Upload
allahmahdiali
View
229
Download
0
Embed Size (px)
Citation preview
8/7/2019 Activity on the Node
1/37
8/7/2019 Activity on the Node
2/37
PPrecendance diagramsrecendance diagrams Unlike Arrow Diagramming that uses the
arrows for activities and nodes for thestart and end of activities, Precedence
Diagramming places the activity on thenodes and uses arrows between thenodes to show the sequence betweeneach activity
Precedence Diagramming is also called"activity-on-the-node"
8/7/2019 Activity on the Node
3/37
AdvantagesAdvantages Physically easier to produce and require far
less draughtsman ship
The need for dummy activities is eliminated
Additional information can be inserted in the
network without affecting the legibility ofthe finished plan
They allow a closer co-ordination betweenthe network and the resultant linked barchart
Time delays can be introduced easier thanwith arrow networks
8/7/2019 Activity on the Node
4/37
EExamplexample 11
8/7/2019 Activity on the Node
5/37
Example 2Example 2
8/7/2019 Activity on the Node
6/37
Example 3Example 3
8/7/2019 Activity on the Node
7/37
Example 4Example 4
8/7/2019 Activity on the Node
8/37
Example 5Example 5
8/7/2019 Activity on the Node
9/37
Example 6Example 6
:OTE You can say that&activities A B merge at D
8/7/2019 Activity on the Node
10/37
Layout of activity boxesLayout of activity boxes
ActivityRef No
Duration
EST
LST
EFT
LFT
8/7/2019 Activity on the Node
11/37
AnalysisAnalysis
Forward passTo obtain EST
All projects may be assumed to start
from day 1 unless specifiedotherwise (due to weather conditions). Alternatively, you can assume
the start as day 0
8/7/2019 Activity on the Node
12/37
Example 7Example 7
A
5
1 6 B
3
6 9 C
10
9 19
8/7/2019 Activity on the Node
13/37
Example 8Example 8
A
5
1 6
B
6
1 7
C
2
D
8
E
2
8/7/2019 Activity on the Node
14/37
Example 8Example 8A
5
1 6
B
6
1 7
C
2
6 8
D
8
7 15
E
2
7 9
We know that an activitycannot start until all
the activities leading toit have completed
Whenever there is morethat one activity
preceding a selected,activity the Early Start
Time of the selectedactivity is the latest of
the preceding EarlyFinish Times
{ , }Max 7 6
8/7/2019 Activity on the Node
15/37
AnalysisAnalysis
Backward passTo obtain LST
8/7/2019 Activity on the Node
16/37
Example 9Example 9
A
5
1 6 B
3
6 9 C
10
9 19
8/7/2019 Activity on the Node
17/37
Example 9Example 9
A
5
1 6 B
3
6 9 C
10
9 19
19
,Once the last activity s Late Finish Time has been set then youcan calculate the activity s Late Start Time by subtracting the
, . . ,activity duration from the Late Finish Date i e for activity C= - =LST 19 10 9
As you proceed through the schedule the Late Finish Time of apreceding activity is the earliest of the prior Late Start Times
8/7/2019 Activity on the Node
18/37
Example 9Example 9
A
5
1
1
6
6
B
3
6
6
9
9
C
10
9
9
19
19
- =9 3 6- =6 5 1 - =19 10 9
8/7/2019 Activity on the Node
19/37
Example 10Example 10
A
5
1
2
6
7
B
6
1
1
7
7
C
2
6
13
8
15
D
8
7
7
15
15
E
2
7
13
9
15
{ , }Min 13 7- =7 6 1
8/7/2019 Activity on the Node
20/37
Start to start logicStart to start logic
The standard sequence where oneactivity precedes another is calledFinish-to-Start
Use the Start-to-Start sequence when
the start of the following activities isdependant upon the start of the
following activity
The Start-to-Start sequence has itsimpact on the forward passcalculations
8/7/2019 Activity on the Node
21/37
NoteNoteNotice that the logic sequence between
activities using the Start-to-Startsequence may include a timecomponent.
For example, we cannot start the pipe
installation at exactly the same as thestart of the trenching operation. The
first activity must get ahead a fewdays, before the piping activity canbegin. Adding a time duration to thesequence between activities is a majorinnovation associated with the
Precedence Diagram
8/7/2019 Activity on the Node
22/37
Example of start-to-startExample of start-to-start An example use of the Start-to-Start
sequence is that of laying undergroundpipe. In such a project a machine digs atrench in which the pipe is placed. Once the
pipe is placed, then the same machine maybe used to backfill the trench. An effectiveproject manager may want to schedule thisproject such that the pipe installation canproceed before the whole trench has been
cut. Similarly, the backfill could beginbefore the entire length of pipe has beeninstalled. To show how the start of oneactivity can affect the start of another, usethe Start-to-Start sequence.
8/7/2019 Activity on the Node
23/37
Example of start-to-startExample of start-to-start
A
5
1 6
B
6
3
C
2
D
8
E
2
SS2
8/7/2019 Activity on the Node
24/37
Example of start-to-startExample of start-to-start
A
5
1 6
B
6
3 9
C
2
6 8
D
8
9 17
E
2
9 11
SS2
8/7/2019 Activity on the Node
25/37
8/7/2019 Activity on the Node
26/37
Example of start-to-startExample of start-to-start
A
5
1
4
6
9
B
6
3
3
9
9
C
2
6
15
8
17
D
8
9
9
17
17
E
2
9
15
11
17
SS2
8/7/2019 Activity on the Node
27/37
Example of start-to-startExample of start-to-start
A
5
1
4
6
9
B
6
3
3
9
9
C
2
6
15
8
17
D
8
9
9
17
17
E
2
9
15
11
17
SS2
:NOTEThe critical path begins with thestart of Activity A
8/7/2019 Activity on the Node
28/37
Finish to finish logicFinish to finish logic
Finish-to-Finish can be thought of aslinking the completion of twoactivities such that the completion of
the prior activity takes place a fewdays before the completion of thesecond activity
8/7/2019 Activity on the Node
29/37
Example of finish to finishExample of finish to finish
Completion of the pipe installationcannot occur until some time afterthe completion of the trenching
activity.
The pipe must all be installed prior to
the completion of the backfill activity
8/7/2019 Activity on the Node
30/37
Example of finish to finishExample of finish to finish
A
5
1 6
B
6
1 7
C
2
6 8
D
8
7 15
E
2
7 9
FF5
FF2
8/7/2019 Activity on the Node
31/37
Example of finish to finishExample of finish to finish
A
5
1 6
B
6
1 7
C
2
6 8
10
D
8
7 15
15
E
2
7 9
13
FF5
FF2
8/7/2019 Activity on the Node
32/37
Example of finish to finishExample of finish to finish
A
5
1 6
B
6
1 7
C
2
6
8
8
10
D
8
7
7
15
15
E
2
7
11
9
13
FF5
FF2
8/7/2019 Activity on the Node
33/37
Example of finish to finishExample of finish to finish
A
5
1 6
7
B
6
1 7
7
C
2
6
8
8
10
D
8
7
7
15
15
E
2
7
11
9
13
FF5
FF2
8/7/2019 Activity on the Node
34/37
8/7/2019 Activity on the Node
35/37
Exercise 1Exercise 1
A
1START
B
3
C
2
F
5END
D
2
H
1
J
3
E
4
G
1
8/7/2019 Activity on the Node
36/37
Solution 1 (forward)Solution 1 (forward)
A
1
0 1START
B
3
1 4 C
2
4 6 F
5
8 13END
D
2
0 2
H
1
0 1 J
3
2 5
E
4
4 8 G
1
8 9
8/7/2019 Activity on the Node
37/37
Solution 1 (backward)Solution 1 (backward)
A
1
0
0
1
1START
B
3
1
1
4
4
C
2
4
6
6
8
F
5
8
8
13
13END
D
2
0
2
2
4
H
1
0
9
1
10
J
3
2
10
5
13
E
4
4
4
8
8
G
1
8
12
9
13