT

LS

LE

LITLIC

LCVLC

VA

XV

YS

VS

YCD

INSTRUMENTATION ABBREVIATION LIST

AIC

AETAC

AEAA

CODE CODE

KC

CODE

YIYA

ZIZS

ZC

LEVEL ALARM

ANALYTICAL TRANSMITTER

PRESSURE DIFFERENTIAL TRANSMITTER

LEVEL SWITCH

LEVEL ELEMENT

LEVEL INDICATING TRANSMITTERLEVEL INDICATING CONTROLLER

LEVEL CONTROL VALVELEVEL CONTROLLER (STAND ALONE)

VIBRATION ALARM

SOLENOID VALVE

SMOKE DETECTOR

VIBRATION SWITCH

SMOKE DAMPER

TEMPERATURE INDICATING CONTROLLERTEMPERATURE INDICATING TRANSMITTER

TEMPERATURE ELEMENT TRANSMITTER

ANALYTICAL INDICATING CONTROLLER

ANALYTICAL ELEMENT TRANSMITTERANALYTICAL CONTROLLER

ANALYTICAL ELEMENTANALYTICAL ALARMDESCRIPTION DESCRIPTION

CLOCK

DESCRIPTION

EQUIPMENT STATUSEQUIPMENT ALARM

POSITION INDICATORPOSITION SWITCH

POSITION CONTROL

NC NORMALLY CLOSED

NO NORMALLY OPEN

I UNDEFINED INTERLOCK LOGIC

FIELDMOUNTED MOUNTED

PANEL AUXILIARYLOCATION

ACCESSIBLE INACCESSIBLELOCATIONAUXILIARY

DISCRETE INSTRUMENTS

SHARED DISPLAY, SHARED CONTROL

PROGRAMMABLE LOGIC CONTROLOR DIRECT DIGITAL CONTROL

DUCT MOUNTEDAVERAGING

ELEMENT/SENSOR ELEMENT/SENSOR

DIFFERENTIAL PRESSUREELEMENT/SENSOR

FLOW ARROWXXX INDICATES AIR TYPE

INSTRUMENT NAMING CONVENTION

XXX - FUNCTION IDNNN - DEVICE NUMBER

LINE TYPE LEGEND

INTERNAL SYSTEM LINK

ELECTRICAL SIGNAL

PNEUMATIC SIGNAL

NNNXXX

TE

~ ~

~ ~

PD

TE

GENERAL INSTRUMENT SYMBOLS

TEMPERATURE

NOTE: CONTROLS SHALL BE SIEMENS. ALL POINTS SHALL COMMUNICATE WITH TAMU UES MAIN BAS.

AI ANALOG INPUTAO ANALOG OUTPUT

DI DISCRETE INPUTDO DISCRETE OUTPUT

N.T.S2

SEQUENCE OF OPERATIONS

~ CONTROLPOWER

NO

BASCONTROLLER

H

C

HWS

HWR

LOCATE SENSORSWHERE SHOWNON THE PLANS

TO NEXT UNIT ON LAN~~

CONTROL POWER

FROM PREVIOUS UNIT ON LAN

SCALE: N.T.S.

VAV TERMINAL UNITS TU-1, -2, -3, -4, & -6 CONTROL DIAGRAM1

VARIABLE AIR VOLUME TERMINAL UNITS W/ HOT WATER COIL

UNIT CONTROLS SHALL BE INTERLOCKED WITH DUST COLLECTOR OPERATION TO PROVIDE MAXIMUM SETAIRFLOW DURING DUST COLLECTOR OPERATION, IN ORDER TO MAINTAIN SPACE PRESSURIZATION WITHIN THEIRRESPECTIVE ZONES.

WHEN DUST COLLECTOR IS NOT ACTIVE, EACH TERMINAL UNIT SHALL MODULATE THE SUPPLY AIR DAMPER TOMAINTAIN THE SPACE TEMPERATURE CONDITIONS. IF THE ZONE REQUIRES COOLING, THE SUPPLY AIR DAMPERSHALL BE MODULATED BETWEEN THE MINIMUM AND MAXIMUM COOLING AIR FLOWS TO MAINTAIN THE SPACETEMPERATURE AT THE COOLING SETPOINT OF 73°F (ADJUSTABLE). IF THE ZONE CALLS FOR HEATING, THE SUPPLYAIR DAMPER SHALL BE MODULATED TO A MINIMUM AND THE HW VALVE SHALL BE MODULATED TO MAINTAIN THESPACE TEMPERATURE AT THE HEATING SETPOINT OF 72°F (ADJUSTABLE). IF ADDITIONAL HEATING IS REQUIREDWHEN THE VALVE IS FULLY OPEN, THE SUPPLY AIR DAMPER SHALL BE MODULATED TO MEET THE ROOMTEMPERATURE REQUIREMENTS. VAV BOX SHALL BE CONNECTED TO ZONE THERMOSTAT.

HOT WATER VALVE EXERCISEPROVIDE AUTOMATIC HOT WATER VALVE EXERCISE (OPEN AND CLOSE) WEEKLY. SET ORIGINAL TIME FORFRIDAYS AT 12AM (ADJUSTABLE).

~

SEQUENCE OF OPERATIONS

~ CONTROLPOWER

NO

BASCONTROLLER

H

C

HWS

HWR

LOCATE SENSORSWHERE SHOWNON THE PLANS

TO NEXT UNIT ON LAN~~

CONTROL POWER

FROM PREVIOUS UNIT ON LAN

SCALE: N.T.S.

VAV TERMINAL UNIT TU-5 CONTROL DIAGRAM3

~

VARIABLE AIR VOLUME TERMINAL UNITS W/ HOT WATER COIL

TERMINAL UNIT SHALL MODULATE THE SUPPLY AIR DAMPER TO MAINTAIN THESPACE TEMPERATURE CONDITIONS. IF THE ZONE REQUIRES COOLING, THESUPPLY AIR DAMPER SHALL BE MODULATED BETWEEN THE MINIMUM ANDMAXIMUM COOLING AIR FLOWS TO MAINTAIN THE SPACE TEMPERATURE ATTHE COOLING SETPOINT OF 73°F (ADJUSTABLE). IF THE ZONE CALLS FORHEATING, THE SUPPLY AIR DAMPER SHALL BE MODULATED TO A MINIMUM ANDTHE HW VALVE SHALL BE MODULATED TO MAINTAIN THE SPACE TEMPERATUREAT THE HEATING SETPOINT OF 72°F (ADJUSTABLE). IF ADDITIONAL HEATING ISREQUIRED WHEN THE VALVE IS FULLY OPEN, THE SUPPLY AIR DAMPER SHALLBE MODULATED TO MEET THE ROOM TEMPERATURE REQUIREMENTS. VAVBOX SHALL BE CONNECTED TO ZONE THERMOSTAT.

HOT WATER VALVE EXERCISEPROVIDE AUTOMATIC HOT WATER VALVE EXERCISE (OPEN AND CLOSE)WEEKLY. SET ORIGINAL TIME FOR FRIDAYS AT 12AM (ADJUSTABLE).

Texa

s R

egis

tere

d En

gine

erin

g Fi

rm F

-147

8198

05 W

hith

orn

Driv

eH

oust

on, T

exas

770

95Em

ail:

SJS

imon

@R

amire

z-Si

mon

.com

Phon

e: (8

32) 2

61-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Ren

ovat

ions

to

TAM

U C

ivil

Engi

neer

ing

Con

cret

e La

bTe

xas

A&M

Uni

vers

ity, C

ivil

Engi

neer

ing

Bldg

. #03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Col

lege

Sta

tion

Cam

pus

M6.1MECHANICALCONTROLS

Addendum 08/17/2017

Texa

s R

egis

tere

d E

ngin

eerin

g Fi

rm F

-147

8198

05 W

hith

orn

Driv

eH

oust

on, T

exas

770

95E

mai

l: S

JSim

on@

Ram

irez-

Sim

on.c

omP

hone

: (83

2) 2

61-1

420

8/17/2017

308 N. Bryan Ave.Bryan, TX 77803P (979)821-2635F (979)775-8224www.arkitex.com

Ren

ovat

ions

to

TAM

U C

ivil

Eng

inee

ring

Con

cret

e La

bTe

xas

A&

M U

nive

rsity

, Civ

il E

ngin

eerin

g B

ldg.

#03

25

Revisions

Number Date

TheArkitexStudio,Inc.

Col

lege

Sta

tion

Cam

pus

M7.1MECHANICALSCHEDULES

Addendum 08/17/2017