ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

Embed Size (px)

Citation preview

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    1/62

    SU.S.NRCUnited States Nuclear Regulatory CommissionProtectingPeopleand theEnvironment

    ACRS MEETING WITHTHE U.S. NUCLEARREGULATORYCOMMISSIONNovember 29, 2011

    1

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    2/62

    L

    U.S.NRCUnited States Nuclear Regulatory CommissionProtectingPeopleand theEnvironment

    Overview

    Said Abdel-Khalik

    2

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    3/62

    Accomplishments Since our last meeting with the

    Commission on June 6, 2011, weissued 16 Reports.

    * Topics:InitialACRS Review of: (1) the NRCNear-Term Task Force Report onFukushima and (2) Staff'sRecommended Actions to be TakenWithout Delay

    U

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    4/62

    * Topics (cont.):- ACRS Review of Staff's

    Prioritizationof RecommendedActions to be Taken in Response toFukushima Lessons Learned (SECY-11-0137)

    - ProposedRulemaking to Introducea Site-Specific PerformanceAssessment and Human IntrusionAnalysis Requirement to 10 CFRPart614

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    5/62

    * Topics (cont.):- Draft SECY Paper, Options forProceedingwith Future Level 3ProbabilisticRisk AssessmentActivities"- Selected Chaptersof the Safety

    Evaluation Report (SER) with OpenItems for Certificationof the U.S.APWR Design- Nine Mile Point Nuclear Station,

    Unit 2, Extended Power UprateApplication5

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    6/62

    * Topics (cont.):- FinalSER Associated with theLicense Renewal Application for

    Hope Creek GeneratingStation- GeneralElectric Topical ReportNEDC-33173P, Supplement 2, Parts1, 2, and 3, "Analysis of Gamma

    Scan Data and Removal of SafetyLimit Minimum CriticalPower Ratio(SLMCPR) Margin"

    6

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    7/62

    * Topics (cont.):- Assessment of the Quality of

    Selected NRC Research Projects- Draft FinalRevision 6 of Standard

    Review Plan Branch TechnicalPosition 7-19, "Guidance forEvaluation of Diversity andDefense-in-Depth in DigitalComputer-BasedInstrumentationand Control Systems"

    - Enhancing the Fuel Cycle OversightProcess

    7

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    8/62

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    9/62

    * Topics (cont.):Draft Regulatory Guides in Supportof Proposed10 CFR 50.46(c) Rule,"Requirements for Emergency CoreCooling Systems for LWRs":m DG 1261, Conducting Periodic:Testing

    for Breakaway Oxidation Behaviorm DG 1262, Testing for Postquench

    Ductilityw]DG 1263, EstablishingAnalyticalLimits for Zirconium-BasedAlloyCladding

    9

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    10/62

    * Topics (cont.):

    Revision 19 to the AP1000 DesignControlDocument (DCD) and theAP1000 FinalSafety Evaluation* In December 2010, we concluded

    that the API000 DCA maintainsthe robustness of the previouslycertified design

    10

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    11/62

    - Rev. 19 to APIO00 DCD (cont.)* Conclusion relied in part oncommitments provided by WEC

    during our meetings which were notyet included in the DCA application

    * Revision 19 of the DCD wassubmitted in June 2011 and staffFSER issued in August 2011

    11

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    12/62

    -Rev. 19 to APIO00 DCD (cont.)DCD Revision 19 Changes/Additional finite element analyses

    of Passive Cooling System Tankvl Additional analyses of seismic and

    thermal load combinationsof theEnhanced Shield Building (ESB)VAdditional Tier 2* information

    describingsteel modules of theESB wall

    /Updated containment accidentpressure analysis

    12

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    13/62

    - Rev. 19 to APIO00 DCD (cont.)* The changes proposed n theAPI00 DCD amendment, including

    those made in Revision 19,maintain the robustness of theprevious certified design.

    * There is reasonableassurancethat the revised design can bebuilt and operated without unduerisk to the health and safety of thepublic.

    13

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    14/62

    New PlantActivities* Reviewing:DC applicationsand SERs associatedwith the U.S. EPR and US-APWR

    designs-Adequacy of Long-Term Core CoolingApproach for the ABWR and US-APWR-Reference COLAs for ABWR, ESBWR,US-APWR, and U.S. EPR

    Subsequent COLAs for API00* Continuing to complete reviews ofavailablematerialpromptly'14

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    15/62

    License Renewal* Interim and final reviews to be

    performed for Columbia,Davis Besse, Seabrook, andSouth Texas

    15

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    16/62

    Power Uprates* Will review the GrandGulf, Turkey

    Point,St. Lucie, Monticello, FortCalhoun, Peach Bottom, and PrairieIsland Extended Power UprateApplications

    * Will review GE Topical Report NEDC-33436P,"BWR Vessel Internals Project,Methodology for DemonstratingSteamDryer Integrity for Power Uprate"

    16

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    17/62

    Other OngoingiFutureActivities Fukushima Longer-Term Reviews SOARCA4 Watts Bar 2 DigitalI&C0 10 CFR 50.46(c)0 Emergency Planning or Small ModularReactors* Revision to the ConstructionReactor

    Oversight ProcessAssessment Program Blending of Low-Level Radioactive Waste Safety Culture Emerging Technical Issues Extended Dry Cask Storage 17

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    18/62

    KU.S.NRCUnited States Nuclear Regulatory CommissionProtectingPeopleand theEnvironment

    ACRS Review ofFUKUSHIMA

    Said Abdel-Khalik18

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    19/62

    ACRS Briefings on Fukushima" April 7- NRC Staff on InitialResponse" May 26- DOE and NEI* June 23 - NRC Staff on Task Force

    Actions* July 12-INPO" August 16 & September 8- Near Term

    Task Force October 7- Fukushima Steering

    Committee

    19

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    20/62

    ACRS Reports on FukushimaResponses to Commission Tasking viaSRM-SECY-11-0093, "Near-Term Reportand Recommendations for AgencyActions Following the Events in Japan"- ACRS Letter Report dated October 13, 2011- ACRS Letter Report dated November 8, 2011

    * Additional Letter Reports will be issuedas we engage with the staff on actionplans related to specificrecommendations

    20

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    21/62

    ACRS Letter - October 13, 2011" Staff's recommended actions are

    appropriately ocused on lessonslearned from what is currentlyknown

    " Near-term recommendationsunlikely to be negated, or renderedinappropriate, y the acquisitionofnew information

    21

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    22/62

    ACRS Letter - October 13, 2011" ACRS review focused on

    completeness and appropriatenessof recommended staff actions

    * Two categoriesof recommendations- Additional immediate actions (2.1-Day

    Report)- Additional actions beyond those

    specified in the NTTF Report22

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    23/62

    ACRS Letter - October 13, 2011Additional Immediate Actions (21-Day Report)

    Actions related to NTTF Recommendation2.1 (seismic and flood re-evaluations)should be expanded to include anexpedited update of the applicableregulatoryguidance,methods, and datafor external flooding

    * Actions related to NTTF Recommendation2.3 (seismic and flood walkdowns) shouldbe expanded to address the integratedeffects of severe storms

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    24/62

    ACRS Letter - October 13, 2011Additional Immediate Actions (21-Day Report)

    Actions related to NTTF Recommendation4.1 (SBO regulatoryactions)should beexpanded to include issuance of anadvanced notice of proposed rulemakingand require licensees to provide anassessment of capabilities o cope withan extended SBO

    * Actions related to NTTF Recommendation5.1 (reliablehardenedvents for Mark Icontainments)should also be applied toBWRs with Mark II containments

    24

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    25/62

    ACRS Letter - October 13, 2011Additional Immediate Actions (21-Day Report)" Discussionswith stakeholdersshould be

    initiatedregardingnear-term actions foradditionalhydrogen controland mitigationmeasures in reactorbuildings for plantswith Mark I and Mark II containments.

    * Information should be requested fromlicensees regardingcurrentplant-specificspent fuel pool instrumentation,powersupplies, and sources of makeup andcooling water.

    25

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    26/62

    ACRS Letter - October 13, 2011Additional Immediate Actions (21-Day Report)* Actions related to NTTF Recommendation8 (integrationof EOPsISAMGsIEDMGs)should be expanded to include fireresponse procedures.

    26

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    27/62

    ACRS Letter - October 13, 2011Additional Recommendations to

    NTTF Report* Performance-based riteria o

    mitigate and manage an extendedSBO should be consideredas analternative to the specific copingtimes proposed n Recommendation4.1z

    27

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    28/62

    ACRS Letter - October 13, 2011Additional Recommendations to

    NTTF ReportRecommendation 6 should beexpanded to include:- a requirement for BWR plants with MarkI and Mark !I containments toimplement combustible gas controlmeasures in reactorbuildings as a near-term defense-in-depth measure.

    - an assessment of the vulnerabilitiesintroducedby shared ventilationsystems or sharedstacks in multi-unitsites.

    28

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    29/62

    ACRS Letter - October 13, 2011Additional Recomm endations to

    NTTF Report

    * Selected reactorand containmentinstrumentationshould be enhancedto withstand beyond-design-basisaccident conditions.

    29

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    30/62

    ACRS Letter - October 13, 2011Additional Recommendations to

    NTTF ReportThe NRC should proactively engagein efforts to define and participate nprograms to capture and analyzedata from the Fukushima event toenhance understandingof severeaccidentphenomena, including BWRmelt progression,seawateradditioneffects, hydrogen transportandcombustion, and safety systemsoperability.

    30

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    31/62

    ACRS Letter - October 13, 2011ContainmentAccident Pressure

    Licensing actions requiringthegrantingof containment accidentpressure (CAP) credit should besuspended until the implicationsofpost-Fukushima containmentpressure control measures areunderstood.

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    32/62

    ACRS Letter - November 8, 2011Staff's three-tierapproachandcriteria or prioritizationof NTTFrecommendations are appropriatesubject to the following additionalrecommendations:

    Rulemaking activities related tostrengthening of SBO mitigationcapabilityshould be expedited

    32

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    33/62

    ACRS Letter - November 8, 2011(additional ecommendations)Tier 1 recommendationsshould beexpanded to include additionalactions identified in our O ctober 13,2011, report:" guidance for flooding hazardsevaluations" integratedwalkdowns" station blackout" BWR hardenedvents" shared ventilations systems" hydrogen control and mitigation" spent fuel pools" integrationof onsite emergencyactions 33

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    34/62

    ACRS Letter - November 8, 2011(additional ecommendations)NTTF recommendation 10.2regardingevaluation of the commandand control structure andqualificationsof decision makersshould be initiated n parallelwithTier 1 activities related to integrationof onsite emergency actions

    34

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    35/62

    ACRS Letter - November 8, 2011(additional ecommendations)Tier 2 recommendationsshould beexpanded to include the additionalrecommendationsregardingenhancement of selected reactorand containment instrumentation,and the need to proactively engage inefforts to capture and analyze datafrom the Fukushima event

    35

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    36/62

    ACRS Letter - November 8, 2011(additional ecommendations)Tier 1 recommendation 7.1-2,"Develop and issue order to licenseesto provide reliableSFPinstrumentation,"should bereconsidered. Schedules for SFPinstrumentation mprovements andother modifications to the SFP shouldbe informed by quantificationof thecontributionmade by SFPs to overallplant risk.

    36

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    37/62

    Summary Staff's recommended actions areappropriately ocused on lessonslearned from what is currently known* Near-term recommendationsunlikely tobe negated, or rendered inappropriate,by the acquisitionof new information* Looking forward to future engagementswith staff to review specific actionsrelated to prioritizationefforts.

    37

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    38/62

    SU.S.NRCUnited States Nuclear Regulatory CommissionProtectingPeopleand theEnvironment

    ProposedRulemakingto addSite-Specific Analysis toPart61

    Michael T. Ryan.38

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    39/62

    SRM-SECY-08-0147Directed the staff to:

    e Proceedwith rulemaking to add site-specific analysis for disposalof largequantitiesof depleted Uranium (DU)

    SRM-SECY-10-00Directed the staff

    Incorporate argelevel waste (LLW)

    Ntonscale blending of low-in the rulemaking

    39

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    40/62

    CurrentPart61 PerformanceObjectivese 61.41 - Principal equirementsfor protection of members of thepublic9 61.42 - Protectionof theinadvertentintruder9 61.43 - Protectionof individualsduring operations

    . 61.44 - Stability of the disposa lsite after closure40

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    41/62

    ProposedMajor Rule ChangesS61.41*Adds Site-Specific Performance

    Assessment*Adds Period-of-Performance POP)of

    20,000 years

    S61.42*Adds Site-Specific IntruderAnalysis"Adds 500 mrem annualdose for anIntruder"Includes POP of 20,000 years

    41

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    42/62

    ProposedMajor Rule Changes461w13Adds Site-Specific Long-Term Analysis:

    -Consider the potential long-termradiological mpacts-Calculate peak dose that would occur20,000 years or more after site closure

    42

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    43/62

    ACRS Recommendations* Part61 should not be amendedas recommended by staff* Assessment methodology should

    be risk informed andperformance based* POP should not be specified inrule; It should be site-specificand risk informed with respect todisposaltechnology and sitecharacteristics

    4,3

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    44/62

    Risk-InformedApproach" Radionuclide Characteristics" Waste Form" Waste Package" DisposalTechnology* Cover Technology" GeohydrologicalEnvironment

    44

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    45/62

    POP* 20,000 years is excessive.

    - IAEA Safety Standard (SSR-5)recommends "severalhundredyears" for short-lived and"severalthousandyears" forintermediate and high-levelwaste

    - DOE (Order435.1) uses 1000years for LLW

    - NRC HLW (Part63) uses 10,000years

    45

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    46/62

    POP (cont.)ACNW previously (1997 and 2000)recommended two-part approach:* (1) Site-specific time to address

    more mobile radionuclides-peak dose for compliance* (2) Qualitativeassessment ,

    without compliance measure, toidentify possible deficiencies inlong term perform ance offacility

    46

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    47/62

    POP (Cont.)" Assessments longer than a few

    hundred to a thousandyearsshould focus on major failures ofa disposal system , rather han afew intruders" Only one commenter out of 15 ondraft proposed languagespecifically supported 20,000 yearPOP

    47

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    48/62

    Disposal of DU" DU can be acceptable waste for

    disposal n a Part61 LLW facility,under certain circumstances" DU can be evaluated in a risk

    informed performance assessmentfor a LLW facility* For example - a range of depth

    of burials could be evaluated tominimize intrudercontact withDU waste

    48

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    49/62

    Inadverten in truders OriginalPart61 - intruderanalysis was

    a simplified bounding calculation toestablish concentrations or certainradionuclides

    More realistic nadvertent intruderscenarios that consider site-specificfactors should be used within a risk-informed approach

    Most LLW is decayed away with only asmall number of radionuclidespresentafter 300 years

    49

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    50/62

    In Conclusion" Greateremphasis on a risk

    informed approach for LLWmanagement" Focus on radionuclidequantity

    rather han waste origins orconcentrations* Realistic treatment of intruder

    protection, including probabilityand consequences of intrusion,andotherparameters(depth of burial,performance of intruderbarriers)

    50

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    51/62

    SU.S.NRCUnited States Nuclear Regulatory CommissionProtectingPeopleand the Environment

    Options for Proceedingwith Future Level 3ProbabilisticRisk

    Assessm ent ActivitiesJohn W. Stetkar

    51

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    52/62

    SEC Y-11-0089" "Options for Proceedingwith Future

    Level 3 ProbabilisticRisk AssessmentActivities"

    " Option 1: Status Quo - Evolutionarydevelopment of PRA technology

    Option 2: Focused Research -Address identified technology gapsbefore conducting full-scope PRA

    * Option 3: Full-scope Level 3 PRA foroperatingnuclearpower plant52

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    53/62

    ACRS Reviews" Subcommittee meetings in November

    2010 andMay 2011" Full Committee meeting in June 2011" ACRS recommended modified version

    of Option 3" SRM for SECY-11-0089 in September2011 approved modified version ofOption 3

    53

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    54/62

    Analytical Advances SinceNUREG.1150

    * PRA methods (human reliability,fires, seismic, other external events)

    * Severe accidentphenomena Risk during shutdown modes* Characterizationand quantification

    of uncertainty

    54

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    55/62

    Industry Advances SinceNUREG.1150

    " Plantoperationsand maintenance Plantmodifications" Risk-informed configurationcontrol Severe accidentmitigationguidance" Emergency planning

    55

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    56/62

    Level 3 PRA" Fully integratedassessment" Identificationof important linkages

    and dependencies (physical,functional,human)

    " Balanced understandingof currentrisk profile and contributors

    56

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    57/62

    Option 3 vs. Option 2" Additional researchwill be needed

    to address specific issues" Level 3 PRA provides scenario-based

    context and focus" Level 3 PRA may identify otherimportantknowledge gaps that

    requirepracticalsolutions" Simplified or bounding assessments

    can distort understandingof actualrisk57

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    58/62

    IntegratedLevel 3 PRA Results* Interim results should benefit from

    integratedassessment of Level 3 riskfor specific hazard categoriesandplant operatingstates- Internal events and hazards at full power- External events at full power- Multi-unit site risk at full power- Internal events and hazards at shutdown-External events at shutdown- Multi-unit site risk, mixed unit modes- Other contributors(e.g., fuel pools, ISFSI)

    58

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    59/62

    Available Technical Information Active industry participationand

    collaborative nput" Selection of participatingplant site" Benefit from existing SPAR models

    and plant-specific analyses" Benefit from other NRC initiatives(e.g., SOARCA)

    " May be prudent to select PWR site,pending understandingof FukushimaDaiichiaccidentprogression

    59

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    60/62

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    61/62

    Expected Level 3 PRA Benefits" Staff knowledge and experience

    from performance of a modern full-scope Level 3 PRA

    * Integratedrisk perspective" Input to emergency planning" Input to resolution of generic issues" Quantitative framework to address

    new reactordesign and siting issues

    61

    Abbreviations

  • 8/3/2019 ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

    62/62

    ABWR Advanced Boiling Water ReactorACNW Advisory Committee on NuclearWasteACRS Advisory Committee on ReactorSafeguards

    APWR Advanced PressurizedWater ReactorAPIO00 Advanced Passive 1000BWR Boiling Water ReactorCAP ContainmentAccident PressureCFR Code of FederalRegulationsCOLA Combined License ApplicationDC Design CertificationDCA Design CertificationAmendmentDCD Design Control DocumentDG Draft Regulatory GuideDOE U.S. Departmentof EnergyDU Depleted UraniumEDMG Extreme D amage Mitigation GuidelineEDO Executive Director or OperationsEOP Emergency OperatingProcedureEPR Evolutionary Power ReactorESB Enhanced Shield BuildingESBWR Economic Simplified Boiling Water

    ReactorFSER FinalSafety EvaluationReportGE GeneralElectricHLW High Level Waste

    IAEAINPOISFSII&CLLWLWRmremNEINRCNTTFPRAPOPPWRRGSAMGSBOSECYSERSF PSOARCASPARSRMWEC

    InternationalAtomic Energy AgencyInstitute of Nuclear Power OperationsIndependent Spent Fuel StorageInstallationInstrumentation& ControlLow Level WasteLight Water ReactormilliremNuclearEnergy InstituteNuclearRegulatory CommissionNear-Term Task ForceProbabilisticRisk AssessmentPeriodof PerformancePressurizedWater ReactorRegulatory GuideSevere Accident Management GuidelineStation BlackoutSecretary of CommissionSafety Evaluation ReportSpent Fuel PoolState-of-the-Art Reactor ConsequenceAnalyses.StandardizedPlantAnalysis RiskStaff Requirements MemorandumiMemorandaWestinghouse Electric Company

    62