Activity on the Node

Embed Size (px)

Citation preview

  • 8/7/2019 Activity on the Node

    1/37

  • 8/7/2019 Activity on the Node

    2/37

    PPrecendance diagramsrecendance diagrams Unlike Arrow Diagramming that uses the

    arrows for activities and nodes for thestart and end of activities, Precedence

    Diagramming places the activity on thenodes and uses arrows between thenodes to show the sequence betweeneach activity

    Precedence Diagramming is also called"activity-on-the-node"

  • 8/7/2019 Activity on the Node

    3/37

    AdvantagesAdvantages Physically easier to produce and require far

    less draughtsman ship

    The need for dummy activities is eliminated

    Additional information can be inserted in the

    network without affecting the legibility ofthe finished plan

    They allow a closer co-ordination betweenthe network and the resultant linked barchart

    Time delays can be introduced easier thanwith arrow networks

  • 8/7/2019 Activity on the Node

    4/37

    EExamplexample 11

  • 8/7/2019 Activity on the Node

    5/37

    Example 2Example 2

  • 8/7/2019 Activity on the Node

    6/37

    Example 3Example 3

  • 8/7/2019 Activity on the Node

    7/37

    Example 4Example 4

  • 8/7/2019 Activity on the Node

    8/37

    Example 5Example 5

  • 8/7/2019 Activity on the Node

    9/37

    Example 6Example 6

    :OTE You can say that&activities A B merge at D

  • 8/7/2019 Activity on the Node

    10/37

    Layout of activity boxesLayout of activity boxes

    ActivityRef No

    Duration

    EST

    LST

    EFT

    LFT

  • 8/7/2019 Activity on the Node

    11/37

    AnalysisAnalysis

    Forward passTo obtain EST

    All projects may be assumed to start

    from day 1 unless specifiedotherwise (due to weather conditions). Alternatively, you can assume

    the start as day 0

  • 8/7/2019 Activity on the Node

    12/37

    Example 7Example 7

    A

    5

    1 6 B

    3

    6 9 C

    10

    9 19

  • 8/7/2019 Activity on the Node

    13/37

    Example 8Example 8

    A

    5

    1 6

    B

    6

    1 7

    C

    2

    D

    8

    E

    2

  • 8/7/2019 Activity on the Node

    14/37

    Example 8Example 8A

    5

    1 6

    B

    6

    1 7

    C

    2

    6 8

    D

    8

    7 15

    E

    2

    7 9

    We know that an activitycannot start until all

    the activities leading toit have completed

    Whenever there is morethat one activity

    preceding a selected,activity the Early Start

    Time of the selectedactivity is the latest of

    the preceding EarlyFinish Times

    { , }Max 7 6

  • 8/7/2019 Activity on the Node

    15/37

    AnalysisAnalysis

    Backward passTo obtain LST

  • 8/7/2019 Activity on the Node

    16/37

    Example 9Example 9

    A

    5

    1 6 B

    3

    6 9 C

    10

    9 19

  • 8/7/2019 Activity on the Node

    17/37

    Example 9Example 9

    A

    5

    1 6 B

    3

    6 9 C

    10

    9 19

    19

    ,Once the last activity s Late Finish Time has been set then youcan calculate the activity s Late Start Time by subtracting the

    , . . ,activity duration from the Late Finish Date i e for activity C= - =LST 19 10 9

    As you proceed through the schedule the Late Finish Time of apreceding activity is the earliest of the prior Late Start Times

  • 8/7/2019 Activity on the Node

    18/37

    Example 9Example 9

    A

    5

    1

    1

    6

    6

    B

    3

    6

    6

    9

    9

    C

    10

    9

    9

    19

    19

    - =9 3 6- =6 5 1 - =19 10 9

  • 8/7/2019 Activity on the Node

    19/37

    Example 10Example 10

    A

    5

    1

    2

    6

    7

    B

    6

    1

    1

    7

    7

    C

    2

    6

    13

    8

    15

    D

    8

    7

    7

    15

    15

    E

    2

    7

    13

    9

    15

    { , }Min 13 7- =7 6 1

  • 8/7/2019 Activity on the Node

    20/37

    Start to start logicStart to start logic

    The standard sequence where oneactivity precedes another is calledFinish-to-Start

    Use the Start-to-Start sequence when

    the start of the following activities isdependant upon the start of the

    following activity

    The Start-to-Start sequence has itsimpact on the forward passcalculations

  • 8/7/2019 Activity on the Node

    21/37

    NoteNoteNotice that the logic sequence between

    activities using the Start-to-Startsequence may include a timecomponent.

    For example, we cannot start the pipe

    installation at exactly the same as thestart of the trenching operation. The

    first activity must get ahead a fewdays, before the piping activity canbegin. Adding a time duration to thesequence between activities is a majorinnovation associated with the

    Precedence Diagram

  • 8/7/2019 Activity on the Node

    22/37

    Example of start-to-startExample of start-to-start An example use of the Start-to-Start

    sequence is that of laying undergroundpipe. In such a project a machine digs atrench in which the pipe is placed. Once the

    pipe is placed, then the same machine maybe used to backfill the trench. An effectiveproject manager may want to schedule thisproject such that the pipe installation canproceed before the whole trench has been

    cut. Similarly, the backfill could beginbefore the entire length of pipe has beeninstalled. To show how the start of oneactivity can affect the start of another, usethe Start-to-Start sequence.

  • 8/7/2019 Activity on the Node

    23/37

    Example of start-to-startExample of start-to-start

    A

    5

    1 6

    B

    6

    3

    C

    2

    D

    8

    E

    2

    SS2

  • 8/7/2019 Activity on the Node

    24/37

    Example of start-to-startExample of start-to-start

    A

    5

    1 6

    B

    6

    3 9

    C

    2

    6 8

    D

    8

    9 17

    E

    2

    9 11

    SS2

  • 8/7/2019 Activity on the Node

    25/37

  • 8/7/2019 Activity on the Node

    26/37

    Example of start-to-startExample of start-to-start

    A

    5

    1

    4

    6

    9

    B

    6

    3

    3

    9

    9

    C

    2

    6

    15

    8

    17

    D

    8

    9

    9

    17

    17

    E

    2

    9

    15

    11

    17

    SS2

  • 8/7/2019 Activity on the Node

    27/37

    Example of start-to-startExample of start-to-start

    A

    5

    1

    4

    6

    9

    B

    6

    3

    3

    9

    9

    C

    2

    6

    15

    8

    17

    D

    8

    9

    9

    17

    17

    E

    2

    9

    15

    11

    17

    SS2

    :NOTEThe critical path begins with thestart of Activity A

  • 8/7/2019 Activity on the Node

    28/37

    Finish to finish logicFinish to finish logic

    Finish-to-Finish can be thought of aslinking the completion of twoactivities such that the completion of

    the prior activity takes place a fewdays before the completion of thesecond activity

  • 8/7/2019 Activity on the Node

    29/37

    Example of finish to finishExample of finish to finish

    Completion of the pipe installationcannot occur until some time afterthe completion of the trenching

    activity.

    The pipe must all be installed prior to

    the completion of the backfill activity

  • 8/7/2019 Activity on the Node

    30/37

    Example of finish to finishExample of finish to finish

    A

    5

    1 6

    B

    6

    1 7

    C

    2

    6 8

    D

    8

    7 15

    E

    2

    7 9

    FF5

    FF2

  • 8/7/2019 Activity on the Node

    31/37

    Example of finish to finishExample of finish to finish

    A

    5

    1 6

    B

    6

    1 7

    C

    2

    6 8

    10

    D

    8

    7 15

    15

    E

    2

    7 9

    13

    FF5

    FF2

  • 8/7/2019 Activity on the Node

    32/37

    Example of finish to finishExample of finish to finish

    A

    5

    1 6

    B

    6

    1 7

    C

    2

    6

    8

    8

    10

    D

    8

    7

    7

    15

    15

    E

    2

    7

    11

    9

    13

    FF5

    FF2

  • 8/7/2019 Activity on the Node

    33/37

    Example of finish to finishExample of finish to finish

    A

    5

    1 6

    7

    B

    6

    1 7

    7

    C

    2

    6

    8

    8

    10

    D

    8

    7

    7

    15

    15

    E

    2

    7

    11

    9

    13

    FF5

    FF2

  • 8/7/2019 Activity on the Node

    34/37

  • 8/7/2019 Activity on the Node

    35/37

    Exercise 1Exercise 1

    A

    1START

    B

    3

    C

    2

    F

    5END

    D

    2

    H

    1

    J

    3

    E

    4

    G

    1

  • 8/7/2019 Activity on the Node

    36/37

    Solution 1 (forward)Solution 1 (forward)

    A

    1

    0 1START

    B

    3

    1 4 C

    2

    4 6 F

    5

    8 13END

    D

    2

    0 2

    H

    1

    0 1 J

    3

    2 5

    E

    4

    4 8 G

    1

    8 9

  • 8/7/2019 Activity on the Node

    37/37

    Solution 1 (backward)Solution 1 (backward)

    A

    1

    0

    0

    1

    1START

    B

    3

    1

    1

    4

    4

    C

    2

    4

    6

    6

    8

    F

    5

    8

    8

    13

    13END

    D

    2

    0

    2

    2

    4

    H

    1

    0

    9

    1

    10

    J

    3

    2

    10

    5

    13

    E

    4

    4

    4

    8

    8

    G

    1

    8

    12

    9

    13