    26-6703-00S |PRODUCTION ORGANISATION & HUMAN RESOURCE MANAGEMENT

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Activity 1

    You have been instructed by the managing director of your company to prepare a site visit

    report for a proposed industrial development scheme in Kuala Terengganu, Malaysia.

    You arrive on site in the late afternoon and have approximately three hours of daylight in

    which to conduct your investigations.

    Question

    a) Working individually for 10 minutes, prepare a list of items you consider relevant forthe formulation of the report which will be used for tender assessment, pre-tender

    planning and pricing the scheme.

    b) From the items identified in a) select three which you feel will have the greatestimpact on construction operations.

  • 7/27/2019 Activity 1 Solution

    2/4

    26-6703-00S |PRODUCTION ORGANISATION & HUMAN RESOURCE MANAGEMENT

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    SUGGESTED CHECK LIST FOR PRE-TENDER SITE SURVEY

    PROJECT TENDER NO.

    DATEPREPARED

    BY

    SITE INVESTIGATION

    1 Availability of site

    2 Location distance from:

    2.1 Head office/traveling time

    2.2 Local transport services

    3 Access to site

    3.1 Road width

    3.2 Existing access

    3.3 Crossings

    3.4 Temporary roads

    3.5 Traffic intensity

    4 Working space available for:4.1 Offices, canteen, stores

    4.2 Bulk material storage, handling

    4.3 Construction purposes

    4.4 Plant (and recovery)

    5 Services/location:

    5.1 Toilets

    5.2 Water

    5.3 Electricity5.4 Telephone

    5.5 Any available from client?

    6 Nature of ground:

    6.1 Surface

    6.2 Bore Holes

    6.3 Levels

    6.4 Piling

  • 7/27/2019 Activity 1 Solution

    3/4

    26-6703-00S |PRODUCTION ORGANISATION & HUMAN RESOURCE MANAGEMENT

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    7 Site Clearance

    7.1 Trees

    7.2 Streams

    7.3 Existing Items7.4 Excavations: room for plant

    7.5 Tips and charges distance

    LOCAL CONDITIONS

    8 Availability of local labour:

    8.1 Type, quality

    8.2 Inducement paid in area

    9 Nearest Labour Exchange

    9.1 Address

    9.2 Other contact details

    10 Damage to existing properties:

    10.1 Adjacent buildings

    10.2 Roads

    10.3 Footpaths

    10.4 Photographs if necessary

    11 Local Resources

    11.1 Builders merchants

    11.2 Sub-contractors

    11.3 Plant hire services

    12 Other large contracts in area

    13 Name and address of adjacent property

    Owners/occupiers

  • 7/27/2019 Activity 1 Solution

    4/4

    26-6703-00S |PRODUCTION ORGANISATION & HUMAN RESOURCE MANAGEMENT

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    SECURITY

    14 General security requirements

    14.1 Fencing: hoarding

    14.2 Fans14.3 Lighting

    15 Watchman/guard dogs

    15.1 Playgrounds

    15.2 Schools

    15.3 General area

    OTHER CONDITIONS

    16 Special conditions: implications of:

    16.1 Penalty/bonus clause

    16.2 Work in phases

    16.3 Special insurances

    17 Items requiring special attention

    when pricing

    18 Possibility of flooding

    19 Fire precautions

    20 Work to be done by Client

    21 Other firms tendering

    22 Additional information