18
ASX ANNOUNCEMENT 30 April 2018 Activities Report for Quarter ended 31 March 2018 HIGHLIGHTS Eastern Goldfields completes placement to raise $30.57 million Further $5.0 million raised through entitlement issue & underwriting Underground mining at Golden Eagle progressing strongly Open pit mining operations resumed at Siberia during February 2018 Resource definition drilling recommenced Reinstated to Official Quotation on ASX post quarter end Cash including gold in circuit and gold in transit of $5.43 million Tradeable securities of $5.01 million $5 million repaid to Investec Australia Limited Undrawn Investmet Limited line of credit $8.81 million OVERVIEW - DAVYHURST PROJECT OPERATIONS REPORT The Davyhurst Project includes both open cut and underground mining targets and is located 120 kilometres north-west of Kalgoorlie. During the March quarter, ramping up activities continued within the 1.2Mtpa gold processing plant, the Davyhurst Mill, with 72,183 tonnes at 1.48g/t treated. March delivered the strongest in results with an increased plant head grade of 1.69g/t and increased through-put rates achieved. Underground mining continues to progress well at Golden Eagle, with total development of 370 metres for the quarter. The decline has advanced past the second level (355 Level) in the mine with ore development now well established. Ore development has been completed on the first level (375 Level), with ore production commenced. A 3,500 metre underground drilling program targeting the Golden Eagle Central Shoot has commenced, with 933 metres completed during the quarter. Samples have been processed and submitted to the laboratory for assay. Siberia open pit mining operations resumed in February, with the focus on the southern cut back of the Sandking pit. Material movement has progressed well in this free digging oxide portion of the pit. Additional grade control drilling has been conducted over the near surface laterite ores situated east of the pit, all of which sits outside the pre-mining ore reserve. Additional drilling is planned targeting mineralised extensions to the south- east. On the ground, resource development and explorations works recommenced in March, with the drilling contractor mobilising two drilling rigs to site. On start‐up, drilling crews were deployed to the Riverina deposit, with exploration works at Menzies. ISSUED CAPITAL Shares: 758.6m Options: 223.6m Current Share Price: $0.150 Market Capitalisation: $114m Cash at 31/03/2018: $3.8m* *Excluding total debt facilities of $35.0m. Drawn to date $18.6m

Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

ASX ANNOUNCEMENT 30 April 2018

Activities Report for Quarter ended 31 March 2018

HIGHLIGHTS

• Eastern Goldfields completes placement to raise $30.57 million

• Further $5.0 million raised through entitlement issue & underwriting

• Underground mining at Golden Eagle progressing strongly

• Open pit mining operations resumed at Siberia during February 2018

• Resource definition drilling recommenced

• Reinstated to Official Quotation on ASX post quarter end

• Cash including gold in circuit and gold in transit of $5.43 million

• Tradeable securities of $5.01 million

• $5 million repaid to Investec Australia Limited

• Undrawn Investmet Limited line of credit $8.81 million

OVERVIEW - DAVYHURST PROJECT OPERATIONS REPORT The Davyhurst Project includes both open cut and underground mining targets and is located 120 kilometres north-west of Kalgoorlie. During the March quarter, ramping up activities continued within the 1.2Mtpa gold processing plant, the Davyhurst Mill, with 72,183 tonnes at 1.48g/t treated. March delivered the strongest in results with an increased plant head grade of 1.69g/t and increased through-put rates achieved. Underground mining continues to progress well at Golden Eagle, with total development

of 370 metres for the quarter. The decline has advanced past the second level (355 Level)

in the mine with ore development now well established. Ore development has been

completed on the first level (375 Level), with ore production commenced.

A 3,500 metre underground drilling program targeting the Golden Eagle Central Shoot has commenced, with 933 metres completed during the quarter. Samples have been processed and submitted to the laboratory for assay. Siberia open pit mining operations resumed in February, with the focus on the southern

cut back of the Sandking pit. Material movement has progressed well in this free digging

oxide portion of the pit. Additional grade control drilling has been conducted over the

near surface laterite ores situated east of the pit, all of which sits outside the pre-mining

ore reserve. Additional drilling is planned targeting mineralised extensions to the south-

east.

On the ground, resource development and explorations works recommenced in March, with the drilling contractor mobilising two drilling rigs to site. On start‐up, drilling crews were deployed to the Riverina deposit, with exploration works at Menzies.

ISSUED CAPITAL

Shares: 758.6m Options: 223.6m Current Share Price: $0.150 Market Capitalisation: $114m Cash at 31/03/2018: $3.8m* *Excluding total debt facilities of $35.0m. Drawn to date $18.6m

Page 2: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Processing Operations

Ore milled for the quarter totalled 72,183 tonnes at 1.48g/t for 3,430 ounces. The plant experienced significant downtime with a total of 31.5 days were lost for the period, principally relating to:

• An adverse weather event ‐ A total of 11 days were lost due to an extreme adverse weather event

• Plant operational issues – A total of 20.5 days were lost due to mill downtime

The site was impacted by a severe weather event that initially struck the site on 11 February 2018. Heavy rain continued over an extended period of time, impacting processing, supply and surface haulage operations as a result of damage to critical road infrastructure. Direct operational impacts resulted in 11 days of mill downtime, although material handling issues relating to wet feed stock persisted past this point, resulting in reduced feed rates for a further 3 days. An additional 20.5 days were lost to operational issues within the plant. These included, but were not limited to, electrical faults, mechanical faults, mechanical failures and blockages. The operational staff remain focussed on improving plant availability, with additional maintenance resources now deployed to site to assist in these endeavours. The focus of the specialised contractor will be to:

• correct any residual defects left over from the refurbishment process

• review and identify key areas for improvement for the plant (optimisation)

• review and strengthen the maintenance plans and requirements

Quarterly processing figures

1.00

1.10

1.20

1.30

1.40

1.50

1.60

1.70

1.80

1.90

2.00

-

10,000

20,000

30,000

40,000

50,000

60,000

70,000

Q Sep 17 Q Dec 17 Q Mar 18

Gra

de

(g/t

)

Ton

nes

Mill

ed

Processing

Tonnes Milled Grade (g/t)

Page 3: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Underground Mining Underground mining continued to progress well at Golden Eagle, with the capital decline development passing the second level (355 Level). Cross cut development on the 355 Level successfully intersected the main ore horizon, with ore drive development commenced prior to the end of the quarter. Ore development was completed on the first level (375 Level), with production drilling and initial ore production commencing during the reporting period. The first level (375) delivered pleasing results, with the main ore lode (Quartz‐Feldspar Lode, or QFL) returning consistency in both grade and geometry. To the north, ore development was extended past the defined limit of the resource model by an additional 53 metres due to grade extensions on the main mineralised lode surface. Following an internal review of the mine design, an additional ore development level (395 Level) above the 375 Level was incorporated into the mine plan. This level will be accessed from the north wall of the open pit and targets additional stoping ore that was previously excluded from the original mining model. Ultimately this re‐design will result in an increase to the planned mined ounces, although some ore production scheduled for the March 2018 quarter has been deferred until the June 2018 quarter as a result of the change. Emergency response training of site personnel was undertaken during the reporting period. Importantly for the stoping schedule, secondary egress for the underground mine was also established. A 3,500 metre underground drilling program has commenced, with good productivity rates achieved to date. The six week program targets the down plunge continuation to the Central Shoot, and will utilise a combination of diamond and underground reverse circulation drilling. A total of 933 metres was completed during the quarter, with samples now processed and submitted to the laboratory for assay.

Mine rescue training at the underground mine

Diamond drilling targeting the Central Shoot

Isometric view of the Golden Eagle underground

mine

Page 4: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Open Pit Mining Siberia open pit mining operations resumed in February, with the focus on the southern cut back of the Sandking

pit. Material movement has progressed well in this free digging oxide portion of the pit. The first significant in-pit

grade control event is planned for May, with ore production scheduled from that point forward.

Additional grade control drilling was conducted over the near surface laterite ores situated east of the pit. This

area will be targeted as a source of ore in early April, all of which sits outside of the larger open pit Reserve model.

Drilling outside of the immediate mining area has identified extensions to this mineralisation. This will be followed

up with some additional infill drilling. Recent metallurgical testing of the Siberia laterites indicates recoveries in

excess of 92% for this material.

Infill drilling on the Sandking low grade dump is planned for April.

PROJECT DEVELOPMENT UPDATE

Drilling operations recommenced in March, with the drilling contractor mobilising two drilling rigs to site. On start‐up, drilling crews were deployed to the Riverina deposit, with exploration works at Menzies. The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource estimate of 2.6Mt @ 2.5g/t Au for 205,000 ounces. It is one of several high priority drilling targets within the Company’s Davyhurst Project and is seen as the next open pit mining focus following on from Siberia. Drilling is designed to infill and upgrade the existing Mineral Resource in accordance with the JORC Code 2012. Opportunities exist to expand and extend the known resource into areas currently constrained by a lack of drilling coverage. An external consultant has been engaged to complete an updated Mineral Resource estimation in accordance with JORC Code 2012 of the Callion deposit, which is located approximately 13 km from the Davyhurst Mill and contains a Mineral Resource of 169,000 tonnes at 2.6g/t for 14,000 ounces. This process is well advanced, with a Resource update scheduled for the June 2018 quarter. This update will aim to quantify both the open pit resource and the larger underground resource which currently remains open at depth. Following on from the Resource update, a mining study will commenced aimed at quantifying both open pit and underground mining potential for this deposit. The Waihi Mineral Resource estimation update process will follow. The Waihi Complex, located approximately 3 kilometres from the Davyhurst Mill, has been identified as an area containing significant potential to provide high grade underground feed to complement the open pit.

EXPLORATION UPDATE During the quarter, the Company continued to progress the regional strategy, outlined below:

• Prioritise some 200+ prospects for drilling

• Prioritise early diamond drilling of prospects to identify mineralisation controls

• Acquire and compile detailed geophysical data

• Compile regional 1:25000 solid geology mapping

• Ongoing 1:5000 and 1:10000 geological project mapping for compilation

• Ongoing historic drilling and geochemical sampling data acquisition and validation

• Ongoing review of regolith and historical sampling efficacy

• Ongoing auger geochemistry acquisition

• Systematic pXRF and spectral data acquisition from all available archival material

Page 5: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

• Establish regional end of hole (EOH), top of fresh rock (TOFR), and base of transported cover

multi‐ element geochemistry

• Establish regional fresh rock spectral dataset for alteration analysis

• Complete structural and genetic model

The Company recently completed diamond tail drilling of the Lady Irene prospect immediately north of Menzies and has commencing drilling of three diamond holes into the known shoots at the historic Yunndaga prospect in Menzies, under the Joint Venture agreement with Intermin.

Diamond drilling at Lady Irene prospect, 2018

The multipurpose rig will then move to the Mount Ida area to complete single holes at the Gordon and Bombay prospects. A shift south to the Mulline project will follow, where holes are planned at Peachtree, Lady Gladys, the Mulline offset target, and at the Young Australia prospect. Upon completion, the drill rig will move south‐east to the Timber Flat area, where two holes will be drilled at the Little Wonder prospect, to establish mineralisation controls and assist targeting of very high grade repetitions to the known mineralisation. A further hole is planned south of Callion at the Gila prospect. Diamond drilling of the Siberia‐Keiths trend, including the Siberia‐Consols area, is planned but will utilise the diamond‐only drill rig as it becomes available from the Resource Development team.

CORPORATE Placement On 5 February 2018, the Company issued 87,500,000 shares to Hawke’s Point at a price of $0.20 per share, with corresponding 1 for 1 free attaching unlisted options to acquire shares in the Company (Options). The Options were issued in two tranches, with one half of the Options having an exercise price of $0.25 and the other half having an exercise price of $0.275, and an expiry date of 5 years after issue subject to an accelerated expiry date should certain objective conditions be met.

Page 6: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Completion of the Placement occurred on 2 February 2018, and total funds raised under the Placement amounted to $30.57 million (before costs). Rights Issue Following the Placement, the Company completed a Right Issue to existing shareholders at an issue price of $0.20 per New Share on the basis of 1 New Share for every 20 existing fully paid ordinary shares, together with a free attaching Option per New Share acquired. On 26 February 2018, the Company advised that it received valid applications under the Rights Issue for 11,247,806 New Shares from shareholders, leaving a shortfall of 24,676,464 shares and options (Shortfall Securities). In addition, the Company received additional applications from existing shareholders for a further 2,773,497 New Shares in accordance with section 2.9 of the prospectus dated 1 February 2018 (as supplemented by the supplementary prospectus dated 20 February 2018) (Prospectus). The Rights Issue was partially underwritten by Investmet Limited and 11,000,000 New Shares and 11,000,000 options were issued to the underwriter. A total of approximately $5.0 million has been raised under the Rights Issue and underwriting. The balance of the shortfall of approximately $2.0 million is available to place until 21 May 2018 GRES On 12 July 2017, the Company received a writ of summons for proceedings in the Supreme Court of Western Australia commenced by GR Engineering Services (GRES) in relation to the Davyhurst Gold Project refurbishment contract entered into by GRES and the Company on 22 September 2016. The Order made by the Supreme Court of Western Australia to wind up Eastern Goldfields was subsequently set aside and the winding up process terminated with the Company returned to its Directors (ASX announcement 17 August 2017). The Company provided further updates on the status of these proceedings on 24 and 25 January 2018. Investec Repayment During the quarter, $5 million was repaid to Investec Australia Limited. Re-instatement to Quotation Post the end of the quarter, on Tuesday 17 April 2018, the Company was reinstated to official quotation on ASX.

OUTLOOK Currently, the Company is moving towards steady state production based on treatment of existing low and medium grade surface stockpiles. The Company expects to ramp up production during the March quarter, based on the introduction of higher grade open pit feed from the Siberia Mining Centre and ore becoming available from the Golden Eagle underground operation. Investor and Media Enquiries

Michael Fotios Executive Chairman T: +61 8 6241 1888 E: [email protected]

Page 7: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Competent Person Statement The information in this report that relates to Exploration Results, Exploration Targets and the Sand King and Missouri Mineral Resources is based on information compiled under the supervision of Mr Michael Thomson, a former employee of Eastern Goldfields Limited, who is Member of the Australian Institute of Mining and Metallurgy. Mr Thomson has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been modified from the original announcement and, in the case of estimates of Mineral Resources, all material assumptions and technical parameters underpinning the estimates in the initial announcement continue to apply and have not materially changed.

The information in this report that relates to Mineral Resources (with the exception of the Sand King and Missouri Mineral Resources) is based on information compiled under the supervision of Mr Michael Thomson, a former employee of Eastern Goldfields Limited, who is Member of the Australian Institute of Mining and Metallurgy. Mr Thomson has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 and 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been modified from the original announcement and, in the case of estimates of Mineral Resources, all material assumptions and technical parameters underpinning the estimates in the initial announcement continue to apply and have not materially changed. This information was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported.

The information in this report that relates to Ore Reserves is based on information compiled by Mr Craig Mann, who is an independent mining engineering consultant and a full-time employee of Entech Pty Ltd, and has sufficient relevant experience to advise Eastern Goldfields Limited on matters relating to mine design, mine scheduling, mining methodology and mining costs. Mr Mann is satisfied that the information provided in this statement has been determined to a PFS level of accuracy, based on the data provided by Eastern Goldfields Limited. The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been modified from the original announcement and, in the case of estimates of Ore Reserves, all material assumptions and technical parameters underpinning the estimates in the initial announcement continue to apply and have not materially changed.

Forward Looking Statements

Eastern Goldfields Limited has prepared this announcement based on information available to it. No representation or

warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions

and conclusions contained in this announcement. To the maximum extent permitted by law, none of Eastern Goldfields

Limited, its directors, employees or agents, advisers, nor any other person accepts any liability, including, without limitation,

any liability arising from fault or negligence on the part of any of them or any other person, for any loss arising from the use

of this announcement or its contents or otherwise arising in connection with it. This announcement is not an offer, invitation,

solicitation or other recommendation with respect to the subscription for, purchase or sale of any security, and neither this

announcement nor anything in it shall form the basis of any contract or commitment whatsoever. This announcement may

contain forward looking statements that are subject to risk factors associated with gold exploration, mining and production

businesses. It is believed that the expectations reflected in these statements are reasonable but they may be affected by a

variety of variables and changes in underlying assumptions which could cause actual results or trends to differ materially,

including but not limited to price fluctuations, actual demand, currency fluctuations, drilling and production results, reserve

estimations, loss of market, industry competition, environmental risks, physical risks, legislative, fiscal and regulatory

changes, economic and financial market conditions in various countries and regions, political risks, project delay or

advancement, approvals and cost estimates.

Page 8: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Table 2: EGS Mineral Resource Statement

1. All Resources listed above with the exception of the Missouri and Sand King Resources were prepared and first disclosed under the JORC Code 2004 (refer to ASX release “Swan Gold Prospectus”, 13/2/2013). It has not been updated since to comply with JORC Code 2012 on the basis that the information has not materially changed since it was last reported. 2. The Missouri and Sand King Mineral Resources has been updated and complies with all relevant aspects of the JORC code 2012. 3. The above table contains rounding errors

Table 3: EGS Mineral Reserve Statement

Reserve Proven Probable Total

('000t) (g/t Au) ('000t) (g/t Au) ('000t) (g/t Au) ('000oz.)

Missouri - Dec 2016 - - 1,205 2.2 1,205 2.2 85

Sand King – Feb 217 - - 8,20 2.5 820 2.5 65

Combined Total - - 2,025 2.3 2,025 2.3 150

('000t) (g/t Au) ('000t) (g/t Au) ('000t) (g/t Au) ('000t) (g/t Au) ('000oz.)

GOLDEN EAGLE 0 0.0 345 2.5 311 2.6 656 2.5 54

LIGHTS OF ISRAEL UNDERGROUND 0 0.0 74 4.3 180 4.2 254 4.2 35

MAKAI SHOOT 0 0.0 1,985 2.0 153 1.7 2,138 2.0 136

WAIHI 0 0.0 805 2.4 109 2.4 914 2.4 71

Central Davyhurst Subtotal 0 0.0 3,200 2.2 800 2.6 3,962 2.3 296

LADY GLADYS 0 0.0 1,858 1.9 190 2.4 2,048 1.9 128

RIVERINA AREA 0 0.0 941 2.4 1,644 2.5 2,585 2.5 205

FOREHAND 0 0.0 386 1.7 436 1.9 822 1.8 48

SILVER TONGUE 0 0.0 155 2.7 19 1.3 174 2.5 14

SUNRAYSIA 0 0.0 175 2.1 318 2.0 493 2.0 32

Riverina-Mulline Subtotal 0 0.0 3,515 2.1 2,607 2.3 6,122 2.2 427

SAND KING 0 0.0 1,773 3.3 680 3.7 2,453 3.4 272

MISSOURI 0 0.0 2,022 3.0 409 2.6 2,431 2.9 227

PALMERSTON / CAMPERDOWN 0 0.0 118 2.3 174 2.4 292 2.4 22

BERWICK MOREING 0 0.0 0 0.0 50 2.3 50 2.3 4

BLACK RABBIT 0 0.0 0 0.0 434 3.5 434 3.5 49

THIEL WELL 0 0.0 0 0.0 18 6.0 18 6.0 3

Siberia Subtotal 0 0.0 3,913 3.1 1,765 3.2 5,678 3.1 577

CALLION 0 0.0 86 2.8 83 2.3 169 2.6 14

Callion Subtotal 0 0.0 86 2.8 83 2.3 169 2.6 14

FEDERAL FLAG 32 2.0 112 1.8 238 2.5 382 2.3 28

SALMON GUMS 0 0.0 199 2.8 108 2.9 307 2.8 28

WALHALLA 0 0.0 448 1.8 216 1.4 664 1.7 36

WALHALLA NORTH 0 0.0 94 2.4 13 3.0 107 2.5 9

MT BANJO 0 0.0 109 2.3 126 1.4 235 1.8 14

MACEDON 0 0.0 0 0.0 186 1.8 186 1.8 11

Walhalla Subtotal 32 2.0 962 2.1 887 2.0 1,881 2.1 126

IGUANA 0 0.0 690 2.1 2,032 2.0 2,722 2.0 177

LIZARD 106 4.0 75 3.7 13 2.8 194 3.8 24

Lady Ida Subtotal 106 4.0 765 2.3 2,045 2.0 2,916 2.1 201

Davyhurst Total 138 3.5 12,441 2.5 8,187 2.4 20,728 2.4 1,641

BALDOCK 0 0.0 136 18.6 0 0.0 136 18.6 81

BALDOCK STH 0 0.0 0 0.0 0 0.0 0 0.0 0

METEOR 0 0.0 0 0.0 143 9.3 143 9.3 43

WHINNEN 0 0.0 0 0.0 39 13.3 39 13.3 17

Mount Ida Total 0 0.0 136 18.6 182 10.2 318 13.8 141

Combined Total 138 3.5 12,577 2.7 8,369 2.6 21,046 2.6 1,782

MEASURED INDICATED INFERRED TOTAL MATERIALPROJECT

Page 9: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Appendix 1: Tenement Listing and Movements During the Quarter

Tenement Status Mineral Field Beginning % End % Note

E16/0337 Granted 16 - Coolgardie 100 100

E16/0344 Granted 16 - Coolgardie 75 75 1

E16/0347 Dead 16 - Coolgardie 100 0

E16/0456 Granted 16 – Coolgardie 100 100

E16/0473 Granted 16 – Coolgardie 100 100

E16/0474 Granted 16 – Coolgardie 100 100

E16/0475 Granted 16 – Coolgardie 100 100

E16/0480 Granted 16 – Coolgardie 100 100

E16/0482 Granted 16 – Coolgardie 100 100

E16/0483 Granted 16 – Coolgardie 100 100

E16/0484 Granted 16 – Coolgardie 100 100

E16/0486 Granted 16 – Coolgardie 100 100

E16/0487 Granted 16 – Coolgardie 100 100

E24/0203 Granted 24 - Broad Arrow 100 100

E29/0419 Dead 29 – North Coolgardie 100 0 7

E29/0640 Granted 29 – North Coolgardie 100 100 2

E29/0641 Granted 29 – North Coolgardie 100 100 2

E29/0889 Granted 29 – North Coolgardie 100 100 4

E29/0895 Granted 29 – North Coolgardie 100 100

E29/0922 Dead 29 – North Coolgardie 100 0 7

E29/0955 Granted 29 – North Coolgardie 100 100

E29/0964 Granted 29 – North Coolgardie 100 100

E29/0966 Granted 29 – North Coolgardie 100 100 7

E29/0984 Granted 29 – North Coolgardie 100 100 7

E30/0333 Granted 30 – North Coolgardie 100 100 4

E30/0334 Granted 30 – North Coolgardie 100 100

E30/0335 Granted 30 – North Coolgardie 100 100

E30/0336 Granted 30 – North Coolgardie 100 100

E30/0338 Granted 30 – North Coolgardie 100 100

E30/0449 Granted 30 – North Coolgardie 100 100

E30/0454 Granted 30 – North Coolgardie 100 100

E30/0468 Granted 30 – North Coolgardie 100 100

L15/0224 Granted 15 – Coolgardie 100 100

L16/0058 Granted 16 – Coolgardie 100 100

L16/0062 Granted 16 – Coolgardie 100 100

L16/0072 Granted 16 – Coolgardie 100 100

L16/0073 Granted 16 – Coolgardie 100 100

L16/0103 Granted 16 – Coolgardie 100 100

L24/0085 Granted 24 – Broad Arrow 100 100

L24/0101 Granted 24 – Broad Arrow 100 100

L24/0115 Granted 24 – Broad Arrow 100 100

L24/0123 Granted 24 – Broad Arrow 100 100

L24/0124 Granted 24 – Broad Arrow 100 100

Page 10: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

L24/0170 Granted 24 – Broad Arrow 100 100

L24/0174 Granted 24 – Broad Arrow 100 100

L24/0188 Granted 24 – Broad Arrow 100 100

L24/0189 Granted 24 – Broad Arrow 100 100

L24/0224 Granted 24 – Broad Arrow 100 100

L24/0232 Granted 24 – Broad Arrow 100 100

L24/0233 Granted 24 – Broad Arrow 100 100

L29/0042 Granted 29 – North Coolgardie 100 100 7

L29/0043 Granted 29 – North Coolgardie 100 100 7

L29/0044 Granted 29 – North Coolgardie 100 100 7

L29/0074 Granted 29 – North Coolgardie 100 100

L29/0109 Granted 29 – North Coolgardie 100 100 7

L30/0035 Granted 30 – North Coolgardie 100 100

L30/0037 Granted 30 – North Coolgardie 100 100

L30/0066 Granted 30 – North Coolgardie 0 100

M16/0262 Granted 16 - Coolgardie 100 100

M16/0263 Granted 16 - Coolgardie 100 100

M16/0264 Granted 16 - Coolgardie 100 100

M16/0268 Granted 16 - Coolgardie 100 100

M16/0470 Granted 16 - Coolgardie 100 100

M24/0039 Granted 24 - Broad Arrow 100 100 5

M24/0115 Granted 24 - Broad Arrow 100 100

M24/0159 Granted 24 - Broad Arrow 100 100

M24/0208 Granted 24 - Broad Arrow 100 100

M24/0376 Granted 24 - Broad Arrow 100 100

M24/0634 Granted 24 - Broad Arrow 100 100 4

M24/0660 Granted 24 - Broad Arrow 100 100 4

M24/0663 Granted 24 - Broad Arrow 100 100 4

M24/0664 Granted 24 - Broad Arrow 100 100 4

M24/0665 Granted 24 - Broad Arrow 100 100 6

M24/0683 Granted 24 - Broad Arrow 100 100 4

M24/0686 Granted 24 - Broad Arrow 100 100 4

M24/0757 Granted 24 - Broad Arrow 100 100 4

M24/0772 Granted 24 - Broad Arrow 100 100 4

M24/0797 Granted 24 - Broad Arrow 100 100 4

M24/0845 Granted 24 - Broad Arrow 100 100 4

M24/0846 Granted 24 - Broad Arrow 100 100 4

M24/0847 Granted 24 - Broad Arrow 100 100 4

M24/0848 Granted 24 - Broad Arrow 100 100 4

M24/0915 Granted 24 - Broad Arrow 100 100 4

M24/0916 Granted 24 - Broad Arrow 100 100 4

M24/0960 Granted 24 - Broad Arrow 100 100

M29/0002 Granted 29 - North Coolgardie 100 100 2

M29/0014 Granted 29 - North Coolgardie 100 100 7

M29/0088 Granted 29 - North Coolgardie 100 100 7

M29/0153 Granted 29 - North Coolgardie 100 100 7

Page 11: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

M29/0154 Granted 29 - North Coolgardie 100 100 7

M29/0165 Granted 29 - North Coolgardie 100 100 2

M29/0184 Granted 29 - North Coolgardie 100 100 7

M29/0212 Granted 29 - North Coolgardie 100 100 7

M29/0410 Granted 29 - North Coolgardie 100 100 7

M29/0420 Granted 29 - North Coolgardie 100 100 7

M29/0422 Granted 29 - North Coolgardie 100 100 2

M30/0102 Granted 30 - North Coolgardie 100 100

M30/0103 Granted 30 - North Coolgardie 100 100

M30/0111 Granted 30 - North Coolgardie 100 100

M30/0123 Granted 30 - North Coolgardie 100 100

M30/0126 Granted 30 - North Coolgardie 100 100

M30/0127 Granted 30 - North Coolgardie 100 100 4

M30/0133 Granted 30 - North Coolgardie 100 100 4

M30/0157 Granted 30 - North Coolgardie 100 100 4

M30/0182 Granted 30 - North Coolgardie 100 100 4

M30/0187 Granted 30 - North Coolgardie 100 100

M30/0253 Granted 30 - North Coolgardie 100 100

M30/0255 Granted 30 - North Coolgardie 100 100

M30/0256 Granted 30 - North Coolgardie 100 100

P16/2921 Granted 16 - Coolgardie 100 100

P16/2922 Granted 16 - Coolgardie 100 100

P24/4395 Granted 24 - Broad Arrow 100 100 4

P24/4396 Granted 24 - Broad Arrow 100 100 4

P24/4400 Granted 24 - Broad Arrow 100 100 4

P24/4401 Granted 24 - Broad Arrow 100 100 4

P24/4402 Granted 24 - Broad Arrow 100 100 4

P24/4403 Granted 24 - Broad Arrow 100 100 4

P24/4750 Granted 24 - Broad Arrow 100 100

P24/4751 Granted 24 - Broad Arrow 100 100

P24/4754 Granted 24 - Broad Arrow 100 100

P24/5073 Granted 24 - Broad Arrow 100 100

P24/5074 Granted 24 - Broad Arrow 100 100

P24/5075 Granted 24 - Broad Arrow 100 100

P29/2153 Granted 29 - North Coolgardie 100 100 7

P29/2154 Granted 29 - North Coolgardie 100 100 7

P29/2155 Granted 29 - North Coolgardie 100 100 7

P29/2156 Granted 29 - North Coolgardie 100 100 7

P29/2251 Granted 29 - North Coolgardie 100 100 7

P29/2252 Granted 29 - North Coolgardie 100 100 7

P29/2253 Granted 29 - North Coolgardie 100 100 7

P29/2254 Granted 29 - North Coolgardie 100 100 7

P29/2268 Dead 29 - North Coolgardie 100 0 7

P29/2269 Dead 29 - North Coolgardie 100 0 7

P29/2286 Dead 29 - North Coolgardie 100 0 7

P29/2287 Dead 29 - North Coolgardie 100 0 7

Page 12: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

P29/2288 Dead 29 - North Coolgardie 100 0 7

P29/2289 Dead 29 - North Coolgardie 100 0 7

P29/2290 Dead 29 - North Coolgardie 100 0 7

P29/2307 Dead 29 - North Coolgardie 100 0 7

P29/2308 Dead 29 - North Coolgardie 100 0 7

P29/2310 Dead 29 - North Coolgardie 100 0 2

P29/2312 Dead 29 - North Coolgardie 100 0 2

P29/2313 Dead 29 - North Coolgardie 100 0 2

P29/2314 Dead 29 - North Coolgardie 100 0 2

P29/2319 Granted 29 - North Coolgardie 100 100 2

P29/2320 Granted 29 - North Coolgardie 100 100 2

P29/2321 Granted 29 - North Coolgardie 100 100 2

P29/2322 Granted 29 - North Coolgardie 100 100 2

P29/2323 Granted 29 - North Coolgardie 100 100 2

P29/2326 Granted 29 - North Coolgardie 100 100 2

P29/2328 Granted 29 - North Coolgardie 100 100 2

P29/2251 Granted 29 - North Coolgardie 100 100 7

P29/2344 Granted 29 - North Coolgardie 100 100 7

P29/2345 Granted 29 - North Coolgardie 100 100 7

P30/1074 Dead 30 - North Coolgardie 100 0 4

P30/1107 Granted 30 - North Coolgardie 100 100

P30/1108 Granted 30 - North Coolgardie 100 100

P30/1109 Granted 30 - North Coolgardie 100 100

P30/1110 Granted 30 - North Coolgardie 100 100 4

P30/1116 Granted 30 - North Coolgardie 100 100 4

P30/1117 Granted 30 - North Coolgardie 100 100 4

P30/1118 Granted 30 - North Coolgardie 100 100 4

P30/1122 Granted 30 - North Coolgardie 100 100 4

Notes 1 EGS holds a % interest in gold rights 2 100% interest in iron rights held by 3rd party 3 100% interest in iron and nickel rights held by 3rd party 4 100% interest in nickel rights held by 3rd party 5 100% interest in gold rights held by EGS 6 90% interest in all mineral rights barr nickel held by EGS 7 Interest being earned in

Page 13: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 1

+Rule 5.5

Appendix 5B

Mining exploration entity and oil and gas exploration entity quarterly report

Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/13, 01/09/16

Name of entity

Eastern Goldfields Limited

ABN Quarter ended (“current quarter”)

69 100 038 266 31 March 2018

Consolidated statement of cash flows Current quarter $A’000

Year to date

(9 months) $A’000

1. Cash flows from operating activities

2,169 5,827 1.1 Receipts from customers

1.2 Payments for

(1,408) (3,909) (a) exploration & evaluation

(b) development (2,394) (9,126)

(c) production (incl. plant repair) (15,601) (18,260)

(d) staff costs (incl. plant repair) (1,629) (4,078)

(e) administration and corporate costs (1,978) (3,343)

1.3 Dividends received (see note 3) - -

1.4 Interest received - -

1.5 Interest and other costs of finance paid (535) (834)

1.6 Income taxes paid - -

1.7 Research and development refunds - -

1.8 GST refund received / Other 1,442 4,303

1.9 Net cash from / (used in) operating activities

(19,933) (29,417)

2. Cash flows from investing activities

- -

2.1 Payments to acquire:

(a) property, plant and equipment

(b) tenements (see item 10) - -

(c) investments - -

(d) other non-current assets - -

Page 14: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 2

Consolidated statement of cash flows Current quarter $A’000

Year to date

(9 months) $A’000

2.2 Proceeds from the disposal of:

- - (a) property, plant and equipment

(b) tenements (see item 10) - -

(c) investments - -

(d) other non-current assets - -

2.3 Cash flows from loans to other entities - -

2.4 Dividends received (see note 3) - -

2.5 Other (provide details if material) - -

2.6 Net cash from / (used in) investing activities

- -

3. Cash flows from financing activities

29,952 29,952 3.1 Proceeds from issues of shares

3.2 Proceeds from issue of convertible notes - -

3.3 Proceeds from exercise of share options 210 356

3.4 Transaction costs related to issues of shares, convertible notes or options

1,630 1,630

3.5 Proceeds from borrowings 3,025 13,148

3.6 Repayment of borrowings (7,918) (8,636)

3.7 Transaction costs related to loans and borrowings

- -

3.8 Dividends paid - -

3.9 Other (provide details if material) - -

3.10 Net cash from / (used in) financing activities

7,886 9,550

4. Net increase / (decrease) in cash and cash equivalents for the period

80 13 4.1 Cash and cash equivalents at beginning of

period

4.2 Net cash from / (used in) operating activities (item 1.9 above)

(19,933) (29,417)

4.3 Net cash from / (used in) investing activities (item 2.6 above)

- -

4.4 Net cash from / (used in) financing activities (item 3.10 above)

23,639 33,190

Page 15: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 3

Consolidated statement of cash flows Current quarter $A’000

Year to date

(9 months) $A’000

4.5 Effect of movement in exchange rates on cash held

- -

4.6 Cash and cash equivalents at end of period

Note: Cash and Cash Equivalents excludes gold in transit and held for refining of $540,728, estimated gold in circuit of $1,100,000 and market value of available for sale financial assets of $5,008,517 as at 31 March 2018.

3,786 3,786

5. Reconciliation of cash and cash equivalents at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts

Current quarter $A’000

Previous quarter $A’000

5.1 Bank balances 3,786 80

5.2 Call deposits - -

5.3 Bank overdrafts - -

5.4 Other (provide details) - -

5.5 Cash and cash equivalents at end of quarter

Note: Cash and Cash Equivalents excludes gold in transit and held for refining of $540,728, estimated gold in circuit of $1,100,000 and market value of available for sale financial assets of $5,008,517 as at 31 March 2018.

3,786 80

6. Payments to directors of the entity and their associates Current quarter $A'000

6.1 Aggregate amount of payments to these parties included in item 1.2 266

6.2 Aggregate amount of cash flow from loans to these parties included in item 2.3

6.3 Include below any explanation necessary to understand the transactions included in items 6.1 and 6.2

• Directors fees

• Payments to entities associated with director Mr Michael Fotios, which are on normal commercial terms and relate to management, staff, office and drilling expenses.

Page 16: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 4

7. Payments to related entities of the entity and their associates

Current quarter $A'000

7.1 Aggregate amount of payments to these parties included in item 1.2 257

7.2 Aggregate amount of cash flow from loans to these parties included in item 2.3

-

7.3 Include below any explanation necessary to understand the transactions included in items 7.1 and 7.2

All payments to related entities and associates are on normal commercial terms. The payments relate to management, staff, office and drilling expenses.

8. Financing facilities available Add notes as necessary for an understanding of the position

Total facility amount at quarter end

$A’000

Amount drawn at quarter end

$A’000

8.1 Loan facilities 20,000 10,000

8.2 Credit standby arrangements 15,000 6,188

8.3 Other (please specify) - -

8.4 Include below a description of each facility above, including the lender, interest rate and whether it is secured or unsecured. If any additional facilities have been entered into or are proposed to be entered into after quarter end, include details of those facilities as well.

Loan facilities: Investec Australia Limited, secured

Credit standby facilities: Investmet and other related entities, unsecured. Interest rate 3% above BBR whilst secured, 19% whilst unsecured.

9. Estimated cash outflows for next quarter $A’000

9.1 Exploration and evaluation 1,000

9.2 Development 4,500

9.3 Production 9,000

9.4 Staff costs 1,000

9.5 Administration and corporate costs 700

9.6 Other (provide details if material) 100

9.7 Total estimated cash outflows 16,300

Page 17: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 5

10. Changes in tenements (items 2.1(b) and 2.2(b) above)

Tenement reference and location

Nature of interest Interest at beginning of quarter

Interest at end of quarter

10.1 Interests in mining tenements and petroleum tenements lapsed, relinquished or reduced

E16/0347

E29/0419

E29/0922

P29/2268

P29/2269

P29/2286

P29/2287

P29/2288

P29/2289

P29/2290

P29/2307

P29/2308

P29/2310

P29/2312

P29/2313

P29/2314

P30/1074

Lapsed 100% 0%

10.2 Interests in mining tenements and petroleum tenements acquired or increased

L30/0066

Granted

0%

100%

Compliance statement

1 This statement has been prepared in accordance with accounting standards and policies which

comply with Listing Rule 19.11A.

2 This statement gives a true and fair view of the matters disclosed.

30 April 2018

Sign here: ............................................................ Date: ............................................. (Director/Company secretary)

MICHAEL FOTIOS

Print name: .........................................................

Page 18: Activities Report for Quarter ended 31 March 2018€¦ · The Riverina Project area is located approximately 48 kilometres north of the Davyhurst Mill, and has a current Mineral Resource

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 6

Notes

1. The quarterly report provides a basis for informing the market how the entity’s activities have been financed for the past quarter and the effect on its cash position. An entity that wishes to disclose additional information is encouraged to do so, in a note or notes included in or attached to this report.

2. If this quarterly report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly report has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.

3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.