Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, P.Eng. Drainage & Environment Manager

Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Embed Size (px)

Citation preview

Page 1: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Adaptive Management & Integrated Stormwater Management Plans

Carrie Baron, P.Eng.

Drainage & Environment

Manager

Page 2: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

• Late 1800’s settlers dyked and dammed local rivers for agricultural purposes

• 1970’s the City of Surrey adopted the “Natural Drainage Policy”

• 1980’s & 1990’s, the City undertook Master Drainage plans (MDPs) for entire City

• MDPs were refined in land use planning projects called Neighbourhood Concept Plans (NCPs).

• 1997 East Clayton Sustainable Community NCP developed where new visions in storm water management were incorporated

• Late 1990’s concept of Integrated Storm Water Management plans (ISMP) as part of LWMP

• ISMPs updated with new Integrated Liquid Waste & Resource Management Plan

Surrey’s Storm Water History

Page 3: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Integrated Liquid Waste and Resource Management Plan (ILWRMP)

In approving the Regions ILWRMP, the Minister added a condition that local governments needed to follow - Condition 7:

Member municipalities, with Metro Vancouver, will develop a program to monitor stormwater and assess the effectiveness of Integrated Stormwater Management Plans.

The program will use a weight of evidence performance measurement approach.

As a result, the Adaptive Management Framework (AMF) Monitoring and Reporting procedure was developed

Page 4: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

AMF Objectives and Goals

Goals:• Be cost effective • Use indicators which are directly related to watershed health and

useful without long term data records • Recommend technically sound and consistent monitoring practices• Link monitoring results to relevant adaptive management practices• Stimulate continuous improvements in watershed health

Objectives: To monitor and protect watershed health; to assess

ISMP effectiveness

Page 5: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Reporting

East Clayton Rock Trench Monitoring

0

0.1

0.2

0.3

0.4

0.5

0.6

Sep 28 12:00 Sep 28 18:00 Sep 29 00:00 Sep 29 06:00 Sep 29 12:00 Sep 29 18:00 Sep 30 00:00 Sep 30 06:00 Sep 30 12:00

Le

ve

l (m

), F

low

(L

/s)

0

5

10

15

20

25

30

Ho

url

y R

ain

(m

m)

Level Flow Rain

62.8 mm Total Rain

(22 hours)

Intensities higher than

upper soil's saturated

infiltration rate

2 mm Runoff

40.8 mm of Rain

Reporting to Ministry with ISMP update reports.

Reports include water chemistry, flow, benthic invertibrates, ISMP implementation, adaptive measures, additional monitoring

Page 6: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Adaptive Management

Adaptive management practices

(AMP) are steps taken in response to

the degradation of watershed health

whether water quantity or quality.

Adaptive management practices can

range from engineered facilities to

education campaigns.

Page 7: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

South Newton Monitoring• Project involved monitoring 2

adjacent catchments of similar size and development. The one development installed significant on-lot BMPs to reduce runoff while the other relied on downstream community detention.

• Monitoring was designed to look at how the BMP development runoff compared to the none BMP development runoff to answer the question:

“Can on lot BMPs effectively manage short and long duration rainfall events?”

Page 8: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

1998 vs. 2014 Land Use

Page 9: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Small storm event

Page 10: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Large and winter storm event

Page 11: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

South Newton Results

• BMPs installed function for small events

• BMPs have limited value during a long or significant rainfall events

• Combination of on-lot and street level BMPs combined with community detention is likely the best management option

• Additional monitoring is continuing for another couple season to confirm the results.

Page 12: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Boundary Bay Ambient Monitoring Program

Page 13: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

• The City of Surrey is building off of the Boundary Bay monitoring program to better identify, trace and manage water quality throughout the City.

Key examples of using data to solve pollution issues include:o bacterial source tracking Cloverdale canal and working with polluter

to resolve issueo Agricultural and water quality education or property owners along key

tributaries of the Little Campbell River

Component of the Adaptive Management Framework

Page 14: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Electrical Fire (2009)

0

5

10

15

20

25

5/Aug 12/Aug 19/Aug 26/Aug 2/Sep

ug/

L

Bear Creek Fire InfluenceAt 152 St - Copper

At 68 Ave - Copper

At 152 St - Nickel

At 68 Ave - Nickel

Page 15: Adaptive Management & Integrated Stormwater Management Plans … ·  · 2015-02-19Adaptive Management & Integrated Stormwater Management Plans Carrie Baron, ... • MDPs were refined

Questions