30

Click here to load reader

ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

Embed Size (px)

Citation preview

Page 1: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

ACT CIVIL & ADMINISTRATIVE TRIBUNAL

MS D v ICON DISTRIBUTION INVESTMENTS LTD (ABN 80373025224) AND JEMENA NETWORKS (ACT) PTY LTD (ABN 24 008 552 663) TRADING AS ACTEWAGL DISTRIBUTION (ABN 76670568688) (Energy and Water) [2017] ACAT 43

EW 518/2016

Catchwords: ENERGY AND WATER - Feed-in tariff – solar PV system generating electricity and feeding-in to the grid – requirement for customer to have safety inspection of system after five years – customer hardship – request for deferment of safety inspection – systemic issues discussed.

Legislation cited: ACT Civil and Administrative Tribunal Act 2008 s 54Electricity Feed-in (Renewable Energy Premium) Act 2008Utilities Act 2000 pt 12Utilities (Technical Regulation) Act 2014

SubordinateLegislation cited: ActewAGL Electricity Service and Installation Rules

Utilities (Consumer Protection Code) Determination 2012Utilities (Electricity Feed-in Code) Determination 2015Utilities (Electricity Service and Installation Rules Code) Determination 2013

Tribunal: Senior Member P SutherlandMember R Vassarotti

Date of Orders: 22 May 2017Date of Reasons for Decision: 9 June 2017

Page 2: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

AUSTRALIAN CAPITAL TERRITORY )CIVIL & ADMINISTRATIVE TRIBUNAL )

BETWEEN:

MS. DApplicant

AND:

ICON DISTRIBUTION INVESTMENTS LTD (ABN 80373025224) AND JEMENA NETWORKS (ACT) PTY LTD

(ABN 24 008 552 663) TRADING AS ACTEWAGL DISTRIBUTION (ABN 76670568688)

Respondent

TRIBUNAL: Senior Member P SutherlandMember R Vassarotti

DATE: 22 May 2017

ORDER

The Tribunal orders that:

1. The name and address of the Applicant not be published.

2. That the complaint application be dismissed.

3. If the Applicant has not had her solar system inverter tested by Friday

16 June 2017, the Respondent is authorised to disconnect the solar system.

………………Signed………..Senior Member P Sutherland

Page 3: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

REASONS FOR DECISION

1. This application was made as a complaint application under Part 12 of the Utilities

Act 2000 (the Utilities Act) by the applicant, Ms D, on 24 November 2016. The

applicant made a complaint that she could not afford to pay for a safety test on

her solar PV system and that the respondent, ActewAGL Distribution (AAD),

had failed to agree to her request that the test be deferred to June 2017. This

request, which was originally made to AAD in mid-2016, was refused on the

basis that safety issues required the test to be completed.

2. The applicant’s inquiry was originally received by the hardship area of ACAT

Energy and Water (ACAT E&W), however, given the complaint did not relate

to electricity supply for her domestic use, it was referred to the Energy and

Water Complaints area of ACAT E&W on 24 November 2016.

3. On 25 November 2016, ACAT E&W referred the complaint to the respondent

asking for a response to the complaint and for provision of relevant documents.

On 9 December 2016, the respondent advised that it was unable to grant an

extension of time until the end of June 2017 for testing of the solar panel

installation at the applicant’s property. The respondent noted that a test every

five years was a requirement of the Utilities (Electrical Service and Installation

Rules Code) Determination 2013 (ES&I Rules Code), which is a technical

code under the Utilities (Technical Regulation) Act 2014.

4. ACAT E&W was not satisfied with this response and, on 31 January 2017, it

approached the Technical Regulator for further information. On 2 February

2017, Mr Simon Grice, Senior Manager, Utilities Technical Regulation, Access

Canberra replied by email confirming that safety testing was necessary for the

inverter within a solar PV generating system. ACAT E&W conducted further

correspondence with the Technical Regulator about the legislative framework

and possible inconsistencies in that framework and ultimately was satisfied that

an accurate and comprehensive response had been given in relation to the

applicant’s complaint.

5. On 23 February 2017, ACAT E&W forwarded the response and associated written

material to the applicant and expressed the opinion that periodic safety testing

2

Page 4: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

of PV solar systems was a necessary safety requirement and that further

investigation of the complaint was not warranted. ACAT E&W advised that it

proposed to close the complaint and asked the applicant to respond in writing by

9 March 2017 if she did not agree with this course of action.

6. On 9 March 2017 and again on 11 April 2017, the applicant forwarded emails

objecting to closure of the complaint and included in these emails considerable

detail about her financial hardship and inability to pay the cost of the safety test.

As these emails contained no additional information on the substantive issue of

testing for safety, ACAT E&W considered closing the complaint without a

hearing, utilising the procedure in section 54 of the ACT Civil and

Administrative Tribunal Act 2008 (the ACAT Act).

7. Rather than proceed under section 54, the Tribunal listed the application for

hearing on 22 May 2017 and a panel comprising Senior Member Peter

Sutherland and Member Rebecca Vassarotti (the Tribunal) conducted the

hearing.

8. After hearing evidence from Mr Grice and submissions by the applicant and the

respondent, the Tribunal made an oral decision to dismiss the complaint and

authorised the respondent to disconnect the solar PV system if the applicant had

not had the system tested by Friday, 16 June 2017. The Tribunal advised the

parties that written reasons for decision would be issued within two weeks.

9. At the request of the applicant, the Tribunal made an order that her name and

address should not be published.

Background to the complaint

10. The applicant contacted ACAT E&W on Thursday 24 November 2016 in relation

to correspondence between herself and AAD regarding their notification of a

requirement that she pay for a safety test on her solar PV inverter.

11. This contact had been preceded by a number of communications from AAD

regarding a requirement that she organise the testing of her PV inverter, which

was part of her roof top solar panel installation. She reported that, throughout

2016, AAD had contacted her regarding a contract requirement for her to test

3

Page 5: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

equipment every five years by a qualified and licensed electrician who holds a

Clean Energy Council accreditation.

12. The applicant is known to ACAT E&W, having previously been a hardship client

of a predecessor agency, the Essential Services Consumer Council (ESCC). She

had exited from the ESCC hardship scheme before 2009, after stabilising her

electricity use and clearing her electricity-related debts.

13. With the assistance of an inheritance, the applicant purchased a solar panel system

in 2010, and took advantage of the original ACT Government feed-in tariff

scheme under the Electricity Feed-in (Renewable Energy Premium) Act 2008.

Under this Feed-in Tariff scheme (FiT scheme), residential customers with

solar PV systems on their roof tops were entitled to a payment of 50.05 cents

per kWh for all electricity generated by their PV system and fed-in to the

ActewAGL grid. The entitlement to this payment continues for 20 years from

the date of installation, however the amount of the FiT payment was reduced to

45.7 cents in July 2011 and the FiT scheme was closed to new entrants on 30

June 2012. The FiT payment is delivered by way of a credit on the customer’s

account with their electricity retailer and is typically between $100 and $500

each quarterly bill depending on the season and the number of solar PV panels

on the roof.

14. The applicant reported that she had not previously been aware of a requirement to

have her solar PV inverter tested, did not understand why this was required

given she had invested in a high quality solar system, and she was not in a

position to pay for this testing. As such, she had not actioned the request for

testing when originally received (sometime in 2016). Due to her financial

position and a range of unplanned expenses, this additional cost of about $200

was still impossible for her to outlay and as such she requested an extension of

time to pay for a period until the end of June 2017.

15. In her documentation, the applicant provided detailed evidence of her financial

hardship. In response, AAD agreed to a 21 day extension and at this point the

applicant contacted ACAT E&W for assistance as she submitted that she was

unable to meet this request because of financial hardship.

4

Page 6: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

16. AAD was contacted on 25 November 2016 to inform them that a complaint had

been received and was being investigated. This advice provided details of the

complaint, including:

(a) The customer has solar panels installed in the property.

(b) The customer had received a letter stating that the system must be tested

every five years (with the system having been installed for six years).

(c) The customer is experiencing financial hardship which means that she was

unable to afford the testing.

(d) AAD is threatening to disconnect the installation unless testing occurred.

(e) AAD had provided a 21 day extension, which the customer believes does

not take into account her financial hardship.

17. On 9 December 2016, AAD provided an email response to the complaint which

cited requirements outlined in the ES&I Rules Code that require owners of solar

panel installation to ensure the PV system inverter is tested every five years. It

noted that this Code is a technical code under the Utilities (Technical

Regulation) Act 2014 and this requirement was part of the obligations and

procedures for the safe, reliable and efficient connection of electrical

installations to an electrical network. AAD noted their requirements including

the need to report to the Utilities Technical Regulation Team (UTRT) on

actions to meet their obligations and their view that the granting of the requested

extension could pose a safety risk to ActewAGL employees and the public.

18. In response to this information, ACAT E&W entered into correspondence with Mr

Simon Grice, Senior Manager at UTRT who was representing the Technical

Regulator. Mr Grice tendered further information regarding the requirement to

test PV system inverters every five years to ensure they are functioning

correcting and will not cause a safety hazard for maintenance staff. Additional

information was provided including the ES&I Rules Code. Through the process

of inquiry, it was established that this Code contained a drafting error in clause

6.17(3) and identified that that the ActewAGL Electricity Service and

Installation Rules (the AAD ES&I Rules) clause 5.5.1(2) correctly reflects the

intent of the Code regarding periodic testing/verification requirement, noting

that safety testing/verification would be relevant to any size of generator. It

5

Page 7: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

noted that AAD is required to gain approval of their Rules by the Director-

General (the Technical Regulator). He noted that the Technical Regulator had

approved the Service and Installation Rules as they reflected the Code intent. He

noted that information regarding the requirement for on-going maintenance

requirements of PV installations is provided on the ActewAGL website, and

that the connection agreement that owners are required to sign includes this

information at clause 5.1a and 8.2a. Mr Grice informed ACAT E&W that the

drafting error contained within the ES&I Rules Code will be corrected as part of

a Code update process.

19. ACAT E&W also engaged with AAD regarding the complaint as part of the

investigation who provided further information regarding the size of the

applicant’s solar system, which they confirmed was a system under 30 kWA.

20. Following inquiries, ACAT E&W contacted the applicant on 23 February 2017

signalling an intent to close the complaint given that the Technical Regulator

had confirmed the need for the periodic testing/verification requirements to

protect staff and network customers and his acknowledgement that, while there

was a drafting error in the Code that created some confusion, there was a clear

intention to require testing.

21. On 9 March 2017, the applicant contacted ACAT E&W to express her

disagreement with the move to close to the matter due to her lack of clarity

regarding the size of her system and, if this size system was covered by the

regime, her concerns about the timing of notice that AAD had provided a

customer on a low income and in financial hardship to meet the testing

requirement, the inability of AAD to respond adequately to issue of financial

hardship, and the impact of disconnecting the solar PV installation which would

exacerbate her financial hardship.

The Legislative Framework

22. ACAT has power under section 54 of the ACAT Act to dismiss an application

without holding a hearing (see Attachment A). If it proposes not to hold a

hearing, ACAT must give the parties notice of this intention and must take into

consideration any representations made by a party within 21 days (or a shorter

6

Page 8: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

period set by ACAT). ACAT may then decide not to hold a hearing if it has

taken into consideration the representation by parties, if it has sufficient

information to make an informed decision, and if it is in the public interest not

to hold a hearing.

23. ACAT E&W has jurisdiction to receive a complaint application in respect of a

feed-in tariff dispute between a customer and a distributor under item 2, Table

172 in Part 12 of the Utilities Act 2000 and section 4.4 of the Electricity Feed-in

Code incorporated in the Utilities (Electricity Feed-in Code) Determination

2015 (see Attachment A). The applicant is a consumer who may be affected by

a possible contravention by a utility of an industry code dealing with utility

service standards.

24. Rule 6.17 of the Utilities (Electrical Service and Installation Rules Code)

Determination 2013 (ES&I Rules Code) concerns ‘Embedded Generation’.

Rule 6.17(3) states:

(3) ES&I Rules must set requirements for all protection measures applying to an embedded generating unit greater than 30kVA to be tested by persons qualified and accredited by the electricity distributor:

(a) when the embedded generating unit is installed and commissioned, before connecting to a electricity distributor’s electricity network; and

(b) at a minimum of every 5 years after connecting to the electricity distributor’s electricity network.

7

Page 9: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

25. The ActewAGL Electricity Service and Installation Rules are made by AAD in

compliance with the ES&I Rules Code. Clause 5.5.1(2) of these Rules states:

(2) Testing

Protection measures applying to an embedded generating unit are to be

tested by qualified persons:

when the embedded generating unit is installed and commissioned,

before connecting to a utility’s network; and

at a minimum of every 5 years after connecting to the utility’s network.

The hearing of the complaint application

26. ACAT E&W initially considered not hearing the application under section 54 of

the ACAT Act, as it had sufficient information to make an informed decision

about the application. However, on reflection, ACAT E&W decided that there

was a significant public interest in holding a public hearing on several grounds:

(a) The applicant was indicating a strong desire to voice her concerns.

(b) There are thousands of solar roof top PV systems in the ACT and issues of

hardship around safety testing and failure of inverters are likely to arise

with some frequency over the next 14 years of the FiT scheme.

(c) Consideration of hardship issues in written reasons for decision may assist

in the development of appropriate hardship policies and contribute to

public awareness of the need for, and cost of, PV solar system testing and

maintenance.

27. The hearing of the complaint application was conducted on the morning of

Monday 22 May 2017. The applicant appeared in person, accompanied by a

support worker from CARE Financial Counselling Service. The respondent was

represented by Ms Sharnie Truesdale, ActewAGL Legal Counsel, and

Ms Joanne Hourigan, AAD Contact Centre Manager, was also present and gave

evidence.

8

Page 10: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

28. Mr Simon Grice, Senior Manager, Utilities Technical Regulation, Access

Canberra attended as a technical witness speaking on behalf of the Technical

Regulator. Mr Grice made the following observations:

(a) PV inverter testing is necessary to ensure the safety of electricity workers

on the network; a faulty inverter may lead to the connection to the grid

becoming live. Testing is also a matter of public safety and may be of

benefit to the customer through detection of a faulty system which is not

delivering electricity to the grid.

(b) South Australia and the Northern Territory require testing every five years

and Victoria every three years. New South Wales does not specify a

specific period, however testing is required under relevant Standards.

(c) Testing of solar PV inverters is carried out by electricians accredited by an

industry body, the Clean Energy Council. Tests generally cost about $200,

however some firms may charge a higher amount and include other

services such as inspection of the solar panels and the electrical wiring of

the PV system. The Technical Regulator is satisfied that solar PV testing

is a mature market in the ACT and that prices are appropriately market-

driven.

(d) There is a drafting error in Rule 6.17(3) of the ES&I Rules Code which

will be corrected in a Code review process. The intention of the Code was

that solar PV inverters should be tested every five years whether they

were greater than 30 kVA or less than 30 kWA. Clause 5.5.1(2) of the

AAD ES&I Rules is a correct statement of the testing regime required for

safety of the network.

29. The applicant directed questions to Mr Grice and made a number of observations:

(a) Her financial position is a little better now than in 2009 because the

Global Financial Crisis has reduced the level of her mortgage payments.

Nevertheless she is still in considerable financial hardship and, as an

example, no longer has her gas supply connected and goes without her gas

hot water system.

9

Page 11: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

(b) She received the notice about testing her solar PV system but couldn’t

even think about the PV because of other financial and personal stresses.

(c) She has consistently asked for deferral of the tests until June 2017, by

which time she expected to have enough money to pay for the test. AAD

declined these requests, simply extending time to complete testing by

21 days on each occasion.

(d) There are difficulties in undertaking the test because of access problems

including a broken gate and over grown vegetation.

(e) She has not drawn down any of her FiT payments and they are

accumulating as a credit on her electricity account. While the FiT

payments are not drawn down, Centrelink does not treat FiT payments as

income under the social security income test. If she were to draw down

from the FiT credit, she would lose some of her pension payment.

30. ActewAGL Distribution gave the following evidence about their business

practices in relation to the FiT:

(a) AAD’s primary concern is the safety of its employees and the public. It

has a duty of care which outweighs hardship considerations.

(b) AAD has no public information process about the safety test

requirements. Legal requirements are explained in the ‘Model Standard

Offer for Basic Connection Services’ applicable to retail customers who

are micro-embedded generators (Exhibit 3), however this document does

not appear to mention any requirement of periodic testing of the solar PV

system.

(c) AAD’s current procedure is to send a letter to the FiT customer on the five

year anniversary date asking for a safety test to be completed and giving a

link to the Clear Energy Council web site for a list of accredited testers. If

the test is not completed in the time specified, further letters are sent.

Where an extension of time is requested, a 21 day extension is generally

granted. AAD has not yet finalised a process for disconnecting solar PV

10

Page 12: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

systems where no test is carried out. Currently there are two customers in

this situation.

(d) A solar PV system would be disconnected from the grid by use of an

isolation switch at the meter box. The switch would be danger tagged and

only the person who placed the tag is authorised to remove it. Accordingly

there would be a substantial cost in reconnecting a system: the cost of the

test; the cost of attendance by an AAD worker to remove the danger tag;

and the cost of an electrician to reconnect the system in the presence of

the AAD worker.

(e) If a solar PV system is disconnected and then reconnected, the FiT

payment would be reinstated. FiT entitlement is not lost.

Consideration and findings

31. Rule 6.17 of the ES&I Rules Code specifies that an embedded generation unit

greater than 30kVA must be tested at a minimum of every five years after

connection to the network, but does not specify any requirement for testing of a

unit less than 30kVA. The AAD ES&I Rules specify that all embedded

generation units must be tested at a minimum of every five years. The

requirement in the Rules is different from the requirement in clause 5.5.1(2) of

the ES&I Rules Code, however Rule 6.17 is not invalidated by this difference.

On the basis of the evidence given on behalf of the Technical Regulator, the

Tribunal is satisfied that a requirement for testing small units every five years is

valid and necessary for safe operation of the AAD electricity network.

32. At the commencement of the hearing, the Tribunal advised the parties that it was

satisfied, on the written material before the Tribunal, that the applicant was in

substantial financial hardship and that no further oral evidence would be

required on this issue. The respondent agreed with this finding.

33. While the applicant is accepted as being in substantial financial hardship, this is

not a basis for waiving the safety test or deferring it for more than a period of

several months. There are no relevant provisions in the FiT regulatory scheme

addressing inability to pay for safety testing and the Tribunal believes that

safety is a paramount consideration. The FiT payment is an income stream for a

11

Page 13: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

household and the necessary maintenance expenses associated with that income

stream should be paid from the income stream.

34. The Tribunal notes that disconnection of a solar PV system does not directly

affect the supply of electricity for domestic household purposes, however there

may be an indirect effect in that the customer will start to receive larger

electricity bills once the credits from the solar PV system cease. This

subsequent hardship would fall within the ACAT energy hardship assistance

program.

35. While hardship cannot be placed above safety in relation to the cost of testing

solar PV systems, the Tribunal considers that it would be desirable for AAD to

develop a hardship approach in relation to the cost of solar PV system testing

and, more urgently, in relation to the cost of replacing a failed inverter, which

can run to several thousand dollars, and is likely to arise for many customers in

the 20 year life of the FiT scheme. This is discussed as a systemic issue below at

[39]-[41].

36. In relation to the applicant, the Tribunal considers it reasonable that she be

ordered to have her inverter tested without further delay and at her own

expense. This arises from several considerations:

(a) Safety considerations are paramount and her solar PV system has not been

tested in more than six years.

(b) Because of the extended period for consideration of her requests for

deferral and her complaint to ACAT E&W, it is now close to 30 June

2017, which is the date she originally specified for completion of the test.

(c) The applicant is in credit on her electricity account and can draw down on

that credit to pay for the safety test. The Tribunal does not accept her

submission that the FiT payments should not be drawn down because of

the impact of the pension income test.

Systemic issues

Public communication about the requirement for safety testing

12

Page 14: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

37. The Tribunal considers that the current arrangements for public communication

about the requirement for safety testing of solar PV systems every five years are

inadequate. The Tribunal suggests that Model Standard Offer (see [30]) should

include a reference to safety testing, with a cross reference to the AAD ES&I

Rules for further information. Specific information about the current safety test

requirements (including hardship provision) should also be published on the

AAD web site.

38. The current process for notifying customers about testing requirements should be

altered to give customers advance notice of the requirement so that they can

budget for the expenditure. The Tribunal recommends the following process:

(a) A first notice is sent to customers three months before the five year test

date informing them of the requirement to arrange a safety test at their

own expense before the test date. This first notice should refer to the list

of accredited testers and ask for contact on hardship issues.

(b) A second notice is sent to the customer immediately after the five year test

date politely asking the customer to arrange the test within 60 days. This

notice should mention hardship arrangements, an AAD complaint

telephone number and the consequences of failure to test, namely

disconnection of the solar PV system.

(c) If the test has not been completed at the end of the 60 day period, a

disconnection warning notice in explicit terms should be sent to the

customer, stating that the system will be disconnected if the test results are

not provided within 21 days. This notice should state the process and

consequences of disconnection, and also contain hardship information and

an ACAT complaint telephone number.

(d) After the 21 days has expired, the system should be listed for

disconnection on a specific day or week and AAD should advise the

customer of this date through an attendance (preferably at the site and

carded if no one is at home).

13

Page 15: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

(e) After the solar PV system has been disconnected, the AAD call centre

must be able to provide specific information about the process for, and

costs of, reconnection.

Hardship provisions for costs associated with solar PV Systems

39. The Tribunal accepts that safety testing should not be deferred for more than

several months in situations where the customer cannot afford to pay for the

test. However, it is desirable that AAD develop hardship arrangements to

manage this problem and also the much larger problem of the cost of replacing

an inverter at several thousand dollars.

40. The obvious basis for such a hardship arrangement would be to use the customer’s

FiT income stream to meet the costs of testing or repairing their solar PV

system. This may be achieved by use of an irrevocable authority signed by the

customer directing their retailer to pay the tester from the customer’s FiT

credits, or some similar arrangement. At the hearing, the representative of the

Technical Regulator advised that there were legislative constraints on action of

this nature and complications because the retailer actually paid the credit, not

AAD. Accordingly there was agreement to convene a roundtable to discuss

possible hardship arrangements, including if necessary changes to the regulatory

framework which might involve amendments to the Electricity Feed-in

(Renewable Energy Premium) Act 2008, the Utilities Act, the Utilities

(Electricity Feed-in Code) Determination 2015, or other instruments. The

roundtable might include the relevant ACT Government agencies, the Technical

Regulator, ACAT and the Independent Competition and Regulatory

Commission, AAD, and community and industry observers.

41. In relation to the cost of replacing an inverter, the Tribunal recommends that ‘No

Interest Loans Scheme’ providers in the Territory consider extending the NILS

Scheme to cover the purchase cost of a replacement inverter.

………………………………..Senior Member P Sutherland

Delivered for and on behalf of the Tribunal

14

Page 16: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

ATTACHMENT A

LEGISLATION

Utilities Act 2000

172 ACAT applicationsA person (the complainant) mentioned in table 172, column 2 may apply to the ACAT in relation to a matter (the complaint) mentioned in column 3 in relation to the complainant.

Table 172 ACAT applications

column 1item

column 2complainant

column 3complaint

1 consumer affected by contravention

contravention of customer contract, or customer retail contract or customer connection contract made under the National Energy Retail Law (ACT), by a utility

2 consumer affected by contravention

contravention of an industry code dealing with utility service standards by a utility

3 consumer a utility fails to provide a utility service to consumer or withdraws a utility service from consumer, and failure or withdrawal causes substantial hardship, or is likely to cause substantial hardship, to consumer

4 person affected by contravention

contravention of s 51 (Protection of personal information) by a utility

5 person affected by contravention

contravention by a utility or a regulated utility of an obligation in relation to its network operations under this Act or the Utilities (Technical Regulation) Act 2014

6 person affected by act or omission

act or omission of an authorised person for a utility or regulated utility in relation to its network operations under this Act or the Utilities (Technical Regulation) Act 2014

7 person on whom charge imposed

capital contribution charge imposed under s 101

ACT CIVIL AND ADMINISTRATIVE TRIBUNAL ACT 2008

54 Decisions without hearing(1) The tribunal may give each party to an application written notice to the

effect that—(a) the tribunal proposes to decide the application without holding a

hearing; and

15

Page 17: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

(b) if the party wishes to make representations about the proposal, the party must make the representations within—(i) 21 days after the day the notice is given; or

(ii) if the tribunal decides that a shorter period is required in all the circumstances of the application—the shorter period.

Note The rules may prescribe a longer period for making representations (see s 25 (1) (e) and (2)).

(2) The tribunal may decide not to hold a hearing in relation to the application only if the tribunal—(a) has given notice under subsection (1); and(b) has taken into consideration any representations made by a party

within the 21-day period or shorter period decided by the tribunal under subsection (1) (b); and

(c) is satisfied that—(i) it is in the public interest not to hold a hearing; and

(ii) the tribunal has sufficient information to make an informed decision on the application.

Note The tribunal must observe natural justice and procedural fairness (see s 7).

UTILITIES (ELECTRICITY FEED-IN CODE) DETERMINATION 2015

4.4 Dispute resolution—Occupier disputes

Disputes between Electricity distributors and Occupiers of premises in relation to the Electricity Feed-in Scheme will be resolved in accordance with the Utilities Act and Complaints procedures developed by the Electricity distributor.An Electricity distributor must develop, maintain and implement procedures to deal with:(1) A Complaint of an Occupier, including:

(a) a right to have the Complaint considered by a senior employee within the Electricity distributor if the Occupier is not satisfied with the manner in which the Electricity distributor is handling the Complaint; and

(b) a Complaint by an Occupier against an Agent of the Electricity distributor; and

(2) the resolution of a dispute between the Electricity distributor and an Occupier.

The procedures implemented by an Electricity distributor must provide for the handling of a Complaint in accordance with the relevant Australian Standard on complaints handling. An Electricity distributor that receives a Complaint from an Occupier must advise the Occupier of the following matters:

16

Page 18: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

(3) in its initial response to the Occupier —the Electricity distributor’s complaint handling practices and procedures; and

(4) in a response giving its final decision on a Complaint —any right the Occupier may have to refer their Complaint to the ACT Civil and Administrative Tribunal (ACAT).

An Electricity distributor must keep its records of a Complaint made by an Occupier for not less than 12 months after the Complaint is resolved.

17

Page 19: ACT CIVIL & ADMINISTRATIVE TRIBUNALclient2.matrix01.act.gov.au/__data/assets/word_doc/0019/1072315/MS...  · Web viewact civil & administrative tribunal. ms d v icon distribution

HEARING DETAILS

FILE NUMBER: EW 0581/2016

PARTIES, APPLICANT: Ms D

PARTIES, RESPONDENT: ActewAGL Distribution

COUNSEL APPEARING, APPLICANT N/A

COUNSEL APPEARING, RESPONDENT Ms Sharnie Truesdale, Legal Counsel

SOLICITORS FOR APPLICANT N/A

SOLICITORS FOR RESPONDENT ActewAGL

TRIBUNAL MEMBERS: Senior Member Peter Sutherland

Member R Vassarotti

DATES OF HEARING: 22 May 2017

18